JPH05282320A - Work scheduling method - Google Patents

Work scheduling method

Info

Publication number
JPH05282320A
JPH05282320A JP10398392A JP10398392A JPH05282320A JP H05282320 A JPH05282320 A JP H05282320A JP 10398392 A JP10398392 A JP 10398392A JP 10398392 A JP10398392 A JP 10398392A JP H05282320 A JPH05282320 A JP H05282320A
Authority
JP
Japan
Prior art keywords
time
lot
scheduling
simulation
stock
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP10398392A
Other languages
Japanese (ja)
Inventor
Kenji Ui
憲司 宇井
Tetsumi Kondo
哲己 近藤
Masahiro Yamashita
正大 山下
Kazuhiro Isomura
一弘 磯村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Steel Corp
Original Assignee
Nippon Steel Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nippon Steel Corp filed Critical Nippon Steel Corp
Priority to JP10398392A priority Critical patent/JPH05282320A/en
Publication of JPH05282320A publication Critical patent/JPH05282320A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Multi-Process Working Machines And Systems (AREA)
  • General Factory Administration (AREA)

Abstract

PURPOSE:To obtain a high precise work scheduling for all subject processes of a scheduling in a short time by calculating a working time and a set-up time or the like by a simulation, setting a completion time and a selected lot as a processing lot, storing the completion lot in a storage medium as a fore stock, and referring to the data at the time of the next scheduling. CONSTITUTION:The simulation of a time lapse management by the working of the subject process of the scheduling is operated (S105), and the obtained stock content and working condition are registered in a storage medium (S106). Then, the material to be treated next is selected, and the scheduling is operated (S107) by referring to the registered content, based on the stock content and the completed material of each process according to a specific rule in consideration of time for delivery or a lot constraint. And also, at the time of starting the simulation, a pipe manufacture schedule and in-factory intermediate device content are inputted (S101 and S102), and used as the working condition and initial stock data (S103 and S104).

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、工程の各々に対するス
ケジューリングを高精度かつ短時間に作成するための作
業スケジューリング方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a work scheduling method for creating a scheduling for each process with high accuracy and in a short time.

【0002】[0002]

【従来の技術】従来、作業スケジュールの作成は、担当
者がその時々の優先順位に従って材料を選択し、手作業
により作業時間を計算することにより行っている。
2. Description of the Related Art Conventionally, a work schedule is created by a person in charge selecting materials according to the priority order at that time and manually calculating work time.

【0003】[0003]

【発明が解決しようとする課題】しかし、上記した従来
技術にあっては、時間的な制約からスケジュールの作成
が特定の工程に限られ、また、作業時間の計算は計算時
間を速くするために平均値などの一定値を用いて計算
し、段取替時間にも一定値を用いている他、スケジュー
ル作成に要するデータの多さから人の判断によって材料
選択を行うにも限界があるため、作成したスケジュール
は精度が低く、実行するには多くの支障がある。
However, in the above-mentioned conventional technique, the schedule creation is limited to a specific process due to the time constraint, and the calculation of the work time is performed in order to shorten the calculation time. Calculation is performed using a fixed value such as an average value, and a fixed value is also used for the setup change time.Because of the large amount of data required to create a schedule, there is a limit to how much material can be selected by human judgment, The created schedule has low accuracy and there are many obstacles to execute it.

【0004】本発明の目的は、スケジュールを高精度か
つ短時間に作成することのできる作業スケジューリング
方法を提供することにある。
An object of the present invention is to provide a work scheduling method capable of creating a schedule with high accuracy and in a short time.

【0005】[0005]

【課題を解決するための手段】上記の目的を達成するた
めに、この発明は、スケジューリングの対象となる工程
の稼働による時間経過管理をシミュレーションし、これ
により得られた在庫内容及び稼働状況を記憶媒体に登録
し、この登録内容を参照して工程毎に納期やロット制約
を考慮した固有のルールに従って工程毎の在庫内容と完
了材とに基づいて次に処理する材料を選択してスケジュ
ーリングを行うようにしている。
In order to achieve the above-mentioned object, the present invention simulates time lapse management due to the operation of a process to be scheduled, and stores the inventory contents and the operation status obtained thereby. Register on the medium, refer to the registered contents, and select the material to be processed next based on the inventory contents and completed materials for each process according to the unique rule considering the delivery date and lot constraint for each process and perform scheduling I am trying.

【0006】[0006]

【作用】上記した手段によれば、スケジューリングで選
択されたロットのデータに基づいて稼働時間、段取り時
間などがシミュレーションにより算出され、完了時刻及
び選択されたロットを処理中ロットとし、かつ、完了ロ
ットを前面在庫として記憶媒体に格納し、このデータを
次のスケジューリングで参照する。これにより、スケジ
ューリングの対象となる全工程について高精度な作業ス
ケジューリングを短時間に得ることができる。
According to the above means, the operating time, the setup time, etc. are calculated by simulation based on the data of the lot selected in the scheduling, and the completion time and the selected lot are treated as the processing lot, and the completed lot is processed. Is stored in the storage medium as the front inventory, and this data is referred to in the next scheduling. As a result, highly accurate work scheduling can be obtained in a short time for all the processes to be scheduled.

【0007】[0007]

【実施例】以下、本発明の実施例について図面を参照し
ながら説明する。
Embodiments of the present invention will be described below with reference to the drawings.

【0008】図1は本発明による作業スケジューリング
方法の処理を示すフローチャートである。ここでは、鉄
鋼業の製造に適用した例を示している。
FIG. 1 is a flow chart showing the processing of the work scheduling method according to the present invention. Here, an example applied to manufacturing in the steel industry is shown.

【0009】データとして、スケジューリングの対象と
なる工程の中で一番最初に処理を行う工程のデータ(こ
の実施例では、造管スケジュール)1と、工場内・中間
仕掛内容を表すデータ(シミュレーション開始時には初
期在庫)2とがある。まず、データ1が入力され(S1
01)、これがシステム内の記憶媒体(例えば、半導体
メモリ)に格納される(S102)。ついでデータ2が
入力され(S103)、これがメモリに格納される(S
104)。このメモリには、前記入力データのほか、シ
ミュレーション開始後には、その処理に伴う在庫内容
(在庫の場所、明細など)と稼働状況(各工程の処理中
材料)が記憶される。
As data, data of a process (the pipe-making schedule in this embodiment) 1 of a process which is the first process to be performed among processes to be scheduled, and data representing the contents of in-process / intermediate work (simulation start) Sometimes there is an initial stock) 2. First, data 1 is input (S1
01), this is stored in the storage medium (for example, semiconductor memory) in the system (S102). Then, data 2 is input (S103) and stored in the memory (S103).
104). In addition to the above-mentioned input data, this memory stores the inventory contents (inventory location, details, etc.) and the operating status (in-process materials of each process) associated with the processing after the simulation is started.

【0010】ついで、入力されたデータに基づいてシミ
ュレーションが実行される(S105)。この処理は、
造管スケジュールまたはスケジューリング機能で選択し
た選択材の内容が伝達され、これと個々の材料の設備能
率値、実働値、そして組み替え時間表などから稼働時
間、段取り時間の計算及び次処理完了工程の決定を行う
工程稼働による時間経過を管理するものである。ここで
実行されたシミュレーション結果は、その完了に伴って
在庫、処理の変化がメモリに登録される(S106)。
この登録内容としては、在庫の場所、明細を示す在庫内
容と各工程の処理中材料を示す稼働状況である。
Then, a simulation is executed based on the input data (S105). This process is
The content of the selected material selected by the pipe making schedule or scheduling function is transmitted, and the operating time and setup time are calculated and the next processing completion process is determined from the equipment efficiency value, the actual operation value, and the recombination time table of each material. It manages the passage of time due to the operation of the process. As for the simulation result executed here, the inventory and the change in processing are registered in the memory upon completion of the simulation (S106).
The registered contents are the location of the stock, the contents of the stock showing the details, and the operating status showing the material being processed in each process.

【0011】さらに、メモリの格納内容を参照してスケ
ジューリングが行われる(S107)。このスケジュー
リングは、メモリに格納された在庫内容と稼働状況とを
参照して在庫の中から次処理材を選択するものである。
このような選択を行うために、スケジューリングの対象
となる工程毎に納期、ロット制約を考慮したルールを所
持する。なお、スケジューリングの対象が無くなった場
合(S108)には、処理を終了する。
Further, scheduling is performed with reference to the contents stored in the memory (S107). In this scheduling, the next processing material is selected from the inventory by referring to the inventory content and operation status stored in the memory.
In order to make such a selection, a rule in consideration of delivery date and lot constraint is possessed for each process to be scheduled. It should be noted that when there are no more scheduling targets (S108), the process is terminated.

【0012】図2は本発明によるスケジューリング及び
シミュレーションの実行に伴うタイミングを示すタイミ
ングチャートである。
FIG. 2 is a timing chart showing timings associated with execution of scheduling and simulation according to the present invention.

【0013】図2においては、スケジューリングの対象
となる工程が縦軸にとられ、時間が横軸にとられてい
る。横軸下の△印は造管や焼鈍、そして冷牽などの工程
の或る材料の処理終了時、すなわち本発明によるシミュ
レータが工程状況を把握する時点である。
In FIG. 2, the vertical axis represents the process to be scheduled and the horizontal axis represents time. The mark Δ on the horizontal axis indicates the end of processing of a certain material in the steps of pipe making, annealing, cold drafting, etc., that is, the time when the simulator according to the present invention grasps the process status.

【0014】図の例では、造管工程は造管スケジュール
のデータの並び順に処理を実行しており、まず、製造ナ
ンバー「4231−1」の作業時間a21が計算され、
a21だけ時間が進むと次の製造ナンバー「4231−
2」との寸法などの諸元値の差から段取替時間a11を
計算する。次に、a11だけ時間が進むと、製造ナンバ
ー「4231−2」の作業時間a22が計算され、a2
2だけ時間が進むと、次の製造ナンバー「4235−
1」との諸元値の差から段取替時間を計算する。諸元値
に差が無い場合、0時間だけ時間が進み、製造ナンバー
「4235−1」の作業時間a23が計算され、a23
だけ進むと次の製造ナンバー「4240−1」との諸元
値の差から段取替時間を計算する。計算した段取替時間
だけ時間が進むと、製造ナンバー「4240−1」の作
業時間a24が計算され、24だけ時間が進むと次の製
造ナンバー「4240−2」との諸元値の差から段取替
時間a12を計算する。さらに、a12だけ時間が進む
と、製造ナンバー「4240−2」の作業時間a25が
計算され、a25だけ時間が進むと、以降、同様の手順
で造管工程の稼働、段取替、休止が行われる。
In the example of the figure, in the pipe making process, the processes are executed in the order in which the data of the pipe making schedule is arranged. First, the working time a21 of the manufacturing number "4231-1" is calculated,
If the time advances by a21, the next manufacturing number "4231-
The setup change time a11 is calculated from the difference between the specification value such as "2" and the dimension value. Next, when the time advances by a11, the working time a22 of the manufacturing number "4231-2" is calculated, and a2
If the time advances by 2, the next manufacturing number "4235-
The setup change time is calculated from the difference between the specification value and "1". If there is no difference in the specification values, the time advances by 0 hours, the working time a23 of the manufacturing number “4235-1” is calculated, and a23
If it advances only by, the setup change time is calculated from the difference of the specification value with the next manufacturing number "4240-1". When the time advances by the calculated setup change time, the working time a24 of the manufacturing number “4240-1” is calculated, and when the time advances by 24, the difference in the specification value with the next manufacturing number “4240-2” is calculated. The setup change time a12 is calculated. Further, when the time advances by a12, the working time a25 of the manufacturing number “4240-2” is calculated, and when the time advances by a25, the pipe making process operation, setup change, and suspension are performed in the same procedure. Be seen.

【0015】ステップ105のシミュレーションの実行
によって、選択材を処理する工程についての稼働時間及
び段取り時間の計算、及び次処理完了工程の決定がなさ
れると、メモリに対して処理完了に伴う在庫、処理の変
化登録が行われる(S106)。以上説明したステップ
105〜107の処理が任意のシミュレーション終了時
間まで周期的に実行されることにより、各工程のスケジ
ュール、材料毎の通過工程予定時刻、工程別在庫量の推
移、ならびに各工程の稼働統計の結果が予測される。
When the simulation of step 105 is performed to calculate the operating time and setup time for the process for processing the selected material and to determine the next process completion process, the inventory and process associated with the process completion are stored in the memory. Change registration is performed (S106). The processes of steps 105 to 107 described above are periodically executed until an arbitrary simulation end time, so that the schedule of each process, the scheduled time of the passing process for each material, the transition of the stock amount by process, and the operation of each process The results of the statistics are predicted.

【0016】次に、焼鈍工程では、まず、造管工程の製
造ナンバー「4231−1」と同様にシミュレーション
開始時点でメモリ内のデータを参照し、焼鈍工程の選択
ルールに従って製造ナンバー「3888−1」を選択
し、作業時間b21が計算され、b21だけ時間が進
む。ついで、変更されたメモリ内データを参照し、焼鈍
工程の選択ルールに従って製造ナンバー「3890−
1」を選択し、前の製造ナンバー「3888−1」との
温度、寸法などの諸元値の差から段取替時間b11を計
算する。次に、b11だけ時間が進むと、製造ナンバー
「3890−1」の作業時間b22が計算され、b22
だけ時間が進む。ついで、変更されたメモリ内のデータ
を参照し、焼鈍工程の選択ルールに従って製造ナンバー
「3890−2」を選択し、前の製造ナンバー「389
0−1」との諸元値の差から段取替時間を計算する。
Next, in the annealing step, first, like the manufacturing number "4231-1" in the pipe making step, the data in the memory is referred to at the time of starting the simulation, and the manufacturing number "3888-1" is used in accordance with the selection rule of the annealing step. Is selected, the working time b21 is calculated, and the time advances by b21. Next, referring to the changed in-memory data, the manufacturing number "3890-
1 ”is selected, and the setup change time b11 is calculated from the difference between the previous manufacturing number“ 3888-1 ”and the specification values such as temperature and dimensions. Next, when the time advances by b11, the working time b22 of the manufacturing number "3890-1" is calculated, and
Only time advances. Then, referring to the changed data in the memory, the manufacturing number "3890-2" is selected according to the selection rule of the annealing process, and the manufacturing number "389" before is selected.
The setup change time is calculated from the difference between the specification values of "0-1".

【0017】次に、計算した段取替時間だけ時間が進む
と、製造ナンバー「3890−2」の作業時間b23が
計算され、b23だけ時間が進む。さらに、変更された
メモリ内のデータを参照し、焼鈍工程の選択ルールに従
って製造ナンバー「4231−1」を選択し、前の製造
ナンバー「3890−2」との諸元値の差から段取替時
間b12を計算する。ついで、b12だけ時間が進む
と、製造ナンバー「4231−1」の作業時間b24が
計算され、b24だけ時間が進む。以降、同様の手順で
焼鈍工程の稼働、段取替、休止が行われる。
Next, when the time advances by the calculated setup change time, the working time b23 of the manufacturing number "3890-2" is calculated, and the time advances by b23. Further, referring to the changed data in the memory, the manufacturing number "4231-1" is selected according to the selection rule of the annealing process, and the setup change is performed from the difference in the specification value from the previous manufacturing number "3890-2". Calculate time b12. Then, when the time advances by b12, the working time b24 of the manufacturing number "4231-1" is calculated, and the time advances by b24. After that, the annealing process is started, set up, and stopped in the same procedure.

【0018】次に、冷牽工程では、まず、造管工程の製
造ナンバー「4231−1」と同様にメモリ内のデータ
を参照し、冷牽工程の選択ルールに従って製造ナンバー
「4421−1」を選択し、作業時間c21が計算さ
れ、c21だけ時間が進む。ついで、変更されたメモリ
内データを参照し、当工程の在庫が無い場合、材欠とし
て材料が別の工程から1個が送られる。または、任意の
数量以上になる時刻まで休止する。こののち、その時刻
で変更されたメモリ内のデータを参照し、冷牽工程の選
択ルールに従って製造ナンバー「3850−1」を選択
し、前の製造ナンバー「4421−1」との寸法などの
諸元値の差から段取替時間c11を計算する。ついで、
c11だけ時間が進むと、製造ナンバー「3850−
1」の作業時間c22が計算され、c22だけ時間が進
む。以後、同様にして冷牽工程の稼働、段取替、休止が
行われる。以上のような処理は、スケジューリングの対
象となる工程すべてについて△印の時点で行われる。
Next, in the cold drafting process, first, like the production number "4231-1" of the pipe making process, the data in the memory is referred to, and the production number "4421-1" is selected according to the selection rule of the cold drafting process. When selected, the working time c21 is calculated, and the time advances by c21. Next, referring to the changed data in the memory, if there is no stock in this step, one piece of material is sent from another step as a lack of material. Or pause until the time when the quantity exceeds a certain amount. After that, referring to the data in the memory changed at that time, the manufacturing number "3850-1" is selected according to the selection rule of the cooling and drafting process, and the dimensions such as the dimensions of the previous manufacturing number "4421-1" are selected. The setup change time c11 is calculated from the difference between the original values. Then,
When the time advances by c11, the manufacturing number "3850-
The working time c22 of "1" is calculated, and the time advances by c22. After that, the cold drafting process is operated, set up, and stopped in the same manner. The above-described processing is performed at the time point marked with Δ for all the processes to be scheduled.

【0019】図3は図2中にある△印の時点で実行され
る各工程のロジックの内、焼鈍工程における処理例であ
る。
FIG. 3 shows an example of processing in the annealing step in the logic of each step executed at the time point marked with Δ in FIG.

【0020】まず、シミュレーション開始時または焼鈍
工程における或る材料の処理が終了した時点で、焼鈍工
程に在庫があれば、メモリ内のデータを参照する。在庫
が無い場合、材欠として材料が別の工程から1個が送ら
れる。或は、任意の数量以上になる時刻まで休止する。
メモリには、データ1とデータ2(S101及びS10
3で入力)の稼働状況を表す完了ロットが登録される。
図3の例では、在庫内容301は、左端の縦列の1),
2),3)・・・が処理の対象となるロット(材料)を
表し、そのロット毎の処理方法や寸法などの明細が、右
端に順次記載の温度ランク、ロットナンバー、温度、外
径、肉厚、工程納期である。例えば、1)のロットの場
合、焼鈍工程では温度ランクは高温の部類に属し、ロッ
トナンバーは「0810」、処理温度は摂氏920度、
処理速度は16.0メートル/分、外径は50.8m
m、肉厚は1.5mm、工程納期は10月1日であるこ
とを示している。また、稼働状況を表す完了ロット30
2は、焼鈍工程において最も最近に処理されたロットを
意味する。例示した完了ロットでは、温度ランクは高
温、ロットナンバーは「0792」、処理温度は摂氏9
20度、処理速度は16.0メートル/分、外径は4
2.7mm、肉厚は2.6mm、工程納期は10月1日
であることを示している。これらの301の在庫内容と
302の稼働状況とを参照し、選択ルール303に従っ
て選択ロット304を選択する(S107)。
First, if there is a stock in the annealing process at the start of the simulation or when the processing of a certain material in the annealing process is completed, the data in the memory is referred to. If there is no stock, one piece is sent from another process as a shortage. Alternatively, it pauses until the time when the number exceeds an arbitrary number.
Data 1 and data 2 (S101 and S10) are stored in the memory.
The completed lot representing the operating status (input in 3) is registered.
In the example of FIG. 3, the inventory content 301 is 1) in the leftmost column,
2), 3) ... represent lots (materials) to be processed, and details of the processing method and dimensions for each lot are listed at the right end in order of temperature rank, lot number, temperature, outer diameter, The thickness and delivery date of the process. For example, in the case of the lot of 1), the temperature rank in the annealing step belongs to the high temperature category, the lot number is “0810”, the processing temperature is 920 degrees Celsius,
Processing speed is 16.0 m / min, outer diameter is 50.8 m
m, the wall thickness is 1.5 mm, and the process delivery date is October 1st. In addition, the completed lot 30 that indicates the operating status
2 means the most recently processed lot in the annealing process. In the illustrated completed lot, the temperature rank is high, the lot number is "0792", and the processing temperature is 9 degrees Celsius.
20 degrees, processing speed 16.0 m / min, outer diameter 4
It shows that the thickness is 2.7 mm, the wall thickness is 2.6 mm, and the process delivery date is October 1st. The selected lot 304 is selected according to the selection rule 303 with reference to the inventory contents of 301 and the operation status of 302 (S107).

【0021】図3の例では、焼鈍工程においては、完了
ロット302に対し、温度ランク、ロットナンバー、処
理温度、処理速度、外径、肉厚が同一で、工程納期が最
小のロットのときに優先順位が1番高くなる。また、温
度ランクから外径までが同一で肉厚が最小であれば第2
優先順位になり、肉厚及び工程納期が最小で他が同一で
あれば第3優先順位になる。これらの他、焼鈍工程の高
温モードにおける選択ルールが選択され、優先順位が最
も下位で高温モードの仕掛かりが無い場合、低温モード
の選択ルールに切り換える。また、低温モードの仕掛か
りも無い場合、材欠休止にする。301のような在庫内
容及び302のような完了ロットの場合、選択されるロ
ットは、温度ランクが同じ高温、ロットナンバーは「0
792」、速度が16.0メートル/分であり、かつ外
径が最も大きな47.0mmになる3)のロットであ
り、優先順位3のルールが選択される。
In the example of FIG. 3, in the annealing process, when the completed lot 302 has the same temperature rank, lot number, processing temperature, processing speed, outer diameter, and wall thickness, and the process delivery time is the smallest, Priority is the highest. If the temperature rank to the outer diameter are the same and the wall thickness is the minimum, the second
It becomes the priority order, and if the thickness and the delivery date of the process are the smallest and the others are the same, the third priority order is given. In addition to these, when the selection rule in the high temperature mode of the annealing process is selected and the priority is the lowest and there is no work in progress in the high temperature mode, the selection rule is switched to the low temperature mode. If there is no work in progress in the low temperature mode, the material shortage is stopped. In the case of an inventory content such as 301 and a completed lot such as 302, the selected lot has a high temperature with the same temperature rank and the lot number is “0”.
792 ", the speed is 16.0 m / min, and the outer diameter is 47.0 mm, which is the largest 3) lot, and the rule of priority 3 is selected.

【0022】次に、選択されたロットが所持している重
量、寸法などと、305のT/Hr(能率)、実働率か
ら作業時間が計算され、完了ロット302と選択ロット
304の寸法などの諸元値の差、及び306の組替所要
時間表・式から段取り替え時間が計算される(S10
5)。これらの作業時間と段取替時間から完了時刻を計
算し、これおをメモリに登録する。また、選択したロッ
トを処理中ロットとして登録し、完了ロットを次の工程
の前面在庫として登録変更を行う(S106)。以上の
処理が終了すると、次の完了工程を探し、時間を進め、
焼鈍工程と同じ手順でその工程の選択ルールに従ってロ
ット選択及び作業時間、段取替時間の計算などをシミュ
レーション終了まで繰り返し実行する。
Next, the working time is calculated from the weight and size possessed by the selected lot, the T / Hr (efficiency) of 305, and the actual operation rate, and the dimensions of the completed lot 302 and the selected lot 304 are calculated. The setup change time is calculated from the difference between the specification values and the change time table / expression of 306 (S10).
5). Completion time is calculated from these work time and setup change time, and this is registered in the memory. Further, the selected lot is registered as the in-process lot, and the completed lot is registered and changed as the front stock of the next process (S106). When the above process is completed, look for the next completed process, advance the time,
In the same procedure as the annealing process, lot selection and calculation of work time and setup change time are repeatedly executed according to the selection rule of the process until the end of the simulation.

【0023】[0023]

【発明の効果】以上説明した通り、この発明は、スケジ
ューリングの対象となる工程の稼働による時間経過管理
をシミュレーションし、これにより得られた在庫内容及
び稼働状況を記憶媒体に登録し、この登録内容を参照し
て工程毎に納期やロット制約を考慮した固有のルールに
従って工程毎の在庫内容と完了材とに基づいて次に処理
する材料を選択してスケジューリングを行うようにした
ので、スケジューリングの対象となる全工程について高
精度な作業スケジューリングを短時間に得ることができ
る。
As described above, according to the present invention, the elapsed time management due to the operation of the process to be scheduled is simulated, and the inventory contents and the operation status obtained thereby are registered in the storage medium. The scheduling target is selected because the material to be processed next is selected based on the stock content and completed material of each process according to the unique rules that take into account the delivery date and lot constraint for each process. Therefore, highly accurate work scheduling can be obtained in a short time for all the processes.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の作業スケジューリング方法の処理を示
すフローチャートである。
FIG. 1 is a flowchart showing a process of a work scheduling method according to the present invention.

【図2】本発明によるスケジューリング及びシミュレー
ションの実行に伴うタイミングを示すタイミングチャー
トである。
FIG. 2 is a timing chart showing timings associated with execution of scheduling and simulation according to the present invention.

【図3】図2中にある△印の時点で実行される各工程の
ロジックのうち、焼鈍工程における処理例である。
FIG. 3 is an example of processing in an annealing step in the logic of each step executed at the time point marked with Δ in FIG.

───────────────────────────────────────────────────── フロントページの続き (72)発明者 磯村 一弘 千葉県君津市君津1番地 新日本製鐵株式 会社君津製鐵所内 ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor Kazuhiro Isomura 1 Kimitsu, Kimitsu-shi, Chiba Nippon Steel Corp. Kimitsu Works Ltd.

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 スケジューリングの対象となる工程の稼
働による時間経過管理をシミュレーションし、これによ
り得られた在庫内容及び稼働状況を記憶媒体に登録し、
この登録内容を参照して工程毎に納期やロット制約を考
慮した固有のルールに従って工程毎の在庫内容と完了材
とに基づいて次に処理する材料を選択してスケジューリ
ングを行うことを特徴とする作業スケジューリング方
法。
1. A simulation of time lapse management due to the operation of a process to be scheduled, and the inventory contents and operation status obtained by the simulation are registered in a storage medium,
It is characterized by selecting the material to be processed next based on the inventory content and completed material of each process according to a unique rule considering the delivery date and lot constraint for each process with reference to this registered content Work scheduling method.
JP10398392A 1992-03-31 1992-03-31 Work scheduling method Pending JPH05282320A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP10398392A JPH05282320A (en) 1992-03-31 1992-03-31 Work scheduling method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP10398392A JPH05282320A (en) 1992-03-31 1992-03-31 Work scheduling method

Publications (1)

Publication Number Publication Date
JPH05282320A true JPH05282320A (en) 1993-10-29

Family

ID=14368554

Family Applications (1)

Application Number Title Priority Date Filing Date
JP10398392A Pending JPH05282320A (en) 1992-03-31 1992-03-31 Work scheduling method

Country Status (1)

Country Link
JP (1) JPH05282320A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0850613A (en) * 1994-08-04 1996-02-20 Mitsubishi Electric Corp Production schedule preeparation supporting device
JP2005524165A (en) * 2002-04-30 2005-08-11 アドバンスト・マイクロ・ディバイシズ・インコーポレイテッド Agent-responsive scheduling in an automated manufacturing environment.
JP2010077454A (en) * 2008-09-24 2010-04-08 Jfe Steel Corp Method and apparatus for planning order of charging into heat-treatment furnace

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03161250A (en) * 1989-11-16 1991-07-11 Nec Corp Production scheduling device

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03161250A (en) * 1989-11-16 1991-07-11 Nec Corp Production scheduling device

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0850613A (en) * 1994-08-04 1996-02-20 Mitsubishi Electric Corp Production schedule preeparation supporting device
JP2005524165A (en) * 2002-04-30 2005-08-11 アドバンスト・マイクロ・ディバイシズ・インコーポレイテッド Agent-responsive scheduling in an automated manufacturing environment.
JP2010077454A (en) * 2008-09-24 2010-04-08 Jfe Steel Corp Method and apparatus for planning order of charging into heat-treatment furnace

Similar Documents

Publication Publication Date Title
JPH09153090A (en) Method and device for forming working process production plan
KR20000076601A (en) Method and apparatus for forming a production plan
US20070117230A1 (en) Computer readable storage medium for work-in-process schedules
JP2007061870A (en) Device and method for preparing rolling schedule, computer program and computer readable storage medium
CN113031542A (en) Semiconductor production line dynamic scheduling method based on load balancing
JP2007079663A (en) Production operation planning apparatus and production operation plan evaluation apparatus
CN104915721B (en) Order production cycle and the measuring method of yield
Gan et al. Scheduling of flexible-sequenced process plans in a mould manufacturing shop
CN100394417C (en) Regular scheduling method with state and performance feedback and its scheduling system
JPH05282320A (en) Work scheduling method
US5523952A (en) Production progress control method
JPH1050571A (en) Method and device for controlling production
JPH02185351A (en) Preparing device for manufacturing plan
JPH02130678A (en) Manufacture plan preparing device
JPH05307552A (en) Work scheduling method
KR20150108159A (en) ACTIVE nD CONSTRUCTION SCHEDULE MANAGING METHOD
JPH11282923A (en) Circulation type production process schedule planning method
JP2869991B2 (en) Production instruction method and device in FMS line
JPH10135096A (en) Scheduling method in semiconductor manufacture
JPH03161250A (en) Production scheduling device
TW200412518A (en) Front end dispatching method and system for long batch processing equipment in semiconductor manufacturing
JPH07168881A (en) Work control system
JP2957561B1 (en) Production line management method
JP2859402B2 (en) How to make a casting schedule
JP2005031794A (en) Scheduling method taking tool change into consideration

Legal Events

Date Code Title Description
A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 19980113