JPH06195402A - Optimal design supporting system for product development - Google Patents
Optimal design supporting system for product developmentInfo
- Publication number
- JPH06195402A JPH06195402A JP26647193A JP26647193A JPH06195402A JP H06195402 A JPH06195402 A JP H06195402A JP 26647193 A JP26647193 A JP 26647193A JP 26647193 A JP26647193 A JP 26647193A JP H06195402 A JPH06195402 A JP H06195402A
- Authority
- JP
- Japan
- Prior art keywords
- product
- design
- information
- cost
- evaluation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000013461 design Methods 0.000 title claims abstract description 138
- 238000012356 Product development Methods 0.000 title claims description 23
- 238000011156 evaluation Methods 0.000 claims abstract description 86
- 238000011161 development Methods 0.000 claims abstract description 23
- 230000002452 interceptive effect Effects 0.000 claims abstract description 6
- 238000005457 optimization Methods 0.000 claims abstract description 5
- 238000004519 manufacturing process Methods 0.000 claims description 34
- 238000000034 method Methods 0.000 claims description 31
- 239000000758 substrate Substances 0.000 claims description 12
- 238000000556 factor analysis Methods 0.000 claims description 9
- 238000007689 inspection Methods 0.000 claims description 6
- 238000012827 research and development Methods 0.000 claims description 5
- 230000006872 improvement Effects 0.000 abstract description 18
- 238000004088 simulation Methods 0.000 abstract description 7
- 238000010586 diagram Methods 0.000 description 42
- 238000003780 insertion Methods 0.000 description 11
- 230000037431 insertion Effects 0.000 description 11
- 238000012545 processing Methods 0.000 description 10
- 230000000694 effects Effects 0.000 description 9
- 230000008569 process Effects 0.000 description 8
- 238000012360 testing method Methods 0.000 description 8
- 238000007796 conventional method Methods 0.000 description 6
- 238000004364 calculation method Methods 0.000 description 4
- 238000003860 storage Methods 0.000 description 4
- 238000004458 analytical method Methods 0.000 description 3
- 230000008859 change Effects 0.000 description 3
- 230000008094 contradictory effect Effects 0.000 description 3
- 238000012423 maintenance Methods 0.000 description 3
- 230000005540 biological transmission Effects 0.000 description 2
- 238000006243 chemical reaction Methods 0.000 description 2
- 238000004140 cleaning Methods 0.000 description 2
- 230000007613 environmental effect Effects 0.000 description 2
- 230000003993 interaction Effects 0.000 description 2
- 238000013441 quality evaluation Methods 0.000 description 2
- 230000009467 reduction Effects 0.000 description 2
- 238000012935 Averaging Methods 0.000 description 1
- 241001590997 Moolgarda engeli Species 0.000 description 1
- 239000000853 adhesive Substances 0.000 description 1
- 230000001070 adhesive effect Effects 0.000 description 1
- XAGFODPZIPBFFR-UHFFFAOYSA-N aluminium Chemical compound [Al] XAGFODPZIPBFFR-UHFFFAOYSA-N 0.000 description 1
- 229910052782 aluminium Inorganic materials 0.000 description 1
- 238000013459 approach Methods 0.000 description 1
- 239000003990 capacitor Substances 0.000 description 1
- 238000011960 computer-aided design Methods 0.000 description 1
- 239000000470 constituent Substances 0.000 description 1
- 238000005520 cutting process Methods 0.000 description 1
- 230000003111 delayed effect Effects 0.000 description 1
- 238000001035 drying Methods 0.000 description 1
- 239000000428 dust Substances 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000004907 flux Effects 0.000 description 1
- 238000007429 general method Methods 0.000 description 1
- 230000010354 integration Effects 0.000 description 1
- 230000007246 mechanism Effects 0.000 description 1
- 238000004377 microelectronic Methods 0.000 description 1
- 239000013307 optical fiber Substances 0.000 description 1
- 238000004806 packaging method and process Methods 0.000 description 1
- 238000004886 process control Methods 0.000 description 1
- 238000011158 quantitative evaluation Methods 0.000 description 1
- 230000005855 radiation Effects 0.000 description 1
- 238000004064 recycling Methods 0.000 description 1
- 230000010076 replication Effects 0.000 description 1
- 238000009420 retrofitting Methods 0.000 description 1
- 238000012552 review Methods 0.000 description 1
- 239000004065 semiconductor Substances 0.000 description 1
- 238000005476 soldering Methods 0.000 description 1
- 235000013599 spices Nutrition 0.000 description 1
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P90/00—Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
- Y02P90/02—Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P90/00—Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
- Y02P90/30—Computing systems specially adapted for manufacturing
Landscapes
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
- General Factory Administration (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】本発明は、回路基板の設計効率向
上のために、計算機援用設計システム(Computer Aided
Design System;以後CADシステムと称する)を用い
て作成した設計情報をもとに、その回路基板の早期製品
化,品質の向上,コストの低減を可能とする製品開発最
適設計支援システムに関する。BACKGROUND OF THE INVENTION The present invention relates to a computer aided design system (Computer Aided) for improving the design efficiency of a circuit board.
The present invention relates to a product development optimum design support system that enables early commercialization, quality improvement, and cost reduction of a circuit board based on design information created using a design system (hereinafter referred to as a CAD system).
【0002】[0002]
【従来の技術】回路基板が作り易い構造であるか否かを
評価する従来の第1の手法としては、設計時にデザイン
・レビューと称して設計や製作等の熟練者が経験に基づ
いて作り易さを判定して、要改良部を指摘する一般的な
手法が知られている。2. Description of the Related Art The first conventional method for evaluating whether or not a circuit board has a structure that is easy to manufacture is referred to as a design review at the time of design, and a person skilled in designing and manufacturing can easily make a circuit board based on experience. There is known a general method for determining the need for improvement and pointing out the portion requiring improvement.
【0003】従来の第2の手法としては、図2に設計と
製造し易さの評価と設計改良の流れを示すように、設計
図をもとに工程計画を行ない推定組立費や時間を算出し
て、この値と設計や製作等熟練者の経験とを加味して構
造の良し悪しを判定する方法がある。As a second conventional method, as shown in FIG. 2 which shows a flow of evaluation of design and manufacturability and design improvement, a process plan is made based on the design drawing and an estimated assembly cost is calculated. Then, there is a method of judging whether the structure is good or bad by taking this value and the experience of a skilled person such as designing and manufacturing into consideration.
【0004】また従来の第3の手法としては、特開昭6
1ー59900号公報に記載されているように、プリン
ト板パッケージの組立自動化率を、自動評価するプリン
ト板パッケージ組立評価方法がある。この方法では、プ
リント板パッケージの組立において部品を挿入する際の
自動化のし易さを評価するため、人手による標準形挿入
半導体集積回路の標準取付時間を100として、被評価
部品の部品挿入のし易さの難易度を減点指数で表わし、
これより人手による部品挿入の部品の積算減点を求めた
うえ、全自動の場合を100として100から人手によ
る積算減点値を差し引き、この値の評点を組立自動化の
指標とするようにしている。A third conventional method is Japanese Patent Laid-Open No.
As described in Japanese Patent Publication No. 1-59900, there is a printed board package assembly evaluation method for automatically evaluating the assembly automation rate of a printed board package. In this method, in order to evaluate the easiness of automation when inserting the components in the assembly of the printed board package, the standard attachment time of the standard insertion semiconductor integrated circuit by hand is set to 100, and the components to be evaluated are inserted. Express the difficulty level with a deduction score,
From this, the accumulated deduction points of the parts inserted manually are calculated, and the fully deducted value is deducted from 100 when the fully automatic case is set to 100, and the score of this value is used as the index of assembly automation.
【0005】[0005]
【発明が解決しようとする課題】上記した従来の第1の
方法では定性的で、評価対象品の構造がどの程度に良い
か悪いかや改良した場合にどれ位の効果があるかを、客
観的・定量的に表現することが難しいうえ、設計や生産
技術に十分な経験のある者しか実施することができない
という問題があった。The first conventional method described above is qualitative, and the objective is to determine how good or bad the structure of the evaluation target product is and how effective it is when it is improved. There is a problem that it is difficult to express quantitatively and quantitatively, and only those who have sufficient experience in design and production technology can implement it.
【0006】従来の第2の方法では、基板全体や部品毎
あるいは部品の一部の組立費が推定できたとしても、そ
の値からだけでは設計構造が良いのか悪いのかや改良が
必要なのか否かが判定しにくく、また評価するのに経験
や知識とかなりの計算時間とが必要で容易には行なえな
いうえ、さらに設計が完了しなければ評価することが難
しいため、設計改良が必要と分ったとしても一旦設計が
完了すると設計変更には多大の時間を要することから、
図2に示すように設計変更を行なうことなく生産に移さ
れて、生産性向上やコスト低減が実現しないことが多い
という問題があった。In the second conventional method, even if the assembly cost of the entire board, each part, or part of the part can be estimated, whether the design structure is good or bad and whether improvement is necessary only from the value can be estimated. It is difficult to judge whether or not it is difficult to evaluate, and it requires experience and knowledge and considerable calculation time to evaluate it, and it is difficult to evaluate unless the design is completed. Even if it happens, once the design is completed, it takes a lot of time to change the design.
As shown in FIG. 2, there has been a problem in that the production is often transferred without making a design change, so that productivity improvement and cost reduction cannot often be realized.
【0007】従来の第3の方法では、経験があまりなく
ても評価が可能であるが、評価指標が回路基板に部品を
挿入する際の組立自動化し易さのみを評点で表わす方法
である。すなわち、通常の回路基板の組立は、回路基板
の装着,挿入部品の挿入,基板反転,チップ部品装着,
乾燥,基板反転,異形部品挿入,手挿入,はんだ付,洗
浄,後付,検査などの多岐にわたる工程を経て回路基板
が製作されるものであるから、部品挿入での工数比は基
板製作全体の10〜30%程度の比率であって、部品挿
入の自動化し易いだけでは、組立易さの良否が正確かつ
総合的に判定できないという問題があった。In the third conventional method, evaluation can be performed without much experience, but the evaluation index is a method in which only the ease of automation of assembly when inserting a component into a circuit board is expressed by a score. That is, assembling a normal circuit board includes mounting the circuit board, inserting the insertion component, reversing the substrate, mounting the chip component,
Since the circuit board is manufactured through various processes such as drying, board reversal, insertion of odd-shaped components, manual insertion, soldering, cleaning, retrofitting, inspection, etc., the man-hour ratio for component insertion is The ratio is about 10 to 30%, and there is a problem that the quality of the ease of assembly cannot be accurately and comprehensively determined only by automating the insertion of the components.
【0008】以上の問題点を総合すると、 (1)評価が定性的であって、定量的評価でない。In sum of the above problems, (1) the evaluation is qualitative, not quantitative.
【0009】(2)経験豊富な者でなければ評価できな
い、或は、ある程度の評価手法の知識を必要とする。(2) Only an experienced person can evaluate, or some knowledge of the evaluation method is required.
【0010】(3)コストだけで評価すると、性能や品
質を総合的に評価ができない。(3) If only the cost is evaluated, the performance and quality cannot be comprehensively evaluated.
【0011】(4)評価に手間もしくはある程度の時間
がかかる。(4) Evaluation takes a lot of time and labor.
【0012】(5)設計が終了する、もしくは終りに近
づかなければ評価ができず、判定後の設計改良が行ない
にくい。(5) The evaluation cannot be performed unless the design is completed or approaches the end, and it is difficult to improve the design after the determination.
【0013】(6)部品ごとに設計の良し悪しが分かり
易くなっていないので、製品改良が行ないにくい。(6) It is difficult to improve the product because the quality of the design of each part is not easy to understand.
【0014】(7)評価指標とコストが関連づけられて
いない。(7) The evaluation index is not associated with the cost.
【0015】ということになる。That is,
【0016】従って、本発明の解決すべき技術的課題は
上記した技術のもつ問題点を解消することにあり、その
目的とするところは、(1)定量的評価であって、
(2)経験を必要とせず、かつ、(3)コスト評価だけ
でなく、性能向上,品質向上および短期製品開発という
相互する評価項目を統一的に評価でき、(4)評価が容
易に、かつ、(5)設計開発の早い段階で評価が行なえ
る。Therefore, the technical problem to be solved by the present invention is to solve the problems of the above-mentioned technique, and the purpose thereof is (1) quantitative evaluation,
(2) No experience is required, and (3) not only cost evaluation, but also mutual evaluation items such as performance improvement, quality improvement, and short-term product development can be evaluated in a unified manner, and (4) evaluation is easy and (5) Evaluation can be done at an early stage of design and development.
【0017】(6)部品レベルで評価できる。(6) It can be evaluated at the component level.
【0018】(7)性能,品質,納期の評価指標を持
ち、かつこの指標がコストと関連づけられている。(7) It has performance, quality, and delivery evaluation indexes, and these indexes are associated with costs.
【0019】(8)設計中のCAD/CAM(Computer
Aided Manufacturing)/CAT(Computer Aided Tes
ting)情報から直接評価が行なえる。(8) CAD / CAM (Computer under design)
Aided Manufacturing) / CAT (Computer Aided Tes)
Evaluation can be done directly from the information.
【0020】(9)設計中に即時に統合的コストの最適
化設計評価が行なえる。(9) Integral cost optimization design evaluation can be performed immediately during design.
【0021】ような評価手法が、自動で行ない得る統合
的コスト最適化設計システムを提供することにある。The evaluation method as described above is to provide an integrated cost optimization design system that can be automatically performed.
【0022】[0022]
【課題を解決するための手段】上記目的を達成するため
に、本発明によれば、製品の設計効率向上のための電子
計算機援用支援システムの対象製品に係る情報に基づい
て、前記対象製品の、配線難易度、製品の大きさ、製造
容易性、納期データ、誤り耐久性データ、信頼性及び保
全性データの内の少なくとも1つを含む製品品質に関す
る情報と、コストデータとからなる評価の対象となる評
価情報を生成する設計評価情報生成部と、前記評価情報
生成部により生成された情報を格納する評価情報データ
ベースと、前記評価情報データベースに格納された情報
に基づき、前記対象製品を製造するためのコストと前記
対象製品の製品品質とに関して、それぞれ同一の評価尺
度を用いて評価指標を生成し、該評価指標に基づいてラ
イフサイクルコストのシミュレーションを行うライフサ
イクルコストシミュレータと、前記対象製品に類似する
類似製品の設計情報を、前記製品を構成する最小の知識
単位に分類し、該最小の知識単位を組み合わせて設計手
順を定義することにより構築されたルールベースエキス
パートシステムと、該ルールベースエキスパートシステ
ムの知識単位を参照し、前記対象製品の設計手順を生成
するための情報の授受を行なう対話手段と、前記ルール
ベースエキスパートシステムの知識単位の情報と、前記
対象製品に係る情報とを用いて、前記対象製品の設計手
順の自動評価を行うデザインルールチェック手段とを有
することができる。In order to achieve the above object, according to the present invention, the target product of the target product of the computer aided support system for improving the design efficiency of the product is identified based on the information of the target product. , Wiring difficulty, product size, manufacturability, delivery date data, error durability data, reliability and maintainability data, and other information about product quality, and cost data. The target product is manufactured based on the design evaluation information generation unit that generates the evaluation information, the evaluation information database that stores the information generated by the evaluation information generation unit, and the information stored in the evaluation information database. Cost and the product quality of the target product, an evaluation index is generated using the same evaluation scale, and the life cycle cost is calculated based on the evaluation index. A life cycle cost simulator for simulating the above and design information of a similar product similar to the target product into the minimum knowledge units that compose the product, and define the design procedure by combining the minimum knowledge units. A rule-based expert system, a dialogue unit for referring to a knowledge unit of the rule-based expert system and exchanging information for generating a design procedure of the target product, and a knowledge unit of the rule-based expert system. Of the target product and design rule check means for automatically evaluating the design procedure of the target product.
【0023】以上を個々に説明すると、まず、性能向
上,低コスト,品質向上および短期製品開発という相反
する,かつ次元の異なる評価項目を、同時に評価して最
適化を行うため同一の評価基準を設けた。Each of the above will be explained individually. First, the same evaluation criteria are used for simultaneously evaluating and optimizing contradictory evaluation items of different performances such as performance improvement, low cost, quality improvement and short-term product development. Provided.
【0024】また、類似製品に関する経験や知識を必要
とせずに評価するため、製品情報に関して、IF〜TH
ENルールベース化された類似製品情報や知識ベースを
有するエキスパートシステムを設けた。In addition, since evaluation is performed without requiring experience or knowledge about similar products, the product information can be evaluated from IF to TH.
An expert system with similar product information and knowledge base that was EN-based was provided.
【0025】更に、組立コストだけでなく、設計,製
造,テスト,運用・保守および再利用・再生利用/廃棄
までのライフサイクルコストを推定できるようにするた
め、ライフサイクルコストシミュレータを設け、評価項
目の達成度をコストをキーにして総合的に評価するもの
である。Further, in order to estimate not only the assembly cost but also the life cycle cost of design, manufacturing, test, operation / maintenance and reuse / reuse / disposal, a life cycle cost simulator is provided and evaluation items are provided. This is a comprehensive evaluation of the degree of achievement of with the cost as the key.
【0026】更に、設計開発の早い段階で設計評価が行
なえるために、設計/製造/検査/運用/再利用・再生
利用/廃棄までの製品の特性実現性とそれを構成する階
層化された作り込み品質とこれらの特性値の多階層構造
における最適化を行えるように、製品品質要因解析手段
を設けた。Furthermore, in order to be able to carry out design evaluation at an early stage of design development, the product characteristic feasibility from design / manufacturing / inspection / operation / reuse / reuse / disposal and the hierarchical structure that constitutes it are hierarchized. A product quality factor analysis means is provided to optimize the built-in quality and these characteristic values in a multi-layered structure.
【0027】更に、製品品質の評価指標を持ち、かつこ
れらの指標とコストとを関連付けるため、特性実現性と
コストとの関係を同一の評価基準で表わすことにより、
配線難易度シミュレータ,誤り耐久性シミュレータ,製
造容易性シミュレータ,納期シミュレータ,信頼性+保
全性シミュレータ,ダウンサイジングシミュレータ,テ
スト容易性シミュレータから構成されるライフサイクル
コストシミュレータを設けた。Furthermore, since the product quality evaluation indexes are provided and these indexes are associated with the costs, the relationship between the characteristic feasibility and the costs is expressed by the same evaluation standard.
We provided a life cycle cost simulator consisting of a wiring difficulty simulator, error durability simulator, manufacturing ease simulator, delivery time simulator, reliability + maintainability simulator, downsizing simulator, and testability simulator.
【0028】設計中に即時に評価が行えるようにするた
め、CAD/CAM/CAT処理装置から設計評価情報
を生成できる標準フォーマットインタフェースを設け
た。A standard format interface capable of generating design evaluation information from a CAD / CAM / CAT processor is provided so that evaluation can be performed immediately during design.
【0029】製品開発に関して、構想段階で開発の意思
決定を行えるようにするため、研究開発で得られると予
測される純利益を、ライフサイクルコストで除するとこ
ろの開発投資効率予測手段を設けた。Regarding product development, a development investment efficiency prediction means for dividing the net profit expected to be obtained by research and development by the life cycle cost is provided in order to make a decision on development at the concept stage. .
【0030】以上の結果、製品開発で製品品質最適化設
計支援をするため、企業経営者も設計担当者も共通の目
標である品質向上という情報で、ゴールを明確化できる
仕組みを設けた。As a result of the above, in order to support the product quality optimization design in product development, a system has been established in which both the company manager and the person in charge of design can clarify the goal with the information of quality improvement, which is a common goal.
【0031】[0031]
【作用】性能向上,低コスト,品質向上および短期製品
開発という相反する評価項目を同時に評価して最適化を
行うための手法は、製品全体の特性実現性とそれを構成
する作り込み品質のSN(Signal Noise)比という同一
の評価基準を設定し統合的な設計評価を行う。SN比に
ついては、たとえば、「光ファイバ・活用の基礎」(オ
ーム社,根本俊雄著,雑誌「エレクトロニクス」昭和5
6年1月号付録)のp.138からp.139に記載さ
れている。[Function] A method for simultaneously evaluating and optimizing contradictory evaluation items such as performance improvement, low cost, quality improvement, and short-term product development is the SN of the product feasibility of the entire product and the built-in quality that constitutes it. (Signal Noise) The same evaluation standard called the ratio is set and integrated design evaluation is performed. Regarding the SN ratio, for example, "Fundamental Use of Optical Fiber" (Ohmsha, Toshio Nemoto, Magazine "Electronics", Showa 5)
January 6 issue appendix) p. 138 to p. 139.
【0032】設計評価情報生成部により、CAD/CA
M/CAT処理装置の出力信号をコストデータ,配線難
易度,製品大きさ,製造容易性,納期データ,誤り耐久
性データ,信頼性+保全性データのうちの少なくとも1
つの情報に変換し、CAD/CAM/CAT処理情報を
直接にライフサイクルコストシミュレータに入力でき
る。The design / evaluation information generation unit allows CAD / CA
The output signal of the M / CAT processor is at least one of cost data, wiring difficulty, product size, manufacturability, delivery date data, error durability data, and reliability + maintainability data.
CAD / CAM / CAT processing information can be directly input to the life cycle cost simulator by converting into one information.
【0033】これにより、設計,製造,テスト,運用,
再利用・再生利用,廃棄までの評価情報を生成できるた
め、製品開発の統合的な設計評価を行うことができる。As a result, design, manufacturing, test, operation,
Since it is possible to generate evaluation information for reuse / reuse and disposal, it is possible to perform integrated design evaluation of product development.
【0034】ライフサイクルコストシミュレータによ
り、設計評価情報生成部で生成された評価情報データベ
ースをもとに、製品品質の評価指標を持ち、かつこれら
の指標とコストとを関連付けるため、特性実現性とコス
トとの関係を同一の評価基準で表わすことにより、配線
難易度,誤り耐久性,製造容易性,納期,信頼性+保全
性,ダウンサイジング性,テスト容易性のうちの一つの
以上からなる情報のシミュレーションを行う。The life cycle cost simulator has product quality evaluation indexes based on the evaluation information database generated by the design evaluation information generating section, and these indexes are associated with costs. By expressing the relationship with the same evaluation criteria, it is possible to use information that is one or more of wiring difficulty, error durability, manufacturability, delivery time, reliability + maintainability, downsizing, and testability. Perform a simulation.
【0035】ルールベースエキスパートシステムによ
り、IF〜THENルールにより類似製品の設計情報を
もとに、設計作業を分析し、製品データとこれを構成す
る最小の知識(作業)単位に分類し、この知識(作業)
単位を組み合せて一つの意味のあるものにした設計手順
によるオブジェクト指向データベースを構成し、属性定
義することにより、類似製品の検索を行う。The rule-based expert system analyzes the design work based on the design information of the similar product according to the IF-THEN rules, classifies the product data and the minimum knowledge (work) unit constituting the product data, and uses this knowledge. (work)
A similar product is searched by constructing an object-oriented database according to a design procedure in which units are combined to make one meaning and defining attributes.
【0036】対話手段により、ルールベースエキスパー
トシステムを効率良く作成し、エキスパートシステムの
知識ベースを参照・変更するための知識編集機能を行な
い、通常の手続き型のプログラムコーティングによる実
行手法作業を不用にした。A rule-based expert system is efficiently created by an interactive means, and a knowledge editing function for referring / changing the knowledge base of the expert system is provided, thereby eliminating the need for execution procedure work by ordinary procedural program coating. .
【0037】デザインルールチェック手段により、ルー
ルベースエキスパートシステムと設計情報およびCAD
/CAM/CAT処理情報を結ぶ設計ルール実行モジュ
ールを用いて、ルールチェックを行う。By the design rule checking means, a rule-based expert system, design information and CAD
A rule check is performed using a design rule execution module that connects / CAM / CAT processing information.
【0038】また、製品品質要因解析手段により、設計
/製造/検査/運用/再利用・再生利用/廃棄までの製
造の特性実現性と、それを構成する作り込み品質とこれ
らの特性値とから成る多階層構造における最適化を行う
ことにより、製品開発の早い段階で設計評価を行えるよ
うにした。Further, by means of the product quality factor analysis means, the feasibility of manufacturing from design / manufacturing / inspection / operation / reuse / reuse / disposal, the built-in quality that constitutes it, and these characteristic values are used. By optimizing the multi-layered structure, the design evaluation can be performed at an early stage of product development.
【0039】さらに、開発投資効率予測手段により、研
究開発で得られると予測される純利益を、ライフサイク
ルコストで除することにより開発投資効率を求め、製品
開発に関して構想段階で開発の意思決定を行う。Further, the development investment efficiency predicting means obtains the development investment efficiency by dividing the net profit expected to be obtained by the research and development by the life cycle cost, and makes a decision on the development at the concept stage regarding the product development. To do.
【0040】[0040]
【実施例】以下、本発明の実施例を図1〜図37によっ
て説明する。Embodiments of the present invention will be described below with reference to FIGS.
【0041】図1は、本発明が適用される製品開発最適
設計支援システムの構成の概要を示す図である。図1に
示す製品開発最適設計支援システム30は、CAD/C
AM/CAT処理装置で作成された、あるいは図示しな
いCAD/CAM/CATデータベースに格納されたデ
ータベースから、例えばEDIF(Electronic Disign
Interchange Format)等の標準フォーマットにより設計
評価情報生成インタフェース部31により抽出されたコ
ストデータ32,配線難易度33,製品大きさ34,製
造容易性35,テスト容易性36,納期データ37,誤
り耐久性データ38,信頼性+保全性データ39による
評価情報データベース40に基づき、自動的に、ライフ
ルサイクルコストシミュレータ50により、各設計評価
情報とコストの関係をシミュレーションを行う。ライフ
サイクルコストシミュレーションの結果は、設計者側と
エキスパートシステムの知識ベースを参照・変更するた
めの知識編集機能を有するユーザーインタフェース60
を介して、設計知識を格納するルールベースエキスパー
トシステム(データと手続の両方を備えた設計知識ベー
ス)90に渡される。ルールベースエキスパートシステ
ム90は、デザインルールチェック75により、製品目
標仕様81,標準部品情報82,特性パラメータ83,
部品配置情報84,誤り耐久性情報85,信頼性+保全
性情報86等よりなる設計情報80と結合されている。FIG. 1 is a diagram showing an outline of the configuration of a product development optimum design support system to which the present invention is applied. The product development optimum design support system 30 shown in FIG.
From a database created by an AM / CAT processing device or stored in a CAD / CAM / CAT database (not shown), for example, EDIF (Electronic Disign
Interchange Format) and the like, the cost data 32 extracted by the design evaluation information generation interface unit 31, the wiring difficulty 33, the product size 34, the manufacturability 35, the testability 36, the delivery date data 37, the error tolerance. Based on the evaluation information database 40 based on the data 38 and the reliability + maintainability data 39, the rifle cycle cost simulator 50 automatically simulates the relationship between each design evaluation information and the cost. The result of the life cycle cost simulation is a user interface 60 having a knowledge editing function for referring and changing the knowledge bases of the designer and the expert system.
Is passed to a rule-based expert system (design knowledge base having both data and procedures) 90 for storing design knowledge. Based on the design rule check 75, the rule-based expert system 90 checks the product target specifications 81, standard part information 82, characteristic parameters 83,
It is combined with design information 80 including component placement information 84, error durability information 85, reliability + maintainability information 86, and the like.
【0042】ルールベースエキスパートシステム(設計
知識ベース)90の内容は類似製品の設計情報を基に、
図3に示すようになっている。ここで、設計作業を分析
し、知識として機能単位のサブ回路,サブ部品化する
と、いくつかの最小の知識(作業)単位にいわゆるオブ
ジェクト、すなわちデータと手続きの両方を備えた単位
に分類することができる。The contents of the rule-based expert system (design knowledge base) 90 are based on the design information of similar products.
It is as shown in FIG. Here, when design work is analyzed and sub-circuits and sub-parts are divided into functional units as knowledge, some minimum knowledge (work) units are classified into so-called objects, that is, units having both data and procedures. You can
【0043】この知識(作業)単位を組み合わせて一つ
の意味のある設計作業を表す。これを設計手順72と呼
ぶことにし、この設計手順をオブジェクト指向型データ
ベースにより階層化して属性定義で呼び出すことによっ
て一連の設計作業全体を表現している。このオブジェク
ト指向型データベースにより、知識(作業)を機能単位
のサブ回路,サブ部品化(モジュール化)することがで
き、設計情報を容易に検索可能となる。The knowledge (work) units are combined to represent one meaningful design work. This is referred to as a design procedure 72, and this design procedure is hierarchized by an object-oriented database and called by an attribute definition to represent a series of design work. With this object-oriented database, knowledge (work) can be made into sub-circuits and sub-components (modularization) in functional units, and design information can be easily searched.
【0044】図3においては、当該ルールベースエキス
パートシステム(設計知識ベース)90の1例として、
製品データ71に対して部品がどのように取りつけられ
るか等の実装機用のNCデータ計算結果73を示してい
る。In FIG. 3, as an example of the rule-based expert system (design knowledge base) 90,
The NC data calculation result 73 for the mounting machine, such as how the parts are attached to the product data 71, is shown.
【0045】実装機で部品を実装する場合、高い実装密
度で配置されていると、図4(a)に示すように、実装
機のヘッドとすでに実装済の縦形部品1との干渉により
実装機では縦形部品2を実装することができないことが
ある。同様に、図4(b)では、アンビルによるリード
のクリンチを行なう場合に、すでに実装済のチップ部品
1とアンビルが干渉することを示している。ここで、ア
ンビルとは部品のリードをクリンチするための実装機の
クリンチ機構である。When components are mounted with a mounting machine, if they are arranged at a high mounting density, as shown in FIG. 4 (a), the mounting machine head and the vertical component 1 that has already been mounted interfere with each other to mount the mounting machine. In some cases, the vertical component 2 cannot be mounted. Similarly, FIG. 4B shows that, when the lead is clinched by the anvil, the chip component 1 already mounted and the anvil interfere with each other. Here, the anvil is a clinching mechanism of a mounting machine for clinching a lead of a component.
【0046】このような実装状態の干渉のルールチェッ
クは、図3のルールベースエキスパートシステム(設計
知識ベース)90の中で、部品配置情報,実装機械名を
もとに、先に実装する部品の部品重複チェックとして、
部品形状定義とは別にリードのクリンチ形状も定義する
ことができる。また実装ルールチェックとして、実装機
のヘッド形状とは別にアンビル形状が別々にチェックで
きるようになっている。このようにデザインルールチェ
ック75はルールベースエキスパートシステム90と設
計情報80およびCAD/CAM/CAT処理装置20
とを結ぶ設計実行モジュールであり、各種の製品目標仕
様81に基づいて、自動でルールチェックができるよう
になっている。Such a rule check of the interference of the mounted state is performed in the rule-based expert system (design knowledge base) 90 shown in FIG. 3 based on the component placement information and the mounting machine name. As part duplication check,
The clinch shape of the lead can be defined separately from the part shape definition. As a mounting rule check, the anvil shape can be checked separately from the head shape of the mounting machine. As described above, the design rule check 75 includes the rule-based expert system 90, the design information 80, and the CAD / CAM / CAT processor 20.
It is a design execution module that connects with and can automatically check rules based on various product target specifications 81.
【0047】ここで、特性を実現するための尺度として
特性実現性(評価指標)というものを仮定し、これをθ
iとし、制約条件として0<θi <1を満たすものとす
る。さらに線形モデルλi=α+βχi,i=1,2・・
・を仮定する。Here, characteristic realizability (evaluation index) is assumed as a scale for realizing the characteristic, and this is taken as θ.
i, and 0 < θi < 1 is satisfied as a constraint condition. Further, a linear model λ i = α + β χ i , i = 1,2 ...
· Assume.
【0048】ここで、α,βをそれぞれ切片及び傾きの
パラメータとする。Here, α and β are parameters of the intercept and the slope, respectively.
【0049】θをロジスティック関数(数1)と仮定
し、次式のように与えるものとする。次式のように与え
られることは、「二値データの解析」(朝倉書店,D.
R.コック著,後藤昌司他訳)のp.24からp.25
に記載されている。It is assumed that θ is a logistic function (Equation 1) and is given by the following equation. What is given by the following equation is "analysis of binary data" (Asakura Shoten, D.M.
R. Cook, Shoji Goto et al.) P. 24 to p. 25
It is described in.
【0050】[0050]
【数1】 [Equation 1]
【0051】(数1)で与えられるθiをχの関数とし
て、β>0を仮定すると、図5(a)に示すようにな
る。Assuming β> 0 with θ i given by (Equation 1) as a function of χ, the result is as shown in FIG. 5 (a).
【0052】ここで、特性実現性θiを次のような変換
式を仮定すると、Here, assuming the following expression for converting the property feasibility θ i ,
【0053】[0053]
【数2】 [Equation 2]
【0054】(数2)を微分すると、Differentiating (Equation 2),
【0055】[0055]
【数3】 [Equation 3]
【0056】(数3)をθ1からθ2まで積分すると、When (Equation 3) is integrated from θ 1 to θ 2 ,
【0057】[0057]
【数4】 [Equation 4]
【0058】ここで、デシベル単位の表現からSN比を
ηとするとHere, assuming that the SN ratio is η from the expression in decibels,
【0059】[0059]
【数5】 [Equation 5]
【0060】例えば(数5)のθiを信頼度とすると、
1−θiは不信頼度なので、(数5)は概念的には信頼
度と不信頼度の比率を表わしている。For example, letting θ i in (Equation 5) be the reliability,
Since 1−θ i is the unreliability, (Equation 5) conceptually represents the ratio of the reliability and the unreliability.
【0061】ここで一例としてある自動支払機の特性実
現性θを考える。このときはθとして例えば信頼度(カ
ードを入れたとき、正しくお金が出てくる割合)は市場
で0.994であったとする。その信頼度を高めるための以
下の3つの機能を追加したときの効果を前述の方法によ
って検討する。Here, consider the characteristic feasibility θ of an automatic payment machine as an example. At this time, as θ, for example, it is assumed that the reliability (the rate at which money is correctly inserted when the card is inserted) is 0.994 in the market. The effect of adding the following three functions for increasing the reliability will be examined by the above method.
【0062】A:部品Aを新部品にする。A: The part A is changed to a new part.
【0063】B:回路を新しくする。B: The circuit is renewed.
【0064】C:耐塵埃装置をつける。C: A dustproof device is attached.
【0065】3つの機能に対して効果確認のために、別
々に試験を行い、このときの強制試験(振動と塵埃を与
えながら100回試験)をした結果により表1に示すデ
ータが得られたとする。In order to confirm the effect on the three functions, the tests were conducted separately, and the data shown in Table 1 was obtained as a result of the forced test (100 times test while applying vibration and dust). To do.
【0066】[0066]
【表1】 [Table 1]
【0067】機能A,B,Cの効果を(数5)によりデ
シベルで表現すると表2のようになる。Table 2 shows the effect of the functions A, B and C expressed in decibels according to (Equation 5).
【0068】[0068]
【表2】 [Table 2]
【0069】従って、3つの機能を全部採用したときの
効果(ゲイン)は、機能A,B,Cがそれぞれ、独立事
象のとき21.30dBとなる。Therefore, the effect (gain) when all three functions are adopted is 21.30 dB when the functions A, B, and C are independent events.
【0070】市場での信頼度0.994は、次のように22.19
dBであるから、3つの機能を全部採用したときの効果
は、The market reliability of 0.994 is 22.19 as follows.
Since it is dB, the effect of adopting all three functions is
【0071】[0071]
【数6】 [Equation 6]
【0072】として、θ=0.99955が得られる。
すなわち、特性実現性θは、99.4%から99.95
5%に向上する。As a result, θ = 0.99955 is obtained.
That is, the characteristic feasibility θ is from 99.4% to 99.95.
Improves to 5%.
【0073】(数5)を利用し、図5(a)をデシベル
単位で表わした結果を図5(b)に示す。すなわち、特
性実現性θとSN比ηは相互に逆変換が可能な関係にあ
ることがわかる。従って、θの関数(数1)より、種々
の評価項目をηに重ね合わせることにより、製品開発を
総合的に評価できることになる。ここでSN比はまた、
ばらつきの大きさをσ,平均値をMとすると、ηは次式
で表わされる。FIG. 5 (b) shows the result of expressing FIG. 5 (a) in decibel units using (Equation 5). That is, it can be seen that the characteristic feasibility θ and the SN ratio η are in a relationship capable of mutually inverse conversion. Therefore, the product development can be comprehensively evaluated by superimposing various evaluation items on η from the function of θ (Equation 1). Here, the SN ratio is also
Assuming that the magnitude of variation is σ and the average value is M, η is expressed by the following equation.
【0074】[0074]
【数7】 [Equation 7]
【0075】(数2)において、λを特性値とし、χを
信号因子として、ある信号因子χの基準点χ0で、差α
がゼロになるよう調整した場合を図6に示す。なお、m
1,m2,…,mhなる目標値にするための信号因子の水
準値をχ1,χ2,…,χhとし、ゼロ調整後の特性値を
λ1,λ2,…,λhとする。In (Equation 2), with λ as a characteristic value and χ as a signal factor, a difference α at a reference point χ 0 of a certain signal factor χ.
FIG. 6 shows the case where the adjustment is made so that the value becomes zero. Note that m
The level values of the signal factors for achieving the target values of 1 , m 2 , ..., m h are χ 1 , χ 2 , ..., χ h, and the characteristic values after zero adjustment are λ 1 , λ 2 , ..., λ. Let h .
【0076】このときの特性値λと信号因子χとの関係
を次式のようにおく。The relationship between the characteristic value λ and the signal factor χ at this time is given by the following equation.
【0077】[0077]
【数8】 [Equation 8]
【0078】いま、比例定数の校正をχ0で行えば、図
6に示すようにβはχ0に対するλの値をλ0として[0078] Now, by performing the calibration of the proportional constants chi 0, the value of lambda for β is chi 0 as shown in FIG. 6 as lambda 0
【0079】[0079]
【数9】 [Equation 9]
【0080】目標値をm,特性値λをyとする。ここで
目標値からずれたときの損失コスト関数をC(λ)とお
くと、図7に示すようになる。The target value is m and the characteristic value λ is y. Here, when the loss cost function when deviating from the target value is C (λ), it becomes as shown in FIG. 7.
【0081】特性値λが目標値mに等しいときは損失コ
ストはゼロ,または特性値λがmに等しいとき損失は最
小である。すなわち、一般に次式が成立する。The loss cost is zero when the characteristic value λ is equal to the target value m, or the loss is minimum when the characteristic value λ is equal to m. That is, the following equation is generally established.
【0082】[0082]
【数10】 [Equation 10]
【0083】[0083]
【数11】 [Equation 11]
【0084】C(λ)を目標値mの周りにテーラー展開
すると、Taylor expansion of C (λ) around the target value m gives
【0085】[0085]
【数12】 [Equation 12]
【0086】ここで(数10),(数11)を(数1
2)に代入して、(λ−m)3以上の項を省略すれば、
損失コスト関数C(λ)は次式で近似される。Here, (Equation 10) and (Equation 11) are replaced by (Equation 1)
Substituting into 2) and omitting terms above (λ-m) 3
The loss cost function C (λ) is approximated by the following equation.
【0087】[0087]
【数13】 [Equation 13]
【0088】ここにkは定数である。図7において、ま
ず特性値λがmからどこまでずれたらトラブルが発生す
るかの機能限界を△0を求める。Here, k is a constant. In FIG. 7, first, Δ 0 is obtained as a functional limit of how much the characteristic value λ deviates from m to cause a trouble.
【0089】(数13)の左辺にA0,右辺の(λ−
m)に△0を代入するとA 0 is on the left side of (Equation 13), and (λ−
Substituting △ 0 for m)
【0090】[0090]
【数14】 [Equation 14]
【0091】ここで、A0はトラブルが生じたときの損
失コスト(の平均)をA0円とする。これから比例定数
kは次式で求められる。Here, A 0 is (the average of) the loss cost when a trouble occurs is A 0 yen. From this, the proportional constant k is obtained by the following equation.
【0092】[0092]
【数15】 [Equation 15]
【0093】従って、損失コスト関数Cは次式で近似さ
れる。Therefore, the loss cost function C is approximated by the following equation.
【0094】[0094]
【数16】 [Equation 16]
【0095】ここで、設計では、特性値λが環境で変化
したり、使用中に劣化したりする。このときの環境条件
と設計寿命中の目標値からの差の2乗の平均を分散と
し、σ2とすると運用損失コストCuを次式で求める。Here, in the design, the characteristic value λ changes in the environment or deteriorates during use. If the average of the square of the difference between the environmental conditions at this time and the target value during the design life is taken as the variance and σ 2 is taken, the operation loss cost Cu is calculated by the following formula.
【0096】[0096]
【数17】 [Equation 17]
【0097】図7において、もし、類似製品のコストA
´と機能限界△´が既知であれば、(数16)から、次
の等式が成立しなければならない。In FIG. 7, if the cost A of a similar product is
If ′ and the functional limit Δ ′ are known, the following equation must be established from (Equation 16).
【0098】[0098]
【数18】 [Equation 18]
【0099】すなわち、図1のユーザーインタフェース
60で、特性値λと目標値仕様mを対話入力すれば、
(数16)からコストCは自動算出できる。That is, by interactively inputting the characteristic value λ and the target value specification m in the user interface 60 of FIG.
The cost C can be automatically calculated from (Equation 16).
【0100】同様にして、図8に示すような生産工程
で、工程の品質水準を求めるのに、その工程が作り出す
製品の特性値をλ1,λ2,…,λnとし、まず平均2乗
誤差すなわち分散をσ2を次式で求められる。Similarly, in the production process as shown in FIG. 8, in order to obtain the quality level of the process, the characteristic values of the product produced by the process are set to λ 1 , λ 2 , ... The error, that is, the variance σ 2 can be obtained by the following equation.
【0101】[0101]
【数19】 [Formula 19]
【0102】そして、製造損失コストCpは次式で計算
できる。Then, the manufacturing loss cost Cp can be calculated by the following equation.
【0103】[0103]
【数20】 [Equation 20]
【0104】ここで、△は生産工場で与えられた許容差
で、Aは工場で不合格品が発見されたときの手直しや再
利用・再生利用や廃棄処分の損失コストである。Here, Δ is the tolerance given at the production factory, and A is the loss cost of rework, reuse / reuse, or disposal when a rejected product is found at the factory.
【0105】設計品質を定量的に評価するため、図10
に示すように、回路基板を例にすると、ユーザーの要求
や開発仕様に基づいた設計要求尺度と設計要求尺度を満
足させるために、開発者が作り込むところの作り込み品
質設計尺度およびそれを構成する特性値さらに特性値を
構成する信号因子の4階層で計測・評価するものであ
る。To quantitatively evaluate the design quality, FIG.
As shown in Fig. 2, using a circuit board as an example, a built-in quality design scale that a developer builds in order to satisfy the design requirement scale and the design requirement scale based on user requirements and development specifications, and configures it. The characteristic values are further measured and evaluated in four layers of signal factors constituting the characteristic values.
【0106】設計要求尺度としては、第1層には配線難
易度,誤り耐久性,製造容易性,短納期性,低コスト
性,信頼性+保全性(含む社会性),ダウンサイジング
性,テスト容易性の8つの尺度で評価している。As the design requirement scale, the first layer has wiring difficulty, error durability, manufacturability, quick delivery, low cost, reliability + maintainability (including sociality), downsizing, and testing. It is evaluated on eight scales of ease.
【0107】作り込み品質設計尺度としては、第2層に
は実装密度,電磁ノイズ特性,伝送線路特性等の尺度で
評価し、さらに第3層としてこれらを構成する特性値お
よび第4層として特性値を構成する信号因子からなる階
層化構造により要因解析を行う。これらの製品品質要因
解析手段51は4階層に構造化した品質尺度を用い、図
9に品質要因解析手段51の構造を示す。As the built-in quality design scale, the second layer is evaluated by a scale such as mounting density, electromagnetic noise characteristic, and transmission line characteristic, and further, characteristic values constituting these layers as the third layer and characteristics as the fourth layer. Factor analysis is performed using a hierarchical structure consisting of signal factors that make up values. These product quality factor analysis means 51 use quality measures structured in four layers, and FIG. 9 shows the structure of the quality factor analysis means 51.
【0108】ここで、例えば、配線難易度,誤り耐久
性,製造容易性,短納期性,低コスト性,信頼性+保全
性,ダウンサイジング性,テスト容易性の設計要求尺度
をθA,θB,θC,θD,θE,θF,θG,θHとし、作り
込み品質設計尺度の(数5)で表わされるSN比をηと
して、いま、このSN比の各項に対応してそれぞれ,ω
1,ω2,・・・,ωnという重みをつけて平均する方式,す
なわち設計要求尺度の重みつき平均は図9に示した例で
説明すると次のようになる。Here, for example, design requirement scales of wiring difficulty, error durability, manufacturability, quick delivery, low cost, reliability + maintainability, downsizing, and testability are represented by θ A , θ. B , θ C , θ D , θ E , θ F , θ G , and θ H, and the SN ratio represented by (Equation 5) of the built-in quality design scale is η, and now each term of this SN ratio is supported. And each, ω
The method of averaging with weights of 1 , ω 2 , ..., ω n, that is, the weighted average of the design requirement measure is as follows when explained with the example shown in FIG.
【0109】設計要求尺度の重みつき平均=(ω1η1+ω
2η2+…+ωnηn)/(ω1+ω2+…+ωn)従って、設計品質設
計尺度は関連する作り込み品質設計尺度のSN比の重み
つけ平均で表わされる。Weighted average of design requirement scale = (ω 1 η 1 + ω
2 η 2 + ... + ω n η n ) / (ω 1 + ω 2 + ... + ω n ). Therefore, the design quality design measure is represented by the weighted average of the SN ratios of the related built-in quality design measures.
【0110】これをもとに、(数5)から特性実現性θ
(0<θ<1)に変換すると、図11に示すように、グ
ラフ化手段(図示せず)で作図化することで、レーダチ
ャートを作成することができる。Based on this, the characteristic feasibility θ from (Equation 5)
When converted to (0 < θ < 1), a radar chart can be created by plotting with a graphing means (not shown) as shown in FIG.
【0111】すなわち、図11のように、8つの設計要
求尺度を視覚化することにより実績値を目標仕様値と比
較して、製品の構想設計段階で合否判定が可能となる。That is, as shown in FIG. 11, by visualizing eight design requirement scales, it is possible to compare the actual value with the target specification value and make a pass / fail judgment at the conceptual design stage of the product.
【0112】配線難易度の作り込み品質設計尺度である
実装密度は基板面積の大小により、基板層数を求めるこ
とで求められる。ここで、配線難易度とは基板に配線す
るための尺度である。The mounting density, which is a built-in quality design measure of wiring difficulty, is obtained by determining the number of board layers depending on the size of the board area. Here, the wiring difficulty is a scale for wiring on the substrate.
【0113】QFP(Quard Flat Package)のパッケー
ジサイズSは図12(a)から次式により求められる。The package size S of the QFP (Quard Flat Package) is obtained from the following equation from FIG.
【0114】[0114]
【数21】 [Equation 21]
【0115】このパッケージを端子ピッチのn倍の間隔
を取って配置すると、その配置ピッチPはWhen this package is arranged at a distance n times the terminal pitch, the arrangement pitch P is
【0116】[0116]
【数22】 [Equation 22]
【0117】D.Seraphimの式(D.P.Seraphim :“Chip
-module-package interfaces",(IEEE,Trans.CHMT,CHMT
-1,p.305〜p.309))から全配線長Lは、D. Seraphim's formula (DPSeraphim: “Chip
-module-package interfaces ", (IEEE, Trans.CHMT, CHMT
-1, p.305 to p.309)), the total wiring length L is
【0118】[0118]
【数23】 [Equation 23]
【0119】ここで、L:全配線長 単位面積当りの必要配線長Laは、Here, L: total wiring length, the required wiring length La per unit area is
【0120】[0120]
【数24】 [Equation 24]
【0121】配線板の配線効率をeとすると、このQF
Pを搭載する配線板に必要な最大配線容量Lmaxは、If the wiring efficiency of the wiring board is e, this QF
The maximum wiring capacity Lmax required for a wiring board mounting P is
【0122】[0122]
【数25】 [Equation 25]
【0123】Pl=0.635mmでNt=200ピンのQFP搭載
の配線板ではLa=45cm/cm2とすると、e=0.25〜0.50
なので、 Lmax=(45/0.5〜45/0.25) 即ち、(90〜180)cm/cm2程度の配線収容能力の配線板
となる。In the case of a QFP-equipped wiring board with Pl = 0.635 mm and Nt = 200 pins, if La = 45 cm / cm 2 , then e = 0.25 to 0.50
Therefore, Lmax = (45 / 0.5 to 45 / 0.25), that is, a wiring board having a wiring accommodating capacity of about (90 to 180) cm / cm 2 .
【0124】2層板のとき、 (90/2〜180/2)cm/cm2=(45〜90)cm/cm2→平均67.5
=70cm/cm2/層 同様にリードピッチ0.5mm,端子数400のときLa=63.0c
m/cm2とすると、 Lmax=63/0.5〜63/0.25=126〜252cm/cm2 1層当り、70cm/cm2の配線ルールでは、 126/70〜252/70=1.8〜3.6≦2〜4層 従って1層当りの配線収容能力をηとし、層数をtとす
ると、In the case of a two-layer board, (90/2 to 180/2) cm / cm 2 = (45 to 90) cm / cm 2 → average 67.5
= 70cm / cm 2 / layer Similarly, when lead pitch is 0.5mm and number of terminals is 400, La = 63.0c
When m / cm 2, Lmax = 63 / 0.5~63 / 0.25 = 126~252cm / cm 2 1 layer per the wiring rule of 70cm / cm 2, 126 / 70~252 / 70 = 1.8~3.6 ≦ 2~ 4 layers Therefore, if the wiring capacity per layer is η and the number of layers is t,
【0125】[0125]
【数26】 [Equation 26]
【0126】(数26)をもとに、実装密度と基板層数
の関係を求めた結果を図12(b)に示す。FIG. 12B shows the result of obtaining the relationship between the mounting density and the number of substrate layers based on (Equation 26).
【0127】次に、ベアボード製造コストCB,Bは、図
13に示すように、定尺(例えば1m×1m)の基板の
板厚,板厚枚数,最小パターン幅等を対話入力すること
により、次式でベアボード製造コストCB,Bが求められ
る。Next, as shown in FIG. 13, the bare board manufacturing cost C B, B is obtained by interactively inputting the plate thickness, the plate thickness number, the minimum pattern width, etc. of a standard size (for example, 1 m × 1 m) substrate. The bare board manufacturing cost C B, B is calculated by the following equation.
【0128】[0128]
【数27】 [Equation 27]
【0129】ベアボード製造コストが(数27)で求め
られたときの、基板層数とベアボード製造コストCB,B
との関係を図14に示す。The number of substrate layers and the bare board manufacturing cost C B, B when the bare board manufacturing cost is calculated by (Equation 27).
FIG. 14 shows the relationship with.
【0130】また、図15に示すように、チャンネル数
や基板の穴の普通径,小径毎のベアボード製造コストが
求められる。更に、図1のCADの製品ライブラリ(図
示せず)に予め格納した部品購入費CQや割掛等と、図
16に示したグルーピング処理用データベース70の部
品群のタクトタイム及び割掛により組立推定費CAを求
め、これらとベアボード製造費CB,Bとを積算すること
により、回路基板のトータルコストが求められる。ここ
で、割掛とは単位時間当りの製造費のことである。Further, as shown in FIG. 15, the bare board manufacturing cost for each of the number of channels, the normal diameter of the holes of the substrate, and the small diameter is required. Furthermore, the parts purchase cost C Q , the cost, etc. stored in advance in the CAD product library (not shown) of FIG. 1 and the tact time and the cost of the group of parts of the grouping processing database 70 shown in FIG. 16 are assembled. The total cost of the circuit board is obtained by obtaining the estimated cost C A and summing these with the bare board manufacturing cost C B, B. Here, the allocation means a manufacturing cost per unit time.
【0131】更に、図12に示した回路基板の配線可能
領域と配線困難領域から基板層数((数26)により信
号層数から求められる。)が求められ、図15に示した
情報をもとに、目標コストを満たす、最適な基板層数を
求めることができる。Further, the number of board layers (obtained from the number of signal layers by (Equation 26)) is obtained from the wirable area and the wiring difficult area of the circuit board shown in FIG. 12, and the information shown in FIG. 15 is also obtained. In addition, the optimal number of substrate layers that satisfies the target cost can be obtained.
【0132】以上の結果をもとに、配線難易度(概略的
には1/基板層数に比例する)とコストの関係を示すと
図17のようになる。Based on the above results, the relationship between the wiring difficulty (generally proportional to 1 / the number of substrate layers) and the cost is shown in FIG.
【0133】回路設計段階において、回路図で使用する
部品は、通常信頼性を確認された認定部品を使用してい
る。従って、認定部品は、例えば、図12のようなQF
Pでは搭載する基板側のパッド(図13(c)参照)寸
法を含めた部品投影面積は確定している。In the circuit design stage, the components used in the circuit diagram are usually certified components whose reliability has been confirmed. Therefore, the certified component is, for example, a QF as shown in FIG.
In P, the component projected area including the size of the board-side pad (see FIG. 13C) to be mounted is fixed.
【0134】従って、使用する回路部品が決められる
と、図13(b),図13(c)のように、CADから
配線可能基板の大きさ、部品総ピン数,格子間隔および
格子間チャンネル数が自動生成され、これにより、(数
26)から配線可能な層数,チャンネル数範囲が推定さ
れる。さらに、(数27)から配線板厚,板取り枚数,
最小パターン幅,ホール数等を仮定すると、ベアボード
製造費が推定される。Therefore, when the circuit components to be used are determined, as shown in FIGS. 13B and 13C, the size of the wirable substrate, the total number of pins of the component, the lattice spacing, and the number of inter-lattice channels are calculated from CAD. Is automatically generated, and the number of layers and the number of channels that can be wired are estimated from (Equation 26). Furthermore, from (Equation 27), the wiring board thickness, the number of boards to be cut,
Assuming the minimum pattern width and the number of holes, the bare board manufacturing cost is estimated.
【0135】このようにして回路設計段階で、実装形態
の推定と、回路基板の総コストを推定することにより、
コストを考慮した回路基板の実装良否が推定できること
になる。In this way, by estimating the mounting form and the total cost of the circuit board at the circuit design stage,
It is possible to estimate the quality of mounting of the circuit board in consideration of the cost.
【0136】また、回路設計段階で、回路図を図36
(a)のように、サブ回路に回路分割(回路切り出し)
して設計しておき、各ブロックを分割して評価し、結果
を図36(b)のように表計算260で集計・表示するこ
とにより、各部の配線難易度(Lmax,ηなどから求めら
れる値),製造容易性(数28)の各部総コスト,基板
面積等の比較ができるようにしている。これにより、均
等な回路の割りふりをユーザが行い、全体としてバラン
スのとれた回路実装を行うことを容易にしている。さら
に、1枚の回路図中の任意の機能ブロックのサブ回路を
切り出し、基板面積等を仮定して、もし基板面積が想定
した面積に搭載できない場合に、回路のASIC化(Ap
plication Specific IC化)等の検討についても支援す
ることもできる。一般に、回路基板は実装設計まで移行
してしまうと再度回路設計まで手戻りして設計変更する
ことになると開発期間が遅くなる。しかし、本発明によ
れば、回路設計段階のブロック回路毎に設計評価ができ
るため、開発期間の短縮化を行なうことができる効果が
ある。At the circuit design stage, the circuit diagram is shown in FIG.
Circuit division (circuit cutout) into sub-circuits as shown in (a)
Then, each block is divided and evaluated, and the results are tabulated and displayed in a spreadsheet 260 as shown in FIG. 36 (b) to obtain the wiring difficulty (Lmax, η, etc.) of each part. Value), manufacturability (Equation 28), total cost of each part, board area, etc. can be compared. This makes it easy for the user to allocate the circuits evenly and to implement a balanced circuit as a whole. Furthermore, by cutting out a sub-circuit of an arbitrary functional block in one circuit diagram and assuming the board area, etc., if the board area cannot be mounted in the assumed area, the circuit is converted to ASIC (Ap
It is also possible to support studies such as replication specific IC conversion). Generally, when the circuit board moves to the packaging design, the development period is delayed when the circuit design is revisited and the design is changed. However, according to the present invention, the design evaluation can be performed for each block circuit at the circuit design stage, so that there is an effect that the development period can be shortened.
【0137】次に、誤り耐久性とコストCNとの関係
は、既述の図7と同様な関係で図18に示すように表わ
される。ここで、誤り耐久性は電磁ノイズ特性や伝送線
路特性等、いわゆる製品を作ってからでないとわからな
い誤りに対しての耐久性である。例えば、これらの誤り
耐久性はSPICE等のアナログシミュレータで解析す
ることが予めできるようになっている。Next, the relationship between the error durability and the cost C N is expressed as shown in FIG. 18 in the same relationship as that of FIG. 7 described above. Here, the error durability is the resistance to errors such as electromagnetic noise characteristics and transmission line characteristics that are not known until a so-called product is manufactured. For example, these error tolerances can be analyzed in advance by an analog simulator such as SPICE.
【0138】次に、製造容易性について、図8のユーザ
インターフェース60(ライン実装順序)を用いて説明す
る。ここで、製造容易性とは製品の作り易さの尺度θc
を表わし、製造容易性θcとコストCMとの関係は図19
に示すように、製品が作り易いほどコストは低減され
る。The manufacturability will be described below with reference to the user interface 60 (line mounting order) shown in FIG. Here, manufacturability is a measure of product easiness of manufacture θc
FIG. 19 shows the relationship between the manufacturability θc and the cost C M.
As shown in, the easier the product is to make, the lower the cost will be.
【0139】ここで製造容易性θcは、製造容易性の重
みωとして、製造性の良いものを1.0から、製造性の
悪いものを0.1として、それぞれの重みωに該当する
部品数の和をa〜jとすると、製造容易性θcは次式の
ようになる。The manufacturability θc is the number of parts corresponding to each weight ω, where the manufacturability weight ω is 1.0 from good manufacturability to 0.1 and poor manufacturability is 0.1. The manufacturability θc is given by
【0140】[0140]
【数28】 [Equation 28]
【0141】(数28)から分かるようにθcは0〜1
の範囲の値を取ることがわかり、部品数を考慮した製品
の作り易さを評価することができる尺度である。As can be seen from (Equation 28), θc is 0 to 1
It is a scale that can evaluate the easiness of making a product considering the number of parts.
【0142】実装図には図8に示すように部品実装情報
のノウハウが盛り込まれている。すなわち、自動化率向
上のための実装順序ルール100には、挿入ICはアキ
シャル部品より先に挿入,挿入ICはラジアル部品よ
り先に挿入,アキシャル部品はラジアル部品より先に
挿入等の実装順序があるが、このルールに基づいて、挿
入IC部品挿入機150→アキシャル部品挿入機160→ラジ
アル部品挿入機180→ロボット異形部品挿入機190→手挿
入200の第1〜5工程までが構成されている。また、専
用ロボット210は機械部品との混載、例えばパワートラ
ンジスタに放熱用ヒートシンクをネジ止めして用いる場
合に使用される。またコネクタは、接触部へのフラック
ス付着防止や耐洗浄性の必要から、手挿入部品220とし
て取扱われる。As shown in FIG. 8, the mounting diagram contains know-how of component mounting information. That is, the mounting order rule 100 for improving the automation rate has a mounting order such that the insertion IC is inserted before the axial part, the insertion IC is inserted before the radial part, and the axial part is inserted before the radial part. However, based on this rule, the insertion IC component inserting machine 150 → axial component inserting machine 160 → radial component inserting machine 180 → robot variant component inserting machine 190 → the first to fifth steps of manual insertion 200 are configured. The dedicated robot 210 is used together with mechanical parts, for example, when a heat sink for heat radiation is screwed to a power transistor and used. Further, the connector is handled as a hand-inserted component 220 because it is necessary to prevent flux from adhering to the contact portion and to have cleaning resistance.
【0143】ここで、すでに図4(a)で述べたよう
な、実装済の部品との部品干渉は図8では、アルミコン
デンサの縦形部品1と縦形部品2として示されている。Here, the component interference with the mounted components as already described with reference to FIG. 4A is shown in FIG. 8 as the vertical component 1 and the vertical component 2 of the aluminum capacitor.
【0144】本発明においては、図16に示すように、
回路部品をグルーピング処理70した類似部品が用意さ
れている。部品形態の類似性により分類した部品群に対
して、チップ部品群には接着剤塗布B,下移動組付↓の
ような動作内容、タクトタイム等の部品実装属性情報が
格納されている。In the present invention, as shown in FIG.
Similar components obtained by grouping 70 the circuit components are prepared. With respect to the component group classified by the similarity of the component form, the chip component group stores operation contents such as adhesive application B, downward movement assembly ↓, and component mounting attribute information such as takt time.
【0145】このような類似部品群でグルーピング処理
70を行いデータベース化し、隣接した部品をグルーピ
ングして、図4のようにヘッド及びアンビルの干渉チェ
ックを行い、さらに図8に示した実装順序ルール100を
もとに部品搭載ラインの実装順序を決定することができ
る。A grouping process 70 is performed on such a group of similar components to create a database, adjacent components are grouped, the head and anvil interference is checked as shown in FIG. 4, and the mounting order rule 100 shown in FIG. The mounting order of the component mounting line can be determined based on
【0146】図21に示すように複数のラインが存在し
ている場合、ラインは、人間の指示に従って、CAD/
CAMシステムから、生産するロットのロット情報を受
信し、納期シミュレータ54により、知識ベースとルー
ルベースの類似計画情報からなるエキスパートシステム
90をもとに、ユーザインタフェース60(計画線表)
の画面で対話入力により計画立案を行うことができる。When there are a plurality of lines as shown in FIG. 21, the line is CAD /
The lot information of the lot to be produced is received from the CAM system, and the delivery date simulator 54 uses the expert system 90 composed of knowledge-based and rule-based similar plan information to create a user interface 60 (plan line table).
You can plan by interactive input on the screen.
【0147】ここで、知識ベース91は、ラインの場合
には同一機能を有するラインが複数あるため、図16に
示した情報にもとづいて動作機能別に同一機能グループ
で統合した階層構造になっており、また同一機能でもタ
クト能力により細分化されている。Here, since the knowledge base 91 has a plurality of lines having the same function in the case of a line, it has a hierarchical structure in which the same function group is integrated for each operation function based on the information shown in FIG. Also, the same function is subdivided by tact ability.
【0148】また、類似製品の過去情報でロットの分割
割付が発生した場合のロット情報は、オブジェクト指向
データベースにより階層構造化されたデータで構成され
ている。Further, the lot information in the case where lot division allocation has occurred in the past information of similar products is composed of data hierarchically structured by the object-oriented database.
【0149】顧客のニーズが多様化し変化する中で、市
場ニーズを提えて、商品を必要な時に必要量だけ、タイ
ムリに生産,供給することが必要である。As customer needs diversify and change, it is necessary to meet market needs and produce and supply merchandise in a timely manner and in a required amount when needed.
【0150】本発明に係るシステムにおいては、計画担
当者のノウハウが、図22に示すIF−THENルール
化されたルールベース形式で、類似製品の計画情報とし
てエキスパートシステムの中に格納されている。図21
に示すユーザインターフェース60(計画線表)の画面
中の生産ロットのロット詳細情報の生産個数,納期等を
参照し、これと類似する製品計画情報をIF〜THEN
ルール形式で呼び出し、これを対話形式で人手で修正す
るものである。In the system according to the present invention, the know-how of the planner is stored in the expert system as plan information of similar products in the IF-THEN rule-based rule-based format shown in FIG. Figure 21
Refer to the production quantity, delivery date, etc. of the lot detailed information of the production lot in the screen of the user interface 60 (planning line table) shown in FIG.
It is called in a rule format and is manually modified in an interactive format.
【0151】このように、納期シミュレータ54によ
り、製品の短納期化が可能となり、短納期性とコストC
Iの関係は図20に示すようになる。ここで、短納期性
とは製品を短期間で市場に生産,供給する尺度である。
製品を生産,供給する時間の逆数で表わす。図20から
わかるように、短期間に製造するほど割掛が一定ならば
コストは当然低減される。As described above, the delivery time simulator 54 can shorten the delivery time of the product, thereby reducing the delivery time and the cost C.
The relationship of I is as shown in FIG. Here, quick delivery is a measure for producing and supplying products to the market in a short period of time.
Expressed as the reciprocal of the time it takes to produce and supply a product. As can be seen from FIG. 20, the cost is naturally reduced if the cost is constant as the manufacturing is performed in a short period of time.
【0152】また、信頼性と保全性に関しても、図23
に示すように、製品の故障率λを回路の故障率λEとメ
カ部品が混載されたときのメカ部品の故障率λMとの合
計値で表されるようになっている。すなわち、図1の標
準部品情報82の中に部品故障率λを登録しておき、製
品に含まれる部品の同部品数N1と故障率λ1の積N1・
λ1から次式により求められる。As for reliability and maintainability, FIG.
As shown in, the failure rate λ of the product is represented by the total value of the failure rate λ E of the circuit and the failure rate λ M of the mechanical parts when the mechanical parts are mixedly mounted. That is, the component failure rate λ is registered in the standard component information 82 of FIG. 1, and the product N 1 of the number N 1 of the same parts included in the product and the failure rate λ 1
It is calculated from λ 1 by the following equation.
【0153】[0153]
【数29】 [Equation 29]
【0154】以上の信頼性+保全性および社会性とコス
トCLの関係は図24に示すようになる。ここで、社会
性とは環境保護や製造物責任など社会に対する製品の影
響度である。The relationship between the reliability + maintainability and sociality and the cost C L is as shown in FIG. Here, sociality is the degree of influence of a product on society such as environmental protection and product liability.
【0155】また、製品のダウンサイジング性は、マイ
クロエレクトロニクス化の進展に伴い、製品の重要な機
能の一つであり、図16に示すようなチップ部品等の表
面実装部品を採用することにより、表面実装化率が向上
し実現される。Further, the downsizing property of the product is one of the important functions of the product along with the progress of microelectronics. By adopting the surface mounting component such as the chip component as shown in FIG. It is realized by improving the surface mounting rate.
【0156】また、回路部品をソリットモデラ(図示せ
ず)を用いて3次元的にすきまなし実装化することによ
り、図25に示すようにダウンサイジング性が向上され
る。Further, the downsizing property is improved as shown in FIG. 25 by mounting the circuit components three-dimensionally with no clearance using a solit modeler (not shown).
【0157】以上のダウンサイジング性とコストCSの
関係は図1の製品の大きさ34を参照し、図27に示す
ように表される。The relationship between the downsizing property and the cost C S described above is expressed as shown in FIG. 27 with reference to the product size 34 in FIG.
【0158】製品の検査は製品品質を保証するために重
要な設計要求尺度である。Product inspection is an important design requirement measure for ensuring product quality.
【0159】図26で示すように、工程能力指数Cpは
次式で求められる。As shown in FIG. 26, the process capability index Cp is calculated by the following equation.
【0160】[0160]
【数30】 [Equation 30]
【0161】すなわち、工程能力係数Cpが達成される
と、製品のばらつきが許容差のかなり内側に入り、いわ
ゆる受入検査は不要になり、その結果テスト容易性とコ
ストCTとの関係は図28(a)に示すようになる。That is, when the process capability coefficient Cp is achieved, the product variation is within the tolerance, so that the so-called acceptance inspection becomes unnecessary, and as a result, the relationship between the testability and the cost C T is shown in FIG. As shown in (a).
【0162】しかし、このためには工程管理が厳しくな
るため、図28(b)のように、チェックコストが高く
なる。そのため適正な管理限界を設定する必要がある。However, for this reason, the process control becomes strict, so that the check cost becomes high as shown in FIG. 28 (b). Therefore, it is necessary to set appropriate control limits.
【0163】以上のようにして求めた、コストは、図2
9に示すように、回路基板では、要求分析,設計(回路
設計CD,部品配置CS,配線CW),製造CM,テストC
T,保守CL(廃棄・再利用・再生利用を含む)等のコス
トが合計され、すなわちライフサイクルトータルコスト
110が図1のライフサイクルコストシミュレータ50に
より求められる。ここで、ライフサイクルコスト110
は、図34に示すように、回路設計コストは既述のCD
等,部品配置コストは既述のCS等,コストは既述のCW
等,製造コストは既述のCM等,テストコストは既述の
CT等,運用・保守コストは既述のCL等,廃棄コストC
Lは既述のCL等の積算として、積算器111によりもとめ
られる。The cost calculated as above is shown in FIG.
As shown in FIG. 9, in the circuit board, requirement analysis, design (circuit design C D , component layout C S , wiring C W ), manufacturing C M , test C
Costs such as T and maintenance CL (including disposal / reuse / recycling) are summed up, that is, life cycle total cost
110 is calculated by the life cycle cost simulator 50 of FIG. Where life cycle cost 110
As shown in FIG. 34, the circuit design cost aforementioned C D
Etc., component placement costs previously described C S etc., the cost aforementioned C W
Etc., manufacturing cost is C M, etc., test cost is C T, etc., operation / maintenance cost is C L, etc., disposal cost C, etc.
L is obtained by the integrator 111 as the above-mentioned integration of C L and the like.
【0164】また、図1のユーザインタフェース60を
介して、図30のライフサイクルコストに示すように製
品目標仕様81が決まると、図21のルールベース類似
計画情報92と同じように、図22に示すIF〜THE
N形式でルールベース化された類似製品パラメータデー
タベース120により、ライフサイクルコスト110を推定す
ることも可能である。Further, when the product target specification 81 is determined through the user interface 60 of FIG. 1 as shown in the life cycle cost of FIG. 30, the same as the rule-based similar plan information 92 of FIG. IF to THE
It is also possible to estimate the life cycle cost 110 from the similar product parameter database 120 that is rule-based in the N format.
【0165】なお、ライフサイクルコストシミュレータ
50は、配線難易度シミュレータ51,誤り耐久性シミ
ュレータ52,製造容易性シミュレータ53,納期シミ
ュレータ54,信頼性+保全性(含む社会性)シミュレ
ータ55,ダウンサイシングシミュレータ56,テスト
容易性シミュレータ57より構成され、これらの構造は
図31に示すようになる。The life cycle cost simulator 50 includes a wiring difficulty simulator 51, an error durability simulator 52, a manufacturability simulator 53, a delivery schedule simulator 54, a reliability + maintainability (including sociality) simulator 55, and downsizing. It is composed of a simulator 56 and a testability simulator 57, and their structures are as shown in FIG.
【0166】これらライフサイクルコストシミュレータ
50は夫々が図示しない並列処理が可能で、かつ分散型
のリアルタイムOS(Operating System)により、同時
並行処理ができるようになっている。Each of these life cycle cost simulators 50 is capable of parallel processing not shown, and is capable of simultaneous parallel processing by a distributed real-time OS (Operating System).
【0167】このようにして製品ライフサイクルコスト
C110が求められるが、研究開発で得られた純利益M
を、Cで割ることにより開発投資効率μが求められる。In this way, the product life cycle cost C110 is obtained, but the net profit M obtained by research and development is M.
Is divided by C, the development investment efficiency μ is obtained.
【0168】このようなライフサイクルコストCと純利
益Mとの関係は図32の開発投資効率予測手段250に示
すようになる。The relationship between the life cycle cost C and the net profit M is as shown in the development investment efficiency predicting means 250 of FIG.
【0169】このときのμは企業としては対象とする製
品によって異なるが、100%以上が望ましいことは明ら
かである。At this time, μ varies depending on the target product as a company, but it is clear that 100% or more is desirable.
【0170】このような開発投資効率予測手段250で開
発投資効率μを、研究開発段階で予測することは、企業
戦略上、非常に重要な指標であり、本発明では自動で求
められるようになっている。以上の本発明の製品開発最
適設計のコンセプトは、図35に示すように、方法論と
コンピュータ支援ツールとヒューマンウェアの3位1体
による達成される。すなわち、方法論としてはライフサ
イクルコスト対応の統一的評価尺度として特性実現性θ
を導入したこと,コンピュータ支援ツールとして、ライ
フサイクルコスト対応シミュレータとしてライフサイク
ルコストシミュレータ50を導入したこと,ヒューマン
ウェアとしてトップダウンとボトムアップの熱い交流の
ために、設計担当者に対して製品品質要因解析手段51
と経営者に対して開発投資効率予測手段250を導入した
ことが特徴である。Predicting the development investment efficiency μ by such a development investment efficiency predicting means 250 at the research and development stage is a very important index in corporate strategy, and is automatically calculated in the present invention. ing. The concept of the product development optimum design of the present invention as described above is achieved by the third place of the methodology, the computer support tool and the humanware as shown in FIG. That is, as a methodology, characteristic feasibility θ as a unified evaluation scale for life cycle cost
The life cycle cost simulator 50 has been introduced as a computer support tool as a life cycle cost compatible simulator, and the top-down and bottom-up hot exchanges as humanware have made it possible for the designer to consider product quality factors. Analysis means 51
The feature is that the development investment efficiency prediction means 250 is introduced to the manager.
【0171】なお、図37に計算機による自動評価項目
310と、ユーザとの対話により評価する評価項目320を各
々まとめて記載する。自動評価項目310を行なうための
機能部は、デザインルールチェック75に備えられ、ユ
ーザとの対話により評価する評価項目320を行なうため
の機能部は、ユーザインターフェース60に備えられて
いる。この図に示すように、計算機による自動評価項目
310としては、部品干渉チェック,配線可能な層数チャ
ンネル数範囲推定,信頼性+保全性評価,ダウンサイジ
ング性評価,ライフサイクルコストシミュレ−ション,
開発投資効率予測がある。ユーザとの対話により評価す
る評価項目320としては、損失コスト計算,ベアボード
製造コスト,サブ回路分割評価,誤り耐久性評価,製造
容易性評価,納期シミュレ−ション,テスト容易性評
価,製品品質要因解析がある。FIG. 37 shows the automatic evaluation items by the computer.
310 and the evaluation items 320 to be evaluated by the dialog with the user are collectively described. A functional unit for performing the automatic evaluation item 310 is provided in the design rule check 75, and a functional unit for performing the evaluation item 320 to be evaluated by the interaction with the user is provided in the user interface 60. As shown in this figure, automatic evaluation items by computer
As 310, component interference check, number of layers that can be wired, channel number range estimation, reliability + maintainability evaluation, downsizing evaluation, life cycle cost simulation,
There is a prediction of development investment efficiency. The evaluation items 320 evaluated by the interaction with the user include loss cost calculation, bare board manufacturing cost, sub-circuit division evaluation, error durability evaluation, manufacturability evaluation, delivery time simulation, testability evaluation, product quality factor analysis. There is.
【0172】本発明によれば回路基板の構想段階でシミ
ュレーションを行うことにより、図33に示すように早
期製品化を可能にするとともに、品質の向上,コストの
低減を可能にする特徴がある。According to the present invention, by performing a simulation at the conceptual stage of the circuit board, it is possible to realize early commercialization as shown in FIG. 33 and to improve quality and reduce cost.
【0173】[0173]
【発明の効果】以上のように、本発明によれば、性能向
上,低コスト,品質向上および短期製品開発ができると
いう相反する開発目標を同時に実現できるという効果が
得られる。As described above, according to the present invention, it is possible to simultaneously achieve the contradictory development goals of performance improvement, low cost, quality improvement and short-term product development.
【0174】また、構想設計段階で、ライフサイクルに
関する多くの情報を取り入れることにより、より質の高
い設計ができるようになった。Further, by incorporating a lot of information about the life cycle at the conceptual design stage, it becomes possible to design with higher quality.
【0175】また、本発明によれば、生産実績がある類
以製品のノウハウを活かして新たな製品を設計すること
が可能になり、新製品の開発期間を短縮できるという効
果も得られる。Further, according to the present invention, it is possible to design a new product by utilizing the know-how of a similar product having a production record, and it is also possible to shorten the development period of the new product.
【0176】CAD/CAM/CAT処理を同時に並列
処理が行なえるので、設計効率が従来に比べて大幅に向
上するという効果も得られる。Since CAD / CAM / CAT processing can be performed in parallel at the same time, there is an effect that the design efficiency is significantly improved as compared with the conventional case.
【0177】更に、本発明によれば、CAD/CAM/
CAT処理装置をつなぐインターフェースを統一したこ
とにより、CADデータを修正するだけでそれ以外のC
AM/CAT用データも修正が可能となり、作業工数を
大幅に低減できるという効果が得られる。Furthermore, according to the present invention, CAD / CAM /
By unifying the interface that connects the CAT processing devices, you can modify the CAD data by simply modifying the CAD data.
The data for AM / CAT can also be modified, and the effect of significantly reducing the number of work steps can be obtained.
【図1】本説明の実施例に係る製品開発最適設計支援シ
ステムの全体構成の概要を示す構成図である。FIG. 1 is a configuration diagram showing an outline of an overall configuration of a product development optimum design support system according to an embodiment of the present description.
【図2】従来の製品設計と製造の評価と改良の流れを例
示する説明図である。FIG. 2 is an explanatory diagram illustrating a flow of conventional product design and manufacturing evaluation and improvement.
【図3】ルールベースエキスパートシステムの設計知識
ベースを示す説明図である。FIG. 3 is an explanatory diagram showing a design knowledge base of a rule-based expert system.
【図4】部品の挿入ヘッド又はアンビルによる干渉を示
す説明図である。FIG. 4 is an explanatory view showing interference by an insertion head or anvil of a component.
【図5】特性実現性と信号因子およびSN比と信号因子
との関係を示す説明図である。FIG. 5 is an explanatory diagram showing a relationship between characteristic feasibility and a signal factor, and an SN ratio and a signal factor.
【図6】信号因子と特性値との関係を示す説明図であ
る。FIG. 6 is an explanatory diagram showing a relationship between a signal factor and a characteristic value.
【図7】特性値と損失コスト関数を示す説明図である。FIG. 7 is an explanatory diagram showing characteristic values and loss cost functions.
【図8】ユーザインターフェースのライン実装順序を示
す説明図である。FIG. 8 is an explanatory diagram showing a line mounting sequence of a user interface.
【図9】ライフサイクルシミュレータの製品品質要因解
析手段を示す説明図である。FIG. 9 is an explanatory diagram showing a product quality factor analysis means of the life cycle simulator.
【図10】製品品質の構成を示す説明図である。FIG. 10 is an explanatory diagram showing the structure of product quality.
【図11】ライフサイクルコストシミュレータ画面の特
性実現性のレーダチャートを示す説明図である。FIG. 11 is an explanatory diagram showing a radar chart of characteristic feasibility of a life cycle cost simulator screen.
【図12】実装密度と基板層数との関係を示す説明図で
ある。FIG. 12 is an explanatory diagram showing the relationship between the mounting density and the number of substrate layers.
【図13】ライフサイクルコストシミュレータ画面のベ
アボードコスト算出のための対話入力画面を示す説明図
である。FIG. 13 is an explanatory diagram showing an interactive input screen for calculating a bare board cost of the life cycle cost simulator screen.
【図14】基板層数とベアボードコストとの関係を示す
説明図である。FIG. 14 is an explanatory diagram showing the relationship between the number of substrate layers and the bare board cost.
【図15】ライフサイクルコストシミュレータ画面の実
装密度とトータルコストを示す説明図である。FIG. 15 is an explanatory diagram showing a mounting density and a total cost of a life cycle cost simulator screen.
【図16】グルーピング処理用データベースを示す説明
図である。FIG. 16 is an explanatory diagram showing a grouping processing database.
【図17】配線難易度とコストとの関係を示す説明図で
ある。FIG. 17 is an explanatory diagram showing a relationship between wiring difficulty and cost.
【図18】誤り耐久性とコストとの関係を示す説明図で
ある。FIG. 18 is an explanatory diagram showing a relationship between error durability and cost.
【図19】製造容易性とコストとの関係を示す説明図で
ある。FIG. 19 is an explanatory diagram showing a relationship between manufacturability and cost.
【図20】短納期化とコストとの関係を示す説明図であ
る。FIG. 20 is an explanatory diagram showing the relationship between shortened delivery time and cost.
【図21】納期シミュレータの構成を説明する説明図で
ある。FIG. 21 is an explanatory diagram illustrating a configuration of a delivery date simulator.
【図22】IF〜THENルール形式による知識ベース
登録例を示す説明図である。FIG. 22 is an explanatory diagram showing an example of knowledge base registration in the IF-THEN rule format.
【図23】製品の故障率を示す説明図である。FIG. 23 is an explanatory diagram showing a failure rate of products.
【図24】信頼性+保全性とコストとの関係を示す説明
図である。FIG. 24 is an explanatory diagram showing a relationship between reliability + maintainability and cost.
【図25】表面実装化率、すきまなし実装化とダウンサ
イジング性を示す説明図である。FIG. 25 is an explanatory diagram showing a surface mounting rate, mounting without clearance and downsizing.
【図26】工程能力係数を示す説明図である。FIG. 26 is an explanatory diagram showing process capability coefficients.
【図27】ダウンサイジング性とコストとの関係を示す
説明図である。FIG. 27 is an explanatory diagram showing a relationship between downsizing property and cost.
【図28】テスト容易性とコストとの関係を示す説明図
である。FIG. 28 is an explanatory diagram showing the relationship between testability and cost.
【図29】ライフサイクルコストのトータルコストカー
ブ図を示す説明図である。FIG. 29 is an explanatory diagram showing a total cost curve diagram of life cycle costs.
【図30】類似製品によるライフサイクルコスト予測を
示す説明図である。FIG. 30 is an explanatory diagram showing life cycle cost prediction based on similar products.
【図31】ライフサイクルコストシミュレータ画面の開
発投資効率予測法を示す説明図である。FIG. 31 is an explanatory diagram showing a development investment efficiency prediction method for a life cycle cost simulator screen.
【図32】ライフサイクルコストシミュレータの構成を
示す説明図である。FIG. 32 is an explanatory diagram showing a configuration of a life cycle cost simulator.
【図33】本発明の設計工数低減の効果を示す説明図で
ある。FIG. 33 is an explanatory diagram showing the effect of reducing the design man-hours of the present invention.
【図34】ライフサイクルコストの構成因子とこれらの
積算方法を示す説明図である。FIG. 34 is an explanatory diagram showing constituent factors of the life cycle cost and a method of accumulating these components.
【図35】本発明の製品開発最適設計のコンセプトを示
す説明図である。FIG. 35 is an explanatory diagram showing the concept of product development optimum design of the present invention.
【図36】表計算による回路ブロック分割評価手段を示
す説明図である。FIG. 36 is an explanatory diagram showing a circuit block division evaluation unit by table calculation.
【図37】計算機による自動評価項目と、ユーザとの対
話により評価する評価項目との説明図である。FIG. 37 is an explanatory diagram of automatic evaluation items by a computer and evaluation items evaluated by a dialog with a user.
20…CAD/CAM/CAT処理装置、31…設計評
価情報部インタフェース部、40…評価情報データベー
ス部、50…ライフサイクルコストシミュレータ、51
…製品品質要因解析手段、75…デザインルールチェッ
ク、80…設計情報、90…ルールベースエキスパート
システム、250…開発投資効率予測手段。20 ... CAD / CAM / CAT processing device, 31 ... Design evaluation information interface unit, 40 ... Evaluation information database unit, 50 ... Life cycle cost simulator, 51
... product quality factor analysis means, 75 ... design rule check, 80 ... design information, 90 ... rule-based expert system, 250 ... development investment efficiency prediction means.
───────────────────────────────────────────────────── フロントページの続き (72)発明者 早川 光春 神奈川県川崎市幸区鹿島田890 日立シス テムプラザ新川崎 株式会社日立製作所情 報システム事業部内 (72)発明者 西田 博 神奈川県小田原市国府津2880番地 株式会 社日立製作所ストレージシステム事業部内 (72)発明者 手塚 要次郎 神奈川県小田原市国府津2880番地 株式会 社日立製作所ストレージシステム事業部内 (72)発明者 森 照夫 神奈川県小田原市国府津2880番地 株式会 社日立製作所ストレージシステム事業部内 (72)発明者 美濃島 智 神奈川県小田原市国府津2880番地 株式会 社日立製作所ストレージシステム事業部内 (72)発明者 池田 正昭 東京都千代田区神田駿河台四丁目6番地 株式会社日立製作所空調システム事業部内 (72)発明者 有本 象治 神奈川県横浜市戸塚区吉田町292番地 株 式会社日立製作所生産技術研究所内 ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor Mitsuharu Hayakawa 890 Kashimada, Sachi-ku, Kawasaki, Kanagawa Hitachi System Plaza Shin-Kawasaki Information Systems Division, Hitachi, Ltd. (72) Inventor Hiroshi Nishida 2880 Kunifu, Odawara, Kanagawa Company Hitachi Storage Systems Division (72) Inventor Yojiro Tezuka 2880 Kozu, Odawara, Kanagawa Stock Company Hitachi Storage Systems Division (72) Inventor Teruo Mori 2880 Kozu, Odawara, Kanagawa Hitachi Ltd. In storage system division (72) Inventor Satoshi Minoshima 2880 Kozu, Odawara-shi, Kanagawa Hitachi Ltd. Storage system division (72) Inventor Masaaki Ikeda 4-chome Kanda Surugadai, Chiyoda-ku, Tokyo (72) Inventor, Shoji Arimoto, 292 Yoshida-cho, Totsuka-ku, Yokohama-shi, Kanagawa Stock company, Hitachi, Ltd.
Claims (6)
用支援システムの対象製品に係る情報に基づいて、前記
対象製品の、配線難易度、製品の大きさ、製造容易性、
納期データ、誤り耐久性データ、信頼性及び保全性デー
タの内の少なくとも1つを含む製品品質に関する情報
と、コストデータとからなる評価の対象となる評価情報
を生成する設計評価情報生成部と、 前記評価情報生成部により生成された情報を格納する評
価情報データベースと、 前記評価情報データベースに格納された情報に基づき、
前記対象製品を製造するためのコストと前記対象製品の
製品品質とに関して、それぞれ同一の評価尺度を用いて
評価指標を生成し、該評価指標に基づいてライフサイク
ルコストのシミュレーションを行うライフサイクルコス
トシミュレータと、 前記対象製品に類似する類似製品の設計情報を、前記製
品を構成する最小の知識単位に分類し、該最小の知識単
位を組み合わせて設計手順を定義することにより構築さ
れたルールベースエキスパートシステムと、 該ルールベースエキスパートシステムの知識単位を参照
し、前記対象製品の設計手順を生成するための情報の授
受を行なう対話手段と、 前記ルールベースエキスパートシステムの知識単位の情
報と、前記対象製品に係る情報とを用いて、前記対象製
品の設計手順の自動評価を行うデザインルールチェック
手段と、 を有することを特徴とする製品開発最適設計支援システ
ム。1. A wiring difficulty level, a product size, and a manufacturability of a target product based on information about the target product of a computer-aided support system for improving product design efficiency.
A design evaluation information generation unit that generates evaluation information that is an evaluation target including information about product quality including at least one of delivery date data, error durability data, reliability and maintainability data, and cost data, An evaluation information database that stores the information generated by the evaluation information generation unit, and based on the information stored in the evaluation information database,
A life cycle cost simulator that generates an evaluation index using the same evaluation scale for each of the cost for manufacturing the target product and the product quality of the target product, and simulates the life cycle cost based on the evaluation index. And a rule-based expert system constructed by classifying design information of similar products similar to the target product into minimum knowledge units that constitute the product and defining a design procedure by combining the minimum knowledge units. And a dialogue unit that refers to a knowledge unit of the rule-based expert system to exchange information for generating a design procedure of the target product, information of the knowledge unit of the rule-based expert system, and the target product. A design that automatically evaluates the design procedure of the target product using the related information. Product development optimal design support system characterized by comprising: a rule check means.
機援用支援システムの対象製品に係る情報に基づいて、
前記対象製品の、配線難易度、製品の大きさ、製造容易
性、納期データ、誤り耐久性データ、信頼性及び保全性
データの内の少なくとも1つを含む製品品質に関する情
報と、コストデータとからなる評価の対象となる評価情
報を生成前記ライフサイクルコストシミュレータに入力
するようにしたことを特徴とする請求項1記載の製品開
発最適設計支援システム。2. The design evaluation information generating section, based on information related to a target product of the computer aided support system,
From information on product quality including at least one of wiring difficulty, product size, manufacturability, delivery date data, error durability data, reliability and maintainability data of the target product, and cost data. The product development optimum design support system according to claim 1, wherein evaluation information to be evaluated is input to the life cycle cost simulator.
は、設計/製造/検査/運用/再利用・再生利用/廃棄
までの製品の特性実現性とそれを構成する作り込み品質
とこれらの特性値とから成る多階層構造における最適化
を行う製品品質要因解析手段を有することを特徴とする
請求項1記載の製品開発最適設計支援システム。3. The life cycle cost simulator is made up of characteristic feasibility of a product from design / manufacturing / inspection / operation / reuse / reuse / disposal, built-in quality constituting the product, and these characteristic values. The product development optimum design support system according to claim 1, further comprising a product quality factor analysis means for performing optimization in a multi-layer structure.
は、研究開発で得られると予測される純利益をライフサ
イクルコストで除することにより開発投資効率を求める
開発投資効率予測手段を有することを特徴とする請求項
1記載の製品開発最適設計支援システム。4. The life cycle cost simulator has a development investment efficiency predicting means for obtaining a development investment efficiency by dividing a net profit expected to be obtained by research and development by a life cycle cost. Item 1 Optimal design support system for product development.
階で、使用する回路部品の部品ピン数の合計値を想定基
板面積からパッド寸法を含めた部品投影面積の集計値を
差し引いた値で割ることによりピン密度を推定し、 該ピン密度に基づいて配線容量を推定し、 該配線容量を一層当りの配線収容可能値で割ることによ
り、実装可能な層数を推定し、 該実装可能な層数と総コスト推定値とを突き合わせて回
路基板実装良否の判定を行なうことための支援を行なう
ことを特徴とする請求項1記載の製品開発最適設計支援
システム。5. The design rule checking means determines a total value of the number of component pins of circuit components to be used in a circuit design stage in the computer-aided support system as a projected area of a component including a pad size from an assumed substrate area. The pin density is estimated by dividing by the value obtained by subtracting the aggregated value, the wiring capacity is estimated based on the pin density, and the number of layers that can be mounted is calculated by dividing the wiring capacity by the wiring accommodating value per layer. 2. The product development optimum design support system according to claim 1, which estimates and compares the number of mountable layers with an estimated total cost to determine whether the circuit board is good or bad.
回路設計段階で、ブロック毎に回路分割して設計し、各
ブロックを分割して評価された結果の情報を入力する手
段と、 前記情報を集計して表示する表示手段と、 各部の配線難易度、製造容易性、各部総コスト、基板面
積の均等な回路の割りふり情報の少なくとも1つを入力
する手段と、 を有することを特徴とする請求項1記載の製品開発最適
設計支援システム。6. The interactive means inputs the information of the result of evaluation by dividing each block into a circuit and designing at the circuit design stage of the circuit board in the computer-aided support system. A means for totalizing and displaying the information, a means for inputting at least one of wiring difficulty of each part, manufacturability, total cost of each part, and circuit allocation information having a uniform board area, The product development optimum design support system according to claim 1, further comprising:
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP26647193A JPH06195402A (en) | 1992-10-26 | 1993-10-25 | Optimal design supporting system for product development |
Applications Claiming Priority (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP4-287260 | 1992-10-26 | ||
JP28726092 | 1992-10-26 | ||
JP26647193A JPH06195402A (en) | 1992-10-26 | 1993-10-25 | Optimal design supporting system for product development |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH06195402A true JPH06195402A (en) | 1994-07-15 |
Family
ID=26547461
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP26647193A Pending JPH06195402A (en) | 1992-10-26 | 1993-10-25 | Optimal design supporting system for product development |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH06195402A (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH11288427A (en) * | 1998-02-03 | 1999-10-19 | Toshiba Corp | Device and method for supporting product life cycle plan and medium device for recording program |
JP2002358449A (en) * | 2001-03-30 | 2002-12-13 | Toshiba Corp | Dealing method, dealing system, and dealing program for electronic product |
JP2006500697A (en) * | 2002-09-23 | 2006-01-05 | オプティマム・パワー・テクノロジー・エルピー | Optimization expert system |
JP2006504169A (en) * | 2002-10-21 | 2006-02-02 | ルノー・エス・アー・エス | Electrical architecture synthesis method and synthesis apparatus |
JP2007164357A (en) * | 2005-12-12 | 2007-06-28 | Fujitsu Ltd | Quality control method, quality control program and quality control system |
JP2007257621A (en) * | 2002-03-08 | 2007-10-04 | Jfe Steel Kk | Apparatus for aiding designing for optimum quality |
US7765175B2 (en) | 2003-09-18 | 2010-07-27 | Optimum Power Technology, L.P. | Optimization expert system |
CN109657938A (en) * | 2018-11-30 | 2019-04-19 | 中南大学 | A kind of identification of Rail Transit System cost impact element and analysis method |
-
1993
- 1993-10-25 JP JP26647193A patent/JPH06195402A/en active Pending
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH11288427A (en) * | 1998-02-03 | 1999-10-19 | Toshiba Corp | Device and method for supporting product life cycle plan and medium device for recording program |
JP2002358449A (en) * | 2001-03-30 | 2002-12-13 | Toshiba Corp | Dealing method, dealing system, and dealing program for electronic product |
JP2007257621A (en) * | 2002-03-08 | 2007-10-04 | Jfe Steel Kk | Apparatus for aiding designing for optimum quality |
JP4623020B2 (en) * | 2002-03-08 | 2011-02-02 | Jfeスチール株式会社 | Optimal quality design support device |
JP2006500697A (en) * | 2002-09-23 | 2006-01-05 | オプティマム・パワー・テクノロジー・エルピー | Optimization expert system |
JP2006504169A (en) * | 2002-10-21 | 2006-02-02 | ルノー・エス・アー・エス | Electrical architecture synthesis method and synthesis apparatus |
US7765175B2 (en) | 2003-09-18 | 2010-07-27 | Optimum Power Technology, L.P. | Optimization expert system |
JP2007164357A (en) * | 2005-12-12 | 2007-06-28 | Fujitsu Ltd | Quality control method, quality control program and quality control system |
CN109657938A (en) * | 2018-11-30 | 2019-04-19 | 中南大学 | A kind of identification of Rail Transit System cost impact element and analysis method |
CN109657938B (en) * | 2018-11-30 | 2023-06-23 | 中南大学 | Rail transit system cost influence element identification and analysis method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US6983232B2 (en) | Electronics assembly systems customer benefit modeling tools and methods | |
US5539652A (en) | Method for manufacturing test simulation in electronic circuit design | |
US6496957B1 (en) | Design evaluating method and apparatus for assisting circuit-board assembly | |
EP0323383A2 (en) | An automated system for evaluating the sensitivity of inventory costs due to fluctuations in customer demand | |
Khadem | Efficacy of lean metrics in evaluating the performance of manufacturing system | |
Thornton et al. | More than just robust design: Why product development organizations still contend with variation and its impact on quality | |
Sanderson | Cost models for evaluating virtual design strategies in multicycle product families | |
Don Taylor et al. | Designing New Products: Compatibility with Existing ProductionFacilities and Anticipated Product Mix | |
JPH06195402A (en) | Optimal design supporting system for product development | |
Herrmann et al. | Reducing throughput time during product design | |
Tirpak | Design-to-manufacturing information management for electronics assembly | |
JPH11175577A (en) | Virtual manufacture support design method and virtual manufacture support design system | |
Galbraith et al. | Analysis in manufacturing systems simulation: a case study | |
Abadir et al. | Economics of electronic design, manufacture and test | |
Tsai et al. | Measuring machine-group flexibility: a case study for surface mount assembly line with different configurations | |
Shina et al. | USING CpkAS A DESIGN TOOL FOR NEW SYSTEM DEVELOPMENT | |
O’Flynn et al. | Computer-based concurrent engineering systems | |
Barton et al. | Feedback of manufacturing experience for DFM design rules | |
Clark et al. | A quality modeling system for predicting the yield of assembly and test processes in the printed circuit assembly industry | |
Chincholkar | Design for production: Using manufacturing cycle time information to improve product development | |
SHAMSUDIN | A STUDY ON OVERALL EQUIPMENT EFFECTIVENESS (OEE) FOR PERFORMANCE MEASUREMENT: CASE STUDY FOR SURFACE MOUNT TECHNOLOGY (SMT) DEPARTMENT | |
Velandia et al. | Complex low volume electronics simulation tool to improve yield and reliability | |
Shina | A design quality and cost model for printed circuit board assembly | |
Goel | A new approach to electronic systems reliability assessment | |
Li | Resource and production planning-post ERP implementation at an EMS provider |