JPH06259436A - Pre-scheduling system - Google Patents

Pre-scheduling system

Info

Publication number
JPH06259436A
JPH06259436A JP4780993A JP4780993A JPH06259436A JP H06259436 A JPH06259436 A JP H06259436A JP 4780993 A JP4780993 A JP 4780993A JP 4780993 A JP4780993 A JP 4780993A JP H06259436 A JPH06259436 A JP H06259436A
Authority
JP
Japan
Prior art keywords
order
load
production plan
production
adjustment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP4780993A
Other languages
Japanese (ja)
Other versions
JPH07109606B2 (en
Inventor
Toshiharu Aoki
俊晴 青木
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NEC Corp
Original Assignee
NEC Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NEC Corp filed Critical NEC Corp
Priority to JP4780993A priority Critical patent/JPH07109606B2/en
Publication of JPH06259436A publication Critical patent/JPH06259436A/en
Publication of JPH07109606B2 publication Critical patent/JPH07109606B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Abstract

PURPOSE:To provide the pre-scheduling system which can execute efficiently a work by converting plan information used for a production control work to information which can be decide easily by a person, and can adjust easily a load. CONSTITUTION:The inside of the pre-scheduling system 2 for receiving a production plan 7 generated by a preceding production plan generating system 1 is provided with a production plan distributing part 9 for distributing each manufacturing order for constituting the production plan 7, a parts constituting information fetching part 3 for receiving each manufacturing order after the distribution from the production plan distributing part 9, and fetching process procedure information of a final product and parts for constituting it, a similar order collecting part 4 for collecting a similar order, and a heaped order generating part 5 for heaping a load in each process of each order by a time unit, and data of the production plan 7 worked by each part thereof are collected to one, outputted and displayed as an adjustment production plan 8 to a load adjusting system 6, and a person in charge of load adjustment executed the load adjustment.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明はプレスケジューリング方
式に関し、特に生産工場での生産計画作成から製造実施
計画作成にいたる各計画の作成方式の中で、計画の日程
調整と拠点間調整等の負荷調整を行う前段階のデータを
作成するプレスケジューリング方式に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a pre-scheduling method, and particularly, in the method of creating each plan from production plan creation to production execution plan creation in a production factory, the load of plan schedule adjustment and inter-site adjustment. The present invention relates to a pre-scheduling method that creates data at a pre-adjustment stage.

【0002】[0002]

【従来の技術】従来の生産計画と製造実施計画との間に
は、計画の日程調整と拠点間調整等の負荷の調整を行う
前段階のデータを作成するという思想はなく、図5の従
来の生産管理システムのブロック図に示すように、生産
計画作成から製造実施計画作成までの負荷調整を行う際
には、生産計画作成システム100で作成した生産計画
101のデータを、データ構造的にもデータ容量的にも
変更を加えず、直接負荷調整システム102に入力して
負荷調整を行っていた。このため、負荷調整システム1
02では、入力された生産計画のデータを直接負荷の状
態で表示しており、負荷調整担当者が、表示された負荷
の状態をすべて確認しながら、独自の判断で負荷調整を
行うようになっていた。
2. Description of the Related Art Between the conventional production plan and the manufacturing execution plan, there is no idea of preparing data before the load adjustment such as schedule adjustment and inter-site adjustment. As shown in the block diagram of the production management system, the data of the production plan 101 created by the production plan creation system 100 is also used in data structure when the load adjustment from the production plan creation to the production execution plan creation is performed. The load adjustment was performed by directly inputting the load adjustment system 102 without changing the data capacity. Therefore, the load adjustment system 1
In 02, the input production plan data is displayed directly in the load state, and the load adjustment personnel can make the load adjustment by their own judgment while confirming all the displayed load states. Was there.

【0003】[0003]

【発明が解決しようとする課題】上述した従来の従来の
生産管理システムでは、生産計画作成から製造実施計画
作成までの負荷の調整を行う際に、生産計画作成システ
ムが作成した生産計画のデータを直接使用するため、負
荷調整担当者は、部品生産計画と最終製品生産計画の両
方を考慮した負荷調整を行わなければならず、負荷調整
を行う際の考慮項目の増大により、調整時間が増大する
と共に、考慮すべき事項が計画から漏れてしまうことに
より調整品質が悪化するという問題点がある。又、負荷
調整担当者が交替すると、負荷調整時に考慮する項目が
変わることがあり、負荷調整の画一化を保つことができ
ないという問題点もある。又、前述の問題点に鑑み、負
荷調整担当者の負担を減じるため、生産計画作成システ
ムで作成した多くの計画をすべて考慮して負荷の調整を
行うことにすると、部品展開・資材管理等を行っている
情報処理システム全体の負荷が大きくなり、他の処理に
影響を与えることがあり、一方これに使用するハードウ
エアは、処理能力および記憶容量の必要量の大きさか
ら、非常に高価なものになるという問題点がある。
In the conventional production control system of the related art described above, the data of the production plan created by the production plan creation system is used when adjusting the load from the production plan creation to the production execution plan creation. Since it is used directly, the load coordinator must adjust the load in consideration of both the parts production plan and the final product production plan, and the adjustment time increases due to the increase of items to be considered when performing the load adjustment. At the same time, there is a problem that the adjustment quality deteriorates because the matters to be considered are omitted from the plan. In addition, if the load adjustment personnel change, the items to be considered during load adjustment may change, and it is not possible to maintain uniform load adjustment. In consideration of the above-mentioned problems, in order to reduce the load on the person in charge of load adjustment, it is necessary to adjust the load in consideration of many plans created by the production plan creation system. The load on the entire information processing system in operation may be large and may affect other processing, while the hardware used for this is very expensive due to the large amount of processing power and storage capacity required. There is a problem that it becomes a thing.

【0004】本発明の目的は、生産管理業務で使用する
計画情報を、人が容易に判断でき、負荷調整がしやすい
情報に変換することにより、効率的な業務遂行を可能と
するプレスケジューリング方式を提供することにある。
It is an object of the present invention to convert the plan information used in the production management work into information that can be easily judged by a person and whose load can be easily adjusted, so that the pre-scheduling system enables efficient work execution. To provide.

【0005】[0005]

【課題を解決するための手段】本発明のプレスケジュー
リング方式は、前位の生産計画作成システムの作成する
最終製品製造オーダーと、前記最終製品製造オーダーを
作成するために必要な部品を製造する複数の部品製造オ
ーダーとからなる生産計画を受け、予め定める基準に従
って前記複数の部品製造オーダーを分離し、再結合し、
後位の負荷調整システムに適合する調整用生産計画とし
て出力する構成である。
The pre-scheduling method of the present invention is a method for manufacturing a final product manufacturing order created by a preceding production plan creating system and a plurality of parts for manufacturing the final product manufacturing order. Receiving a production plan consisting of parts manufacturing orders, separating and recombining the plurality of parts manufacturing orders according to a predetermined standard,
The configuration is such that it is output as a production plan for adjustment that fits the load adjustment system at the rear stage.

【0006】本発明のプレスケジューリング方式は、生
産計画を形成する複数の部品製造オーダーの分離および
再結合を、前記複数の部品製造オーダーの指示する部品
の製造がすべて完了した時点で最終製品製造オーダーの
指示する製品の製造を開始する工程手順情報を持つ新し
いオーダーを作成する部品構成情報取り込み機能と、前
記複数の部品製造オーダーの中で生産条件が等しい複数
のオーダーを選別し前記選別後の各オーダーの同一工程
の負荷を足し合わせて新しいオーダーを作成する類似オ
ーダーまとめ機能と、前記生産計画を形成する複数のオ
ーダーの中でオーダー単位の情報を必要としない任意の
オーダーの各工程の負荷をこの負荷の発生する時間単位
に山積みしこの山積みした結果を再度オーダーとして作
成する機能とで行ってもよい。
The pre-scheduling system of the present invention separates and rejoins a plurality of component manufacturing orders forming a production plan at the time when all the manufacturing of the components instructed by the plurality of component manufacturing orders is completed. The component configuration information importing function for creating a new order having process procedure information for starting the production of the product instructed by, and a plurality of orders having the same production condition among the plurality of component manufacturing orders are selected and The similar order summarizing function that creates the new order by adding the load of the same process of the order and the load of each process of the arbitrary order that does not need the information of the order unit among the multiple orders forming the production plan. With the function to pile up in a time unit where this load occurs and to create the result of this pile up again as an order. It may be.

【0007】[0007]

【実施例】次に、本発明の実施例について図面を参照し
て説明する。
Embodiments of the present invention will now be described with reference to the drawings.

【0008】図1は本発明の一実施例のブロック図であ
る。
FIG. 1 is a block diagram of an embodiment of the present invention.

【0009】図1に示すように、前位の生産計画作成シ
ステム1の作成する生産計画7を受けるプレスケジュー
リングシステム2は、生産計画7を構成する最終製品製
造オーダーと、この最終製品製造オーダーを作成するた
めに必要な部品を製造する複数の部品製造オーダーとを
予め定める基準に従って分離し、再結合し、後位の負荷
調整システム6に適合する調整用生産計画8として出力
する。さらに、プレスケジューリングシステム2の内部
には、生産計画7を構成する各製造オーダーを振り分け
る生産計画振り分け部9と、生産計画振り分け部9から
振り分け後の各製造オーダーを受け、最終製品とこれを
構成する部品との工程手順情報を取り込む部品構成情報
取り込み部3と、類似のオーダーをまとめる類似オーダ
ーまとめ部4と、各オーダーの各工程の負荷を時間単位
に山積みする山積みオーダー作成部5とがある。部品構
成情報取り込み部3と類似オーダーまとめ部4と山積み
オーダー作成部5とによって加工された生産計画7のデ
ータは、1つにまとめられ調整用生産計画8として出力
される。調整用生産計画8は、負荷調整システム6の入
力となり、負荷調整システム6では調整用生産計画8を
負荷の情報として表示し、負荷調整担当者が、負荷調整
を行う。
As shown in FIG. 1, the pre-scheduling system 2 that receives the production plan 7 created by the preceding production plan creation system 1 includes the final product manufacturing order that constitutes the production plan 7 and the final product manufacturing order. A plurality of parts manufacturing orders for manufacturing the parts necessary for creating are separated and recombined according to a predetermined standard, and output as an adjustment production plan 8 suitable for the load adjustment system 6 at the subsequent stage. Further, inside the pre-scheduling system 2, a production plan distribution unit 9 that distributes each production order that constitutes the production plan 7, and each production order that has been distributed from the production plan distribution unit 9 are received to form a final product and this. There is a component configuration information capturing unit 3 that captures process procedure information for a component to be processed, a similar order grouping unit 4 that groups similar orders, and a stacking order creation unit 5 that stacks the load of each process of each order in units of time. . The data of the production plan 7 processed by the parts configuration information capturing unit 3, the similar order grouping unit 4, and the pile-up order preparing unit 5 are put together into one and output as the adjustment production plan 8. The adjustment production plan 8 is input to the load adjustment system 6, and the load adjustment system 6 displays the adjustment production plan 8 as load information, and the load adjustment person in charge performs the load adjustment.

【0010】次に動作について説明する。Next, the operation will be described.

【0011】図2は本発明のプレスケジューリングシス
テムの部品構成情報取り込み部の一処理方法を説明する
説明図である。
FIG. 2 is an explanatory view for explaining a processing method of the component configuration information capturing section of the pre-scheduling system of the present invention.

【0012】生産計画7には、最終製品計画11として
の[オーダー1]14と、部品計画12としての[オー
ダー2]15、[オーダー3]16、[オーダー4]1
7、[オーダー5]18および[オーダー6]19との
各情報が入っている。生産を行う場合には、部品計画1
2で指示した生産を完了してから、最終製品計画11の
生産を開始する。
In the production plan 7, [Order 1] 14 as the final product plan 11 and [Order 2] 15, [Order 3] 16 and [Order 4] 1 as the parts plan 12 are provided.
7, [Order 5] 18 and [Order 6] 19 are included. For production, parts planning 1
After the production instructed in 2 is completed, the production of the final product plan 11 is started.

【0013】部品構成情報取り込み部3は、最終製品計
画11および部品計画12の情報を受け、部品構成情報
を取り込んだ調整用生産計画8として出力する。調整用
生産計画8は、計画の内部に[オーダー2]20、[オ
ーダー3]21、[オーダー4]22、[オーダー5]
23および[オーダー6]24に記述された製造と検査
がすべて完了してから、[オーダー1]25に記述され
た製造と検査を行うという工程手順を含んだ部品構成情
報を持つ。
The parts configuration information fetching section 3 receives the information of the final product plan 11 and the parts plan 12 and outputs it as the adjustment production plan 8 which fetches the parts configuration information. The adjustment production plan 8 includes [Order 2] 20, [Order 3] 21, [Order 4] 22, and [Order 5] inside the plan.
23 and [Order 6] 24, after having completed all the manufacturing and inspection described, [Order 1] 25 has the component configuration information including the process procedure of performing the manufacturing and inspection described.

【0014】図3は本発明のプレスケジューリングシス
テムの類似オーダーまとめ部の一処理方法を説明する説
明図である。
FIG. 3 is an explanatory view for explaining a processing method of the similar order arranging unit of the pre-scheduling system of the present invention.

【0015】類似オーダーまとめ部4は、生産計画7の
中から部品計画12の情報を受け、[オーダー8]3
1、[オーダー9]32、[オーダー10]33に記述
された製品が、同一の工程手順を有し、納期が等しく、
各工程のリードタイムが同じ場合には、調整用生産計画
8として[オーダー11]34を作成する。
The similar order grouping unit 4 receives the information of the parts plan 12 from the production plan 7, and [Order 8] 3
The products described in No. 1, [Order 9] 32, and [Order 10] 33 have the same process procedure and the same delivery date,
When the lead time of each process is the same, [Order 11] 34 is created as the adjustment production plan 8.

【0016】部品計画12の[オーダー8]31の[工
程I]40の負荷が“10”であり、[オーダー9]の
[工程I]41の負荷が“11”であり、[オーダー1
0]33の[工程I]42の負荷が“11”の場合、調
整要生産計画8の[オーダー11]34の[工程I]4
3の負荷は、部品計画12の各計画の[工程I]の負荷
を足した値となり、負荷は“32”となる。
The load of the [Process I] 40 of the [Order 8] 31 of the parts plan 12 is "10", the load of the [Process I] 41 of the [Order 9] is "11", and the [Order 1]
0] 33 [Process I] 42 has a load of “11”, [Order 11] 34 [Process I] 4 of the production plan 8 requiring adjustment
The load of 3 is a value obtained by adding the loads of [Process I] of each plan of the component plan 12, and the load is “32”.

【0017】図4は本発明のプレスケジューリングシス
テムの山積みオーダー作成部の一処理方法を説明する説
明図である。
FIG. 4 is an explanatory view for explaining a processing method of the piled-up order creating section of the pre-scheduling system of the present invention.

【0018】生産計画7の中の部品計画12の[オーダ
ー12]51、[オーダー13]52および[オーダー
14]53は、負荷調整対象外の計画であり、負荷調整
を行う時点では、各工程での負荷の大きさが分かれば良
い。
[Order 12] 51, [Order 13] 52 and [Order 14] 53 of the parts plan 12 in the production plan 7 are plans which are not subject to load adjustment, and at the time of load adjustment, each process is performed. You just need to know the size of the load.

【0019】部品計画12の[オーダー12]51に記
述された製品は、[工程M]60、[工程N]63、
[工程O]64および[工程P]65を通って生産され
る。
The products described in [Order 12] 51 of the parts plan 12 are [Process M] 60, [Process N] 63,
It is produced through [Process O] 64 and [Process P] 65.

【0020】次に、部品計画12の各計画を、山積みオ
ーダー作成部5により、調整用生産計画8として出力す
る。調整用生産計画8の[オーダー15]55、[オー
ダー16]56、[オーダー17]57および[オーダ
ー18]58は、部品計画12の各計画の同一工程の負
荷をまとめ、新たに作成した計画である。
Next, each of the plans of the parts plan 12 is output as the adjustment production plan 8 by the pile-up order creating section 5. [Order 15] 55, [Order 16] 56, [Order 17] 57, and [Order 18] 58 of the adjustment production plan 8 are newly created plans in which the loads of the same process of each plan of the parts plan 12 are summarized. Is.

【0021】[工程M]に着目した場合、[オーダー1
2]51として記述された製品は、[工程M]60の負
荷が“10”完了日“1”、[オーダー13]52に記
述された製品は、[工程M]61の負荷が“11”完了
日“2”、[オーダー14]53に記述された製品は、
[工程M]62の負荷が“11”完了日が“3”でそれ
ぞれ作業される。これらの[工程M]のすべての負荷を
まとめ、調整用生産計画8の[オーダー15]55を作
成する。[オーダー15]55は、[工程M]を複数回
通る計画として作成される。[オーダー12]51にお
ける[工程M]60の負荷が“10”であり完了日が
“1”であるので、[オーダー15]55の完了日が
“1”である[工程M]70に負荷の“10”を加算す
る。[オーダー13]52の[工程M]61の負荷の値
“11”は[オーダー15]55の完了日が“2”の
[工程M]71に加算する。[オーダー14]53の
[工程M]の負荷の値“11”は、[オーダー15]5
5の完了日が“3”の[工程M]72に加算する。[オ
ーダー15]55における他の完了日の[工程M]7
3、[工程M]74および[工程M]75は、生産計画
7に完了日が等しい[工程M]が無いため、負荷が
“0”となる。
When focusing on [Process M], [Order 1
2] For the product described as 51, the load of [Process M] 60 is “10”, the completion date is “1”, and for the product described in [Order 13] 52, the load of [Process M] 61 is “11”. The product described in the completion date “2”, [Order 14] 53 is
[Process M] The load of "62" is "11", and the completion date is "3". All the loads of these [process M] are put together to create [Order 15] 55 of the production plan 8 for adjustment. [Order 15] 55 is created as a plan that passes through [Process M] multiple times. Since the load of [Process M] 60 in [Order 12] 51 is “10” and the completion date is “1”, the load is applied to [Process M] 70 where the completion date of [Order 15] 55 is “1”. "10" of is added. The load value “11” of the [Process M] 61 of the [Order 13] 52 is added to the [Process M] 71 of the [Order 15] 55 having the completion date of “2”. The load value “11” of [Process M] of [Order 14] 53 is [Order 15] 5
The completion date of 5 is added to the [process M] 72 whose completion date is "3". [Order M] 7 [Process M] 7 on the other completion date in 55
3, [Process M] 74 and [Process M] 75 have a load of “0” because there is no [Process M] with the same completion date in the production plan 7.

【0022】生産計画7の他の工程である[工程N]、
[工程O]および[工程P]の負荷はそれぞれ別々に調
整用生産計画8の[オーダー16]56、[オーダー1
7]57および[オーダー18]58に加算する。
[Process N] which is another process of the production plan 7,
The loads of [Process O] and [Process P] are separately set in [Order 16] 56 and [Order 1] of the production plan 8 for adjustment.
7] 57 and [Order 18] 58.

【0023】[0023]

【発明の効果】以上説明したように、本発明は、最終製
品製造オーダーと部品製造オーダーとの両方の計画を一
つのオーダーとしてまとめ、負荷調整時に部品製造オー
ダーから最終製品製造オーダーに至るまでの任意のオー
ダーの調整を行う場合に、他のオーダーを考慮すること
なく完全同期で調整することを可能とし、これにより、
負荷調整時に負荷調整担当者が調整対象のオーダーと同
期関係にあるオーダーを考慮する必要がなく、調整時の
考慮項目の減少、調整時間の削減、考慮すべき項目の漏
れの防止がそれぞれ可能となるという効果がある。又、
負荷調整システムでは、負荷情報を1つにまとめた情報
として表示することができ、画一的な負荷調整手順によ
る負荷調整が可能となるといった効果もある。さらに、
本発明は、類似のオーダーをまとめ、オーダー情報を持
つ必要のないオーダーもすべてまとめ、これらを工程数
分のオーダーとして新たに作成することにより、管理対
象のオーダー数を少なくすることも可能であるので、情
報システム全体の負荷を低減し、必要とされるハードウ
エアの処理能力を小さくすることができるという効果も
期待できる。
As described above, according to the present invention, plans for both the final product manufacturing order and the parts manufacturing order are put together as one order, and from the parts manufacturing order to the final product manufacturing order during load adjustment. When adjusting an arbitrary order, it is possible to perform adjustment in full synchronization without considering other orders, which allows
When adjusting the load, the load adjuster does not need to consider the orders that are in synchronization with the order to be adjusted, and it is possible to reduce the items to be considered during adjustment, reduce the adjustment time, and prevent the leakage of items to be considered. There is an effect that. or,
In the load adjustment system, the load information can be displayed as one piece of information, and there is an effect that the load adjustment can be performed by a uniform load adjustment procedure. further,
According to the present invention, it is possible to reduce the number of orders to be managed by collecting similar orders, collecting all orders that do not need to have order information, and newly creating these as the orders for the number of processes. Therefore, it is possible to expect an effect that the load of the entire information system can be reduced and the required processing capacity of hardware can be reduced.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の一実施例のブロック図である。FIG. 1 is a block diagram of an embodiment of the present invention.

【図2】本発明の部品構成情報取り込み部の一処理方法
を説明する説明図である。
FIG. 2 is an explanatory diagram illustrating a processing method of a component configuration information importing unit of the present invention.

【図3】本発明の類似オーダーまとめ部の一処理方法を
説明する説明図である。
FIG. 3 is an explanatory diagram illustrating a processing method of a similar order grouping unit according to the present invention.

【図4】本発明の山積みオーダー作成部の一処理方法を
説明する説明図である。
FIG. 4 is an explanatory diagram illustrating a processing method of the piled-up order creation unit of the present invention.

【図5】従来の生産管理システムのブロック図である。FIG. 5 is a block diagram of a conventional production management system.

【符号の説明】[Explanation of symbols]

1 生産計画作成システム 2 プレスケジューリングシステム 3 部品構成情報取り込み部 4 類似オーダーまとめ部 5 山積みオーダー作成部 6 負荷調整システム 7 生産計画 8 調整用生産計画 9 生産計画振り分け部 11 最終製品計画 12 部品計画 14 オーダー1 15 オーダー2 16 オーダー3 17 オーダー4 18 オーダー5 19 オーダー6 20 調整用生産計画8内部の部品オーダー2 21 調整用生産計画8内部の部品オーダー3 22 調整用生産計画8内部の部品オーダー4 23 調整用生産計画8内部の部品オーダー5 24 調整用生産計画8内部の部品オーダー6 25 調整用生産計画8内部の最終製品オーダー1 31 生産オーダー8 32 生産オーダー9 33 生産オーダー10 34 調整用生産計画11 40 生産オーダー8の工程I 41 生産オーダー9の工程I 42 生産オーダー10の工程I 43 生産オーダー11の工程I 51 生産オーダー12 52 生産オーダー13 53 生産オーダー14 55 調整用生産オーダー15 56 調整用生産オーダー16 57 調整用生産オーダー17 58 調整用生産オーダー18 60 生産オーダー12の工程M 61 生産オーダー13の工程M 62 生産オーダー14の工程M 63 生産オーダー12の工程N 64 生産オーダー12の工程O 65 生産オーダー12の工程P 70 調整用生産オーダー15の完了日1の工程M 71 調整用生産オーダー15の完了日2の工程M 72 調整用生産オーダー15の完了日3の工程M 73 調整用生産オーダー15の完了日4の工程M 74 調整用生産オーダー15の完了日5の工程M 75 調整用生産オーダー15の完了日6の工程M 1 Production Plan Creation System 2 Pre-Scheduling System 3 Parts Configuration Information Importing Unit 4 Similar Order Summary Unit 5 Stacking Order Creation Unit 6 Load Adjustment System 7 Production Plan 8 Adjustment Production Plan 9 Production Plan Distribution Unit 11 Final Product Plan 12 Parts Plan 14 Order 1 15 Order 2 16 Order 3 17 Order 4 18 Order 5 19 Order 6 20 Internal production order 8 for adjustment production plan 8 21 Internal production order 8 for adjustment production plan 8 22 Internal production order 8 for adjustment production plan 8 23 Parts order 5 inside adjustment production plan 8 24 Parts order inside adjustment production plan 8 6 25 Final product order inside adjustment production plan 8 1 31 Production order 8 32 Production order 9 33 Production order 10 34 Adjustment production Plan 1 1 40 Production Process I 41 of production order 9 process I 42 of production order 9 process I 43 of production order 10 process I 51 of production order 11 production order 12 52 production order 13 53 production order 14 55 adjustment production order 15 56 adjustment production order 16 57 adjustment production order 17 58 adjustment production order 18 60 production order 12 process M 61 production order 13 process M 62 production order 14 process M 63 production order 12 process N 64 production order 12 process O 65 production order 12 Process P 70 Adjustment production order 15 completion date 1 process M 71 Adjustment production order 15 completion date 2 process M 72 Adjustment production order 15 completion date 3 process M 73 Adjustment production order 15 Completion date of process M 74 adjustment production order 15 of completion date 4 Step M of the day 6 of the process M 75 adjustment for production order 15

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 前位の生産計画作成システムの作成する
最終製品製造オーダーと、前記最終製品製造オーダーを
作成するために必要な部品を製造する複数の部品製造オ
ーダーとからなる生産計画を受け、予め定める基準に従
って前記複数の部品製造オーダーを分離し、再結合し、
後位の負荷調整システムに適合する調整用生産計画とし
て出力することを特徴とするプレスケジューリング方
式。
1. A production plan including a final product manufacturing order created by a preceding production plan creating system and a plurality of parts manufacturing orders for manufacturing the parts required to create the final product manufacturing order, Separating and recombining the plurality of component manufacturing orders according to predetermined criteria,
A pre-scheduling method that outputs as a production plan for adjustment that is compatible with the load adjustment system at the rear stage.
【請求項2】 生産計画を形成する複数の部品製造オー
ダーの分離および再結合を、前記複数の部品製造オーダ
ーの指示する部品の製造がすべて完了した時点で最終製
品製造オーダーの指示する製品の製造を開始する工程手
順情報を持つ新しいオーダーを作成する部品構成情報取
り込み機能と、前記複数の部品製造オーダーの中で生産
条件が等しい複数のオーダーを選別し前記選別後の各オ
ーダーの同一工程の負荷を足し合わせて新しいオーダー
を作成する類似オーダーまとめ機能と、前記生産計画を
形成する複数のオーダーの中でオーダー単位の情報を必
要としない任意のオーダーの各工程の負荷をこの負荷の
発生する時間単位に山積みしこの山積みした結果を再度
オーダーとして作成する機能とで行うことを特徴とする
請求項1記載のプレスケジューリング方式。
2. The manufacturing of a product instructed by a final product manufacturing order at the time when all the manufacturing of the parts instructed by the plurality of component manufacturing orders has been completed for the separation and recombination of the plurality of component manufacturing orders forming the production plan. Part configuration information import function for creating a new order having process procedure information for starting the process, and selection of a plurality of orders having the same production conditions among the plurality of part manufacturing orders, and load of the same process of each order after the selection A similar order summarizing function that creates a new order by adding the above, and the load of each process of an arbitrary order that does not require order unit information among the plurality of orders that form the production plan. 2. The function according to claim 1, wherein the function is to pile up a unit and to create a result of the pile up again as an order. Scheduling method.
JP4780993A 1993-03-09 1993-03-09 Pre-scheduling method Expired - Lifetime JPH07109606B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP4780993A JPH07109606B2 (en) 1993-03-09 1993-03-09 Pre-scheduling method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP4780993A JPH07109606B2 (en) 1993-03-09 1993-03-09 Pre-scheduling method

Publications (2)

Publication Number Publication Date
JPH06259436A true JPH06259436A (en) 1994-09-16
JPH07109606B2 JPH07109606B2 (en) 1995-11-22

Family

ID=12785698

Family Applications (1)

Application Number Title Priority Date Filing Date
JP4780993A Expired - Lifetime JPH07109606B2 (en) 1993-03-09 1993-03-09 Pre-scheduling method

Country Status (1)

Country Link
JP (1) JPH07109606B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11221739A (en) * 1998-02-06 1999-08-17 Tokyo Electric Power Co Inc:The Production scheduling device and power monitoring device
CN111539681A (en) * 2020-04-10 2020-08-14 广州地铁设计研究院股份有限公司 Work plan summarizing method and device

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02310703A (en) * 1989-05-26 1990-12-26 Chugoku Nippon Denki Software Kk Process managing device
JPH0520336A (en) * 1991-07-15 1993-01-29 Fujitsu Ltd Load stack type production simulation method

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02310703A (en) * 1989-05-26 1990-12-26 Chugoku Nippon Denki Software Kk Process managing device
JPH0520336A (en) * 1991-07-15 1993-01-29 Fujitsu Ltd Load stack type production simulation method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11221739A (en) * 1998-02-06 1999-08-17 Tokyo Electric Power Co Inc:The Production scheduling device and power monitoring device
CN111539681A (en) * 2020-04-10 2020-08-14 广州地铁设计研究院股份有限公司 Work plan summarizing method and device
CN111539681B (en) * 2020-04-10 2023-09-26 广州地铁设计研究院股份有限公司 Work plan summarizing method and device

Also Published As

Publication number Publication date
JPH07109606B2 (en) 1995-11-22

Similar Documents

Publication Publication Date Title
DE69909791T2 (en) DISTRIBUTED COMPUTER ENVIRONMENT WITH REAL-TIME SEQUENCE LOGIC AND TIME-DETERMINIST ARCHITECTURE
US20190227533A1 (en) Method and apparatus for dynamic intelligent scheduling
WO2021244263A1 (en) Method for constructing automated production control architecture
US11550306B2 (en) Information collection system for industrial equipment, control apparatus for industrial equipment, and information collection method for industrial equipment
CN108009258A (en) It is a kind of can Configuration Online data collection and analysis platform
CN101976240A (en) Form number generating method and system
JPH06259436A (en) Pre-scheduling system
US20230253793A1 (en) Intermittent characteristic-based demand-side resource coordination control method and system
JPH1110490A (en) Input planning scheduling system
JPH043208A (en) Digital type repeating control system
CN114610803A (en) Data processing method and device, electronic equipment and storage medium
JPH07182420A (en) Production planning device
Towill et al. The dynamics of capacity planning for flexible manufacturing system startup
CN106778044A (en) The method and apparatus of data processing
Sarder et al. Production Design by Simulation Software “Witness”–A Case Study
CN112650163A (en) Intelligent manufacturing system cooperative control method and system and computer equipment
CN113609122A (en) Data quality scanning method and system
CN109190990A (en) Processing method and processing unit
JP2692407B2 (en) Production scheduling device
JPH09225786A (en) Production scheduling support system and its method
JPH04146056A (en) Production-scheduling system
JPH07182424A (en) Production scheduling device
JPH04111756A (en) Scheduling device
JP2791040B2 (en) Stop plan creation support device
Murata et al. Exploring Loss Hidden in Digital Scheduling Data

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 19960507