JPH0635981A - Drawing data managing method - Google Patents

Drawing data managing method

Info

Publication number
JPH0635981A
JPH0635981A JP4214749A JP21474992A JPH0635981A JP H0635981 A JPH0635981 A JP H0635981A JP 4214749 A JP4214749 A JP 4214749A JP 21474992 A JP21474992 A JP 21474992A JP H0635981 A JPH0635981 A JP H0635981A
Authority
JP
Japan
Prior art keywords
design
data
drawing data
update
master
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP4214749A
Other languages
Japanese (ja)
Other versions
JP2851489B2 (en
Inventor
Haruaki Yajima
春秋 矢島
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsubishi Electric Corp
Original Assignee
Mitsubishi Electric Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsubishi Electric Corp filed Critical Mitsubishi Electric Corp
Priority to JP4214749A priority Critical patent/JP2851489B2/en
Publication of JPH0635981A publication Critical patent/JPH0635981A/en
Application granted granted Critical
Publication of JP2851489B2 publication Critical patent/JP2851489B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Processing Or Creating Images (AREA)

Abstract

PURPOSE:To update a drawing without time inconsistency (while being synchronized) by using information showing overlap design at the time of updating the drawing. CONSTITUTION:This method is provided with a master drawing D/B (data base) 1, design drawing D/B 2, drawing update program 3 to update the contents of the master drawing D/B 1 by using design data in the design drawing D/B 2, and process managing data 4 to manage the process of respective plans in the design drawing D/B 2. When the drawing update program 3 is activated, the design data of a drawing update object completed the process are extracted from the design drawing D/B 2, and processing is repeated until the object data are eliminated. Further, new design data are referred to by retrieving the process managing data 4 for the design data of the update object and when the master design data are already updated, the master drawing D/B 1 is updated on the condition that the master design data are already updated. In the other case, the step is repeatedly processed.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】この発明は、コンピュータを用い
て屋外配線工事等に関する図面を管理する図面データ管
理方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a drawing data management method for managing drawings relating to outdoor wiring work and the like using a computer.

【0002】[0002]

【従来の技術】図7は従来の配線工事図面の管理を行う
図面データ管理システムを示す構成図であり、図におい
て、1は一定地域における現在の配線状況を示す図面デ
ータが蓄積されているマスタ図面データベース(以下、
マスタ図面D/Bと言う)、2は上記一定地域内におけ
る工事対象範囲に対して新規に工事を行うための設計図
の設計図データを格納する設計図データベース(以下、
設計図D/Bと言う)である。
2. Description of the Related Art FIG. 7 is a block diagram showing a conventional drawing data management system for managing wiring work drawings. In the drawing, 1 is a master in which drawing data showing a current wiring situation in a certain area is accumulated. Drawing database (hereinafter,
A master drawing D / B), 2 is a design drawing database (hereinafter, referred to as a “design drawing database” that stores design drawing data of a design drawing for newly constructing a construction target area in the above-mentioned certain area.
Design drawing D / B).

【0003】次に動作について説明する。先ず、図7
(a)のようにマスタ図面D/B1から工事対象範囲の
図面データを読み出す。この例では2本の電柱と電線及
び家形が存在している。この図面を元図として同図
(b)に示すような、小柱,引込み線等を追加した設計
図を作成する。次に、同図(c)において、この設計図
を直接参照するか、又は一旦設計図データベース2に格
納されたものを読み出したものを参照して工事請負会社
が工事を行う。工事終了後、その設計図を必要に応じて
修正した後、同図(d)のように設計図D/B2に格納
する。そしてこの格納された設計図を基に工事料金の精
算が行われる。
Next, the operation will be described. First, FIG.
As shown in (a), the drawing data of the construction target range is read from the master drawing D / B1. In this example, there are two utility poles, an electric wire, and a house shape. Using this drawing as the original drawing, a design drawing is added with small columns, service lines, etc., as shown in FIG. Next, in FIG. 2C, the construction contractor carries out the construction by directly referring to this design drawing or by referring to the one that is once stored in the design drawing database 2 and read out. After the construction is completed, the design drawing is corrected as needed and then stored in the design drawing D / B2 as shown in FIG. Then, the construction fee is settled based on the stored design drawing.

【0004】次にマスタ図面D/B1の更新を行う。こ
れは上記設計図から今回の工事で追加した部分のみ、即
ち、同図(a)の上記元図に追加した部分のみを同図
(e)のように抽出し、この部分でマスタ図面D/B1
の対象範囲を更新する。以後は、この更新された図面が
次の設計の際の元図として使用される。このような図面
更新は、図面更新プログラムを用いて、例えば1日1回
定時に、その日に上がった各設計図について行われる。
Next, the master drawing D / B1 is updated. This is because only the part added in this construction from the above-mentioned design drawing, that is, only the part added to the original drawing in FIG. 3A is extracted as shown in FIG. 2E, and the master drawing D / B1
Update the target range of. Thereafter, this updated drawing is used as the original drawing for the next design. Such a drawing update is performed using the drawing update program, for example, once a day at a fixed time for each design drawing that has been posted on that day.

【0005】次に重複設計について図8と共に説明す
る。先ず、同図(a)に示すようにマスタ図面D/B1
から元図を読み出す。次に、同図(b)のように、電柱
と引込み線を追加した設計図を作り、これをA設計(親
設計)として設計図D/B2に格納する。次に同図
(c)のように、(a)の元図と重複する範囲(但し、
座標や縮尺は任意)を読み出し、これに該当する部分を
設計図D/B2から読み出すと、同図(d)のようにA
設計の設計図が得られる。このA設計に対して同図
(e)のように、さらに変圧器と引込み線を追加し、こ
の追加部分をB設計(子設計)として設計図D/B2に
格納する。
Next, overlapping design will be described with reference to FIG. First, as shown in FIG. 3A, the master drawing D / B1
Read the original drawing from. Next, as shown in FIG. 6B, a design drawing to which telephone poles and service lines are added is created, and this is stored in the design drawing D / B2 as the A design (parent design). Next, as shown in (c) of the figure, a range overlapping with the original figure of (a) (however,
(Coordinates and scales are arbitrary), and when the corresponding part is read from the design drawing D / B2, A as shown in FIG.
A blueprint for the design is obtained. A transformer and a lead-in wire are further added to this A design as shown in (e) of the same figure, and this additional portion is stored in the design drawing D / B2 as a B design (child design).

【0006】上記A設計,B設計のような重複設計によ
る工事を行う場合、通常は親設計であるA設計の工事を
完了してから子設計であるB設計の工事を行うが、B設
計の工事が簡単な場合は、B設計の工事が先に完了する
ことがある。このような場合は、B設計に関する図面更
新がA設計より先に行われることになる。
In the case of performing work by overlapping design such as the above-mentioned A design and B design, normally the work of A design which is a parent design is completed and then the work of B design which is a child design is carried out. If the work is simple, the work for design B may be completed first. In such a case, the drawing update for the B design is performed before the A design.

【0007】[0007]

【発明が解決しようとする課題】従来の図面データ管理
方法は以上のように構成されているので、重複設計にお
けるB設計の工事がA設計の工事より先に完了した場合
は、図面マスタD/B1の図面更新を行うとき、B設計
に関する更新が、A設計に関する更新が行われていない
状態で行われる。このため、図8の例では、同図(e)
における変圧器と引込み線が設けられるべき102で示
す電柱がマスタ図面D/B1には存在していないことに
なる。図面更新プログラムは例えば1日1回定時に起動
され、重複設計の工事完了の順序に関しては無関心にプ
ログラムを実行するので、上記の場合は、「存在するは
ずの設備がない」といった異常ケースとして処理され
る。このような場合は、「仮撤去」と呼ばれる処理や
「リカバリ」と呼ばれる処理などの特殊な処理が行われ
るが、1回の更新時間が非常に長くなるという問題点が
あった。
Since the conventional method for managing drawing data is configured as described above, when the work for B design in the overlapping design is completed before the work for A design, the drawing master D / When the drawing of B1 is updated, the update of the B design is performed in the state where the update of the A design is not performed. Therefore, in the example of FIG.
In the master drawing D / B1, the utility pole indicated by 102 where the transformer and the drop wire in FIG. The drawing update program is started once a day, for example, and executes the program indifferently with regard to the order of completion of construction of overlapping designs, so in the above case, it is processed as an abnormal case such as "there is no facility that should exist". To be done. In such a case, a special process such as a process called "temporary removal" or a process called "recovery" is performed, but there is a problem that one update time becomes very long.

【0008】この発明は上記のような問題点を解消する
ためになされたもので、正しい図面更新が可能な図面デ
ータ管理方法を得ることを目的とする。
The present invention has been made to solve the above problems, and an object of the present invention is to obtain a drawing data management method capable of correctly updating a drawing.

【0009】[0009]

【課題を解決するための手段】この発明に係る図面デー
タ管理方法は、設計図データに重複設計部分がある場
合、親設計(又は子設計)の情報を記憶すると共に、子
設計図(又は親設計図)データがマスタ図面D/Bに更
新される時、親設計図(又は子設計図)データがすでに
更新済であるかどうかを示す情報を記憶するようにした
ものである。
A drawing data management method according to the present invention stores information on a parent design (or child design) when a design drawing data has an overlapping design portion, and at the same time, stores a child design drawing (or parent design). When the design drawing data is updated to the master drawing D / B, information indicating whether or not the parent design drawing (or child design drawing) data has already been updated is stored.

【0010】[0010]

【作用】この発明における図面データ管理方法は、時間
的に先に作成された設計図データの内容が、それよりも
後に作成されたものよりも先にマスタ図面D/Bに反映
されるため、正しいマスタ図面D/Bの作成・維持が可
能となる。
In the drawing data management method according to the present invention, the contents of the design drawing data created earlier in time are reflected in the master drawing D / B before those created later. It is possible to create and maintain the correct master drawing D / B.

【0011】[0011]

【実施例】 実施例1.以下、この発明の一実施例を図について説明
する。図1において、1は前述したマスタ図面D/B、
2は同じく設計図D/B、3は設計図D/B2の設計図
データを用いてマスタ図面D/B1の内容を更新する図
面更新プログラム、4は設計図D/B2内の各設計図の
工程を管理する工程管理データである。
EXAMPLES Example 1. An embodiment of the present invention will be described below with reference to the drawings. In FIG. 1, 1 is the master drawing D / B described above,
2 is the same as the design drawing D / B, 3 is the drawing update program for updating the contents of the master drawing D / B1 using the design drawing data of the design drawing D / B2, and 4 is the design drawing of each design drawing in the design drawing D / B2. It is process management data for managing the process.

【0012】表1は工程管理データ4のイメージを示す
ものであり、設計番号に対応して工程情報と各設計図の
設計番号及び各設計の親子関係をテーブル型式で記憶し
ている。上記工程情報には各設計図に対する図面の更新
状況が含まれている。
Table 1 shows an image of the process control data 4, and stores process information corresponding to the design number, the design number of each design drawing, and the parent-child relationship of each design in a table format. The process information includes the update status of the drawing for each design drawing.

【0013】[0013]

【表1】 [Table 1]

【0014】次に動作について説明する。子設計の工程
が終了すると、その設計図データを図面更新プログラム
3を用いてマスタ図面D/B1に反映させる。図2は、
図面更新プログラム3の処理を示すフローチャートであ
る。図2において、ステップST21で図面更新プログ
ラム3を起動するとステップST22で工程が終了とな
った図面更新対象の設計図データを設計図D/B2から
抽出し、ステップST23で対象データが終わるまで処
理をくり返す。ステップST24では更新対象の設計図
データの表1の工程管理データ4を検索して親設計図デ
ータを参照する。ステップST25でその親設計図デー
タが更新済であればステップST26に、そうでなけれ
ばステップST22〜ST25の繰り返し処理に分岐す
る。ステップST26では親設計図データが更新済とい
う条件下で、マスタ図面D/B1の更新が行われる。な
お、従来の図面更新方法と同様、図面更新プログラム3
は毎日定時刻(複数時刻設定可)に起動される。
Next, the operation will be described. When the child design process is completed, the design drawing data is reflected on the master drawing D / B1 using the drawing update program 3. Figure 2
9 is a flowchart showing the processing of the drawing update program 3. In FIG. 2, when the drawing update program 3 is started in step ST21, the drawing update target design drawing data whose process is completed is extracted from the design drawing D / B2 in step ST22, and the process is executed until the target data ends in step ST23. Repeat. In step ST24, the process control data 4 in Table 1 of the design drawing data to be updated is searched to refer to the parent design drawing data. If the parent design drawing data has been updated in step ST25, the process branches to step ST26, and if not, the process repeats to steps ST22 to ST25. In step ST26, the master drawing D / B1 is updated under the condition that the parent design drawing data has been updated. It should be noted that as with the conventional drawing update method, the drawing update program 3
Is activated every day at a fixed time (multiple times can be set).

【0015】実施例2.なお、上記実施例1では、ステ
ップST24,ST25により子設計図データの図面更
新時に親設計図データの更新状況を取得する方法を示し
たが、親設計図データの図面更新時に子設計の工程管理
データに“親設計更新済情報”を登録して判断を行うと
いう方法を用いてもよい。図3においては、構成は図1
と同様であり、符号1〜4はそれぞれ図1と対応してい
るが、図面更新順序が図1とは異なっており、親設計図
データを先に更新することを示している。
Example 2. In the first embodiment, the method of acquiring the update status of the parent design drawing data when updating the drawings of the child design drawing data in steps ST24 and ST25 has been described. A method of registering “parent design updated information” in the data and making a determination may be used. In FIG. 3, the configuration is shown in FIG.
1, the reference numerals 1 to 4 respectively correspond to FIG. 1, but the drawing update order is different from that in FIG. 1 and indicates that the parent design drawing data is updated first.

【0016】図4は図3の図面更新プログラム3の処理
を示すフローチャートである。この処理は基本的な動作
は図2と同じであるが、チェック方法が異なっており、
ステップST44で親設計更新済情報(更新対象設計図
データ中に保持している)によって更新か否かを判定す
るようにしている。親設計更新済情報は、当該設計図デ
ータの親設計図データが更新される時に当該設計図デー
タにセットされるもので、同様に当該設計図データの子
設計図データに対してもステップST45,ST46に
より更新済情報のセットを行う。
FIG. 4 is a flow chart showing the processing of the drawing update program 3 of FIG. The basic operation of this process is the same as in FIG. 2, but the check method is different.
In step ST44, it is determined whether or not the update is based on the parent design update completion information (held in the update target design drawing data). The parent design updated information is set in the design drawing data when the parent design drawing data of the design drawing data is updated, and similarly in step ST45, for the child design drawing data of the design drawing data. The updated information is set in ST46.

【0017】親設計図データに子設計図データの認識を
持たせるために、子設計図データを設計図D/B2に登
録する際、重複する情報を親設計図データに登録しなけ
ればならない。図5は設計図データを登録する時のイメ
ージ図である。5は登録処理プログラムを示す。図6は
図5の登録処理プログラム5を説明したフローチャート
である。
In order to allow the parent design drawing data to recognize the child design drawing data, when registering the child design drawing data in the design drawing D / B2, duplicate information must be registered in the parent design drawing data. FIG. 5 is an image diagram when registering design drawing data. Reference numeral 5 indicates a registration processing program. FIG. 6 is a flowchart explaining the registration processing program 5 of FIG.

【0018】ステップST60で登録処理プログラム5
が起動されると、ステップST61で親設計図データを
用いるか否かが調べられ、用いる場合は、ステップST
62で工程管理データ4の該当する親設計工程管理デー
タに子設計番号等の情報が登録される。次にステップS
T63でその設計図データが設計図D/B2に登録され
た後、ステップST64で終了となる。また、ステップ
ST61で親設計図データを用いない場合は、その設計
図データはそのままステップST63で登録される。
In step ST60, the registration processing program 5
Is started, it is checked in step ST61 whether or not the parent design drawing data is used.
At 62, information such as a child design number is registered in the corresponding parent design process management data of the process management data 4. Then step S
After the design drawing data is registered in the design drawing D / B2 at T63, the process ends at step ST64. When the parent design drawing data is not used in step ST61, the design drawing data is registered as it is in step ST63.

【0019】[0019]

【発明の効果】以上のように、この発明によれば、図面
更新時に重複設計を示す情報を用いるようにしたので、
時間的に矛盾のない(同期のとれた)図面更新が可能と
なり「存在するはずの設備がない」といった異常ケース
を大幅に削減することができる。また、異常ケースを減
少させることにより、図面更新処理の信頼性が向上する
等の効果がある。
As described above, according to the present invention, the information indicating the overlapping design is used when updating the drawing.
Drawing updates that are consistent in time (synchronized) can be performed, and anomalous cases such as "there is no facility that should exist" can be greatly reduced. Further, by reducing the number of abnormal cases, there is an effect that the reliability of the drawing update process is improved.

【図面の簡単な説明】[Brief description of drawings]

【図1】この発明の実施例1を示す構成図である。FIG. 1 is a configuration diagram showing a first embodiment of the present invention.

【図2】この発明の実施例1の動作を示すフローチャー
トである。
FIG. 2 is a flowchart showing the operation of the first embodiment of the present invention.

【図3】この発明の実施例2を示す構成図である。FIG. 3 is a configuration diagram showing a second embodiment of the present invention.

【図4】この発明の実施例2の動作を示すフローチャー
トである。
FIG. 4 is a flowchart showing the operation of the second embodiment of the present invention.

【図5】この発明の実施例2の登録処理プログラムを実
行する場合の構成図である。
FIG. 5 is a configuration diagram for executing a registration processing program according to the second embodiment of the present invention.

【図6】上記登録処理プログラムのフローチャートであ
る。
FIG. 6 is a flowchart of the registration processing program.

【図7】従来の図面データ管理方法を示す構成図であ
る。
FIG. 7 is a configuration diagram showing a conventional drawing data management method.

【図8】重複設計を説明する構成図である。FIG. 8 is a configuration diagram illustrating an overlapping design.

【符号の説明】[Explanation of symbols]

1 マスタ図面データベース 2 設計図データベース 1 Master drawing database 2 Design drawing database

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 マスタ図面データベースから設計対象範
囲の図面データを呼び出し、この図面データに対して設
計を加えて設計図データを作成し、この設計図データを
設計図データベースに格納し、上記設計に応じた工事が
完了した後、上記設計図データにおける上記設計を加え
た部分により上記マスタ図面データベースの内容を更新
する図面データ管理方法において、複数の設計図データ
に重複する部分がある場合に、その重複関係があること
を示す情報と、その重複関係にある設計図データによる
上記図面更新の状況を示す情報とを記憶するようにした
ことを特徴とする図面データ管理方法。
1. A drawing data of a design target range is called from a master drawing database, a design is added to this drawing data to create design drawing data, and the design drawing data is stored in the design drawing database, and the above design is designed. In the drawing data management method that updates the contents of the master drawing database with the part added with the design in the design drawing data after the completion of the corresponding construction, if there are overlapping parts in a plurality of design drawing data, A drawing data management method, characterized in that information indicating that there is an overlapping relationship and information that indicates the status of the drawing update by the design drawing data having the overlapping relationship are stored.
JP4214749A 1992-07-21 1992-07-21 Drawing data management method Expired - Fee Related JP2851489B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP4214749A JP2851489B2 (en) 1992-07-21 1992-07-21 Drawing data management method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP4214749A JP2851489B2 (en) 1992-07-21 1992-07-21 Drawing data management method

Publications (2)

Publication Number Publication Date
JPH0635981A true JPH0635981A (en) 1994-02-10
JP2851489B2 JP2851489B2 (en) 1999-01-27

Family

ID=16660946

Family Applications (1)

Application Number Title Priority Date Filing Date
JP4214749A Expired - Fee Related JP2851489B2 (en) 1992-07-21 1992-07-21 Drawing data management method

Country Status (1)

Country Link
JP (1) JP2851489B2 (en)

Also Published As

Publication number Publication date
JP2851489B2 (en) 1999-01-27

Similar Documents

Publication Publication Date Title
CN114169860A (en) Enterprise organizational structure synchronization method
JPH0635981A (en) Drawing data managing method
CN100499496C (en) A method and device for realization of the configuration transaction and commissioning mechanism
JP2000184595A (en) Display drawing generation management system and storage medium for recording processing program thereof
KR100958927B1 (en) Apparatus and method of AP equipment information synchronizing for AP equipment management system
JPH11213006A (en) Information managing device and its history information managing method
CN116226066B (en) Low code platform code synchronization method and device, electronic equipment and storage medium
CN112463344B (en) Data analysis method and device
US11762875B2 (en) Machine assisted data aggregation
CN112925856B (en) Entity relationship analysis method, entity relationship analysis device, entity relationship analysis equipment and computer storage medium
JP2726743B2 (en) CAD drawing management system
JP2003288429A (en) Garage certificate issuing method, computer program and recording medium with its program recorded
JP2002366589A (en) Design support system
JP2001236211A (en) Distributed system
JPH05242176A (en) Generation control system for drawing
JP2008221918A (en) Work plan assist system, method, and program
JP2003091431A (en) System, method and program for selecting and executing test scenario
JP2925667B2 (en) Process flow creation system
JP3433858B2 (en) Resource management device
CN117827834A (en) Method and system for intelligently analyzing and warehousing JSON format interface based on distributed scheduling
JP2740473B2 (en) Version restoration method
JPH07146787A (en) Method for retrieving influence program
JPH07234809A (en) Data processing method and computer with check skip function
JPH0561743A (en) Automatic updating system between masters
JPH05153236A (en) Automatic settlement system for consistency in station data update

Legal Events

Date Code Title Description
FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20071113

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20081113

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20081113

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091113

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091113

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101113

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111113

Year of fee payment: 13

LAPS Cancellation because of no payment of annual fees