JPH05306599A - Decision method of stripping time of pressure welding concrete lining form device and stripping instruction device - Google Patents
Decision method of stripping time of pressure welding concrete lining form device and stripping instruction deviceInfo
- Publication number
- JPH05306599A JPH05306599A JP4135716A JP13571692A JPH05306599A JP H05306599 A JPH05306599 A JP H05306599A JP 4135716 A JP4135716 A JP 4135716A JP 13571692 A JP13571692 A JP 13571692A JP H05306599 A JPH05306599 A JP H05306599A
- Authority
- JP
- Japan
- Prior art keywords
- temperature
- stripping
- formwork
- concrete
- demolding
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
- Lining And Supports For Tunnels (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】本発明は、山岳トンネル等のトン
ネルの一次覆工に使用される型枠装置の脱型時期を的確
に判定する方法とこれに使用する装置に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for accurately determining a demolding time of a formwork apparatus used for primary lining of a tunnel such as a mountain tunnel, and an apparatus used for the method.
【0002】[0002]
【従来の技術】従来、山岳トンネルの掘削壁面に対する
一次覆工においては、吹き付け工法に代わって、クロー
ラを備えた移動型の型枠装置が実用化されつつある。こ
の型枠装置は、吹き付け工法の欠点である粉塵の発生を
抑え骨材等の跳ね返りに伴う経済的なロスを解消する等
の理由により、掘削断面に沿った鋼製型枠を掘削断面に
沿って配設し、地山と前記型枠との間隙にフレッシュコ
ンクリートを打設充填させ、所要強度の発現を待って前
記型枠を脱型させて平滑な覆工面を形成するものであ
る。2. Description of the Related Art Conventionally, in a primary lining on an excavated wall surface of a mountain tunnel, a movable formwork device equipped with a crawler has been put into practical use instead of the spraying method. This formwork device uses a steel formwork along the excavation cross section along the excavation cross section for the reasons such as suppressing the generation of dust, which is a drawback of the spraying method, and eliminating the economic loss due to the rebound of aggregate etc. The mold is placed and filled with fresh concrete by pouring and filling in the gap between the ground and the mold, and the mold is demolded after the required strength is developed to form a smooth lining surface.
【0003】この型枠装置を使用してトンネルの掘削壁
面に一次覆工する圧着コンクリート覆工法として、既に
本願出願人により、特開平3−235899号、特開平
3−235898号、特開平4−64696号に示され
ている。図4乃至図5を参照して前記型枠装置1の一例
を説明すると、自走用のクローラ2上にターンテーブル
3が回転自在に載置され、該ターンテーブル3に左右方
向ジャッキ4及び上下方向ジャッキ5が装備されてお
り、各ジャッキ4,5のロッド先端部には、このジャッ
キの伸縮によって拡開自在な型枠6,7,8がヒンジ9
を介して設けられている。As a crimping concrete lining method for making a primary lining on the excavated wall surface of a tunnel using this formwork device, the applicant of the present invention has already disclosed JP-A-3-235899, JP-A-3-235898, and JP-A-4-23598. No. 64696. An example of the formwork apparatus 1 will be described with reference to FIGS. 4 to 5. A turntable 3 is rotatably mounted on a self-propelled crawler 2, and the turntable 3 includes a left-right jack 4 and an up-down direction. A directional jack 5 is provided, and at the rod tips of the jacks 4 and 5, form frames 6, 7 and 8 which can be expanded by the expansion and contraction of the jacks are hinged 9.
It is provided through.
【0004】そして、前記型枠6,7,8には所要の土
圧計10,バイブレータ11,供試体採取型枠12,及
び早期強度測定用ピン13が設けられて、型枠6に設け
られた打設管6aから掘削壁面14と前記型枠表面との
間隙15に打設されたフレッシュコンクリートの強度発
現の管理を行うようになされている。The molds 6, 7 and 8 are provided with a required earth pressure gauge 10, a vibrator 11, a sample-collecting mold 12 and a pin 13 for early strength measurement. The strength development of the fresh concrete cast from the casting pipe 6a into the gap 15 between the excavation wall surface 14 and the surface of the mold is controlled.
【0005】[0005]
【発明が解決しようとする課題】しかしながら、上述の
打設コンクリートの強度を測定し、所定強度の発現後に
地山16の掘削壁面14に対して、型枠6,7,8の脱
型の時期を決定するには、図5に示す早期強度測定用ピ
ン13を小型ジャッキ等で荷重Pを掛けて覆工コンクリ
ートの一部を撥り出すことでコンクリート強度を計って
いたので、一次覆工コンクリートの一部を破壊してしま
う、前記早期強度測定用ピンを引き抜く作業が手間の掛
かるものであるといった欠点があった。However, the strength of the above-mentioned cast concrete is measured, and after the predetermined strength is exhibited, the molds 6, 7 and 8 are removed from the excavation wall surface 14 of the natural ground 16 at the time of demolding. In order to determine, the concrete strength was measured by applying a load P to the early strength measuring pin 13 shown in FIG. 5 with a small jack or the like to repel a part of the lining concrete, and therefore the primary lining concrete However, there are drawbacks that some of them are destroyed and the work for pulling out the early strength measuring pin is troublesome.
【0006】本発明は、上記の課題に鑑みてなされたも
ので、一次覆工コンクリートを破壊することなく、か
つ、脱型時期を検査する作業も容易になしえる圧着コン
クリート覆工型枠装置の脱型時期の判定方法、及びこれ
に使用する装置を提供することを目的とする。The present invention has been made in view of the above problems, and provides a crimping concrete lining form device that does not destroy the primary lining concrete and can easily perform the work of inspecting the demolding time. It is an object of the present invention to provide a method for determining a demolding time and a device used therefor.
【0007】[0007]
【課題を解決するための手段】本発明の上記課題を解決
し上記目的を達成するための要旨は、型枠装置の型枠に
覆工コンクリートの温度を測定する温度センサーを少な
くとも一つ以上設け、前記覆工コンクリートを打設して
いる場所の坑内周辺温度を測定する温度センサーを設
け、前記各温度センサーの数値から積算温度を算出し、
該積算温度が圧縮強度と積算温度の相関表から導かれる
所定の圧縮強度に対応する数値に達したら型枠の脱型を
指示させることに存する。また、請求項2に記載のよう
に、型枠装置の型枠に少なくとも一つ以上設けられた温
度センサーの数値データと前記型枠装置で覆工コンクリ
ートを打設している場所の坑内周辺温度を測定する温度
センサーの数値データの各々を計測器で読取り、該計測
器からの数値データを基に記憶演算器で積算温度を算出
し、この算出した積算温度の数値データを制御器に取り
入れて該制御器に予め設定された数値に達したらこの制
御器からトリガー信号を発し、該トリガー信号により脱
型を指示する信号を報知器により発する脱型指示装置と
したことに存する。The object of the present invention to solve the above problems and to achieve the above objects is to provide at least one temperature sensor for measuring the temperature of lining concrete on a formwork of a formwork apparatus. , Providing a temperature sensor for measuring the ambient temperature in the mine at the place where the lining concrete is placed, and calculating the integrated temperature from the numerical values of the temperature sensors,
When the integrated temperature reaches a numerical value corresponding to a predetermined compressive strength derived from the correlation table of the compressive strength and the integrated temperature, the mold releasing instruction is instructed. In addition, as described in claim 2, numerical data of at least one temperature sensor provided in the formwork of the formwork device and ambient temperature inside the mine at the place where the lining concrete is placed by the formwork device. Each of the numerical data of the temperature sensor for measuring is read by the measuring instrument, the integrated temperature is calculated by the storage arithmetic unit based on the numerical data from the measuring instrument, and the calculated numerical value of the integrated temperature is taken into the controller. This is because the demolding instructing device emits a trigger signal from this controller when the value reaches a value preset in the controller, and a signal for instructing demolding by the trigger signal is issued by an annunciator.
【0008】[0008]
【作用】本発明の圧着コンクリート覆工型枠装置の脱型
時期の判定方法によれば、積算温度の測定データを収集
して、これを圧縮強度と積算温度の相関表から所望圧縮
強度に覆工コンクリートが達したことが非破壊試験で判
定できることになる。よって、積算温度が所定の数値に
達したら、型枠装置の脱型を行うことができる。また、
型枠の脱型指示をマイクロコンピュータを使用して、積
算温度が所定値に達したら、シグナルを発するようにプ
ログラミングしておくことで、脱型の時期を自動的に知
ることができて、手間の掛からないものとなる。According to the method for determining the demolding time of the crimping concrete lining formwork apparatus of the present invention, the measured data of the integrated temperature is collected, and it is covered with the desired compressive strength from the correlation table of the compressive strength and the integrated temperature. The non-destructive test can be used to judge that the work concrete has reached. Therefore, when the integrated temperature reaches a predetermined value, the mold device can be demolded. Also,
By using a microcomputer to issue a mold release instruction, the programming can be performed so that a signal is emitted when the integrated temperature reaches a predetermined value, so that the time of mold release can be automatically known. It will not be costly.
【0009】[0009]
【実施例】次に、本発明について図面を参照して説明す
る。図1は、本発明に係る脱型指示装置の構成概略図で
あり、図2は型枠に取り付けた温度センサーの一部を示
す斜視図である。図3は圧縮強度と積算温度の相関表で
ある。図において、符号20は周辺温度測定用温度セン
サー、21,22…25は各々型枠用温度センサー、2
6は脱型指示装置、27は計測器、28は記憶演算器、
29はコンピュータの制御器、30は報知器を各々示し
ている。DESCRIPTION OF THE PREFERRED EMBODIMENTS Next, the present invention will be described with reference to the drawings. FIG. 1 is a schematic configuration diagram of a demolding instruction device according to the present invention, and FIG. 2 is a perspective view showing a part of a temperature sensor attached to a mold. FIG. 3 is a correlation table of compressive strength and integrated temperature. In the figure, reference numeral 20 is a temperature sensor for measuring ambient temperature, 21, 22 ... 25 are temperature sensors for molds, 2 respectively.
6 is a demolding instruction device, 27 is a measuring instrument, 28 is a memory computing unit,
Reference numeral 29 is a controller of the computer, and 30 is an alarm.
【0010】本発明の圧着コンクリート覆工型枠装置の
脱型時期の判定方法は、一次覆工したコンクリートの強
度を積算温度により推定して、型枠装置の型枠の脱型時
期を判定しようとするものである。以下具体的に装置等
を説明して脱型時期の判定方法を述べる。In the method for determining the demolding time of the crimp concrete lining formwork device of the present invention, the strength of the primary lining concrete is estimated from the integrated temperature to determine the demolding time of the formwork of the formwork device. It is what Hereinafter, the apparatus and the like will be specifically described, and a method for determining the demolding time will be described.
【0011】先ず、従来例で説明した図4に示す型枠装
置1の型枠6,7,8に図2に示すように覆工コンクリ
ートの温度を測定する型枠用温度センサー21を設け
る。例えば、前記型枠用温度センサーを型枠6には1
個、左右の型枠7,7に各々1個、左右の型枠8,8に
も各々1個にして設ける。こうして、掘削壁面14に沿
って略半円形状に展開させた型枠6,7,8に合計5個
の型枠用温度センサー21を装着する。First, as shown in FIG. 2, a mold temperature sensor 21 for measuring the temperature of the lining concrete is provided on the molds 6, 7 and 8 of the mold device 1 shown in FIG. For example, the mold temperature sensor is attached to the mold 6.
One for each of the left and right molds 7, 7 and one for each of the left and right molds 8, 8. In this way, a total of five mold temperature sensors 21 are attached to the molds 6, 7, and 8 which are developed in a substantially semicircular shape along the excavation wall surface 14.
【0012】次に、型枠装置1に任意の箇所に、前記覆
工コンクリートを打設している場所の坑内周辺温度を測
定する周辺温度測定用温度センサー20(図示せず)を
設ける。そして、図1を参照して脱型指示装置26の概
要を説明すると、上記各温度センサー20,21のリー
ド線の一端を脱型指示装置26の計測器27の接続端子
に接続する。この計測器27により温度センサーで測定
した温度が数値データに変換される。Next, an ambient temperature measuring temperature sensor 20 (not shown) for measuring the ambient temperature inside the mine at the place where the lining concrete is placed is provided at an arbitrary position in the formwork apparatus 1. The outline of the demolding instruction device 26 will be described with reference to FIG. 1. One end of the lead wire of each of the temperature sensors 20 and 21 is connected to a connection terminal of a measuring instrument 27 of the demolding instruction device 26. The measuring device 27 converts the temperature measured by the temperature sensor into numerical data.
【0013】前記計測器27の後段に記憶演算器28が
接続されており、計測器27からの温度数値データを基
にして、以下に示す式がプログラミングされた前記記憶
演算器28にて積算温度を算出する。A storage computing unit 28 is connected to the latter stage of the measuring unit 27, and based on the temperature numerical data from the measuring unit 27, the storage computing unit 28 programmed with the following formula is used to calculate the integrated temperature. To calculate.
【0014】[0014]
【数1】 [Equation 1]
【0015】上記数式において、Mxはx回目の温度デ
ータ測定時における積算温度(℃・min)、Tiはi
回目の温度データ測定時の打設コンクリートの温度
(℃)、Toiはi回目の温度データ測定時の周辺温度
(℃)、Δtは温度データを測定する時間の間隔(mi
n)である。In the above formula, Mx is the integrated temperature (° C.min) at the time of the x-th temperature data measurement, and Ti is i.
The temperature (° C) of the poured concrete at the time of the temperature data measurement, Toi is the ambient temperature (° C) at the time of the i-th temperature data measurement, and Δt is the time interval (mi) for measuring the temperature data.
n).
【0016】前記記憶演算器28によって算出された積
算温度が、この記憶演算器28の後段に接続された制御
器29へ、各温度測定の度に逐一データとして送られ
る。そしてこの制御器29では、予め設定された積算温
度(Msとする)と前記記憶演算器28からの積算温度
(Mx)との比較を行い、x回目の積算温度Mxが初め
てMx≧Msとなった時に、トリガー信号を発するよう
になされている。The integrated temperature calculated by the storage / calculation unit 28 is sent to the controller 29 connected to the subsequent stage of the storage / calculation unit 28 as data for each temperature measurement. Then, the controller 29 compares the preset integrated temperature (denoted by Ms) with the integrated temperature (Mx) from the storage calculator 28, and the integrated temperature Mx of the x-th time becomes Mx ≧ Ms for the first time. It is designed to emit a trigger signal when it is turned on.
【0017】前記トリガー信号が制御器29の後段に接
続された報知器30に送信され、この報知器30が前記
トリガー信号によって作動し、脱型の時期が来たことを
例えば報知灯の点滅やスピーカから音声合成装置を介し
て「脱型の時間です。」と放送する等して作業者に知ら
せる。このようにして、脱型指示装置26が構成されて
いる。The trigger signal is transmitted to the annunciator 30 connected to the subsequent stage of the controller 29, and the annunciator 30 is activated by the trigger signal to indicate that it is time to release the mold, for example, by blinking an annunciator lamp or The operator is informed by broadcasting from the speaker via the voice synthesizer, "It's time to leave the mold." In this way, the demolding instruction device 26 is configured.
【0018】また、前記制御装置29における積算温度
の設定については、打設した覆工コンクリートが所望の
強度になるときの積算温度を図3に示す、圧縮強度−積
算温度の相関表から対応する積算温度Msを求めるもの
である。この相関表の縦軸は圧縮強度σ(kgf/cm
2)で、横軸は積算温度M(℃・min)である。Further, the setting of the integrated temperature in the control device 29 corresponds to the integrated temperature when the placed lining concrete has a desired strength from the compression strength-integrated temperature correlation table shown in FIG. The integrated temperature Ms is obtained. The vertical axis of this correlation table is the compressive strength σ (kgf / cm
2 ), the horizontal axis is the integrated temperature M (° C · min).
【0019】上記相関表は、予め実験によってトンネル
の一次覆工に使用される急硬性コンクリートを所定の条
件(周辺温度20℃)で打設し、材令90分までの各積
算温度におけるコンクリートの圧縮強度を円柱供試体
(φ10・20cm)を採取してこれを圧縮試験機にか
けて測定し、その圧縮強度を表にプロットして作成した
ものである。図3に示す相関表では、σx=0.074
Mxのリニアな相関関係が得られており、相関係数r2
=0.938という高い相関が認められるものである。
なお、0.074の数値は回帰係数を示すものであり、
配合条件等のコンクリートの硬化速度によって異なる。The above-mentioned correlation table shows that, in a preliminary experiment, rapid-hardening concrete to be used for the primary lining of a tunnel was placed under predetermined conditions (ambient temperature 20 ° C.), and the concrete at each accumulated temperature up to 90 minutes was used. The compressive strength was prepared by collecting a cylindrical test piece (φ10 · 20 cm), measuring it with a compression tester, and plotting the compressive strength in a table. In the correlation table shown in FIG. 3, σx = 0.074
A linear correlation of Mx is obtained, and the correlation coefficient r 2
A high correlation of = 0.938 is recognized.
The numerical value of 0.074 shows the regression coefficient,
Depends on the hardening rate of concrete such as mixing conditions.
【0020】よって、トンネルの坑内温度の条件によ
り、各温度毎に予め相関表を作成しておいて、所望の圧
縮強度に対応する積算温度を各々の相関表から求めて、
この積算温度の値Msを前記制御器29に設定しておく
ものである。このように、トンネル一次覆工において積
算温度法を若材令の急硬性コンクリートに適用させるこ
とにより、本発明がなしえるようになったものである。Therefore, a correlation table is prepared in advance for each temperature depending on the conditions of the tunnel internal temperature, and the integrated temperature corresponding to the desired compressive strength is obtained from each correlation table,
This integrated temperature value Ms is set in the controller 29. As described above, the present invention can be achieved by applying the integrated temperature method to the early hardening concrete in the primary lining of the tunnel.
【0021】そして上記脱型指示装置26を型枠装置1
に装備してトンネルの一次覆工を行う方法を説明する
と、地山16を所定長掘削した後、型枠装置1を自走さ
せて一次覆工する場所に移動させ、掘削壁面14に沿っ
て半円形に型枠6,7,8を各ジャッキ4,5で拡開さ
せる。次に、打設管6aから急硬性コンクリートを間隙
15に打設する。急硬性コンクリートの間隙15への充
填後、脱型指示装置26を作動させ、例えば2分間隔毎
に各温度センサー20,21,…25から得られる温度
データを基に積算温度Mxを算出する。Then, the demolding instructing device 26 is used as the formwork device 1.
The method of carrying out the primary lining of the tunnel by equipping with the above is explained. After excavating the natural ground 16 for a predetermined length, the formwork apparatus 1 is moved by itself to a place for primary lining, and along the excavated wall surface 14. The molds 6, 7 and 8 are expanded in a semicircular shape with the jacks 4 and 5. Next, the rapid hardening concrete is poured into the gap 15 from the casting pipe 6a. After the rapid-hardening concrete is filled in the gap 15, the demolding indicator 26 is operated, and the integrated temperature Mx is calculated based on the temperature data obtained from the temperature sensors 20, 21, ... 25, for example, at intervals of 2 minutes.
【0022】そして、複数回測定した時における積算温
度Mxが、Mx≧Msとなったときに脱型指示装置26
の報知器30からシグナルがでる。これにより、作業者
は一次覆工した急硬性コンクリートが所望の圧縮強度に
達したことが判り、型枠装置1のジャッキ4,5を操作
して型枠6,7,8を脱型させて、この型枠装置1を他
の場所に退避させるものである。なお、型枠装置は移動
型であっても固定型の型枠装置であっても何等差し支え
ないものである。Then, when the integrated temperature Mx when measured a plurality of times becomes Mx ≧ Ms, the demolding instruction device 26.
A signal is emitted from the alarm device 30. From this, the operator found that the rapidly-hardened concrete that had undergone the primary lining had reached the desired compressive strength, and operated the jacks 4 and 5 of the formwork apparatus 1 to demold the formwork 6, 7 and 8. The formwork apparatus 1 is retracted to another place. It should be noted that the formwork device may be either a movable formwork or a fixed formwork form device.
【0023】[0023]
【発明の効果】以上説明したように、本発明の圧着コン
クリート覆工型枠装置の脱型時期の判定方法は、型枠装
置の型枠に覆工コンクリートの温度を測定する温度セン
サーを少なくとも一つ以上設け、前記覆工コンクリート
を打設している場所の坑内周辺温度を測定する温度セン
サーを設け、前記各温度センサーの数値から積算温度を
算出し、該積算温度が所定の数値に達したら型枠の脱型
を指示させるようにしたので、従来のように覆工コンク
リート面を破壊することがなく脱型の時期を知るための
作業者において手間が掛からず、作業が能率的で工期の
短縮ともなる。また、覆工コンクリート面がその一部で
破壊されることがないのできれいな仕上がりとなる。As described above, the method for determining the demolding time of the crimping concrete lining formwork apparatus of the present invention is such that at least one temperature sensor for measuring the temperature of the lining concrete is attached to the formwork of the formwork apparatus. If more than one is provided, a temperature sensor is provided to measure the ambient temperature inside the mine at the place where the lining concrete is cast, and the integrated temperature is calculated from the numerical values of the temperature sensors, and when the integrated temperature reaches a predetermined numerical value. Since it is designed to instruct the demolding of the formwork, it does not require the operator to know the time of demolding without destroying the lining concrete surface as in the past, and the work is efficient and the construction period is It also shortens. Moreover, since the lining concrete surface is not destroyed in part, a clean finish is obtained.
【0024】脱型指示装置により、積算温度を予め制御
器に設定しておくことで脱型の時期を自動的に知ること
ができて、手間の掛かる積算算出作業が短時間で成しえ
て作業能率の向上となる。By using the demolding instruction device, it is possible to automatically know the demolding time by setting the integrated temperature in the controller in advance, and the laborious integration calculation work can be completed in a short time. It will improve the efficiency.
【図1】本発明に係る脱型指示装置の構成概略図であ
る。FIG. 1 is a schematic configuration diagram of a mold release instruction device according to the present invention.
【図2】型枠に取り付けた温度センサーの一部を示す斜
視図である。FIG. 2 is a perspective view showing a part of a temperature sensor attached to a mold.
【図3】圧縮強度と積算温度の相関表である。FIG. 3 is a correlation table of compressive strength and integrated temperature.
【図4】従来例に係る型枠装置の使用状態を示す一部を
断面にした正面図である。FIG. 4 is a front view, partly in section, showing a usage state of a formwork apparatus according to a conventional example.
【図5】同じく早期強度測定用ピンの使用状態を示す一
部断面図である。FIG. 5 is a partial cross-sectional view showing a usage state of the early strength measuring pin.
20 周辺温度測定用温度センサー、21,22…25
型枠用温度センサー、26 脱型指示装置、27 計
測器、28 記憶演算器、29 コンピュータの制御
器、30 報知器。20 Ambient temperature measuring temperature sensors 21, 22, ... 25
Mold temperature sensor, 26 mold release indicator, 27 measuring instrument, 28 memory calculator, 29 computer controller, 30 alarm.
Claims (2)
度を測定する温度センサーを少なくとも一つ以上設け、
前記覆工コンクリートを打設している場所の坑内周辺温
度を測定する温度センサーを設け、前記各温度センサー
の数値から積算温度を算出し、該積算温度が圧縮強度と
積算温度の相関表から導かれる所定の圧縮強度に対応す
る数値に達したら型枠の脱型を指示させることを特徴と
してなる圧着コンクリート覆工型枠装置の脱型時期の判
定方法。1. A formwork of a formwork apparatus is provided with at least one temperature sensor for measuring the temperature of lining concrete,
A temperature sensor for measuring the ambient temperature inside the mine at the place where the lining concrete is placed is provided, the integrated temperature is calculated from the numerical values of the temperature sensors, and the integrated temperature is derived from the correlation table of the compressive strength and the integrated temperature. A method for determining the demolding time of a crimping concrete lining formwork device, characterized by instructing demolding of a formwork when a numerical value corresponding to a given predetermined compressive strength is reached.
けられた温度センサーの数値データと前記型枠装置で覆
工コンクリートを打設している場所の坑内周辺温度を測
定する温度センサーの数値データの各々を計測器で読取
り、該計測器からの数値データを基に記憶演算器で積算
温度を算出し、この算出した積算温度の数値データを制
御器に取り入れて該制御器に予め設定された数値に達し
たらこの制御器からトリガー信号を発し、該トリガー信
号により脱型を指示する信号を報知器により発するよう
にしたことを特徴としてなる脱型指示装置。2. Numerical data of at least one temperature sensor provided on the formwork of the formwork device and a temperature sensor for measuring the ambient temperature inside the mine at the place where the lining concrete is placed by the formwork device. Each of the numerical data is read by the measuring instrument, the integrated temperature is calculated by the storage arithmetic unit based on the numerical data from the measuring instrument, and the numerical data of the calculated integrated temperature is taken into the controller and preset in the controller. A demolding instruction device characterized in that a trigger signal is issued from this controller when the specified value is reached, and a signal for instructing demolding by the trigger signal is issued by an annunciator.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP4135716A JP2542308B2 (en) | 1992-04-30 | 1992-04-30 | Demolding instruction device for crimping concrete lining formwork device and method for judging demolding time |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP4135716A JP2542308B2 (en) | 1992-04-30 | 1992-04-30 | Demolding instruction device for crimping concrete lining formwork device and method for judging demolding time |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH05306599A true JPH05306599A (en) | 1993-11-19 |
JP2542308B2 JP2542308B2 (en) | 1996-10-09 |
Family
ID=15158218
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP4135716A Expired - Lifetime JP2542308B2 (en) | 1992-04-30 | 1992-04-30 | Demolding instruction device for crimping concrete lining formwork device and method for judging demolding time |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2542308B2 (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2009155819A (en) * | 2007-12-25 | 2009-07-16 | Kajima Corp | Equipment for placing lining concrete in tunnel |
JP2012026734A (en) * | 2010-07-20 | 2012-02-09 | Sato Kogyo Co Ltd | Lined concrete demolding time determination method and demolding time determination system |
JP2012036717A (en) * | 2010-06-29 | 2012-02-23 | Fraunhofer Ges Zur Foerderung Der Angewandten Forschung Ev | Casing element, and device and method for allocating identifier to casing element |
JP2012242346A (en) * | 2011-05-24 | 2012-12-10 | Techno Pro Kk | Strength estimation apparatus for lining concrete, system and method |
WO2013021951A1 (en) * | 2011-08-08 | 2013-02-14 | 株式会社Just.Will | Recyclable formwork |
JP2014077241A (en) * | 2012-10-09 | 2014-05-01 | Just Will Co Ltd | Cast concrete strength management system |
CN112945493A (en) * | 2021-01-29 | 2021-06-11 | 石家庄铁道大学 | Tunnel lining vibration response simulation test system |
KR102438277B1 (en) * | 2022-03-21 | 2022-08-31 | (주)한조엔지니어링 | Movable steel box-type formwork for concrete pouring and construction method using the same |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS63107695A (en) * | 1986-10-21 | 1988-05-12 | 株式会社大林組 | Injection execution control method in method of back-filling injection construction |
-
1992
- 1992-04-30 JP JP4135716A patent/JP2542308B2/en not_active Expired - Lifetime
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS63107695A (en) * | 1986-10-21 | 1988-05-12 | 株式会社大林組 | Injection execution control method in method of back-filling injection construction |
Cited By (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2009155819A (en) * | 2007-12-25 | 2009-07-16 | Kajima Corp | Equipment for placing lining concrete in tunnel |
JP2012036717A (en) * | 2010-06-29 | 2012-02-23 | Fraunhofer Ges Zur Foerderung Der Angewandten Forschung Ev | Casing element, and device and method for allocating identifier to casing element |
JP2012026734A (en) * | 2010-07-20 | 2012-02-09 | Sato Kogyo Co Ltd | Lined concrete demolding time determination method and demolding time determination system |
JP2012242346A (en) * | 2011-05-24 | 2012-12-10 | Techno Pro Kk | Strength estimation apparatus for lining concrete, system and method |
WO2013021951A1 (en) * | 2011-08-08 | 2013-02-14 | 株式会社Just.Will | Recyclable formwork |
JP2013036230A (en) * | 2011-08-08 | 2013-02-21 | Just Will Co Ltd | Recyclable formwork |
US9074378B2 (en) | 2011-08-08 | 2015-07-07 | Just.Will Co., Ltd. | Recyclable formwork |
JP2014077241A (en) * | 2012-10-09 | 2014-05-01 | Just Will Co Ltd | Cast concrete strength management system |
CN112945493A (en) * | 2021-01-29 | 2021-06-11 | 石家庄铁道大学 | Tunnel lining vibration response simulation test system |
CN112945493B (en) * | 2021-01-29 | 2022-11-15 | 石家庄铁道大学 | Tunnel lining vibration response simulation test system |
KR102438277B1 (en) * | 2022-03-21 | 2022-08-31 | (주)한조엔지니어링 | Movable steel box-type formwork for concrete pouring and construction method using the same |
Also Published As
Publication number | Publication date |
---|---|
JP2542308B2 (en) | 1996-10-09 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN111337409B (en) | Test device and method for simulating influence of rainfall on seepage dynamic of karst tunnel | |
CN108198504B (en) | Centrifugal test device for simulating multi-line shield crossing existing structure and test method thereof | |
JP2542308B2 (en) | Demolding instruction device for crimping concrete lining formwork device and method for judging demolding time | |
CN107989634A (en) | A kind of information-based monitoring system of tunnel lining trolley concrete cast | |
JPS60253617A (en) | Method and apparatus for measuring compactness of soil on site | |
JP5231493B2 (en) | Lining concrete demolding time judging method and demolding time judging system | |
CN114199686B (en) | Model test device and method for operating highway tunnel lining disease evolution law | |
JP2020519798A (en) | Precast segment for tunnels and method of making and monitoring such precast segment | |
JP6511316B2 (en) | Concrete placement management method | |
CN111189698A (en) | Device and method for testing internal and external deformation characteristics of anchoring rock body under corrosion creep condition | |
JP6179767B2 (en) | Tunnel lining arch concrete stop management method | |
JP4754382B2 (en) | Method for estimating strength characteristics of reinforcing bars in existing structures | |
JPH0750104B2 (en) | Nondestructive evaluation method and device for concrete | |
JP2013159939A (en) | Compaction control method for concrete | |
RU2389987C1 (en) | Method of measuring force in working reinforcement bars of reinforced concrete structure | |
US5101667A (en) | Method enabling a diagnosis to be made of the condition of a conduit or gallery and equipment for the implementation thereof | |
JP6909025B2 (en) | Measuring device and evaluation test method for ground improvement | |
CN113848122B (en) | Hydraulic tunnel surrounding rock and lining structure simulation test method considering external water pressure | |
CN210483749U (en) | Visible two-lining mold building system | |
JP2006169758A (en) | Ground bearing capacity testing apparatus and ground bearing capacity testing method | |
JP2575067B2 (en) | Formwork equipment | |
CN113686603A (en) | Deep-buried tunnel surrounding rock and lining structure combined bearing simulation test method | |
JP3893572B2 (en) | Sand pile construction method | |
CN111060558A (en) | Steel pipe concrete compactness detection system and method | |
JP2647250B2 (en) | Automatic control device for steel form for secondary lining |