JPH067162Y2 - Steel pile guide formwork equipment for underwater foundation construction - Google Patents

Steel pile guide formwork equipment for underwater foundation construction

Info

Publication number
JPH067162Y2
JPH067162Y2 JP5157188U JP5157188U JPH067162Y2 JP H067162 Y2 JPH067162 Y2 JP H067162Y2 JP 5157188 U JP5157188 U JP 5157188U JP 5157188 U JP5157188 U JP 5157188U JP H067162 Y2 JPH067162 Y2 JP H067162Y2
Authority
JP
Japan
Prior art keywords
steel
frame
guide
steel pile
underwater concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP5157188U
Other languages
Japanese (ja)
Other versions
JPH01154254U (en
Inventor
登志夫 秦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kumagai Gumi Co Ltd
Original Assignee
Kumagai Gumi Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kumagai Gumi Co Ltd filed Critical Kumagai Gumi Co Ltd
Priority to JP5157188U priority Critical patent/JPH067162Y2/en
Publication of JPH01154254U publication Critical patent/JPH01154254U/ja
Application granted granted Critical
Publication of JPH067162Y2 publication Critical patent/JPH067162Y2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
  • Underground Or Underwater Handling Of Building Materials (AREA)

Description

【考案の詳細な説明】 〔産業上の利用分野〕 この考案は、橋梁の水中基礎を鋼製脚設置方式で施工す
る場合に使用する鋼杭ガイド型枠装置に関するものであ
る。
[Detailed Description of the Invention] [Industrial field of application] The present invention relates to a steel pile guide formwork device used when constructing an underwater foundation of a bridge by a steel leg installation method.

〔従来の技術〕[Conventional technology]

従来、橋梁の水中基礎を鋼製脚設置方式で施工する場合
は、まず第11図ないし第13図に示すように、平行に
配置された多数の鋼製枠杆8と、隣り合う枠杆8を連結
する多数の鋼製連結枠杆9と、前記枠杆8および連結枠
杆9に固着された鋼杭打込ガイド用鋼製ガイド部材10
とからなる鋼製導枠11を製作し、かつその鋼製導枠1
1の周囲に鋼製外側型枠12を固着して、型枠付き導枠
13を製作する。
Conventionally, when constructing an underwater foundation of a bridge by a steel leg installation method, first, as shown in FIGS. 11 to 13, a large number of steel frame rods 8 arranged in parallel and adjacent frame rods 8 are used. A large number of steel connecting frame rods 9 for connecting the two, and the frame rod 8 and the steel guide members 10 for steel pile driving guides fixed to the connecting frame rods 9.
And a steel guide frame 1 made of
A steel outer mold 12 is fixed to the periphery of 1 to manufacture a conductive frame 13 with a mold.

次に第14図に示すように、水底地盤14の掘下凹所に
敷設した敷砂15の上に前記型枠付き導枠13を載置
し、次いで第15図に示すように、その型枠付き導枠1
3における鋼杭打込ガイド用鋼製ガイド部材10をガイ
ドとして多数の鋼管杭からなる鋼杭16と型枠付き導枠
13の周辺に位置する4〜6本のガイド杭17とを水底
地盤14に打設する。
Next, as shown in FIG. 14, the guide frame 13 with the formwork is placed on the sand 15 laid in the digging recess of the subseabed 14, and then the mold is placed as shown in FIG. Guide frame with frame 1
Using the steel guide member 10 for steel pile driving guide in 3 as a guide, a steel pile 16 composed of a large number of steel pipe piles and 4 to 6 guide piles 17 located around the guide frame 13 with the formwork are provided on the subseabed 14. Set in.

次に前記鋼製外側型枠12と鋼杭16およびガイド杭1
7との間に水中コンクリートを打設した直後に、潜水夫
が水中コンクリートの表面を平滑になるように整形し、
続いて第16図に示すように、橋脚本体のフーチングと
柱と梁とが一体になっている鋼製橋脚フレーム18を、
ガイド杭17によりガイドしながら吊り降ろし、その橋
脚フレーム18を各ガイド杭に固定したブラケットに載
置する。
Next, the steel outer formwork 12, the steel pile 16 and the guide pile 1
Immediately after placing the underwater concrete between the and 7, the diver shaped the surface of the underwater concrete to be smooth,
Subsequently, as shown in FIG. 16, a steel pier frame 18 in which the footing of the pier main body and the pillars and beams are integrated,
It is hung down while being guided by the guide piles 17, and the pier frame 18 thereof is placed on the brackets fixed to the respective guide piles.

次に第17図に示すように、前記橋脚フレーム18にお
ける鋼製フーチングと各鋼杭16および上部を切断した
ガイド杭17との間に水中コンクリートを打設して、鋼
製フーチングと各鋼杭16と各ガイド杭17とを一体化
する。
Next, as shown in FIG. 17, underwater concrete is placed between the steel footings in the pier frame 18 and the steel piles 16 and the guide piles 17 with the upper part cut off to make the steel footings and the steel piles. 16 and each guide pile 17 are integrated.

〔考案が解決しようとする課題〕[Problems to be solved by the device]

前記鋼製導枠11は架設構造物であるので、経済性を優
先させるために小断面の導枠構成部材が用いられ、その
ため鋼杭打設時に鋼製導枠が大きく変形することがあ
る。
Since the steel guide frame 11 is a erected structure, a guide frame constituent member having a small cross section is used in order to give priority to economic efficiency, and therefore the steel guide frame may be largely deformed during steel pile driving.

鋼性導枠11が変形した場合は、水中コンクリート打設
前に型枠付き導枠13を水中から引上げて整形する必要
があるので、煩雑な工程を必要とする。
When the steel guiding frame 11 is deformed, it is necessary to pull up the guiding frame 13 with formwork from the water to shape it before pouring the underwater concrete, which requires a complicated process.

また水中コンクリートを打設した直後に、潜水夫が水中
コンクリートの表面を平滑になるように整形するが、水
中コンクリートの表面積が著しく広く、かつ水中コンク
リートの上方に鋼杭16およびガイド杭17が林立して
おり、しかも適当な作業足場もなく、鋼杭16の側面に
表示したコンクリート均し天端指示マークが見にくい等
の悪条件が重なるので、コンクリート表面整形作業が困
難であると共に、高精度の仕上がり表面が得られない。
Immediately after placing the underwater concrete, the diver shapes the surface of the underwater concrete to be smooth, but the surface area of the underwater concrete is remarkably large, and the steel pile 16 and the guide pile 17 are forested above the underwater concrete. In addition, since there is no suitable work scaffold and bad conditions such as the concrete leveling top end indication mark displayed on the side surface of the steel pile 16 are difficult to see, the concrete surface shaping work is difficult and highly precise. The finished surface cannot be obtained.

前記鋼製外側型枠12内に打設された水中コンクリート
すなわち先行打設水中コンクリートの表面精度が悪い
と、その水中コンクリートの表面と鋼製フーチングの下
面との間に間隙が生じ、鋼製フーチング内に打設した水
中コンクリートすなわち後行打設水中コンクリートがそ
の間隙から漏洩するので、鋼製脚フレームの下面に、ゴ
ム製シール材,布製シール材または鋼製綱等のシール材
を取付けて対処している。しかし、先行打設水中コンク
リートの表面仕上精度が悪くてその表面に大きな凹凸が
あると、シール効果が不完全になって鋼製フーチングの
下面と先行打設水中コンクリートの表面の凹部との間か
ら後行打設水中コンクリートが漏洩する。したがって、
先行打設水中コンクリートの表面仕上げ精度を向上させ
ることが大きな課題になっている。
If the surface accuracy of the underwater concrete cast in the steel outer formwork 12, that is, the previously cast underwater concrete is poor, a gap is created between the surface of the underwater concrete and the lower surface of the steel footing, and the steel footing is formed. Since the underwater concrete placed inside, that is, the submerged concrete that is placed behind leaks from the gap, a sealing material such as rubber sealing material, cloth sealing material or steel rope is attached to the bottom surface of the steel leg frame. is doing. However, if the surface finish accuracy of the pre-cast underwater concrete is poor and there are large irregularities on the surface, the sealing effect will be incomplete, and the space between the lower surface of the steel footing and the recessed portion of the surface of the pre-cast underwater concrete will become insufficient. Subsequent casting underwater concrete leaks. Therefore,
Improving the surface finish accuracy of pre-cast underwater concrete has become a major issue.

また鋼製フーチング内の後行打設水中コンクリートの自
重は、先行打設水中コンクリートに作用し、そのため鋼
製橋脚フレームを設置する場所の地盤が軟弱な場合は、
後行打設水中コンクリートの重量およびこれに作用する
荷重を、軟弱地盤が支えることはできないので、先行打
設水中コンクリートが支えることになり、そのため先行
打設水中コンクリートに埋込まれた前記鋼製導体11の
剛性が小さいと、先行打設水中コンクリートが沈下した
り破壊することがあるので、地盤改良等の処置が必要な
場合もある。
In addition, the weight of trailing cast underwater concrete in the steel footing acts on the preceding cast underwater concrete, so if the ground where the steel pier frame is installed is weak,
Since the soft ground cannot support the weight of trailing cast underwater concrete and the load acting on it, the preceding cast underwater concrete will support it. If the rigidity of the conductor 11 is low, the underwater concrete cast in advance may sink or be destroyed, so that measures such as ground improvement may be necessary.

この考案は、鋼杭打込時の鋼杭ガイド型枠装置の変形を
防止することができ、かつ外側型枠内に打設された水中
コンクリートの表面を容易に高精度で平面状に仕上げる
ことができる水中基礎施工用鋼杭ガイド型枠装置を提供
することを目的とするものである。
This invention can prevent the deformation of the steel pile guide formwork device when driving the steel pile, and can easily and accurately finish the surface of the underwater concrete cast in the outer formwork into a flat surface. It is an object of the present invention to provide a steel pile guide formwork device for underwater foundation construction capable of performing the above.

〔課題を解決するための手段〕[Means for Solving the Problems]

前記目的を達成するために、この考案の水中基礎施工用
鋼杭ガイド型枠装置においては、多数の鋼製枠材1,2
が格子状に配置されると共に溶接により固着されて、格
子状骨組フレーム3が構成され、その格子状骨組フレー
ム3における各鋼杭挿入空間4内の各辺の中央部に配置
された鋼杭打込ガイド用鋼製ガイド部材5は前記枠材
1,2に固定され、前記格子状骨組フレーム3の周囲に
鋼製外側型枠6の下部が固定され、前記各枠材1,2の
上部に枠材長手方向に延長する鋼製作業足場兼均し定規
部材7が固定されている。
In order to achieve the above-mentioned object, in the steel pile guide formwork device for underwater foundation construction of the present invention, a large number of steel frame members 1 and 2 are used.
Are arranged in a lattice shape and fixed by welding to form a lattice-shaped frame frame 3, and the steel pile driving is arranged in the lattice-shaped frame frame 3 at the center of each side in each steel pile insertion space 4. The steel guide member 5 for the embedded guide is fixed to the frame members 1 and 2, the lower part of the steel outer formwork 6 is fixed around the lattice-shaped frame 3, and the upper part of each of the frame members 1 and 2 is fixed. A steel work scaffolding and leveling ruler member 7 extending in the longitudinal direction of the frame material is fixed.

〔作用〕[Action]

作業足場兼均し定規部材7の上面を定規として利用し
て、外側型枠6内に打設された水中コンクリート19の
表面の均し仕上げ作業を行ない、かつ作業足場兼均し定
規部材7の上面を水中コンクリート19の打設および水
中コンクリート19の表面仕上げの際の作業足場として
使用する。
Using the upper surface of the work scaffolding and leveling ruler member 7 as a ruler, the surface of the underwater concrete 19 cast in the outer formwork 6 is leveled and finished, and the work scaffolding and leveling ruler member 7 The upper surface is used as a work scaffold when placing the underwater concrete 19 and finishing the surface of the underwater concrete 19.

また格子状骨組フレーム3を構成する各鋼製枠材1,2
が鋼製作業足場兼均し定規部材7により補強されて、格
子状骨組フレーム3が強化される。
Further, each of the steel frame members 1 and 2 constituting the lattice frame 3
Is reinforced by the steel work scaffolding and leveling ruler member 7, and the lattice-shaped frame 3 is strengthened.

〔実施例〕〔Example〕

次にこの考案を図示の例によって詳細に説明する。 Next, the present invention will be described in detail with reference to the illustrated example.

第1図ないし第4図はこの考案の一実施例に係る鋼杭ガ
イド型枠装置20を示し、第5図は鋼杭打込ガイド用鋼
製ガイド部材5付きの格子状骨組フレーム3を示すもの
であって、前後方向に延長する多数の箱形断面の鋼製枠
材1と左右方向に延長する多数の箱形断面の鋼製枠材2
とが、格子状に配置されると共に溶接により固着され
て、多数の正方形の鋼杭挿入空間4を有する格子状骨組
フレーム3が構成され、各鋼杭挿入空間4における各辺
の中央に鋼杭打込ガイド用鋼製ガイド部材5が配置さ
れ、そのガイド部材5の基端部は鋼製枠材1,2に対し
溶接により固着されている。
1 to 4 show a steel pile guide formwork device 20 according to an embodiment of the present invention, and FIG. 5 shows a lattice-shaped frame 3 with a steel guide member 5 for a steel pile driving guide. A large number of box-shaped cross-section steel frame members 1 extending in the front-rear direction and a large number of box-section cross-section steel frame members 2 extending in the left-right direction
And are arranged in a lattice shape and fixed by welding to form a lattice-shaped frame frame 3 having a large number of square steel pile insertion spaces 4, and a steel pile is provided at the center of each side in each steel pile insertion space 4. A steel guide member 5 for a driving guide is arranged, and the base end portion of the guide member 5 is fixed to the steel frame members 1 and 2 by welding.

前記各鋼製枠材1,2の上部に、前後方向および左右方
向に延長するT形断面の鋼製作業足場兼均し定規部材7
が載置されて溶接により固着され、かつ前記格子状骨組
フレーム3の外周に鋼板製外側型枠6の下部が溶接によ
り固着され、さらに外側型枠6と周囲の作業足場兼均し
定規部材7との間に、多数の鋼板製連結部材21が外側
型枠周囲方向に間隔をおいて配置され、その連結部材2
1は外側型枠6および作業足場兼均し定規部材7に対し
溶接により固着され、また作業足場兼均し定規部材7の
水平な上面は外側型枠6の水平な上面と同一レベルまた
はほぼ同一レベルに配置されている。
On the upper part of each of the steel frame members 1 and 2, a steel work scaffolding and leveling ruler member 7 having a T-shaped cross section extending in the front-rear direction and the left-right direction.
Is placed and fixed by welding, and the lower part of the steel plate outer mold 6 is fixed by welding to the outer periphery of the lattice-shaped frame 3, and further the outer mold 6 and the surrounding work scaffolding and leveling ruler member 7 And a large number of steel plate connecting members 21 are arranged at intervals in the circumferential direction of the outer mold, and the connecting members 2
1 is fixed to the outer formwork 6 and the work scaffolding / smoothing ruler member 7 by welding, and the horizontal upper surface of the work scaffolding / smoothing ruler member 7 is at the same level as or substantially the same as the horizontal upper surface of the outer formwork 6. It is located on the level.

第6図は鋼杭ガイド型枠装置の変形例を示すものであっ
て、中間部の鋼製枠材1,2としてH形鋼が用いられる
と共に、鋼板からなる外側型枠6を取付ける周辺の枠材
1Aとして溝形鋼が用いられ、かつT形断面の鋼製作業
足場兼均し定規部材7は鋼製枠材1,2から上方に分離
して配置され、その鋼製枠材1,2と前記作業足場兼均
し定規部材7とは、格子状に配置された作業足場兼均し
定規部材7の各交点で、鋼板製連結部材28を介して溶
接により結合されている。
FIG. 6 shows a modified example of the steel pile guide formwork apparatus, in which H-shaped steel is used as the steel frame members 1 and 2 in the middle part, and the outer formwork 6 made of a steel plate is attached to the surrounding area. A channel steel is used as the frame material 1A, and a steel work scaffolding and leveling ruler member 7 having a T-shaped cross section is arranged above the steel frame materials 1 and 2 separately. The work scaffolding and leveling ruler member 7 and the work scaffolding 2 and the leveling ruler member 7 are welded to each other at each intersection of the work scaffolding and leveling ruler members 7 arranged in a lattice pattern.

第6図に示す鋼杭ガイド型枠装置の場合は、作業足場兼
均し定規部材7により区画された各区画部分が相互に連
通しているので、コンクリートの充填性が良くなり、か
つ第1図ないし第4図に示す鋼杭ガイド型枠装置に比べ
て、鋼材使用量が少なくて済むので経済的である。
In the case of the steel pile guide formwork device shown in FIG. 6, since each partition part partitioned by the work scaffolding and leveling ruler member 7 communicates with each other, the filling property of concrete is improved, and Compared with the steel pile guide formwork device shown in Figs. 4 to 4, the amount of steel used is small, which is economical.

第7図はこの考案の実施例の鋼杭ガイド型枠装置20と
組合わせて使用されるシール材付き鋼性橋脚フレーム2
2を示すものであって、下端にフランジを備えている鋼
制枠材23が格子上に配置されると共に相互に溶接によ
り固着されて、格子状骨組フレーム24が構成され、か
つその格子状骨組フレーム24の外側に鋼製フーチング
型枠25が溶接により固着され、前記格子状骨組フレー
ム24を構成する各鋼製枠材23は各鋼製作業足場兼均
し定規部材7と同一間隔で配置され、さらに格子状骨組
フレーム24を構成する各鋼製枠材23の下面の全長に
わたってゴム製シール材26が接着剤により固着されて
いる。
FIG. 7 shows a steel pier frame 2 with a sealing material used in combination with the steel pile guide formwork device 20 of the embodiment of the present invention.
2 shows a steel frame member 23 having a flange at its lower end, which is arranged on a lattice and fixed to each other by welding, to form a lattice frame 24, and the lattice frame thereof. A steel footing formwork 25 is fixed to the outside of the frame 24 by welding, and the steel frame members 23 constituting the lattice-shaped frame 24 are arranged at the same intervals as the steel work scaffolding and leveling ruler members 7. Further, a rubber sealing material 26 is fixed by an adhesive over the entire length of the lower surface of each steel frame member 23 constituting the lattice-shaped frame 24.

第8図ないし第10図はこの考案の一実施例に係る鋼杭
ガイド型枠装置20の使用状態を示すものであって、ま
ず水底地盤14の掘下凹所に敷設された敷砂15の上
に、鋼杭ガイド型枠装置20が載置され、前記骨組フレ
ーム3の各鋼杭挿入空間4における4箇のガイド部材5
の間に鋼管杭からなる鋼杭16が挿入され、その鋼杭1
6が4箇のガイド部材5をガイドとして水底地盤14に
打設され、各鋼杭16の上部は鋼杭ガイド型枠装置20
の上面よりも上方に突出される。
8 to 10 show a usage state of the steel pile guide formwork apparatus 20 according to the embodiment of the present invention. First, the sand pile 15 laid in the digging recess of the water bottom ground 14 is shown. A steel pile guide formwork device 20 is placed on the top, and four guide members 5 in each steel pile insertion space 4 of the frame frame 3 are placed.
A steel pile 16 composed of a steel pipe pile is inserted between the
6 is cast on the water bottom ground 14 using the four guide members 5 as guides, and the upper portion of each steel pile 16 is a steel pile guide formwork device 20.
Is projected above the upper surface of.

次に鋼製外側型枠6により囲まれた部分に水中コンクリ
ート19が打設され、かつその水中コンクリート19の
上面が、外側型枠6および作業足場兼均し定規部材7の
上面と同一レベルになるように外側型枠6および作業足
場兼均し定規部材7の上面を均し定規として均されて平
面状に仕上げられる。この場合、前記作業足場兼均し定
規部材7の上面は水中コンクリート19を均すときの定
規としての他に、水中コンクリート打設作業および水中
コンクリート均し作業を行なう場合の潜水夫の作業足場
としても利用される。
Next, underwater concrete 19 is placed in a portion surrounded by the steel outer formwork 6, and the upper surface of the underwater concrete 19 is at the same level as the outer formwork 6 and the upper surfaces of the work scaffolding and leveling ruler member 7. Thus, the upper surfaces of the outer formwork 6 and the work scaffolding / leveling ruler member 7 are leveled as a leveling ruler and finished in a flat shape. In this case, the upper surface of the work scaffolding and leveling ruler member 7 is used as a ruler for leveling the underwater concrete 19 and also as a work scaffold for a diver when performing underwater concrete placing work and underwater concrete leveling work. Is also used.

次に第9図および第10図に示すように、水中コンクリ
ート19を打設した鋼杭ガイド型枠装置20のうえに、
シール剤付き鋼製橋脚フレーム22が吊り降ろされて、
ゴム製シール材26が鋼製作業足場兼均し定規部材7お
よび水中コンクリート19の上面に載置され、次いでフ
ーチング型枠25内にフーチングコンクリート27が打
設される。この場合、シール材26が水平な鋼製作業足
場兼均し定規部材7および水中コンクリート19の上面
に載置されるので、フーチングコンクリート27の漏洩
が防止される。
Next, as shown in FIG. 9 and FIG. 10, on the steel pile guide formwork device 20 in which the underwater concrete 19 is placed,
The steel pier frame 22 with sealant was hung down,
The rubber sealing material 26 is placed on the upper surfaces of the steel work scaffolding and leveling ruler member 7 and the underwater concrete 19, and then the footing concrete 27 is placed in the footing form 25. In this case, the sealing material 26 is placed on the upper surfaces of the horizontal steel work scaffolding and leveling ruler member 7 and the underwater concrete 19, so that the footing concrete 27 is prevented from leaking.

外側型枠6内に水中コンクリート19を打設して均す場
合、その水中コンクリート19の表面が作業足場兼均し
定規部材7の上面よりも僅かに低い平面になるように均
してもよい。
When pouring and leveling the underwater concrete 19 in the outer formwork 6, the surface of the underwater concrete 19 may be leveled so as to be a plane slightly lower than the upper surface of the work scaffolding / leveling ruler member 7. .

この考案を実施する場合、枠材1,2および作業足場兼
均し定規部材としては、図示以外の任意断面のものを使
用してもよい。
When carrying out this invention, as the frame members 1 and 2 and the work scaffolding / leveling ruler member, those having an arbitrary cross section other than those shown in the drawings may be used.

〔考案の効果〕[Effect of device]

この考案は、前述のように構成されているので、以下に
記載するような効果を奏する。
Since the present invention is configured as described above, it has the following effects.

格子状骨組フレーム3を構成する各枠材1,2の上部に
鋼製作業足場兼均し定規部材7が固定されているので、
鋼製外側型枠6内に打設された水中コンクリート19を
均らして表面仕上げする場合、前記作業足場兼均し定規
部材7の上面を均し定規として利用して、水中コンクリ
ート19の表面均し仕上げを高精度で行なうことがで
き、かつ潜水夫が作業足場兼均し定規部材7の上面を作
業足場として利用して、鋼製外側型枠6内への水中コン
クリート19の打設作業および水中コンクリート19の
表面の均し作業を容易かつ安全に行なうことができ、さ
らに格子状骨組フレーム3を構成する各鋼製枠材1,2
が鋼製作業足場兼均し定規部材7により補強されて、格
子状骨組フレーム3が強化されるので、鋼杭を打込む際
に骨組フレーム3が変形するのを防止することができ、
そのため変形が発生した鋼杭ガイド型枠装置を水中から
引き上げて整形するという煩雑な作業を行なう必要がな
く、しかもガイド部材5付きの格子状骨組フレーム3
と、作業足場兼均し定規部材7と外側型枠6とが一体化
されているので、水中基礎を高能率でかつ低コストで施
工することができる。
Since the steel work scaffolding and leveling ruler member 7 is fixed to the upper portions of the frame members 1 and 2 constituting the lattice-shaped frame 3,
When the underwater concrete 19 cast in the steel outer formwork 6 is leveled and surface-finished, the upper surface of the work scaffolding / leveling ruler member 7 is used as a leveling ruler, and the surface leveling of the underwater concrete 19 is performed. The finishing work can be performed with high accuracy, and the diver can use the upper surface of the work scaffolding and leveling ruler member 7 as a work scaffolding to place the underwater concrete 19 in the steel outer formwork 6 and The surface of the underwater concrete 19 can be leveled easily and safely, and each of the steel frame members 1 and 2 constituting the lattice-shaped frame 3
Is reinforced by the steel work scaffolding and leveling ruler member 7, and the lattice-shaped frame 3 is reinforced, so that it is possible to prevent the frame 3 from being deformed when the steel pile is driven,
Therefore, it is not necessary to perform the complicated work of pulling up the deformed steel pile guide formwork device from the water and shaping it, and moreover, the lattice-shaped frame 3 with the guide member 5 is required.
Since the work scaffolding and leveling ruler member 7 and the outer formwork 6 are integrated, the underwater foundation can be constructed with high efficiency and at low cost.

また水中コンクリート19の表面を高精度で仕上げるこ
とができるので、鋼製作業足場兼均し定規部材7および
水中コンクリート19の上に載置されたシール材付き鋼
製橋脚フレーム22における鋼製フーチング型枠25内
にフーチングコンクリート27を打設した際に、そのフ
ーチングコンクリートが漏洩するのを防止することがで
き、かつ先行打設により作成された基礎は強固な鋼杭ガ
イド型枠装置20と水中コンクリート19とにより構成
されているので、水中基礎設置部の地盤が軟弱であって
も、フーチングコンクリート打設時に先行打設基礎が破
壊したり沈下したりするのを防止することができる。
Further, since the surface of the underwater concrete 19 can be finished with high accuracy, the steel footing type in the steel work scaffolding and leveling ruler member 7 and the steel pier frame 22 with the sealing material placed on the underwater concrete 19 When the footing concrete 27 is placed in the frame 25, the footing concrete can be prevented from leaking, and the foundation created by the preceding placing is a solid steel pile guide formwork device 20 and underwater concrete. Therefore, even if the ground of the underwater foundation installation part is soft, it is possible to prevent the preceding foundation to be destroyed or settled during the placing of footing concrete.

【図面の簡単な説明】[Brief description of drawings]

第1図ないし第4図はこの考案の一実施例に係る水中基
礎施工用鋼杭ガイド型枠装置を示すものであって、第1
図は平面図、第2図は第1図のA−A線断面図、第3図
は第1図のB−B線断面図、第4図は第2図の一部を拡
大して示す断面図である。第5図は鋼杭打込ガイド用鋼
製ガイド部材付きの格子状骨組フレームを示す平面図、
第6図は鋼杭ガイド型枠装置の変形例を示す縦断側面
図、第7図はシール材付き鋼製橋脚フレームを示す一部
縦断正面図である。第8図は鋼杭ガイド型枠装置を設置
して外側型枠の中に水中コンクリートを打設した状態を
示す縦断正面図、第9図はシール材付き鋼製橋脚フレー
ムを鋼杭ガイド型枠装置およびその中の水中コンクリー
トからなる水中基礎に載置してフーチングコンクリート
を打設した状態を示す一部縦断正面図、第10図は第9
図の一部を拡大して示す縦断正面図である。 第11図ないし第13図は従来の鋼製導枠を示すもので
あって、第11図は平面図、第12図は第11図のC−
C線拡大断面図、第13図は第11図のD−D線拡大断
面図である。第14図ないし第17図は従来の水中基礎
および鋼製橋脚フレーム設置施工順序を示す概略縦断正
面図である。 図において、1は鋼製枠材、2は鋼製枠材、3は格子状
骨組フレーム、4は鋼杭挿入空間、5は鋼杭打込ガイド
用鋼製ガイド部材、6は鋼製外側型枠、7は鋼製作業兼
均し定規部材、19は水中コンクリート、20は鋼杭ガ
イド型枠装置、21は鋼板製連結部材、22はシール材
付き鋼製橋脚フレーム、23は鋼製枠材、24は格子状
骨組フレーム、25は鋼製フーチング型枠、26はゴム
製シール材、27はフーチングコンクリートである。
1 to 4 show a steel pile guide formwork apparatus for underwater foundation construction according to an embodiment of the present invention.
The drawing is a plan view, FIG. 2 is a sectional view taken along line AA of FIG. 1, FIG. 3 is a sectional view taken along line BB of FIG. 1, and FIG. 4 is an enlarged view of part of FIG. FIG. FIG. 5 is a plan view showing a lattice-shaped frame with a steel guide member for a steel pile driving guide,
FIG. 6 is a vertical sectional side view showing a modified example of the steel pile guide formwork device, and FIG. 7 is a partial vertical sectional front view showing a steel pier frame with a sealing material. Fig. 8 is a vertical sectional front view showing a state in which the steel pile guide formwork device is installed and underwater concrete is placed in the outer formwork, and Fig. 9 is a steel pile pier frame with a sealant attached to the steel pile guide formwork. FIG. 10 is a partial vertical sectional front view showing a state in which footing concrete is placed by placing it on an underwater foundation consisting of the device and the underwater concrete therein.
It is a vertical front view which expands and shows a part of figure. 11 to 13 show a conventional steel guide frame, in which FIG. 11 is a plan view and FIG. 12 is C- in FIG.
C line enlarged sectional view, FIG. 13 is a DD line enlarged sectional view of FIG. FIG. 14 to FIG. 17 are schematic vertical sectional front views showing the installation sequence of the conventional underwater foundation and steel pier frame. In the figure, 1 is a steel frame member, 2 is a steel frame member, 3 is a lattice frame frame, 4 is a steel pile insertion space, 5 is a steel guide member for a steel pile driving guide, and 6 is a steel outer mold. Frame, 7 steel work and leveling ruler member, 19 underwater concrete, 20 steel pile guide formwork device, 21 steel plate connecting member, 22 steel pier frame with sealing material, 23 steel frame material , 24 is a lattice frame frame, 25 is a steel footing form, 26 is a rubber sealing material, and 27 is footing concrete.

Claims (1)

【実用新案登録請求の範囲】[Scope of utility model registration request] 【請求項1】多数の鋼製枠材1,2が格子状に配置され
ると共に溶接により固着されて、格子状骨組フレーム3
が構成され、その格子状骨組フレーム3における各鋼杭
挿入空間4内の各辺の中央部に配置された鋼杭打込ガイ
ド用鋼製ガイド部材5は前記枠材1,2に固定され、前
記格子状骨組フレーム3の周囲に鋼製外側型枠6の下部
が固定され、前記各枠材1,2の上部に枠材長手方向に
延長する鋼製作業足場兼均し定規部材7が固定されてい
る水中基礎施工用鋼杭ガイド型枠装置。
1. A large number of steel frame members 1 and 2 are arranged in a grid pattern and are fixed by welding, and a grid frame frame 3 is formed.
And a steel guide member 5 for steel pile driving guides arranged at the center of each side in each steel pile insertion space 4 in the lattice frame 3 is fixed to the frame members 1 and 2, The lower part of the steel outer formwork 6 is fixed around the lattice-shaped frame 3, and the steel work scaffolding and leveling ruler member 7 extending in the longitudinal direction of the frame material is fixed to the upper part of each of the frame materials 1 and 2. Steel pile guide formwork equipment for underwater foundation construction.
JP5157188U 1988-04-19 1988-04-19 Steel pile guide formwork equipment for underwater foundation construction Expired - Lifetime JPH067162Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP5157188U JPH067162Y2 (en) 1988-04-19 1988-04-19 Steel pile guide formwork equipment for underwater foundation construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP5157188U JPH067162Y2 (en) 1988-04-19 1988-04-19 Steel pile guide formwork equipment for underwater foundation construction

Publications (2)

Publication Number Publication Date
JPH01154254U JPH01154254U (en) 1989-10-24
JPH067162Y2 true JPH067162Y2 (en) 1994-02-23

Family

ID=31277593

Family Applications (1)

Application Number Title Priority Date Filing Date
JP5157188U Expired - Lifetime JPH067162Y2 (en) 1988-04-19 1988-04-19 Steel pile guide formwork equipment for underwater foundation construction

Country Status (1)

Country Link
JP (1) JPH067162Y2 (en)

Also Published As

Publication number Publication date
JPH01154254U (en) 1989-10-24

Similar Documents

Publication Publication Date Title
CN105649197A (en) Post-pouring belt construction method conducted under green-landscape-first condition
CN110344335B (en) Method for constructing steel trestle, initial platform and cofferdam in bridge construction process
CN105178358B (en) Vertical supporting system for reverse construction method and construction method of vertical supporting system
CN111827349A (en) Method for quickly constructing underground structure of subway station by adopting combined structure technology
JPH067162Y2 (en) Steel pile guide formwork equipment for underwater foundation construction
JP3251567B2 (en) Construction method of open caisson bottom
CN210238492U (en) Crown beam type miniature pile construction formwork capable of being circulated
JP2868725B2 (en) Seawall repair method
CN105951844A (en) Roof node structure adopting cover-excavation method and construction method of roof node structure
JP2599299B2 (en) Retaining wall and retaining method in soft ground
CN217840090U (en) Full-height inverted filter frame for pile-plate type retaining wall
CN109898403A (en) The underwater canal case steel suspension bridge of urban rives construction method nested with double steel sheet-pile cofferdam
CN220352860U (en) Template lacing wire structure
JP7480069B2 (en) How to reinforce existing revetments
CN214301864U (en) Sump pit and post-cast strip collision node
CN114991015B (en) Viaduct bearing platform construction method and bearing platform template used by same
CN113026753B (en) Design bottom sealing concrete construction structure and method for water seepage cofferdam
CN217923627U (en) Recoverable shaped steel stand stake device
CN217480231U (en) Plate-type tower crane foundation construction structure combined with raft
CN216238560U (en) Supporting structure for auxiliary construction of oversized foundation pit
JPH07138972A (en) Construction method for underground skeleton
JPS61134422A (en) Method of building precast concrete underground continuous wall
JPS6035491B2 (en) The body of the well or submerge
CN115094948A (en) Pile-plate type retaining wall combined frame and construction method
CN112922028A (en) Construction method suitable for oversized circular subway station