JPH06212688A - Building method of wooden house by use of panel - Google Patents

Building method of wooden house by use of panel

Info

Publication number
JPH06212688A
JPH06212688A JP5200892A JP5200892A JPH06212688A JP H06212688 A JPH06212688 A JP H06212688A JP 5200892 A JP5200892 A JP 5200892A JP 5200892 A JP5200892 A JP 5200892A JP H06212688 A JPH06212688 A JP H06212688A
Authority
JP
Japan
Prior art keywords
floor
panel
panels
house
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP5200892A
Other languages
Japanese (ja)
Inventor
Hideki Sama
秀樹 佐間
Takao Nagase
孝夫 永瀬
Toru Iwata
徹 岩田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HIGASHI NIPPON HOUSE KK
Original Assignee
HIGASHI NIPPON HOUSE KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HIGASHI NIPPON HOUSE KK filed Critical HIGASHI NIPPON HOUSE KK
Priority to JP5200892A priority Critical patent/JPH06212688A/en
Publication of JPH06212688A publication Critical patent/JPH06212688A/en
Pending legal-status Critical Current

Links

Landscapes

  • Building Environments (AREA)
  • Load-Bearing And Curtain Walls (AREA)

Abstract

PURPOSE:To reduce the manday by building a wooden house with the combination of prefabricated structural framing members with floor panels, wall panels, roof panels, eaves top panels, and ceiling panels with a plurality of respective standards. CONSTITUTION:The frame of a house is formed by use of floor panels 1, wall panels 2, roof panels 3, eaves top panels 4, and ceiling panels 5 having a plurality of standards respectively and prefabricated structural framing members. Arbitrary numbers of the floor panels 1 are combined and fixed with the structural framing members on the base to form the floor of the first floor and arbitrary numbers of wall panels 2 are combined and fixed with structural framing members to form respective walls as the outer walls, inner walls, and partitions of the first floor and to constitute the first floor construction. Next, the second floor is formed in the same way with the first floor. And thereafter, arbitrary numbers of the roof panels 3, the eaves top panels 4, and the ceiling panels 5 are combined and fixed with the structural framing members in the same manner. In this way, by forming respective roof, eaves top, and ceiling, a wooden house is erected.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】この発明は、家屋の建築方法に関
するものである。特には、一戸建て木造家屋建築にパネ
ルを用いて木造家屋を建築する方法に関するものであ
る。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of building a house. In particular, it relates to a method of constructing a wooden house by using panels in a single-family wooden house construction.

【0002】[0002]

【従来の技術】従来一戸建て木造家屋を建築するにはま
ず基礎工事をし、そこに土台を設け、土台に柱を設け、
かつ必要な軸組を設ける。例えば、間柱、通しぬき、火
打ちばり、床柱、たる木など多くの必要部材を各々の適
便の箇所に使用し、建て上げ、建て上げ最後は屋根の野
地板を敷いて、建て方は終わるものである。これらは他
所において、必要な部材の一部は、加工・組立てられて
来るが、ほとんどは、現場で組み立てられるものであ
る。そのため多くの資材・部材を必要とするものである
のみならず、多くの人数、日数をも必要とするものであ
る。この土台から二階、屋根までまず通し柱を使用して
建築する方法は、今日でも普通に行われているものであ
る。この普通に行われている工法に対し、今日省力化、
簡略化を目的として、プレハブ工法及びパネル工法とい
う建築方法も行われている。プレハブ工法とは、家屋の
建築に必要とする部材、例えば柱、側壁、窓、その他の
部材を予め工場などで加工・組立を行い、それらの部材
を現場で組上げる方法である。プレハブ工法は、単に組
み立てるのみという便利性があり、今日でも多くの所で
使用されているものである。またこのプレハブ工法とも
一部重なり合うものであるが、パネル工法という方法も
ある。パネル工法は、例えば多種多様のパネル材を使用
し、家屋の外側壁、内側壁、屋根などをパネルによって
構築する方法である。この方法もプレハブ工法と同様、
省力化、簡略化にとっては便利なものであり、今日、あ
る程度、一戸建立家屋の建築に取り入れられているもの
である。
2. Description of the Related Art Conventionally, in order to build a detached wooden house, first of all, foundation work is performed, a foundation is provided there, and a pillar is provided on the foundation.
And provide the necessary shafts. For example, many necessary members such as studs, through-holes, fire pits, floor posts, and rafters are used for each convenient location, and the building is finished. is there. In other places, some of the necessary members are processed and assembled, but most of them are assembled on site. Therefore, not only a large number of materials and members are required, but also a large number of people and days are required. The method of building through the pillars from the base to the second floor and the roof is a common practice today. Labor saving is done to this ordinary construction method today,
For the purpose of simplification, prefabricated construction method and panel construction method are also used. The prefabricated method is a method in which members required for building a house, such as pillars, side walls, windows, and the like, are processed and assembled in advance in a factory or the like, and then those members are assembled on site. The prefabricated method has the convenience of simply assembling and is still used in many places today. There is also a method called the panel method, although it partially overlaps with this prefabricated method. The panel construction method is, for example, a method of constructing an outer wall, an inner wall, a roof and the like of a house with panels by using various kinds of panel materials. This method is similar to the prefab method
It is convenient for labor saving and simplification, and is used to some extent today in the construction of detached houses.

【0003】[0003]

【解決しようとする課題】一戸建て木造家屋建築におい
て、従来方法は、上台を作り、柱を立て、必要な部材を
各所に取り付け、順次、屋根まで形成し、野地板を屋根
に取り付け、しかる後、家屋の側壁を形成するという方
法をとっていた。このため、家屋の建て方に多くの部
材、資材を必要とするのみならず多くの人数と多くの日
数を要するものであった。家屋の骨格のみを建て上げる
だけでも4〜5日は要し、更に外側や内側あるいは間仕
切壁などの側壁面を作るのにも多くの日数を要するもの
であった。この多くの資材、部材及び人数と日数を省力
化し、かつ簡略に家屋の建て方ができるとされるのがプ
レハブ工法とかパネル工法である。しかし、このプレハ
ブ工法にしても、組立は簡略化されるが、時には組み合
わせ部分の接合がうまく行かなかったり、組立接着方法
に多くの時間を要したりするという欠点があり、人数的
にはうまく行っても日数的に4〜5日も、その組立てに
掛かったりするものであった。またパネル工法も従来の
ものは家屋の側壁や床、また屋根など一部分をパネル化
してその部材を使用するものであり、プレハブ工法同様
にあるいはそれとともに使用されるものであり、その組
立・結合に日数を要するという欠点とともに、各種各様
のパネルが用いられるので、家屋を規格化し、その規格
に適合するように規格的にパネルを使用するにも不便な
ものであり、今日においては、パネル工法はまだそれほ
どには一般的なものではないものである。
[Problems to be solved] In a single-family wooden house construction, the conventional method is to make an upper stand, erect columns, attach necessary members to various places, sequentially form a roof, attach a base plate to the roof, and then, The method was to form the side wall of the house. Therefore, not only a large number of members and materials are required for building a house, but also a large number of people and a large number of days are required. It took 4 to 5 days to build only the skeleton of the house, and it took a lot of days to make side walls such as the outside, inside, and partition walls. The prefabricated construction method and the panel construction method are said to be capable of easily constructing a house while saving a lot of materials, members, the number of people and the number of days. However, even with this prefabricated method, the assembly is simplified, but sometimes there are drawbacks that the joining of the combined parts does not work well, and the assembly bonding method takes a lot of time, so it is not good for the number of people. Even if it went, it took 4 to 5 days to assemble it. In addition, the conventional panel construction method uses a part of the side wall, floor, roof, etc. of the house as a panel, and is used in the same way as or together with the prefabricated construction method. In addition to the drawback that it takes days, various types of panels are used, so it is inconvenient to standardize houses and use panels standardly to comply with the standard. Is still not that common.

【0004】[0004]

【課題を解決するための手段】従来の一戸建立て木造家
屋建築には、前にのべたような各々の欠点があるもので
ある。そこで、これらの欠点を改良し、より省力化、簡
略化を行うためには、次のような方法を用いることによ
って行われる。それは、木造家屋建築方法において、各
々複数の規格を有する床パネル、壁パネル、屋根パネ
ル、軒天パネル、天井パネルと予め加工される構造軸組
部材とを用い、該構造軸組部材を適所適便に使用し、家
屋土台部を形成し、次に適便規格の床パネルを任意数、
該土台部構造軸組部材に組み合わせ固定し、家屋1階部
の床を形成し、次に適便規格の壁パネルを任意数、構造
軸組部材とともに組み合わせ固定し、家屋1階部の外壁
・内壁及び間仕切壁としての側壁を形成し、家屋1階部
とし、次に2階部も1階部同様、構造軸組部材に、任意
数の適便規格の床パネルを組み合わせ固定し、2階部床
を形成し、後、1階部同様に、適便規格の壁パネルを任
意数、構造軸組部材とともに組み合わせ固定し、2階部
の外壁・内壁及び間仕切壁としての側壁を形成して、2
階部を形成し、以後、同様に適便規格の屋根パネル、軒
天パネル、天井パネルの任意数を構造軸組部材とともに
組み合わせ固定し、各々家屋の屋根、軒天、天井の各部
を形成して行くことによって木造家屋を建築することを
特徴とする木造家屋建築方法によって、目的は達成され
るものである。また従前には見られなかった家屋建築方
法を提供しようとするものである。
[Means for Solving the Problems] The conventional single-family detached wooden house construction has the drawbacks as mentioned above. Therefore, in order to improve these drawbacks, and further save labor and simplify, the following method is used. It uses a floor panel, a wall panel, a roof panel, an eaves panel, a ceiling panel and a structural framing member which are pre-processed in a wooden house construction method, and the structural framing member is placed in an appropriate position. It is used for stools, forms the base of the house, and then an arbitrary number of floor panels of the appropriate stool standard,
Combined and fixed to the base structural structural member to form the floor of the first floor of the house, and then combine and fix an arbitrary number of wall panels of suitable standards with the structural structural member to fix the outer wall of the first floor of the house. The inner wall and the side wall as a partition wall are formed to form the first floor of the house, and then the second floor is fixed to the structural frame member by combining any number of floor panels conforming to the appropriate flight standards and fixing them on the second floor. After forming the partial floor, as in the case of the first floor, an arbitrary number of wall panels conforming to the standard of convenience are combined and fixed together with the structural frame members, and the side walls as outer and inner walls and partition walls of the second floor are formed. Two
After forming the floors, similarly, any number of roof panels, eaves ceiling panels, and ceiling panels of appropriate standards are combined and fixed together with the structural frame members to form the roof, eaves, and ceiling portions of the house. The purpose is achieved by a method of constructing a wooden house, which is characterized by constructing a wooden house by going up. It also seeks to provide a method of building a home that was previously unheard of.

【0005】[0005]

【実施例】以下、この発明について、図に従って実施例
を説明する。この発明の実施例は、2階建家屋の建築を
目的としているものである。図1から図14までは、こ
の発明の工法を示す全体参考図及び部分参考図であり、
図15は、金具の全体参考図である。また図16は、こ
の方法の実施によって取り付けられるパネルの取付部位
を示す片面参考図である。この発明は家屋の床、側壁、
屋根、軒天、天井、その他可能な箇所を全て、規格化さ
れたパネルでもって構成しようとするものであり、全く
骨組材としての構造軸組部材を使用しないとするもので
はなく、必要範囲の構造軸組部材を用いるものである。
しかし、この構造軸組部材も、規格的に構成されている
ものである。この発明ではまず床パネル、壁パネル、屋
根パネル、軒天パネル、天井パネルの各々を必要規格に
標準化する。それによると、各パネルは次のように標準
化される。 1)壁パネル ・パネルの厚みは、大壁、片真壁用の2種類とする。 外壁パネル ・幅0.5P、1.0P、1.5P、2.0Pの4サイ
ズを標準とする。(1P=910mm) ・高さは、梁成に対応して2730mm、2670mm
の2サイズとする。 内壁パネル ・幅0.5P、1.0P、1.5P、2.0Pの4サイ
ズを標準とする。 ・高さは、梁成に対応して4サイズとする。 外部開口部パネル ・幅については1.0P、1.5P、2.0P、3.0
Pの4サイズとする。 ・開口部は、上下に分割されたパネルで構成する。 ・内法高さを原則として2000mmとし、上部パネル
の標準化を図る。 ・サッシ高さは、原則として3尺、3.5尺、4尺、
4.5尺、6尺、6.6尺の6サイズとする。 間仕切壁パネル ・高さは、天井高さ2400mm、2550mmに対応
して2サイズとする。 内壁開口部パネル、間仕切壁開口部パネル ・出入り口(ドア)と袖壁部分は分離させ、出入り口上
部パネルと袖壁パネルから構成する。 ・出入り口の高さは原則として2000mmとする。 ・天井高さ2400mm、2550mmの2仕様に対応
する。 2)床パネル ・幅は1.0Pとし、長さは1.0P、1.5P、2.
0P、2.5P、3.0P、3.5P、4.0Pの7サ
イズを標準化とする。 3)屋根パネル ・屋根勾配は、原則として3.5、4.5、5.0寸の
3種類とする。 ・軒の出は、750mmを原則とする。 ・ケラバの出は、600mmを原則とする。 ・パネルの幅は、ケラバ以外は原則として1.0Pとす
る。また、最大長さは4000mmまでとする。 4)軒天パネル ・長さは、4.0Pを目安とし、短いものを作らない。
サイズの調整は、出隅部分で行う。 5)天井パネル ・幅は1.0Pとし、長さは2.0、2.5、3.0、
3.5、4.0の4種類を標準とする。また、各部屋の
調整用の端パネルは、幅0.5P、1.0Pタイプの2
種類とする。 このように標準化された各パネルの種類と、サイズは、
次の表の如くである。パネルの種類は、壁が6種類のほ
かは各1種類となり、合計10種類。 ・サイズは、幅または長さを示す。1.0P=910
(芯々)を示す。また、壁パネルは柱のスパン、床パネ
ルは長さ(梁スパン)、屋根パネルは母屋の位置、軒天
パネルは長さ、天井パネルは長さによるサイズを表示し
た。 ・屋根勾配によるサイズの違いは除く。・・・・・屋根
パネル ・開口部の形状によるパネルサイズの違いは除く。 ・屋根パネルの長さは、垂木の定尺長さ4.0mを限度
とする。 ・壁パネルの高さの違いは、サイズより除く。 このように規格標準化された各パネルは工場で大量に生
産することができるし、またストックすることもでき
る。各パネルはまた、これらの標準化の他に、例えば、
床パネルの場合には、内部に断熱保温材を入れて形成す
ることもできるし、また壁パネルや天井パネルのように
パネル枠としてのみ構成し、内装の段階で化粧板や他の
好みの合板材などを固定装着することも可能なようにパ
ネルは構成することもできるものである。パネルは、こ
のように規格化されて工場で生産されるものである。一
方また構造軸組部材は、パネルの規格に適合するように
予め加工することができるし、家屋注文主の希望によ
り、パネル規格に合わせて、予め加工することも可能で
ある。従って家屋建築図面に適合するように予め加工は
簡単にできるものである。これら構造軸組部材とパネル
とは常に適合するように形成されるものである。パネル
の規格化から当然のことである。そして、これらから、
このように規格標準化された各パネルを使用して、家屋
を構築するには当然に設計図面によって各種の寸法は定
められ、構造軸組部材も、その設計図面通りに形成され
るし、更に各パネルのサイズいくらのものがどこに何枚
必要とするかということも設計の段階で知ることができ
るものである。それは各パネルの規格が定まっているこ
とから容易に算出することができる。そこでこの各パネ
ルを用いて、家屋を構築する方法について説明する。
[図1]は基礎工事の状態を示す図である。家屋建築に
は当然の如く、土台を設けるための基礎部分を必要とす
る。今日は、ほとんどコンクリート基礎工事で行われ
る。この実施例も、コンクリートによって基礎を設けて
いる。[図1]は、コンクリート基礎工事完了後で、こ
れから土台を設ける前の状態をも示しているものであ
る。この実施例では、土台を設ける前に、基礎コンクリ
ートの上に若干のパッキンを入れることも可能であると
している。こうすることにより、土台と基礎コンクリー
トとの間に若干の隙間が設けられ、通風がよくなり、家
屋が全て建て終わった後、湿気を防ぎ 家屋全体の防湿
の効果が期待できるものでもある。[図2]は、土台を
基礎コンクリートに取り付けた状態を示しているもので
ある。基礎工事完了後、基礎コンクリートに土台を取り
付ける。この土台を取り付けるに、この実施例では、埋
め込み座金を使用する。この埋め込み座金によって、土
台と基礎コンクリートを固定するものである。この埋め
込み座金は、その頭の部分まで、土台内に埋め込まれる
ので、土台上に座金が出ることはない。従来は、土台上
にナットやボルトの頭が出るため、土台上に他の構造軸
組部材あるいは板材などを取り付けあるいは敷くのに不
便なものであった。この埋め込み座金を使用することに
よって、このような不便は解消される。[図3]は、土
台敷き、床梁入れ完了後の状態を示すものである。[図
2]により、土台の取り付けが完了した後、1階部床を
形成するに必要な構造軸組部材を各々取り付ける。この
構造軸組部材は、大引きであったり、梁であったり、そ
の他の部材であったりする。これらの部材の使用は、寒
冷地とか、温暖地とかによって、その使用する構造軸組
部材が異なるものであることは当然である。この実施例
では、梁を使用している。このようにして、土台と、他
の構造軸組部材とがしっかりと固定される。しかる後に
この構造軸組部材の上に、一定規格(設計図面によっ
て、すでに決定されている規格のパネル)の床パネルを
順次組み合わせ敷いて、各々釘などで固定する。この場
合、床パネルの構造軸組部材への取り付け固定は、他の
公知方法でもよい。また床パネルは断熱材の含まれてい
るもの、そうでないもの各種の床パネルを使用できる。
このようにして、床パネルを敷き、組み合わせ固定する
ことにより、1階床部が形成される[図4]は、このよ
うにして敷かれ組み合わせ固定された1階床部を示すも
のである。[図4]に示す如くに床パネルは簡単に敷か
れ固定される。この場合、床パネルには、壁パネル用の
構造軸組部材を取り付けるために必要な、構造が適便に
設けられているものである。このようにして、1階床部
は形成される。こうすることにより、火打梁を省略する
ことができる。[図5][図6]は1階部壁パネルの取
り付け状態を外側及び内側から見た状態を示すものであ
る。[図4]によって1階床パネルが取り付け完了後、
壁パネルが取り付けられる。壁パネルは、構造軸組部
材、例えば柱、2階床梁などとともに、必要な箇所に取
り付けられる。壁パネルは、外壁を形成するもの、内壁
を形成するもの、また各部屋を形成する間仕切壁とし
て、適便に使用される。即ち、外壁パネル、外壁開口パ
ネル、内壁パネル、内壁開口パネル、間仕切壁パネル、
間仕切開口パネルがあり、各々組み合わされ、適便の箇
所に取り付けられ、その用途を果たすものである。例え
ば、外壁パネルは1階部外壁部分に、また外壁開口パネ
ルは、1階部の窓部位や玄関、その他開口を必要とする
所、例えば台所、風呂、便所などの部位に使用される。
内壁パネルは、部屋の内側に表示されるように使用され
る。また内壁開口パネルは,内壁の開口部に、間仕切パ
ネルは、各部屋の間仕切、あるいは他の必要箇所に、間
仕切開口パネルは、屋内の窓や、その他の必要な箇所に
取り付けられるものである。これらの壁パネルは、パネ
ル枠のみとしても、またパネル枠に合板材あるいは他の
壁材を取り付けたものでも、また片面のみ合板材あるい
は他の壁材を設けたものでも使用できるものである。こ
れら壁パネルは、予め1階部床パネルに設けられている
構造部位や、他の構造軸組部材に、釘など公知方法によ
って、取り付け固定されるものである。これら壁パネル
を使用することにより、間柱、筋違い、などの必要部材
を省略することができるものである。[図7]は、これ
ら1階部の壁パネルの取り付けが完了し、2階部の床梁
の取り付けが完了した状態を示すものである。この[図
7]に示すように、壁パネルは、適便の規格のものが縦
にも、また横にも、適便に使用されるものである。この
使用は、すでに設計図面の段階で知られているものであ
るから、簡単に取り付けられるものである。この壁パネ
ル取り付け完了と同時に2階部床梁の組立も完了するも
のである。[図8]は2階部床パネル取り付け状態を示
すものである。1階部の壁パネルの取り付け完了と同時
に2階部の床梁も取り付け完了しているものである。こ
の2階用構造軸組部材にも、1階部の壁パネルが取り付
け固定されるものだからである。2階部用床梁に取り付
けられる床パネルは1階部の床パネル同様に取り付けら
れる。床パネルには、断熱材などの含まれているものを
使用することもできる。床パネルの固定は、1階部の床
パネルの固定と同様に行う。当然に2階部床パネルに
も、必要な構造が設けられている。それは、2階部の壁
パネルの取り付けに必要であるから当然である。また、
2階部への階段開口部なども、必要な箇所に設けられて
いるものである。このようにして、2階部床パネルが取
り付けられる。ここでも火打梁を省略することができ
る。[図9]は2階部壁パネル取り付け状態を示すもの
である。2階部床パネルの取り付け完了後、1階部壁パ
ネルと同様に、2階部にも、必要な壁パネルを、1階部
と同様に、構造軸組部材とともに必要な箇所に、一定規
格の壁パネルを取り付け設けて行く。壁パネルの用途、
目的は1階部の場合と同様に各々必要な箇所に公知の方
法で取り付け固定するものである。このようにしてパネ
ルを取り付けることによって、2階部においても間柱、
筋違などの必要部材を省略することが可能である。この
ようにして2階部の壁パネルを取り付ける。この壁パネ
ルの取り付けと同時に、屋根用構造軸組部材も取り付け
られて行く。屋根構造軸組部材の一部は、また2階部の
壁パネルを固定するものでもある。[図10][図1
1]は、屋根パネルの取り付けられる状態を示すもので
ある。2階部壁パネル取り付け完了と同時に屋根構造軸
組部材、例えば敷きげた、陸ばり、真づか、棟木、その
他の部材によって、屋根部が形成される。屋根部が形成
された後、屋根パネルを必要数、各々の屋根部に敷き固
定する。このようにして屋根板が設けられるものであ
る。屋根パネルを敷き固定することにより、家屋外観の
建て方は完了する。[図12]はこの方法によって行わ
れた家屋の建て方が完了した状態を示すものである。こ
の建て方完了までに、この工法では2日間程で完了する
ものである。大工の数にしても5−6名で済み、延べ人
数でも10−12名で済むこととなる。家屋の建て方が
完了しても、その後において更にこのパネルを用いた方
法は使用されるものである。[図13]は、軒天パネル
の使用を表示しているものである。軒天パネルは、家屋
の軒に使用されるもので、軒裏に設けるものである。こ
の軒天パネルは、パネル枠のみとしても、またパネル枠
に合板材などを張った状態でも使用することができるも
のである。パネル枠としてのみ使用した場合には、後
日、注文主の好みに合わせて、種々の合板材あるいは他
の板材を使用することができるものである。[図14]
は天井パネルの使用状態を示すものである。家屋の建て
方が完了し、家屋内部の構築時に使用するものである
が、天井パネルは、1階部天井あるいはまた2階部天井
にも取り付けられるものである。従来天井は、回り縁に
天井板を載せ、更に天井板に裏桟を設け、つり木などで
吊ったような構造に設けられるものであるが、この方法
では、天井パネルを構造軸組部材に固定するので、従前
の多くの部材を全く使用することなく天井を形成するも
のである。天井パネルは、パネル枠としても使用でき、
後日内装仕上時に、好みの合板材、その他板材を使用で
きるものである。[図15]は防振吊具である。この防
振吊具は、天井パネルを吊り上げるとともに、天井パネ
ルの揺れを防ぐ目的でも使用されるものである。この防
振吊具を使用することにより、天井パネルにかかる揺れ
をできるだけ吸収し、家屋全体の揺れをもできるだけ小
さくしようとするものである。このようにこの発明は、
従前には見られなかった方法であり、構造軸組部材に、
各パネルを必要数取り付けて行くのみの簡単な方法によ
って、木造家屋を建築することができるものである。そ
のため、この方法では、普通には必要な多くの他の部材
を省略することができる。例えば、つなぎ梁を必要とし
ないし、火打梁、間柱、筋違などの省略をもすることが
可能である。また天井構造においても、例えば回り縁を
不要とすることも可能である。このように、この発明
は、家屋建築では、従前見られなかったような方法を提
供しているものである。
Embodiments of the present invention will be described below with reference to the drawings. The embodiment of the present invention is intended for building a two-story house. 1 to 14 are an overall reference diagram and a partial reference diagram showing the construction method of the present invention,
FIG. 15 is an overall reference diagram of the metal fitting. In addition, FIG. 16 is a one-sided reference diagram showing a mounting portion of a panel mounted by carrying out this method. This invention is
The roof, eaves, ceiling, and all other possible points are to be constructed with standardized panels, and it is not intended to use structural frame members as frame members at all, A structural frame member is used.
However, this structural frame member is also constructed in a standard manner. In the present invention, each of the floor panel, the wall panel, the roof panel, the eaves panel, and the ceiling panel is first standardized to the required standard. According to that, each panel is standardized as follows. 1) Wall panel-There are two types of panel thickness: large wall and single wall. Outer wall panel ・ 4 sizes of width 0.5P, 1.0P, 1.5P, 2.0P are standard. (1P = 910mm) ・ The height is 2730mm and 2670mm corresponding to the beam formation.
2 sizes. Inner wall panel ・ 4 sizes of width 0.5P, 1.0P, 1.5P, 2.0P are standard.・ The height will be 4 sizes corresponding to the beam. External opening panel-Width is 1.0P, 1.5P, 2.0P, 3.0
It is 4 sizes of P. -The opening shall consist of panels that are divided into upper and lower parts.・ In principle, the inner height will be 2000 mm and the upper panel will be standardized.・ In principle, the sash height is 3, 5, 4,
There are 6 sizes of 4.5, 6 and 6.6. Partition wall panel ・ The height will be 2 sizes corresponding to ceiling heights of 2400 mm and 2550 mm. Inner wall opening panel, partition wall opening panel ・ The entrance and exit (door) and the sleeve wall part are separated, and are composed of the entrance upper door panel and the sleeve wall panel.・ In principle, the height of the entrance / exit is 2000 mm. -Compatible with 2 specifications of ceiling height of 2400 mm and 2550 mm. 2) Floor panel ・ Width is 1.0P and length is 1.0P, 1.5P, 2.
7 sizes of 0P, 2.5P, 3.0P, 3.5P, 4.0P are standardized. 3) Roof panel ・ As a general rule, there are three types of roof slopes: 3.5, 4.5, and 5.0 inches.・ In principle, the eaves should be 750 mm.・ In principle, the length of keraba will be 600 mm.・ In principle, the width of the panel is 1.0P except for keraba. The maximum length is up to 4000 mm. 4) Eaves panel-The length should be 4.0P as a guideline, and do not make short ones.
Adjust the size at the projected corner. 5) Ceiling panel ・ Width is 1.0P and length is 2.0, 2.5, 3.0,
Four types of 3.5 and 4.0 are standard. In addition, the end panel for adjustment of each room has a width of 0.5P, 1.0P type 2
Let's make it a kind. The types and sizes of each standardized panel are
It is as shown in the following table. There are a total of 10 types of panels, one for each type except for 6 types of walls. ・ Size indicates width or length. 1.0P = 910
Indicates (core). In addition, the wall panel shows the column span, the floor panel shows the length (beam span), the roof panel shows the position of the purlin, the eaves panel shows the length, and the ceiling panel shows the size according to the length. -Excluding the difference in size due to the roof slope.・ ・ ・ ・ ・ Roof panel ・ Excludes the difference in panel size due to the shape of the opening.・ The roof panel length is limited to 4.0 m, which is the standard length of rafters. -Wall panel height differences are excluded from the size. Each standardized panel can be mass-produced in the factory or stocked. In addition to these standardizations, each panel also
In the case of a floor panel, it can be formed by putting heat insulating material inside, or it can be configured only as a panel frame like a wall panel or ceiling panel, and can be used as a decorative panel or other favorite at the interior stage. The panel can be configured so that a plate material or the like can be fixedly mounted. The panel is standardized in this way and produced in the factory. On the other hand, the structural frame member can be pre-processed so as to conform to the panel standard, or can be pre-processed according to the panel standard at the request of the house orderer. Therefore, the processing can be easily performed in advance so as to conform to the house architectural drawing. The structural frame member and the panel are always formed so as to be matched with each other. It is natural from the standardization of panels. And from these,
In order to construct a house using each standardized panel, various dimensions are naturally determined by the design drawings, and the structural frame members are also formed according to the design drawings. It is also possible to know at what stage and how many panel sizes are needed at the design stage. It can be easily calculated because the standard of each panel is fixed. Therefore, a method of constructing a house using each panel will be described.
[Fig. 1] is a diagram showing a state of foundation work. As a matter of course, the building of a house needs a foundation to set up a foundation. Today, most of the concrete foundation work is done. This example also has a foundation made of concrete. [Fig. 1] also shows the state after the completion of the concrete foundation work and before the foundation is installed. In this embodiment, it is possible to put some packing on the foundation concrete before the foundation is provided. By doing so, a slight gap is provided between the foundation and the concrete foundation, ventilation is improved, and moisture can be prevented and moisture can be expected from the entire house after the entire house has been built. [Fig. 2] shows a state in which the foundation is attached to the foundation concrete. After the foundation work is completed, the foundation is attached to the foundation concrete. To attach the base, a buried washer is used in this example. This embedded washer secures the foundation to the foundation concrete. Since the embedded washer is embedded in the base up to the head portion, the washer does not appear on the base. Conventionally, the heads of nuts and bolts appear on the base, which makes it inconvenient to attach or lay other structural frame members or plates on the base. By using this embedded washer, such inconvenience is eliminated. [FIG. 3] shows a state after the foundation has been laid and the floor beams have been inserted. According to [Fig. 2], after the installation of the base is completed, the structural frame members necessary for forming the first floor are attached. The structural frame member may be a large pull, a beam, or another member. As for the use of these members, it goes without saying that the structural frame members used differ depending on whether it is a cold region or a warm region. In this embodiment, a beam is used. In this way, the base and the other structural frame members are firmly fixed. Thereafter, a floor panel of a certain standard (a panel of a standard already determined by the design drawing) is laid on the structural frame member in sequence and fixed by nails or the like. In this case, other known methods may be used for attaching and fixing the floor panel to the structural frame member. In addition, various types of floor panels can be used, with or without insulation.
In this way, the first-floor portion is formed by laying floor panels and fixing them in combination [FIG. 4] shows the first-floor portion thus laid and combined and fixed. The floor panel is easily laid and fixed as shown in FIG. In this case, the floor panel is appropriately provided with the structure necessary for mounting the structural frame member for the wall panel. In this way, the first floor is formed. By doing so, the striking beam can be omitted. [FIG. 5] [FIG. 6] show the mounting state of the first floor wall panel viewed from the outside and the inside. After the installation of the floor panel on the first floor by [Fig. 4],
Wall panels are attached. The wall panels are attached where necessary with the structural frame members, such as columns, second floor beams and the like. The wall panel is conveniently used as an outer wall, an inner wall, and a partition wall forming each room. That is, the outer wall panel, the outer wall opening panel, the inner wall panel, the inner wall opening panel, the partition wall panel,
There are partition opening panels, each of which is combined and attached at a convenient place to fulfill its purpose. For example, the outer wall panel is used for the outer wall portion of the first floor, and the outer wall opening panel is used for the window portion, the entrance, and other places requiring an opening, such as a kitchen, a bath, and a toilet in the first floor.
Interior wall panels are used to be displayed inside the room. Further, the inner wall opening panel is attached to the opening portion of the inner wall, the partition panel is attached to a partition of each room, or to another necessary place, and the partition opening panel is attached to an indoor window or other necessary place. These wall panels can be used as a panel frame only, a plywood material or another wall material attached to the panel frame, or a plywood material or other wall material provided on only one side. These wall panels are attached and fixed to a structural portion previously provided on the first-floor floor panel or another structural frame member by a known method such as nailing. By using these wall panels, necessary members such as studs, braces, etc. can be omitted. [FIG. 7] shows a state in which the installation of the wall panels on the first floor is completed and the installation of the floor beams on the second floor is completed. As shown in this [Fig. 7], the wall panel is a standard one that is suitable for convenient use, and is used both vertically and horizontally. This use is easy to install as it is already known at the design drawing stage. Simultaneously with the completion of the wall panel installation, the assembly of the second floor floor beam will be completed. [FIG. 8] shows the mounting state of the second floor panel. At the same time that the wall panels on the first floor were installed, the floor beams on the second floor were also installed. This is because the wall panel on the first floor is also attached and fixed to the structural frame member for the second floor. The floor panel attached to the floor beam for the second floor is attached similarly to the floor panel for the first floor. The floor panel may include a heat insulating material or the like. The floor panels are fixed in the same way as the floor panels on the first floor. Needless to say, the necessary structure is also provided on the floor panels on the second floor. It is natural because it is necessary to install the wall panel on the second floor. Also,
The stairway opening to the second floor is also provided where necessary. In this way, the second floor panel is attached. Here too, the bait beam can be omitted. [FIG. 9] shows a state in which the second floor wall panel is attached. After completing the installation of the second floor panel, the required wall panels on the second floor, as well as the first floor wall panel, are fixed to the required locations along with the structural frame members, as in the first floor. Install the wall panel of. Wall panel applications,
The purpose is to attach and fix the necessary parts to each required part by a known method as in the case of the first floor. By installing the panels in this way, the studs,
It is possible to omit a necessary member such as a brace. In this way, the second floor wall panel is attached. Simultaneously with the installation of the wall panel, the roof structural frame member is also installed. A portion of the roof structural frame members also secures the second floor wall panel. [FIG. 10] [FIG. 1
1] shows a state in which the roof panel is attached. Simultaneously with the completion of the second floor wall panel installation, the roof portion is formed by roof structural frame members, such as paved, lantern, spruce, purlin, and other members. After the roofs are formed, the required number of roof panels are laid and fixed on each roof. The roof plate is thus provided. The building of the exterior of the house is completed by laying and fixing the roof panels. [FIG. 12] shows a state in which the building of the house performed by this method is completed. By this construction method, it will be completed in about two days until the construction is completed. The number of carpenters will be 5-6, and the total number will be 10-12. Even after the building of the house is completed, the method using this panel is used thereafter. FIG. 13 shows the use of the eaves panel. The eaves panel is used on the eaves of houses and is installed behind the eaves. This eaves panel can be used not only as a panel frame but also in a state where a plywood material or the like is stretched over the panel frame. When used only as a panel frame, various plywood materials or other board materials can be used at a later date according to the preference of the orderer. [Fig. 14]
Indicates the usage status of the ceiling panel. Although the building of the house is completed and it is used when building the interior of the house, the ceiling panel is also attached to the ceiling of the first floor or the ceiling of the second floor. Conventionally, a ceiling is provided with a ceiling board on the periphery, a back rail is provided on the ceiling board, and the ceiling board is provided with a structure such as hanging by a tree. Therefore, the ceiling is formed without using many conventional members. The ceiling panel can also be used as a panel frame,
At the time of finishing the interior at a later date, it is possible to use plywood materials and other board materials of your choice. [FIG. 15] shows a vibration-proof suspension. The anti-vibration hanger is used not only for lifting the ceiling panel but also for preventing the ceiling panel from shaking. By using this anti-vibration hanger, it is intended to absorb the sway applied to the ceiling panel as much as possible and to reduce the sway of the entire house as much as possible. Thus, the invention is
It is a method that was not seen before, and for structural frame members,
It is possible to build a wooden house by a simple method of installing the required number of panels. As such, many other components that would normally be needed can be omitted in this way. For example, a connecting beam is not required, and it is possible to omit staking beams, studs, braces, and the like. Also in the ceiling structure, for example, the peripheral edge may be unnecessary. Thus, the present invention provides a method never before seen in home construction.

【0006】[0006]

【発明の効果】このように構成されるこの方法の発明
は、プレカットした構造軸組部材にパネル化した各部位
を簡単に取り付けることができるので、主に現場での工
数削減、工期の短縮、施行の簡略化、大工の有効利用、
住宅機能・居住性の向上、作業の安全等々が大きく向上
を有するものである。例えば、この工法を採用すること
により、工期については、土台の構築から屋根の取り付
けまでほとんど二日間程度で済むという効果を有するも
のである。また、従前に比して、部材数が少なくして済
み、更には、耐震性、通気性にもすぐれた効果を有する
ものである。このように、この発明は、従前には求めら
れなかった大きな効果を有するものである。
According to the invention of this method constructed as described above, each panelized portion can be easily attached to the pre-cut structural frame member, so that mainly the on-site man-hours and the construction period can be shortened. Simplification of enforcement, effective use of carpenter,
It has significant improvements in housing functions, habitability, work safety, and so on. For example, by adopting this construction method, the construction period has an effect that it takes almost two days from the construction of the foundation to the installation of the roof. In addition, the number of members is smaller than before, and further, it has excellent effects on earthquake resistance and air permeability. As described above, the present invention has a great effect which has not been required before.

【図面の簡単な説明】[Brief description of drawings]

【図1】 土台下に敷かれるパッキンの全体参考図[Fig. 1] Overall reference diagram of packing laid under the base

【図2】 土台取付状態部分参考図[Fig. 2] Reference diagram of the state where the base is attached

【図3】 土台敷き1階部床梁入れ完了部分参考図[Fig. 3] Reference drawing for the part where the floor beams have been placed on the ground floor

【図4】 1階部床パネル敷き完了部分参考図[Fig. 4] Reference drawing for the completed floor panel laying on the first floor

【図5】 1階部構造軸組及び壁パネル外側部分参考
[Fig. 5] Reference drawing of the first floor structural framework and the outer part of the wall panel

【図6】 1階部構造軸組及び壁パネル内側部分参考
[Fig. 6] Reference drawing of the first floor structural framework and the inner part of the wall panel

【図7】 2階部構造軸組[床梁]入れ完了部分参考
[Fig. 7] Reference drawing for the completed part of the 2nd floor structural framework [floor beam]

【図8】 2階部床パネル敷き状態部分参考図[Figure 8] Second floor floor panel laid state reference diagram

【図9】 2階部構造軸組及び壁パネル部分参考図[Fig. 9] Reference drawing of structural framework and wall panel for the second floor

【図10】 屋根パネル及び構造軸組部分参考図[Fig.10] Roof panel and structural frame part reference diagram

【図11】 屋根パネル敷き状態部分参考図[Fig. 11] Reference drawing of the roof panel laying part

【図12】 建て方完了全体参考図[Fig.12] Reference diagram for the entire building process

【図13】 構造軸組及び軒天パネル取り付け部分参
考図
[Fig. 13] Reference diagram of structural frame and eaves panel installation part

【図14】 構造軸組及び天井パネル取り付け全体参
考図
FIG. 14: Reference diagram for the entire structural framework and ceiling panel installation

【図15】 天井パネル防振吊具全体参考図[Fig.15] Reference drawing for the whole of the ceiling panel anti-vibration hanger

【図16】 パネル取付部位を示す片面参考図FIG. 16 is a one-sided reference diagram showing a panel mounting portion.

【符合の説明】[Explanation of sign]

(1)…………床パネル (2)…………壁パネル (3)…………屋根パネル (4)…………軒天パネル (5)…………天井パネル (1) ………… Floor panel (2) ………… Wall panel (3) ………… Roof panel (4) ………… Eaves panel (5) ………… Ceiling panel

─────────────────────────────────────────────────────
─────────────────────────────────────────────────── ───

【手続補正書】[Procedure amendment]

【提出日】平成5年10月14日[Submission date] October 14, 1993

【手続補正1】[Procedure Amendment 1]

【補正対象書類名】明細書[Document name to be amended] Statement

【補正対象項目名】図面の簡単な説明[Name of item to be corrected] Brief description of the drawing

【補正方法】変更[Correction method] Change

【補正内容】[Correction content]

【図面の簡単な説明】[Brief description of drawings]

【図1】 土台下に敷かれるパッキンの
全体状態図
[Figure 1] Overall state diagram of packing laid under the base

【図2】 土台取付状態部分図[Fig. 2] Partial view of base mounting state

【図3】 土台敷き1階部床梁入れ完了
部分図
[Fig. 3] Partial view of the first floor floor beam insertion completed

【図4】 1階部床パネル敷き完了部分
[Fig. 4] Partial drawing of the completed floor panel on the first floor

【図5】 1階部構造軸組及び壁パネル
外側部分図
FIG. 5: Partial view of the first floor structural framework and outside wall panel

【図6】 1階部構造軸組及び壁パネル
内側部分図
FIG. 6 Partial view of the first floor structural framework and inside wall panel

【図7】 2階部構造軸組[床梁]入れ
完了部分図
[Figure 7] Partial view of the 2nd floor structural framework [floor beam] insertion completed

【図8】 2階部床パネル敷き状態部分
[Figure 8] Partial view of the second floor floor panel layout

【図9】 2階部構造軸組及び壁パネル
部分図
[Fig. 9] Partial view of the second floor structural framework and wall panel

【図10】 屋根パネル及び構造軸組部分
FIG. 10 Partial view of roof panel and structural frame

【図11】 屋根パネル敷き状態部分図[Figure 11] Partial view of the roof panel

【図12】 建て方完了全体図[Fig. 12] Overall view of building completion

【図13】 構造軸組及び軒天パネル取付
け部分図
FIG. 13: Partial view of structural framework and eaves panel installation

【図14】 構造軸組及び天井パネル取付
け部分図
FIG. 14: Partial view of structural framework and ceiling panel installation

【図15】 天井パネル防振吊具全体図[Fig.15] Overall view of anti-vibration suspenders for ceiling panel

【図16】 パネル取付部位を示す片面図FIG. 16 is a one side view showing a panel mounting portion.

【手続補正2】[Procedure Amendment 2]

【補正対象書類名】図面[Document name to be corrected] Drawing

【補正対象項目名】全図[Correction target item name] All drawings

【補正方法】変更[Correction method] Change

【補正内容】[Correction content]

【図1】 [Figure 1]

【図2】 [Fig. 2]

【図3】 [Figure 3]

【図4】 [Figure 4]

【図5】 [Figure 5]

【図6】 [Figure 6]

【図7】 [Figure 7]

【図8】 [Figure 8]

【図9】 [Figure 9]

【図12】 [Fig. 12]

【図10】 [Figure 10]

【図11】 FIG. 11

【図13】 [Fig. 13]

【図14】 FIG. 14

【図15】 FIG. 15

【図16】 FIG. 16

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】木造家屋建築方法において、各々複数の規
格を有する床パネル、壁パネル、屋根パネル、軒天パネ
ル、天井パネルと予め加工される構造軸組部材とを用
い、該構造軸組部材を適所適便に使用し、家屋土台部を
形成し、次に適便規格の床パネルを任意数、該土台部構
造軸組部材に組み合わせ固定し、家屋1階部の床を形成
し、次に適便規格の壁パネルを任意数、構造軸組部材と
ともに組み合わせ固定し、家屋1階部の外壁・内壁及び
間仕切壁としての側壁を形成し、家屋1階部とし、次に
2階部も1階部同様、構造軸組部材に、任意数の適便規
格の床パネルを組み合わせ固定し、2階部床を形成し、
後、1階部同様に、適便規格の壁パネルを任意数、構造
軸組部材とともに組み合わせ固定し、2階部の外壁・内
壁及び間仕切壁としての側壁を形成して、2階部を形成
し、以後、同様に適便規格の屋根パネル、軒天パネル、
天井パネルの任意数を構造軸組部材とともに組み合わせ
固定し、各々家屋の屋根、軒天、天井の各部を形成して
行くことによって木造家屋を建築することを特徴とする
木造家屋建築方決。
1. A method for constructing a wooden house, wherein a floor panel, a wall panel, a roof panel, an eaves panel, a ceiling panel and a structural framing member which are preprocessed, each having a plurality of standards, are used. To form the base of the house, and then attach and fix any number of floor panels conforming to the applicable standards to the base structure structural members to form the floor of the first floor of the house. A number of wall panels conforming to the appropriate standard are combined and fixed together with the structural frame members to form the outer and inner walls of the first floor of the house and side walls as partition walls, and the first floor of the house, and then the second floor as well. As with the first floor, the structural frame members are combined and fixed with any number of floor panels conforming to the appropriate flight standards to form the second floor.
After that, similarly to the first floor, an arbitrary number of wall panels conforming to the appropriate flight standards are combined and fixed together with the structural frame members to form the outer and inner walls of the second floor and side walls as partition walls to form the second floor. After that, likewise, roof panels, eaves panels, etc.
A wooden house construction method characterized by constructing a wooden house by combining and fixing any number of ceiling panels together with structural frame members and forming each part of the roof, eaves and ceiling of the house.
JP5200892A 1992-01-28 1992-01-28 Building method of wooden house by use of panel Pending JPH06212688A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP5200892A JPH06212688A (en) 1992-01-28 1992-01-28 Building method of wooden house by use of panel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP5200892A JPH06212688A (en) 1992-01-28 1992-01-28 Building method of wooden house by use of panel

Publications (1)

Publication Number Publication Date
JPH06212688A true JPH06212688A (en) 1994-08-02

Family

ID=12902798

Family Applications (1)

Application Number Title Priority Date Filing Date
JP5200892A Pending JPH06212688A (en) 1992-01-28 1992-01-28 Building method of wooden house by use of panel

Country Status (1)

Country Link
JP (1) JPH06212688A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017120023A (en) * 2015-12-25 2017-07-06 大根 弘行 Bearing wall and building structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017120023A (en) * 2015-12-25 2017-07-06 大根 弘行 Bearing wall and building structure

Similar Documents

Publication Publication Date Title
US5359816A (en) Buildings and methods of constructing buildings
JPH06212688A (en) Building method of wooden house by use of panel
US5177914A (en) Vertical section building construction
JPH0718744A (en) Domelike structure
JP2003049484A (en) Construction method for wooden house
JP3854404B2 (en) building
JP7096606B2 (en) Wall structure, wooden building, and how to build a wooden building
JP2003049481A (en) Construction method for wooden house
JP2003336312A (en) Building
JPH053636Y2 (en)
JP3510791B2 (en) Building unit with air conditioner and unit building
WO1997012099A1 (en) Joint connector device and method for assembling prefabricated building panels
KR100490486B1 (en) Panelized Wood Construction Method
JP2889472B2 (en) Building exterior wall panels and building exterior walls using the panels
JPH09325689A (en) Structural cross section confirmation mechanism of house
JP3207311B2 (en) Roof structure with setback unit
JP3496073B2 (en) Building method
JPH08326159A (en) Unit building
JP4007953B2 (en) Building construction method
JPS6221940A (en) Outer contour building method of wood framework prefabricated house
JPS627808Y2 (en)
JPH0355327A (en) Building and constructing technique therefor
JPH11236731A (en) Wooden building and execution method of feather pattern material thereof
JP2004324309A (en) Woody building
JPH08333838A (en) Roof unit with separation wall