JPH0680344U - Automatic controller for maximum power demand - Google Patents
Automatic controller for maximum power demandInfo
- Publication number
- JPH0680344U JPH0680344U JP2947993U JP2947993U JPH0680344U JP H0680344 U JPH0680344 U JP H0680344U JP 2947993 U JP2947993 U JP 2947993U JP 2947993 U JP2947993 U JP 2947993U JP H0680344 U JPH0680344 U JP H0680344U
- Authority
- JP
- Japan
- Prior art keywords
- motor
- power
- soft
- control device
- operating
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Supply And Distribution Of Alternating Current (AREA)
- Motor And Converter Starters (AREA)
- Protection Of Static Devices (AREA)
Abstract
(57)【要約】 (修正有)
【目的】無駄な電力を消費するモーターを,ソフトスタ
ートで間欠運転し,エネルギーの節減をはかる。
【構成】工場の不稼働で運転しているモーターMを間欠
運転により使用電力を下げ,最需要期には,デマンドコ
ントロールにより電力を管理し契約電力を越えそうな時
は,ワイヤレス方式により負荷をコントロールし,かつ
ソフトスタート制御装置Sにより,立ちあげ時の消費電
力の削減とモーターや機器の損傷を保護する。
【効果】ハイテクテクノロジー化された電子機器と,新
開発したソフトスタート制御装置の粗合せにより,より
効果的な省エネと,デマンドコントロールの省力化を計
り,従来不可能であった分野の問題点を解決する。
(57) [Summary] (Corrected) [Purpose] To save energy by intermittently operating a motor that consumes wasted power by soft start. [Structure] The electric power used is reduced by intermittently operating the motor M that is operating when the factory is not operating. In the most demanding period, the demand control manages the electric power, and when the contracted electric power is likely to be exceeded, the load is wirelessly applied. The control and soft start control device S reduce the power consumption at startup and protect the motor and equipment from damage. [Effect] Highly-tech electronic equipment and newly-developed soft-start control device are roughly matched to achieve more effective energy saving and demand control labor saving. Solve.
Description
現在の電力事情は夏場の最大需要期に,供給能力が不足するため, 電力会社は,需要家の自家用変電所に取引メーターを設置し,30 分単位で最大需要電力を測定し記録している。500KW契約以下 の需要家の場合は,この30分内で契約電力を超過すると,当月よ りその超過した電力量が基本契約料金となり,以後最大需要電力が 幾ら下まわっても,以後の11月間は,この料金となる。500K W以上の需要家の場合は,30分間で4%以上契約電力を超過した 場合,超過電力に基本料金を乗じた金額に,更に1,5倍した金額 を支払うことになる。また重ねて契約を超過すると契約電力の変更 となる場合もある。 このため各需要家は,需要電力をデマンドコントローラー(最大電 力量監視計)等で常に管理し超過しそうな時は,負荷を一時停止さ せて契約電力量を越えないようにする対策が必要となる。 Since the current power situation is such that the supply capacity is insufficient during the maximum demand period in the summer, the power company installs a transaction meter at the customer's private substation and measures and records the maximum power demand in 30-minute units. . In the case of a customer with a contract of 500 KW or less, if the contracted power is exceeded within this 30 minutes, the excess amount of power will be the basic contracted charge from the current month, and even if the maximum power demand falls below that month, it will continue for the next 11 months. Is this charge. In the case of a customer of 500 kW or more, if the contracted power exceeds 4% for 30 minutes, the amount of excess power multiplied by the basic charge will be paid 1,5 times as much. In addition, if the number of contracts is exceeded, the contracted power may be changed. Therefore, it is necessary for each customer to constantly manage the demand power with a demand controller (maximum power monitor) and take measures to suspend the load so as not to exceed the contract power when it is likely to exceed. Become.
変電所の受電側の取引用計器より,パルス検出器によりデマンドコ ントローラーに伝達する。デマンドコントローラーは,30分計測 を行い,目標電力を超過しそうな時は,事前に第1警報を発報する 。そこで電力管理者により止められる負荷を停止させる。警報は第 2,第3と続き30分を無事に通過し電力に余裕が出れば,停止し た負荷を再起動させ以下繰返す。 The transaction instrument on the power receiving side of the substation transmits it to the demand controller with a pulse detector. The demand controller measures for 30 minutes and issues the first alarm in advance when the target power is likely to be exceeded. Therefore, the load stopped by the power manager is stopped. The alarm continues for 30 minutes after the 2nd and 3rd, and if there is enough power, the stopped load is restarted and the following procedure is repeated.
(1)頻繁に負荷をON−OFFさせるため,起動時のショックロ ードにより,モーターや駆動機器の損傷が起きる。 (2)再起動時,立ちあげ電力を消費するため需要電力が短時間で あるが増える。 (3)管理室より負荷のある現場に,ON−OFF命令を行う場合 ,当該回路を配線する必要があり,大変経費がかかることと ,大工場の場合は物理的に不可能な場合が多いい。 (4)負荷の停止,再起動は,電力管理者要員の手作業となり警報 発報から短時間で行うため手遅れになる場合もある。 (1) Since the load is turned on and off frequently, the shock load at startup causes damage to the motor and drive equipment. (2) When restarting, power consumption is increased because the startup power is consumed. (3) When an ON-OFF command is issued from the control room to a site with a load, it is necessary to wire the circuit concerned, which is very expensive, and in the case of a large factory, it is often physically impossible. Good. (4) Stopping and restarting the load must be done manually by the electric power manager, and it can be too late because the alarm is issued in a short time.
(1)通常のインダクションモーターは,立ちあげ時の最大起動電 流は,定格電流の8倍とされている。このため頻繁にモータ ーをON−OFFすると,モーターは,立ちあげ累積熱によ り焼損する。間欠的にしか稼働しないモーターを連続運転に しておくのはこのためである。稼働していないモーターであ ってもモーターは,その規定回転数を維持するため電力を消 費する。このようなモーターは不稼働時には停止させ,稼働 時には,ソフトスタートにより稼働時間のみ運転する。 ソフトスタート機能による電流制限で,定格電流の2倍以下 に押えるため,モーター温度は,連続運転時よりも低くなる 。この結果,工場全体の使用電力量が低下し,最大需要電力 量も低くなる。 (2)夏季の最大需要電力量を,更に下げることにより,より大き な効果を上げる事が出来る。従来の停止命令をプログラム入 力出来るデマンドコントローラー(市販品)を利用し,停止 出力信号,再起動出力信号をワイヤレス方式により負荷に伝 達する。その方法は,デマンドコントローラーの出力をプロ グラムシーケンサーに入力する。シケンサーにコードー番号 をプログラムする。シーケンサー出力をトランシーバー固定 局に入力する(親局)。負荷側にトランシーバ固定局を設け る(子局)。コード番号で指定された負荷側固定局は負荷を 停止させ報告をアンサーする。 例,負荷01番停止せよ 第1警報がデマンドコントローラーより出力→シーケンサー 010信号→親局送信→子局受信→負荷停止→子局返事送信 →親局返事受信 (3)停止した負荷を再起動する時,ソフトスタートを行うため, モーターや機器の損傷を保護し,立ちあげ消費電力を節減す る。 (1) For a normal induction motor, the maximum starting current at startup is set to 8 times the rated current. For this reason, if the motor is frequently turned on and off, the motor will start up and burn out due to accumulated heat. This is why motors that operate only intermittently are kept in continuous operation. Even if the motor is not running, the motor consumes power to maintain the specified speed. Such a motor is stopped when it is not operating, and when it is operating, it is operated only during the operating time by soft start. The soft start function limits the current to less than twice the rated current, so the motor temperature becomes lower than during continuous operation. As a result, the power consumption of the entire factory is reduced and the maximum power demand is also reduced. (2) By further reducing the maximum power demand in summer, a greater effect can be achieved. Using a conventional demand controller (commercially available product) that can program a stop command, the stop output signal and restart output signal are transmitted to the load wirelessly. In that method, the output of the demand controller is input to the program sequencer. Program the code number in the sequencer. Input the sequencer output to the transceiver fixed station (master station). A transceiver fixed station is installed on the load side (slave station). The fixed station on the load side specified by the code number stops the load and answers the report. Example: Stop load 01 The first alarm is output from the demand controller → Sequencer 010 signal → Master station transmission → Slave station reception → Load stop → Slave station reply transmission → Master station reply reception (3) Restart the stopped load At this time, a soft start is performed to protect the motor and equipment from damage, and to start up and save power consumption.
【実施例】 考案の効果 (1)450トン成型機において,メインの油圧ポンプモーターと サブの油圧ポンプモーターで運転されていた。メインモータ ーは,比較的忙しく稼働しているが,サブモーター(200 V,3相,22KW)は,1サイクル120秒に対して,稼 働時間は4,5秒であった。そこで機械の制御盤より信号を 取出し,ソフトスタート装置を設置し,稼働時間のみモータ ーを運転した。この結果,改善前の消費電力が5,5KWh ,改善後が1,1KWhとなり,4,4KWhの省エネが行 え,省エネ率80%となった。 (2)契約電力430KWの需要家の最大需要電力が,夏季のピー ク時に480KWとなった。そこで当考案の最大需要電力の 制御装置を設置し,3台の空調設備を制御した。結果は最大 需要電力がピーク時で430KWに戻すことに成功した。Example Effects of the Invention (1) A 450-ton molding machine was operated by a main hydraulic pump motor and a sub hydraulic pump motor. The main motor was operating relatively busy, but the sub motor (200 V, 3 phase, 22 kW) had an operating time of 4,5 seconds for 120 seconds per cycle. Therefore, we extracted the signal from the control panel of the machine, installed a soft start device, and operated the motor only during operating hours. As a result, the power consumption before improvement was 5,5 KWh and after improvement was 1,1 KWh, and energy saving of 4,4 KWh was achieved, resulting in an energy saving rate of 80%. (2) The maximum power demand of consumers with a contract power of 430 kW was 480 kW at the peak of summer. Therefore, we installed a controller for the maximum power demand of the present invention to control three air conditioning equipment. The result was that the maximum power demand was returned to 430 kW at the peak.
【図1】 システム全体の構成図変電所,電力管理部,
不稼働時間の長いモーターのソフトスタート,親局,子
局の構成図である。以下各ブロックごとに説明する。[Figure 1] Overall system configuration diagram Substation, power management unit,
It is a soft-start of a motor with a long down time, a master station, and a block diagram of a slave station. Each block will be described below.
【図2】 ソフトスタート制御の構成図時間設定器によ
りサイリスター制御装置を制御する。スタート信号によ
り,時間設定器出力は,0Vから+10Vまで上昇す
る。上昇速度を時間設定器で設定する。サイリスター制
御装置は,入力電圧が0〜+10V変化に対してAC2
00Vの電源電圧を0〜200Vに制御する。200V
に達すると,電磁開閉器がONとなり,サイリスターを
バイパスしサイリスターに流れる電流を零とする。した
がって容量の小さいサイリスターが使用出来る。FIG. 2 is a block diagram of soft start control. The thyristor control device is controlled by a time setting device. The start signal causes the time setter output to rise from 0V to + 10V. Set the rising speed with the time potentiometer. The thyristor control device has AC2 for input voltage change of 0 to + 10V.
The power supply voltage of 00V is controlled to 0 to 200V. 200V
Then, the electromagnetic switch is turned on, bypassing the thyristor and making the current flowing through the thyristor zero. Therefore, a thyristor with a small capacity can be used.
【図3】 デマンドコントローラーのシステム構成図電
力会社で設置した取引用計器の信号をパルス検出器によ
りデマンドコントローラーに伝達する。デマンドコント
ローラーは,目標電力,現在電力,負荷停止−負荷再起
動プログラムがあらかじめ設定されている。[Fig. 3] System configuration diagram of demand controller The signal of the transaction instrument installed at the electric power company is transmitted to the demand controller by the pulse detector. The demand controller has preset target power, current power, load stop-load restart program.
【図4】 親局負荷停止−再起動システムの構成図デマ
ンドコントローラーからの,停止や再起動信号をプログ
ラムシーケンサーで受ける。シーケンサーには,子局の
識別番号をプログラムしておく。デマンドコントローラ
ーより,ON信号の停止命令を受けると,該当子局識別
番号を親局無線送受信装置におくる。送受信装置は,子
局に該当識別番号を送信し,子局からの返事確認信号を
受信する。これにより複数の子局を自由に制御すること
が出来る。再起動の場合もデマンドコントローラーのO
FF信号で同じ工程となるため説明を省略する。[Figure 4] Master station load stop-restart system configuration diagram The program sequencer receives stop and restart signals from the demand controller. The identification number of the slave station is programmed in the sequencer. When the ON signal stop command is received from the demand controller, the corresponding slave station identification number is sent to the master station wireless transceiver. The transmitter / receiver transmits the corresponding identification number to the slave station and receives the reply confirmation signal from the slave station. This allows a plurality of slave stations to be controlled freely. Demand controller O also when restarting
Since the same process is performed for the FF signal, the description is omitted.
【図5】 子局負荷停止一再起動システムの構成図親局
より送信されてきた信号を信号解析器で解析し,自番号
であった場合は,対象負荷を停止させ,返事確認信号を
親局に送信する。再起動の場合も同じ工程となるため説
明を省略する。[Fig. 5] Configuration diagram of slave station load stop / restart system The signal transmitted from the master station is analyzed by a signal analyzer, and if it is its own number, the target load is stopped and a reply confirmation signal is sent to the master station. Send to. The description of the same process will be omitted for restarting.
Claims (3)
べ,休止時間の長いモーターは,一時停止させ稼働時に
は電流制限によりモーターをソフトスタートさせて,起
動電流によるモーターの発熱を保護し,ソフトスタート
完了後,全電圧に達すると内部の電圧制御用サイリスタ
ーを電磁開閉器でバイパスしサイリスターを保護する制
御装置1. The load state of the induction motor is checked, and the motor with a long down time is temporarily stopped, and when operating, the motor is soft-started by current limiting to protect the heat generation of the motor due to the starting current, and after the soft-start is completed, A control device that protects the thyristor by bypassing the internal voltage control thyristor with an electromagnetic switch when the full voltage is reached.
ーラーにより管理し,モーターを,ON−OFFさせる
ことにより,モーターや機器の損傷を保護を目的とし
た,ソフトスタート制御装置2. A soft start control device for the purpose of protecting damage to a motor and equipment by controlling the maximum demand power in summer and the like by a demand controller and turning the motor on and off.
現場に,停止又は起動命令を,ワイヤレス方式により全
自動で行う制御装置3. A control device for automatically issuing a stop or start command from a management center to a site where a motor is installed by a wireless system.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2947993U JPH0680344U (en) | 1993-04-26 | 1993-04-26 | Automatic controller for maximum power demand |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2947993U JPH0680344U (en) | 1993-04-26 | 1993-04-26 | Automatic controller for maximum power demand |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH0680344U true JPH0680344U (en) | 1994-11-08 |
Family
ID=12277228
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2947993U Pending JPH0680344U (en) | 1993-04-26 | 1993-04-26 | Automatic controller for maximum power demand |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH0680344U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2012115937A (en) * | 2010-11-30 | 2012-06-21 | Denso Corp | Automated equipment |
-
1993
- 1993-04-26 JP JP2947993U patent/JPH0680344U/en active Pending
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2012115937A (en) * | 2010-11-30 | 2012-06-21 | Denso Corp | Automated equipment |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP4547776B2 (en) | Demand control system for electric equipment, demand control method, demand control management apparatus, and demand control management method | |
CN104040829B (en) | The load that solar energy for photovoltaic system synchronizes | |
CN107255347B (en) | A kind of cooler compressor operation power detecting method and air conditioner | |
CN101553696B (en) | Air conditioner and control method thereof | |
JP2001008385A (en) | Power storing system | |
CN108168043B (en) | Variable flow active energy-saving automatic control system of central air-conditioning water system | |
CN105190193A (en) | Air conditioning control device, air conditioning control system, and air conditioning control method | |
CN105135606A (en) | Method and device for controlling air conditioner | |
JP2959349B2 (en) | Demand control system for air conditioner | |
JP4127449B2 (en) | Air conditioner | |
JPH0680344U (en) | Automatic controller for maximum power demand | |
JPH1089744A (en) | Number of operating set control method of air conditioner and device for the same | |
JPS63302237A (en) | Demand control device of air conditioner | |
CN116907077A (en) | Flexible regulation and control system and method for VRV air conditioner load | |
CN109405186B (en) | Setting method of initial operating frequency, variable frequency controller and variable frequency air conditioner | |
CN115663841A (en) | Multi-scene intelligent frequency converter based on dual optimization control and use method thereof | |
JP2020167758A (en) | Storage battery control system | |
JP2007028873A (en) | Demand control system | |
JPH0544980A (en) | Controlling method for air conditioner | |
CN108614215B (en) | Generator performance testing device | |
CN111089412A (en) | Control method and control system of power-controllable air conditioner | |
JPH1172252A (en) | Electric power storage type air conditioner | |
CN112421643A (en) | Flexible load measurement and control method | |
JP2001338036A (en) | Negotiation type energy management method and system | |
CN111005889A (en) | Intelligent pump station main motor pit ventilation adjusting system and ventilation adjusting method |