JPH0660085A - Materials requirement plan forming system - Google Patents

Materials requirement plan forming system

Info

Publication number
JPH0660085A
JPH0660085A JP21481992A JP21481992A JPH0660085A JP H0660085 A JPH0660085 A JP H0660085A JP 21481992 A JP21481992 A JP 21481992A JP 21481992 A JP21481992 A JP 21481992A JP H0660085 A JPH0660085 A JP H0660085A
Authority
JP
Japan
Prior art keywords
factory
item
information
code
material requirement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP21481992A
Other languages
Japanese (ja)
Inventor
Yukiyasu Tachihara
幸泰 立原
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NEC Corp
Original Assignee
NEC Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NEC Corp filed Critical NEC Corp
Priority to JP21481992A priority Critical patent/JPH0660085A/en
Publication of JPH0660085A publication Critical patent/JPH0660085A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • General Factory Administration (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

PURPOSE:To form a materials requirement plan for manufacturing across plural factories and sections whose working date calendars are different, on a single system. CONSTITUTION:The plural kinds of working date calendars are registered in a working date calendar file 5 according to the actual working date of each factory and section. Then, a factory code table 6 is constructed in order to relate the working date calendars with the factories and sections, and a factory code is set as the item of a list of item master file 8 in a parts chart information file 7 in order to relate the list of items with the factory in charge of the manufacture. Thus, the formation of the materials requirement plan across the plural factories can be attained by using the factory code as a key.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は資材所要計画立案方式に
関し、特に製造品目が稼働日又は資材所要計画立案周期
の異なる複数の生産工場、又は複数の生産部門において
製造される場合の資材所要計画の立案方式に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a material requirement planning method, and in particular, a material requirement plan in the case where manufactured items are manufactured in a plurality of production plants or a plurality of production departments having different working days or material requirement planning cycles. Concerning the planning method of.

【0002】[0002]

【従来の技術】従来の資材所要計画の立案方式は、1シ
ステムにおいて単一の管理用の稼働日カレンダ情報ファ
イルを用い、部品表の品目構成に従い品目構成の段階ご
とに各品目の手配に要するリードタイムに基づいて、手
配に要するリードタイムの日数分だけ稼働日カレンダの
日付を遡って資材の所要時期を算出し、製造オーダ情報
を生成している。
2. Description of the Related Art A conventional material requirement planning method uses a single working day calendar information file for one system and requires each item to be arranged at each stage of item composition according to the item composition of a parts table. Based on the lead time, the required time of the material is calculated by tracing back the date of the working calendar by the number of days of the lead time required for the arrangement, and the manufacturing order information is generated.

【0003】このため、従来では、稼働日又は資材所要
計画の周期が異なる複数の生産工場(以下、工場とい
う)、又は複数の生産部門(以下、部門という)にまた
がって製造される製品については、工場ごとにシステム
を保有し、部品表,稼働日カレンダーの基準情報を分割
して整備した上で、各工場において資材の所要計画を立
案している。
Therefore, conventionally, a product manufactured over a plurality of production plants (hereinafter referred to as factories) or a plurality of production departments (hereinafter referred to as departments) having different working days or material requirement plan cycles is Each factory has its own system, and after dividing and maintaining standard information such as parts list and working day calendar, each factory makes necessary material plans.

【0004】[0004]

【発明が解決しようとする課題】この従来の資材所要計
画立案方式では、稼働日又は資材所要計画周期の異なる
複数工場又は部門にまたがり、製造される製品において
は、部品表情報の内、品目構成情報手配リードタイムに
基づく資材所要量展開を関係している工場の数と少なく
とも同じ回数だけ実施する必要がある。
According to this conventional material requirement planning method, in a product manufactured across a plurality of factories or departments having different working days or material requirement planning cycles, the product composition in the parts table information is It is necessary to carry out material requirement development based on information arrangement lead time at least as many times as the number of factories involved.

【0005】これは、例えば、製造の過程でA工場から
B工場を経て、再びA工場で製造される製品の場合、A
工場の資材所要量の展開を実施した後、B工場の資材所
要量の展開を実施し、その後、再度A工場の資材所要量
の展開を実施しなければならない。このため、資材所要
計画立案に時間がかかり、また、各工場や各部門におい
て個別に情報処理装置を設置しなければならないという
問題点がある。
For example, in the case of a product manufactured in the A factory from the A factory to the B factory in the manufacturing process,
After the material requirements of the factory have been expanded, the material requirements of the factory B must be expanded, and then the material requirements of the factory A must be expanded again. Therefore, there is a problem that it takes time to prepare a material requirement plan, and that each factory and each department must individually install an information processing device.

【0006】[0006]

【課題を解決するための手段】本発明は、複数の生産工
場における資材所要計画の立案方式であって、前記各生
産工場の稼働日に対応する稼働日カレンダ情報ファイル
を保有し、前記各生産工場とその稼働日カレンダとを工
場コードをキーとして対応させることにより、前記各工
場の実稼働日を考慮した資材所要量を展開し、これに基
づいて製造オーダ情報を生成することを特徴とする。
The present invention is a method for drafting a material requirement plan in a plurality of production plants, which has an operating day calendar information file corresponding to the operating days of each of the production plants, By associating the factory and its operating day calendar with the factory code as a key, the material requirement amount is developed in consideration of the actual operating day of each factory, and the manufacturing order information is generated based on this. .

【0007】[0007]

【実施例】次に、本発明について図面を参照して説明す
る。
DESCRIPTION OF THE PREFERRED EMBODIMENTS Next, the present invention will be described with reference to the drawings.

【0008】図1は資材所要計画システムの概念図であ
る。図1において、本発明の所要計画立案方式は、資材
所要量展開部4に基準日程計画ファイル10を付加し、
稼働日カレンダ情報ファイル5,工場コードテーブル6
及び部品表情報ファイル7を参照の上、各品目ごとに製
造を担当する工場及び部門の稼働日を考慮した資材所要
量展開を実施し、製造オーダの生成を実現している。
FIG. 1 is a conceptual diagram of a material requirement planning system. In FIG. 1, the requirement planning method of the present invention adds a reference schedule planning file 10 to a material requirement expanding unit 4,
Working day calendar information file 5, factory code table 6
Also, referring to the parts table information file 7, the material requirements are developed for each item in consideration of the operating days of the factory and department in charge of manufacturing, and the production of the manufacturing order is realized.

【0009】稼働日カレンダ情報登録部1は、工場又は
部門の稼働スケジュールに基づいて、稼働日や休止日
(休暇,棚卸日,休日振替)を端末装置13により入力
し、稼働日カレンダ情報ファイル5へ登録する。工場コ
ードテーブル登録部2は、上記の稼働日カレンダ情報登
録部1で登録された稼働日カレンダと工場コードを対応
されらテーブルを作成するために、稼働日カレンダコー
ドをキーとして端末装置14により入力する。その際、
稼働日カレンダ情報ファイル5に登録されていない稼働
日カレンダコードを入力した場合、稼働日カレンダ情報
ファイル5に未登録である旨のメッセージを端末装置1
4に送信する。
The working day calendar information registration unit 1 inputs working days and rest days (vacations, inventory days, holiday transfers) through the terminal device 13 based on the working schedule of the factory or department, and the working day calendar information file 5 Register to. The factory code table registration unit 2 inputs the operation day calendar code by the terminal device 14 as a key in order to create a table in which the operation day calendar registered in the above operation day calendar information registration unit 1 is associated with the factory code. To do. that time,
When a working day calendar code that is not registered in the working day calendar information file 5 is entered, a message indicating that it is not registered in the working day calendar information file 5 is displayed on the terminal device 1.
Send to 4.

【0010】稼働日カレンダコード入力後、その稼働日
カレンダコードが稼働日カレンダ情報ファイル5上に存
在する時は、工場コード入力画面を送信し、工場コード
の入力を受付け、図2(a)に示すようなレコード形式
のテーブルを作成し、工場コードテーブル6へ登録す
る。また、工場コードを追加する場合には、図2(b)
に示すように、レコード上末尾の工場コードの後に追加
登録された工場コードを付加し、レコードの更新を行
う。
After the input of the working day calendar code, when the working day calendar code exists in the working day calendar information file 5, the factory code input screen is transmitted and the input of the factory code is accepted. A table in the record format as shown is created and registered in the factory code table 6. When adding a factory code, see Fig. 2 (b).
As shown in, the factory code additionally registered is added after the factory code at the end of the record, and the record is updated.

【0011】部品表情報登録部3は、部品表情報ファイ
ル7に包含される品目マスタファイル8及び品目構成マ
スタファイル9へそれぞれ品目情報(品目番号,品目名
称,規格,リードタイム,内作/外作区分,工場コード
等の品目固有の属性情報)と、品目構成情報(親品目番
号,子品目番号,構成単位数量:親品目を1つ製造する
際に、必要となる子品目の数量等の品目間の関係を表わ
す情報)とを登録,更新する。
The parts table information registration unit 3 writes item information (item number, item name, standard, lead time, in-house / outside) to the item master file 8 and the item structure master file 9 included in the parts table information file 7. Item-specific attribute information such as crop classification and factory code) and item composition information (parent item number, child item number, component unit quantity: the number of child items required when one parent item is manufactured, etc.) Information indicating the relationship between items) and

【0012】本発明においては、端末装置15により部
品表情報登録部3から品目マスタファイル8上に工場コ
ード項目を登録することにより、各品目単位に製造を行
う工場、又は部門、ひいては各品目を製造することが可
能である稼働日へと関連づけている。そして、資材所要
量展開部4は、端末装置16により基準日程計画システ
ムで生成された基準日程計画ファイル10内の基準日程
計画情報(最上位品目の製造オーダ完了日)に基づいて
資材所要量の展開を行い、品目構成情報の各レベルの品
目毎に製造オーダ情報を生成し、それを製造オーダ情報
ファイル11内に格納する。
In the present invention, by registering the factory code items in the item master file 8 from the parts table information registration section 3 by the terminal device 15, the factory or department which manufactures each item unit, and eventually each item. It relates to the working days that can be manufactured. Then, the material requirement expansion unit 4 calculates the material requirement based on the reference schedule planning information (the production order completion date of the highest-order item) in the reference schedule planning file 10 generated by the reference schedule planning system by the terminal device 16. Expansion is performed, manufacturing order information is generated for each item of each level of the item configuration information, and the manufacturing order information is stored in the manufacturing order information file 11.

【0013】次に、この製造オーダ情報生成方式の一例
を以下に示す。
Next, an example of this manufacturing order information generation system is shown below.

【0014】図3に示す部品表情報を持つ製品Aにおい
て、工場コードa及びbは、稼働日カレンダが異なる資
材所要計画立案の周期が同一である場合の処理を、図4
に示す流れ図を参照して説明する。
In the product A having the parts table information shown in FIG. 3, the factory codes a and b have the same processing cycle when the material requirement planning cycles with different working day calendars are the same.
This will be described with reference to the flowchart shown in FIG.

【0015】まず、製品Aの製造オーダを基準日程計画
の製造オーダ完了日より、リードタイムの日数分を工場
コードaの稼働日カレンダの休日を考慮した上で、製造
オーダの着手日を算出して製品Aの製造オーダを生成す
る。この例においては、オーダ完了日の2日前は休日で
あり、従って、製品Aのオーダ着手日は、その前日とな
る。
First, the production order start date of the production order of the product A is calculated by taking the lead time days from the production order completion date of the standard schedule into consideration of the working day calendar holidays of the factory code a. To generate the manufacturing order of the product A. In this example, two days before the order completion date is a holiday, so the order starting date of the product A is the day before that.

【0016】ここで、算出された製品Aの製造ロット着
手日、及び数量が下位品目a,bのデマンド(需要)情
報へと展開される(図5参照)。品目aに対するデマン
ド情報は、製品Aのオーダ着手日に対応して同一日に生
成されるが、品目bに対するデマンド情報は、製品Aの
製造オーダ着手日が品目bの製造を行う工場の稼働日カ
レンダを参照すると、休日と設定されている。従って、
品目bに対するデマンド情報は、製品Aの製造オーダ着
手日の直前の日に、品目bに対するデマンド情報が生成
される。
Here, the calculated production lot start date and quantity of the product A are developed into the demand information of the subordinate items a and b (see FIG. 5). The demand information for the item a is generated on the same day corresponding to the order start date of the product A, while the demand information for the item b is the manufacturing order start date of the product A is the working day of the factory that manufactures the item b. According to the calendar, it is set as a holiday. Therefore,
As the demand information for the item b, the demand information for the item b is generated on the day immediately before the start of the manufacturing order of the product A.

【0017】このように生成された品目a及びbに対す
る各デマンド情報が、品目a及びbそれぞれの製造オー
ダ終了日となるため、この情報を基準にして品目a及び
bの各情報内のリードタイム,工場コードに基づき、製
品Aの場合と同様に、品目a及びbの製造オーダ着手日
をそれぞれ算出して製造オーダを生成する。
Since the demand information for the items a and b thus generated becomes the manufacturing order end date of the items a and b, the lead time in each information of the items a and b is based on this information. Based on the factory code, as in the case of the product A, the production order start dates of the items a and b are calculated, and the production order is generated.

【0018】以上、述べてきた処理を品目構成情報の末
端品目に至るまで繰り返し、製品Aの全構成品目に対し
て製造オーダ情報を生成する。そして、生成された製造
オーダ情報は、製造オーダが生成される都度、製造オー
ダ情報ファイル11へ登録する。このようにして、本発
明においては、稼働日の異なる複数工場、部門にまたが
る製造品目の資材所要計画を単一のシステムで、また、
単一の処理サイクルで実現している。
The above-described processing is repeated until the end item of the item configuration information, and the production order information is generated for all the configuration items of the product A. Then, the generated manufacturing order information is registered in the manufacturing order information file 11 every time the manufacturing order is generated. In this way, in the present invention, a single system can be used for material requirement planning of manufactured items across multiple factories and departments with different working days.
It is realized in a single processing cycle.

【0019】次に、資材所要計画立案の周期が異なる場
合について説明する。この場合、部品表情報,工場コー
ド等の情報は、前述の場合と同様に、図3に示す内容に
基づくものとし、工場コードaを持つ工場を資材所要計
画立案の対象とする。
Next, the case where the cycle of material requirement planning is different will be described. In this case, the information such as the parts table information and the factory code is based on the content shown in FIG. 3 as in the case described above, and the factory having the factory code a is the target of the material requirement planning.

【0020】この場合の処理について、図4に示す流れ
図を参照して説明する。
The processing in this case will be described with reference to the flow chart shown in FIG.

【0021】まず、最初の処理として、計画立案対象の
工場コードを指定し、このコードを各品目の製造オーダ
生成時に各品目情報内の工場コードと突き合わせ、合致
する工場コードを持つ品目のみ製造オーダの生成を行
う。この場合、品目b以下の下位品目は工場コードbを
持っているため、資材所要計画立案の対象外となる。そ
して、工場コードbは対象として計画立案時、今回生成
された品目bに対するデマンド情報に基づいて製造オー
ダの生成し、資材所要量の展開を実施する。
First, as a first process, a factory code to be planned is specified, this code is matched with the factory code in each item information when the manufacturing order of each item is generated, and only the item having the matching factory code is manufactured. Is generated. In this case, the subordinate items below the item b have the factory code b, and thus are excluded from the material requirement planning. Then, at the time of planning, the factory code b is used as a target to generate a manufacturing order based on the demand information for the item b generated this time, and to develop the material requirements.

【0022】このように、本発明においては、工場コー
ドを識別することにより、資材所要計画立案周期の異な
る複数工場にまたがる場合についても、単一システムに
よる対応を可能としている。
As described above, according to the present invention, by identifying the factory code, it is possible to deal with a case where a plurality of factories having different material requirement planning cycles are covered by a single system.

【0023】[0023]

【発明の効果】以上説明したように本発明は、稼働日の
異なる複数工場又は部門にまたがる製造品目の資材所要
計画を立案する場合、工場コードにより、複数の稼働日
カレンダを切り分け、かつ参照することによって、単一
システムにおいて単一の処理サイクルで計画立案を行う
ことができるため、処理時間の大幅な短縮がはかれると
共に、情報処理装置の設備の統合が可能となり、設備投
資コストが削減できるという効果を有する。
As described above, according to the present invention, when a material requirement plan for a manufactured item that extends over a plurality of factories or departments with different working days is prepared, a plurality of working day calendars are divided and referred to by a factory code. By doing so, it is possible to plan in a single processing cycle in a single system, so that it is possible to significantly reduce the processing time, it is possible to integrate the equipment of the information processing device, and it is possible to reduce the capital investment cost. Have an effect.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の一実施例である資材所要計画システム
を示す概念図である。
FIG. 1 is a conceptual diagram showing a material requirement planning system which is an embodiment of the present invention.

【図2】図1の工場コードテーブルのレコード構成を示
す図である。
FIG. 2 is a diagram showing a record configuration of a factory code table in FIG.

【図3】図1の部品表情報ファイルの一例を示す概念図
である。
FIG. 3 is a conceptual diagram showing an example of a parts table information file in FIG.

【図4】図1の資材所要量展開部の処理手順を示す流れ
図である。
FIG. 4 is a flow chart showing a processing procedure of a material requirement developing unit of FIG.

【図5】資材所要量展開の一例を説明する概念図であ
る。
FIG. 5 is a conceptual diagram for explaining an example of material requirement development.

【符号の説明】[Explanation of symbols]

1 稼働日カレンダ情報登録部 2 工場コードテーブル登録部 3 部品表情報登録部 4 資材所要量展開部 5 稼働日カレンダ情報ファイル 6 工場コードテーブル 7 部品表情報ファイル 8 品目マスタファイル 9 品目構成マスタファイル 10 基準日程計画ファイル 11 製造オーダ情報ファイル 12 情報処理装置 13〜16 端末装置 1 Working day calendar information registration section 2 Factory code table registration section 3 Parts list information registration section 4 Material requirement expansion section 5 Working day calendar information file 6 Factory code table 7 Parts list information file 8 Item master file 9 Item composition master file 10 Standard schedule planning file 11 Manufacturing order information file 12 Information processing device 13 to 16 Terminal device

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 複数の生産工場における資材所要計画の
立案方式であって、前記各生産工場の稼働日に対応する
稼働日カレンダ情報ファイルを保有し、前記各生産工場
とその稼働日カレンダとを工場コードをキーとして対応
させることにより、前記各工場の実稼働日を考慮した資
材所要量を展開し、これに基づいて製造オーダ情報を生
成することを特徴とする資材所要計画立案方式。
1. A method of drafting a material requirement plan in a plurality of production plants, which has an operating day calendar information file corresponding to the operating days of each of the production plants, and stores each of the production plants and their operating day calendars. A material requirement planning method characterized by expanding the material requirements in consideration of the actual operating days of each factory by using the factory code as a key and generating manufacturing order information based on this.
JP21481992A 1992-08-12 1992-08-12 Materials requirement plan forming system Pending JPH0660085A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP21481992A JPH0660085A (en) 1992-08-12 1992-08-12 Materials requirement plan forming system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP21481992A JPH0660085A (en) 1992-08-12 1992-08-12 Materials requirement plan forming system

Publications (1)

Publication Number Publication Date
JPH0660085A true JPH0660085A (en) 1994-03-04

Family

ID=16662052

Family Applications (1)

Application Number Title Priority Date Filing Date
JP21481992A Pending JPH0660085A (en) 1992-08-12 1992-08-12 Materials requirement plan forming system

Country Status (1)

Country Link
JP (1) JPH0660085A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0896037A (en) * 1994-09-28 1996-04-12 Nec Corp Calendar calculation device
JP2001184117A (en) * 1999-12-27 2001-07-06 Toyota Motor Corp Device and method for ordering parts and recording medium
WO2004036325A1 (en) * 2002-10-16 2004-04-29 Honda Giken Kogyo Kabushiki Kaisha Step processing configuration/management method in factory production step management system

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6225610A (en) * 1985-07-26 1987-02-03 Osaka Bosui Kensetsushiya:Kk Chemical grout injection work

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6225610A (en) * 1985-07-26 1987-02-03 Osaka Bosui Kensetsushiya:Kk Chemical grout injection work

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0896037A (en) * 1994-09-28 1996-04-12 Nec Corp Calendar calculation device
JP2001184117A (en) * 1999-12-27 2001-07-06 Toyota Motor Corp Device and method for ordering parts and recording medium
WO2004036325A1 (en) * 2002-10-16 2004-04-29 Honda Giken Kogyo Kabushiki Kaisha Step processing configuration/management method in factory production step management system

Similar Documents

Publication Publication Date Title
US5237495A (en) Production/purchase management processing system and method
US6557002B1 (en) Data management system for storing structural element data management program
JP4979074B2 (en) Traceability management system and traceability management method
CN112818189A (en) Visual process technology single scheduling method, system and platform
US7127307B2 (en) Generation/management apparatus of production processing structure in factory production management system
JPH0660085A (en) Materials requirement plan forming system
JPH1131179A (en) Method and device for managing inter-company transaction progress
JPH10333709A (en) Process information management system
US6221538B1 (en) Method for automating manufacture of photomask
US20020123811A1 (en) Production management system and program
JPH07271864A (en) Production control method
JP4892248B2 (en) Production planning system and semiconductor device manufacturing method
JP2001166928A (en) Device for automatically generating job net
JPH01264751A (en) Preparation for production process planning table
JP2947048B2 (en) BOM management method
JP2004062526A (en) Production management system
JPH086997A (en) Preparing method for arrow diagram master classified by types
JPH07175857A (en) Production planning system
JPH08315018A (en) Method for calculating parts preparation date by using retrospective date
JP5007609B2 (en) Production order creation program and production order creation device
JP2023173532A (en) Process generation system
JPH05181871A (en) Production scheduling device
JPH06342443A (en) Work operation system
JPH03149162A (en) Synchronous production scheduling planning device
JP2001306123A (en) Planning system for carrying in parts for knock-down production to shipping base

Legal Events

Date Code Title Description
A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 19981110