JPH0573006U - Snow melting structure such as roads and parking lots - Google Patents

Snow melting structure such as roads and parking lots

Info

Publication number
JPH0573006U
JPH0573006U JP1425592U JP1425592U JPH0573006U JP H0573006 U JPH0573006 U JP H0573006U JP 1425592 U JP1425592 U JP 1425592U JP 1425592 U JP1425592 U JP 1425592U JP H0573006 U JPH0573006 U JP H0573006U
Authority
JP
Japan
Prior art keywords
heat insulating
insulating material
concrete
snow melting
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP1425592U
Other languages
Japanese (ja)
Other versions
JP2515753Y2 (en
Inventor
雄喜 森田
Original Assignee
株式会社雄電社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社雄電社 filed Critical 株式会社雄電社
Priority to JP1425592U priority Critical patent/JP2515753Y2/en
Publication of JPH0573006U publication Critical patent/JPH0573006U/en
Application granted granted Critical
Publication of JP2515753Y2 publication Critical patent/JP2515753Y2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Cleaning Of Streets, Tracks, Or Beaches (AREA)
  • Road Paving Structures (AREA)

Abstract

(57)【要約】 【目的】 断熱材の敷設が簡便で、生コンクリートの使
用量も計算でき、しかも断熱材の撓み変形等を確実に防
ぐことができる融雪構造体の提供を目的とする。 【構成】 適宜厚さの角型に形成すると共にその上面か
ら裏面に貫通する適宜形状のコンクリート流し込み穴2
を穿設・配列し且つその外周縁に該穴構成凹欠部3を形
成した断熱材1を路床4とヒーター(ヒーター管9)と
の間に敷き詰めて、コンクリート流し込み穴2内並びに
互いに隣接する各断熱材1の短辺縁間の穴構成凹欠部3
相互の適合によって構成されたコンクリート流し込み穴
5内に流れ込んだ生コンクリートの各固化部6によるコ
ンクリート舗装層7の支えによって車両11等の荷重によ
る断熱材1の撓み変形等を確実に防ぐ様にしたことであ
る。
(57) [Abstract] [Purpose] It is an object of the present invention to provide a snow melting structure that is simple in laying a heat insulating material, can calculate the amount of fresh concrete used, and can reliably prevent flexural deformation of the heat insulating material. [Structure] A concrete pouring hole 2 having a square shape with an appropriate thickness and having an appropriate shape penetrating from the upper surface to the back surface thereof.
The heat insulating material 1 in which the holes are formed and arranged and the hole forming recessed portion 3 is formed on the outer peripheral edge thereof is spread between the roadbed 4 and the heater (heater tube 9), and is adjacent to each other in the concrete pouring hole 2 Hole forming recess 3 between the short side edges of each heat insulating material 1
By supporting the concrete pavement layer 7 by the solidified portions 6 of the ready-mixed concrete that flowed into the concrete pouring holes 5 configured by mutual adaptation, it is possible to reliably prevent the bending deformation of the heat insulating material 1 due to the load of the vehicle 11 or the like. That is.

Description

【考案の詳細な説明】[Detailed description of the device]

【0001】[0001]

【産業上の利用分野】[Industrial applications]

本考案は、道路・駐車場等の融雪構造体に関し、詳しくはコンクリート舗装さ れた道路・駐車場等の該コンクリート舗装層の下にヒーターを埋設してなる融雪 構造体の改良に関するものである。 The present invention relates to a snow melting structure for roads, parking lots, etc., and more particularly to an improvement of a snow melting structure in which a heater is embedded under the concrete paving layer for concrete paved roads, parking lots, etc. ..

【0002】[0002]

【従来の技術及びその問題点】[Prior art and its problems]

従来、この種の融雪構造体としては、図3,図4に示した構造のものと、図5 ,図6に示した構造のものとが知られている。しかし乍ら、図3,図4に示す前 者の融雪構造体は路床4上に、外周縁を互いに付き合せ隣接させて断熱材10を敷 き詰めた構造であるから、路床4とコンクリート舗装層7下に鉄筋8を上下に配 して配管されたヒーター管9との間の断熱材10はその厚さ方向(高さ方向)を支 える支持構造が全くない。従って、舗装層7の表面所謂路面7aを走行する車両11 等の荷重により断熱層 が図示の如く撓み変形を起こし、それが原因となって路 面7aに亀裂が入りその補修が面倒で手間が掛かるばかりか、その補修費が莫大な ものになると共に、埋設されたヒーター管が破裂する等、危険がある。一方、図 5,図6に示した後者の融雪構造体の場合は断熱材10を路床4上に配設する時に 各断熱材10の外周縁間を空けた状態で敷き詰めて各断熱材10間にコンクリート流 し込み間隙12を確保して置き、その間隙12に生コンクリートを流し込んでコンク リート舗装層7を路床4上に断熱材10の外周にて支える構造としてあるから、前 者の様な問題を少しは解決できる反面、目安で断熱材10を路床4上に敷き詰めて 各断熱材10間にコンクリート流し込み間隙12を形成確保する施工方法であるため に断熱材10の敷設作業が面倒で、しかもコンクリート流し込み間隙12の間隔にバ ラツキがあることから、生コンクリートの使用量が計算できない等、施工性の面 において問題があった。 Conventionally, as the snow melting structure of this type, the structures shown in FIGS. 3 and 4 and the structures shown in FIGS. 5 and 6 are known. However, since the former snow melting structure shown in FIGS. 3 and 4 has a structure in which the heat insulating material 10 is laid on the roadbed 4 so that the outer peripheral edges thereof are brought into contact with each other and adjacent to each other, There is no support structure for supporting the heat insulating material 10 between the heater pipe 9 in which the reinforcing bars 8 are arranged above and below the concrete pavement layer 7 in the thickness direction (height direction). Therefore, the heat-insulating layer causes a bending deformation as shown in the figure due to the load of the vehicle 11 traveling on the surface of the pavement layer 7, the so-called road surface 7a, which causes cracks on the road surface 7a, which is troublesome to repair. In addition to the cost, the repair cost is enormous and there is a danger that the embedded heater tube will burst. On the other hand, in the case of the latter snow melting structure shown in FIGS. 5 and 6, when the heat insulating material 10 is arranged on the roadbed 4, the heat insulating material 10 is spread over the outer peripheral edges of the heat insulating material 10 so that the heat insulating material 10 can be spread over the heat insulating material 10. A concrete pouring gap 12 is secured between them, and fresh concrete is poured into the gap 12 to support the concrete pavement layer 7 on the roadbed 4 on the outer periphery of the heat insulating material 10. Although such problems can be solved a little, the work of laying the heat insulating material 10 should be carried out because it is a construction method in which the heat insulating material 10 is spread on the roadbed 4 as a guide and the concrete pouring gap 12 is formed between the heat insulating materials 10. There was a problem in terms of workability, such as the amount of fresh concrete used could not be calculated because it was troublesome and there were variations in the intervals of the concrete pouring gap 12.

【0003】[0003]

【考案が解決しようとする課題】[Problems to be solved by the device]

本考案はこの様な従来事情に鑑みてなされたものであり、その解決しようとす る技術的課題は、断熱材の敷設が簡便で、生コンクリートの使用量も計算でき、 しかも断熱材の撓み変形等を確実に防ぐことができる融雪構造体の提供を目的と する。 The present invention has been made in view of such conventional circumstances, and the technical problem to be solved is that the laying of a heat insulating material is easy, the amount of fresh concrete used can be calculated, and the bending of the heat insulating material can be calculated. It is an object of the present invention to provide a snow melting structure capable of reliably preventing deformation and the like.

【0004】[0004]

【課題を達成するための手段】[Means for achieving the object]

上記目的を達成するために本考案が講じる技術的手段は、適宜厚さの角型に形 成すると共にその上面から裏面に貫通する適宜形状のコンクリート流し込み穴を 穿設・配列し且つその外周縁に該穴構成凹欠部を形成した断熱材を路床とヒータ ーとの間に敷き詰めたことを特徴とする。 To achieve the above-mentioned object, the technical means taken by the present invention is to form a square shape having an appropriate thickness, and to form and arrange a concrete pouring hole of an appropriate shape that penetrates from the upper surface to the back surface and to form the outer peripheral edge thereof. In addition, a heat insulating material having the hole forming concave portion is spread between the roadbed and the heater.

【0005】[0005]

【作用】[Action]

而して、上記した本考案の技術的手段によれば、外周縁同志を互いに付き合わ せ隣接させて断熱材を路床上に敷き詰め配設し、然る後、ヒーター管を配管せし めて生コンクリートを断熱材上に流し込んでコンクリート舗装を行なう。それに より、断熱材の上面からその裏面即ち路床上面に向けて抜けるコンクリート流し 込み穴内並びに互いに隣接する各断熱材の外周縁間の穴構成凹欠部相互の適合に よって構成されたコンクリート流し込み穴内に流れ込んだ生コンクリートの固化 部が路床上にコンクリート舗装層を支える柱として作用し、断熱材の撓み変形等 を防ぐ。 Thus, according to the above-mentioned technical means of the present invention, the outer peripheral edges are placed adjacent to each other and the heat insulating material is laid on the roadbed so as to be adjacent to each other. Concrete pavement is carried out by pouring concrete onto the heat insulating material. As a result, in the concrete pouring hole that escapes from the upper surface of the heat insulating material toward the back surface, that is, the upper surface of the roadbed, as well as in the concrete pouring hole that is formed by matching the hole forming recesses between the outer peripheral edges of the adjacent heat insulating materials. The solidified portion of the ready-mixed concrete that flows into the building acts as a pillar that supports the concrete pavement layer on the roadbed, and prevents the heat insulating material from bending and deforming.

【0006】[0006]

【実施例】【Example】

本考案の実施の一例を図面に基づいて以下説明すると、断熱材1は発砲ウレタ ン等の材料を用いて用途に応じた適宜厚さと大きさを有する角型、図面では平面 略長方形状に形成すると共にその上面から裏面に貫通する適宜形状のコンクリー ト流し込み穴2を穿設・配列し且つその外周縁に該穴構成凹欠部3を形成せしめ てなり、上面からその裏面即ち路床4上面に向けて抜けるコンクリート流し込み 穴2内並びに互いに隣接する各断熱材1の外周縁間の穴構成凹欠部3相互の適合 (照合合致)によって構成されたコンクリート流し込み穴5内に流れ込んだ生コ ンクリートの固化部6を路床4上にコンクリート舗装層7を支える柱として作用 させ、舗装層7の表面所謂路面7aを走行する車両11等の荷重による断熱材1の撓 み変形等を防ぐ断熱材保護構造とする。 An embodiment of the present invention will be described below with reference to the drawings. The heat insulating material 1 is made of a material such as a foam urethane and has a rectangular shape having an appropriate thickness and size according to the application, and in the drawing is a substantially rectangular shape. In addition, a concrete casting hole 2 having an appropriate shape penetrating from the upper surface to the rear surface is formed and arranged, and the hole forming recessed portion 3 is formed on the outer peripheral edge thereof. From the upper surface to the rear surface, that is, the upper surface of the roadbed 4. The concrete concrete that flows into the concrete pouring hole 5 that is formed by the mutual matching (matching match) between the hole forming recesses 3 between the outer peripheral edges of the adjacent heat insulating materials 1 and the concrete 2 The solidification part 6 of the above acts as a pillar that supports the concrete pavement layer 7 on the roadbed 4, and prevents the heat insulating material 1 from bending and deforming due to the load of the vehicle 11 traveling on the surface of the pavement layer 7, the so-called road surface 7a. Use a heat material protection structure.

【0007】 コンクリート流し込み穴2は、角や丸形等の適宜形状で図示した如く、断熱材 の上面から裏面に貫通させた断熱材1の長手方向一列に並ぶ様に複数穿設する 一方、穴構成凹欠部3は、前記穴2の開孔形状の半分又はその一部分を構成する 凹欠形状にて且つ四方方向において隣り合う断熱材1の外周各辺縁に適合し合う 位置関係で断熱材1の四隅コーナーを含む外周各辺縁図面ではその短辺縁に凹設 して、図1に示した如く互いに隣接する各断熱材1の短辺縁間に穴構成凹欠部3 相互の適合によってコンクリート流し込み穴5が構成される様にしてある。As shown in the figure, the concrete pouring holes 2 are formed in an appropriate shape such as a corner or a round shape, and a plurality of holes are formed so as to line up in a longitudinal direction of the heat insulating material 1 that penetrates from the upper surface to the back surface of the heat insulating material. The constitutional recessed portion 3 constitutes half or a part of the opening shape of the hole 2 and has a recessed shape and fits with each outer peripheral edge of the heat insulating material 1 adjacent in four directions. In each peripheral edge drawing including the four corners of No. 1 as shown in FIG. 1, the short edge is provided with a recess, and as shown in FIG. 1, the hole forming recesses 3 are fitted between the short edges of the adjacent heat insulating materials 1. The concrete pouring hole 5 is constituted by the above.

【0008】 而して、外周縁同志を互いに付き合わせ隣接させて断熱材1を路床4上に敷き 詰め配設し、然る後、上下に鉄筋8を配したヒーター管9を配管せしめて生コン クリートを断熱材1上に流し込んでコンクリート舗装を行なう。すると、予め設 計された断面積即ち生コンクリートの流入容積にて断熱材1の上面からその裏面 即ち路床4上面に向けて設けたコンクリート流し込み穴2内並びに互いに隣接す る各断熱材1の短辺縁間の穴構成凹欠部3相互の適合によって構成されたコンク リート流し込み穴5内に流れ込んだ生コンクリートの固化部6が路床4上にコン クリート舗装層7を支える柱として作用し、各固化部6の支えによって車両11等 の荷重による断熱材1の撓み変形等を確実に防ぐものできる(図2参照)。Then, the heat insulating material 1 is laid on the roadbed 4 so that the outer peripheral edges thereof are brought into contact with each other so as to be adjacent to each other, and thereafter, the heater pipe 9 having the reinforcing bars 8 arranged above and below is piped. Concrete pavement is performed by pouring green concrete onto the heat insulating material 1. Then, in the pre-designed cross-sectional area, that is, the inflow volume of the fresh concrete, from the upper surface of the heat insulating material 1 to the back surface thereof, that is, the upper surface of the roadbed 4, the inside of the concrete pouring hole 2 and adjacent heat insulating materials 1 The solidified portion 6 of the ready-mixed concrete that has flown into the concrete pouring hole 5 formed by the mutual fitting of the hole forming concave portions 3 between the short side edges acts as a pillar that supports the concrete pavement layer 7 on the roadbed 4. By the support of each solidifying portion 6, it is possible to reliably prevent the heat insulating material 1 from bending and deforming due to the load of the vehicle 11 or the like (see FIG. 2).

【0009】[0009]

【考案の効果】[Effect of the device]

本考案の道路・駐車場等の融雪構造体は叙上の如く、上面から裏面即ち路床上 面に向けて設けた適宜形状のコンクリート流し込み穴内並びに互いに隣接する各 断熱材の外周縁間の穴構成凹欠部相互の適合によって構成されたコンクリート流 し込み穴内に生コンクリートを流し込んで、その流れ込んだ生コンクリートの固 化部にてコンクリート舗装層を支える様にしてなるから、車両等の荷重による断 熱材の撓み変形等を確実に防ぐことが出来る。しかも、予め設計した断面積のコ ンクリート流し込み穴内に生コンクリートを流し込んでコンクリート舗装層を支 える様に構成してなるから、コンクリート舗装時の生コンクリートの使用量が計 算でき、従来の様に断熱材を路床上に敷き詰め配設する際の作業性や生コンクリ ートの使用量等による施工性の問題は全くない。従って、本考案の道路・駐車場 等の融雪構造体によれば、断熱材の敷設が簡便で、生コンクリートの使用量も計 算でき、しかも断熱材の撓み変形等を確実に防ぐことが出来る。 The snow melting structure of the present invention, such as a road and a parking lot, has a hole construction between the outer peripheral edges of the adjacent heat insulating materials inside the concrete pouring holes provided from the upper surface to the rear surface, that is, the upper surface of the roadbed as described above. Fresh concrete is poured into the concrete pouring hole that is configured by the mutual fitting of the recesses, and the concrete pavement layer is supported by the solidified portion of the poured fresh concrete. It is possible to reliably prevent bending deformation of the heat material. Moreover, since the concrete pavement layer is supported by pouring fresh concrete into the concrete pouring hole with a pre-designed cross-sectional area, the amount of fresh concrete used during concrete pavement can be calculated, and the conventional method is used. There is no problem in workability when laying the heat insulating material on the roadbed and workability due to the amount of fresh concrete used. Therefore, according to the snow melting structure for roads, parking lots, etc. of the present invention, it is easy to lay a heat insulating material, the amount of green concrete used can be calculated, and the bending deformation of the heat insulating material can be reliably prevented. .

【図面の簡単な説明】[Brief description of drawings]

【図1】 本考案道路・駐車場等の融雪構造体の実施の
一例を示した平面図で、切欠して示す。
FIG. 1 is a plan view showing an example of implementation of a snow melting structure for a road, a parking lot, etc. according to the present invention, which is cut away.

【図2】 図1のII−II線に沿えた縦断正面図である。FIG. 2 is a vertical sectional front view taken along line II-II in FIG.

【図3】 従来例を示した平面図で、切欠して示す。FIG. 3 is a plan view showing a conventional example, with a cutout.

【図4】 図3の縦断正面図である。4 is a vertical front view of FIG.

【図5】 従来例を示した平面図で、切欠して示す。FIG. 5 is a plan view showing a conventional example, with a cutout.

【図6】 図5の縦断正面図である。FIG. 6 is a vertical front view of FIG.

【符号の説明】[Explanation of symbols]

1…断熱材 2,5…コンク
リート流し込み穴 3…穴構成凹欠部 4…路床 6…固化部 7…コンク
リート舗装層
DESCRIPTION OF SYMBOLS 1 ... Insulating material 2, 5 ... Concrete pouring hole 3 ... Hole structure recessed part 4 ... Roadbed 6 ... Solidification part 7 ... Concrete pavement layer

Claims (1)

【実用新案登録請求の範囲】[Scope of utility model registration request] 【請求項1】 コンクリート舗装された道路・駐車場等
の該コンクリート舗装層の下にヒーターを埋設してなる
融雪構造体に於いて、適宜厚さの角型に形成すると共に
その上面から裏面に貫通する適宜形状のコンクリート流
し込み穴を穿設・配列し且つその外周縁に該穴構成凹欠
部を形成した断熱材を路床とヒーターとの間に敷き詰め
たことを特徴とする道路・駐車場等の融雪構造体。
1. A snow melting structure in which a heater is embedded under a concrete paving layer of a concrete paved road, parking lot or the like, which is formed in a square shape having an appropriate thickness and is formed from the upper surface to the back surface. A road / parking lot characterized by laying out and arranging a concrete pouring hole having an appropriate shape therethrough, and laying a heat insulating material having a hole-forming recessed portion at its outer peripheral edge between the roadbed and the heater Snow melting structure.
JP1425592U 1992-03-18 1992-03-18 Snow melting structure such as roads and parking lots Expired - Lifetime JP2515753Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1425592U JP2515753Y2 (en) 1992-03-18 1992-03-18 Snow melting structure such as roads and parking lots

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1425592U JP2515753Y2 (en) 1992-03-18 1992-03-18 Snow melting structure such as roads and parking lots

Publications (2)

Publication Number Publication Date
JPH0573006U true JPH0573006U (en) 1993-10-05
JP2515753Y2 JP2515753Y2 (en) 1996-10-30

Family

ID=11855986

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1425592U Expired - Lifetime JP2515753Y2 (en) 1992-03-18 1992-03-18 Snow melting structure such as roads and parking lots

Country Status (1)

Country Link
JP (1) JP2515753Y2 (en)

Also Published As

Publication number Publication date
JP2515753Y2 (en) 1996-10-30

Similar Documents

Publication Publication Date Title
JP4508923B2 (en) Snow melting panel, manufacturing method thereof, and snow melting roadbed
JPH0573006U (en) Snow melting structure such as roads and parking lots
JP2020056292A (en) Unit member for construction, manufacturing method for the same, member connecting body, and concrete construction method
CN210262567U (en) Post-pouring belt for cement concrete pavement
JPH0735506U (en) Joint formwork for water-permeable pavement
JP3343598B2 (en) Hanging wall type retaining wall method for lightweight embankment method
JPH0751534Y2 (en) Floor slab with concrete dam
JP3750135B1 (en) Building foundation and building foundation method
JP6650775B2 (en) Construction material for raising the gutter
JP2767379B2 (en) Basic construction method of free slope gutter
JP6775217B1 (en) Drainage basin construction method
JP2773024B2 (en) Groove structure with lid and groove lid forming method
CN115313289A (en) Pavement communication pipeline fixing device for preventing communication pipeline from being damaged and construction method
JP2859139B2 (en) Construction structure of pedestrian road boundary block and pedestrian road boundary
JPH11280008A (en) Precast paving floor board and manufacture thereof
JP3364083B2 (en) Embedded material for concrete slab, substrate for concrete slab having the embedded material, and concrete slab using the substrate
JPS5851208Y2 (en) Structures such as bridges and elevated roads
JP2557040Y2 (en) Pavement structure of snow melting road
JP3048605U (en) Flexible joint material for concrete pavement
JPH10131106A (en) Guide frame body for laying block
JP3091431U (en) Filling lid
JPS5821843Y2 (en) concrete wall
JP3050252U (en) Snow melting road structure
JPS6145267Y2 (en)
JPH1088792A (en) Construction method for building structure