JPH0642100A - Support hardware for eaves soffit material - Google Patents

Support hardware for eaves soffit material

Info

Publication number
JPH0642100A
JPH0642100A JP4120691A JP12069192A JPH0642100A JP H0642100 A JPH0642100 A JP H0642100A JP 4120691 A JP4120691 A JP 4120691A JP 12069192 A JP12069192 A JP 12069192A JP H0642100 A JPH0642100 A JP H0642100A
Authority
JP
Japan
Prior art keywords
eaves
roof
eaves ceiling
building
ceiling material
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP4120691A
Other languages
Japanese (ja)
Other versions
JP2688305B2 (en
Inventor
Kiyoshi Hirai
清 平井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Misawa Homes Co Ltd
Original Assignee
Misawa Homes Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Misawa Homes Co Ltd filed Critical Misawa Homes Co Ltd
Priority to JP4120691A priority Critical patent/JP2688305B2/en
Publication of JPH0642100A publication Critical patent/JPH0642100A/en
Application granted granted Critical
Publication of JP2688305B2 publication Critical patent/JP2688305B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Roof Covering Using Slabs Or Stiff Sheets (AREA)

Abstract

PURPOSE:To make it possible to mount support hardware with ease and hence enhance on-site workability. CONSTITUTION:An eaves soffit hanger hardware 26 which is used as a support hardware for an eaves soffit material 25 is clamped between beams 27 and 30 on one end and mounted to a building while a wall side edge of the eaves soffit material 25 is supported on the other end. Since the eaves soffit hanger hardware 26 is mounted to the building side, mounting work can be carried out on a building unit 2 or from the side. Furthermore, there is no need to mount the support hardware to the lower side of a roof panel 10 in an upward posture in order to mount to the roof panel 10, which makes it possible to mount easily and hence enhance workability on site.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、軒天井材の支持具に係
り、特にユニット式建物や鉄骨軸組建物等において屋根
パネルで構成される屋根に利用できる。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a support member for eaves ceiling material, and in particular, it can be used for a roof composed of roof panels in a unit type building or a steel frame building.

【0002】[0002]

【背景技術】従来より、ユニット式建物や鉄骨軸組建物
等において複数の屋根パネルで屋根を構成するパネル工
法の屋根が知られている。このパネル工法の屋根におけ
る軒天井材の取付けは、図8に示されるように、軽量気
泡コンクリートパネル製の外壁80に軒天井材81の端
部を取付けることが難しいため、建設現場において屋根
パネル82を設置した後、そのフレーム83に吊り具8
4を介して取付けていた。
BACKGROUND ART Conventionally, a roof of a panel construction method is known in which a roof is composed of a plurality of roof panels in a unit-type building, a steel frame building, or the like. As shown in FIG. 8, it is difficult to attach the eaves ceiling material to the roof of this panel construction method because it is difficult to attach the end portion of the eaves ceiling material 81 to the outer wall 80 made of a lightweight cellular concrete panel. After installing the
It was attached via 4.

【0003】[0003]

【発明が解決しようとする課題】しかしながら、このよ
うな従来の軒天井材81の取付構造では、吊り具84を
屋根パネル82の設置後に屋根の下側から取付けなけれ
ばならず、つまり作業者は吊り具84の取付作業を上向
きで行わなければならず、現場作業が煩雑となって作業
性が低下するという問題があった。
However, in such a conventional structure for mounting the eaves ceiling material 81, the suspenders 84 must be mounted from the underside of the roof after the roof panel 82 is installed, that is, the worker. There has been a problem that the work of attaching the hangings 84 must be performed upwards, which complicates the site work and reduces workability.

【0004】本発明の目的は、取付作業を容易にできて
建設現場での作業性を向上できる軒天井材の支持具を提
供することにある。
An object of the present invention is to provide a support member for an eaves ceiling material, which can be easily mounted and improved in workability at a construction site.

【0005】[0005]

【課題を解決するための手段】本発明は、屋根パネルで
構成される屋根の軒天井材の壁側端部を支持する支持具
であって、一端側が建物の躯体や外壁等の躯体側に固定
され、他端側で軒天井材の壁側端部を支持することを特
徴とするものである。この際、建物がユニット式建物の
場合には、軒天井材の支持具の一端側を建設現場で設置
される上下の躯体間、例えばボックス状の建物ユニット
の天井梁や柱上端と、その建物ユニット上に載置される
屋根ユニットや屋根パネルの床梁や柱下端との間に挟持
することが好ましい。
DISCLOSURE OF THE INVENTION The present invention is a support tool for supporting the wall side end portion of the eaves ceiling material of a roof composed of roof panels, one end side of which is the body side such as the skeleton or outer wall of a building. It is characterized in that it is fixed and supports the wall-side end of the eaves ceiling material at the other end side. At this time, if the building is a unit-type building, one end of the eaves ceiling material support is installed between the upper and lower skeletons installed at the construction site, for example, a ceiling beam or a pillar upper end of a box-shaped building unit and the building. It is preferable to sandwich the roof unit and the roof panel mounted on the unit between the floor beam and the lower end of the pillar.

【0006】[0006]

【作用】このような本発明では、軒天井材の支持具は、
建物の躯体や外壁等の躯体側に固定され、従来のように
屋根パネルに取付けられないので、建設現場において屋
根パネルを設置する前に取付けることが可能となる。こ
のため、軒天井材の支持具は例えば建物ユニットの上面
や側面からの作業等で取付けることができ、作業者は従
来のように上向き作業を行う必要がないために建設現場
作業が簡単となって作業性も向上する。この後、軒天井
材の壁側を支持具に取付けるとともに、軒先側を屋根パ
ネルの軒先部分等に固定することで軒天井材は取付けら
れる。
In the present invention as described above, the support member for the eaves ceiling material is
Since it is fixed to the frame side of the building or the outer wall of the building and cannot be attached to the roof panel as in the past, it is possible to attach it before installing the roof panel at the construction site. Therefore, the support member for the eaves ceiling material can be attached by, for example, work from the top surface or side surface of the building unit, and the worker does not need to perform the upward work as in the past, which simplifies the construction site work. Workability is also improved. Then, the eaves ceiling material is attached by attaching the wall side of the eaves ceiling material to the support and fixing the eaves side to the eaves portion of the roof panel or the like.

【0007】[0007]

【実施例】以下、本発明の一実施例を図面に基づいて説
明する。図1に示すように、本実施例が適用されるユニ
ット式建物1は、ボックス状の建物ユニット2を複数組
み合わせることで居室部分が構成され、この建物ユニッ
ト2の上には鉄骨軸組による小屋組3が設けられてい
る。小屋組3は、束4、棟木5、母屋6、登り梁7、隅
木8等の鉄骨下地材を建物ユニット2上で接合すること
で構成される。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the present invention will be described below with reference to the drawings. As shown in FIG. 1, a unit-type building 1 to which the present embodiment is applied has a room portion formed by combining a plurality of box-shaped building units 2. On top of the building unit 2, a shed made of a steel framework is provided. Set 3 is provided. The shed group 3 is configured by joining steel-frame base materials such as a bundle 4, purlins 5, purlins 6, climbing beams 7, corner trees 8 on the building unit 2.

【0008】小屋組3の上には複数の屋根パネル10が
設置され、寄棟屋根を構成している。屋根パネル10
は、図2に示すように、チャンネル材で枠組みされたフ
レーム11の上面に野地板12を貼り、この野地板12
の上に図示しない防水シートおよび水切り13を介して
屋根仕上材14を貼ることで構成される。
A plurality of roof panels 10 are installed on the roof 3 to form a dormitory roof. Roof panel 10
As shown in FIG. 2, a field plate 12 is attached to the upper surface of a frame 11 framed by channel material.
The roof finishing material 14 is attached to the above with a waterproof sheet and a drainer 13 not shown.

【0009】屋根パネル10の軒先端縁近くの野地板1
2は、軒先端縁に沿って切欠かれ、図3にも示すように
この切欠き部分に内樋15が取付けられている。内樋1
5は、塩化ビニルで被覆された鋼板等により成形され、
野地板12に合わせて傾斜されたフランジ部分を野地板
12に固定することで取付けられている。また、内樋1
5の端部は、屋根パネル10の側端縁近くで端板16に
より仕切られ、各屋根パネル10毎に独立して形成され
ている。
Base plate 1 near the edge of the eaves of the roof panel 10
2 is cut out along the edge of the eaves, and the inner gutter 15 is attached to this cutout portion as shown in FIG. Uchigu 1
5 is formed by a steel plate or the like coated with vinyl chloride,
It is attached by fixing the flange part inclined according to the base plate 12 to the base plate 12. Also, the inner gutter 1
The end of 5 is partitioned by the end plate 16 near the side edge of the roof panel 10, and is independently formed for each roof panel 10.

【0010】内樋15の底面15Aは、図4,5に示す
ように、一方の端板16から他方の端板16に向かって
下る水勾配が付けられている。この水勾配の下流側の端
部には、図2にも示すように、内樋15内の雨水を排水
する排水管17が設けられている。排水管17は、図2
にも示すように、内樋15内に設けられたストレーナー
18にエルボー19、呼び樋20等を介して縦樋21を
接続して構成され、図4に示すように各屋根パネル10
の内樋15毎に設けられたり、図5に示すように隣接す
る屋根パネル10の内樋15同士を枝管22を介して連
結して2つ以上の屋根パネル10毎に1つの排水管17
を設けてもよい。
As shown in FIGS. 4 and 5, the bottom surface 15A of the inner gutter 15 is provided with a water gradient descending from one end plate 16 toward the other end plate 16. As shown in FIG. 2, a drain pipe 17 for draining rainwater in the inner gutter 15 is provided at the downstream end of the water gradient. The drain pipe 17 is shown in FIG.
As shown in FIG. 4, a vertical gutter 21 is connected to a strainer 18 provided in the inner gutter 15 via an elbow 19, a calling gutter 20 and the like, and as shown in FIG.
The inner gutter 15 is provided for each inner gutter 15 or, as shown in FIG. 5, the inner gutters 15 of the adjacent roof panels 10 are connected to each other through a branch pipe 22, and one drain pipe 17 is provided for each two or more roof panels 10.
May be provided.

【0011】屋根パネル10の軒先端縁には、図2に示
すように、軒先部分をカバーする軒先化粧材23が取付
けられている。化粧材23は、内樋15と同様に、塩化
ビニル被覆された鋼板等で構成され、その一端が内樋1
5の内面に係止され、他端が軒先のフレーム11に固定
された受材24に固定されることで取付けられている。
As shown in FIG. 2, an eaves-end cosmetic material 23 for covering the eaves-end portion is attached to the edge of the eaves of the roof panel 10. Like the inner gutter 15, the decorative material 23 is made of a vinyl chloride-coated steel plate or the like, and one end thereof has a inner gutter 1
It is attached by being locked to the inner surface of 5 and the other end being fixed to the receiving member 24 fixed to the frame 11 at the eaves tip.

【0012】屋根パネル10の軒先部分の下方には軒天
井材25が取付けられている。軒天井材25は、塩化ビ
ニルで被覆された鋼板等を折板加工する等で成形され、
軒先側の端縁は軒先化粧材23を介して受材24に釘止
めなどで固定され、壁側の端縁は本発明の軒天井材の支
持具である軒天吊り金物26に固定されている。
An eave ceiling material 25 is attached below the eaves portion of the roof panel 10. The eaves ceiling material 25 is formed by folding a steel plate or the like coated with vinyl chloride,
The edge on the eaves side is fixed to the receiving material 24 via the eaves-edge decorative material 23 by nailing or the like, and the edge on the wall side is fixed to the eaves ceiling hanging hardware 26 which is a support for the eaves ceiling material of the present invention. There is.

【0013】軒天吊り金物26は、図2に示すように、
側断面が略逆L字形に形成され、その一端は例えば2階
建の建物の場合、2階を構成する建物ユニットの天井梁
27に係止されるように折曲されている。また、他端に
は2つのフランジ26A,26Bが形成され、軒天井材
25を挟持して固定可能に構成されている。フランジ2
6Aには排水管17を固定するためのつかみ金具28が
固定されている。軒天吊り金物26は、2階の建物ユニ
ット上に設置される屋根床パネル29の梁30と2階の
天井梁27とで挟持されて固定され、2階の外壁パネル
31に沿って延設されている。
The eaves ceiling hanging hardware 26, as shown in FIG.
The side cross section is formed in a substantially inverted L shape, and one end thereof is bent so as to be locked by a ceiling beam 27 of a building unit constituting the second floor in the case of a two-story building, for example. Further, two flanges 26A and 26B are formed at the other end so that the eaves ceiling material 25 can be sandwiched and fixed. Flange 2
A holding metal fitting 28 for fixing the drainage pipe 17 is fixed to 6A. The eaves ceiling hanging hardware 26 is clamped and fixed by a beam 30 of a roof floor panel 29 installed on a building unit on the second floor and a ceiling beam 27 on the second floor, and extended along an outer wall panel 31 on the second floor. Has been done.

【0014】一方、隣接して配置される屋根パネル10
のジョイント部分には、図3に示すように、雨垂れ防止
具32が設けられている。雨垂れ防止具32は、図6,
7に示すように、1枚のプレートを2つの隅部32A,
32Bに向かって傾斜するように折曲し、かつ隅部32
A,32B間に立上がり部33を設けて構成される。ま
た、雨垂れ防止具32の隅部32A,32B側の側面
は、下方に折曲されて水切り34が形成されている。こ
の雨垂れ防止具32は、屋根パネル10のジョイント部
において、野地板12および屋根仕上材14間に挿入さ
れており、屋根パネル10のジョイント部つまり内樋1
5が設けられていない部分を流れる雨水等を、隣接する
屋根パネル10の各内樋15に振り分けて流すように構
成されている。
On the other hand, the roof panel 10 arranged adjacently
As shown in FIG. 3, a raindrop preventive tool 32 is provided at the joint portion of. The raindrop prevention tool 32 is shown in FIG.
As shown in FIG. 7, one plate is attached to two corners 32A,
32B, and the corner 32
A rising portion 33 is provided between A and 32B. Further, the side surfaces of the raindrop prevention tool 32 on the corners 32A and 32B side are bent downward to form drainers 34. The raindrop prevention tool 32 is inserted between the roof plate 12 and the roof finishing material 14 at the joint portion of the roof panel 10, and the joint portion of the roof panel 10, that is, the inner gutter 1
It is configured such that rainwater or the like that flows through a portion where 5 is not provided is distributed to each inner gutter 15 of the adjacent roof panel 10 and flows.

【0015】このような本実施例においては、工場にお
いて予め建物ユニット2および屋根パネル10を制作し
ておく。屋根パネル10には、予め内樋15や軒先化粧
板23等も取付けておく。次いで、これらの建物ユニッ
ト2、屋根パネル10および小屋組3を構成する束4や
母屋6等を建設現場に輸送する。この際、屋根パネル1
0はトラックに積み重ねて輸送でき、屋根ユニットのよ
うに嵩張らないので従来に比べて輸送に必要なトラック
の台数を少なくできる。
In this embodiment, the building unit 2 and the roof panel 10 are manufactured in advance in the factory. An inner gutter 15 and an eaves decorative plate 23 are attached to the roof panel 10 in advance. Next, the building unit 2, the roof panel 10, and the bundle 4 and the purlin 6 that form the shed 3 are transported to the construction site. At this time, roof panel 1
No. 0 can be transported by stacking it on a truck and is not bulky like a roof unit, so the number of trucks required for transportation can be reduced compared to the conventional case.

【0016】建設現場では、建物ユニット2を組み合わ
せて居室部を構成し、この居室部の上に束4等で小屋組
3を構成する。なお、軒天吊り金物26は建物ユニット
2の設置後、軒天吊り金物26の一端の折曲部を天井梁
27に係止し、その上に屋根床パネル29を設置するこ
とで梁27,30で挟持され、小屋組3の構成前に取付
けられる。次に、小屋組3の上に屋根パネル10を順次
設置して寄棟屋根を構成する。この屋根パネル10の設
置により内樋15の設置も自動的に完了する。その後、
屋根パネル10に屋根仕上材14を取付けるとともに、
ジョイント部の必要箇所にコーキング等で防水処理を行
う。さらに、屋根パネル10のジョイント部に雨垂れ防
止具32を取付けて屋根面の仕上げ作業を完了する。
At a construction site, a building unit 2 is combined to form a living room, and a shed assembly 3 is formed on the living room by a bundle 4 and the like. In addition, after the building unit 2 is installed, the eaves ceiling hanging metal fitting 26 locks the bent portion at one end of the eaves ceiling hanging hardware 26 to the ceiling beam 27, and installs the roof floor panel 29 on the ceiling beam 27, so that the beam 27, It is sandwiched by 30 and attached before the construction of the shed assembly 3. Next, the roof panels 10 are sequentially installed on the shed assembly 3 to form a dormitory roof. The installation of the roof panel 10 automatically completes the installation of the inner gutter 15. afterwards,
While attaching the roof finishing material 14 to the roof panel 10,
Waterproof the joints where necessary by caulking. Further, the raindrop prevention tool 32 is attached to the joint portion of the roof panel 10 to complete the roof surface finishing work.

【0017】次に、軒先部分の排水管17の接続等を開
口されている軒天部分から行い、軒天井材25を軒天吊
り金物26および軒先化粧材23を介して取付けて軒先
部分の仕上げ作業を行い、これによりユニット式建物1
の屋根が完成する。
Next, the connection of the drainage pipe 17 of the eaves portion is performed from the eaves ceiling portion that is opened, and the eaves ceiling material 25 is attached via the eaves ceiling hanging metal fittings 26 and the eaves ornamental material 23 to finish the eaves portion. Work is done, which results in a unitary building 1
Roof is completed.

【0018】このような本実施例によれば、次のような
効果がある。すなわち、軒天井材25の壁側端部を建物
ユニット2の躯体である梁27,30に取付けられた軒
天吊り金物26で支持し、軒先側を屋根パネル10の受
材24に取付けているので、従来のように建設現場で屋
根パネル10に軒天井材25の吊り具を取付ける必要が
なく、現場の作業性を向上できる。特に、軒天吊り金物
26は、建物ユニット2の梁27,30側に取付けられ
るため、屋根パネル10の設置前に取付けることがで
き、かつ例えば建物ユニット2の天井パネル上に作業者
がのって建物ユニット2の上面から取付けることもで
き、あるいは足場等にのって建物ユニット2の側面から
取付けることもできるため、従来の吊り具のように上向
き作業をしないで取付けることができて作業性をより向
上できる。
According to this embodiment, the following effects can be obtained. That is, the wall-side end of the eaves ceiling material 25 is supported by the eaves ceiling hanging hardware 26 attached to the beams 27 and 30 which are the frame of the building unit 2, and the eaves side is attached to the receiving material 24 of the roof panel 10. Therefore, unlike the conventional case, it is not necessary to attach a suspender for the eaves ceiling material 25 to the roof panel 10 at the construction site, and the workability at the site can be improved. In particular, since the eaves-mounting hardware 26 is attached to the beams 27, 30 side of the building unit 2, it can be attached before the installation of the roof panel 10 and, for example, an operator can mount it on the ceiling panel of the building unit 2. Can be installed from the top of the building unit 2 or from the side of the building unit 2 on a scaffolding, etc., so that it can be installed without the upward work as in the conventional hanging equipment, and workability is improved. Can be further improved.

【0019】また、軒天吊り金物26は、建物ユニット
2の天井梁27および屋根床パネル29の梁30で挟持
して固定しており、吊り金物26をボルト止めや溶接等
で建物ユニット2側に取付ける必要がないため、現場作
業をより簡易にできて作業性をより向上できる。
Further, the eaves ceiling hanging hardware 26 is clamped and fixed by the ceiling beam 27 of the building unit 2 and the beam 30 of the roof floor panel 29, and the hanging hardware 26 is bolted or welded to the building unit 2 side. Since it is not necessary to mount it on the work site, work at the site can be simplified and workability can be further improved.

【0020】さらに、軒天吊り金物26にフランジ26
A,26Bを形成し、軒天井材25の壁側端縁をフラン
ジ26A,26B間で挟んで支持するように構成してい
るため、軒天井材25の壁側端縁をフランジ26A,2
6B間に挿入し、軒先側端縁を屋根パネル10の化粧材
23、受材24に接着剤や釘等で固定するだけで、軒天
井材25を簡単に取付けることができて作業性をより向
上できる。
Further, the eaves ceiling hanging hardware 26 is provided with a flange 26.
A and 26B are formed, and the wall-side edge of the eaves ceiling material 25 is configured to be sandwiched between the flanges 26A and 26B to be supported, so that the wall-side edge of the eaves ceiling material 25 is formed into the flanges 26A and 2B.
It is possible to easily attach the eaves ceiling material 25 by inserting it between the 6Bs and fixing the edge of the eaves side to the decorative material 23 and the receiving material 24 of the roof panel 10 with an adhesive or nails. Can be improved.

【0021】また、軒天吊り金物26のフランジ26A
に排水管17のつかみ金物28を固定できるように構成
したので、つかみ金物28の取付けが簡単にできて排水
管17の納まりを良好にできる。
Further, the flange 26A of the eaves-mounting hardware 26
Since the gripping piece 28 of the drainage pipe 17 can be fixed, the gripping piece 28 can be easily attached and the drainage pipe 17 can be stored in a good condition.

【0022】さらに、軒天吊り金物26は略逆L字形に
形成され、外壁パネル31の上面および側面に沿って設
けられており、軒天井材25の壁側端縁は外壁パネル3
1の側面部分に設けられているので、軒先部分の防水を
確実なものにできる。すなわち、軒天井材25の壁側端
縁はフランジ26A,26Bに挟持されているので雨水
等が侵入する虞れは少なく確実な防水が行え、かつ軒天
吊り金物26と外壁パネル31との間に雨水が侵入して
も、外壁31に沿って上方まで移動しなければ建物ユニ
ット2内まで侵入できないので、この部分の防水も確実
である。また、外壁パネル31を建物ユニット2の上端
面まで設けることができるので、耐火性能を向上できる
とともに、1階用の建物ユニット2と同じ外壁パネル3
1や梁27を用いることができて建物ユニット2の生産
性も向上できる。
Further, the eaves ceiling hanging hardware 26 is formed in a substantially inverted L shape and is provided along the upper surface and the side surface of the outer wall panel 31, and the wall side edge of the eaves ceiling material 25 is the outer wall panel 3.
Since it is provided on the side surface portion of 1, the eaves portion can be reliably waterproofed. That is, since the wall-side edge of the eaves ceiling material 25 is sandwiched between the flanges 26A and 26B, there is little risk that rainwater or the like will enter, and reliable waterproofing can be performed, and between the eaves ceiling mount hardware 26 and the outer wall panel 31. Even if rainwater intrudes into the building unit 2, it cannot enter the building unit 2 unless it moves upward along the outer wall 31, so that this portion is also waterproof. Further, since the outer wall panel 31 can be provided up to the upper end surface of the building unit 2, the fire resistance performance can be improved and the same outer wall panel 3 as the building unit 2 for the first floor can be provided.
1 and the beam 27 can be used, and the productivity of the building unit 2 can be improved.

【0023】また、屋根パネル10に予め内樋15を内
蔵しているので、建設現場では屋根パネル10を設置す
るだけで内樋15の設置も自動的に行われ、従来のよう
に建設現場において屋根パネル10の設置後に樋の設置
作業を行う必要がないため、現場作業が簡易になって作
業性を向上できる。さらに、内樋15を各屋根パネル1
0に工場等で予め取付けているので、内樋15部分の防
水処理を工場で行え、屋根パネル10の防水処理を確実
に行うことができる。特に、内樋15を各屋根パネル1
0毎に独立させているので、各屋根パネル10のジョイ
ント部分で内樋15同士を接続する必要がなく、従来雨
漏りしやすかった樋のジョイント部分が無いため樋15
を確実に防水でき、かつ現場作業も軽減できる。
Further, since the inner gutter 15 is built in the roof panel 10 in advance, the inner gutter 15 is automatically installed only by installing the roof panel 10 at the construction site. Since it is not necessary to perform the installation work of the gutter after the installation of the roof panel 10, the site work is simplified and the workability can be improved. Furthermore, the inner gutter 15 is attached to each roof panel 1
Since it is preliminarily installed at 0 in a factory or the like, the waterproof treatment of the inner gutter 15 portion can be performed in the factory, and the roof panel 10 can be reliably waterproofed. Especially, the inner gutter 15 is attached to each roof panel 1
Since it is independent for each 0, it is not necessary to connect the inner gutters 15 to each other at the joint part of each roof panel 10, and since there is no gutter joint part that was easy to leak rain in the past, the gutter 15
Can be reliably waterproofed, and on-site work can be reduced.

【0024】また、屋根パネル10によって屋根を構成
しているので、屋根ユニットを用いた場合に比べてコス
トを低減できる。特に、屋根ユニットは嵩張るため輸送
費が高いのに対し、屋根パネル10を用いれば積み重ね
て輸送できるため輸送費を著しく低減できる。
Further, since the roof is constituted by the roof panel 10, the cost can be reduced as compared with the case where the roof unit is used. In particular, the roof unit is bulky and therefore expensive to transport, whereas the roof panel 10 can be transported in a stacked manner, which can significantly reduce the transportation cost.

【0025】さらに、屋根パネル10のジョイント部分
に雨垂れ防止具33を設けたので、ジョイント部を流れ
る雨水等を各内樋15に導入でき、ジョイント部の軒先
からの雨垂れを防止することができる。
Further, since the raindrop preventive 33 is provided at the joint portion of the roof panel 10, rainwater flowing through the joint portion can be introduced into each inner gutter 15 and raindrop from the eaves of the joint portion can be prevented.

【0026】なお、本発明は前述の実施例に限定される
ものではなく、本発明の目的を達成できる範囲での変
形、改良等は本発明に含まれるものである。例えば、前
記実施例では、軒天井材25の支持具である軒天吊り金
物26を梁27,30間で挟持して固定していたが、例
えば屋根床パネル29が無い場合等には梁27にボルト
止めや溶接で固定してもよい。また、梁27,30に取
付ける場合に限らず、建物ユニットの図示しない柱の上
面や外壁パネル31の上面にボルト等で固定してもよ
く、要するに本発明は軒天井材の支持具が屋根パネル1
0ではなく、建物の躯体側に取付けられていればよい。
It should be noted that the present invention is not limited to the above-described embodiments, but includes modifications and improvements as long as the object of the present invention can be achieved. For example, in the above-described embodiment, the eaves ceiling hanging hardware 26, which is a support member for the eaves ceiling material 25, is clamped and fixed between the beams 27 and 30, but when the roof floor panel 29 is not provided, the beams 27 are used. It may be fixed by bolting or welding. Further, the invention is not limited to the case where the beams are attached to the beams 27 and 30, and may be fixed to the upper surface of the pillar (not shown) of the building unit or the upper surface of the outer wall panel 31 with bolts or the like. 1
Instead of 0, it may be attached to the building side of the building.

【0027】また、軒天井材25の支持具としては前記
実施例の軒天吊り金物26に限らず、例えば、ピース状
に形成された軒天吊り金物を所定間隔で複数配置して軒
天井材25を支持してもよいし、前記実施例の軒天吊り
金物26のフランジ26A,26Bに相当する軒天井材
25を保持するコ字形の保持具と梁27,30に固定さ
れる側面L字形の支持具とを別部材とし、保持具を軒天
井材25に沿って連続する長尺物で形成し、この保持具
を適宜な受材等を介して所定間隔で配置された複数の支
持具で支持するように構成された軒天吊り金物で軒天井
材25を支持してもよく、その形状、材質等の具体的構
成は軒天井材の支持具を取付ける部位の形状等に応じて
適宜設定すればよい。さらに、軒天井材25の支持構造
も前記実施例のようにフランジ26A,26B間に挟む
構造のものに限らず、例えばフランジを1つだけ設け、
釘等で固定するようにしてもよく、実施にあたって適宜
設定すればよい。
Further, the support member for the eaves ceiling material 25 is not limited to the eaves ceiling hanging hardware 26 of the above-mentioned embodiment, and for example, a plurality of pieces of the eaves ceiling hanging hardware are arranged at a predetermined interval and the eaves ceiling material is provided. 25 may be supported, or a side-face L-shape fixed to the U-shaped holder for holding the eaves ceiling material 25 corresponding to the flanges 26A and 26B of the eaves ceiling hanging hardware 26 and the beams 27 and 30. Is a separate member, and the holder is formed of a continuous long object along the eaves ceiling material 25, and a plurality of the holders are arranged at predetermined intervals via appropriate receiving members or the like. The eaves ceiling material 25 may be supported by an eaves ceiling hanging hardware, and the specific configuration such as the shape and the material thereof may be appropriately changed according to the shape of the portion to which the eaves ceiling material support is attached. Just set it. Further, the supporting structure of the eaves ceiling material 25 is not limited to the structure of sandwiching between the flanges 26A and 26B as in the above-mentioned embodiment, and for example, only one flange is provided,
It may be fixed with nails or the like, and may be set appropriately for implementation.

【0028】また、本発明の軒天井材の支持具は、前記
実施例のような寄棟屋根の軒天井材を支持するものに限
らず、切妻屋根、入り母屋屋根、片流れ屋根等の種々の
形状の屋根の軒天井材の支持に広く利用できる。さら
に、本発明が用いられる建物は前記実施例のように建物
ユニット2等で構成されるユニット式建物1に限らず、
鉄骨軸組等で構成される建物等でもよい。
Further, the support member for eaves ceiling material of the present invention is not limited to the one for supporting the eaves ceiling material of the dormitory roof as in the above-mentioned embodiment, but various types of gable roofs, entrance purlin roofs, one-way roofs, etc. It can be widely used for supporting eaves ceiling material of shaped roof. Furthermore, the building in which the present invention is used is not limited to the unit type building 1 including the building unit 2 and the like as in the above-mentioned embodiment,
A building or the like composed of a steel frame or the like may be used.

【0029】[0029]

【発明の効果】以上に述べたように、本発明の軒天井材
の支持具によれば、その取付作業を容易にできて建設現
場での作業性を向上できるという効果がある。
As described above, according to the support member for eaves ceiling material of the present invention, there is an effect that the mounting work can be facilitated and the workability at the construction site can be improved.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の一実施例が用いられるユニット式建物
を示す概略斜視図である。
FIG. 1 is a schematic perspective view showing a unit-type building in which an embodiment of the present invention is used.

【図2】本実施例の軒天井材の支持具が用いられた屋根
の軒先部分を示す断面図である。
FIG. 2 is a cross-sectional view showing an eaves tip portion of a roof using a support member for an eaves ceiling material according to the present embodiment.

【図3】本実施例の軒天井材の支持具が用いられた屋根
の軒先部分を示す斜視図である。
FIG. 3 is a perspective view showing an eaves tip portion of a roof using the support member for the eaves ceiling material of the present embodiment.

【図4】屋根パネルの内樋の排水構造を示す概略側面図
である。
FIG. 4 is a schematic side view showing a drainage structure of an inner gutter of a roof panel.

【図5】屋根パネルの内樋の他の排水構造を示す概略側
面図である。
FIG. 5 is a schematic side view showing another drainage structure of the inner gutter of the roof panel.

【図6】屋根の雨垂れ防止具を示す斜視図である。FIG. 6 is a perspective view showing a raindrop prevention tool for a roof.

【図7】屋根パネルのジョイント部分を示す側面図であ
る。
FIG. 7 is a side view showing a joint portion of the roof panel.

【図8】本発明の従来例を示す概略側面図である。FIG. 8 is a schematic side view showing a conventional example of the present invention.

【符号の説明】[Explanation of symbols]

1 ユニット式建物 2 建物ユニット 10 屋根パネル 25 軒天井材 26 軒天井材の支持具である軒天吊り金物 27 天井梁 29 屋根床パネル 30 梁 31 外壁パネル 1 unit type building 2 building unit 10 roof panel 25 eaves ceiling material 26 eaves eaves hanging fixture which is a support for ceiling material 27 ceiling beam 29 roof floor panel 30 beam 31 outer wall panel

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 屋根パネルで構成される屋根の軒天井材
の壁側端部を支持する支持具であって、一端側が建物の
躯体側に固定され、他端側で軒天井材の壁側端部を支持
することを特徴とする軒天井材の支持具。
1. A support tool for supporting a wall-side end portion of an eaves ceiling material of a roof composed of roof panels, one end side of which is fixed to a skeleton side of a building, and the other end side thereof is a wall side of the eaves ceiling material. A support member for eaves ceiling material, which is characterized by supporting end portions.
【請求項2】 一端側がユニット式建物の建設現場で設
置される上下の躯体間に挟持されて固定されたことを特
徴とする請求項1記載の軒天井材の支持具。
2. A support member for eaves ceiling material according to claim 1, wherein one end side is clamped and fixed between upper and lower skeletons installed at a construction site of a unit type building.
JP4120691A 1992-05-13 1992-05-13 Eave ceiling material support structure Expired - Lifetime JP2688305B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP4120691A JP2688305B2 (en) 1992-05-13 1992-05-13 Eave ceiling material support structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP4120691A JP2688305B2 (en) 1992-05-13 1992-05-13 Eave ceiling material support structure

Publications (2)

Publication Number Publication Date
JPH0642100A true JPH0642100A (en) 1994-02-15
JP2688305B2 JP2688305B2 (en) 1997-12-10

Family

ID=14792580

Family Applications (1)

Application Number Title Priority Date Filing Date
JP4120691A Expired - Lifetime JP2688305B2 (en) 1992-05-13 1992-05-13 Eave ceiling material support structure

Country Status (1)

Country Link
JP (1) JP2688305B2 (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5141224A (en) * 1974-10-02 1976-04-07 Nat Jutaku Kenzai
JPS5186374A (en) * 1975-01-27 1976-07-28 Mitsubishi Electric Corp HANDOTAISOCHINOHYOMENSHORIHOHO
JPS5511645A (en) * 1978-07-11 1980-01-26 Mitsubishi Electric Corp Pickup device
JPS5615940U (en) * 1979-07-17 1981-02-12
JPS5796318A (en) * 1980-12-05 1982-06-15 Olympus Optical Co Ltd Automatic exposure control device of ttl direct photometric camera
JPS59121702A (en) * 1982-12-28 1984-07-13 三菱電機株式会社 Discharge lamp unit
JPH02304152A (en) * 1989-05-18 1990-12-17 Sekisui House Ltd Roof panel fitted with eaves back cradling

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5141224A (en) * 1974-10-02 1976-04-07 Nat Jutaku Kenzai
JPS5186374A (en) * 1975-01-27 1976-07-28 Mitsubishi Electric Corp HANDOTAISOCHINOHYOMENSHORIHOHO
JPS5511645A (en) * 1978-07-11 1980-01-26 Mitsubishi Electric Corp Pickup device
JPS5615940U (en) * 1979-07-17 1981-02-12
JPS5796318A (en) * 1980-12-05 1982-06-15 Olympus Optical Co Ltd Automatic exposure control device of ttl direct photometric camera
JPS59121702A (en) * 1982-12-28 1984-07-13 三菱電機株式会社 Discharge lamp unit
JPH02304152A (en) * 1989-05-18 1990-12-17 Sekisui House Ltd Roof panel fitted with eaves back cradling

Also Published As

Publication number Publication date
JP2688305B2 (en) 1997-12-10

Similar Documents

Publication Publication Date Title
JP2688305B2 (en) Eave ceiling material support structure
JP2608360B2 (en) Roof panel
JP2688306B2 (en) Roof eaves ceiling
JPH0623622Y2 (en) Domer mounting structure
JP2557161B2 (en) Roof unit with parapet
JPH0622439U (en) Raindrop prevention equipment
JP2018090995A (en) Water proof structure of outer wall
JPS63284344A (en) Roof panel
JPH0755267Y2 (en) Door roof structure
JPH054489Y2 (en)
JP2549041B2 (en) Panel assembly structure and assembly method
JP3220084B2 (en) Eaves structure of thatched roof
JPH10169073A (en) Unit type metallic tile roof, unit type metallic tile roof set and construction method
JPH11293838A (en) Roof balcony of unitized building
JP2593062Y2 (en) Balcony with gutter
JP2004285577A (en) Knockdown house
JPH0642102A (en) Method for constructing eave ceiling of panel type roof
KR860000031Y1 (en) Prefabricated camp
JPH034644Y2 (en)
JP2721491B2 (en) Handrail
JPH05133046A (en) Roof panel for building
JPH08260635A (en) Drainage structure of building
JPH04371643A (en) Roof structure
JPH06322815A (en) Structure of balcony for house
JPH0642059A (en) Joint structure of unit with parapet

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 19970722