JPH073826A - Construction method of dome-like roof in underground tank - Google Patents

Construction method of dome-like roof in underground tank

Info

Publication number
JPH073826A
JPH073826A JP4081094A JP8109492A JPH073826A JP H073826 A JPH073826 A JP H073826A JP 4081094 A JP4081094 A JP 4081094A JP 8109492 A JP8109492 A JP 8109492A JP H073826 A JPH073826 A JP H073826A
Authority
JP
Japan
Prior art keywords
roof
prestress
constructed
ground
side wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP4081094A
Other languages
Japanese (ja)
Inventor
Masabumi Nakano
正文 中野
Yoshinori Kawamura
佳則 川村
Takeshi Shirasago
健 白砂
Satoru Amano
悟 天野
Masamichi Yasunaga
正道 安永
Hitoshi Takeuchi
等 武内
Masanobu Kuroda
正信 黒田
Atsuo Imojima
淳生 妹島
Ken Nakano
謙 中野
Minoru Nada
実 名田
Masatoshi Kato
正利 加藤
Takemasa Yamada
武正 山田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Mitsui Construction Co Ltd
Kajima Corp
Shimizu Construction Co Ltd
Obayashi Corp
Tokyo Gas Co Ltd
Shimizu Corp
Original Assignee
Taisei Corp
Mitsui Construction Co Ltd
Kajima Corp
Shimizu Construction Co Ltd
Obayashi Corp
Tokyo Gas Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp, Mitsui Construction Co Ltd, Kajima Corp, Shimizu Construction Co Ltd, Obayashi Corp, Tokyo Gas Co Ltd, Shimizu Corp filed Critical Taisei Corp
Priority to JP4081094A priority Critical patent/JPH073826A/en
Publication of JPH073826A publication Critical patent/JPH073826A/en
Withdrawn legal-status Critical Current

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

PURPOSE:To reduce an initial amount of prestress to be introduced in the case a dome-like roof of an underground tank is constructed. CONSTITUTION:After an earth retaining wall 1 is constructed in the ground G, a dome-like roof 2 is constructed and is temporarily borne on an opening edge 1a facing to the ground of the earth retaining wall 1, and then, a primary prestress is introduced to the peripheral surface 2a of the roof 2 along the circumferential direction. After that, a bottom slab 4 and a part 5a of the side wall continued to the bottom slab 4 are constructed in an excavated hole 3 formed inside the earth retaining wall 1 to make a space 6 between part 5a of the side wall and the roof 2, and a secondary prestress is introduced to the peripheral surface 2a of the roof 2. In the case the primary prestress is introduced, horizontal thrust force occurring in the roof 2 is reduced by excavation load W of the ground G, and in the case the secondary prestress is introduced, prestress force is not propagated to the side wall, so that an initial amount of prestress is reduced as a whole.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、内部に低温液化ガス等
が貯蔵されるコンクリート製の地下タンクにおけるドー
ム式屋根の構築方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a dome type roof in a concrete underground tank in which a low temperature liquefied gas or the like is stored.

【0002】[0002]

【従来の技術】従来、この種のタンクを地下に構築する
場合には、まず、地盤を掘削して形成した掘削穴内に、
コンクリート製の底版と、底版の周縁部から立設するコ
ンクリート製の筒状側壁とからなる躯体を構築してい
く。
2. Description of the Related Art Conventionally, in the case of constructing a tank of this type underground, first, in a drill hole formed by excavating the ground,
A skeleton consisting of a concrete bottom slab and a concrete cylindrical side wall standing upright from the peripheral portion of the bottom slab is constructed.

【0003】そして、躯体完成後、側壁の開口縁に躯体
の開口を覆うコンクリート製のドーム式の屋根を施工し
て両者を連結するとともに、屋根の外周部内に、この外
周部に沿って複数のPC鋼材を挿入して巻回し、これら
PC鋼材を緊張してその状態を保持し、いわゆるプレス
トレスを導入している。このプレストレス力は、屋根
が、自重および鉛直荷重によって生じる水平スラスト力
により広がることを防止して、構築状態を支持する作用
をなす。
After the skeleton is completed, a concrete dome type roof covering the opening of the skeleton is constructed on the opening edge of the side wall to connect the two, and at the same time, in the outer peripheral portion of the roof, a plurality of ridges are formed along the outer peripheral portion. A PC steel material is inserted and wound, and these PC steel materials are tensioned to maintain the state, so-called prestress is introduced. This prestressing force prevents the roof from spreading due to the horizontal thrust force generated by its own weight and vertical load, and serves to support the construction state.

【0004】[0004]

【発明が解決しようとする課題】ところで、上記方法に
おいては、躯体(の側壁)に連結された状態で屋根の外
周部にプレストレスを導入するから、側壁に対してその
プレストレス力が伝播する。したがって、プレストレス
の導入量は、前記水平スラスト力に対する抵抗量に、側
壁に伝播する量を加えたものとしなければならない。す
なわち、プレストレス力は、単に屋根の水平スラスト力
に抵抗し得るだけ導入するに留まらず、これに加えて、
側壁に伝播する損失分を導入する必要があり、このた
め、プレストレス導入が効率的でない不具合があった。
また、プレストレスの導入量を、屋根の水平スラスト力
に抵抗し得る分よりも低い量に抑えたい要求も出てきて
いる。
By the way, in the above method, since prestress is introduced into the outer peripheral portion of the roof while being connected to (the side wall of) the body, the prestressing force propagates to the side wall. . Therefore, the amount of prestress introduced must be the amount of resistance to the horizontal thrust force plus the amount of propagation to the sidewall. That is, the prestressing force is not limited to introducing only the horizontal thrust force of the roof, and in addition to this,
Since it is necessary to introduce a loss component that propagates to the side wall, there is a problem that prestress introduction is not efficient.
There is also a demand for the amount of prestress introduced to be lower than the amount capable of resisting the horizontal thrust force of the roof.

【0005】本発明は、上記事情に鑑みてなされたもの
で、地下タンクのドーム式屋根を構築する際に導入する
プレストレスの導入量を、従来よりも低減することがで
き、効率よいプレストレス導入を実施し得る、地下タン
クにおけるドーム式屋根の構築方法を提供することを目
的としている。
The present invention has been made in view of the above circumstances, and the amount of prestress to be introduced when constructing a dome type roof for an underground tank can be reduced as compared with the prior art, and an efficient prestress can be achieved. It is intended to provide a method of constructing a dome type roof in an underground tank that can be introduced.

【0006】[0006]

【課題を解決するための手段】本発明は、上記目的を達
成するためになされたものであって、地盤中に構築され
る、コンクリート製の側壁および底版からなる有底筒状
の躯体と、この躯体の開口を覆うコンクリート製の円盤
状ドーム式屋根とからなる地下タンクを構築するにあた
り、地盤中に筒状の土止め壁を構築した後、この土止め
壁の地上に臨む開口縁に、前記屋根を施工して仮支持
し、次いで、この屋根の外周部に、周方向に沿って第1
次プレストレスを導入し、次いで、土止め壁の内側の地
盤を掘削してから、この掘削穴の中に、前記底版および
この底版に続く前記側壁の一部を構築してこの側壁の一
部と前記屋根との間にスペースをあけた状態とし、次い
で、前記屋根の外周部に第2次プレストレスを導入する
ことを特徴としている。
The present invention has been made in order to achieve the above-mentioned object, and is a bottomed cylindrical body composed of a concrete side wall and a bottom slab, which is constructed in the ground. In constructing an underground tank consisting of a concrete disk-shaped dome roof covering the opening of this frame, after constructing a cylindrical earth retaining wall in the ground, on the opening edge of this earth retaining wall facing the ground, The roof is constructed and temporarily supported, and then the first portion along the circumferential direction is provided on the outer peripheral portion of the roof.
Next, the prestress is introduced, and then the ground inside the earth retaining wall is excavated, and then the bottom slab and a part of the side wall following the bottom slab are built in the drill hole to form a part of the side wall. A space is provided between the roof and the roof, and then a secondary prestress is introduced into the outer peripheral portion of the roof.

【0007】[0007]

【作用】本発明の地下タンクにおけるドーム式屋根の構
築方法によれば、第1次プレストレスの導入量は、土止
め壁周囲の地盤の土圧および水圧からなる掘削荷重によ
り、土止め壁を介して屋根に生じる水平スラスト力が減
じられるので、所要量よりも低減できる。さらに、第2
次プレストレスを導入する際には、側壁と屋根との間に
スペースがあいているから、そのプレストレス力は側壁
に伝播せず、このため、その導入量は、最終的に必要な
プレストレス力に達するまでで済む。この結果、全体の
プレストレス導入量を従来よりも低減でき効率的にプレ
ストレスを導入できる。
According to the method for constructing a dome type roof in an underground tank according to the present invention, the amount of introduction of the first prestress is such that the earth retaining wall is constructed by the excavating load consisting of earth pressure and water pressure around the earth retaining wall. The horizontal thrust force generated on the roof is reduced, so that the required amount can be reduced. Furthermore, the second
When introducing the next prestress, since there is a space between the side wall and the roof, the prestressing force does not propagate to the side wall. All you need to do is reach your strength. As a result, the total prestress introduction amount can be reduced as compared with the conventional case, and the prestress can be introduced efficiently.

【0008】[0008]

【実施例】以下、図面を参照して本発明の一実施例を工
程順に説明する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the present invention will be described below in order of steps with reference to the drawings.

【0009】[工程1]図1に示すように、まず、地盤
G中に、構築する地下タンクの躯体を構成する側壁に応
じた土止め壁1を、筒状に構築する。
[Step 1] As shown in FIG. 1, first, in the ground G, the earth retaining wall 1 corresponding to the side wall forming the skeleton of the underground tank to be constructed is constructed in a cylindrical shape.

【0010】[工程2]土止め壁1の上部の開口縁1a
を地上に臨ませ、この開口縁1aに、土止め壁1の開口
を覆ってコンクリート製のドーム式の屋根2を、打設コ
ンクリートにより構築するとともに、この屋根2を、土
止め壁1に仮支持させる。
[Step 2] Opening edge 1a at the top of the earth retaining wall 1
To the ground, the opening edge 1a covers the opening of the earth retaining wall 1 to construct a concrete dome type roof 2 by casting concrete, and the roof 2 is temporarily attached to the earth retaining wall 1. Support.

【0011】[工程3]屋根2の外周部2a内に、この
外周部2aに沿って複数のPC鋼材(図示略)を挿入し
て巻回し、これらPC鋼材を緊張してその状態を保持す
ることにより、第1次プレストレスを導入する。この第
1次プレストレスの導入量は、施工時に必要な所要量で
あって、最終的に導入する量の半分程度とする。
[Step 3] Inside the outer peripheral portion 2a of the roof 2, a plurality of PC steel materials (not shown) are inserted along the outer peripheral portion 2a and wound, and the PC steel materials are tensioned and held in that state. By doing so, the first prestress is introduced. The introduction amount of the first prestress is a required amount required at the time of construction, and is about half of the finally introduced amount.

【0012】[工程4]土止め壁1の内側の地盤Gを掘
削する。
[Step 4] The ground G inside the earth retaining wall 1 is excavated.

【0013】[工程5]図2に示すように、この掘削穴
3の底部に、地下タンクの躯体を構成する底版4を構築
し、次いで、この底版4の外周部に、同じく地下タンク
の躯体を構成する側壁の一部5aを立設して構築し、こ
の側壁の一部5aと前記屋根2の外周部2aとの間に、
スペース6をあけた状態とする。
[Step 5] As shown in FIG. 2, a bottom slab 4 which constitutes the skeleton of the underground tank is constructed at the bottom of the excavation hole 3, and then the skeleton of the underground tank is also provided on the outer peripheral portion of the bottom slab 4. Part of the side wall 5a that is constructed by standing up and constructed, between the part 5a of the side wall and the outer peripheral portion 2a of the roof 2,
The space 6 is left open.

【0014】[工程6]屋根2の外周部2aに巻回した
前記PC鋼材をさらに緊張して、この外周部2aに、第
2次プレストレスを導入する。この第2次プレストレス
の導入量は、最終的に必要な量である。
[Step 6] The PC steel material wound around the outer peripheral portion 2a of the roof 2 is further tensioned to introduce a second prestress into the outer peripheral portion 2a. The amount of the secondary prestress introduced is the amount finally required.

【0015】これで屋根2は構築されたことになる。次
いで、地下タンクを最終的に構築するには、前記スペー
ス6にコンクリートを打設して側壁5を完成させ、この
側壁5と屋根2とを連結する。図3は、底版4および側
壁5からなる躯体7と、屋根2からなる完成状態の地下
タンク8を示している。
The roof 2 is now constructed. Next, in order to finally construct the underground tank, concrete is poured into the space 6 to complete the side wall 5, and the side wall 5 and the roof 2 are connected. FIG. 3 shows a skeleton 7 consisting of a bottom slab 4 and side walls 5, and a completed underground tank 8 consisting of a roof 2.

【0016】上記本実施例のドーム式の屋根2を構築す
る方法においては、[工程4]における地盤Gの掘削に
ともなって、図1に示すように、土止め壁1の周囲の地
盤Gの土圧および水圧からなる掘削荷重Wが、内側に向
けて作用し、この掘削荷重Wは、土止め壁1を介して、
屋根2の自重および鉛直荷重によって生じる水平スラス
ト力を打ち消す力として、屋根2に作用する。
In the method of constructing the dome type roof 2 of the present embodiment, as the ground G is excavated in [Step 4], as shown in FIG. 1, the ground G around the earth retaining wall 1 is removed. An excavating load W consisting of earth pressure and water pressure acts toward the inside, and this excavating load W passes through the earth retaining wall 1
It acts on the roof 2 as a force for canceling the horizontal thrust force generated by the own weight and the vertical load of the roof 2.

【0017】[工程3]におけるプレストレスの導入量
は、最終的な導入量の半分程度と前述したが、たとえ
ば、掘削穴3を形成する[工程4]の段階で、屋根2に
必要なプレストレスの導入量を最終的に必要な導入量の
50%で、掘削荷重Wによる水平スラスト力を打ち消す
力がプレストレス力を10%補うとすれば、[工程3]
におけるプレストレスの導入量は、実質的に40%でよ
いわけである。
The amount of prestress introduced in [Step 3] is about half of the final amount introduced, but for example, the amount of prestress required for the roof 2 at the stage of [Step 4] for forming the excavation hole 3 is increased. If the amount of stress introduced is 50% of the final required amount and the force for canceling the horizontal thrust force due to the excavating load W supplements the prestress force by 10%, [Step 3]
The introduction amount of prestress in the above is substantially 40%.

【0018】そしてこれにより、[工程6]における第
2次プレストレスの導入量は、最終的に必要な導入量の
50%で済む。したがって、屋根2に対して導入するプ
レストレスの総合量は、最終的に必要な量から、上記掘
削荷重Wによって補われる量を差し引いたもの、この場
合で言えば90%となる。
As a result, the amount of secondary prestress to be introduced in [Step 6] is 50% of the finally required amount. Therefore, the total amount of prestress to be introduced into the roof 2 is the finally required amount minus the amount compensated by the excavation load W, which is 90% in this case.

【0019】従来では、屋根に導入するプレストレス
を、水平スラスト力に抵抗し得るだけの導入量に加え
て、側壁に伝播する損失分を導入する必要があったが、
本実施例における導入量は、屋根の水平スラスト力に抵
抗し得るだけの導入量よりも低くて済むわけである。し
たがって、屋根へのプレストレス導入に要する設備(P
C鋼材や緊張用ジャッキ等)の負担軽減が可能であり、
効率的にプレストレスを導入できる。
Conventionally, it has been necessary to introduce the prestress introduced into the roof into an amount sufficient to resist the horizontal thrust force, and also to introduce the loss that propagates to the side wall.
In the present embodiment, the introduction amount is lower than the introduction amount that can resist the horizontal thrust force of the roof. Therefore, the equipment required to introduce prestress to the roof (P
It is possible to reduce the burden on C steel material, jacks for tension, etc.,
Prestress can be introduced efficiently.

【0020】[0020]

【発明の効果】以上説明したように、本発明の地下タン
クにおけるドーム式屋根の構築方法によれば、地盤中に
構築される、コンクリート製の側壁および底版からなる
有底筒状の躯体と、この躯体の開口を覆うコンクリート
製の円盤状ドーム式屋根とからなる地下タンクを構築す
るにあたり、地盤中に筒状の土止め壁を構築した後、こ
の土止め壁の地上に臨む開口縁に、前記屋根を施工して
仮支持し、次いで、この屋根の外周部に、周方向に沿っ
て第1次プレストレスを導入し、次いで、土止め壁の内
側の地盤を掘削してから、この掘削穴の中に、前記底版
およびこの底版に続く前記側壁の一部を構築してこの側
壁の一部と前記屋根との間にスペースをあけた状態と
し、次いで、前記屋根の外周部に第2次プレストレスを
導入することを特徴とするもので、第1次プレストレス
を導入する際、地盤の掘削荷重によって屋根に生じる水
平スラスト力が減じられ、第2次プレストレスを導入す
る際には側壁にプレストレス力が伝播しないから、全体
としてプレストレスの導入量が低減し、効率的にプレス
トレスを導入できるといった効果を奏する。
As described above, according to the method for constructing a dome type roof in an underground tank of the present invention, a bottomed cylindrical frame body constructed of concrete side walls and a bottom slab is constructed, In constructing an underground tank consisting of a concrete disk-shaped dome roof covering the opening of this frame, after constructing a cylindrical earth retaining wall in the ground, on the opening edge of this earth retaining wall facing the ground, The roof is constructed and temporarily supported, then the primary prestress is introduced to the outer peripheral portion of the roof along the circumferential direction, then the ground inside the earth retaining wall is excavated, and then the excavation is performed. In the hole, the bottom slab and a part of the side wall subsequent to the bottom slab are constructed to leave a space between the part of the side wall and the roof, and then a second portion is formed on the outer periphery of the roof. Characterized by introducing next prestress Therefore, when introducing the first pre-stress, the horizontal thrust force generated on the roof by the excavation load of the ground is reduced, and when introducing the second pre-stress, the pre-stress force does not propagate to the side wall. As a whole, the amount of introduction of prestress is reduced, and it is possible to effectively introduce prestress.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の一実施例方法における工程の前半を示
す側断面図である。
FIG. 1 is a side sectional view showing a first half of steps in a method according to an embodiment of the present invention.

【図2】同後半を示す側断面図である。FIG. 2 is a side sectional view showing the latter half.

【図3】完成状態の地下タンクの側断面図である。FIG. 3 is a side sectional view of the underground tank in a completed state.

【符号の説明】[Explanation of symbols]

1 土止め壁 1a 開口縁 2 ドーム式屋根 2a 外周部 3 掘削穴 4 底版 5 側壁 5a 側壁の一部 6 スペース 7 躯体 8 タンク G 地盤 W 掘削荷重 1 Earth retaining wall 1a Opening edge 2 Dome type roof 2a Peripheral part 3 Excavation hole 4 Bottom plate 5 Side wall 5a Part of side wall 6 Space 7 Body 8 Tank G Ground W Excavation load

───────────────────────────────────────────────────── フロントページの続き (51)Int.Cl.6 識別記号 庁内整理番号 FI 技術表示箇所 E04H 7/18 302 9023−2E (71)出願人 000206211 大成建設株式会社 東京都新宿区西新宿一丁目25番1号 (71)出願人 000174943 三井建設株式会社 東京都千代田区岩本町3丁目10番1号 (72)発明者 中野 正文 東京都北区上十条三丁目3番23号 (72)発明者 川村 佳則 東京都板橋区赤塚新町三丁目34番地 アー バンライフゆりの木通り東1号棟305号室 (72)発明者 白砂 健 東京都千代田区神田司町二丁目3番地 株 式会社大林組内 (72)発明者 天野 悟 東京都千代田区神田司町二丁目3番地 株 式会社大林組内 (72)発明者 安永 正道 東京都港区元赤坂一丁目2番7号 鹿島建 設株式会社内 (72)発明者 武内 等 東京都港区元赤坂一丁目3番8号 鹿島建 設株式会社東京支店内 (72)発明者 黒田 正信 東京都港区芝浦一丁目2番3号 清水建設 株式会社内 (72)発明者 妹島 淳生 東京都港区芝浦一丁目2番3号 清水建設 株式会社内 (72)発明者 中野 謙 東京都新宿区西新宿一丁目25番1号 大成 建設株式会社内 (72)発明者 名田 実 東京都新宿区西新宿一丁目25番1号 大成 建設株式会社内 (72)発明者 加藤 正利 東京都千代田区岩本町三丁目10番1号 三 井建設株式会社内 (72)発明者 山田 武正 東京都千代田区岩本町三丁目10番1号 三 井建設株式会社内─────────────────────────────────────────────────── ─── Continuation of the front page (51) Int.Cl. 6 Identification number Office reference number FI Technical indication location E04H 7/18 302 9023-2E (71) Applicant 000206211 Taisei Corporation Shinjuku-ku, Shinjuku-ku, Tokyo No. 25-1 (71) Applicant 000174943 Mitsui Construction Co., Ltd. 3-10-1 Iwamoto-cho, Chiyoda-ku, Tokyo (72) Inventor Masafumi Nakano 3-23-3 Kamuijojo, Kita-ku, Tokyo (72) Invention Author Yoshinori Kawamura 3-34, Akatsukashinmachi, Itabashi-ku, Tokyo Urban Life Yuri-no-Dori East Building 1 Room 305 (72) Inventor Ken Shirasuna 2-3 Kandaji-cho, Chiyoda-ku, Tokyo Obayashi Corporation (72) ) Inventor Satoru Amano 2-3 Kandaji-cho, Chiyoda-ku, Tokyo Obayashi Corporation (72) Incorporator Masamichi Yasunaga 1-2-7 Moto-Akasaka, Minato-ku, Tokyo Kashima Ken Incorporated Co., Ltd. (72) Inventor Takeuchi et al., Moto Akasaka 1-3-8, Minato-ku, Tokyo Kashima Construction Co., Ltd. Tokyo Branch (72) Inventor Masanobu Kuroda 1-3-2 Shibaura, Minato-ku, Tokyo Shimizu Construction Co., Ltd. (72) Inventor Junsei Sejima 1-3-2 Shibaura, Minato-ku, Tokyo Shimizu Construction Co., Ltd. (72) Inventor Ken Ken Nakano 1-25-1 Nishi-Shinjuku, Shinjuku-ku, Tokyo Taisei Construction Co., Ltd. (72) Inventor Minoru Nada 1-25-1 Nishishinjuku, Shinjuku-ku, Tokyo Taisei Construction Co., Ltd. (72) Inventor Masatoshi Kato 3-10-1 Iwamotocho, Chiyoda-ku, Tokyo Mitsui Construction Co., Ltd. (72) Inventor Takemasa Yamada 3-10-1 Iwamotocho, Chiyoda-ku, Tokyo Mitsui Construction Co., Ltd.

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 地盤中に構築される、コンクリート製の
側壁および底版からなる有底筒状の躯体と、この躯体の
開口を覆うコンクリート製の円盤状ドーム式屋根とから
なる地下タンクを構築するにあたり、 地盤中に筒状の土止め壁を構築した後、この土止め壁の
地上に臨む開口縁に、前記屋根を施工して仮支持し、次
いで、この屋根の外周部に、周方向に沿って第1次プレ
ストレスを導入し、次いで、土止め壁の内側の地盤を掘
削してから、この掘削穴の中に、前記底版およびこの底
版に続く前記側壁の一部を構築してこの側壁の一部と前
記屋根との間にスペースをあけた状態とし、次いで、前
記屋根の外周部に第2次プレストレスを導入することを
特徴とする地下タンクにおけるドーム式屋根の構築方
法。
1. An underground tank is constructed which is constructed in the ground and has a bottomed cylindrical skeleton composed of a concrete side wall and a bottom slab, and a concrete disk-shaped dome type roof covering the opening of the skeleton. After constructing a cylindrical earth retaining wall in the ground, the roof is constructed and temporarily supported at the opening edge of the earth retaining wall facing the ground, and then the outer peripheral portion of the roof is circumferentially supported. Along with the introduction of the first prestress, then excavating the ground inside the earth retaining wall, and then constructing the bottom slab and a part of the side wall following the bottom slab in this drilling hole, A method for constructing a dome type roof in an underground tank, characterized in that a space is left between a portion of a side wall and the roof, and then a second prestress is introduced into an outer peripheral portion of the roof.
JP4081094A 1992-04-02 1992-04-02 Construction method of dome-like roof in underground tank Withdrawn JPH073826A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP4081094A JPH073826A (en) 1992-04-02 1992-04-02 Construction method of dome-like roof in underground tank

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP4081094A JPH073826A (en) 1992-04-02 1992-04-02 Construction method of dome-like roof in underground tank

Publications (1)

Publication Number Publication Date
JPH073826A true JPH073826A (en) 1995-01-06

Family

ID=13736806

Family Applications (1)

Application Number Title Priority Date Filing Date
JP4081094A Withdrawn JPH073826A (en) 1992-04-02 1992-04-02 Construction method of dome-like roof in underground tank

Country Status (1)

Country Link
JP (1) JPH073826A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2003080942A1 (en) * 2002-03-22 2003-10-02 Bebo Arch International Ag Arch systems
US6719492B1 (en) 2002-03-22 2004-04-13 Bebotech Corporation Top arch overfilled system
US6988337B1 (en) 2002-03-22 2006-01-24 Bebotech Corporation Means and method for constructing a fully precast top arch overfilled system
US7305798B1 (en) 2002-04-25 2007-12-11 Bebo Of America Composite overfilled arch system

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2003080942A1 (en) * 2002-03-22 2003-10-02 Bebo Arch International Ag Arch systems
US6719492B1 (en) 2002-03-22 2004-04-13 Bebotech Corporation Top arch overfilled system
US6922950B2 (en) 2002-03-22 2005-08-02 Bebotech Corporation Top arch overfilled system
US6988337B1 (en) 2002-03-22 2006-01-24 Bebotech Corporation Means and method for constructing a fully precast top arch overfilled system
US7305798B1 (en) 2002-04-25 2007-12-11 Bebo Of America Composite overfilled arch system

Similar Documents

Publication Publication Date Title
JP2001262515A (en) Method for constructing temporary bearing
JPH073826A (en) Construction method of dome-like roof in underground tank
JP2000212978A (en) Underground tank and construction method of underground tank
JPH1018424A (en) Root wrapping reinforcing structure of column base of steel post or the like
JPH10168915A (en) Method of ground excavation construction in coffering sheet pile
JP3641227B2 (en) Construction method of underground structure
JPH11152928A (en) Base isolation building and method of base isolating construction of existing building
JP2950325B1 (en) Construction method of seismic isolation building
JP3399574B2 (en) How to build an underground tank
JPH03275816A (en) Building method for main slab in underground space
JP2007092370A (en) Aseismatic reinforcing construction method of reinforced concrete existing building
JP3809618B2 (en) Foundation pile and construction method of foundation pile
JP7296311B2 (en) Construction method of underground structure
JPH06212829A (en) Method of constructing roof for tank
JP2000045542A (en) Foundation base isolation method for existing structure
JP3039457B2 (en) How to build a large roof
JP3220915B2 (en) Underground tank construction method
JP3000704B2 (en) How to build a fully buried underground tank
JPH0115671B2 (en)
JP2003035051A (en) Steel plate for earthquake resisting wall and method for building steel-plate earthquake resisting wall
JPH0742238A (en) Roof structure and construction method
JPH06346621A (en) Roof construction method of underground tank
JPH08105122A (en) Underground and aboveground simultaneous execution method of structure
JPH08170444A (en) Method for constructing concrete roof
JPH06173278A (en) Foundation structure for building structure

Legal Events

Date Code Title Description
A300 Withdrawal of application because of no request for examination

Free format text: JAPANESE INTERMEDIATE CODE: A300

Effective date: 19990608