JPH0632465U - Suspension cleat hanging jig - Google Patents

Suspension cleat hanging jig

Info

Publication number
JPH0632465U
JPH0632465U JP6658292U JP6658292U JPH0632465U JP H0632465 U JPH0632465 U JP H0632465U JP 6658292 U JP6658292 U JP 6658292U JP 6658292 U JP6658292 U JP 6658292U JP H0632465 U JPH0632465 U JP H0632465U
Authority
JP
Japan
Prior art keywords
hanging
span
cleats
spancrete
cleat
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP6658292U
Other languages
Japanese (ja)
Inventor
孝司 辻本
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Maeda Corp
Original Assignee
Maeda Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Maeda Corp filed Critical Maeda Corp
Priority to JP6658292U priority Critical patent/JPH0632465U/en
Publication of JPH0632465U publication Critical patent/JPH0632465U/en
Pending legal-status Critical Current

Links

Landscapes

  • Load-Engaging Elements For Cranes (AREA)

Abstract

(57)【要約】 【目的】 スパンクリートの敷設が安全で容易に行える
ようにする。 【構成】 頂板1の下面に、垂下板15を設け、この垂
下板15の側面に、水平方向に突出して、スパンクリー
トの端面に形成された穴に挿入できる棒状体22を設
け、前記頂板1の上面に、吊り下げ用索条を係合できる
吊金具2を取り付けた鋼製のスパンクリート用吊治具。
(57) [Summary] [Purpose] To make spancrete laying safe and easy. [Structure] A hanging plate 15 is provided on the lower surface of the top plate 1, and a bar-shaped body 22 that protrudes in the horizontal direction and can be inserted into a hole formed in an end face of a spancrete is provided on a side surface of the hanging plate 15. A steel spancrete hanging jig with a hanging metal fitting 2 that can engage hanging ropes on the top surface.

Description

【考案の詳細な説明】[Detailed description of the device]

【0001】[0001]

【産業上の利用分野】[Industrial applications]

本考案は、建築物の構築で、合成床版として敷設するスパンクリートの吊り上 げに使用する吊治具に関する。 The present invention relates to a hanging jig used for lifting spancrete laid as a composite floor slab in building construction.

【0002】[0002]

【従来の技術】[Prior art]

従来、スパンクリート30を敷設するには、図5に示すように、スパンクリー ト30に直接ワイヤーを掛けてクレーンで吊り、敷設作業を行っていた。 Conventionally, in laying the span cleats 30, as shown in FIG. 5, a wire is directly hung on the span cleats 30 to be hung by a crane and laid.

【0003】[0003]

【考案が解決しようとする課題】[Problems to be solved by the device]

前記従来のスパンクリート30の敷設作業は、ワイヤーを外す作業が危険であ り、また、ワイヤーを外した後スパンクリート30の側面部33を、その前に敷 設したスパンクリート30の側面部33に密接させるための調整も必要であった 。 In the conventional laying work of the span cleats 30, it is dangerous to remove the wires, and after the wires are removed, the side surface part 33 of the span cleats 30 is brought into close contact with the side surface part 33 of the span cleats 30 laid before it. It was also necessary to make adjustments.

【0004】 本考案は、前記事項に鑑みなされたものであり、スパンクリートの敷設が安全 で容易に行えるようにすることを技術的課題とする。The present invention has been made in view of the above-mentioned matters, and an object thereof is to make span cleats laying safe and easy.

【0005】[0005]

【課題を解決するための手段】[Means for Solving the Problems]

本考案は、前記課題を解決するため、スパンクリートの吊り下げ用の吊治具を 形成し、その吊治具を次に記載する構成のものとした。 In order to solve the above-mentioned problems, the present invention forms a suspension jig for suspending span cleats, and the suspension jig has the structure described below.

【0006】 すなわち、頂板1の下面に、下方に垂下する垂下板15を設け、この垂下板1 5の側面に、水平方向に突出して、スパンクリート30の端面31に形成された 穴32に挿入できる棒状体22を設け、前記頂板1の上面に、吊り下げ用索条を 係合できる吊金具2を取り付けて鋼製のスパンクリート用吊治具とした。That is, a hanging plate 15 that hangs downward is provided on the lower surface of the top plate 1, and the side surface of the hanging plate 15 can be inserted horizontally into the hole 32 formed in the end surface 31 of the span cleat 30. A rod-shaped body 22 was provided, and a hanging metal fitting 2 capable of engaging a hanging rope was attached to the upper surface of the top plate 1 to form a steel spancrete hanging jig.

【0007】[0007]

【作用】 本考案のスパンクリート用吊治具は、図4に示すように、スパンクリート30 の端面31の側面部33寄りの位置の穴32に、スパンクリート用吊治具の棒状 体22を、それぞれ挿入して、スパンクリート用吊治具を、スパンクリート30 の端面31の4箇所に取り付ける。As shown in FIG. 4, the spancrete suspension jig of the present invention is such that the rods 22 of the spanclet suspension jig are inserted into the holes 32 at positions near the side surface 33 of the end face 31 of the spancleat 30. Then, the suspension jigs for span cleats are attached to the end faces 31 of the span cleats 30 at four positions.

【0008】 そして、スパンクリート用吊治具の吊金具2に、索条を係合してクレーンによ り吊り上げる。 そして、前記スパンクリート用吊治具は、スパンクリート30の端面31に取 り付けるので、スパンクリート30の側面部33に索条が存在しない。Then, the rope is engaged with the hanging metal fitting 2 of the hanging jig for spancrete, and the crane is hoisted. Since the span cleat hanging jig is attached to the end surface 31 of the span cleat 30, there is no cord on the side surface portion 33 of the span cleat 30.

【0009】 したがって、スパンクリート30をクレーンの索条で吊り上げた状態で、その スパンクリート30の側面部33を、その前に敷設したスパンクリート30の側 面部33に密接させて敷設することができる。Therefore, with the span cleats 30 suspended by the ropes of the crane, the side surface portion 33 of the span cleats 30 can be laid in close contact with the side surface portion 33 of the span cleats 30 laid in front thereof.

【0010】[0010]

【実施例】【Example】

以下、本考案の実施例の説明をする。図1・図2は、本考案の一実施例を示す ものである。 Hereinafter, an embodiment of the present invention will be described. 1 and 2 show an embodiment of the present invention.

【0011】 この実施例は、幅が200mmで、高さが200mmのH形鋼を、略200m mの長さに切断して本体を形成している。 そして、前記本体の下部板26の両側の側部、及び本体の頂板1の他側部(図 1の右側の側部)を、それぞれ50mmの幅切落し、下部板26の両側の側部、 及び頂板1の他側部を、頂板1の一側部(図1の左側の側部)より幅を狭く形成 している。In this embodiment, an H-section steel having a width of 200 mm and a height of 200 mm is cut into a length of about 200 mm to form a main body. Then, the side portions on both sides of the lower plate 26 of the main body and the other side portion (the side portion on the right side in FIG. 1) of the top plate 1 of the main body are each cut by a width of 50 mm. The width of the other side portion of the top plate 1 is narrower than that of one side portion of the top plate 1 (the side portion on the left side in FIG. 1).

【0012】 H形鋼で形成された本体を、前記の如く加工することによって、頂板1の他側 部寄りの下面に、下方に垂下する垂下板15が設けられ、垂下板15の下端に、 前記頂板1と平行となる下部板26を設けたものが形成される。By processing the main body made of H-shaped steel as described above, a hanging plate 15 that hangs downward is provided on the lower surface near the other side of the top plate 1, and at the lower end of the hanging plate 15, What is provided with a lower plate 26 which is parallel to the top plate 1 is formed.

【0013】 そして、前記の如く形成された垂下板15の一側面に、補強板16が溶接によ り取り付けてあり、この補強板16の中央部よりやや下方寄りの位置には、取り 付け用孔17が設けてある。A reinforcing plate 16 is attached to one side surface of the hanging plate 15 formed as described above by welding. The reinforcing plate 16 is attached at a position slightly lower than the central portion of the reinforcing plate 16. A hole 17 is provided.

【0014】 前記取り付け用孔17には、パイプで形成された棒状体22の基部が嵌入され 、溶接により固着されることにより、前記垂下板15の側面に、垂下板15と直 角で水平方向に突出する棒状体22が設けられる。A base portion of a rod-shaped body 22 formed of a pipe is fitted into the mounting hole 17 and fixed by welding, so that the side surface of the hanging plate 15 is perpendicular to the hanging plate 15 in a horizontal direction. A rod-shaped body 22 that projects to the side is provided.

【0015】 そして、前記パイプで形成された棒状体22は、合成床板として敷設されるコ ンクリート製のスパンクリート30の端面31に形成された穴32に着脱可能に 挿入できる外径に形成されている。The rod-shaped body 22 formed of the pipe is formed to have an outer diameter that can be removably inserted into a hole 32 formed in an end surface 31 of a spancrete 30 made of concrete which is laid as a synthetic floorboard. .

【0016】 さらに、前記頂板1の上面で、前記棒状体22の上方の位置には、吊り下げ用 索条を係合する吊金具2が、前記棒状体22と同一方向に、溶接により固着され ている。Further, on the upper surface of the top plate 1, above the rod-shaped body 22, a suspending metal fitting 2 for engaging a hanging rope is fixed by welding in the same direction as the rod-shaped body 22. ing.

【0017】 また、前記頂板1の一側部には、ねじ孔3が穿設してあり、このねじ孔3には 、止ボルト8がねじ込まれており、この止ボルト8の下端には、水平方向に突出 する押え金具9が設けてある。A screw hole 3 is formed on one side of the top plate 1, and a fixing bolt 8 is screwed into the screw hole 3, and a lower end of the fixing bolt 8 is A holding metal fitting 9 that projects horizontally is provided.

【0018】 次に、前記実施例の使用方法について述べる。前記実施例のスパンクリート用 吊治具は、図4に示すように、スパンクリート30の左右の端面31の両側の側 面部33寄りの位置の穴32に、4個のスパンクリート用吊治具の棒状体22を 、それぞれ挿入する。Next, a method of using the embodiment will be described. As shown in FIG. 4, the suspension jigs for the span cleats of the above-described embodiment are provided with four rod members of the suspension cleats for spun cleats in the holes 32 at positions near the side surface portions 33 on both sides of the left and right end surfaces 31 of the span cleats 30. 22 are respectively inserted.

【0019】 そして、止ボルト8をねじ込んで、止ボルト8の先端に設けた押え金具9で、 スパンクリート30の上面を押さえて、スパンクリート用吊治具を、スパンクリ ートに固定する。Then, the set bolt 8 is screwed in, and the upper surface of the span cleat 30 is pressed by the holding metal fitting 9 provided at the tip of the set bolt 8 to fix the span cleat suspension jig to the span cleat.

【0020】 次に、前記スパンクリート用吊治具の吊金具2に、図4に示すように索条を係 合してクレーンで吊り上げる。 前記スパンクリート用吊治具は、スパンクリート30の端面31に取り付ける ので、スパンクリート30の側面部33には索条が存在しない。Next, as shown in FIG. 4, a rope is engaged with the hanging metal fitting 2 of the hanging jig for the spancrete, and it is lifted by a crane. Since the span cleat hanging jig is attached to the end surface 31 of the span cleat 30, there is no cord on the side surface portion 33 of the span cleat 30.

【0021】 したがって、スパンクリート30をクレーンの索条で吊り上げた状態で、その スパンクリート30の側面部33を、その前に敷設したスパンクリート30の側 面部33に、密接させて敷設することができる。Therefore, in a state in which the span cleats 30 are suspended by the ropes of the crane, the side surface portion 33 of the span cleats 30 can be laid in close contact with the side surface portion 33 of the span cleats 30 laid in front thereof.

【0022】 そして、止ボルト8の押さえ金具9で、スパンクリート30を押さえると、ス パンクリート30をクレーンで吊り上げてないとき、索条やスパンクリート用吊 治具に、他の物が当たっても、スパンクリート用吊治具が、スパンクリート30 から外れない。When the span cleat 30 is pressed by the holding metal 9 of the stop bolt 8, when the span cleat 30 is not lifted by a crane, even if another object hits the rope or the span cleat hanging jig, The spancrete hanging jig does not come off from the spancrete 30.

【0023】 しかしながら、止ボルト8を設けなくても、クレーンによって吊り上げている ときには、スパンクリート用吊治具は、索条によって、棒状体22が、穴32に 挿入される向きに引っ張られているので、スパンクリート用吊治具は外れない。However, even when the stop bolt 8 is not provided, when the hoisting jig for spancrete is pulled by the rope in the direction in which the rod-shaped body 22 is inserted into the hole 32 when hoisting by the crane. , The suspension jig for spancleats cannot be removed.

【0024】 図3は別の実施例を示すものであり、以下さきの実施例と同様の部分は同一の 符号を用い説明を省略した。 この実施例は、スパンクリート用吊治具の垂下板15に、2個の棒状体22を 並列して設けたものである。FIG. 3 shows another embodiment, and the same portions as those in the previous embodiment are designated by the same reference numerals and the description thereof is omitted. In this embodiment, two rod-shaped bodies 22 are provided in parallel on the hanging plate 15 of the spancrete hanging jig.

【0025】 また、前記止ボルト8に設けた押さえ金具9は、円板状に形成してもよい。 さらに、垂下板15を強固なものに形成すれば、下部板26は除くことができ る。Further, the pressing fitting 9 provided on the stop bolt 8 may be formed in a disc shape. Further, if the hanging plate 15 is made strong, the lower plate 26 can be removed.

【0026】[0026]

【考案の効果】[Effect of device]

本考案のスパンクリート用吊治具は、スパンクリート30の端面31に形成さ れた穴32に挿入して取り付けるので、取り付けが容易であり、また吊り上げ時 に、スパンクリート30に取り付けたスパンクリート用吊治具が滑り、スパンク リート30が傾き、或は落下する等の恐れがなく安全である。 Since the spanclet suspension jig of the present invention is inserted into the hole 32 formed in the end surface 31 of the spancleat 30 and mounted, it is easy to mount, and the spanclet suspension jig mounted on the spancleat 30 at the time of lifting. Is safe because there is no risk of slipping, tilting or falling of the spancrete 30.

【0027】 そして、吊り上げ用の索条が、スパンクリート30の側面部33に存在しない ので、スパンクリート30を吊り上げた状態で、そのスパンクリート30の側面 部33を、その前に敷設したスパンクリート30の側面部33に密接させた状態 で吊り降ろすことができ、スパンクリート30を吊り降ろした後に横方向に移動 させて調整する必要もなくなった。Since no rope for lifting is present on the side surface portion 33 of the span cleats 30, the side surface portion 33 of the span cleats 30 is hung in the side surface portion of the span cleats 30 in front of the span cleats 30 in a suspended state. It was possible to hang it in close contact with the 33, and it became unnecessary to move the spancrete 30 after moving it down and adjust it laterally.

【図面の簡単な説明】[Brief description of drawings]

【図1】 本考案の一実施例の側面図FIG. 1 is a side view of an embodiment of the present invention.

【図2】 本考案の一実施例の正面図FIG. 2 is a front view of an embodiment of the present invention.

【図3】 本考案の別の実施例の正面図FIG. 3 is a front view of another embodiment of the present invention.

【図4】 本考案の実施例の使用状態を示す斜視図FIG. 4 is a perspective view showing a usage state of an embodiment of the present invention.

【図5】 従来例の吊り上げ状態を示す斜視図FIG. 5 is a perspective view showing a lifting state of a conventional example.

【符号の説明】[Explanation of symbols]

1…頂板 2…吊金具 15…垂下板 22…棒状体 30…スパンクリート 31…端面 32…穴 DESCRIPTION OF SYMBOLS 1 ... Top plate 2 ... Hanging metal fittings 15 ... Hanging plate 22 ... Rod-shaped body 30 ... Span cleats 31 ... End surface 32 ... Hole

Claims (1)

【実用新案登録請求の範囲】[Scope of utility model registration request] 【請求項1】 頂板1の下面に、下方に垂下する垂下板
15を設け、この垂下板15の側面に、水平方向に突出
して、スパンクリート30の端面31に形成された穴3
2に挿入できる棒状体22を設け、前記頂板1の上面
に、吊り下げ用索条を係合できる吊金具2を取り付けた
鋼製のスパンクリート用吊治具。
1. A hanging plate 15 which hangs downward is provided on a lower surface of the top plate 1, and a side surface of the hanging plate 15 is provided with a hole 3 formed in an end surface 31 of a span cleat 30 so as to project in a horizontal direction.
2. A steel spancrete hanging jig in which a rod-shaped body 22 that can be inserted into 2 is provided, and a hanging metal fitting 2 that can engage a hanging rope is attached to the upper surface of the top plate 1.
JP6658292U 1992-09-24 1992-09-24 Suspension cleat hanging jig Pending JPH0632465U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP6658292U JPH0632465U (en) 1992-09-24 1992-09-24 Suspension cleat hanging jig

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP6658292U JPH0632465U (en) 1992-09-24 1992-09-24 Suspension cleat hanging jig

Publications (1)

Publication Number Publication Date
JPH0632465U true JPH0632465U (en) 1994-04-28

Family

ID=13320098

Family Applications (1)

Application Number Title Priority Date Filing Date
JP6658292U Pending JPH0632465U (en) 1992-09-24 1992-09-24 Suspension cleat hanging jig

Country Status (1)

Country Link
JP (1) JPH0632465U (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3089080B2 (en) * 1992-02-06 2000-09-18 旭化成工業株式会社 Pigment composition

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3089080B2 (en) * 1992-02-06 2000-09-18 旭化成工業株式会社 Pigment composition

Similar Documents

Publication Publication Date Title
JPH08133661A (en) Concrete block lifting means
JPH0632465U (en) Suspension cleat hanging jig
JPH0734069Y2 (en) Lifting device for car or counterweight in elevator
JPS6316705Y2 (en)
JPS636138Y2 (en)
CN210286481U (en) Prefabricated component's transport frock
JPH052744Y2 (en)
JP3092296B2 (en) Concrete large flat plate construction method and the same hanging bracket
JP3004731U (en) Multi-point hanging jig
JPH0585478B2 (en)
JPH0643361Y2 (en) Lifting jig
JPH0674642B2 (en) Jig for suspending wall materials and its usage
JPH04111861U (en) Lifting jig for extruded hollow concrete slab
JP2512649Y2 (en) U-shaped groove suspender
JPH072549Y2 (en) Crane lifting equipment
JPH0714314Y2 (en) Posture adjustment mechanism for crane load
JPH0683686U (en) Floor panel hanger
JPH0748882Y2 (en) Panel hangings
JPH0687493U (en) Concrete floor slab
JPH0444534Y2 (en)
JPH0547178Y2 (en)
JPH06135677A (en) Horizontal suspending-up device for pca plate
JPS61168084U (en)
JPH0329649U (en)
JPH04107773U (en) sling