JPH058282B2 - - Google Patents

Info

Publication number
JPH058282B2
JPH058282B2 JP60059477A JP5947785A JPH058282B2 JP H058282 B2 JPH058282 B2 JP H058282B2 JP 60059477 A JP60059477 A JP 60059477A JP 5947785 A JP5947785 A JP 5947785A JP H058282 B2 JPH058282 B2 JP H058282B2
Authority
JP
Japan
Prior art keywords
rail
concrete
gate
suspended
slab
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP60059477A
Other languages
Japanese (ja)
Other versions
JPS61221403A (en
Inventor
Hiroshi Nakayama
Yoichi Ootaka
Noboru Funato
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tokyu Construction Co Ltd
Original Assignee
Tokyu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tokyu Construction Co Ltd filed Critical Tokyu Construction Co Ltd
Priority to JP5947785A priority Critical patent/JPS61221403A/en
Publication of JPS61221403A publication Critical patent/JPS61221403A/en
Publication of JPH058282B2 publication Critical patent/JPH058282B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Machines For Laying And Maintaining Railways (AREA)

Description

【発明の詳細な説明】 <産業上の利用分野> 本発明は電車用走行路の施工方法に関するもの
である。
DETAILED DESCRIPTION OF THE INVENTION <Industrial Field of Application> The present invention relates to a method of constructing a running track for trains.

<従来の技術> コンクリート製道床にレールを敷設する場合に
次のような問題がある。
<Conventional technology> When laying rails on a concrete track bed, there are the following problems.

<イ> コンクリート道床上の枕木は正確な高
さ、位置に敷設しなければならない。
<B> Sleepers on the concrete track bed must be installed at the correct height and position.

しかしコンクリート道床の平面形状は正確で
はないから、くさびなどを挿入しつつ枕木の高
さや位置を決めるのは手数を要する作業であ
る。
However, since the planar shape of the concrete track bed is not accurate, determining the height and position of the sleepers while inserting wedges is a time-consuming task.

<ロ> 所定の高さ、位置に位置決めした枕木の
周囲には間詰めコンクリートを打設して枕木を
固定しなければならない。
<B> The sleepers must be fixed by placing filler concrete around the sleepers that have been positioned at the specified height and position.

このように道床コンクリートの表面を多少低
く設定し、その後間詰めコンクリートを打設す
るという二重の作業が必要となる。
In this way, a double work is required: setting the surface of the track bed concrete somewhat low and then placing filler concrete.

<ハ> コンクリート枕木や間詰めコンクリート
の重量の増加によりスラブに加わる加重が大き
くなる。
<C> As the weight of concrete sleepers and filler concrete increases, the load applied to the slab increases.

そのためスラブ側の寸法が過大となる。 Therefore, the dimension on the slab side becomes excessive.

<本発明の目的> 本発明は上記のような点を改善するためになさ
れたもので次のような車両走行路の施工方法を提
供することを目的とする。
<Objective of the present invention> The present invention has been made in order to improve the above-mentioned points, and an object of the present invention is to provide the following method of constructing a vehicle running road.

<イ> レールの高さ調整が容易な施工方法 <ロ> スラブ駆体のコンクリート打設作業を1
回行うだけで完成することができ、2回目の間
詰めコンクリートの打設を省略できる施工方
法。
<A> Construction method that allows easy rail height adjustment <B> Concrete pouring work for slab structure
A construction method that can be completed in just one step and eliminates the need for a second pouring of filler concrete.

<本発明の構成> 次に本発明の一実施例を図面と共に説明する。<Configuration of the present invention> Next, one embodiment of the present invention will be described with reference to the drawings.

<イ> 門型材 門型材1は、線路横断方向に位置させる主桁1
1と、その両端に垂直に設けた脚柱12により構
成する。
<A> Gate material The gate material 1 is the main girder 1 located in the cross-track direction.
1 and pillars 12 provided vertically at both ends thereof.

門型材1の主桁11の長さは1組の軌条レール
2をまたぐことのできるだけの長さで構成する。
The length of the main girder 11 of the gate member 1 is set to be long enough to straddle one set of rails 2.

脚柱12の下端には車輪13を、脚柱12に対
して垂直のピンで軸支する。
A wheel 13 is pivotally supported at the lower end of the pedestal 12 by a pin perpendicular to the pedestal 12.

<ロ> 吊り下げ装置 主桁11にはレール吊り下げ用の吊り下げ装置
3を設ける。
<B> Hanging device The main girder 11 is provided with a hanging device 3 for hanging the rail.

吊り下げ装置3は例えば垂直に設けたボルト3
1と、ボルト下端に取り付けたつめ32によつて
構成する。
The hanging device 3 is, for example, a bolt 3 installed vertically.
1 and a pawl 32 attached to the lower end of the bolt.

ボルト31は主桁11に開設した長孔に沿つ
て、主桁11の軸方向、すなわちレール横断方向
にスライド自在である。
The bolts 31 are slidable along the long holes formed in the main girder 11 in the axial direction of the main girder 11, that is, in the rail transverse direction.

ボルト31はその上部のナツト33などを回転
することにより上昇下降が自在である。
The bolt 31 can be moved up and down by rotating a nut 33 on the top thereof.

もちろん上記の組合せに限らず、主桁11の軸
方向、及び上昇、下降が自由な構成であればその
他の公知の装置を利用できる。
Of course, the combination is not limited to the above, and other known devices can be used as long as the main girder 11 can be freely moved up and down in the axial direction.

<ハ> 門型材群の連結 同一形状、寸法の門型材1を複数基並行に設置
し、各門型材1間を、レールの方向と並行の連結
材4で連結する。
<C> Connection of gate-shaped members A plurality of gate-shaped members 1 having the same shape and dimensions are installed in parallel, and each gate-shaped member 1 is connected by a connecting member 4 parallel to the direction of the rail.

この場合、門型材1と連結材4を剛結せず、垂
直ピンなどを介して連結することによつて曲線部
通過の際に各門型材1間の角度を変えることが可
能となる。
In this case, by connecting the gate-shaped members 1 and the connecting members 4 through vertical pins or the like instead of rigidly connecting them, it becomes possible to change the angle between each gate-shaped member 1 when passing through a curved portion.

<ニ> ターゲツト 門型材1群の一定の位置、好ましくは中心位置
にターゲツト5を設けておく場合もある。
<D> Target A target 5 may be provided at a certain position, preferably at the center, of the first group of portal members.

ターゲツト5としては簡単な目盛りでもよい
が、レーザ測量機に対応できるような公知のター
ゲツトを利用すると、直線の設定には便利であ
る。
Although a simple scale may be used as the target 5, it is convenient to use a known target that can be used with a laser surveying instrument to set a straight line.

<本発明の施工方法> 次に施工方法について説明する。<Construction method of the present invention> Next, the construction method will be explained.

<イ> レール側の装備 レール2の下面に、クランプ22を介して固定
板21を適当な間隔で取り付ける。
<B> Equipment on the rail side Attach the fixing plates 21 to the lower surface of the rail 2 via clamps 22 at appropriate intervals.

この固定板21はレール間を横断する枕木とは
異なり、1本のレールの下面に取り付ける小型の
金属板である。
This fixed plate 21 is different from a sleeper that crosses between rails, and is a small metal plate attached to the lower surface of one rail.

そして1枚の固定板21には垂直ボルトを複数
本貫通し、ボルト下部には埋め込みナツト筒23
をねじ込んでこれを固定板21の下面に露出させ
る。
A plurality of vertical bolts are passed through one fixing plate 21, and a nut cylinder 23 is embedded in the lower part of the bolt.
is screwed in to expose it on the lower surface of the fixing plate 21.

<ロ> レールの吊り下げ 装備の終わつたレール2を2本並行に、複数組
の門型材1の吊り下げ装置3で吊り下げ、車輪1
3を使つて所定位置まで前進させる。
<B> Hanging the rails Two fully equipped rails 2 are suspended in parallel using the hanging device 3 of multiple sets of gate materials 1, and the wheels 1 are suspended.
3 to move it forward to the specified position.

<ハ> スラブの形状 その時スラブ6は中央に軌道設置用の溝61を
レール延長方向に凹設しておく場合(第3図)
と、溝61を凹設せず、スラブ6の上面を平面形
状に仕上げてしまう場合(第4図)とがあるが、
後者については後述する。
<C> Shape of the slab In this case, the slab 6 has a groove 61 for installing the track in the center in the direction of rail extension (Figure 3)
In some cases, the groove 61 is not recessed and the upper surface of the slab 6 is finished in a planar shape (Fig. 4).
The latter will be discussed later.

<ニ> コンクリート打設 所定位置まで門型材1群を移動させたら、レー
ル中心線をターゲツト5を利用して設定する。
<D> Concrete pouring After moving the first group of gate materials to the specified position, set the rail center line using target 5.

次に吊り下げ装置3の横断方向への移動と上下
動を行つてレール2を正確な位置に保持する。
The suspension device 3 is then moved transversely and vertically to hold the rail 2 in the correct position.

従つてレール2は溝61内で空中に浮いている
ことになる。
Therefore, the rail 2 is floating in the air within the groove 61.

この状態で溝61内にコンクリートを打設すれ
ば、レール2下面の埋め込みナツト筒23は正確
な位置でコンクリート内に埋め込まれ、レール2
の固定が完了する。
If concrete is poured into the groove 61 in this state, the embedded nut cylinder 23 on the lower surface of the rail 2 will be embedded in the concrete at the correct position, and the rail 2
fixation is completed.

<ホ> 他の実施例1(第4図) 門型材1から、2本の吊り下げ装置3の両外側
に型枠7を同様に垂下する構成を採用することも
できる。
<E> Other Embodiment 1 (FIG. 4) It is also possible to adopt a configuration in which the formwork 7 is similarly suspended from the gate material 1 on both outsides of the two hanging devices 3.

この型枠7もスライド、及び昇降可能なロツド
71の下部に固定することによつてコンクリート
打設範囲の設定が簡単にできる。
By fixing this formwork 7 to the lower part of the rod 71 which can slide and move up and down, the concrete pouring range can be easily set.

<ヘ> その他の実施例2(第5図) リニアモーターカー電車用の走行路を施工する
場合には、門型材1からリアクシヨンプレート8
を吊り下げ、このリアクシヨンプレート8の下面
に設けた埋め込みナツト筒81が埋設する状態で
コンクリートを打設する。
<F> Other Example 2 (Fig. 5) When constructing a running track for a linear motor train, from the gate material 1 to the reaction plate 8
is suspended, and concrete is poured in such a state that the embedded nut cylinder 81 provided on the lower surface of the reaction plate 8 is buried.

<本発明の効果> 本発明は上記したようになるから次のような効
果を期待できる。
<Effects of the Present Invention> Since the present invention is as described above, the following effects can be expected.

<イ> コンクリート打設前に、門型材群でレー
ルを支持しておく。
<B> Before pouring concrete, support the rails with gate blocks.

従つて高さの調整、横断方向の位置の調整は
きわめて容易である。
Therefore, height adjustment and transverse position adjustment are extremely easy.

<ロ> 門型材に支えられて正確な位置で空中に
浮かんだ状態のレールに、将来レールを固定す
べき固定板を吊り下げた後、コンクリートを打
設するものである。
<B> Concrete is poured after a fixing plate to which the rail will be fixed in the future is suspended from the rail, which is suspended in the air at a precise position supported by the gate-shaped material.

従つてレールは、設計通りの正しい位置で、
硬化したコンクリート上に固定されることにな
る。
Therefore, the rail is in the correct position as designed,
It will be fixed on hardened concrete.

<ハ> 従つて将来のようにスラブ上にならべて
高さ調整を行う枕木は一切不要であり、足場の
悪い場所で枕木を運搬したり敷設する作業も必
要としない。
<C> Therefore, there is no need for sleepers to be arranged on slabs and height adjusted as in the future, and there is no need to transport or install sleepers in areas with poor footing.

<ニ> スラブコンクリートの打設だけで構成が
完了するから、従来のような間詰めコンクリー
トが不要である。
<D> Since the construction is completed by simply placing slab concrete, there is no need for filler concrete as in the past.

従つて無駄な死荷重が減少し、下部構造の寸
法も必要最少限のものとすることができる。
Therefore, unnecessary dead loads are reduced, and the dimensions of the lower structure can be reduced to the minimum necessary.

<ホ> 枕木を使用しないことから、レール下高
が減少できる。
<E> Since sleepers are not used, the lower height of the rail can be reduced.

その結果、電車床面高さが下がるので、プラ
ツトホーム等の周辺設備の建築物の高さを低く
することができる。
As a result, the height of the train floor is lowered, making it possible to lower the height of peripheral equipment such as platforms.

<ヘ> 門型材には車輪が有るので、コンクリー
トが硬化したらすぐに次の区間まで移動でき
る。
<F> Since the portal has wheels, it can be moved to the next section as soon as the concrete hardens.

そのためレールの運搬、セツト、調整の時間
と作業を短く簡単にして工程を短縮することが
できる。
Therefore, the time and work required for transporting, setting, and adjusting the rails can be shortened and simplified, thereby shortening the process.

<ト> 従来の技術には、レール支承装置の主桁
上面に、主桁と直交する方向にレールを登載
し、このレールの下面にまくらぎを取り付けた
後、コンクリートを打設する上吊り式施工法が
存在する。
<G> Conventional technology includes a top suspension type in which a rail is mounted on the top surface of the main girder of a rail support device in a direction perpendicular to the main girder, sleepers are attached to the bottom surface of this rail, and then concrete is poured. Construction methods exist.

しかしこの方法では、レールの下方に軌道と直
交する方向に主桁が位置するため、コンクリート
を打設する際に障害となり、型枠の組立て形状も
複雑となるため、打設作業が煩雑となる。
However, with this method, the main girder is located below the rail in a direction perpendicular to the track, which becomes an obstacle when pouring concrete, and the shape of the formwork is complicated, making the pouring work complicated. .

それに対して本発明は、レールを門型材より吊
り下げて配置し、コンクリートを打設するため、
レールより下方のコンクリート打設空間には、他
の機材は何も存在しない。
In contrast, in the present invention, the rails are suspended from the gate material and concrete is poured.
There is no other equipment in the concrete placement space below the rail.

従つて、コンクリートの打設に支障をきたすこ
とがなく、型枠も両側に設置するだけで済み、打
設作業を容易に行うことができる。
Therefore, there is no problem with concrete pouring, it is only necessary to install formwork on both sides, and the pouring work can be carried out easily.

【図面の簡単な説明】[Brief explanation of drawings]

第1図:本発明の施工方法の一実施例を施工中
の状態の説明図、第2,3図:施工順序の説明
図、第4,5図:他の実施例の説明図 1……門型材、2……レール、3……吊り下げ
装置、7……型枠、8……リアクシヨンプレー
ト。
Fig. 1: An explanatory diagram of one embodiment of the construction method of the present invention under construction, Figs. 2 and 3: An explanatory diagram of the construction order, Figs. 4 and 5: An explanatory diagram of other embodiments 1... Gate material, 2...Rail, 3...Hanging device, 7...Formwork, 8...Reaction plate.

Claims (1)

【特許請求の範囲】 1 スラブコンクリートの打設前に、 門型材群によつて吊り下げたレールを、 スラブ空間内に位置せしめ、 レールの高さ、方向を設定した後、 レールに吊り下げたレール固定板を埋設する状
態で、 スラブコンクリートを打設して行う、 電車用走行路の施工方法。
[Claims] 1. Before pouring concrete slabs, a rail suspended by a group of portal members is positioned in the slab space, and after setting the height and direction of the rail, the rail is suspended from the rail. A construction method for train tracks that involves placing slab concrete with rail fixing plates buried.
JP5947785A 1985-03-26 1985-03-26 Construction of running road for tramcar Granted JPS61221403A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP5947785A JPS61221403A (en) 1985-03-26 1985-03-26 Construction of running road for tramcar

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP5947785A JPS61221403A (en) 1985-03-26 1985-03-26 Construction of running road for tramcar

Publications (2)

Publication Number Publication Date
JPS61221403A JPS61221403A (en) 1986-10-01
JPH058282B2 true JPH058282B2 (en) 1993-02-01

Family

ID=13114420

Family Applications (1)

Application Number Title Priority Date Filing Date
JP5947785A Granted JPS61221403A (en) 1985-03-26 1985-03-26 Construction of running road for tramcar

Country Status (1)

Country Link
JP (1) JPS61221403A (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4840103A (en) * 1971-09-28 1973-06-13

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5013305U (en) * 1973-06-04 1975-02-12

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4840103A (en) * 1971-09-28 1973-06-13

Also Published As

Publication number Publication date
JPS61221403A (en) 1986-10-01

Similar Documents

Publication Publication Date Title
JP2019501320A (en) Prefabricated slab type anti-vibration track structure system and related construction method
KR20140109732A (en) Three-dimensional solid shape of the Embedded Rail concrete block manufacturing method and Embedded Rail Track System constructing methods using Embedded Rail concrete blocks manufactured by this method
KR20140076937A (en) 3D precast slab track manufacturing device
US4970773A (en) Method of and apparatus for locating operational surfaces on a track electromagnetically levitated vehicles
EP1092065A1 (en) Railway system and its supporting structure, as well as their method of construction
CA2075745C (en) Track for railroad and method of constructing the same
JPH058282B2 (en)
JP2000008304A (en) Pedestal for rail road work beam and execution method of pedestal for rail road work beam
JP2021173051A (en) Viaduct construction method and viaduct construction device
JP3087093B2 (en) The structure of the vertical bridge in the railway viaduct
JP4047093B2 (en) Construction method of multilevel intersection road
EP0574673A2 (en) Process for laying a railroad-subway superstructure without ballast and apparatus for producing said superstructure
JPS62185905A (en) Moving type mold frame construction method of slab of high bridge
CN221501604U (en) Ballastless track laying formwork support tool
JPH058281B2 (en)
JPS62233312A (en) Running truck for moving mold frame apparatus
JPS5829388B2 (en) Approach work equipment for railroad tracks, etc.
JPS6133082B2 (en)
JPH0827702A (en) Formwork construction for track floating slab
NL1009537C2 (en) Track support structure for railway system comprises track bearing slab fixed to integral spacers projecting from bottom of pre-stressed concrete trough units post tensioned in long lengths and supported on piled columns
JPH07116831B2 (en) Traveling mobile formwork device
JPS62206162A (en) Moving type mold frame construction method of high bridge slab
JPS62189255A (en) Running and moving mold frame apparatus for constructing high bridge slab
JPS62206161A (en) Moving type mold frame construction method of high bridge slab
JPS61146964A (en) Moving mold frame apparatus of slab concrete of high bridge