JPH0620604U - Steel column joint structure - Google Patents

Steel column joint structure

Info

Publication number
JPH0620604U
JPH0620604U JP6003192U JP6003192U JPH0620604U JP H0620604 U JPH0620604 U JP H0620604U JP 6003192 U JP6003192 U JP 6003192U JP 6003192 U JP6003192 U JP 6003192U JP H0620604 U JPH0620604 U JP H0620604U
Authority
JP
Japan
Prior art keywords
column
metal
joint
steel
joined
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP6003192U
Other languages
Japanese (ja)
Inventor
英史 久鍋
茂 平川
英成 松尾
Original Assignee
日立金属株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 日立金属株式会社 filed Critical 日立金属株式会社
Priority to JP6003192U priority Critical patent/JPH0620604U/en
Publication of JPH0620604U publication Critical patent/JPH0620604U/en
Pending legal-status Critical Current

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

(57)【要約】 【目的】 鉄骨造又は鉄骨鉄筋コンクリート造建築物の
鉄骨柱どうしを接合するとき、建築現場における溶接作
業をなくし、溶接接合部品質の安定性向上、接合作業の
簡略化、作業時間の短縮等を目的とする。 【構成】 鉄骨柱1の端部と溶接接合する柱接合部2
と、ボルト穴を有する基部4と、柱接合部と基部との間
に位置し柱接合部及び基部の外形寸法より一部又は全体
が小さい断面の胴部3とから成る金物A5を溶接接合し
た鉄骨柱1と、前記柱接合部と基部と胴部と同一の構成
を有する金物B10を溶接接合した他の鉄骨柱6とを、
前記金物A5及び前記金物B10の基部4、9にてボル
ト接合11、12する。
(57) [Abstract] [Purpose] When joining steel columns of a steel frame or steel reinforced concrete structure, eliminating welding work at the construction site, improving the stability of the quality of welded joints, simplifying the joining work, and working The purpose is to reduce the time. [Structure] A column joint portion 2 that is welded to an end of a steel column 1
And a metal part A5 consisting of a base part 4 having a bolt hole and a body part 3 which is located between the pillar joint part and the base part and has a cross section partially or wholly smaller than the outer dimensions of the pillar joint part and the base part. A steel frame pillar 1 and another steel frame pillar 6 to which a metal fitting B10 having the same structure as the pillar joint portion, the base portion and the body portion is welded and joined,
The bolts 11 and 12 are joined at the bases 4 and 9 of the metal piece A5 and the metal piece B10.

Description

【考案の詳細な説明】[Detailed description of the device]

【0001】[0001]

【産業上の利用分野】[Industrial applications]

本考案は鉄骨造又は鉄骨鉄筋コンクリート造建物の鉄骨柱と鉄骨柱の接合部構 造に関する。 The present invention relates to a joint structure between steel columns and steel columns of a steel frame structure or a steel frame reinforced concrete building.

【0002】[0002]

【従来の技術】[Prior art]

従来、鉄骨柱と鉄骨柱との接合は、図15、図16に示す方法で行なわれてい た。先ず接合しようとする鉄骨柱6の裏側に裏当金15を当接して固定する。次 に鉄骨柱6と鉄骨柱1とを接合治具16により固定した後、溶接により柱1、6 を接合17する。 また、実開昭62−38304号公報には、はりと接合する仕口部用の金物の 上部に、柱と接合する金物を締結した、柱と柱接合装置が記載されているが、鉄 骨柱どうしの接合に関するものではない。 Conventionally, the steel column and the steel column are joined by the method shown in FIGS. 15 and 16. First, the backing plate 15 is abutted and fixed to the back side of the steel column 6 to be joined. Next, the steel columns 6 and the steel columns 1 are fixed by a joining jig 16, and the columns 1 and 6 are joined 17 by welding. Further, Japanese Utility Model Laid-Open No. 62-38304 discloses a pillar-to-column joining device in which a fitting to be joined to a beam is fastened to an upper portion of a fitting to be joined to a beam. It is not about joining columns together.

【0003】[0003]

【考案が解決しようとする課題】[Problems to be solved by the device]

上記従来の接合方法は、建築現場での屋外溶接作業となるので、溶接作業時の 天候等により接合部の品質が左右されてばらつきがある。また、溶接作業工数以 外に、鉄骨柱へ裏当金と接合治具の取付け、溶接接合完了後に接合治具の除去等 の実質作業以外の付帯作業工数を必要とするが、建築現場にてこのような多大の 工数を要すると工期の遅延を招く恐れがある。 従って本考案は、建築現場にて鉄骨柱と鉄骨柱を接合するに際し、溶接作業を なくして溶接接合部の品質の安定性向上を図ると共に、接合作業の簡略化、作業 時間の短縮等を目的とする。 Since the above-mentioned conventional joining method is an outdoor welding work at a construction site, the quality of the joint varies depending on the weather at the time of the welding work. In addition to the man-hours required for welding, additional man-hours other than the actual work such as attaching the backing metal and joining jig to the steel column and removing the joining jig after welding and joining are required at the construction site. If such a large number of man-hours are required, the work period may be delayed. Therefore, the present invention aims to improve the stability of the quality of the welded joint by eliminating the welding work when joining steel columns to each other at a construction site, simplify the joining work, and shorten the work time. And

【0004】[0004]

【課題を解決するための手段】[Means for Solving the Problems]

本考案は、予め工場において、鉄骨柱の接合しようとする端部に金物を溶接に より取付けておく。次に、この柱を建築現場に持ち込み、金物を取付けた他の柱 の金物の基部とボルト、ナットで締結することにより、鉄骨柱どうしの接合を可 能とするものである。 先ず第1の考案は、鉄骨柱の端部と溶接接合する柱接合部と、ボルト穴を有す る基部と、柱接合部と基部との間に位置し柱接合部及び基部の外形寸法より一部 又は全体が小さい断面の胴部とから成る金物Aを溶接接合した鉄骨柱と、前記柱 接合部と基部と胴部と同一の構成を有する金物Bを溶接接合した他の鉄骨柱とを 、前記金物A及び前記金物Bの基部にてボルト接合する接合部の構造である。 次に第2の考案は、上記第1の考案における金物A及び/又は金物Bの胴部を 中実にし、同じく第3の考案は、胴部を中空にする。 更に第4の考案は、上記第1乃至3の考案における金物A及び/又は金物Bの 鉄骨柱と接合する柱接合部に、溶接開先と裏当部を有する突出部を設け、同じく 第5の考案は、ボルト接合するための突出部を設ける接合部の構造である。 更に第6の考案は、上記第1乃至5の考案における金物Aと金物Bのそれぞれ の基部接合面において、いずれか一方の金物の接合面に凸状部を、他方の金物の 接合面に凹状部を設け、凹状部の中に凸状部を挿入して凹凸嵌合し、同じく第7 の考案は、いずれか一方の金物の接合部に凸状突出部を、他方の金物の接合部に 凹状穴部を設け、凹状穴部の中に凸状突出部を挿入してはめあい嵌合し、はめあ い嵌合した側面においてボルトで固定する接合部の構造である。 In the present invention, a metal object is attached to the end of the steel column to be joined by welding in advance in a factory. Next, by bringing this column to the construction site and fastening it to the base of the metal of another column to which the metal is attached with bolts and nuts, it is possible to join the steel columns together. First of all, the first invention is based on the external dimensions of the column joint portion and the base portion which are located between the column joint portion which is welded and joined to the end portion of the steel column, the base portion having the bolt holes, and the column joint portion and the base portion. A steel frame column welded and joined to the metal A, which is partially or wholly composed of a body having a small cross section, and another steel frame column welded and joined to the column joint, the base, and the metal B having the same structure as the body. , A structure of a joint portion where bolts are joined at the bases of the metal A and the metal B. Next, in the second invention, the body of the hardware A and / or B in the first invention is made solid, and in the third invention, the body is made hollow. Further, a fourth invention is to provide a projecting portion having a welding groove and a backing portion at a column joint portion of the metal article A and / or the metal article B in the first to third inventions, which is joined to the steel frame column, and the fifth invention is also provided. The invention of [1] is a structure of a joint portion provided with a protruding portion for bolt-joining. Further, the sixth invention is such that, in the respective base joint surfaces of the metal pieces A and B in the first to fifth inventions, a convex portion is formed on one of the metal piece joint surfaces and a concave portion is formed on the other metal piece joint surface. And a convex portion is inserted into the concave portion to fit the concave and convex portions. Similarly, the seventh invention is that the convex projecting portion is provided at the joint portion of one of the metal pieces and the convex projecting portion is formed at the joint portion of the other metal article. This is a joint structure in which a concave hole portion is provided, a convex protruding portion is inserted into the concave hole portion, and they are fitted and fitted, and the side faces where the fitting is fitted are fixed by bolts.

【0005】[0005]

【作用及び効果】[Action and effect]

本考案によれば、工場建屋内での溶接作業が可能となるので、従来のような建 築現場での溶接作業が不要となり、溶接時の天候、湿度、気温等による溶接接合 部の品質のばらつきが防止される。また、鉄骨柱へ裏当金と接合治具の取り付け 、鉄骨柱の溶接接合が完了後の接合治具の除去等実質作業以外の付帯作業が不要 となる。本考案の接合部はボルト接合であるので、上記不都合が排除されると共 に、建築現場にて簡便に作業ができる。 According to the present invention, since the welding work in the factory building is possible, the conventional welding work at the construction site is unnecessary, and the quality of the welded joint due to the weather, humidity, temperature, etc. during welding can be improved. Variation is prevented. In addition, it is not necessary to perform additional work other than the actual work such as attaching the backing plate and the joining jig to the steel column, and removing the joining jig after the welding and joining of the steel column is completed. Since the joint portion of the present invention is a bolt joint, the above inconvenience is eliminated, and at the same time, it is possible to easily perform the work at the construction site.

【0006】[0006]

【実施例】【Example】

図1及び図2はそれぞれ本考案の第1実施例の平面図及び側面図である。 金物A5及び金物B10はそれぞれ柱接合部2、7と基部4、9と胴部3、8 にて構成される。鉄骨柱1及び6はBOX形の閉鎖断面柱であり、その端部はそ れぞれ金物の柱接合部2、7に溶接接合されている。金物の基部4、9にはボル ト穴が形成されており、ボルト11とナット12で基部4、9を締結することに より、鉄骨柱1と鉄骨柱6とが接合される。胴部3、8は中実になっているので 、鉄骨柱1、6の外形寸法より、小さな断面になっていても、鉄骨柱と同等以上 の強度及び剛性を確保できる。 1 and 2 are a plan view and a side view, respectively, of a first embodiment of the present invention. The hardware A5 and the hardware B10 are composed of the column joint portions 2 and 7, the base portions 4 and 9, and the body portions 3 and 8, respectively. The steel columns 1 and 6 are BOX-shaped closed cross-section columns, and their ends are welded to the column joints 2 and 7 of the hardware, respectively. Bolt holes are formed in the base parts 4 and 9 of the metal object, and the steel columns 1 and 6 are joined by fastening the base parts 4 and 9 with the bolts 11 and the nuts 12. Since the body portions 3 and 8 are solid, even if the cross-section is smaller than the outer dimensions of the steel frame columns 1 and 6, strength and rigidity equal to or higher than those of the steel frame columns can be secured.

【0007】 図3及び図4はそれぞれ本考案の第2実施例の平面図及び側面図である。 鉄骨柱は鉄骨鉄筋コンクリート造に一般的に用いられるT字形鋼1、6であり 、前記実施例と同様に、その端部はそれぞれ金物の柱接合部2、7に溶接接合さ れている。本実施例では、金物A5と金物B10の柱接合部は鉄骨柱の断面外形 を包含した四辺形になっているので、T字形鋼以外のクロスH形鋼やH形鋼等の 鉄骨柱の場合でも同様な形状の金物で対応できる。この金物の胴部3、8も上記 第1実施例と同様に中実になっているので、鉄骨柱と同等以上の性能の胴部が得 られる。3 and 4 are a plan view and a side view, respectively, of a second embodiment of the present invention. The steel columns are T-shaped steels 1 and 6 which are generally used for steel reinforced concrete construction, and the ends thereof are welded and joined to the column joints 2 and 7 of the metal parts, respectively, as in the above embodiment. In the present embodiment, since the column joints of the hardware A5 and the metal B10 are quadrilaterals including the cross-sectional outer shape of the steel column, in the case of steel column such as cross H-section steel or H-section steel other than T-section steel. However, it can be handled with a similar shape of hardware. Since the body parts 3 and 8 of the metal object are also solid as in the first embodiment, a body part having a performance equal to or higher than that of the steel column can be obtained.

【0008】 図5及び図6はそれぞれ本考案の第3実施例の平面図及び側面図である。 本実施例は胴部3、8にそれぞれ中空部3a、8aを設けた金物を用いた場合 である。これによって金物の重量及びコストの低減が図れる。5 and 6 are a plan view and a side view, respectively, of a third embodiment of the present invention. In this embodiment, the metal parts having the hollow parts 3a and 8a in the body parts 3 and 8 are used. As a result, the weight and cost of the hardware can be reduced.

【0009】 図7及び図8はそれぞれ本考案の第4実施例の平面図及び側面図である。 本実施例は金物A5と金物B10の柱接合部2、7に鉄骨柱1、6との溶接用 開先2a、7aと裏当部2b、7bを設けた金物を採用したものである。これに より鉄骨柱側の開先や裏当金の取り付けが不要となり、鉄骨加工工場での加工工 数の低減及び工期の短縮が可能となる。7 and 8 are a plan view and a side view, respectively, of a fourth embodiment of the present invention. In this embodiment, the metal fitting A5 and the metal fitting B10 are provided with the welding portions 2a and 7a for welding the steel columns 1 and 6 and the backing portions 2b and 7b at the column joining portions 2 and 7, respectively. This eliminates the need to install a groove on the steel column side or a backing plate, which can reduce the processing man-hours and the work period at the steel frame processing plant.

【0010】 図9及び図10はそれぞれ本考案の第5実施例の平面図及び側面図である。 本実施例は金物A5と金物B10の柱接合部2、7に鉄骨柱1、6とボルト1 3接合するための突出部2c、7cを設けたものであり、突出部にはボルト13 を固定するためのタップ穴2d、7dが設けてある。本金物は鉄骨柱とボルト接 合されるので、鋳鋼、鍛鋼のみならず球状黒鉛鋳鉄の材料でも適用可能である。9 and 10 are a plan view and a side view, respectively, of a fifth embodiment of the present invention. In this embodiment, the protrusions 2c and 7c for connecting the steel columns 1 and 6 and the bolts 13 to the column joints 2 and 7 of the metal A5 and the metal B10 are provided, and the bolts 13 are fixed to the protrusions. There are tapped holes 2d and 7d for doing so. Since this metal is bolted to a steel column, it can be applied to not only cast steel and forged steel but also spheroidal graphite cast iron.

【0011】 図11及び図12はそれぞれ本考案の第6実施例の平面図及び側面図である。 本実施例は金物A5及び金物B10の基部4、9の接合面に凹凸状部4a、9 aを設け、凹凸嵌合する金物5、10を採用したものである。これにより、鉄骨 柱接合時の芯出し作業工数の低減が可能となる。11 and 12 are a plan view and a side view, respectively, of a sixth embodiment of the present invention. In the present embodiment, uneven parts 4a and 9a are provided on the joint surfaces of the base parts 4 and 9 of the metal parts A5 and B10, and the metal parts 5 and 10 which are fitted in the concave and convex parts are adopted. This makes it possible to reduce the man-hours for centering work when joining steel columns.

【0012】 図13及び図14はそれぞれ本考案の第7実施例の平面図及び側面図である。 本実施例は金物A5及び金物B10の基部4、9の接合部において、いずれか 一方の金物として金物A5の基部接合部に凸状突出部4bを形成し、他方の金物 B10に凹状穴部9bを形成し、凹状穴部9bの中に凸状突出部4bを挿入して はめあい嵌合し、側面においてボルト14で固定する。これによっても、鉄骨柱 接合時の芯出し作業工数の低減が可能となる。13 and 14 are a plan view and a side view, respectively, of a seventh embodiment of the present invention. In this embodiment, in the joint portion between the base portions 4 and 9 of the metal piece A5 and the metal piece B10, a convex protrusion 4b is formed on the base portion of the metal piece A5 as one of the metal pieces, and the concave hole portion 9b is formed on the other metal piece B10. Then, the convex projecting portion 4b is inserted into the concave hole portion 9b, fitted and fitted, and fixed on the side surface with the bolt 14. This also makes it possible to reduce the man-hours for centering work when joining steel columns.

【0013】[0013]

【考案の効果】[Effect of device]

本考案により、建築現場の溶接作業をなくし、溶接接合部の品質向上、接合作 業の簡略化、作業時間の短縮等が可能となる。 According to the present invention, it is possible to eliminate the welding work at the construction site, improve the quality of the welded joint, simplify the welding work, and shorten the working time.

【図面の簡単な説明】[Brief description of drawings]

【図1】本考案第1実施例の平面図である。FIG. 1 is a plan view of a first embodiment of the present invention.

【図2】本考案第1実施例の側面図である。FIG. 2 is a side view of the first embodiment of the present invention.

【図3】本考案第2実施例の平面図である。FIG. 3 is a plan view of a second embodiment of the present invention.

【図4】本考案第2実施例の側面図である。FIG. 4 is a side view of a second embodiment of the present invention.

【図5】本考案第3実施例の平面図である。FIG. 5 is a plan view of a third embodiment of the present invention.

【図6】本考案第3実施例の側面図である。FIG. 6 is a side view of a third embodiment of the present invention.

【図7】本考案第4実施例の平面図である。FIG. 7 is a plan view of a fourth embodiment of the present invention.

【図8】本考案第4実施例の側面図である。FIG. 8 is a side view of a fourth embodiment of the present invention.

【図9】本考案第5実施例の平面図である。FIG. 9 is a plan view of a fifth embodiment of the present invention.

【図10】本考案第5実施例の側面図である。FIG. 10 is a side view of a fifth embodiment of the present invention.

【図11】本考案第6実施例の平面図である。FIG. 11 is a plan view of a sixth embodiment of the present invention.

【図12】本考案第6実施例の側面図である。FIG. 12 is a side view of a sixth embodiment of the present invention.

【図13】本考案第7実施例の平面図である。FIG. 13 is a plan view of a seventh embodiment of the present invention.

【図14】本考案第7実施例の側面図である。FIG. 14 is a side view of a seventh embodiment of the present invention.

【図15】従来の鉄骨柱接合方法を説明する平面図であ
る。
FIG. 15 is a plan view illustrating a conventional steel frame column joining method.

【図16】従来の鉄骨柱接合方法を説明する側面図であ
る。
FIG. 16 is a side view explaining a conventional method of joining a steel frame column.

【符号の説明】[Explanation of symbols]

1、6…鉄骨柱 2、7…柱接合部
3、8…胴部 4、9…基部 5…金物A
10…金物B 11…ボルト 12…ナット 1
5…裏当金 16…接合治具 17…溶接接合部
1, 6 ... Steel columns 2, 7 ... Column joints
3, 8 ... Body 4, 9 ... Base 5 ... Hardware A
10 ... Hardware B 11 ... Bolt 12 ... Nut 1
5 ... Backing metal 16 ... Joining jig 17 ... Welded joint

Claims (7)

【実用新案登録請求の範囲】[Scope of utility model registration request] 【請求項1】 鉄骨柱の端部と溶接接合する柱接合部
と、ボルト穴を有する基部と、柱接合部と基部との間に
位置し柱接合部及び基部の外形寸法より一部又は全体が
小さい断面の胴部とから成る金物Aを溶接接合した鉄骨
柱と、前記柱接合部と基部と胴部と同一の構成を有する
金物Bを溶接接合した他の鉄骨柱とを、金物A及び金物
Bの基部にてボルト接合してなることを特徴とする鉄骨
柱の接合部構造。
1. A column joint portion which is welded and joined to an end portion of a steel column, a base portion having a bolt hole, a portion which is located between the column joint portion and the base portion, and a part or the whole of the outer dimensions of the column joint portion and the base portion. A steel frame column welded and joined to a metal article A comprising a body having a small cross section, and another steel frame column welded and joined to a metal article B having the same structure as the column joint part, the base and the body part. A joint portion structure of a steel column, characterized in that the base portion of the hardware B is joined by bolts.
【請求項2】 金物A及び/又は金物Bの胴部が中実で
ある請求項1記載の鉄骨柱の接合部構造。
2. The joint structure of a steel column according to claim 1, wherein the body of the hardware A and / or the metal B is solid.
【請求項3】 金物A及び/又は金物Bの胴部が中空で
ある請求項1記載の鉄骨柱の接合部構造。
3. The joint structure of a steel column according to claim 1, wherein the body of the hardware A and / or the metal B is hollow.
【請求項4】 金物A及び/又は金物Bの鉄骨柱と接合
する柱接合部に、溶接開先と裏当部を有する突出部を設
けた請求項1乃至3記載の鉄骨柱の接合部構造。
4. The joint structure of a steel column according to claim 1, wherein a protrusion having a welding groove and a backing portion is provided at a column joint portion of the metal piece A and / or the metal piece B which is joined to the steel frame pillar. .
【請求項5】 金物A及び/又は金物Bの鉄骨柱と接合
する柱接合部に、ボルト接合するための突出部を設けた
請求項1乃至3記載の鉄骨柱の接合部構造。
5. The joint structure of a steel frame pillar according to claim 1, wherein a protrusion portion for bolting is provided at a column joint portion of the metal piece A and / or the metal piece B that is joined to the steel frame pillar.
【請求項6】 金物Aと金物Bのそれぞれの基部の接合
面において、いずれか一方の金物の接合面に凸状部を、
他方の金物の接合面に凹状部を設け、凹状部の中に凸状
部を挿入して、凹凸嵌合することを特徴とする請求項1
乃至5記載の鉄骨柱の接合部構造。
6. A convex portion is formed on a joining surface of either one of the bases of the metal pieces A and B,
The concave portion is provided on the joint surface of the other metal object, and the convex portion is inserted into the concave portion to engage with the concave and convex portions.
The joint structure of the steel frame according to any one of claims 1 to 5.
【請求項7】 金物Aと金物Bのそれぞれの基部の接合
部において、いずれか一方の金物の接合部に凸状突出部
を、他方の金物の接合部に凹状穴部を設け、凹状穴部の
中に凸状突出部を挿入してはめあい嵌合し、はめあい嵌
合した側面においてボルトで固定することにより接合す
ることを特徴とする請求項1乃至5記載の鉄骨柱の接合
部構造。
7. At the joints of the bases of the metal pieces A and B, a convex protrusion is provided at the joint portion of one of the metal pieces, and a concave hole portion is provided at the joint portion of the other metal piece. 6. The joint structure for a steel column according to claim 1, wherein a convex projection is inserted into the inside to fit and fit, and the side surface where the fitting is fitted is fixed by a bolt.
JP6003192U 1992-08-26 1992-08-26 Steel column joint structure Pending JPH0620604U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP6003192U JPH0620604U (en) 1992-08-26 1992-08-26 Steel column joint structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP6003192U JPH0620604U (en) 1992-08-26 1992-08-26 Steel column joint structure

Publications (1)

Publication Number Publication Date
JPH0620604U true JPH0620604U (en) 1994-03-18

Family

ID=13130297

Family Applications (1)

Application Number Title Priority Date Filing Date
JP6003192U Pending JPH0620604U (en) 1992-08-26 1992-08-26 Steel column joint structure

Country Status (1)

Country Link
JP (1) JPH0620604U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011064041A (en) * 2009-09-18 2011-03-31 Hitachi Metals Techno Ltd Column joint structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011064041A (en) * 2009-09-18 2011-03-31 Hitachi Metals Techno Ltd Column joint structure

Similar Documents

Publication Publication Date Title
JPH0620604U (en) Steel column joint structure
JPH08311989A (en) Joint structure of steel skeleton building construction
JPH09217419A (en) Reinforcing structure of steel frame member
JPH08284250A (en) Joint section of wooden pillar and steel framed beam
JPH1150556A (en) Joint structure of base with column
JPH0636125Y2 (en) Independent pillar
JP2662763B2 (en) Column / beam joint
JP2612152B2 (en) Pillar
JP2569618Y2 (en) Work stage for steel structure
JP3034563U (en) Tie rod device for construction or civil engineering where functional components are joined using friction welding
JPH0512398Y2 (en)
JP2004169372A (en) Welding joint structure of pole and beam
JPH06185114A (en) Joining method for steel-pipe column
JPH0711204Y2 (en) Joint structure of columns and beams
JPH027964Y2 (en)
JPS5835767Y2 (en) Joining hardware between H-shaped columns and beams in steel frame structures
JPH0732646Y2 (en) Beam-column joint structure of non-orthogonal part
JP2662760B2 (en) Joint structure between steel pipe column and beam
JPS6136607Y2 (en)
JP2669282B2 (en) Pillar structure
JPH0245361Y2 (en)
JPH0762742A (en) Fixing method for pedestal of steelwork pillar in precast reinforced concrete pillar
JPH076304U (en) Column base structure
JPH0423999Y2 (en)