JPH07133015A - Bobbin supplying device - Google Patents

Bobbin supplying device

Info

Publication number
JPH07133015A
JPH07133015A JP30478093A JP30478093A JPH07133015A JP H07133015 A JPH07133015 A JP H07133015A JP 30478093 A JP30478093 A JP 30478093A JP 30478093 A JP30478093 A JP 30478093A JP H07133015 A JPH07133015 A JP H07133015A
Authority
JP
Japan
Prior art keywords
conveyor
yarn
bobbins
conveyer
feeder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP30478093A
Other languages
Japanese (ja)
Inventor
Takashi Nakagawa
隆 中川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Murata Machinery Ltd
Original Assignee
Murata Machinery Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Murata Machinery Ltd filed Critical Murata Machinery Ltd
Priority to JP30478093A priority Critical patent/JPH07133015A/en
Publication of JPH07133015A publication Critical patent/JPH07133015A/en
Pending legal-status Critical Current

Links

Landscapes

  • Replacing, Conveying, And Pick-Finding For Filamentary Materials (AREA)
  • Control Of Conveyors (AREA)
  • Filling Or Emptying Of Bunkers, Hoppers, And Tanks (AREA)
  • Feeding Of Articles To Conveyors (AREA)

Abstract

PURPOSE:To prevent situation that a parts feeder becomes incapable of supplying bobbins caused by slide-down of a big pipe of bobbins at one time. CONSTITUTION:A detecting means 27 for bobbins exsist in the specific height position on a conveyer is provided on a conveyer 4 for feeding a big pile of bobbins simultaneously supplied in large quantities to a feeder bowl 6 by inclining a waggon 2. When the detecting means 27 detects the bobbins in the position higher than the prefixed reference position in the specific position on the conveyer 4, it is considered that there is a pipe part of the bobbins on the conveyer, and the supplying capacity of the conveyer is controlled to the low level by shortening the operating time of the conveyer 4 or decreasing the driving speed, and the bobbins are split little by little, so as to be supplied into the feeder bowl 6.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、自動ワインダーの機台
を循環する管糸搬送トレイの管糸供給装置に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a yarn feeding device for a yarn feeding tray which circulates through a machine stand of an automatic winder.

【0002】[0002]

【従来の技術】従来、自動ワインダーの各錘に精紡管糸
を供給する場合、管糸をワゴンにばら積みして管糸供給
装置まで運搬し、該ワゴンを荷あけ装置で反転、傾倒し
て、ワゴン内の管糸をコンベア上に段階的に荷あけし、
該コンベアにより荷あけされた管糸の積み山を切崩しな
がら振動式パーツフィーダーのフィーダーボール内に送
給していた。そして、上記パーツフィーダーと、それに
続く分離コンベアにより、フィーダーボール内の管糸を
1個ずつ分離して天尻判別部に送給し、天尻判別を行な
った後、供給ステーションからの管糸要求に応じて上記
天尻判別部の管糸を整列シュート内に投下し、該整列シ
ュートの下方に停止されている空トレイのペグに挿立し
て供給していた。
2. Description of the Related Art Conventionally, in the case of supplying a spinning yarn to each weight of an automatic winder, the yarns are piled up in a wagon and conveyed to a yarn feeding device, and the wagon is inverted and tilted by a unloading device. , Unloading the yarn in the wagon onto the conveyor in stages,
The pile of pipe threads unloaded by the conveyor was fed while being fed into the feeder ball of the vibrating parts feeder. Then, the parts feeder and the separating conveyor following the parts feeder separate the yarns in the feeder ball one by one, and feed the yarns to the tail end discrimination section to perform the tail end discrimination, and then to request the yarn from the supply station. In accordance with the above, the yarn from the above-mentioned top end determining portion was dropped into the alignment chute, and was inserted into the peg of the empty tray stopped below the alignment chute and supplied.

【0003】このような管糸供給装置において、振動式
パーツフィーダーの分離供給能力を飽和させないために
は、フィーダーボール内の管糸の量が多くなり過ぎない
ようにする必要があり、このため、フィーダーボール内
にレベルセンサを設けそれによりコンベアの駆動を制御
して間欠的に行ないフィーダーボール内の管糸の量を調
整するようにしていた。
In such a yarn feeder, in order not to saturate the separating and feeding ability of the vibrating part feeder, it is necessary to prevent the amount of yarn in the feeder ball from becoming too large. A level sensor is provided in the feeder ball to control the drive of the conveyor to intermittently adjust the amount of the yarn in the feeder ball.

【0004】ところが、上記コンベアの駆動を間欠的に
行った場合においても、コンベア上に荷あけされた管糸
の山が、切崩されずにそのままフィーダーボール内にな
だれ込むと、パーツフィーダーが供給不能となる事態が
発生する恐れがあった。
However, even when the above conveyor is driven intermittently, if the piles of the tubing unloaded on the conveyor rush into the feeder ball without being broken, the parts feeder cannot be supplied. There was a risk that

【0005】[0005]

【発明が解決しようとする課題】本発明は、従来のこの
ような点に鑑みて、パーツフィーダーが供給不能となる
事態を防止することが可能な管糸供給装置を提供するこ
とを目的とするものである。
SUMMARY OF THE INVENTION The present invention has been made in view of the above-mentioned problems, and an object of the present invention is to provide a yarn supplying device capable of preventing a situation in which a parts feeder cannot be supplied. It is a thing.

【0006】[0006]

【課題を解決するための手段】同時に多量に供給された
管糸をフィーダボールへ送給するコンベアに、該コンベ
ア上の所定の高さ位置に存在する管糸の検知手段を設け
た。
Means for Solving the Problems At the same time, a conveyer for feeding a large amount of supplied yarn to a feeder ball is provided with a detector for the yarn present at a predetermined height position on the conveyor.

【0007】[0007]

【作用】検知手段が、コンベア上の所定の位置におい
て、予め定めた基準より高い位置で管糸を検知した場合
には、コンベア上に管糸の山積部分が存在するものとみ
なし、コンベアの駆動時間を短縮するか、若しくは駆動
速度を低速にして該コンベアの供給能力をローレベルに
制御する。
When the detecting means detects the yarn at a predetermined position on the conveyor at a position higher than a predetermined reference, it is considered that there is a pile portion of the yarn on the conveyor, and the conveyor is driven. The supply capacity of the conveyor is controlled to a low level by shortening the time or lowering the driving speed.

【0008】[0008]

【実施例】実施の一例について図面と供に説明する。DESCRIPTION OF THE PREFERRED EMBODIMENTS An example of the embodiment will be described with reference to the drawings.

【0009】図1において、本発明の管糸供給装置1
は、管糸をばら積みして運搬するワゴン2を反転、傾倒
して荷あけする荷あけ装置3、荷あけされた管糸の積み
山を切り崩しながらフィーダーボール6内へ送給する2
段に分割されたコンベア4,5振動式のパーツフィーダ
7、該パーツフィーダ7より順次送出される管糸を1個
ずつ分離して供給する分離コンベア8、該分離コンベア
8より供給された管糸の天尻判別を行なう天尻判別部
9、該天尻判別部9よりトレイ搬送路12の一部に設け
た供給ステーション11に停止している空トレイ13に
管糸を投下して挿立する整列シュート10より主に構成
されている。14は整列シュート10の下端に開閉自在
に設けたシュートガイドである。
Referring to FIG. 1, a yarn feeder 1 of the present invention.
Is a unloading device 3 for inverting and tilting a wagon 2 for transporting bulk piled yarns and tilting it, and feeding into the feeder ball 6 while breaking down the pile of piled pipe yarns 2
Conveyors 4, 5 vibrating parts feeder 7 divided into stages, separating conveyor 8 for separating and supplying the yarns sequentially sent out from the parts feeder 7, one by one, and the yarns supplied from the separating conveyer 8. A top end determining portion 9 for determining the top end, and a thread is dropped from the top end determining portion 9 to an empty tray 13 stopped at a supply station 11 provided in a part of the tray transport path 12 for insertion. It is mainly composed of an alignment chute 10. Reference numeral 14 denotes a chute guide provided at the lower end of the alignment chute 10 so as to be openable and closable.

【0010】荷あけ装置3は、図1中右方向より進入し
たワゴン2を収容して拘持する可動フレーム31を備え
ている。可動フレーム31は、その背部において同期回
転する平行な一対のエンドレスチェーン32(図1中手
前側は省略されている。)に両側から軸5において回転
自在に支持され、該エンドレスチェーン32は荷あけ装
置3の上下に配置した一対のスプロケット33,34間
に張架され、図示しない動力により駆動される。更に、
上記可動フレーム31の背部には、その両側に設けた一
対のガイド溝36に係合するガイドローラ37を突設し
ている。また、上記エンドレスチェーン32の一部に
は、該エンドレスチェーン32の軌道に沿って所定の間
隔で複数段(図示例では3段)設けたリミットスイッチ
21,22,23に当接するドック38を設けている。
The unloading device 3 is provided with a movable frame 31 for accommodating and holding the wagon 2 which has entered from the right side in FIG. The movable frame 31 is rotatably supported on the shaft 5 from both sides by a pair of parallel endless chains 32 (the front side in FIG. 1 is omitted) that rotate synchronously at the back thereof, and the endless chains 32 are unloaded. It is stretched between a pair of sprockets 33 and 34 arranged above and below the device 3, and is driven by a power not shown. Furthermore,
A guide roller 37 is provided on the back of the movable frame 31 so as to engage with a pair of guide grooves 36 provided on both sides thereof. Further, a part of the endless chain 32 is provided with a dock 38 that abuts against limit switches 21, 22, and 23 provided at a plurality of stages (3 stages in the illustrated example) at predetermined intervals along the track of the endless chain 32. ing.

【0011】コンベア4は、上記荷あけ装置3よりパー
ツフィーダ7に向けて設けられ、その周囲に樋状の側壁
41を設けてある。また、該コンベア4の終端部42に
は、該部よりフィーダーボール6の略中央上位に至るコ
ンベア5が連続している。該コンベア5は、上記コンベ
ア4と共通の駆動源により同時に一定の速度比で間欠的
に駆動され、コンベア5の速度はコンベア4の速度に対
して充分高速であるように設定してある。上記コンベア
4及びコンベア5の1回の間欠駆動における駆動時間に
は、長短2種類が存在し、該長短2種類の駆動時間は後
述するセンサ27からの信号により切換えられる。
The conveyor 4 is provided toward the parts feeder 7 from the unloading device 3, and a gutter-shaped side wall 41 is provided around the conveyor 4. Further, at the terminal end portion 42 of the conveyer 4, the conveyer 5 extending from the above portion to substantially the upper center of the feeder ball 6 is continuous. The conveyor 5 is intermittently driven by a common drive source at the same time at a constant speed ratio, and the speed of the conveyor 5 is set to be sufficiently higher than the speed of the conveyor 4. There are two types of driving time in the intermittent driving of the conveyor 4 and the conveyor 5, one of which is long and the other of which is short, and the driving time of the two types of long and short is switched by a signal from a sensor 27 described later.

【0012】そして、コンベア4の搬送方向略中央、及
び、コンベア5の搬送面上には、該部における管糸の有
無を検知するセンサ24,25を設けている。また、コ
ンベア5の終端部51の上位には、コンベア4とコンベ
ア5の連続部分、若しくは、コンベア4の終端部42の
搬送面上方の所定の高さ位置における管糸の有無を検知
するセンサ27を設けている。尚、26は、フィーダー
ボール6内に貯溜されている管糸の量を検知するための
レベルセンサである。
Sensors 24 and 25 for detecting the presence / absence of a yarn in the conveyor 4 are provided substantially at the center of the conveyor 4 in the conveying direction and on the conveying surface of the conveyor 5. Further, above the terminal end portion 51 of the conveyor 5, a sensor 27 that detects the presence or absence of a yarn at a predetermined continuous position above the conveying surface of the conveyor 4 and the end portion 42 of the conveyor 4 or a continuous portion of the conveyor 4 and the conveyor 5. Is provided. Incidentally, reference numeral 26 is a level sensor for detecting the amount of the tube yarn stored in the feeder ball 6.

【0013】次に、実施例に基づいて管糸供給装置1の
作動について説明する。
Next, the operation of the yarn feeding device 1 will be described based on an embodiment.

【0014】図1において、管糸をばら積みしたワゴン
2は、31´の如く最下端に位置している可動フレーム
31に、2´の如く停止され、その位置で可動フレーム
31に拘持される。そして、チェーン32の駆動によ
り、ワゴン2は可動フレーム31ごと上昇され、且つ、
可動フレーム31のガイドローラ37がガイド溝36で
案内されることにより、反転され、傾倒されることによ
り、上記ワゴン2内の管糸はコンベア4上に荷あけされ
る。この際、ワゴン2は、一時に傾倒されるのではな
く、チェーン32に設けたドック38が3段のリミット
スイッチ21,22,23に夫々当接して、該スイッチ
を蹴る度毎に上記チェーン32の駆動を一担停止して、
その角度位置を保持した後、センサ24が、該部のコン
ベア4上に管糸が存在しないことを検知することによ
り、該センサ24から出力される荷あけ要求信号に応じ
てチェーン32を駆動し、ワゴン2を漸次傾倒すること
により、該ワゴン2内の管糸をコンベア4上に少しずつ
荷あけする。
In FIG. 1, the wagon 2 in which the yarns are piled up in bulk is stopped by the movable frame 31 located at the lowermost end like 31 'and held by the movable frame 31 at that position. . Then, by driving the chain 32, the wagon 2 is lifted together with the movable frame 31, and
When the guide roller 37 of the movable frame 31 is guided by the guide groove 36, the guide roller 37 is inverted and tilted, so that the yarn in the wagon 2 is unloaded onto the conveyor 4. At this time, the wagon 2 is not tilted at a time, but the dock 38 provided on the chain 32 abuts on the three-stage limit switches 21, 22, 23, respectively, and each time the switch is kicked, the chain 32 is moved. Stop the drive of
After holding the angular position, the sensor 24 detects that there is no yarn on the conveyor 4 of the section, and drives the chain 32 according to the unloading request signal output from the sensor 24. By gradually inclining the wagon 2, the yarn in the wagon 2 is gradually unloaded onto the conveyor 4.

【0015】次いで、レベルセンサ26が、フィーダー
ボール6内の管糸の残量が少くなったことを検知する
と、上記レベルセンサ26からの信号により、コンベア
4及びコンベア5が所定時間ずつの間欠駆動を行ない、
荷あけされた管糸をフィーダーボール6内へ送給する。
この際、コンベア4に対して、コンベア5を高速で駆動
することにより、コンベア4上に荷あけされた管糸の積
み山の前端部分の管糸を少しずつ切り崩してフィダーボ
ール6内へ投下する。
Next, when the level sensor 26 detects that the remaining amount of the yarn in the feeder ball 6 is low, the signal from the level sensor 26 causes the conveyors 4 and 5 to intermittently drive for a predetermined time. The
The unloaded tube yarn is fed into the feeder ball 6.
At this time, by driving the conveyor 5 at a high speed with respect to the conveyor 4, the tubular yarn at the front end portion of the pile of the tubular yarn unloaded on the conveyor 4 is gradually cut and dropped into the feeder ball 6. .

【0016】そして、レベルセンサ26がフィーダーボ
ール6内に貯溜された管糸の量が、所定のレベルに達し
たことを検知すると、該レベルセンサ26からの信号に
よりコンベア4及びコンベア5の間欠駆動を停止して、
フィーダーボール6内への管糸の送給を停止する。この
際、コンベア5上に管糸が存在していないことがセンサ
25により検知されれば、コンベア4及びコンベア5を
直ちに停止せずに、上記センサ25がコンベア5上の管
糸を検出した後に停止する。これは、フィーダーボール
6内への管糸供給の即応性を高めるためである。
When the level sensor 26 detects that the amount of the yarn thread stored in the feeder ball 6 has reached a predetermined level, the signal from the level sensor 26 intermittently drives the conveyor 4 and the conveyor 5. Stop
The feeding of the tubing into the feeder ball 6 is stopped. At this time, if the sensor 25 detects that there is no yarn on the conveyor 5, then the sensor 25 detects the yarn on the conveyor 5 without immediately stopping the conveyors 4 and 5. Stop. This is to enhance the responsiveness of the supply of the yarn into the feeder ball 6.

【0017】パーツフィーダ7は、分離コンベア8の始
端部に常に管糸が位置するよう図示しない手段によりそ
の作動を制御されている。そして、搬送路12の供給ス
テーション11に空トレイ13が停止されると、該部か
らのシュート要求に従い、天尻判別部9で天尻判別を終
えて該部に位置していた管糸が整列シュート10内に投
下され、シュートガイド14でガイドされて、上記空ト
レイ13上に挿立され供給される。
The operation of the parts feeder 7 is controlled by means (not shown) so that the yarn is always positioned at the starting end of the separating conveyor 8. Then, when the empty tray 13 is stopped at the supply station 11 of the transport path 12, the top end determination section 9 finishes the top end determination, and the yarns located in that section are aligned in accordance with the chute request from that section. It is dropped into the chute 10, guided by the chute guide 14, and inserted and supplied on the empty tray 13.

【0018】同時に、分離コンベア8が作動して、該コ
ンベア8の始端部に位置している管糸を天尻判別部9に
送給し、該部において天尻判別した後待機させ、次の供
給に備える。
At the same time, the separating conveyer 8 is operated to feed the yarn at the starting end of the conveyer 8 to the top edge determining portion 9, and after the top edge determining portion 9 determines the top edge, the standby state is set. Prepare for supply.

【0019】そして、コンベア4上の管糸が殆どフィー
ダーボール6側に供給され、該部に管糸が無いことをセ
ンサ24が検知すると、荷あけ装置3のチェーン32
が、該チェーン32に設けたドック38が次のリミット
スイッチ22を蹴るまで回動し、可動フレーム31を更
に一定量傾倒して、ワゴン2内の管糸をコンベア4上に
荷あけする。
When most of the yarn on the conveyor 4 is supplied to the feeder ball 6 side and the sensor 24 detects that there is no yarn on the feeder ball 6, the chain 32 of the unloading device 3 is detected.
However, the dock 38 provided on the chain 32 is rotated until the next limit switch 22 is kicked, the movable frame 31 is further tilted by a certain amount, and the yarn in the wagon 2 is unloaded onto the conveyor 4.

【0020】この際、荷あけされる管糸の量は、可動フ
レーム31の傾斜角度とは必ずしも一致せず、少ない場
合もあれば、多量に荷あけされてしまう場合もある。こ
のうち前者の荷あけ量が少ない場合は、センサ24の検
出信号に応じてワゴン2を更に傾倒し、管糸を荷あけす
れば良いが、後者の多量に荷あけされてしまった場合に
は、コンベア4上に山積みになる。
At this time, the amount of the unwound tubing does not necessarily match the inclination angle of the movable frame 31, and there are cases where it is small and unloaded. If the former is less loaded, the wagon 2 may be further tilted in accordance with the detection signal of the sensor 24 to load the yarn, but if the latter is loaded too much, , Piled up on the conveyor 4.

【0021】そして、コンベア4、及びコンベア5の管
糸が漸次フィーダーボール6内に送給され、上記管糸山
積み部分が、図1中2点鎖線で示される如く、コンベア
4の終端部42に達し、該管糸をセンサ27が検知する
とコンベア4及びコンベア5の1回の間欠駆動における
駆動時間が短時間運転側に切換わる。
Then, the yarns of the conveyors 4 and 5 are gradually fed into the feeder ball 6, and the piled portion of the yarns is fed to the end portion 42 of the conveyor 4 as shown by the chain double-dashed line in FIG. When the yarn reaches the sensor and the sensor 27 detects the yarn, the driving time in one intermittent drive of the conveyor 4 and the conveyor 5 is switched to the short-time operation side.

【0022】それに伴い、コンベア4の終端部42に達
した管糸の山積み部分は、コンベア4により低速で供給
される間にコンベア5により少しずつ切り崩されフィー
ダーボール6内に送給されるので、上記山積み部分の管
糸がフィーダーボール6内に一度に多量になだれ落ちる
といった事態は起こらない。そして、上記山積み部分の
管糸が切り崩され、センサ27が管糸を検出しなくなる
と、コンベア4及びコンベア5の間欠駆動は再び長時間
運転側に切換わり、通常の送給状態となる。
Accordingly, the piled portion of the yarn reaching the end portion 42 of the conveyor 4 is gradually cut by the conveyor 5 and fed into the feeder ball 6 while being fed at a low speed by the conveyor 4. The situation in which the pile yarns of the piled portion drool into the feeder ball 6 in large quantities at once does not occur. When the yarns in the piled portion are broken and the sensor 27 no longer detects the yarns, the intermittent drive of the conveyors 4 and 5 is switched to the long-time operation side again, and the normal feeding state is set.

【0023】尚、上述の実施例においては、センサ27
の検出信号に基づいて、コンベア4及びコンベア5の1
回の間欠駆動における駆動時間を短時間運転に切換える
一例を示したが、上記コンベア4及びコンベア5の駆動
源となるモータの回転数をインバータで制御する等の手
段により、該コンベア4及びコンベア5の駆動を低速運
転に切換えて、管糸の山積み部分が徐々に切り崩される
ようにすることも可能である。
In the above embodiment, the sensor 27
1 of the conveyor 4 and the conveyor 5 based on the detection signal of
An example in which the driving time in the intermittent driving of one time is switched to the short-time driving is shown, but the conveyor 4 and the conveyor 5 are controlled by means such as controlling the number of rotations of the motor serving as the drive source of the conveyor 4 and the conveyor 5 with an inverter. It is also possible to switch the driving of No. 1 to low speed operation so that the piled portion of the tube yarn is gradually cut.

【0024】また、コンベア4とコンベア5との駆動を
独立して行ない、コンベア5に対するコンベア4の速度
比を更に落とすか、若しくはコンベア4を停止して管糸
の山積み部分の切り崩しを行っても良い。
Further, even if the conveyor 4 and the conveyor 5 are independently driven to further reduce the speed ratio of the conveyor 4 to the conveyor 5, or the conveyor 4 is stopped and the piled portion of the yarn is cut down. good.

【0025】[0025]

【発明の効果】本発明の管糸供給装置は、上述のとお
り、同時に多量に供給された管糸をフィーダボールへ送
給するコンベアに、該コンベア上の所定の高さ位置に存
在する管糸の検知手段を設けので、コンベア上に管糸の
山積部分が存在しても、一時に多量の管糸がパーツフィ
ーダになだれ落ちることがなく、該パーツフィーダーが
供給不能となる事態を防止することが可能である。
As described above, the tubing yarn feeder of the present invention is provided on a conveyor for feeding a large amount of tubing yarn simultaneously supplied to a feeder ball, and a tubing yarn existing at a predetermined height position on the conveyor. Even if a pile of piles of yarn exists on the conveyor, a large amount of yarn does not drop into the parts feeder at one time, preventing the situation where the parts feeder cannot be supplied. Is possible.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の実施例の管糸供給装置を示す側面図で
ある。
FIG. 1 is a side view showing a yarn feeder according to an embodiment of the present invention.

【符号の説明】[Explanation of symbols]

1 管糸供給装置 2 ワゴン 3 荷あけ装置 4,5 コンベア 6 フィーダーボール 7 パーツフィーダ 8 分離コンベア 9 天尻判別部 10 整列シュート 11 供給ステーション 24,25 センサ 26 レベルセンサ 27 センサ(山積管糸検知手段) 1 Pipe Thread Supply Device 2 Wagon 3 Unloading Device 4, 5 Conveyor 6 Feeder Ball 7 Parts Feeder 8 Separation Conveyor 9 Amajiri Discrimination Section 10 Alignment Chute 11 Supply Station 24, 25 Sensor 26 Level Sensor 27 Sensor (Mounted Pipe Thread Detection Means )

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 同時に多量に供給された管糸をフィーダ
ボールへ送給するコンベアに、該コンベア上の所定の高
さ位置に存在する管糸の検知手段を設けたことを特徴と
する管糸供給装置。
1. A yarn thread detecting device for detecting a yarn thread existing at a predetermined height position on the conveyor, which is provided on a conveyor for feeding a large amount of the yarn thread simultaneously supplied to a feeder ball. Supply device.
JP30478093A 1993-11-10 1993-11-10 Bobbin supplying device Pending JPH07133015A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP30478093A JPH07133015A (en) 1993-11-10 1993-11-10 Bobbin supplying device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP30478093A JPH07133015A (en) 1993-11-10 1993-11-10 Bobbin supplying device

Publications (1)

Publication Number Publication Date
JPH07133015A true JPH07133015A (en) 1995-05-23

Family

ID=17937144

Family Applications (1)

Application Number Title Priority Date Filing Date
JP30478093A Pending JPH07133015A (en) 1993-11-10 1993-11-10 Bobbin supplying device

Country Status (1)

Country Link
JP (1) JPH07133015A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102837993A (en) * 2011-06-24 2012-12-26 村田机械株式会社 Yarn supply tube supplying device and control method of the same
CN111285188A (en) * 2020-03-27 2020-06-16 青岛宏大纺织机械有限责任公司 Vibration flat plate bobbin yarn conveying device and method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102837993A (en) * 2011-06-24 2012-12-26 村田机械株式会社 Yarn supply tube supplying device and control method of the same
CN111285188A (en) * 2020-03-27 2020-06-16 青岛宏大纺织机械有限责任公司 Vibration flat plate bobbin yarn conveying device and method

Similar Documents

Publication Publication Date Title
US4763773A (en) Doffed package transporting apparatus
JP3834509B2 (en) Conveyor with variable speed control
EP2495191B1 (en) Bobbin delivering device and automatic winder
US4566263A (en) Device for storage of empty bobbins for a spinning frame
US4591084A (en) Method and apparatus for feeding and accumulating ribbon material
JPH07133015A (en) Bobbin supplying device
JPH08337317A (en) Bobbin supplying device
JP2784296B2 (en) Paper transport control device
JPH0449045Y2 (en)
JPH0616226A (en) Bobbin supply device
JP3435550B2 (en) Container feeding device for filling machine
JPH11199040A (en) Container conveying device
JPH01127569A (en) Method and device for conveying waywinding package
JPH04214428A (en) Device for supplying and discharging bobbin
JPH09110136A (en) Blank feeder
JP2002179244A (en) Aligning device
JP3186374B2 (en) Tray transport system
JPH03111347A (en) Automatic charger of magazine
JPH0735454U (en) Winding tube supply device
JP2006312541A (en) Fixed volume supply device
JPS58139979A (en) Conveying method and device for cone cheese
JPS61188371A (en) Bobbin extracting and supplying device
JPH06245688A (en) Aligning and transferring apparatus for fish body
JP2916343B2 (en) Sheet dispenser
CN117485659A (en) Intelligent production and transportation line for mining products