JPH06176028A - Operation plan scheduling device - Google Patents

Operation plan scheduling device

Info

Publication number
JPH06176028A
JPH06176028A JP33032892A JP33032892A JPH06176028A JP H06176028 A JPH06176028 A JP H06176028A JP 33032892 A JP33032892 A JP 33032892A JP 33032892 A JP33032892 A JP 33032892A JP H06176028 A JPH06176028 A JP H06176028A
Authority
JP
Japan
Prior art keywords
plan
component
parts
work
change
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP33032892A
Other languages
Japanese (ja)
Inventor
Hiroshi Sato
弘 佐藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toshiba Corp
Original Assignee
Toshiba Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toshiba Corp filed Critical Toshiba Corp
Priority to JP33032892A priority Critical patent/JPH06176028A/en
Publication of JPH06176028A publication Critical patent/JPH06176028A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • General Factory Administration (AREA)

Abstract

PURPOSE:To minimize reserved components and shorten the lead time by indicating re-operation as to a component for which replanning needs to be indicated as a result of the diversion of reserved components. CONSTITUTION:The plan of a machine whose operation process has high priority is read out of an assembly plan information file 6, its constituent components are expanded by referring to component constitution information in a component constitution information file 5, and reserved components registered in a diverted component storage information file 7 for the respective constituent components are preferentially put on order. Then a component diversion rescheduling means 8 considers that operation for the same component is completed when the same component is present and outputs no operation indication, and writes a re- operation indication and a re-ordering indication as operation indication information in an operation indication information file 9 as to a nonidentical component, namely, a component for which replanning should be indicated as a result of the diversion of the reserved components, thereby scheduling the operation.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、製造業における製造管
理、組立管理システムに用いられ、号機または製品(以
下、号機として総称する)に対して構成部品の展開を行
ない、組立作業計画のスケジューリングを行なうスケジ
ューリング装置に係り、特に作業計画の変更によって保
留部品が発生した際に、その保留部品の取扱いを優先的
に他の計画に転用して活用するようにした作業計画スケ
ジューリング装置に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention is used in a manufacturing control system and an assembly control system in a manufacturing industry, and develops components for a machine or product (hereinafter collectively referred to as machine) and schedules an assembly work plan. More particularly, the present invention relates to a work plan scheduling apparatus which, when a reserved part is generated due to a change in a work plan, preferentially diverts and uses the handling of the reserved part to another plan. .

【0002】[0002]

【従来の技術】従来、製造業における製品組立の作業計
画は、最終的に製品の組立を行なうまでに、幾レベルか
の工程があり、下位レベルで組み立てられた部品を基に
上位レベルの組み立てが行なわれるような部品構成にて
成り立っている。
2. Description of the Related Art Conventionally, a work plan for assembling products in the manufacturing industry has several levels of steps until the final assembly of products, and the upper level assembly is based on the parts assembled at the lower level. It is made up of parts such that

【0003】ところで、以上のような製品組立の作業計
画において、計画の変更が生じた場合には、下位レベル
で組み立てられた部品は、既に号機に対しての紐付けが
行なわれており、再スケジューリングによって日程がず
れた場合、部品は保留扱いとなり、またキャンセルにな
った部品に関しては、人手によりメンテナンスを行なっ
て他の計画での転用を考えなければならない。さらに、
頻繁に計画変更が発生した場合には、計画の変更すら行
なうことができなかったり、本来他の計画に転用できる
部品に関しても、倉庫に入ったまま使用されなかったり
というように、倉庫の棚の有効活用、あるいは効率的な
作業計画のスケジューリングを行なうことは非常に困難
なことである。
By the way, in the work plan for product assembly as described above, when the plan is changed, the parts assembled at the lower level have already been linked to the machine, If the schedule is shifted due to scheduling, the parts are treated as pending, and the canceled parts must be manually maintained and considered for use in another plan. further,
If the plan changes frequently, you cannot even change the plan, or even if you can't use the parts that were originally diverted to another plan, they will remain unused in the warehouse. It is very difficult to effectively utilize or schedule work plans efficiently.

【0004】[0004]

【発明が解決しようとする課題】以上のように、従来の
作業計画のスケジューリングにおいては、作業計画の変
更、またはキャンセルが余儀なくされ、既に下位工程で
の組立が完了して、保留扱いにしなければならない部品
が出るような場合、計画の変更が受け付けられなかった
り、やむを得ず変更を行なったとしても、オペレータの
操作により他計画への転用を考えなければ、保留部品が
倉庫内に残ったままになり、効率的な倉庫の棚の運用、
作業計画のスケジューリングを行なうことが困難である
という問題があった。
As described above, in the conventional work plan scheduling, the work plan must be changed or canceled, and the assembly in the lower process has already been completed and the work plan must be put on hold. If there are parts that do not meet the plan, even if the plan change is not accepted or if it is unavoidable, if the operator does not consider diversion to another plan, the reserved parts will remain in the warehouse. , Efficient warehouse shelf operation,
There is a problem that it is difficult to schedule a work plan.

【0005】本発明の目的は、作業計画のスケジューリ
ング時に、計画変更により発生した保留部品を優先的に
活用して、作業計画の再スケジューリングを行なうこと
により、倉庫の棚の在庫を減らして保留部品を最小限に
抑え、完成済みの保留部品を使うことによりリードタイ
ムの短縮を図ることが可能な極めて信頼性の高い作業計
画スケジューリング装置を提供することにある。
An object of the present invention is to reduce the inventory of the shelves in the warehouse by rescheduling the work plan by preferentially utilizing the reserved parts generated by the plan change when scheduling the work plan. It is an object of the present invention to provide an extremely reliable work plan scheduling apparatus capable of minimizing lead time by using completed holding parts.

【0006】[0006]

【課題を解決するための手段】上記の目的を達成するた
めに本発明では、製造業における製造、組立の作業計画
をスケジューリングする装置において、作業計画の変更
時に、変更の対象となる号機および変更の区分を入力す
る計画変更入力手段と、計画変更入力手段からの変更号
機および変更区分を受け付けると、該当号機の構成部品
を展開して各構成部品の組立進捗状況を調べ、既に組立
が完成して倉庫内に仕掛かっている部品が存在する場合
に、当該部品を保留部品として転用部品保存手段に登録
する転用部品取出手段と、作業計画の変更に伴なう作業
計画の再スケジューリングを要求する再スケジューリン
グ要求手段と、再スケジューリング要求手段からの再ス
ケジューリング要求を入力すると、作業工程の優先度の
高い号機の構成部品を展開し、各構成部品について転用
部品保存手段に登録されている保留部品に優先的に引き
当てを行ない、保留部品を転用したことによって再計画
の指示を行なわなければならない部品について再作業指
示を行なうことにより、作業計画のスケジューリングを
行なう部品転用再スケジューリング手段とを備えて構成
している。
In order to achieve the above-mentioned object, according to the present invention, in a device for scheduling a work plan for manufacturing and assembling in a manufacturing industry, when a work plan is changed, the machine to be changed and the change When the plan change input means for inputting the category of the number, the changed machine and the change category from the plan change input means are accepted, the components of the relevant machine are expanded, the assembly progress status of each component is checked, and the assembly is already completed. If there is a part in progress in the warehouse, the part is registered as a reserved part in the converted part storage means, and a rescheduling request for rescheduling the work plan due to the work plan change is made. When the scheduling requesting means and the rescheduling requesting means from the rescheduling requesting means are inputted, the constituent parts of the machine having the high priority of the work process. To prioritize the reserved parts registered in the converted part storage means for each component, and give the rework instruction for the parts that need to be replanned by diverting the reserved parts. Accordingly, the component diversion rescheduling means for scheduling the work plan is provided.

【0007】[0007]

【作用】従って、本発明の作業計画スケジューリング装
置においては、作業計画の変更時に、変更の対象となる
号機および変更の区分を受け付けると、該当号機の構成
部品を展開して各構成部品の組立進捗状況が調べられ、
既に組立が完成して倉庫内に仕掛かっている部品が存在
する場合には、その部品が保留部品として転用部品保存
手段に登録され、作業計画の変更に伴なう作業計画の再
スケジューリング要求を入力すると、作業工程の優先度
の高い号機の構成部品が展開され、各構成部品について
転用部品保存手段に登録されている保留部品が優先的に
引き当てが行なわれ、保留部品を転用したことによって
再計画の指示を行なわなければならない部品について再
作業指示を行なうことによって、作業計画のスケジュー
リングが行なわれることにより、既に仕掛かり中の部品
を持つ号機の製造、組立作業計画の変更を容易に行なう
ことができ、変更により発生した保留部品を他の計画に
転用することにより、倉庫の棚の使用数の削減、ならび
に号機組立のリードタイムの短縮を図ることができる。
Therefore, in the work plan scheduling apparatus of the present invention, when the work plan is changed, when the machine number to be changed and the classification of the change are accepted, the constituent parts of the concerned machine are expanded and the assembling progress of each constituent part is progressed. The situation is investigated,
If there is a part that has already been assembled and is in the warehouse, the part is registered as a reserved part in the diversion part storage means, and a rescheduling request for the work plan accompanying the change of the work plan is input. Then, the components of the machine with the highest priority in the work process are expanded, and the reserved parts registered in the converted part storage means are assigned with priority for each component, and the reserved parts are diverted and re-planned. The work plan is scheduled by issuing a re-work instruction for the parts that must be instructed, and it is easy to change the manufacturing plan and the assembly work plan of the machine with the parts already in process. The number of warehouse shelves used can be reduced by reusing the reserved parts generated by the changes to other plans, and the number of units assembled can be reduced. It is possible to shorten the time.

【0008】[0008]

【実施例】本発明は、通常行なわれる組立作業計画のス
ケジューリングに対して、作業計画の変更を行なった場
合に発生する保留部品を優先的に他の計画に転用するも
のである。以下、上記のような考え方に基づく本発明の
一実施例について、図面を参照して詳細に説明する。図
1は、本発明による作業計画スケジューリング装置の全
体構成例を示す機能ブロック図である。
BEST MODE FOR CARRYING OUT THE INVENTION The present invention preferentially diverts a reserved part that occurs when a work plan is changed to another plan in comparison with the scheduling of an assembly work plan that is normally performed. An embodiment of the present invention based on the above concept will be described below in detail with reference to the drawings. FIG. 1 is a functional block diagram showing an example of the overall configuration of a work plan scheduling apparatus according to the present invention.

【0009】すなわち、本実施例の作業計画スケジュー
リング装置は、図1に示すように、計画変更入力端末1
と、再スケジューリング要求端末2と、計画変更受付手
段3、転用部品取出し手段4、部品構成情報ファイル
5、組立計画情報ファイル6、転用部品保存情報ファイ
ル7、部品転用再スケジューリング手段8、作業指示情
報ファイル9を有する製造管理計算機10とから構成し
ている。
That is, as shown in FIG. 1, the work plan scheduling apparatus of this embodiment has a plan change input terminal 1
, A rescheduling request terminal 2, a plan change acceptance means 3, a diverted parts takeout means 4, a parts configuration information file 5, an assembly plan information file 6, a diverted parts storage information file 7, a parts diversion rescheduling means 8, work instruction information It is composed of a manufacturing control computer 10 having a file 9.

【0010】ここで、計画変更入力端末1は、作業計画
の変更時に、変更の対象となる号機、およびその変更の
区分(計画キャンセルなのか、日程の変更なのか)を、
画面入力により選択するものである。また、再スケジュ
ーリング要求端末2は、作業計画の変更に伴なう作業計
画の再スケジューリングを要求するものである。一方、
計画変更受付手段3は、計画変更入力端末1からの変更
号機および変更区分を受け付けるものである。
Here, when the work plan is changed, the plan change input terminal 1 determines the number of the machine to be changed and the classification of the change (whether the plan is canceled or the schedule is changed).
It is selected by screen input. The rescheduling request terminal 2 requests the rescheduling of the work plan accompanying the change of the work plan. on the other hand,
The plan change receiving means 3 receives the change machine and the change classification from the plan change input terminal 1.

【0011】また、転用部品取出し手段4は、計画変更
受付手段3により変更号機および変更区分を受け付ける
と、部品構成情報ファイル5の部品構成情報を参照して
該当号機の構成部品を展開し、組立計画情報ファイル6
の組立計画情報を参照して各構成部品の組立進捗状況を
調べ、既に組立が完成して倉庫内に仕掛かっている部品
が存在する場合に、その部品を保留部品として転用部品
保存情報ファイル7に登録すると共に、日程の変更のみ
で後から組立の必要な部品を組立計画情報ファイル6に
登録するものである。一方、部品構成情報ファイル5
は、部品構成情報を保存するものである。また、組立計
画情報ファイル6は、日程の変更のみで後から組立の必
要な部品情報を組立計画情報として保存するものであ
る。さらに、転用部品保存情報ファイル7は、転用部品
保存情報を保存するものである。
When the plan change accepting means 3 accepts the changed machine and the change classification, the diverted parts taking-out means 4 refers to the parts composition information in the parts composition information file 5 to develop the components of the corresponding machine and assemble them. Plan information file 6
The assembly progress status of each component is checked by referring to the assembly plan information of No., and when there is a part that is already assembled and is in the warehouse, the part is stored as a reserved part in the diversion part storage information file 7. In addition to the registration, the parts required to be assembled later are registered in the assembly plan information file 6 only by changing the schedule. On the other hand, the parts configuration information file 5
Is for storing the component configuration information. Further, the assembly plan information file 6 stores the parts information that needs to be assembled later only as a schedule change as the assembly plan information. Further, the diverted component storage information file 7 stores diverted component storage information.

【0012】一方、部品転用再スケジューリング手段8
は、再スケジューリング要求端末2からの再スケジュー
リング要求を入力すると、組立計画情報ファイル6より
作業工程の優先度の高い号機の計画を読み出し、その構
成部品を部品構成情報ファイル5の部品構成情報を参照
して展開し、各構成部品について転用部品保存情報ファ
イル7に登録されている保留部品に優先的に引き当てを
行ない、同一部品が存在する場合には、同部品は既に作
業完了済みであるとして作業指示は出力せず、同一部品
が存在しない部品について、すなわち保留部品を転用し
たことによって再計画の指示を行なわなければならない
部品について、再作業指示、再発注指示を作業指示情報
として作業指示情報ファイル9に対して書き込みを行な
うことにより、作業計画のスケジューリングを行なうも
のである。また、作業指示情報ファイル9は、部品転用
再スケジューリング手段8からの作業指示情報を保存す
るものである。次に、以上のように構成した本実施例の
作業計画スケジューリング装置の動作について、図2な
いし図5を用いて説明する。まず、図2は、通常組立計
画をスケジューリングする際に必要となる完成号機に対
する部品構成の一例を示す図である、
On the other hand, the parts diversion rescheduling means 8
When a rescheduling request is input from the rescheduling request terminal 2, the plan of the machine having the higher priority of the work process is read from the assembly plan information file 6 and the component parts thereof are referred to the component structure information of the component structure information file 5. Then, for each component, the reserved parts registered in the diversion part storage information file 7 are assigned with priority, and if the same parts exist, the parts are considered to have already been completed. No instruction is output, and a work instruction information file with re-work instructions and re-order instructions as work instruction information for parts that do not have the same parts, that is, for parts for which rescheduling instructions must be given by diverting reserved parts By writing in 9, the work plan is scheduled. Further, the work instruction information file 9 stores the work instruction information from the parts diversion rescheduling means 8. Next, the operation of the work plan scheduling apparatus of the present embodiment configured as described above will be explained using FIG. 2 to FIG. First, FIG. 2 is a diagram showing an example of a component configuration for a completed machine, which is required when scheduling a normal assembly plan,

【0013】図2において、号機Aについて説明する
と、まず、完成号機は、“a”〜“e”の部品により構
成され、“a”部品、“c”部品、“e”部品について
は、さらに“a1”〜“a3”、“c1”〜“c2”、
“e1”〜“e3”の部品により構成され、“c2”部
品については、さらに“c21”〜“c25”の部品に
より構成されている。
Referring to FIG. 2, the machine A will be described. First, the completed machine is composed of parts "a" to "e", and the parts "a", "c" and "e" will be further described. "A1" to "a3", "c1" to "c2",
It is composed of parts "e1" to "e3", and the part "c2" is further composed of parts "c21" to "c25".

【0014】通常、組立計画をスケジューリングする場
合、図2の右記の工程1より順に作業計画が作られ、最
終的に工程1〜工程2の部品が全て完成された時点で、
最終工程である工程3の計画が作成されることになる。
なお、号機Bについても、同様の考え方により、その説
明は省略するが、部品“c”と“d”については、号機
Aとの共通部品であることだけ述べておく。次に、以上
の条件により作成された号機Aの作業計画について、計
画キャンセルを行なう場合の処理について説明する。計
画変更受付手段3、および転用部品取出手段4では、図
3に示すようなフロー図に従って処理が行なわれる。
Normally, when scheduling an assembly plan, a work plan is created in order from step 1 on the right side of FIG. 2, and finally when all the parts of steps 1 and 2 are completed,
A plan for the final step, Step 3, will be created.
The description of the machine B is omitted based on the same idea, but only the parts “c” and “d” are common parts to the machine A. Next, with respect to the work plan of the number A machine created under the above conditions, a process for canceling the plan will be described. The plan change accepting means 3 and the diverted parts extracting means 4 perform processing according to the flow chart shown in FIG.

【0015】すなわち、まず、計画変更入力端末1よ
り、変更の対象となる号機と変更の区分(1=キャンセ
ル、2=日程変更)を指定し、計画変更受付手段3に入
力する。
That is, first, from the plan change input terminal 1, the number of the machine to be changed and the category of the change (1 = cancel, 2 = change schedule) are specified and input to the plan change receiving means 3.

【0016】計画変更受付手段3により、以上の受け付
けが完了すると、転用部品取出手段4により、該当号機
Aの構成部品が部品構成情報ファイル5の部品構成情報
を参照しながら展開され、各構成部品の進捗状況が組立
計画情報ファイル6の組立計画情報より参照される。こ
の結果、構成部品の進捗状況が“未着手”であれば、何
もしないで、構成部品の進捗状況が“完了済み”であれ
ば、転用部品保存情報ファイル7にその部品情報が登録
される。
When the above-mentioned acceptance is completed by the plan change accepting means 3, the diversion parts extracting means 4 develops the constituent parts of the corresponding machine A with reference to the part composition information of the part composition information file 5, The progress status of is referred to from the assembly plan information in the assembly plan information file 6. As a result, if the progress status of the component is “not yet started”, nothing is done, and if the progress status of the component is “completed”, the component information is registered in the diversion component storage information file 7. .

【0017】次に、以上の変更要求が完了したら、再ス
ケジューリング要求端末2より、部品転用再スケジュー
リング手段8に作業計画の再スケジューリングを要求す
る。すると、部品転用再スケジューリング手段8では、
図4に示すようなフロー図に従って処理が行なわれる。
Next, when the above-mentioned change request is completed, the re-scheduling request terminal 2 requests the component diversion re-scheduling means 8 to re-schedul the work plan. Then, in the parts diversion rescheduling means 8,
The processing is performed according to the flowchart shown in FIG.

【0018】すなわち、まず、組立計画情報ファイル6
の組立計画情報より、作業工程の優先度の高い号機が読
み出され、その構成部品が部品構成情報ファイル5の部
品構成情報を参照して展開され、各構成部品1つ1つに
ついて転用部品保存情報ファイル7に登録されている保
留部品に引き当てが行なわれる。この結果、同一部品が
存在する場合には、同部品は既に作業完了済みであると
して作業指示は出されない。また、同一部品が存在しな
い部品については、作業指示情報が作業指示情報ファイ
ル9に書き込まれる。以上の処理が、構成部品の全てに
対して行なわれる。
That is, first, the assembly plan information file 6
From the assembly plan information of No., the machine with the highest priority of the work process is read out, its component parts are developed by referring to the component structure information of the component structure information file 5, and the diversion part is stored for each one of the component parts. The reserved parts registered in the information file 7 are allocated. As a result, when the same component exists, the work instruction is not issued because the work of the same component has already been completed. Further, the work instruction information is written in the work instruction information file 9 for the parts that do not have the same parts. The above processing is performed for all the components.

【0019】図5は、本実施例と従来の方法でスケジュ
ーリングを行なった場合の、(a)工数および作業指示
の積み上げ、(b)倉庫の棚の使用数の減少効果の一例
を示す図である。
FIG. 5 is a diagram showing an example of the effects of (a) stacking of man-hours and work instructions and (b) reduction of the number of shelves used in a warehouse when scheduling is performed by this embodiment and the conventional method. is there.

【0020】図5(a)の上段が従来のスケジューリン
グを行なった場合の工数および作業指示の積み上げ図、
下段が本実施例による工数および作業指示の積み上げ図
である。
The upper part of FIG. 5A is a stacking diagram of man-hours and work instructions when the conventional scheduling is performed,
The lower part is a stacking diagram of man-hours and work instructions according to the present embodiment.

【0021】また、図5(b)の1が号機Aがキャンセ
ルになった時点での倉庫棚の使用数の積上げ図、図5
(b)の2が従来のスケジューリングを行なった場合の
倉庫の棚の使用数の積上げ図、図5(b)の3が本実施
例による場合の倉庫の棚の使用数の積上げ図である。
Further, 1 in FIG. 5 (b) is a stacking diagram of the number of warehouse shelves used when the machine A is canceled, FIG.
2B of FIG. 5B is a stacked diagram of the number of used shelves in the warehouse when the conventional scheduling is performed, and 3 of FIG. 5B is a stacked diagram of the used number of shelves in the warehouse according to the present embodiment.

【0022】上述したように、本実施例では、製造業に
おける製造、組立の作業計画をスケジューリングする装
置を、作業計画の変更時に、変更の対象となる号機、お
よびその変更の区分(計画キャンセルなのか、日程の変
更なのか)を、画面入力により選択する計画変更入力端
末1と、作業計画の変更に伴なう作業計画の再スケジュ
ーリングを要求する再スケジューリング要求端末2と、
計画変更入力端末1からの変更号機および変更区分を受
け付ける計画変更受付手段3と、計画変更受付手段3に
より変更号機および変更区分を受け付けると、部品構成
情報ファイル5の部品構成情報を参照して該当号機の構
成部品を展開し、組立計画情報ファイル6の組立計画情
報を参照して各構成部品の組立進捗状況を調べ、既に組
立が完成して倉庫内に仕掛かっている部品が存在する場
合に、その部品を保留部品として転用部品保存情報ファ
イル7に登録すると共に、日程の変更のみで後から組立
の必要な部品を組立計画情報ファイル6に登録する転用
部品取出し手段4と、再スケジューリング要求端末2か
らの再スケジューリング要求を入力すると、組立計画情
報ファイル6より作業工程の優先度の高い号機の計画を
読み出し、その構成部品を部品構成情報ファイル5の部
品構成情報を参照して展開し、各構成部品について転用
部品保存情報ファイル7に登録されている保留部品に優
先的に引き当てを行ない、同一部品が存在する場合に
は、同部品は既に作業完了済みであるとして作業指示は
出力せず、同一部品が存在しない部品について、すなわ
ち保留部品を転用したことによって再計画の指示を行な
わなければならない部品について、再作業指示、再発注
指示を作業指示情報として作業指示情報ファイル9に対
して書き込みを行なうことにより、作業計画のスケジュ
ーリングを行なう部品転用再スケジューリング手段8と
から構成したものである。
As described above, in the present embodiment, the apparatus for scheduling the work plan for manufacturing and assembling in the manufacturing industry, when the work plan is changed, the machine to be changed and the classification of the change (plan cancel). Or a schedule change), a plan change input terminal 1 for selecting by screen input, a rescheduling request terminal 2 for requesting rescheduling of a work plan accompanying a change of the work plan,
When the plan change accepting means 3 for accepting the change machine and the change category from the plan change input terminal 1 and the change machine and the change category are accepted by the plan change accepting means 3, refer to the component configuration information in the component configuration information file 5 When the component parts of the Unit No. are expanded and the assembly progress information of the assembly plan information file 6 is referred to check the assembly progress status of each component, if the assembly is completed and there is a part in the warehouse, The part is registered as a reserved part in the converted part storage information file 7, and a converted part extracting means 4 for registering a part which needs to be assembled later in the assembly plan information file 6 only by changing the schedule, and a rescheduling request terminal 2 When a rescheduling request is input from the assembly plan information file 6, the plan of the machine with the highest priority of the work process is read and the When a component is expanded with reference to the component configuration information in the component configuration information file 5, the reserved component registered in the diverted component storage information file 7 is assigned to each component with priority, and when the same component exists Does not output a work instruction because the work has already been completed for the same part, and does not output a work order, and does not output a work order for a part that does not have the same part, that is, a part for which a rescheduling instruction must be given by diverting a reserved part The re-ordering instruction is written in the work instruction information file 9 as work instruction information, so as to schedule the work plan.

【0023】従って、組立作業計画のキャンセル、日程
変更時にも、オペレータの操作を必要とすることなく、
組立作業計画のスケジューリングの際に、製造指示が出
されて実際に製造され倉庫内に仕掛かっている部品を有
効的に取り込むようにしているため、倉庫の使用棚を削
減して保留部品を最小限に抑えることが可能となり、ま
た完成済みのキャンセル部品を優先的に使用するように
しているため、リードタイムの短縮を図ることが可能と
なる。
Therefore, even when the assembly work plan is canceled or the schedule is changed, the operator's operation is not required,
When scheduling the assembly work plan, we effectively take in the parts that have been instructed and actually manufactured and are in process in the warehouse. Since the completed canceling parts are preferentially used, the lead time can be shortened.

【0024】[0024]

【発明の効果】以上説明したように本発明によれば、作
業計画の変更時に、変更の対象となる号機および変更の
区分を受け付けると、該当号機の構成部品を展開して各
構成部品の組立進捗状況を調べ、既に組立が完成して倉
庫内に仕掛かっている部品が存在する場合に、当該部品
を保留部品として転用部品保存手段に登録し、作業計画
の変更に伴なう作業計画の再スケジューリング要求を入
力すると、作業工程の優先度の高い号機の構成部品を展
開し、各構成部品について転用部品保存手段に登録され
ている保留部品に優先的に引き当てを行ない、保留部品
を転用したことによって再計画の指示を行なわなければ
ならない部品について再作業指示を行なうことにより、
作業計画のスケジューリングを行なうようにしたので、
作業計画のスケジューリング時に、計画変更により発生
した保留部品を優先的に活用して、作業計画の再スケジ
ューリングを行なうことにより、倉庫の棚の在庫を減ら
して保留部品を最小限に抑え、完成済みの保留部品を使
うことによりリードタイムの短縮を図ることが可能な極
めて信頼性の高い作業計画スケジューリング装置が提供
できる。
As described above, according to the present invention, when a work plan is changed, if the number of the machine to be changed and the classification of the change are accepted, the constituent parts of the concerned machine are expanded and each constituent part is assembled. Check the progress status and if there is a part that has already been assembled and is in the warehouse, register the part as a reserved part in the diversion part storage means and re-create the work plan due to the work plan change. When a scheduling request is entered, the components of the machine with the highest priority in the work process are expanded, and each component is assigned to the reserved parts registered in the diverted parts storage means, and the reserved parts are diverted. By issuing rework instructions for parts that must be replanned by
Since I plan to schedule work plans,
When scheduling a work plan, the reserved parts generated due to the plan change are preferentially used and the work plan is rescheduled to reduce the inventory of warehouse shelves and minimize the reserved parts. It is possible to provide an extremely reliable work plan scheduling apparatus that can shorten the lead time by using the reserved parts.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明による作業計画スケジューリング装置の
一実施例を示す機能ブロック図。
FIG. 1 is a functional block diagram showing an embodiment of a work plan scheduling apparatus according to the present invention.

【図2】同実施例における通常組立計画をスケジューリ
ングする際に必要となる号機の部品構成の一例を示す
図。
FIG. 2 is a diagram showing an example of a component configuration of a machine required when scheduling a normal assembly plan in the same embodiment.

【図3】同実施例における計画変更受付手段、転用部品
取出手段の動作を説明するためのフロー図。
FIG. 3 is a flowchart for explaining the operation of the plan change accepting means and the diversion part extracting means in the embodiment.

【図4】同実施例における部品転用スケジューリング手
段の動作を説明するためのフロー図。
FIG. 4 is a flowchart for explaining the operation of the component diversion scheduling means in the embodiment.

【図5】同実施例における工数・作業指示の積み上げ、
および倉庫棚の使用数の減少効果を説明するための図。
[FIG. 5] Accumulation of man-hours / work instructions in the embodiment,
FIG. 6 is a diagram for explaining the effect of reducing the number of warehouse shelves used.

【符号の説明】[Explanation of symbols]

1…計画変更入力端末、2…再スケジューリング要求端
末、3…計画変更受付手段、4…転用部品取出し手段、
5…部品構成情報ファイル、6…組立計画情報ファイ
ル、7…転用部品保存情報ファイル、8…部品転用再ス
ケジューリング手段、9…作業指示情報ファイル、10
…製造管理計算機。
1 ... Plan change input terminal, 2 ... Rescheduling request terminal, 3 ... Plan change receiving means, 4 ...
5 ... Parts configuration information file, 6 ... Assembly plan information file, 7 ... Diversion parts storage information file, 8 ... Parts diversion rescheduling means, 9 ... Work instruction information file, 10
… Manufacturing control calculator.

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 製造業における製造、組立の作業計画を
スケジューリングする装置において、 前記作業計画の変更時に、変更の対象となる号機および
変更の区分を入力する計画変更入力手段と、 前記計画変更入力手段からの変更号機および変更区分を
受け付けると、該当号機の構成部品を展開して各構成部
品の組立進捗状況を調べ、既に組立が完成して倉庫内に
仕掛かっている部品が存在する場合に、当該部品を保留
部品として転用部品保存手段に登録する転用部品取出手
段と、 前記作業計画の変更に伴なう作業計画の再スケジューリ
ングを要求する再スケジューリング要求手段と、 前記再スケジューリング要求手段からの再スケジューリ
ング要求を入力すると、作業工程の優先度の高い号機の
構成部品を展開し、各構成部品について前記転用部品保
存手段に登録されている保留部品に優先的に引き当てを
行ない、保留部品を転用したことによって再計画の指示
を行なわなければならない部品について再作業指示を行
なうことにより、前記作業計画のスケジューリングを行
なう部品転用再スケジューリング手段と、 を備えて成ることを特徴とする作業計画スケジューリン
グ装置。
1. In a device for scheduling a work plan for manufacturing and assembly in a manufacturing industry, when the work plan is changed, a plan change input means for inputting a machine to be changed and a classification of the change, the plan change input When the changed number and change classification from the means are accepted, the components of the relevant number are expanded and the assembly progress status of each component is checked, and when there is a component that is already assembled and is in the warehouse, A diverted part extracting means for registering the part as a reserved part in the diverted part storage means, a rescheduling request means for requesting rescheduling of the work plan accompanying the change of the work plan, and a rescheduling request means for rescheduling When the scheduling request is input, the components of the machine with the highest priority in the work process are expanded, and Scheduling of the work plan by giving priority to the reserved parts registered in the parts storing means, and issuing a rework instruction for the parts that need to be replanned by diverting the reserved parts. A work plan scheduling device, comprising:
JP33032892A 1992-12-10 1992-12-10 Operation plan scheduling device Pending JPH06176028A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP33032892A JPH06176028A (en) 1992-12-10 1992-12-10 Operation plan scheduling device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP33032892A JPH06176028A (en) 1992-12-10 1992-12-10 Operation plan scheduling device

Publications (1)

Publication Number Publication Date
JPH06176028A true JPH06176028A (en) 1994-06-24

Family

ID=18231399

Family Applications (1)

Application Number Title Priority Date Filing Date
JP33032892A Pending JPH06176028A (en) 1992-12-10 1992-12-10 Operation plan scheduling device

Country Status (1)

Country Link
JP (1) JPH06176028A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008015962A (en) * 2006-07-10 2008-01-24 Toyota Motor Corp Computing device of proposed change of production shipment plan which allows production increase
JP2012185739A (en) * 2011-03-07 2012-09-27 Mitsubishi Heavy Ind Ltd Diversion management device and diversion management program
CN113011739A (en) * 2021-03-18 2021-06-22 航天科工空间工程发展有限公司 Rolling scheduling method and computer readable storage medium for satellite production

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008015962A (en) * 2006-07-10 2008-01-24 Toyota Motor Corp Computing device of proposed change of production shipment plan which allows production increase
JP2012185739A (en) * 2011-03-07 2012-09-27 Mitsubishi Heavy Ind Ltd Diversion management device and diversion management program
CN113011739A (en) * 2021-03-18 2021-06-22 航天科工空间工程发展有限公司 Rolling scheduling method and computer readable storage medium for satellite production

Similar Documents

Publication Publication Date Title
US4931932A (en) Computerized system with means to automatically clear and sell wait-listed customer reservations
US12068071B2 (en) System and method of dynamically generating work assignments
KR19980070002A (en) Multi-Objective Decision-Making Method
Sharma et al. New setup-oriented dispatching rules for a stochastic dynamic job shop manufacturing system with sequence-dependent setup times
JPH06176028A (en) Operation plan scheduling device
JP2000030179A (en) Method for planning allocation of freight car
JP2007213141A (en) Personnel distribution system, personnel distribution method, personnel distribution program, and recording medium with the program recorded thereon
JPH10177608A (en) Work flow system
JPH10162296A (en) Vehicle allocation planning device
Kim et al. Multi-agent-based scheduling methods for hybrid cellular production lines in semiconductor industry
US20220114534A1 (en) Method and apparatus for cell-based workforce scheduling
Chincholkar et al. Stochastic coloured Petri nets for modelling and evaluation, and heuristic rule base for scheduling of FMS
JPH03189702A (en) Berth control expert system
JP4149028B2 (en) Scheduling / arrangement management system
JP2000057215A (en) Factory governing production planning system
JP2021121887A (en) Information processing device, processing method and program
Balla et al. Production planning with SAP APO
Stjernholm et al. Optimized Transport and Efficient Goods Reception-Using Time Slot Management to Optimize Performance at the Interface Between External and Internal Logistics
JP2024117505A (en) Management device and logistics information management method
JPH08137972A (en) Shortest shipping route judging device
JP2005302050A (en) Scheduling and arrangement management system
JP3520097B2 (en) Library system control method and library system
JP2002342512A (en) Repair management system and repair system for equipment
Brennan A manufacturing paradigm for knowledge-intensive firms
Rau Scheduling Air Mobility Command's Channel Cargo Missions