JPH05321564A - Shaft intrusion device - Google Patents

Shaft intrusion device

Info

Publication number
JPH05321564A
JPH05321564A JP12879192A JP12879192A JPH05321564A JP H05321564 A JPH05321564 A JP H05321564A JP 12879192 A JP12879192 A JP 12879192A JP 12879192 A JP12879192 A JP 12879192A JP H05321564 A JPH05321564 A JP H05321564A
Authority
JP
Japan
Prior art keywords
shaft
shafts
penetrating
excavation
penetration
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP12879192A
Other languages
Japanese (ja)
Inventor
Minoru Aoi
実 青井
Takeshi Tsujii
剛 辻井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kobe Steel Ltd
Original Assignee
Kobe Steel Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kobe Steel Ltd filed Critical Kobe Steel Ltd
Priority to JP12879192A priority Critical patent/JPH05321564A/en
Publication of JPH05321564A publication Critical patent/JPH05321564A/en
Pending legal-status Critical Current

Links

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
  • Earth Drilling (AREA)

Abstract

PURPOSE:To carry a large number of extension shafts under a stabilized state from a housing position to an intruding position in an attempt to inhibit an increase in the weight and size of a device. CONSTITUTION:Extension drilling shafts 24 are laid out in both width and length in an erected state and housed in a shaft housing device 14. A take out carrier 16 is installed to the shaft housing device 14. This take out carrier 16 suspends the above drilling shafts 24 on a column unit basis. Each of the drilling shafts 24 is carried to a shaft intruding and pulling device simultaneously by allowing the take out carrier to travel thereat.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、地中止水壁施工機械や
地盤改良機械をはじめとする基礎工事機械、ボーリング
装置等において、複数の軸同士を連結しながらこれらを
地中へ貫入するための装置に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a foundation construction machine such as a ground suspension water wall construction machine or a ground improvement machine, a boring machine, etc., for connecting a plurality of shafts and penetrating them into the ground. Of the device.

【0002】[0002]

【従来の技術】一般に、上記のような基礎工事機械等に
おいては、長尺の軸が使用されることが多い。例えば、
地中撹拌式の地盤改良装置においては、何十メートルに
も及ぶ撹拌軸が上下方向に設置される。このような長尺
の軸は、そのままでは製造、運搬が極めて困難であるた
め、一般には軸方向に複数に分割され、工事現場で適宜
継ぎ足されながら地中へ貫入される。
2. Description of the Related Art Generally, a long shaft is often used in the above-mentioned foundation construction machine. For example,
In the ground agitation type ground improvement device, agitation shafts of tens of meters are installed vertically. Since such a long shaft is extremely difficult to manufacture and transport as it is, it is generally divided into a plurality of parts in the axial direction and appropriately inserted at the construction site to penetrate into the ground.

【0003】さらに近年は、軸同士を自動的に連結しな
がらこれらを貫入する装置も種々提案されている。例え
ば特開平2−243817号公報には、撹拌軸保持装置
部に格納した撹拌軸を撹拌軸つかみ装置部で把持しなが
ら、掴み機構部の旋回により上記撹拌軸をガイドフレー
ム前面まで移動させて順次継足し定位置へ供給するよう
にしたものが示されている。また、特公平3−4419
8号公報には、アーム先端に設けられた継足しホルダ
で、収納位置に収納されている2本の軸を一度に把持し
た後、これらの軸を上記アームの旋回に伴って上記収納
位置から貫入位置まで同時に水平移動させるようにした
ものが示されている。この装置によれば、2本の軸の移
送及び貫入を一度に行うことができる利点がある。
Further, in recent years, various types of devices have been proposed in which the shafts are automatically connected to each other while penetrating them. For example, in Japanese Unexamined Patent Publication No. 2-243817, while the stirring shaft stored in the stirring shaft holding device unit is gripped by the stirring shaft gripping device unit, the stirring shaft unit is swung to move the stirring shaft to the front surface of the guide frame, and sequentially. It is shown to be replenished and supplied to a fixed position. In addition, Japanese Patent Publication No. 3-4419
In Japanese Patent No. 8 publication, a joint holder provided at the tip of an arm grips two shafts stored in a storage position at a time, and then these shafts are moved from the storage position as the arm rotates. It is shown that it is moved horizontally to the penetration position at the same time. This device has the advantage that the two shafts can be transferred and penetrated at the same time.

【0004】[0004]

【発明が解決しようとする課題】近年、上記軸の貫入作
業の能率向上を図るため、3本以上の軸を一方向に並べ
た状態で同時に貫入する装置の開発が要望されている。
In recent years, in order to improve the efficiency of the work of penetrating the shaft, it has been desired to develop a device for penetrating three or more shafts in one direction at the same time.

【0005】ここで、上記各公報に示される装置はいず
れも、アーム等の旋回部材の先端で軸を把持し、上記旋
回部材の旋回によって軸を移送するものであるため、1
本あるいは2本といった少数本の軸の供給は行うことが
できるが、3本以上の多数本の軸を一度に供給するとな
ると、これらの軸の重量に耐え得るまで旋回部材の強度
を高めなければならず、その補強による重量増大は免れ
得ない。また、上記旋回には大きなスペースを要するこ
とになり、装置小型化の大きな妨げとなる。また、多数
本の軸を一度に旋回させると装置がバランスを崩し易
く、機械の安定性を害するおそれがある。
Here, in each of the devices disclosed in the above publications, the shaft is gripped by the tip of a turning member such as an arm, and the shaft is transferred by the turning of the turning member.
Although it is possible to supply a small number of shafts such as two or two, when supplying a large number of shafts of three or more at once, the strength of the swiveling member must be increased until the weight of these shafts can be withstood. In addition, the increase in weight due to the reinforcement cannot be avoided. In addition, a large space is required for the turning, which greatly hinders downsizing of the device. Further, when a large number of shafts are swiveled at one time, the device is likely to lose its balance, which may impair the stability of the machine.

【0006】本発明は、このような事情に鑑み、装置全
体の重量増大及び大型化を抑えながら、複数本の軸を安
定して同時供給し、継足し貫入することができる軸貫入
装置を提供することを目的とする。
In view of such circumstances, the present invention provides a shaft penetrating device capable of stably supplying a plurality of shafts at the same time and adding and penetrating them while suppressing an increase in weight and size of the entire device. The purpose is to do.

【0007】[0007]

【課題を解決するための手段】本発明は、地盤に対して
軸を順に継足しながら貫入するための軸貫入装置におい
て、複数の軸を予め定められた貫入並び方向に並べた状
態で保持し、これらの軸を同時に地中へ貫入する貫入手
段と、複数の軸を上記貫入並び方向及びこれに略直交す
る収納並び方向の双方に並べ、かつ立直させた状態で収
納する軸収納手段と、この軸収納手段に各軸の上方にお
いて上記収納並び方向に走行可能となるように設置され
た移動部材と、この移動部材に昇降可能に設けられ、上
記軸収納手段において上記貫入並び方向に並べられた全
ての軸を一度に保持する昇降部材とを備えたものである
(請求項1)。
DISCLOSURE OF THE INVENTION The present invention relates to a shaft penetrating device for penetrating the ground while sequentially adding the shafts to each other, and holding a plurality of shafts arranged in a predetermined penetrating direction. , A penetration means for penetrating these shafts into the ground at the same time, and a shaft accommodating means for accommodating a plurality of shafts both in the penetrating direction and in the accommodating direction substantially orthogonal thereto, and accommodating in an upright state, A moving member installed in the shaft accommodating means so as to be able to travel in the accommodating arrangement direction above each axis, and a movable member that can be moved up and down and arranged in the penetrating arrangement direction in the shaft accommodating means. And an elevating member for holding all the shafts at once (Claim 1).

【0008】さらに、上記貫入位置の近傍に昇降可能に
設置され、この貫入手段の貫入位置に搬送された全ての
軸を一度に保持する軸保持手段を備えることにより、後
述のようなより優れた効果が得られる(請求項2)。
Further, since it is provided with a shaft holding means which is installed so as to be able to move up and down in the vicinity of the penetration position and holds all the shafts conveyed to the penetration position of the penetration means at one time, it is more excellent as described later. An effect is obtained (Claim 2).

【0009】また本発明は、複数の軸を予め定められた
貫入並び方向に並べた状態で保持し、これらの軸を同時
に地中へ貫入する貫入手段と、地盤上に設置される基台
と、この基台上に上記貫入並び方向と略直交する収納並
び方向に走行可能に設置され、複数の軸を上記貫入並び
方向及び収納並び方向の双方に並べ、かつ立直させた状
態で収納する軸収納手段とを備え、この軸収納手段の走
行によりこの軸収納手段に収納された各軸が上記貫入手
段による貫入位置に到達するように軸収納手段における
各軸の収納位置を設定したものである(請求項3)。
Further, according to the present invention, a plurality of shafts are held in a state of being arranged in a predetermined penetrating arrangement direction, and a penetrating means for penetrating these shafts simultaneously into the ground, and a base installed on the ground. A shaft that is installed on the base so that it can travel in a storage arrangement direction that is substantially orthogonal to the penetration arrangement direction, and that stores a plurality of shafts in both the penetration arrangement direction and the storage arrangement direction and in an upright state. And a storage position of each shaft in the shaft storage means so that each shaft stored in the shaft storage means reaches a penetration position by the penetration means by traveling of the shaft storage means. (Claim 3).

【0010】[0010]

【作用】請求項1記載の装置によれば、例えば次の要領
で複数本の軸の継足し貫入を行うことができる。
According to the apparatus of the first aspect, it is possible to add and penetrate a plurality of shafts in the following manner, for example.

【0011】まず、軸収納手段の各位置に軸を収納し、
かつ、昇降部材が軸収納手段における最前列(すなわち
貫入手段に最も近い列)に貫入並び方向に並べられた軸
と対応する位置まで移動部材を移動させる一方、貫入手
段によって複数本の軸を貫入並び方向に並べた状態で保
持し、これらを地盤に対して同時に所定の深さまで貫入
する。この貫入深さは適宜設定すればよいが、貫入され
た軸の上端が、軸収納手段に収納されている継足し用軸
の下端よりも下方に位置するまで貫入することがより好
ましい。また、貫入後は、貫入手段と既貫入の軸とを切
り離して貫入手段を上限位置まで上昇させる。
First, the shaft is stored in each position of the shaft storing means,
Further, the elevating member moves the moving member to a position corresponding to the shaft arranged in the penetrating direction in the frontmost row (that is, the row closest to the penetrating means) in the shaft housing means, while the penetrating means penetrates the plurality of shafts. It is held in a state of being aligned in the arranging direction, and they are simultaneously penetrated into the ground to a predetermined depth. This penetration depth may be set as appropriate, but it is more preferred that the upper end of the penetrated shaft penetrates until it is located below the lower end of the supplementary shaft housed in the shaft housing means. After the penetration, the penetration means and the already penetrated shaft are separated to raise the penetration means to the upper limit position.

【0012】次に、上記昇降部材によって上記最前列に
おける全ての軸を同時に保持し、この昇降部材を移動部
材に対して上昇させることにより、各軸を吊り上げる。
この状態のまま、搬送部材を貫入手段に向けて走行さ
せ、昇降部材に保持した各軸を貫入手段の貫入位置へ供
給する。そして、この位置で、継足し用軸の下端が既に
貫入されている軸の上端に到達するまで昇降部材を移動
部材に対して下降させ、ここで両軸の連結を行う。その
後、昇降部材と各軸とを切離し、移動部材を貫入位置か
ら退避させ、継足した各軸に貫入手段を連結することに
より、この状態から直ちに継足し貫入を開始することが
できる。
Next, all the shafts in the front row are simultaneously held by the elevating members, and the elevating members are lifted with respect to the moving members to suspend the shafts.
In this state, the conveying member is made to travel toward the penetrating means, and each shaft held by the elevating member is supplied to the penetrating position of the penetrating means. Then, at this position, the elevating member is lowered with respect to the moving member until the lower end of the connecting shaft reaches the upper end of the shaft that has already penetrated, and here the two shafts are connected. After that, the lifting member and each shaft are separated from each other, the moving member is retracted from the penetrating position, and the penetrating means is connected to each jointed shaft, so that the jointing can be immediately started from this state.

【0013】さらに、請求項2記載の装置によれば、移
動部材及び昇降部材により継足し用軸を貫入位置に供給
し、これを軸保持手段で保持した後、昇降部材と各軸と
を切り離してそのまま昇降部材及び移動部材を退避させ
ることができ、この間に軸保持部材及びこれに保持され
た軸を下降させて軸の継足し作業を行うことができる。
Further, according to the apparatus of the second aspect, the joining shaft is supplied to the penetrating position by the moving member and the elevating member, and the shaft holding means holds the joint shaft, and then the elevating member and each shaft are separated. As a result, the elevating member and the moving member can be retracted as they are, and the shaft holding member and the shaft held by the shaft holding member can be lowered during this time to perform the work of adding the shaft.

【0014】請求項3記載の装置によれば、次の要領で
軸の継足し貫入を行うことができる。
According to the apparatus of the third aspect, the shaft can be added and penetrated in the following manner.

【0015】まず、軸収納手段の各位置に軸を収納し、
かつ、この軸収納手段を貫入手段の貫入位置から離れた
位置に待機させた状態で、前記装置と同様に貫入手段に
よって複数本の軸を地盤に対して同時に所定の深さまで
貫入する。この貫入深さについては、軸収納手段に収納
されている継足し用軸の下端よりも下方に位置するまで
貫入するようにする。
First, the shaft is stored in each position of the shaft storing means,
Further, in a state in which the shaft accommodating means is made to stand by at a position apart from the penetration position of the penetration means, a plurality of shafts are simultaneously penetrated into the ground to a predetermined depth by the penetration means similarly to the above-mentioned device. With regard to this penetration depth, the penetration is made until it is located below the lower end of the connecting shaft housed in the shaft housing means.

【0016】次に、上記貫入手段と貫入した軸とを切離
し、貫入手段を上限位置まで上昇させた後、軸収納手段
において最前列に貫入並び方向に並べられた軸が貫入位
置に到達するまで基台上で軸収納手段を走行させる。そ
の後、再び貫入手段を下降させて軸収納手段に収納され
ている軸と連結し、再び貫入手段を上昇させて各軸を吊
り上げる。その後、軸収納手段を元の待機位置へ戻し、
貫入手段及びこれに吊られている軸を下降させてこれら
の軸と既貫入の軸とを連結することにより、この状態か
ら直ちに軸の継足し貫入を開始することができる。
Next, after separating the penetrating means from the penetrating shaft and raising the penetrating means to the upper limit position, until the shafts arranged in the penetrating direction in the front row in the shaft accommodating means reach the penetrating position. The shaft storage means is run on the base. Then, the penetrating means is lowered again to connect with the shaft housed in the shaft housing means, and the penetrating means is lifted again to lift each shaft. After that, return the shaft storage means to the original standby position,
By lowering the penetrating means and the shaft hung on the penetrating means and connecting these shafts with the already penetrated shaft, it is possible to immediately start the additional penetration of the shaft from this state.

【0017】[0017]

【実施例】本発明の第1実施例を図1〜10に基づいて
説明する。なお、この実施例では、6本の掘削軸24を
幅方向(本発明における貫入並び方向;図2左右方向)
に並べて同時に地中へ継足し貫入する多軸掘削機につい
て説明するが、本発明において同時貫入する軸は、複数
であればその本数を問わない。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS A first embodiment of the present invention will be described with reference to FIGS. In addition, in this embodiment, the six excavation shafts 24 are arranged in the width direction (the penetrating direction in the present invention; the horizontal direction in FIG. 2).
A multi-axis excavator which is arranged side by side and which simultaneously penetrates into the ground and penetrates will be described. However, in the present invention, the number of simultaneously penetrating shafts does not matter.

【0018】図1及び図2に示す掘削機は、地盤10上
を走行する基台12を備え、この基台12上に、軸収納
装置(軸収納手段)14、取出キャリア16、軸貫入引
抜装置(貫入手段)18、及び軸着脱装置20が設置さ
れている。
The excavator shown in FIGS. 1 and 2 is equipped with a base 12 that runs on the ground 10, and on this base 12, a shaft housing device (shaft housing means) 14, a take-out carrier 16, and a shaft penetrating and extracting. A device (penetration means) 18 and a shaft attaching / detaching device 20 are installed.

【0019】軸収納装置14は、軸収納ラック21を備
えている。この軸収納ラック21は上記基台12上に立
設されており、この軸収納ラック21内における上記基
台12の上面に、軸支持装置22が配置されている。
The shaft storage device 14 is provided with a shaft storage rack 21. The shaft storage rack 21 is erected on the base 12, and a shaft support device 22 is arranged on the upper surface of the base 12 in the shaft storage rack 21.

【0020】この軸支持装置22は、図3に示すような
軸支持筒26を多数個備え、これらの軸支持筒26が上
下を向く状態で軸支持装置22本体の上面に固定されて
いる。各軸支持筒26内には、ラジアル軸受27及びス
ラスト軸受28を介して支持軸30が回転可能に支持さ
れており、この支持軸30は、各掘削軸24下端の連結
部24aに形成された嵌入穴25内に嵌入可能な形状と
されている。この嵌入穴25は、掘削軸24同士を連結
する際に、相手方の掘削軸24の上端部が嵌入される穴
であり、この嵌入穴25が各支持軸30に外篏されるこ
とにより、この支持軸30の本数分だけ掘削軸24が軸
収納ラック21内に支持されている。
The shaft support device 22 is provided with a large number of shaft support cylinders 26 as shown in FIG. 3, and these shaft support cylinders 26 are fixed to the upper surface of the main body of the shaft support device 22 in a state of facing vertically. A support shaft 30 is rotatably supported in each shaft support cylinder 26 via a radial bearing 27 and a thrust bearing 28. The support shaft 30 is formed at a connecting portion 24a at the lower end of each excavation shaft 24. It has a shape that can be fitted into the fitting hole 25. The fitting hole 25 is a hole into which the upper end portion of the other digging shaft 24 is fitted when the digging shafts 24 are connected to each other. The excavation shafts 24 are supported in the shaft storage rack 21 by the number of the support shafts 30.

【0021】ちなみにこの実施例では、図2に示すよう
に装置の幅方向に6本並べられた掘削軸24が、図1に
示すように装置の前後方向に4列にわたって配されてい
る。
By the way, in this embodiment, as shown in FIG. 2, six excavating shafts 24 arranged in the width direction of the machine are arranged in four rows in the longitudinal direction of the machine as shown in FIG.

【0022】上記軸支持筒26の下面には、ボルト3
1,32等で減速機34が固定されており、この減速機
34の出力軸38がキー40を介して相対回転不能に上
記支持軸30に連結される一方、減速機34の入力軸に
回転方向位置決めモータ36の駆動軸が連結されてい
る。従って、この回転方向位置決めモータ36の作動に
より、減速機34を介して支持軸30及び掘削軸24が
一体に自軸回りに回転駆動されるようになっている。
On the lower surface of the shaft support cylinder 26, the bolt 3
The speed reducer 34 is fixed by 1, 32 etc., and the output shaft 38 of the speed reducer 34 is connected to the support shaft 30 via a key 40 so as not to rotate relative to the output shaft 38, while the output shaft 38 rotates about the input shaft of the speed reducer 34. The drive shaft of the directional positioning motor 36 is connected. Therefore, by the operation of the rotation direction positioning motor 36, the support shaft 30 and the excavation shaft 24 are integrally driven to rotate about their own axis via the speed reducer 34.

【0023】各回転方向位置決めモータ36の駆動軸に
はポテンショメータ等からなる収納側回転角センサ42
が接続され、この収納側回転角センサ42によって、回
転方向位置決めモータ36の駆動軸の基準角度からの回
転角、換言すれば、各支持軸30に支持されている掘削
軸24の回転位相が軸ごとに個別に検出されるようにな
っている。
The drive shaft of each rotation direction positioning motor 36 has a storage side rotation angle sensor 42 including a potentiometer or the like.
Is connected to the storage side rotation angle sensor 42, and the rotation angle from the reference angle of the drive shaft of the rotation direction positioning motor 36, in other words, the rotation phase of the excavation shaft 24 supported by each support shaft 30 is the axis. Each is individually detected.

【0024】取出キャリア16は、上記軸収納装置14
に収納された掘削軸24を一列ずつ(すなわち6本ず
つ)取出して軸貫入引抜装置18へ供給するものであ
る。その構造を図4〜図8に示す。
The take-out carrier 16 is the shaft storage device 14 described above.
The excavation shafts 24 stored in the column are taken out row by row (that is, six rows each) and supplied to the shaft penetration and extraction device 18. The structure is shown in FIGS.

【0025】上記軸収納ラック21の上端には前後方向
(図4では左右方向)に左右一対のガイドレール44が
敷設され、これに沿って走行可能に走行機(移動部材)
46が設置されている。この走行機46は、上記ガイド
レール44上を転動する車輪47,48と、車輪48を
歯車49a,49bを介して回転駆動する走行モータ5
0とを備え、この走行機46の前端に昇降機52が設け
られている。
A pair of left and right guide rails 44 is laid in the front-rear direction (left-right direction in FIG. 4) on the upper end of the shaft storage rack 21, and a traveling machine (moving member) can be run along the guide rails 44.
46 is installed. The traveling machine 46 includes wheels 47 and 48 rolling on the guide rail 44, and a traveling motor 5 that rotationally drives the wheels 48 via gears 49a and 49b.
0, and an elevator 52 is provided at the front end of the traveling machine 46.

【0026】この昇降機52は、上記走行機46に固定
されたフレーム54を備え、このフレーム54には複数
の上下シリンダ56が下向きに固定されている。各上下
シリンダ56のロッド56aの先端(すなわち下端)に
はブラケット58が固定され、このブラケット58に把
持フレーム(昇降部材)60が水平状態で連結されてい
る。また、図4,6に示すように、把持フレーム60に
は上方に延びる案内ロッド62が固定されるとともに、
フレーム54側に各案内ロッド62が挿通される案内筒
64が固定されており、上記上下シリンダ56の伸縮に
より、案内筒64と案内ロッド62とが摺動するように
しながら把持フレーム60がフレーム54に対して昇降
するようになっている。
The elevator 52 includes a frame 54 fixed to the traveling machine 46, and a plurality of upper and lower cylinders 56 are fixed to the frame 54 downward. A bracket 58 is fixed to the tip (i.e., lower end) of the rod 56a of each of the upper and lower cylinders 56, and a holding frame (elevating member) 60 is connected to the bracket 58 in a horizontal state. Further, as shown in FIGS. 4 and 6, a guide rod 62 extending upward is fixed to the grip frame 60, and
A guide cylinder 64, through which each guide rod 62 is inserted, is fixed to the frame 54 side, and the grip frame 60 holds the frame 54 while the guide cylinder 64 and the guide rod 62 slide as the upper and lower cylinders 56 expand and contract. It is designed to move up and down.

【0027】なお、図5,7では便宜上、上記案内ロッ
ド62及び案内筒64の図示を省略している。
5 and 7, the guide rod 62 and the guide cylinder 64 are not shown for the sake of convenience.

【0028】図7,8に示すように、上記把持フレーム
60は、水平方向に延びる前後一対(図7では上下一
対)の骨材60cを備えている。両骨材60cは、複数
の横骨60aによって間欠的に連結され、適当な横骨6
0aに上記上下シリンダ56のロッド56aの下端が連
結されており、各横骨60aの間に、各掘削軸24の上
端部が貫通する穴60bが形成されている。
As shown in FIGS. 7 and 8, the grip frame 60 is provided with a pair of front and rear aggregates (a pair of upper and lower in FIG. 7) extending horizontally. Both aggregates 60c are intermittently connected by a plurality of transverse bones 60a, and the appropriate transverse bones 6
0a is connected to the lower ends of the rods 56a of the upper and lower cylinders 56, and holes 60b through which the upper ends of the respective excavation shafts 24 pass are formed between the horizontal frames 60a.

【0029】両骨材60aの適所には、これを貫通する
ようにして複数対の把持シリンダ66が内側向きに固定
されており、各把持シリンダ66のロッド66aの先端
にはブラケット68を介して前後一対の軸把持板70が
固定されている。両軸把持板70は、骨材60aと略同
等の領域にわたって水平方向に延び、その適所には、図
8に示すように各掘削軸24の上端部を前後から把持す
るための把持部が形成されている。
A plurality of pairs of gripping cylinders 66 are fixed inward at appropriate positions of both aggregates 60a, and a bracket 68 is provided at the tip of rod 66a of each gripping cylinder 66 via a bracket 68. A pair of front and rear shaft grip plates 70 are fixed. Both shaft grip plates 70 extend in the horizontal direction over a region substantially equivalent to the aggregate 60a, and grip parts for gripping the upper end of each excavation shaft 24 from the front and the back are formed at appropriate positions as shown in FIG. Has been done.

【0030】また、上記ガイドレール44の近傍には、
リミットスイッチ等からなる位置決め手段が配設され、
上記把持フレーム60が軸保持ラック21内の掘削軸2
4の真上の位置、あるいは後述の軸貫入引抜装置18に
よる軸貫入位置に到達した時点で停止するように、走行
機44の走行制御動作、すなわち位置決め動作が行われ
るようになっている。
In the vicinity of the guide rail 44,
Positioning means consisting of limit switches etc. is provided,
The gripping frame 60 is used for the excavation shaft 2 in the shaft holding rack 21.
4, a traveling control operation, that is, a positioning operation of the traveling machine 44 is performed so that the traveling machine 44 is stopped at a position immediately above 4 or a shaft penetration position by the shaft penetration extraction device 18 described later.

【0031】軸貫入引抜装置18は、図1,2に示すよ
うに基台12上に立設された門型フレーム71を備えて
いる。この門型フレーム71には、昇降ハウジング88
が昇降可能に支持されており、この昇降ハウジング88
が、図外の引抜ウインチの巻上げにより引き上げられ、
逆に図外の貫入ウインチの巻上げにより積極的に引き下
げられるようになっている。
As shown in FIGS. 1 and 2, the shaft penetrating / pulling-out device 18 is provided with a gate-shaped frame 71 erected on the base 12. The portal frame 71 includes a lifting housing 88.
Is supported so that it can be moved up and down.
Is pulled up by winding a pull-out winch (not shown),
On the contrary, it is designed to be pulled down positively by hoisting a penetrating winch (not shown).

【0032】この昇降ハウジング88内には、図9に示
すような上下方向に延びる駆動軸72が回転可能に設け
られている。この駆動軸72の上端は、スイベルジョイ
ント74及び改良剤供給ポート76を介して改良剤タン
ク(図示せず)に接続されている。駆動軸72の中間部
位には筒部材78が固定され、この筒部材78が、上記
昇降ハウジング88に固定された減速機80のハウジン
グに軸受79を介して回転可能に支持されている。上記
筒部材78の外周面にはギア82が固定されており、こ
のギア82が減速機80のギア84に噛合されている。
この減速機80の入力軸は、図1に示す掘削モータ85
に連結されている。
A drive shaft 72 extending in the vertical direction as shown in FIG. 9 is rotatably provided in the lift housing 88. The upper end of the drive shaft 72 is connected to a modifier tank (not shown) via a swivel joint 74 and a modifier supply port 76. A tubular member 78 is fixed to an intermediate portion of the drive shaft 72, and the tubular member 78 is rotatably supported by a housing of a speed reducer 80 fixed to the elevating housing 88 via a bearing 79. A gear 82 is fixed to the outer peripheral surface of the cylindrical member 78, and the gear 82 is meshed with a gear 84 of the speed reducer 80.
The input shaft of the speed reducer 80 is the excavation motor 85 shown in FIG.
Is linked to.

【0033】この駆動軸72の下部は、スラスト軸受8
6を介して上記昇降ハウジング88の内板88aにスラ
スト支持されており、この駆動軸72の下端部にフラン
ジ89を介してチャック90が連結されている。このチ
ャック90は、上記掘削軸24の上端を把持する状態と
開放する状態とに切換可能に構成されている。従って、
このチャック90により上記掘削軸24を把持した状態
で上記軸回転駆動モータ85を回転駆動することによ
り、減速機80を介して駆動軸72、フランジ89、チ
ャック90、及び掘削軸24を一体に回転駆動できるよ
うになっている。
The lower part of the drive shaft 72 is the thrust bearing 8
It is thrust-supported to the inner plate 88a of the elevating housing 88 via 6, and a chuck 90 is connected to the lower end of the drive shaft 72 via a flange 89. The chuck 90 is configured to be switchable between a state in which the upper end of the excavation shaft 24 is held and a state in which the upper end is opened. Therefore,
By rotating the shaft rotation drive motor 85 while holding the excavation shaft 24 by the chuck 90, the drive shaft 72, the flange 89, the chuck 90, and the excavation shaft 24 are integrally rotated via the speed reducer 80. It can be driven.

【0034】また、上記チャック90及び各掘削軸24
も中央に貫通穴をもつ筒状とされており、図外の改良剤
タンク内の地盤改良剤が上記改良剤供給ポート76、ス
イベルジョイント74、駆動軸72、チャック90、及
び掘削軸24内を通って地盤10内に供給されるように
なっている。
Further, the chuck 90 and each excavation shaft 24
Also has a cylindrical shape with a through hole in the center, and the ground improvement agent in the improvement agent tank (not shown) flows through the inside of the improvement agent supply port 76, the swivel joint 74, the drive shaft 72, the chuck 90, and the excavation shaft 24. It is adapted to be supplied to the ground 10 through the ground.

【0035】上記駆動軸72の適所にはギア92が固定
され、このギア92に噛合されるギア94が昇降ハウジ
ング88に回転可能に支持されており、このギア94の
回転軸96に駆動側回転角センサ98が連結されてい
る。この駆動側回転角センサ98はポテンショメータ等
からなり、上記回転軸96の回転角、換言すれば、上記
駆動軸72に連結された掘削軸24の回転位相を検出す
るように構成されている。
A gear 92 is fixed at an appropriate position on the drive shaft 72, and a gear 94 meshed with the gear 92 is rotatably supported by the elevating housing 88. A rotation shaft 96 of the gear 94 rotates on the drive side. The corner sensor 98 is connected. The drive-side rotation angle sensor 98 is composed of a potentiometer or the like, and is configured to detect the rotation angle of the rotation shaft 96, in other words, the rotation phase of the excavation shaft 24 connected to the drive shaft 72.

【0036】なお、本発明において軸同士の具体的な連
結構造は問わず、従って、上記嵌入穴25の形状も種々
考えられるが、この形状に合わせて支持軸30の上端部
の形状を設定すれば、この支持軸30で掘削軸24を支
持することが可能である。例えば、上記支持軸30及び
嵌入穴25の断面形状が異形でなく完全な円形であって
も、掘削軸24の自重に起因する摩擦力で掘削軸24と
支持軸30とを一体に回転させることが可能である。ま
た、このような支持軸30の嵌入によらず、掘削軸24
の上端部や下端部等を外側から保持することによって
も、掘削軸24の支持が可能である。
In the present invention, the specific connecting structure of the shafts does not matter, and therefore, the shape of the fitting hole 25 may be various, but the shape of the upper end portion of the support shaft 30 may be set according to this shape. For example, the excavation shaft 24 can be supported by the support shaft 30. For example, even if the cross-sectional shapes of the support shaft 30 and the fitting hole 25 are not irregular but completely circular, the excavation shaft 24 and the support shaft 30 are integrally rotated by the frictional force caused by the weight of the excavation shaft 24. Is possible. In addition, regardless of the insertion of the support shaft 30 as described above, the excavation shaft 24
The excavation shaft 24 can also be supported by holding the upper end portion, the lower end portion, and the like from the outside.

【0037】上記門型フレーム71の中腹部には、図
1,2に示すような軸案内装置100が設けられてい
る。この軸案内装置100は、門型フレーム71の幅方
向(図2では左右方向)全域に延びる基台102を備
え、この基台102の両端が門型フレーム71の両支柱
に固定されている。基台102の左右両翼にはブラケッ
ト104が立設され、このブラケット104に水平軸回
りに回動可能にアーム部材105が取付けられている。
An axial guide device 100 as shown in FIGS. 1 and 2 is provided in the middle abdomen of the portal frame 71. The shaft guide device 100 includes a base 102 extending in the entire width direction (the left-right direction in FIG. 2) of the gate frame 71, and both ends of the base 102 are fixed to both columns of the gate frame 71. A bracket 104 is erected on both left and right wings of the base 102, and an arm member 105 is attached to the bracket 104 so as to be rotatable around a horizontal axis.

【0038】このアーム部材105は、起伏シリンダ1
10の伸縮により回動駆動されるように構成されるとと
もに、その回動径方向に延びる複数本のアーム106を
有し、各アーム106の間に案内爪108が設けられて
いる。各案内爪108は、上記アーム部材105が図1
二点鎖線に示すように倒伏している状態で、各チャック
90に把持された掘削軸24に対応する位置に設けられ
ており、この掘削軸24が後方(図1の左方)から挿入
可能な状態(開状態)と、掘削軸24の水平方向の動き
を規制して上下方向の動きのみを許容する軸案内状態
(閉状態)とに切換可能に構成されている。
This arm member 105 is used for the undulating cylinder 1.
The arm 10 is configured to be rotationally driven by expansion and contraction of 10, and has a plurality of arms 106 extending in the rotational radial direction, and a guide claw 108 is provided between each arm 106. Each of the guide claws 108 has the arm member 105 shown in FIG.
It is provided at a position corresponding to the excavation shaft 24 held by each chuck 90 in a state of lying down as shown by the chain double-dashed line, and this excavation shaft 24 can be inserted from the rear (left side in FIG. 1). It is configured to be switchable between a normal state (open state) and a shaft guide state (closed state) that restricts the horizontal movement of the excavation shaft 24 and allows only the vertical movement.

【0039】軸着脱装置20は、既に地盤10に貫入さ
れた状態にある第1の掘削軸24の上端部と、次に貫入
すべき第2の掘削軸24の下端部とを自動的に連結し、
あるいは切り離すものであり、従来公知のもの等が適用
可能である。ただし、本発明ではこの軸着脱装置20を
必ずしも要せず、軸継手構造によっては手動で軸連結及
び切離しを行うようにしてもよい。
The shaft attaching / detaching device 20 automatically connects the upper end of the first excavating shaft 24 which has already been penetrated into the ground 10 and the lower end of the second excavating shaft 24 to be penetrated next. Then
Alternatively, it is separated, and a conventionally known one or the like can be applied. However, in the present invention, the shaft attaching / detaching device 20 is not necessarily required, and the shaft connection and disconnection may be performed manually depending on the shaft joint structure.

【0040】この掘削機は、図略のコントローラを備
え、このコントローラにより、軸収納装置14に収納さ
れている掘削軸24の回転方向の位置決め(すなわち回
転位相の調整)が行われるようになっている。
This excavator is provided with a controller (not shown), which is used to position the excavation shaft 24 housed in the shaft housing device 14 in the rotational direction (that is, to adjust the rotational phase). There is.

【0041】次に、この掘削機が軸貫入時に行う動作を
図10のタイムチャートを参照しながら説明する。
Next, the operation of the excavator when the shaft penetrates will be described with reference to the time chart of FIG.

【0042】(a) チャック90により第1列目における
計6本の掘削軸24をそれぞれ把持し、かつ、掘削モー
タ85の正回転動作、引抜ウインチの巻下げ動作、及び
貫入ウインチの巻上げ動作により、上記各掘削軸24を
個別に回転駆動しながら、地中へ貫入する。詳しくは、
各掘削モータ85の作動により、チャック90及びこれ
に連結された各掘削軸24を自軸回りに回転駆動すると
ともに、上記両ウインチの作動で昇降ハウジング88全
体を強制的に引き下げ、第1列目の全掘削軸24を同時
に地盤10内へ貫入する。そして、これらの掘削軸24
の大部分が地盤10内に入った状態、すなわち、各掘削
軸24の上端が、軸収納装置14に収納されている継足
し用軸24の下端よりも下がった状態で、上記掘削モー
タ85、引抜機・貫入ウインチの動作を止め、第1列目
の掘削軸24の貫入動作を終了する。
(A) The chuck 90 grips each of the six excavation shafts 24 in the first row, and the excavation motor 85 rotates forward, the pulling winch lowers, and the penetration winch winds. The individual digging shafts 24 are individually driven to rotate and penetrate into the ground. For more information,
By operating each excavating motor 85, the chuck 90 and each excavating shaft 24 connected thereto are rotationally driven about its own axis, and the entire lifting housing 88 is forcibly pulled down by the operation of both winches, so that the first row All the excavation shafts 24 of the above are simultaneously penetrated into the ground 10. And these excavation axes 24
Of the excavating motor 85, the upper end of each excavating shaft 24 is lower than the lower end of the supplementary shaft 24 accommodated in the shaft accommodating device 14, The operation of the extractor / penetration winch is stopped, and the penetration operation of the first row excavation shaft 24 is completed.

【0043】(b) 貫入終了時点で検出された各掘削軸2
4の回転位相を駆動側回転角センサ98で検出し、この
位相と、軸収納装置14に収納されている第2列目の掘
削軸24の回転位相とを個別に比較し、両回転位相が合
致するように各回転位置決めモータ36に個別にコント
ローラから制御信号を出力して第2列目の支持軸30及
びこれに支持される各掘削軸24をそれぞれ適当な角度
まで回転させる。この位相調節により、既貫入の第1列
目の各掘削軸24と次の第2列目の各掘削軸24とが直
ちに連結可能な状態となる。
(B) Each excavation shaft 2 detected at the end of penetration
The rotation phase of No. 4 is detected by the drive side rotation angle sensor 98, and this phase and the rotation phase of the second row excavating shaft 24 stored in the shaft storage device 14 are individually compared, and both rotation phases are determined. A control signal is individually output from the controller to each rotary positioning motor 36 so as to match, and the second-row support shaft 30 and each excavation shaft 24 supported thereby are rotated to appropriate angles. By this phase adjustment, the already excavated first excavation shafts 24 in the first row and the next excavated excavation shafts 24 in the second row are ready to be connected.

【0044】なお、上記貫入動作を開始する前の段階で
は、駆動軸72及びチャック90を適当に回してその回
転角を所定の基準角度にリセットしておくようにする。
At the stage before the penetration operation is started, the drive shaft 72 and the chuck 90 are appropriately rotated to reset the rotation angle thereof to a predetermined reference angle.

【0045】(c) 上記調整動作中、第1列目の各掘削軸
24を把持している各チャック90を開状態に切換え、
これらのチャック90から各掘削軸24を解放する。
(C) During the adjusting operation, the chucks 90 holding the excavating shafts 24 in the first row are switched to the open state,
Each excavation shaft 24 is released from these chucks 90.

【0046】(d) 引抜ウインチを巻上げ方向に作動させ
ることにより、昇降ハウジング88を下限位置(図1に
下側の二点鎖線で示す位置)から上限位置(図1に上側
の二点鎖線で示す位置)まで引上げる。
(D) By operating the pull-out winch in the winding direction, the elevating housing 88 is moved from the lower limit position (the position shown by the lower double-dashed line in FIG. 1) to the upper limit position (the upper double-dashed line in FIG. 1). (Position shown).

【0047】(e) この昇降ハウジング88の引上げ動作
中、軸収納装置14側において、取出キャリア16によ
る第2列目の掘削軸24の取出動作を行う。まず、走行
機46を適当な距離だけ走らせて、昇降機52を第2列
目の掘削軸24の上方の位置に位置決めする。次に、昇
降機52の上下シリンダ56を伸ばして把持フレーム6
0を下降させ、この把持フレーム60の把持シリンダ6
6の伸長により両軸把持板70を相互接近する方向(す
なわち内側方向)に移動させて両軸把持板70により第
2列目の掘削軸24を全て同時に把持する。(図7,8
の状態)。この状態で上記上下シリンダ56を収縮させ
ることにより、第2列目の掘削軸24を支持軸30から
一度に引き上げる。
(E) During the raising operation of the elevating housing 88, the take-out carrier 16 takes out the second row of the excavating shafts 24 on the side of the shaft storage device 14. First, the traveling machine 46 is run for an appropriate distance to position the elevator 52 at a position above the second row excavating shaft 24. Next, the upper and lower cylinders 56 of the elevator 52 are extended to hold the gripping frame 6
0 is lowered and the gripping cylinder 6 of this gripping frame 60 is
By the extension of 6, both shaft gripping plates 70 are moved in a direction in which they approach each other (that is, inward direction), and the excavating shafts 24 in the second row are gripped by the both shaft gripping plates 70 at the same time. (Figs. 7, 8
Condition). In this state, the upper and lower cylinders 56 are contracted to pull up the second row excavation shaft 24 from the support shaft 30 at once.

【0048】(f) 上記引抜ウインチの巻上げ動作完了時
点、すなわち昇降シリンダ88が最上の位置に到達した
時点で、上記掘削軸24を吊り上げたまま走行機46を
軸貫入引抜装置18に向けて前進させる。このとき、軸
案内装置100の起伏シリンダ110を収縮させて案内
爪108を開いた状態でアーム部材105全体を倒伏さ
せておき、各案内爪108に、上記取出キャリア16で
搬送される掘削軸24の中間部を挿入し、この位置で走
行機46の走行を停止させる。これにより、第2列目の
掘削軸24は各昇降ハウジング88による貫入位置、す
なわち第1列目の掘削軸24の真上の位置にそれぞれ位
置決めされたことになる。
(F) When the hoisting operation of the pull-out winch is completed, that is, when the elevating cylinder 88 reaches the uppermost position, the traveling machine 46 is advanced toward the shaft penetrating and extracting device 18 while the excavating shaft 24 is being lifted. Let At this time, the entire arm member 105 is laid down in a state in which the hoisting cylinder 110 of the shaft guide device 100 is contracted to open the guide claws 108, and the excavation shaft 24 conveyed by the unloading carrier 16 to each guide claw 108. Then, the traveling of the traveling machine 46 is stopped at this position. As a result, the excavation shafts 24 in the second row are positioned at the penetration positions of the elevating housings 88, that is, the positions directly above the excavation shafts 24 in the first row.

【0049】(g) 各案内爪108を閉状態に切換えて各
掘削軸24の水平方向の移動を規制し、この状態で上下
シリンダ56を再び伸長させることにより、各掘削軸2
4を、その下端の連結部24aが既に貫入されている第
1列目の掘削軸24の上端と嵌合する位置まで下降し、
軸着脱装置20の作動により、第1列目の掘削軸24の
上端と第2列目の掘削軸24の連結部24aとを連結す
る。
(G) The guide claws 108 are switched to the closed state to regulate the horizontal movement of the excavation shafts 24, and the upper and lower cylinders 56 are extended again in this state, whereby the respective excavation shafts 2 are moved.
4 down to the position where the lower end of the connecting portion 24a is fitted with the upper end of the first row excavating shaft 24 that has already penetrated,
The operation of the shaft attaching / detaching device 20 connects the upper end of the excavating shaft 24 in the first row and the connecting portion 24a of the excavating shaft 24 in the second row.

【0050】(h) 取出キャリア16の把持シリンダ66
を収縮させることにより、両軸把持板70を離間させ、
これら軸把持板70から各掘削軸24を解放する。
(H) Grasping cylinder 66 of take-out carrier 16
By contracting the two shaft grip plates 70,
Each excavation shaft 24 is released from these shaft grip plates 70.

【0051】(i) 上下シリンダ56の収縮により把持フ
レーム60を上昇させ、かつ走行機46の作動で取出キ
ャリア16全体の後退を開始した後、所定のタイミング
で引抜ウインチの巻下げ動作を開始し、昇降ハウジング
88をその自重で下降させる。そして、この昇降ハウジ
ング88の各チャック90が各掘削軸24の上端部に到
達した時点で、昇降ハウジング88の下降動作を停止
し、各チャック90を閉状態に切換えて第2列目の各掘
削軸24を把持する。
(I) After the upper and lower cylinders 56 are contracted to raise the gripping frame 60, and the traveling machine 46 is actuated to start the retreat of the entire unloading carrier 16, the withdrawal winch lowering operation is started at a predetermined timing. , The elevating housing 88 is lowered by its own weight. Then, when each chuck 90 of the elevating housing 88 reaches the upper end portion of each excavation shaft 24, the descending operation of the elevating housing 88 is stopped, each chuck 90 is switched to the closed state, and each excavation in the second row. Hold the shaft 24.

【0052】(j) 各案内爪108を開き、かつ起伏シリ
ンダ110を伸ばしてアーム部材105全体を図3,4
に示す起立位置まで退避させ、この状態で、前記と同様
に掘削モータ85の正回転方向の作動、引抜ウインチの
巻下げ作動、及び貫入ウインチの巻上げ動作により、チ
ャック90に把持した第2列目の掘削軸24と、この第
2列目の掘削軸24に連結された第1列目の掘削軸24
とを一体に回転駆動し、地中へ貫入する。以下、このよ
うな動作を繰り返すことにより、複数本の掘削軸24を
順次継ぎ足しながら、地中深くへ貫入していくことがで
きる。
(J) Open the guide claws 108 and extend the undulating cylinder 110 so that the arm member 105 as a whole is shown in FIGS.
The evacuation position shown in FIG. 2 is retracted, and in this state, in the same manner as described above, the second row gripped by the chuck 90 is operated by the operation of the excavating motor 85 in the forward rotation direction, the lowering operation of the pull-out winch, and the hoisting operation of the penetrating winch. Excavating shaft 24 of the first row, and the excavating shaft 24 of the first row connected to the excavating shaft 24 of the second row
Drive and rotate together and penetrate into the ground. Hereinafter, by repeating such an operation, it is possible to penetrate deep into the ground while successively adding a plurality of excavation shafts 24.

【0053】なお、貫入後、各掘削軸24の引抜を行う
場合には、上記と逆の動作を行うようにすればよい。す
なわち、掘削モータ85を逆回転方向に作動させながら
掘削軸24を地盤10から引上げ、軸着脱装置20で掘
削軸24同士の連結を切り離した後、取出キャリア16
を用いて各掘削軸24を支持軸30上へ格納するように
すればよい。
When the excavation shafts 24 are to be pulled out after the penetration, the reverse operation to the above may be performed. That is, the excavation shaft 24 is pulled up from the ground 10 while operating the excavation motor 85 in the reverse rotation direction, the excavation shaft 24 is disconnected from the excavation shaft 24 by the shaft attaching / detaching device 20, and then the extraction carrier 16 is removed.
Each excavation shaft 24 may be stored on the support shaft 30 by using.

【0054】以上のように、この装置では、次のような
効果を得ることができる。
As described above, with this device, the following effects can be obtained.

【0055】 軸収納装置14内に継足し用掘削軸2
4を縦横に並べて収納し、その上方で取出キャリア16
を走らせることにより、上記軸収納装置14内の掘削軸
24を列単位でピックアップし、貫入位置へ同時に搬送
するようにしているので、従来装置のようにアーム旋回
で軸を搬送するものに比べ、掘削軸24を安定して貫入
位置へ送り出すことができる。また、6本同時の供給を
行っても、各部材の強度的負担が少なく、よって補強に
よる重量増大を抑えることができる。さらに、掘削軸2
4の移送に要するスペースも僅かで、装置全体の大型化
を招かない。
The excavation shaft 2 for extension in the shaft storage device 14
4 are arranged side by side vertically and stored, and the take-out carrier 16
By excavating, the excavation shafts 24 in the shaft storage device 14 are picked up in a row unit and are simultaneously conveyed to the penetration position. Therefore, compared with a conventional device that conveys the shafts by arm rotation. The excavation shaft 24 can be stably sent to the penetration position. Further, even if six pieces are supplied at the same time, the load on the strength of each member is small, and therefore the weight increase due to the reinforcement can be suppressed. Furthermore, the excavation axis 2
The space required for the transfer of No. 4 is also small, and the entire apparatus is not enlarged.

【0056】 軸貫入引抜装置18に軸案内装置10
0を設けているので、既貫入の掘削軸24に継足された
掘削軸24を軸案内装置100で安定した状態に保持す
ることができる。
The shaft guide device 10 is attached to the shaft penetrating and extracting device 18.
Since 0 is provided, the excavation shaft 24 joined to the already penetrated excavation shaft 24 can be held in a stable state by the shaft guide device 100.

【0057】 全掘削軸24を立直状態で収納してい
るので、その保管スペースが小さくて済み、また、軸継
足し回数を減らすために掘削軸24の軸長を大きくして
も、上記保管スペースの増大は招かない。
Since all the excavation shafts 24 are stored in an upright state, their storage space is small, and even if the shaft length of the excavation shafts 24 is increased to reduce the number of shaft additions, the above storage space is kept. Does not increase.

【0058】次に、第2実施例を図11に基づいて説明
する。この実施例では、軸貫入引抜装置18の門型フレ
ーム71に、軸保持部材130が昇降可能に設置されて
いる。この軸保持部材130は、貫入位置に供給された
6本の軸を全て同時に上下2個所で把持するように構成
されている。
Next, a second embodiment will be described with reference to FIG. In this embodiment, the shaft holding member 130 is installed on the portal frame 71 of the shaft penetrating / pulling device 18 so as to be movable up and down. The shaft holding member 130 is configured to simultaneously grip all six shafts supplied to the penetration position at two upper and lower positions.

【0059】このような装置によれば、前記実施例と同
様に取出キャリア16で一列の掘削軸24を貫入位置へ
供給した後、これらの掘削軸24を軸保持部材130で
保持することにより、この時点からすぐに取出キャリア
16を退避させることができる。取出キャリア16退避
後は、上記軸保持部材130を下降させて各掘削軸24
を既貫入の掘削軸24に連結し、かつ、継足した掘削軸
24の両端をチャック90に連結してから軸保持部材1
30と各掘削軸24とを切り離すことにより、この状態
から直ちに継足し貫入を開始することができる。
According to such an apparatus, as in the case of the above-described embodiment, after the row of excavating shafts 24 is supplied to the penetration position by the take-out carrier 16, the excavating shafts 24 are held by the shaft holding member 130, The take-out carrier 16 can be immediately retracted from this point. After retracting the unloading carrier 16, the shaft holding member 130 is lowered to move each of the excavating shafts 24.
Is connected to the already excavated excavating shaft 24, and both ends of the excavated excavating shaft 24 connected to the chuck 90 are connected to the shaft holding member 1
By separating 30 and each excavation shaft 24, it is possible to immediately replenish and start penetration from this state.

【0060】すなわち、この装置では、既貫入の掘削軸
24と継足し掘削軸24とを連結する前に取出キャリア
16を退避させることができるので、前記実施例装置の
ように、上記掘削軸24同士の連結後に取出キャリア1
6を退避させる装置に比べ、軸同士を連結してから継足
し掘削軸24と軸貫入引抜装置18のチャック90とを
連結するまでに要する時間をさらに短縮することがで
き、これにより、継足し作業能率をより向上させること
ができる。
That is, in this device, since the take-out carrier 16 can be retracted before the excavation shaft 24 that has already penetrated is connected to the excavation shaft 24 by connecting the excavation shaft 24 and the excavation shaft 24, the above-mentioned excavation shaft 24 can be retracted. Take-out carrier 1 after connecting each other
As compared with a device for retracting 6, the time required for connecting the shafts to each other and connecting the excavation shaft 24 and the chuck 90 of the shaft penetrating and extracting device 18 can be further shortened. The work efficiency can be further improved.

【0061】次に、第3実施例を図12,13に基づい
て説明する。この実施例では、前記実施例における取出
キャリア16が省略され、その代わりに、軸収納装置1
4全体が基台12上に収納並び方向(図12,13左右
方向)に走行可能に設置されている。
Next, a third embodiment will be described with reference to FIGS. In this embodiment, the take-out carrier 16 in the previous embodiment is omitted, and instead, the shaft storage device 1 is used.
The whole 4 is installed on the base 12 so that it can travel in the storage arrangement direction (left and right direction in FIGS. 12 and 13).

【0062】具体的に、上記基台12上には、上記収納
並び方向に延びる一対のガイドレール140が敷かれて
いる。一方、軸収納装置14は、各掘削軸24を支持す
る底壁142と、図13に示すような一対の側壁146
と、軸貫入引抜装置18から離れた側に設けられた背壁
144とを備え、前方(図13右方)にのみ開口した状
態となっている。そして、上記底壁142の下面に、上
記ガイドレール140上を転動するローラ148が取付
けられており、このローラ148が図略のモータで回転
駆動されることにより、軸収納装置14全体がガイドレ
ール140上を走行するようになっている。
Specifically, on the base 12, a pair of guide rails 140 extending in the storage arrangement direction is laid. On the other hand, the shaft storage device 14 includes a bottom wall 142 that supports each of the excavation shafts 24 and a pair of side walls 146 as shown in FIG.
And a back wall 144 provided on the side away from the shaft penetration / extraction device 18, and is in a state of being opened only at the front (right side in FIG. 13). A roller 148 rolling on the guide rail 140 is attached to the lower surface of the bottom wall 142, and the roller 148 is driven to rotate by a motor (not shown) to guide the entire shaft storage device 14. It is designed to run on the rail 140.

【0063】このような装置によれば、前記実施例の
(a)〜(d)の動作を行った後、次の要領で継足し貫入を行
うことができる。
According to such an apparatus, the device of the above embodiment is
After performing the operations of (a) to (d), it is possible to add and penetrate by the following procedure.

【0064】(A) 軸収納装置14を、図12,13実線
に示す待機位置から前方(同図右方)へ走らせ、その最
前列に収納された各掘削軸24が貫入位置に到達した時
点で走行を停止する。
(A) When the shaft accommodating device 14 is moved forward from the standby position shown in solid lines in FIGS. 12 and 13 (to the right in the drawing), and each of the excavating shafts 24 stored in the front row reaches the penetration position. To stop running.

【0065】(B) 昇降ハウジング88を下降させて各チ
ャック90と掘削軸24の上端部とを連結する。
(B) The elevating housing 88 is lowered to connect the chucks 90 to the upper end of the excavation shaft 24.

【0066】(C) 昇降ハウジング88を引き上げて各掘
削軸24を吊り上げ、軸収納装置14全体を後退させて
元の待機位置へ戻す。
(C) The elevating housing 88 is pulled up to hoist each excavation shaft 24, and the entire shaft storage device 14 is retracted to return to the original standby position.

【0067】(D) 昇降ハウジング88を下降させ、吊り
下げている掘削軸24の下端を既貫入の掘削軸24の上
端に連結する。次いで、各掘削モータ85を作動させな
がら昇降ハウジング88を下降させることにより、継足
し貫入を行うことができる。
(D) The elevating housing 88 is lowered to connect the lower end of the suspended excavation shaft 24 to the upper end of the already penetrated excavation shaft 24. Then, the elevating housing 88 is lowered while operating the respective excavating motors 85, whereby additional penetration can be performed.

【0068】その後、さらに2回目、3回目の継足し貫
入を行う場合には、軸収納装置14の第2列目、第3列
目、…に収納された掘削軸24がそれぞれ貫入位置に到
達するまで軸収納装置14全体を走行させることによ
り、全ての掘削軸24を貫入位置へ供給することができ
る。
Thereafter, when the second and third additional penetrations are performed, the excavation shafts 24 stored in the second row, the third row, ... Of the shaft storage device 14 reach the respective penetration positions. By moving the entire shaft storage device 14 until that time, all the excavation shafts 24 can be supplied to the penetration position.

【0069】以上のように、この装置では、軸収納装置
14自体を走行させることにより、継足し掘削軸24を
収納状態のままで貫入位置まで供給するようにしている
ので、掘削軸24の搬送をより安定した状態で行うこと
ができる。また、掘削軸24を搬送するために特別な部
材を設ける必要がなくなり、構造がより簡略化される。
As described above, in this device, the shaft storage device 14 itself is made to travel to supply the excavation shaft 24 to the penetration position in the stored state, so that the excavation shaft 24 is transported. Can be performed in a more stable state. Further, it is not necessary to provide a special member to convey the excavation shaft 24, and the structure is further simplified.

【0070】なお、本発明は上記各実施例に限定される
ものでなく、例として次のような態様をとることも可能
である。
The present invention is not limited to the above embodiments, and the following modes can be adopted as examples.

【0071】(1) 本発明では、収納並び方向の掘削軸の
収納列数を問わず、装置の規模に応じて適宜設定すれば
よい。
(1) In the present invention, regardless of the number of storage rows of the excavating shafts in the storage arrangement direction, it may be appropriately set according to the scale of the device.

【0072】(2) 上記実施例では、同時に貫入される掘
削軸24を完全な一直線上に並べたものを示したが、本
発明では、各掘削軸が必ず一直線上に並んでいなくても
よく、例えば収納並び方向に僅かずつ位置をずらして同
時貫入するようにしてもよい。また、複数の掘削軸24
を曲率半径の大きな円弧状に並べて同時貫入するように
してもよい。この場合には、軸収納手段14の各列にお
いて上記掘削軸24を円弧状に並べるようにすればよ
い。また本発明では、貫入並び方向と収納並び方向とが
完全に直交していなくてもよく、両者が僅かに傾斜して
いてもよい。
(2) In the above embodiment, the excavating shafts 24 which are simultaneously penetrated are arranged in a complete straight line. However, in the present invention, the excavating shafts 24 are not necessarily in a straight line. Of course, for example, the positions may be slightly shifted in the storage arrangement direction so that they simultaneously penetrate. In addition, a plurality of excavation axes 24
May be arranged in an arc shape having a large radius of curvature so as to penetrate simultaneously. In this case, the excavation shafts 24 may be arranged in an arc shape in each row of the shaft storage means 14. Further, in the present invention, the penetrating and arranging directions may not be completely orthogonal to each other, and both may be slightly inclined.

【0073】(3) 前記第1実施例及び第2実施例におい
て、取出キャリア16の把持部は必ずしも掘削軸24の
上端をつかむものでなくてもよく、その中間部を貫入並
び方向の両側から挾むような構造のものでも、上記と同
様の効果を得ることが可能である。
(3) In the first and second embodiments described above, the gripping portion of the take-out carrier 16 does not necessarily have to grasp the upper end of the excavation shaft 24, but the middle portion of the gripping portion from both sides in the direction of penetration. Even with a sandwiched structure, the same effect as described above can be obtained.

【0074】(4) 本発明は、軸を互いに連結させながら
貫入するための装置に広く適用できるものであり、地盤
改良装置、ボーリング装置等、種々の貫入装置に広く適
用可能である。
(4) The present invention can be widely applied to a device for penetrating while connecting shafts to each other, and can be widely applied to various penetrating devices such as a ground improvement device and a boring device.

【0075】[0075]

【発明の効果】以上のように、本発明によれば、次のよ
うな効果を得ることができる。
As described above, according to the present invention, the following effects can be obtained.

【0076】請求項1記載の装置は、軸収納手段におい
て搬送部材及び昇降部材を走行させることにより、軸収
納手段において貫入並び方向に並べられている軸を列単
位で同時に貫入位置へ供給するようにしたものであるの
で、貫入並び方向の軸の並び本数が多い場合にも安定し
た状態で各軸を同時に貫入位置まで搬送することができ
る効果がある。また、従来に比べて搬送部材の強度的負
担が小さく、搬送に要するスペースも小さいので、装置
全体の重量増大、及び大型化を効果的に抑えることがで
きる。
In the apparatus according to the first aspect of the present invention, the conveying member and the elevating member are moved in the shaft accommodating means so that the shafts arranged in the penetrating direction in the shaft accommodating means are simultaneously supplied to the penetrating position row by row. Therefore, even if the number of shafts arranged in the penetrating direction is large, the shafts can be simultaneously conveyed to the penetrating position in a stable state. In addition, since the carrying member is lighter in terms of strength and the space required for carrying is smaller than in the conventional case, it is possible to effectively suppress an increase in weight and an increase in size of the entire apparatus.

【0077】さらに、請求項2記載の装置によれば、搬
送部材及び昇降部材により貫入位置に供給した軸を軸保
持手段に受け渡すことにより、これらの軸を既貫入の軸
や貫入手段に連結する前に搬送部材及び昇降部材を貫入
位置から退避させることができ、これにより、作業能率
をより高めることができる効果がある。
Further, according to the apparatus of the second aspect, the shafts supplied to the penetrating position by the conveying member and the elevating member are transferred to the shaft holding means, so that these shafts are connected to the already penetrated shafts or the penetrating means. The conveying member and the elevating / lowering member can be retracted from the penetrating position before the operation, and thus there is an effect that the work efficiency can be further enhanced.

【0078】また、請求項3記載の装置では、軸収納手
段全体を基台上で走行させることにより、この軸収納手
段に収納されている軸を収納状態のままで上記貫入位置
へ供給するようにしたものであるので、各軸をさらに安
定した状態で搬送することができる効果がある。しか
も、各軸を搬送するための特別な部材を不要にすること
ができ、装置の構造をより簡略化することができる。
Further, in the apparatus according to the third aspect of the present invention, the shaft stored in the shaft storing means is supplied to the penetration position in the stored state by moving the entire shaft storing means on the base. Therefore, there is an effect that each shaft can be transported in a more stable state. In addition, it is possible to eliminate the need for a special member for transporting each shaft, and it is possible to further simplify the structure of the device.

【図面の簡単な説明】[Brief description of drawings]

【図1】上記多軸掘削機の側面図である。FIG. 1 is a side view of the multi-axis excavator.

【図2】上記多軸掘削機の正面図である。FIG. 2 is a front view of the multi-axis excavator.

【図3】上記多軸掘削機における軸支持装置の要部を示
す断面図である。
FIG. 3 is a cross-sectional view showing a main part of a shaft support device in the multi-axis excavator.

【図4】上記多軸掘削機における取出キャリアの側面図
である。
FIG. 4 is a side view of an extraction carrier in the multi-axis excavator.

【図5】上記取出キャリアの正面図である。FIG. 5 is a front view of the take-out carrier.

【図6】上記取出キャリアの平面図である。FIG. 6 is a plan view of the takeout carrier.

【図7】図5のA−A線断面図である。7 is a cross-sectional view taken along the line AA of FIG.

【図8】図7のB−B線断面図である。8 is a cross-sectional view taken along line BB of FIG.

【図9】上記多軸掘削機における軸貫入引抜装置の要部
を示す断面正面図である。
FIG. 9 is a cross-sectional front view showing a main part of a shaft penetration and withdrawal device in the multi-axis excavator.

【図10】上記多軸掘削機による貫入作業時の各装置の
作動状態を示すタイムチャートである。
FIG. 10 is a time chart showing an operating state of each device during a penetration operation by the multi-axis excavator.

【図11】本発明の第2実施例における掘削機の側面図
である。
FIG. 11 is a side view of an excavator according to a second embodiment of the present invention.

【図12】本発明の第3実施例における掘削軸の側面図
である。
FIG. 12 is a side view of an excavation shaft according to a third embodiment of the present invention.

【図13】上記掘削軸の平面図である。FIG. 13 is a plan view of the excavation shaft.

【符号の説明】[Explanation of symbols]

10 地盤 12 基台 14 軸収納装置(軸収納手段を構成) 16 取出キャリア 18 軸貫入引抜装置(貫入手段) 24 掘削軸(軸) 46 走行機(走行部材) 60 把持フレーム(昇降部材) 130 軸保持部材(軸保持手段) 10 Ground 12 Base 14 Shaft storage device (constituting shaft storage means) 16 Extraction carrier 18 Shaft penetration extraction device (penetration means) 24 Excavation shaft (axle) 46 Traveling machine (traveling member) 60 Grasping frame (elevating member) 130 Shaft Holding member (shaft holding means)

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 地盤に対して軸を順に継足しながら貫入
するための軸貫入装置において、複数の軸を予め定めら
れた貫入並び方向に並べた状態で保持し、これらの軸を
同時に地中へ貫入する貫入手段と、複数の軸を上記貫入
並び方向及びこれに略直交する収納並び方向の双方に並
べ、かつ立直させた状態で収納する軸収納手段と、この
軸収納手段に各軸の上方において上記収納並び方向に走
行可能となるように設置された移動部材と、この移動部
材に昇降可能に設けられ、上記軸収納手段において上記
貫入並び方向に並べられた全ての軸を一度に保持する昇
降部材とを備えたことを特徴とする軸貫入装置。
1. A shaft penetrating device for penetrating a ground while sequentially connecting the shafts, wherein a plurality of shafts are held in a state of being arranged in a predetermined penetrating arrangement direction, and these shafts are simultaneously grounded. A penetrating means for penetrating into the shaft, a shaft accommodating means for accommodating a plurality of shafts in both the penetrating arrangement direction and an accommodating arrangement direction substantially orthogonal to the penetrating arrangement direction, and accommodating the shafts in an upright state; A moving member installed so as to be able to travel in the storage arrangement direction above and all the shafts arranged in the shaft accommodation means that can be moved up and down and arranged in the penetration arrangement direction at a time. A shaft penetrating device, comprising:
【請求項2】 請求項1記載の軸貫入装置において、上
記貫入位置の近傍に昇降可能に設置され、この貫入手段
の貫入位置に搬送された全ての軸を一度に保持する軸保
持手段を備えたことを特徴とする軸貫入装置。
2. The shaft penetrating apparatus according to claim 1, further comprising a shaft holding means that is installed in the vicinity of the penetrating position so as to be able to move up and down and holds all the shafts conveyed to the penetrating position of the penetrating means at a time. A shaft penetrating device characterized in that
【請求項3】 地盤に対して軸を順に継足しながら貫入
するための軸貫入装置において、複数の軸を予め定めら
れた貫入並び方向に並べた状態で保持し、これらの軸を
同時に地中へ貫入する貫入手段と、地盤上に設置される
基台と、この基台上に上記貫入並び方向と略直交する収
納並び方向に走行可能に設置され、複数の軸を上記貫入
並び方向及び収納並び方向の双方に並べ、かつ立直させ
た状態で収納する軸収納手段とを備え、この軸収納手段
の走行によりこの軸収納手段に収納された各軸が上記貫
入手段による貫入位置に到達するように軸収納手段にお
ける各軸の収納位置を設定したことを特徴とする軸貫入
装置。
3. A shaft penetrating device for penetrating the ground while sequentially adding the shafts, wherein a plurality of shafts are held in a state of being arranged in a predetermined penetrating arrangement direction, and these shafts are simultaneously grounded. A penetrating means for penetrating into the ground, a base installed on the ground, and a traveling base installed on the base in a storage alignment direction substantially orthogonal to the penetration alignment direction, and a plurality of shafts are installed in the penetration alignment direction and the storage position. And a shaft storing means for storing in an upright state, arranged in both of the arranging directions so that the shafts stored in the shaft storing means reach the penetration position by the penetration means by traveling of the shaft storing means. A shaft penetrating device, characterized in that a storage position of each shaft in the shaft storing means is set.
JP12879192A 1992-05-21 1992-05-21 Shaft intrusion device Pending JPH05321564A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP12879192A JPH05321564A (en) 1992-05-21 1992-05-21 Shaft intrusion device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP12879192A JPH05321564A (en) 1992-05-21 1992-05-21 Shaft intrusion device

Publications (1)

Publication Number Publication Date
JPH05321564A true JPH05321564A (en) 1993-12-07

Family

ID=14993545

Family Applications (1)

Application Number Title Priority Date Filing Date
JP12879192A Pending JPH05321564A (en) 1992-05-21 1992-05-21 Shaft intrusion device

Country Status (1)

Country Link
JP (1) JPH05321564A (en)

Similar Documents

Publication Publication Date Title
US6581698B1 (en) Drilling device and method for drilling a well
US4765401A (en) Apparatus for handling well pipe
JP3241235B2 (en) Drilling method and drilling equipment
CN112832699A (en) Drilling equipment
KR101575171B1 (en) Apparatus for installing underground well pipe
JP2018513931A (en) Rod mounting device for drilling machine
JPS6320996B1 (en)
JPH05321564A (en) Shaft intrusion device
JP2008248604A (en) Method of advancing shield machine and shield machine
CN215057203U (en) Drilling equipment
TWI740251B (en) Low-headroom excavator and assembly method thereof
JPH05156636A (en) Shaft inserting device
JPH0658070A (en) Shaft penetrating device
JP4714792B1 (en) Bucket type drilling device
JPH05272286A (en) Shaft penetration device
JP3637173B2 (en) Excavator lifting device
TWI822500B (en) Mainframe rotation mechanism and rotation method for excavation apparatus
JP2596662B2 (en) Drilling rig
US20240011235A1 (en) Pile Driving Apparatus
JPH05321565A (en) Shaft intrusion device
JPH062478A (en) Shaft piercing device
JP3019256B2 (en) Segment assembling method and segment assembling apparatus
JPH0650079A (en) Method of use of shaft intruder and shaft intruder
KR101854260B1 (en) Drill ship
JPH0742472A (en) Automatic boring device