JPH07282112A - Skeleton construction method scheduling system - Google Patents

Skeleton construction method scheduling system

Info

Publication number
JPH07282112A
JPH07282112A JP6070475A JP7047594A JPH07282112A JP H07282112 A JPH07282112 A JP H07282112A JP 6070475 A JP6070475 A JP 6070475A JP 7047594 A JP7047594 A JP 7047594A JP H07282112 A JPH07282112 A JP H07282112A
Authority
JP
Japan
Prior art keywords
construction method
floor construction
floor
model
plan
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP6070475A
Other languages
Japanese (ja)
Inventor
Yusuke Yamazaki
山崎雄介
Hiroshi Tokuda
浩 徳田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP6070475A priority Critical patent/JPH07282112A/en
Publication of JPH07282112A publication Critical patent/JPH07282112A/en
Pending legal-status Critical Current

Links

Abstract

PURPOSE:To perform the comparison of schedule plans and schedule simulation on which the various kinds of condition setting are reflected in a short time by modeling design information and execution information. CONSTITUTION:Schedule objects relating to the design of a floor construction method are described as floor construction method models, the schedule objects relating to an execution schedule are described as flooring method models, information is exchanged through links among the objects and a detailed schedule is hierarchically extended. The floor construction method models are composed of an application skeleton construction method, an applicable floor construction method, an application span length, load conditions and a beam arrangement method, etc., the structures of members such as the specifications of beams, columns and floors, concrete strength, the attributes of PC beams and the attributes of a PICOS construction method, etc., are added to the floor construction method models and floor construction method schedule models are prepared. In the meantime, flooring method schedule model for which temporary loads, deflection allowable values, retention days, an execution section division number, crane machine kind, the number of supports in respective execution stages, the number of support layers and a joining state, etc., are set is prepared and the floor construction method schedule is prepared with the flooring method schedule model and the floor construction method schedule model.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、設計情報と施工情報を
モデル化することにより、躯体構工法の構造的かつ施工
的な適用可能性を検討し、適切な仕様を設定しコストを
算出することができる躯体構工法計画システムに関する
ものである。
[Industrial application] The present invention examines the structural and constructional applicability of the frame construction method by modeling design information and construction information, sets appropriate specifications and calculates costs. The present invention relates to a structure construction method planning system that can be used.

【0002】[0002]

【従来の技術】図49は、従来の躯体構工法計画システ
ムの例を示し、設計条件として、構造、規模、スパン・
階高、仕上、積載荷重、小梁配置、部材断面を入力し、
また施工条件として、工区の分割状態、PC化するか否
か、支保工存置可否を入力し、さらに揚重機種、単価情
報を入力し、処理系においては、施工条件、設計条件の
適用可能性および力学的検討を評価するとともに、工法
設計、作業計画、積算単価、仮設・工期等をコスト評価
し、最終的に工法比較一覧表、工法内容・工事別コスト
を出力するようにしている。
2. Description of the Related Art FIG. 49 shows an example of a conventional frame construction method planning system, which includes design conditions such as structure, scale and span.
Enter floor height, finish, load capacity, beam layout, member cross section,
In addition, as the construction conditions, enter the division status of the work section, whether or not to convert to PC, whether or not the supporting work can be stored, and also the lifting model and unit price information. In the processing system, the applicability of construction conditions and design conditions In addition to evaluating the mechanical examination, cost evaluation of construction method design, work plan, unit price, temporary construction / construction period, etc., finally output construction method comparison list, construction method contents / construction cost.

【0003】[0003]

【発明が解決しようとする課題】しかしながら、従来の
躯体構工法計画システムにおいては、シミュレーション
条件の設定に、設計計画と施工計画の両方の知識をデー
タとして一括入力する必要があり、データ入力に専門的
知識と膨大な時間を要するという問題を有している。ま
た、新しい計画方法や構・工法を追加する場合には、プ
ログラムの各所を修正していく必要があり拡張性に乏し
いという問題があり、さらに、複数の計画案を同時に評
価することができないという問題を有している。
However, in the conventional structure construction method planning system, it is necessary to collectively input knowledge of both the design plan and the construction plan as data in setting the simulation conditions, and specialized in data input. There is a problem that it takes a lot of time and knowledge. In addition, when adding a new planning method or construction / construction method, it is necessary to modify each part of the program, and there is a problem of lack of expandability. Furthermore, it is not possible to evaluate multiple planning plans at the same time. I have a problem.

【0004】本発明は、上記課題を解決するためのもの
で、設計情報と施工情報をモデル化することにより、様
々な条件設定を反映した計画シミュレーションおよび計
画案の比較を短時間で行うことができる躯体構工法計画
システムを提供することを目的とする。
The present invention is intended to solve the above problems. By modeling design information and construction information, it is possible to compare plan simulations and plan plans reflecting various condition settings in a short time. The purpose is to provide a structure construction planning system that can be used.

【0005】[0005]

【課題を解決するための手段】そのために、本発明の躯
体構工法計画システムは、床に関する部材の物的構成、
組み合わせ方、接合方法を床構法とし、床の工事方法、
手順を床工法とし、床構法と床工法を合わせたものを床
構工法としたとき、対象とする床構法モデルの属性であ
る床構法に適用可能なすべての床構工法を選定する手段
と、対象とする床構法モデルの属性とユーザ入力によ
り、床構法計画モデルを設定する手段と、前記選定され
た床構工法から、作成した床構法計画モデルの条件を満
たす床構工法を選定する手段と、ユーザ入力により床工
法計画モデルを設定する手段と、選定された床構工法か
ら、作成した床工法計画モデルの条件を満たす床構工法
を選定する手段と、前記床構法計画モデルと床工法計画
モデルの組み合わせにより床構工法計画を設定する手段
と、選定された各床構工法ごとに床、小梁の仕様を決定
する手段と、選定された各床構工法ごとにコストを算定
する手段とを備えたことを特徴とする。
To this end, the skeleton construction method planning system of the present invention has a physical structure of members relating to the floor,
The method of combining and joining is the floor construction method, the floor construction method,
When the procedure is the floor construction method, and the combination of the floor construction method and the floor construction method is the floor construction method, a means for selecting all floor construction methods applicable to the floor construction method that is the attribute of the target floor construction model, Means for setting a floor construction method planning model by the attribute of the target floor construction method model and user input; and means for selecting a floor construction method satisfying the conditions of the created floor construction planning model from the selected floor construction method , Means for setting a floor construction method model by user input, means for selecting a floor construction method satisfying the conditions of the created floor construction plan model from the selected floor construction method, said floor construction method model and floor construction method plan A means to set the floor construction method plan by combining the models, a means to determine the specifications of the floor and beam for each selected floor construction method, and a means to calculate the cost for each selected floor construction method. Equipped with And wherein the door.

【0006】[0006]

【作用】本発明においては、床構工法の設計にかかわる
計画対象を床構法モデル、施工計画にかかわる計画対象
を床工法モデルとして記述し、併せて計画プロセスの機
能と枠組を計画遂行のための知識計画モデルとして構造
化し、オブジェクト指向のパラダイムを適用してシステ
ム化している。計画プロセス中で使用される構・工法モ
デル、構・工法計画モデルともにオブジェクトであり、
オブジェクト間のリンクを通じて情報のやりとりを行
い、詳細な計画を階層的に展開していくようにしてい
る。
In the present invention, the planning object related to the floor construction method design is described as the floor construction method model, and the planning object related to the construction plan is described as the floor construction method model. It is structured as a knowledge planning model and systematized by applying an object-oriented paradigm. Both the structure / construction method model and the structure / construction method planning model used in the planning process are objects,
Information is exchanged through links between objects, and detailed plans are developed hierarchically.

【0007】[0007]

【実施例】以下、本発明の実施例を図面を参照しつつ説
明する。図1は、本発明の躯体構工法計画システムの1
実施例を示し、システム全体の流れと各機能を示す構成
図である。初期画面を経て、先ず、プロジェクト情報の
管理・選択を実行する。ここで、基本情報、設計情報、
計画結果情報を順次選択、変更、修正すると、構工法概
要計画が設定される。この構工法概要計画は、構工法計
画メニュー画面において、床構工法選定、工期算定、杭
構法選定、躯体構法選定、クレーン選定、プロジェクト
情報表示の各機能画面において逐次、入力、修正、変更
が行われ最善の計画が作られていく。
Embodiments of the present invention will be described below with reference to the drawings. FIG. 1 shows 1 of a structure construction method planning system of the present invention.
FIG. 3 is a configuration diagram illustrating an overall system flow and each function according to an embodiment. First, through the initial screen, management / selection of project information is executed. Here, basic information, design information,
When the plan result information is sequentially selected, changed, and modified, the construction method outline plan is set. This construction method outline plan can be sequentially input, modified, and changed on each function screen of floor construction method selection, construction period calculation, pile construction method selection, frame construction method selection, crane selection, and project information display on the construction method planning menu screen. I will make the best plan.

【0008】図2は前記基本情報の管理・選択画面を示
し、ここで、プロジェクト情報、構工法概要計画、構工
法基本計画、構工法詳細計画を選択する。プロジェクト
情報を選択すると、基本情報、設計情報、計画結果情報
のメニュー画面を呼び出すことができる。構工法概要計
画を呼び出すと、全体工法計画、カレンダー設定、指標
設定のメニュー画面を呼び出すことができる。構工法基
本計画を呼び出すと、構法選定、工程計画、仮設計画の
メニュー画面を呼び出すことができる。構工法詳細計画
を呼び出すと、床構工法選定のメニュー画面を呼び出す
ことができる。
FIG. 2 shows a management / selection screen for the basic information, in which project information, a construction method outline plan, a construction method basic plan, and a construction method detailed plan are selected. If you select project information, you can call the menu screen for basic information, design information, and plan result information. When you call up the construction method overview plan, you can call up the menu screen for the overall construction method plan, calendar setting, and index setting. When you call the construction method basic plan, you can call the menu screen for construction method selection, process planning, and temporary design drawings. When you call up the detailed construction method plan, you can call up the menu screen for floor construction method selection.

【0009】図3は図2のプロジェクト情報のうち基本
情報の表示画面を示し、図4はその入力画面を示してい
る。この画面上で、工事名称、建設地、発注者、設計
者、施工者、用途、着工年月日、竣工年月日、敷地、道
路幅、環境条件、施工条件、敷地条件、中間層地盤種
類、支持層岩種、支持層地盤、地下水データ等を入力
(図4の黒丸)すると、図3の画面に表示されることに
なる。
FIG. 3 shows a display screen of basic information of the project information shown in FIG. 2, and FIG. 4 shows its input screen. On this screen, construction name, construction site, orderer, designer, builder, application, construction date, completion date, site, road width, environmental condition, construction condition, site condition, middle class ground type Input the rock type of the support layer, ground of the support layer, groundwater data, etc. (black circles in FIG. 4), and the data will be displayed on the screen of FIG.

【0010】図5は図2のプロジェクト情報のうち設計
情報と計画結果情報の管理選択を行う画面を示し、設計
情報の新規作成、表示、削除や、既存の設計情報を元に
新しい設計情報の作成や、計画結果情報の新規登録、そ
の表示、削除や、既存の計画結果情報を元に新しい計画
結果情報の作成や、計画結果情報の選択を行う。
FIG. 5 shows a screen for managing and selecting design information and plan result information from the project information shown in FIG. Creation, new registration of plan result information, display and deletion thereof, creation of new plan result information based on existing plan result information, and selection of plan result information are performed.

【0011】図6は図5の画面で選択した設計情報の入
力画面を示し、延床面積、地下見付面積、塔屋階数、積
載荷重、スパン数、使用最大スパン長、カーテンウォー
ルの有無、打込み物の種類、階数、長さ、位置、高さ、
基準階高、基準階床面積等を入力する。図7は、図6の
画面で入力した設計情報の表示画面を示し、前記各種デ
ータに加えて、建物の斜視図や平面図等が表示される。
なお、設計情報を修正する場合には図6の画面に戻る。
FIG. 6 shows an input screen for the design information selected on the screen shown in FIG. 5. The total floor area, the underground found area, the number of tower floors, the load capacity, the number of spans, the maximum span length used, the presence or absence of curtain walls, and the driving Type, floor, length, position, height,
Enter the standard floor height, standard floor area, etc. FIG. 7 shows a display screen of the design information input on the screen of FIG. 6, in which a perspective view and a plan view of the building are displayed in addition to the various data.
When the design information is modified, the screen returns to the screen shown in FIG.

【0012】図8は、図2の構工法概要計画のうち全体
工法計画の入力画面を示し、入力された基本情報および
設計情報から適用可能な構法を選択肢として表示してい
る。以上のようにして入力、選択した情報は、図5の画
面で計画結果情報をクリックすることにより、図9に示
す計画結果情報として表示される。計画結果情報は、構
工法概要計画情報、躯体構法情報、杭構法情報、地下工
事情報、カレンダー情報、クレーン情報からなる。この
計画結果情報の中で未入力のものは入力画面を呼び出し
て入力し、または、既に入力されたものを修正できる。
FIG. 8 shows an input screen for the overall construction method plan in the construction method outline plan shown in FIG. 2, in which applicable construction methods are displayed as options from the input basic information and design information. The information input and selected as described above is displayed as the planning result information shown in FIG. 9 by clicking the planning result information on the screen of FIG. The plan result information includes construction method outline plan information, frame construction method information, pile construction method information, underground construction information, calendar information, and crane information. For this plan result information that has not been entered, it is possible to call the input screen and enter it, or to correct the already entered information.

【0013】図10は図1の構工法概要計画メニュー画
面を示し、全体工法計画機能の実行、日曜祭日をどのよ
うにあつかうかのカレンダー情報の設定、工期および労
務に関する指標データの設定を行う。図11は、図10
の画面で選択した全体工法計画に関係するデータと選定
結果を表示する画面を示し、選択した全体工法計画に基
づいて計画データが表示される。図11において工法名
を選択すると、図12に示す全体工法の詳細情報が表示
される。図13は図10の画面で設定する指標データを
説明する画面を示し、工期短縮率、躯体工期短縮率、躯
体労務量削減率、工業化率のそれぞれ計画値と目標値の
説明が表示されている。
FIG. 10 shows the construction method outline planning menu screen of FIG. 1, in which the execution of the entire construction method planning function, the setting of calendar information on how to handle Sundays and holidays, and the setting of index data relating to the construction period and labor. 11 is the same as FIG.
The screen showing the data related to the whole construction method selected on the screen and the selection result is shown, and the plan data is displayed based on the selected whole construction method plan. When the construction method name is selected in FIG. 11, detailed information on the entire construction method shown in FIG. 12 is displayed. FIG. 13 shows a screen for explaining the index data set on the screen of FIG. 10, in which a plan value and a target value for the work period reduction rate, the construction period reduction rate, the body labor labor reduction rate, and the industrialization rate are displayed. .

【0014】図14は、図1の構工法計画メニュー画面
を示し、基本情報、設計情報および計画結果情報の表示
が可能であり、そして、プロジェクト情報の表示、工期
算定機能の実行、躯体構工法、杭構工法、床構工法、ク
レーン選定機能の実行を選択することができる。
FIG. 14 shows the construction method planning menu screen of FIG. 1, in which basic information, design information and planning result information can be displayed, and project information is displayed, the construction period calculation function is executed, and the structure construction method is displayed. , Pile construction method, Floor construction method, Crane selection function can be selected.

【0015】図15は、図14の画面で選択した工期算
定機能データの表示画面を示し、工期算定に必要な情報
が表示され、ここで、工事補正値情報、地下工事工法、
PC(プレキャスト化)工事情報を入力・修正する場合
には、「データ修正」の文字をクリックすると図16に
示す工期算定データ修正画面が表示される。工期算定を
実行する場合には、「工期算定実行」の文字をクリック
すると図17に示す工期工程画面が表示され、標準工期
と計画中の工期が比較できるようにしている。
FIG. 15 shows a display screen of the work period calculation function data selected on the screen of FIG. 14, in which the information necessary for the work period calculation is displayed. Here, the construction correction value information, the underground construction method,
When inputting / correcting PC (precast) construction information, clicking the word "data correction" displays the work period calculation data correction screen shown in FIG. When executing the work period calculation, clicking the character “work period calculation execution” displays the work period process screen shown in FIG. 17 so that the standard work period and the planned work period can be compared.

【0016】図18は図1および図14に示した躯体構
法選定画面を示し、躯体構法選定に必要な情報および選
定結果を表示し、この画面から詳細情報の表示および躯
体構法の選定を行う。躯体構法情報を入力・修正する場
合には「詳細スパン長修正」の文字をクリックすると、
図19に示す入力画面が表示され、詳細スパン長の入力
を確認するために平面図を表示する場合には、「平面図
表示」の文字をクリックすると、図20に示す画面が表
示される。図21は躯体構法の詳細情報を示す画面であ
る。
FIG. 18 shows the frame construction method selection screen shown in FIGS. 1 and 14, displaying the information necessary for the frame construction method selection and the selection result, and the detailed information is displayed and the frame construction method is selected from this screen. When inputting / correcting the frame structure information, click the word "Detail span length correction"
When the input screen shown in FIG. 19 is displayed and the plan view is displayed in order to confirm the input of the detailed span length, clicking the letters “plan view display” displays the screen shown in FIG. FIG. 21 is a screen showing detailed information on the frame construction method.

【0017】図22は図1および図14に示したクレー
ン選定(仮設計画)機能のうちクレーン標準モデル選択
画面を示し、クレーン選定に必要な情報とクレーン計画
標準モデルを表示する画面である。モデルが選択されて
いるか否かはモデル名の右に「選択」、「未選択」で区
別される。図23は図22の画面で選択したクレーン計
画モデルの修正画面を示し、クレーン計画モデル情報の
一覧表示とクレーン計画モデルの平面図を表示してい
る。図では2台のクレーンの設置位置(×印)とクレー
ンの行動範囲が表示され、クレーンの位置の移動、台
数、最大吊荷重等が修正される。
FIG. 22 shows a crane standard model selection screen of the crane selection (temporary design) function shown in FIGS. 1 and 14, and is a screen for displaying information necessary for crane selection and a crane planning standard model. Whether or not a model is selected is distinguished by "selected" and "unselected" to the right of the model name. FIG. 23 shows a screen for modifying the crane planning model selected on the screen of FIG. 22, showing a list of crane planning model information and a plan view of the crane planning model. In the figure, the installation position of the two cranes (marked with X) and the action range of the crane are displayed, and the movement of the crane position, the number of cranes, the maximum lifting load, etc. are corrected.

【0018】図24は図1および図14に示した床構工
法選定機能のうち床構工法計画管理画面を示している。
この画面において、床構工法計画を新規に作成し、床構
工法計画の選定結果を表示し、床構工法計画を削除し、
単価情報を修正することができる。図24において、
「新規」の文字をクリックすると図25に示す床構工法
計画のコード入力画面が表示される。また、「単価変
更」の文字をクリックすると図26に示す単価情報修正
画面が表示される。
FIG. 24 shows a floor construction method plan management screen of the floor construction method selection function shown in FIGS. 1 and 14.
On this screen, create a new floor construction method plan, display the selection results of the floor construction method plan, delete the floor construction method plan,
Unit price information can be modified. In FIG. 24,
When the character "new" is clicked, the code input screen for the floor construction method plan shown in FIG. 25 is displayed. Further, when the character "change unit price" is clicked, the unit price information correction screen shown in FIG. 26 is displayed.

【0019】図27は、床構工法モデルの管理選択と選
定対象とする床構法モデルの選択を行う画面である。床
構法モデルを選択する場合には、1スパンのモデル図の
上に表示されているモデル名をクリックし選択する。床
構法モデルを新規に作成する場合には、「モデル作成」
の文字をクリックし、「床構法計画」を選択し、モデル
名をクリックする。
FIG. 27 is a screen for performing management selection of a floor construction method model and selection of a floor construction method model to be selected. When selecting the floor construction model, click the model name displayed on the model diagram of one span to select it. When creating a new floor construction model, click "Create Model".
Click the letter, select "Floor construction plan", and click the model name.

【0020】図28は図27の画面で選択する床工法計
画モデルの表示画面を示し、図29は床構法計画モデル
の登録画面を示し、図30は床工法計画モデルの登録画
面を示している。図31および図32は複数の床構工法
の選定結果の表示画面を示し、コストが最も低いものを
カラーで識別可能にしている。図33は床構工法の決定
を行う画面を示し、床構法モデル名と適用可能な床構工
名、コストが表示されている。
FIG. 28 shows a display screen of a floor construction method plan model selected on the screen of FIG. 27, FIG. 29 shows a floor construction method plan model registration screen, and FIG. 30 shows a floor construction method plan model registration screen. . FIG. 31 and FIG. 32 show display screens of the selection results of a plurality of floor construction methods, and the one with the lowest cost can be identified by color. FIG. 33 shows a screen for determining a floor construction method, in which the floor construction model name, applicable floor construction name, and cost are displayed.

【0021】次に、本発明の詳細を床構工法を例にして
説明する。なお、本システムにおいては、「床構法」、
「床工法」および「床構工法」の意味は、 床構法:床に関する部材の物的構成、組み合わせ方、接
合方法 床工法:床の工事方法、手順 床構工法:床構法と床工法を合わせたもの である。
Next, the details of the present invention will be described by taking a floor construction method as an example. In addition, in this system, "floor construction method",
The meaning of "floor construction method" and "floor construction method" is: floor construction method: physical composition, combination method, and joining method of members related to floor floor construction method: floor construction method, procedure floor construction method: combining floor construction method and floor construction method It is a thing.

【0022】図34は、床構工法計画における各モデル
間の関係と情報を示す図である。床構法モデルは、適用
躯体構法、適用可能な床構法、適用スパン長、荷重条
件、小梁配置方法等からなり、この床構法モデルに、梁
・柱・床の仕様、コンクリート強度、PC小梁の属性、
PICOS構法(PC板と後打ちコンクリートによる工
法)の属性等、部材の構造を追加し、床構法計画モデル
が作成される。一方、仮設荷重、たわみ許容値、存置日
数、工区分割数、クレーン機種、各施工段階でのサポー
ト本数、サポート層数、接合状態等を設定した床工法計
画モデルを作成し、この床工法計画モデルと前記床構法
計画モデルにより床構工法計画を作成するものである。
FIG. 34 is a diagram showing the relationship and information between the models in the floor construction method plan. The floor construction method model consists of applicable frame construction method, applicable floor construction method, applicable span length, load condition, beam arrangement method, etc. This floor construction model includes beam / column / floor specifications, concrete strength, PC beam Attributes of
The floor construction method planning model is created by adding the structure of members such as attributes of PICOS construction method (construction method using PC board and post-cast concrete). On the other hand, a floor construction method planning model is created by setting temporary load, allowable deflection, number of days left, number of divisions of work area, crane model, number of supports at each construction stage, number of support layers, joining state, etc. And a floor construction method plan is created by the floor construction method planning model.

【0023】図35は前記床構法モデルが階層構造にな
っていることを示し、図36〜図38は前記床構法モデ
ルの種類とその属性情報を示し、図39は躯体構法別に
分類した適用可能な床構法モデルを示している。
FIG. 35 shows that the floor construction method model has a hierarchical structure, FIGS. 36 to 38 show types of the floor construction method model and their attribute information, and FIG. 39 is applicable by classifying by the construction method Shows a simple floor construction model.

【0024】図40および図41は、本発明における床
構工法の選定方法を説明するための処理の流れを示す図
である。先ず、ステップで選定対象とするスパンをユ
ーザにより決定し、ステップにおいて、対象とする床
構法モデルの属性である床構法に、適用可能なすべての
床構工法を選定する。ステップにおいては、対象とす
る床構法モデルの属性とユーザ入力により、床構法計画
モデルを設定する。なお、床構法計画モデルは1つの床
構法モデルに対して複数のモデルが作成可能である。ス
テップでは、ステップで選定された床構工法から、
作成した床構法計画モデルの条件を満たす床構工法を選
定する。ステップでは、ユーザ入力により、床工法計
画モデルを設定する。床工法計画モデルは、1つの床構
法計画モデルに対して複数のモデルが作成可能である。
ステップでは、ステップで選定された床構工法か
ら、作成した床工法計画モデルの条件を満たす床構工法
を選定する。ステップでは、床構法計画モデルと床工
法計画モデルの組み合わせにより床構工法計画を設定す
る。床構工法計画は、床構法計画モデルと床工法計画モ
デルとのすべての組み合わせを設定可能にしている。そ
して、選定された各床構工法ごとに床、小梁の仕様を決
定する。ステップではステップで選定された各床構
工法ごとにコストを算定する。そして、ステップでス
テップで選定された各床構工法の中からステップ、
の検討結果を参考にし、1つの床構工法を設定する。
40 and 41 are diagrams showing the flow of processing for explaining the method of selecting the floor construction method according to the present invention. First, the user determines the span to be selected in step, and in step, all applicable floor construction methods are selected for the floor construction method that is the attribute of the target floor construction model. In the step, a floor construction method planning model is set according to the attribute of the floor construction method model and the user input. Note that a plurality of floor construction method planning models can be created for one floor construction method model. In the step, from the floor construction method selected in the step,
A floor construction method that meets the conditions of the created floor construction plan model is selected. In step, a floor construction method planning model is set by user input. In the floor construction method planning model, a plurality of models can be created for one floor construction method planning model.
In the step, a floor construction method satisfying the conditions of the created floor construction method planning model is selected from the floor construction methods selected in the step. In step, the floor construction method plan is set by combining the floor construction method planning model and the floor construction method planning model. In the floor construction method plan, all combinations of the floor construction method planning model and the floor construction method planning model can be set. Then, the floor and beam specifications are determined for each selected floor construction method. In step, the cost is calculated for each floor construction method selected in step. And, from each floor construction method selected in step in step, step,
One floor construction method will be set up by referring to the examination results.

【0025】次に、各クラス・オブジェクトごとに変数
とメソッド(手続き)を説明する。図42は、床構工法
計画のオブジェクト構成図である。床構工法計画は、床
選定情報モジュール全体を管理し、対象としている各種
床計画モデルの属性を保持することを目的とする。手続
きの概要は以下のとおりである。
Next, variables and methods (procedures) will be described for each class object. FIG. 42 is an object block diagram of a floor construction method plan. The floor construction method plan is intended to manage the entire floor selection information module and hold the attributes of various floor planning models targeted. The outline of the procedure is as follows.

【0026】オブジェクトのリンク:床計画情報モジ
ュール内のオブジェクト間のリンクを行い、リンク先の
オブジェクトの属性を取得する。これにより、多量かつ
複雑な床計画情報フレームを明確に表現し、拡張性の高
いオブジェクト構成を実現することができる。
Object linking: The objects in the floor plan information module are linked and the attributes of the linked objects are acquired. As a result, a large amount of complicated floor plan information frames can be clearly expressed, and a highly expandable object configuration can be realized.

【0027】初期値設定:各種計画モデルに適当な初
期値を、プロジェクト情報や躯体構法情報等を参考にし
て設定する。
Initial value setting: An appropriate initial value for various planning models is set with reference to project information, frame construction method information, and the like.

【0028】床構工法計画:「床構工法計画」・「床
工法計画」にメッセージ送信することにより、床構工法
選定機能を起動させる。また、「床構工法計画」・「床
工法計画」にメッセージ送信することにより、1スパン
を構成する部材のコスト総計を算出する。
Floor construction method plan: The floor construction method selection function is activated by sending a message to the "floor construction method plan" / "floor construction method plan". Also, by sending a message to the “floor construction method plan” / “floor construction method plan”, the total cost of the members constituting one span is calculated.

【0029】図43は、床構法計画のオブジェクト構成
図である。床構法計画の目的は、1スパンを構成してい
る部材をオブジェクトとして定義し、オブジェクト単位
でのモデル図表示を実現させることである。また、使用
時のプロセスのチェックと1スパンを構成する部位ごと
に求めたコストから1スパンのコストの算出を行う。そ
してスパンを構成する部位を定義し、そのインスタント
・オブジェクトとして選定対象となる1スパンを構成す
る部材を定義する。手続きの概要は以下のとおりであ
る。
FIG. 43 is an object block diagram of a floor construction plan. The purpose of the floor construction plan is to define the members that compose one span as an object and realize the model diagram display for each object. Also, the process for use is checked and the cost of one span is calculated from the cost obtained for each part forming one span. Then, the parts constituting the span are defined, and the members constituting one span to be selected as the instant object are defined. The outline of the procedure is as follows.

【0030】平面図表示:1スパンのモデル図(平面
図)を表示する。クラス・オブジェクトがインスタント
・オブジェクトにメッセージ送信することにより部材単
位で描画させる。
Plan view display: A model view (plan view) of one span is displayed. The class object sends a message to the instant object so that it is drawn on a member-by-member basis.

【0031】コスト合計:1スパンを構成する部位ご
とに求めたコストの合計の算出を行う。
Total cost: The total cost calculated for each part constituting one span is calculated.

【0032】図44は、図36の床構法モデル5の場合
のオブジェクト構成図である。
FIG. 44 is an object configuration diagram in the case of the floor construction method model 5 of FIG.

【0033】図45は床工法計画のオブジェクト構成図
を示し、たわみ許容値、工区分割数等の工事情報の属性
と各コストの算定項目ごとのコスト算定、プロセスごと
のチェックの手続きを持つ。
FIG. 45 shows an object block diagram of a floor construction method plan, which has attributes of construction information such as an allowable deflection value, the number of divisions of work sections, etc., and has a procedure for cost calculation for each cost calculation item and a check for each process.

【0034】図46は、床構工法のオブジェクト構成図
を示し、各床構工法の適用条件による選定、仕様の検
討、コストの算定を行い、その結果をクラス・オブジェ
クトの属性値として登録する。手続きの概要は以下のと
おりである。
FIG. 46 shows an object configuration diagram of the floor construction method. Selection according to application conditions of each floor construction method, examination of specifications, cost calculation, and registration of the result as an attribute value of a class object. The outline of the procedure is as follows.

【0035】適用条件による選定実行:「床計画管
理」の属性である「適用可能な床構工法」に登録されて
いる床構工法の中から各床構工法の適用条件を満たすも
のを選定する。
Execution of selection according to the applicable conditions: From the floor construction methods registered in “Applicable floor construction methods” which is an attribute of “floor plan management”, those that satisfy the application conditions of each floor construction method are selected. .

【0036】仕様決定:床構工法ごとに床の仕様を決
定する。
Specification determination: The floor specifications are determined for each floor construction method.

【0037】コスト算出:床構工法ごとの床のコスト
を算出する。
Cost calculation: The cost of the floor for each floor construction method is calculated.

【0038】図47は小梁のオブジェクト構成図を示
し、各小梁の適用条件による選定、仕様の検討(ひびわ
れチェック)、コストの算定を行い、その結果をクラス
・オブジェクトの属性値として登録する。手続きの概要
は以下のとおりである。
FIG. 47 is a diagram showing an object structure of a beam, which is selected according to the application conditions of each beam, the specification is examined (crack check), the cost is calculated, and the result is registered as an attribute value of the class object. . The outline of the procedure is as follows.

【0039】仕様決定(ひびわれチェック):小梁が
PCの場合にPC小梁のひびわれチェックを行う。ここ
でNGとなった場合はPC小梁は適用不可とする。
Specification determination (crack check): When the beam is a PC, the PC beam is checked for cracks. If the result is NG here, the PC beam is not applicable.

【0040】コスト算出:小梁ごとのコストを算出す
る。
Cost calculation: The cost for each beam is calculated.

【0041】図48は床単価コストのオブジェクト構成
図を示し、床のコスト算定に必要な情報の単価データを
持つものとする。
FIG. 48 shows an object configuration diagram of floor unit cost, and has unit price data of information necessary for floor cost calculation.

【0042】[0042]

【発明の効果】以上の説明から明らかなように本発明に
よれば、躯体構工法計画を工程計画、仮設計画とあわせ
て概略、基本、詳細と階層的に展開できるので、計画の
整合性が保たれ計画精度を向上させることができる。ま
た、設計情報と施工情報をモデル化することにより、様
々な条件設定を反映した計画シミュレーションおよび計
画案の比較を短時間で行うことができる。さらに、新し
い計画方法や構・工法を追加する場合にシステムの拡張
が容易となり、システム開発が効率化できる。
As is apparent from the above description, according to the present invention, the structure construction method plan can be hierarchically developed in outline, basic, and detail together with the process plan and the tentative design image. The planning accuracy can be improved. In addition, by modeling the design information and the construction information, it is possible to compare the plan simulation and the plan proposal reflecting various condition settings in a short time. Furthermore, when a new planning method or construction / construction method is added, the system can be easily expanded and system development can be made more efficient.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の躯体構工法計画システムの1実施例を
示し、システム全体の流れと各機能を示す構成図であ
る。
FIG. 1 is a configuration diagram showing an embodiment of a skeleton construction method planning system of the present invention and showing a flow and respective functions of the entire system.

【図2】図1の基本情報の管理・選択画面を示す図であ
る。
FIG. 2 is a diagram showing a basic information management / selection screen of FIG.

【図3】図2のプロジェクト情報のうち基本情報の表示
画面を示す図である。
3 is a diagram showing a display screen of basic information of the project information of FIG.

【図4】図3の基本情報の入力画面を示す図である。FIG. 4 is a diagram showing a basic information input screen of FIG. 3;

【図5】図2のプロジェクト情報のうち設計情報と計画
結果情報の管理選択を行う画面を示す図である。
5 is a diagram showing a screen for management selection of design information and plan result information in the project information of FIG. 2;

【図6】図5の画面で選択した設計情報の入力画面を示
す図である。
6 is a diagram showing a design information input screen selected on the screen of FIG. 5;

【図7】図6の画面で入力した設計情報の表示画面を示
す図である。
FIG. 7 is a diagram showing a display screen of design information input on the screen of FIG. 6;

【図8】図2の構工法概要計画のうち全体工法計画の入
力画面を示す図である。
FIG. 8 is a diagram showing an input screen for an overall construction method plan of the construction method outline plan of FIG. 2;

【図9】図5の画面で選択した計画結果情報の表示画面
を示す図である。
9 is a diagram showing a display screen of the planning result information selected on the screen of FIG.

【図10】図1の構工法概要計画メニュー画面を示す図
である。
FIG. 10 is a diagram showing a construction method outline plan menu screen of FIG. 1;

【図11】図10の画面で選択した全体工法計画に関係
するデータと選定結果を表示する画面を示す図である。
11 is a diagram showing a screen displaying data related to the overall construction method plan selected on the screen of FIG. 10 and a selection result.

【図12】図11の画面で選択した全体工法の詳細情報
の表示画面を示す図である。
FIG. 12 is a view showing a display screen of detailed information of the entire construction method selected on the screen of FIG. 11.

【図13】図10の画面で設定する指標データの説明画
面を示す図である。
13 is a diagram showing an explanation screen of index data set on the screen of FIG.

【図14】図1の構工法計画メニュー画面を示す図であ
る。
FIG. 14 is a diagram showing a construction method planning menu screen of FIG. 1.

【図15】図14の画面で選択した工期算定機能データ
の表示画面を示す図である。
FIG. 15 is a diagram showing a display screen of work period calculation function data selected on the screen of FIG. 14;

【図16】図15の画面で選択した工期算定データ修正
画面を示す図である。
16 is a diagram showing a work period calculation data correction screen selected on the screen of FIG.

【図17】図15の画面で選択した工期工程画面を示す
図である。
17 is a diagram showing a construction process screen selected on the screen of FIG.

【図18】図1および図14に示した躯体構法選定画面
を示す図である。
FIG. 18 is a diagram showing a frame construction method selection screen shown in FIGS. 1 and 14;

【図19】図18の画面で選択した詳細スパン長修正画
面を示す図である。
FIG. 19 is a diagram showing a detailed span length correction screen selected on the screen of FIG. 18;

【図20】図19の画面で修正した詳細スパン長の入力
を確認するための画面を示す図である。
20 is a diagram showing a screen for confirming the input of the detailed span length corrected on the screen of FIG.

【図21】躯体構法の詳細情報を示す画面である。FIG. 21 is a screen showing detailed information on a frame construction method.

【図22】図1および図14に示したクレーン選定機能
のうちクレーン標準モデル選択画面を示す図である。
FIG. 22 is a diagram showing a crane standard model selection screen of the crane selection function shown in FIGS. 1 and 14;

【図23】図22の画面で選択したクレーン計画モデル
の修正画面を示す図である。
23 is a diagram showing a screen for modifying the crane planning model selected on the screen of FIG. 22. FIG.

【図24】図1および図14に示した床構工法選定機能
のうち床構工法計画管理画面を示す図である。
FIG. 24 is a diagram showing a floor construction method plan management screen of the floor construction method selection function shown in FIGS. 1 and 14;

【図25】図24の画面で選択した床構工法計画のコー
ド入力画面を示す図である。
25 is a diagram showing a code input screen of the floor construction method plan selected on the screen of FIG. 24.

【図26】図24の画面で選択した単価情報修正画面を
示す図である。
FIG. 26 is a view showing a unit price information correction screen selected on the screen of FIG. 24.

【図27】床構工法モデルの管理選択と選定対象とする
床構法モデルの選択を行う画面を示す図である。
FIG. 27 is a diagram showing a screen for performing management selection of a floor construction method model and selection of a floor construction method model to be selected.

【図28】図27の画面で選択する床工法計画モデルの
表示画面を示す図である。
28 is a diagram showing a display screen of a floor construction method planning model selected on the screen of FIG. 27. FIG.

【図29】図27の画面で選択する床構法計画モデルの
登録画面を示す図である。
29 is a diagram showing a registration screen of a floor construction plan model selected on the screen of FIG. 27.

【図30】図27の画面で選択する床工法計画モデルの
登録画面を示す図である。
FIG. 30 is a view showing a registration screen of a floor construction method planning model selected on the screen of FIG. 27.

【図31】複数の床構工法の選定結果の表示画面を示す
図である。
FIG. 31 is a diagram showing a display screen of selection results of a plurality of floor construction methods.

【図32】複数の床構工法の選定結果の表示画面を示す
図である。
FIG. 32 is a view showing a display screen of selection results of a plurality of floor construction methods.

【図33】床構工法の決定を行う画面を示す図である。FIG. 33 is a diagram showing a screen for determining a floor construction method.

【図34】本発明の床構工法計画における各モデル間の
関係と情報を示す図である。
FIG. 34 is a diagram showing relationships and information between models in the floor construction method plan of the present invention.

【図35】図34の床構法モデルの構造を示す図であ
る。
FIG. 35 is a diagram showing the structure of the floor construction model of FIG. 34.

【図36】図35の床構法モデルの種類とその属性情報
を示す図である。
FIG. 36 is a diagram showing the types of floor construction model of FIG. 35 and their attribute information.

【図37】図35の床構法モデルの種類とその属性情報
を示す図である。
FIG. 37 is a diagram showing types of floor construction models of FIG. 35 and their attribute information.

【図38】図35の床構法モデルの種類とその属性情報
を示す図である。
FIG. 38 is a diagram showing types of floor construction model of FIG. 35 and attribute information thereof.

【図39】躯体構法別に分類した適用可能な床構法モデ
ルを示す図である。
[Fig. 39] Fig. 39 is a diagram illustrating applicable floor construction method models classified according to a frame construction method.

【図40】本発明における床構工法の選定方法を説明す
るための処理の流れを示す図である。
FIG. 40 is a diagram showing a flow of processing for explaining a method for selecting a floor construction method according to the present invention.

【図41】図40に続く処理の流れを示す図である。41 is a diagram showing the flow of processes following FIG. 40. FIG.

【図42】床構工法計画のオブジェクト構成図である。FIG. 42 is an object configuration diagram of a floor construction method plan.

【図43】床構法計画のオブジェクト構成図である。FIG. 43 is an object block diagram of a floor construction plan.

【図44】図36の床構法モデル5の場合のオブジェク
ト構成図である。
FIG. 44 is an object configuration diagram in the case of the floor construction method model 5 of FIG. 36.

【図45】床工法計画のオブジェクト構成図である。FIG. 45 is an object configuration diagram of a floor construction method plan.

【図46】床構工法のオブジェクト構成図である。FIG. 46 is an object configuration diagram of the floor construction method.

【図47】小梁のオブジェクト構成図である。FIG. 47 is an object block diagram of a beam.

【図48】床単価コストのオブジェクト構成図である。[Fig. 48] Fig. 48 is an object configuration diagram of a floor unit cost.

【図49】従来の躯体構工法計画システムを説明するた
めの図である。
FIG. 49 is a diagram for explaining a conventional structure construction method planning system.

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】床に関する部材の物的構成、組み合わせ
方、接合方法を床構法とし、床の工事方法、手順を床工
法とし、床構法と床工法を合わせたものを床構工法とし
たとき、対象とする床構法モデルの属性である床構法に
適用可能なすべての床構工法を選定する手段と、対象と
する床構法モデルの属性とユーザ入力により、床構法計
画モデルを設定する手段と、前記選定された床構工法か
ら、作成した床構法計画モデルの条件を満たす床構工法
を選定する手段と、ユーザ入力により床工法計画モデル
を設定する手段と、選定された床構工法から、作成した
床工法計画モデルの条件を満たす床構工法を選定する手
段と、前記床構法計画モデルと床工法計画モデルの組み
合わせにより床構工法計画を設定する手段と、選定され
た各床構工法ごとに床、小梁の仕様を決定する手段と、
選定された各床構工法ごとにコストを算定する手段とを
備えたことを特徴とする躯体構工法計画システム。
1. A floor construction method is used as a physical configuration, a combination method, and a joining method of members related to a floor, a floor construction method and procedure are a floor construction method, and a combination of the floor construction method and the floor construction method is a floor construction method. , A method for selecting all floor construction methods applicable to the floor construction method which is an attribute of the target floor construction model, and a means for setting a floor construction plan model by the attributes of the target floor construction model and user input From the selected floor construction method, means for selecting a floor construction method that meets the conditions of the created floor construction plan model, means for setting a floor construction plan model by user input, and the selected floor construction method, A means for selecting a floor construction method that satisfies the conditions of the created floor construction method model, a means for setting a floor construction method plan by combining the floor construction method planning model and the floor construction method planning model, and for each selected floor construction method To , Means for determining a small beam specifications,
A skeleton construction method planning system comprising means for calculating the cost for each selected floor construction method.
JP6070475A 1994-04-08 1994-04-08 Skeleton construction method scheduling system Pending JPH07282112A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP6070475A JPH07282112A (en) 1994-04-08 1994-04-08 Skeleton construction method scheduling system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP6070475A JPH07282112A (en) 1994-04-08 1994-04-08 Skeleton construction method scheduling system

Publications (1)

Publication Number Publication Date
JPH07282112A true JPH07282112A (en) 1995-10-27

Family

ID=13432596

Family Applications (1)

Application Number Title Priority Date Filing Date
JP6070475A Pending JPH07282112A (en) 1994-04-08 1994-04-08 Skeleton construction method scheduling system

Country Status (1)

Country Link
JP (1) JPH07282112A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002146825A (en) * 2000-11-07 2002-05-22 Landes Co Ltd Automatic selection system in civil engineering construction method and automatic selection method and server and data base used in method
JP2008276591A (en) * 2007-05-01 2008-11-13 Shimizu Corp Building information processing system and building information processing method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002146825A (en) * 2000-11-07 2002-05-22 Landes Co Ltd Automatic selection system in civil engineering construction method and automatic selection method and server and data base used in method
JP2008276591A (en) * 2007-05-01 2008-11-13 Shimizu Corp Building information processing system and building information processing method

Similar Documents

Publication Publication Date Title
US7529650B2 (en) Computer-implemented building design and modeling and project cost estimation and scheduling system
Li et al. Optimizing construction planning schedules by virtual prototyping enabled resource analysis
Candelario-Garrido et al. A quantitative analysis on the feasibility of 4D planning graphic systems versus conventional systems in building projects
Li et al. Virtual experiment of innovative construction operations
US20200250354A1 (en) Building information modeling system with self-configuration
Huang et al. Planning gang formwork operations for building construction using simulations
JP3337207B2 (en) Construction system support system
Huhnt et al. Data management for animation of construction processes
US20100274374A1 (en) System and process for the detailed design and production of reinforcement for buildings
Schwabe et al. BIM applications of rule-based checking in construction site layout planning tasks
Wu et al. BIM-based estimation of vertical transportation demands during the construction of high-rise buildings
Ko et al. Making formwork design lean
Zouein MoveSchedule: A planning tool for scheduling space use on construction sites
JP2006201979A (en) Program for supporting construction planning of building
Parrish Applying a set-based design approach to reinforcing steel design
KR102112749B1 (en) Method for managing of the tower crane using construction management plan and computer readable media thereof
JPH07282112A (en) Skeleton construction method scheduling system
JP2005018673A (en) Method for supporting formation of process chart
JP3756416B2 (en) Simple quantity setting method of structure, simple quantity setting device, and storage medium used therefor
Chua et al. Application of component state model for identifying constructability conflicts in a merged construction schedule
Alkass et al. Computerized crane selection for construction projects
Sawhney Simulation-based planning for construction
Winstanley et al. Model-based planning utilizing activity aggregation based on zones
JPH07247688A (en) Work plan control system based on 3-dimensional data
Winstanley et al. An integrated project planning environment