JPH05280054A - Reinforcement soil method and device of plate anchor type for double shut embankment - Google Patents

Reinforcement soil method and device of plate anchor type for double shut embankment

Info

Publication number
JPH05280054A
JPH05280054A JP10235392A JP10235392A JPH05280054A JP H05280054 A JPH05280054 A JP H05280054A JP 10235392 A JP10235392 A JP 10235392A JP 10235392 A JP10235392 A JP 10235392A JP H05280054 A JPH05280054 A JP H05280054A
Authority
JP
Japan
Prior art keywords
plate anchor
soil
sand
sheet pile
double
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP10235392A
Other languages
Japanese (ja)
Inventor
Goro Kuno
悟郎 久野
Tsunetaro Iwabuchi
常太郎 岩淵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NIPPON KENSETSUGIYOU KEIEI KYOKAI
Daito Kogyo Co Ltd
Original Assignee
NIPPON KENSETSUGIYOU KEIEI KYOKAI
Daito Kogyo Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NIPPON KENSETSUGIYOU KEIEI KYOKAI, Daito Kogyo Co Ltd filed Critical NIPPON KENSETSUGIYOU KEIEI KYOKAI
Priority to JP10235392A priority Critical patent/JPH05280054A/en
Publication of JPH05280054A publication Critical patent/JPH05280054A/en
Pending legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

PURPOSE:To suppress effectively the shearing deformation of the soil and sand as stopping, enhance the stability of the constructed embankment and also the reliance upon the works executed, and save the costs of executing works to a great extent. CONSTITUTION:Sheet piles are driven parallel in two rows 1, 2 to build double structural sheet pile works, and the upper parts of the two rows are coupled by tie rods 3. The space between these rows of sheet piles is filled with the soil and sand S as stopping, and in the under-part inside of one of the sheet pile rows 1, a plate anchor 5 is embedded being oriented as against the direction in which the soil and sand deforms. This plate anchor is tied by a wire rope 6 with the over-part of the other sheet pile row 2 so as to suppress the shearing deformation X of the soil and sand. Thus plate anchor type reinforcement soil devices 5, 6 are installed and constructed. When the double shut embankment is to be dismantled, the plate anchor 5 is removed and collected using the wire rope 6. The plate anchor 5 is equipped with a plurality of check plates 5a, 5b which are arranged against the direction in which the soil and sand as stopping makes compressive and shearing deforomation.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、海、河川中に各種の構
造物を築造する際に、その構造物の基礎周辺を周囲水域
から隔離するために施工される二重締切堤のプレートア
ンカー式補強土工法及び装置に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a plate anchor for a double cut-off wall, which is constructed to separate the foundation of the structure from surrounding water when constructing various structures in the sea or river. Type reinforced earth construction method and device.

【0002】[0002]

【従来の技術】上記の二重締切堤は、一般に深い水中に
大規模な堤体を構築する際に採用される。例えば、図5
に示すように海底、河川床Gに鋼矢板を間隔を置き2連
に打設して矢板列1,2に建て込み、矢板列1,2の上
部間をタイロツド3で連結し、矢板列1,2間に土砂を
充填して中詰土砂S層を形成し二重締切りの堤体に構築
するとともに、矢板列2内側の水位を徐々に低下させる
につれ段階的に切梁、腹起しなどが設置されている。
2. Description of the Related Art The above-mentioned double cut-off dam is generally adopted when constructing a large-scale dam body in deep water. For example, in FIG.
As shown in Fig. 2, steel sheet piles are laid in two rows at intervals on the seabed and the river bed G and built in the sheet pile rows 1 and 2, and the upper portions of the sheet pile rows 1 and 2 are connected by the tie rod 3 to form the sheet pile row 1 , Soil layer is filled between 2 to form a medium-filled sediment S layer to build a double cut-off levee body, and as the water level inside the sheet pile row 2 is gradually decreased, the beams and bellows are gradually raised. Is installed.

【0003】前記の二重締切堤は、図5に示すように中
詰土砂Sの土圧と残留水圧Psw、地盤の土圧(受働土
圧)Pe、水圧Pw、さらにタイロツド3の張力等の荷
重が加わり、矢板列1,2及び中詰土砂Sが一体となつ
て外力に抗する一種の複合構造体となる。また、この堤
体の安定性は中詰土砂Sの剪断強度に大きく左右される
ので、その中詰土砂には大きな剪断強度が期待できる粒
度配合の良好な砂、砂利が適用される。従って、浚渫
土、掘削土等の粘性土が混入された場合、その中詰土砂
の内部摩擦角が極端に低下して剪断強度が大幅に減少
し、中詰土砂の自重による圧縮変形や偏荷重による剪断
変形が容易となる。即ち水圧の変動、堤体内側の水抜き
や掘削等による外圧変動等により容易に変形されて、こ
の堤体は容易に破壊される不安定なものとなる。例え
ば、図示右側の水抜きにより左側の水圧Pw が偏荷重に
なると、中詰土砂Sが矢示方向に剪断変形されて点線の
ように転倒し易くなる。前記堤体には、必要に応じて随
時にさらに鋼矢板を打設したり、矢板列の下部に置砂を
配置したり、あるいは切梁により補強するなどの安定策
が施されている。
As shown in FIG. 5, the above-mentioned double cut-off dike includes the earth pressure and residual water pressure Psw of the earth and sand S, the earth pressure (passive earth pressure) Pe of the ground, the water pressure Pw, and the tension of the tie rod 3 and the like. When the load is applied, the sheet pile rows 1 and 2 and the filling sand S are integrated to form a kind of composite structure that resists external force. Further, since the stability of the bank body is greatly influenced by the shear strength of the medium soil S, sand or gravel having a good grain size combination that is expected to have high shear strength is applied to the medium soil. Therefore, when cohesive soil such as dredged soil or excavated soil is mixed, the internal friction angle of the inner filling material is extremely reduced and the shear strength is greatly reduced, and the compressive deformation and uneven load due to the self-weight of the inner filling material Shear deformation due to is easy. That is, it is easily deformed by fluctuations in water pressure, fluctuations in external pressure due to drainage of water inside the bank, excavation, etc., and this bank becomes unstable and easily destroyed. For example, when the water pressure Pw on the left side becomes an unbalanced load due to drainage on the right side in the figure, the inner filling soil S is sheared and deformed in the direction of the arrow and easily falls as indicated by the dotted line. If necessary, the bank body is provided with a stabilizing measure such as further placing a steel sheet pile, arranging sand in the lower part of the sheet pile row, or reinforcing it with a cutting beam.

【0004】[0004]

【発明が解決しようとする課題】従来の二重締切堤は、
その堤体安定のために中詰土砂として大きな剪断強度が
期待できる粒度配合の良好な砂、砂利が必要となるが、
この堤体が仮設構造物である点を考慮すると、浚渫土、
掘削土等の現地調達可能な土砂を中詰土砂として使用
し、経済的に有利な施工を行なうことが望まれている。
しかし、これは堤体の安定性に問題が生じる。
SUMMARY OF THE INVENTION The conventional double breakwater is
In order to stabilize the levee body, it is necessary to use sand and gravel with a good grain size mixture that can be expected to have a large shear strength as medium-filled soil.
Considering that this levee body is a temporary structure, dredged soil,
It is desired to use economically advantageous construction by using locally procurable earth and sand such as excavated soil as the medium earth and sand.
However, this causes a problem in the stability of the bank.

【0005】本発明は、前記のような課題に対処するた
めに開発されたものであつて、その目的とする処は、中
詰土砂の剪断変形を効果的に抑制して、その堤体の安定
性、施工信頼性を向上し大幅な施工コストの節減を可能
にした二重締切堤のプレートアンカー式補強土工法及び
装置を提供するにある。
The present invention was developed in order to address the above-mentioned problems, and the object of the present invention is to effectively suppress the shear deformation of the medium-filled earth and sand, and (EN) It is an object to provide a plate anchor type reinforced earth work method and device for a double cut-off dam, which improves stability and construction reliability and enables significant reduction in construction costs.

【0006】[0006]

【課題を解決するための手段】本発明は、矢板を平行2
連に打設して二重の矢板列に建て込み、両矢板列の上部
間をタイロツドで連結して、両矢板列の間に中詰土砂を
充填するとともに、一方の矢板列の内側下部にプレート
アンカーを中詰土砂の変形方向に対向させて埋設し、同
プレートアンカーと他方の矢板列の上部間をワイヤロー
プで連結して中詰土砂の剪断変形を抑制するプレートア
ンカー式補強土装置として組み込み構築することによ
り、さらに、その二重締切堤の解体に際し前記ワイヤロ
ープによりプレートアンカーを撤去して回収することに
より、堤体構築を容易にするとともに、中詰土砂の剪断
変形を効果的に抑制して堤体を安定せしめ、かつその撤
去、回収を容易にしている。
SUMMARY OF THE INVENTION In the present invention, a sheet pile is made into a parallel plate.
Pile them in a row and build them in a double sheet pile row, connect the upper parts of both sheet pile rows with tie rods, fill the space between the two sheet pile rows with sand and fill the lower part of the inside of one sheet pile row. As a plate anchor-type reinforced soil device that embeds plate anchors facing each other in the direction of deformation of the filled soil and connects the plate anchor and the upper part of the other sheet pile row with a wire rope to suppress shear deformation of the filled soil. The built-in construction further facilitates the construction of the dam body by removing the plate anchors by the wire rope and collecting them when dismantling the double-damage dike, and at the same time effectively shears and deforms the filling soil. It suppresses and stabilizes the bank, and facilitates its removal and recovery.

【0007】また、前記のプレートアンカー式補強土装
置において、前記中詰土砂の下部に埋設され同中詰土砂
の圧縮及び剪断の変形方向に対向して配置される複数枚
の抑止プレートを具備したプレートアンカーと、同プレ
ートアンカーと矢板列の上部間を連結するワイヤロープ
からなり、そのアンカー性能を高めて中詰土砂の剪断変
形の抑制性能、信頼性をさらに向上している。
Further, the plate anchor type reinforced soil device is provided with a plurality of restraining plates which are embedded in the lower portion of the intermediate filling soil and which are arranged so as to face each other in the deformation direction of compression and shear of the intermediate filling soil. It consists of a plate anchor and a wire rope that connects the plate anchor and the upper part of the sheet pile row. The anchor performance is enhanced to further improve the shear deformation suppression performance and reliability of the filled soil.

【0008】[0008]

【作用】平行2連の矢板列の建て込み、矢板列上部間の
タイロツド連結、中詰土砂の充填とともに、一方の矢板
列の内側下部にプレートアンカーを中詰土砂の変形方向
に対向させて埋設し、同プレートアンカーと他方の矢板
列の上部間をワイヤロープで連結して中詰土砂の剪断変
形を抑制するプレートアンカー式補強土装置として組み
込み、容易に二重締切堤に構築され、偏荷重等による中
詰土砂の剪断変形時に、そのプレートアンカーは強い土
圧を受けて優れたアンカー力を発揮し、そのアンカー力
はワイヤロープを介し他方の矢板列に中詰土砂の剪断変
形の抑制力として負荷され、中詰土砂の剪断変形が効果
的に抑制されその剪断強度が大幅に増加されて、その二
重締切堤の安定性及び施工信頼性が格段に向上されると
ともに、前記ワイヤロープによりプレートアンカーが容
易に撤去、回収される。
[Operation] Along with the construction of two parallel rows of sheet piles, connecting the tiles between the tops of the sheet pile rows, and filling of the middle filling soil, a plate anchor is embedded in the inner lower part of one of the sheet pile rows facing the deformation direction of the middle filling soil. Then, the plate anchor and the upper part of the other sheet pile row were connected with a wire rope and incorporated as a plate anchor-type reinforced soil device that suppresses shear deformation of the filled soil, and it was easily constructed on a double cut-off wall and had an unbalanced load. The plate anchor exerts an excellent anchoring force under the strong earth pressure during shearing deformation of the medium-filled earth and sand, and the anchoring force suppresses the shearing deformation of the middle-filled earth and sand to the other sheet pile row via the wire rope. As a result, the shear deformation of the medium soil is effectively suppressed, the shear strength is greatly increased, and the stability and construction reliability of the double levee are significantly improved. Plates anchor the rope easily removed and recovered.

【0009】また、前記プレートアンカーは、中詰土砂
の圧縮及び剪断の変形方向に対向して配置される複数枚
の抑止プレートを具備し、各抑止プレートは強い土圧を
受けて強力なアンカー力を発揮し中詰土砂の剪断変形の
抑制性能、信頼性がさらに高められる。
Further, the plate anchor comprises a plurality of restraining plates arranged so as to face each other in the compressing and shearing deformation directions of the filled soil, and each restraining plate receives a strong earth pressure and has a strong anchoring force. It further enhances the performance of suppressing the shear deformation of the filled sand and the reliability.

【0010】[0010]

【実施例】図1に本発明の二重締切堤のプレートアンカ
ー式補強土工法及び装置の一実施例、図2(A)(B)
にプレートアンカー式補強土装置の各実施例、図3に同
装置の作用、図4にプレートアンカーの各実施例を示
す。図中1,2は海底、河川床G等に矢板(鋼矢板)を
平行2連に打設して建て込まれた矢板列、3は矢板列
1,2の上部間を連結した鋼棒、ワイヤロープ等のタイ
ロツド、5は水平方向に指向される抑止プレート5aと
垂直方向に指向される抑止プレート5bを具備したプレ
ートアンカー、6はプレートアンカーと矢板列(鋼矢
板)上部との間に連設されたワイヤロープ、7はワイヤ
ロープの上端部の止着部材、Sは中詰土砂、5,6はプ
レートアンカー式補強土装置であつて、図1のように海
底あるいは河川床Gに矢板(鋼矢板)を導枠(図示省
略)に沿わせ精度良く平行2連に屏風打ちして水密性に
優れた二重の矢板列1,2に建て込み、矢板列1,2の
上部間を適宜間隔を置きタイロツド3で連結して、矢板
列1,2間に中詰土砂Sを充填するとともに、一方の矢
板列1の内側下部にプレートアンカー5を中詰土砂Sの
変形方向に対向させて埋設し、そのプレートアンカー5
と他方の矢板列2の上部との間を緊張状態のワイヤロー
プ6で連結して中詰土砂Sの剪断変形を抑制するプレー
トアンカー式補強土装置5,6として組み込み構築する
二重締切堤のプレートアンカー式補強土工法になつてい
る。
[Embodiment] FIG. 1 shows an embodiment of a plate anchor type reinforced earth construction method and apparatus for a double levee of the present invention, FIG. 2 (A) (B)
Fig. 3 shows each embodiment of the plate anchor type reinforced soil device, Fig. 3 shows the operation of the device, and Fig. 4 shows each embodiment of the plate anchor. In the drawing, reference numerals 1 and 2 denote a sheet pile row in which piles of steel sheet piles (steel sheet piles) are laid in parallel on the seabed or river bed G, and 3 is a steel rod connecting the upper portions of the sheet pile rows 1 and 2, Tie rods such as wire ropes, 5 is a plate anchor having a horizontally oriented restraining plate 5a and a vertically oriented restraining plate 5b, and 6 is a link between the plate anchor and the upper part of the sheet pile (steel sheet pile). A wire rope is installed, 7 is a fastening member at the upper end of the wire rope, S is a filling soil, 5 and 6 are plate anchor type reinforced earth devices, and a sheet pile is attached to the seabed or riverbed G as shown in FIG. (Steel sheet pile) is laid along a guide frame (not shown) with high precision in parallel folding screens and built into double sheet pile rows 1 and 2 with excellent watertightness, and between the upper portions of the sheet pile rows 1 and 2. Connect the tie rods 3 at appropriate intervals and fill the piles S between the sheet pile rows 1 and 2. As well as, embedded in the plate anchor 5 inside bottom of one sheet pile row 1 is opposed to the deformation direction of Chutsume sand S, the plate anchor 5
And the upper part of the other sheet pile row 2 are connected by a wire rope 6 in a tensioned state to suppress the shear deformation of the filling soil S and are incorporated as a plate anchor type reinforced soil device 5, 6 It is a plate anchor type reinforced earth method.

【0011】矢板列1,2の建込は、海底、河川床G等
の障害物、軟弱土等を除去して行われ、鋼矢板を堅牢な
導枠(ガイド)に沿わせ、好ましくは屏風打ちして精度
よく建て込み施工され、地盤の状態や締切り内部の水替
え、掘削等に対応させて所望の根入れ長さに打設され
る。また、矢板列1,2間に充填される中詰土砂Sに
は、大きい剪断強度が期待される粒度配合の良好な砂、
砂利が好適であるが、本発明ではその剪断変形が効果的
に抑制されるため、必要に応じて浚渫土や掘削土等が使
用可能となり、中詰土砂Sの充填とプレートアンカー式
補強土装置5,6の組込は並行して行われ、例えば、図
1のように図示右側を排水して掘削し、左側の水圧Pw
が偏荷重として負荷される場合、プレートアンカー5
は、矢板列1の内側下部の水底地盤Gあるいはその近傍
にて、その矢板列1に対し1m程度の間隔を置き、中詰
土砂Sの変形方向に対抗せしめ図示のように並行に配設
して中詰土砂S内に埋設され、そのプレートアンカー5
に連結したワイヤロープ6にプレロードLをかけて所望
の緊張力を付与した緊張状態とし、そのワイヤロープ6
の上端部を他方の矢板列2の上部に止着部材7で結合し
プレートアンカー式補強土装置5,6として組み込ま
れ、このプレートアンカー式補強土装置は、二重締切堤
の長さ方向に適宜間隔を置き多数並設される。ワイヤロ
ープ6上端部と矢板列2上部は、好ましくは中詰土砂S
層の剪断変形が最大となる中詰土砂Sの天端と最大水位
との間で止着される。
The piles of sheet piles 1 and 2 are built by removing obstacles such as the seabed and riverbed G, soft soil, etc., and the steel sheet piles are guided along a robust guide frame, preferably a folding screen. It is struck and built with high precision, and it is laid to the desired rooting length according to the condition of the ground, water changes inside the deadline, excavation, etc. In addition, the medium-filled earth and sand S filled between the sheet pile rows 1 and 2 is a good sand with a particle size mixture that is expected to have a large shear strength,
Gravel is preferable, but since shear deformation is effectively suppressed in the present invention, dredged soil, excavated soil, etc. can be used as needed, and filling of medium filling sand S and plate anchor type reinforced soil equipment are possible. The assembling of 5 and 6 is carried out in parallel. For example, as shown in FIG.
Is applied as an unbalanced load, the plate anchor 5
Is placed at a space of about 1 m with respect to the sheet pile row 1 at or near the water bottom ground G at the lower inner side of the sheet pile row 1 and arranged in parallel as shown in the figure so as to oppose the deformation direction of the filling sand S. Is buried in the middle filling soil S and its plate anchor 5
A preload L is applied to the wire rope 6 connected to the wire rope 6 to bring the wire rope 6 to a desired tension, and the wire rope 6
The upper end of the sheet pile is connected to the upper part of the other sheet pile row 2 by a fastening member 7 to be incorporated as plate anchor type reinforced soil devices 5 and 6. A large number are arranged in parallel at appropriate intervals. The upper end of the wire rope 6 and the upper part of the sheet pile row 2 are preferably filled with sand S
It is fixed between the top and the maximum water level of the middle filling soil S where the shear deformation of the layer is maximum.

【0012】プレートアンカー式補強土装置5,6は、
前記のようにプレートアンカー5、ワイヤロープ6等か
らなり、また、そのプレートアンカー5は、中詰土砂S
の圧縮変形及び剪断変形の方向への対向性を高める抑止
プレート5a,5b(図示垂直方向と水平方向)を具備
し、二重締切堤の規模等に対応して長さ1〜2m程度に
形成され、比較的に長い場合、図2(A)のようにプレ
ートアンカー5の前端縁部にワイヤロープ6の両端部を
適宜手段で間隔を置き連結して、その抑止プレート5
a,5bの埋設方向を安定せしめ、比較的に短い場合、
図2(B)のようにプレートアンカー5の前端縁部にワ
イヤロープ6の一端部を適宜手段で連結する。さらに、
図4(A)のように抑止プレート5aと抑止プレート5
bを十字状に連結した構造、図4(B)のように抑止プ
レート5aの一端部上に抑止プレート5bを連結した構
造、図4(C)のように抑止プレート5aの一端部に抑
止プレート5bの中間部を連結した構造、又は図4
(D)のように抑止プレート5aの中間部上に抑止プレ
ート5bを連結した構造等に構成され、中詰土砂S層の
土砂材や形状、規模等に対応させて適宜に選択して使用
される。
The plate anchor type reinforcing soil devices 5 and 6 are
As described above, the plate anchor 5, the wire rope 6, etc. are used.
It is equipped with restraint plates 5a, 5b (vertical direction and horizontal direction in the drawing) that enhance the opposition to the direction of compression deformation and shear deformation, and are formed to have a length of about 1 to 2 m according to the scale of the double levee. In the case of a relatively long length, both ends of the wire rope 6 are connected to the front end edge of the plate anchor 5 with an appropriate means, as shown in FIG.
Stabilize the embedding direction of a and 5b, and if relatively short,
As shown in FIG. 2B, one end of the wire rope 6 is connected to the front end edge of the plate anchor 5 by an appropriate means. further,
As shown in FIG. 4 (A), the inhibition plate 5a and the inhibition plate 5
b connected in a cross shape, a structure in which the inhibition plate 5b is connected on one end of the inhibition plate 5a as shown in FIG. 4B, and a inhibition plate at one end of the inhibition plate 5a as shown in FIG. 4C 5b is a structure in which the intermediate portions are connected, or FIG.
As shown in (D), the restraint plate 5a has a structure in which the restraint plate 5b is connected to the middle portion of the restraint plate 5a, and is appropriately selected and used in accordance with the earth and sand material, shape, scale, etc. of the middle layer of earth and sand S layer. It

【0013】前記のプレートアンカー式補強土装置5,
6は、偏荷重等による中詰土砂Sの剪断変形Xを抑制し
てその剪断強度を増大し、二重締切堤を安定せしめるた
めに組み込まれ、そのプレートアンカー5は、図1及び
図3に示すように左側の矢板列1内側の中詰土砂S下部
に埋設されて、中詰土砂の自重により強力な土圧を受け
その移動が効果的に拘束されて優れたアンカー力を発揮
する。例えば、図示右側を排水すると、左側の水圧Pw
等がその二重締切堤に偏荷重として負荷され、中詰土砂
Sが矢示方向に剪断変形Xされて堤体の転倒、破壊の原
因になるが、中詰土砂Sが剪断変形Xをし始めると、そ
のプレートアンカー5は、矢板列2の上部からワイヤロ
ープ6を介し矢示方向の引張力Tを受け、中詰土砂Sの
下部に深く埋設されて強い土圧を受けているため、図3
のように引張力Tの水平方向分力に対しては、垂直方向
の抑止プレート5bに作用する土圧Pbが反力となり、
引張力Tの垂直平方向分力に対しては、水平方向の変形
抑止プレート5aに作用する土圧Paが反力となり、そ
のプレートアンカー5は前記の強力な反力を受け、即ち
強力なアンカー力を発揮しワイヤロープ6を介し矢板列
2の傾倒を阻止して、中詰土砂Sの剪断変形Xを効果的
に抑制し中詰土砂Sの剪断強度を著しく増大する。ま
た、二重締切堤の内側で行われる水中工事等が終了する
と、その内部に水張りされて中詰土砂Sが取り出され、
ワイヤロープ6により各プレートアンカー5も順次に取
り出されて容易、迅速に撤収して回収され、タイロツ
ド、各矢板等も撤収される。
The above-mentioned plate anchor type reinforcing soil device 5,
6 is incorporated in order to suppress the shear deformation X of the filling soil S due to an unbalanced load or the like to increase the shear strength and stabilize the double levee, and the plate anchor 5 thereof is shown in FIGS. 1 and 3. As shown in the figure, it is buried in the lower part of the inner filling sand S inside the sheet pile 1 on the left side, receives a strong earth pressure due to its own weight, and its movement is effectively restrained to exert an excellent anchoring force. For example, if the right side of the drawing is drained, the left side water pressure Pw
Etc. is applied as an unbalanced load to the double levee, which causes shear deformation X of the middle sill sand S in the direction of the arrow, causing overturning and destruction of the levee body, but the middle sill sand S undergoes shear deformation X. When started, the plate anchor 5 receives a tensile force T from the upper portion of the sheet pile row 2 through the wire rope 6 in the direction of the arrow, and is deeply buried in the lower portion of the filling sand S to receive strong earth pressure, Figure 3
As described above, against the horizontal component of the tensile force T, the earth pressure Pb acting on the vertical restraining plate 5b becomes a reaction force,
The earth pressure Pa acting on the horizontal deformation suppressing plate 5a becomes a reaction force against the vertical force component of the tensile force T in the vertical direction, and the plate anchor 5 receives the strong reaction force, that is, the strong anchor. The force is exerted to prevent the sheet pile row 2 from being tilted through the wire ropes 6 to effectively suppress the shear deformation X of the filling soil S and significantly increase the shear strength of the filling soil S. In addition, when the underwater work done inside the double cut-off wall is completed, the inside is filled with water and the filled sand S is taken out.
The plate anchors 5 are also sequentially taken out by the wire rope 6, and can be easily and quickly withdrawn and collected, and the tie rods, sheet piles, etc. are also withdrawn.

【0014】上記のように中詰土砂の剪断強度が効果的
に増加されるため、大きい剪断強度が期待される粒度配
合の良好な砂、砂利に限らず、浚渫土や掘削土等を多く
使用しても、二重締切堤の剪断強度が確保されて優れた
安定性を有し、また、前記のプレートアンカー式補強土
装置は、二重締切堤の長さ方向に適宜間隔を置き配設さ
れてその堤体内に容易に組み込まれ、比較的に簡単な機
構となつて従来のような複雑な機構の安全策が不要にな
り、容易、迅速に施工されて大幅なコスト節減が可能と
なる等の利点を有する。
Since the shear strength of the medium-filled soil is effectively increased as described above, not only sand and gravel having a good grain size composition, which is expected to have high shear strength, but also dredged soil, excavated soil, etc. are used in large quantities. However, the shear strength of the double levee is ensured and it has excellent stability, and the plate anchor type reinforced soil device is arranged at appropriate intervals in the length direction of the double levee. It is easily installed in the levee body, and the relatively simple mechanism eliminates the need for a safety mechanism of the conventional complex mechanism, and it is easy and quick to construct, which enables significant cost savings. And so on.

【0015】前記のプレートアンカー式補強土装置は、
二重締切堤の規模や中詰砂等に対応させて図4に示すよ
うな各種のプレートアンカーが選択して使用されるとと
もに、必要に応じて複数のプレートアンカーを連結した
り、各矢板列の内側にそれぞれ併設して中詰土砂の2方
向の剪断変形を防止するなどの設計も可能である。
The plate anchor type reinforced soil device is
Various plate anchors such as those shown in Fig. 4 are selected and used according to the scale of the double cut-off bank and filling sand, etc., and a plurality of plate anchors can be connected or each sheet pile row can be used as required. It is also possible to design side by side to prevent shear deformation of the middle soil in two directions.

【0016】[0016]

【発明の効果】本発明は、前述のように平行2連の矢板
列の建て込み、矢板列上部間のタイロツド連結、中詰土
砂の充填とともに、中詰土砂の剪断変形を抑制するプレ
ートアンカー式補強土装置の組み込みにより容易に二重
締切堤に構築され、そのプレートアンカー式補強土装置
は、比較的に簡単な機構により二重締切堤内に容易に組
み込まれ、そのプレートアンカーは強力な土圧を受けそ
の移動が効果的に拘束されて優れたアンカー力を発揮
し、中詰土砂の剪断変形を効果的に抑制しその剪断強度
を大幅に増加してその堤体を安定せしめ、前記ワイヤロ
ープによりプレートアンカーが容易に撤去、回収され、
また、前記プレートアンカーの複数枚の抑止プレートに
よりさらに強力なアンカー力が発揮されて中詰土砂の剪
断変形の抑制性能、信頼性がさらに高められ、前記のよ
うに浚渫土や掘削土等の使用も可能となるなど、施工が
容易、迅速に遂行され二重締切堤の安定性、施工信頼性
に著しく向上されるとともに、大幅なコスト節減が可能
となる。
INDUSTRIAL APPLICABILITY As described above, according to the present invention, the plate anchor type is used for suppressing the shear deformation of the middle stuffed earth, as well as the construction of the parallel two rows of sheet piles, the tied connection between the upper parts of the piles, the filling of the middle stuffed soil. The reinforced soil device is easily built into the double levee, and the plate anchor type reinforced soil device is easily incorporated into the double levee by a relatively simple mechanism, and the plate anchor has strong earth pressure. The movement of the wire rope is effectively restrained and exerts an excellent anchoring force, which effectively suppresses the shear deformation of the filling soil and greatly increases its shear strength to stabilize the dam body, and the wire rope Allows the plate anchors to be easily removed and recovered,
Further, the plurality of restraint plates of the plate anchors exert a stronger anchoring force to further enhance the restraint performance and reliability of the shear deformation of the filled soil, and the use of dredged soil or excavated soil as described above. The construction is easy and quick, and the stability and construction reliability of the double cut-off dike are significantly improved, and significant cost savings are possible.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の二重締切堤のプレートアンカー式補強
土工法及び装置の一実施例を示す断面図
FIG. 1 is a cross-sectional view showing an embodiment of a plate anchor type reinforced earth method and device for a double cut-off dam of the present invention.

【図2】プレートアンカー式補強土装置の各実施例を示
す各斜視図(A)(B)
FIG. 2 is perspective views (A) and (B) showing examples of the plate anchor type reinforced soil device.

【図3】プレートアンカー式補強土装置の作用を説明す
る要部拡大断面図
FIG. 3 is an enlarged sectional view of an essential part for explaining the action of the plate anchor type reinforced soil device.

【図4】プレートアンカーの各実施例を示す各側視図
(A)〜(D)
FIG. 4 is a side view (A) to (D) showing each embodiment of the plate anchor.

【図5】二重締切り堤体の従来例を示す断面図である。FIG. 5 is a sectional view showing a conventional example of a double cut-off dam.

【符号の説明】[Explanation of symbols]

1,2 矢板列 3 タイロツド 5 プレートアンカー 5a,5b 抑止プレート 6 ワイヤロープ 5,6 プレートアンカー式補強土装置 S 中詰土砂 X 剪断変形 1, 2 Sheet pile row 3 Tirotod 5 Plate anchor 5a, 5b Restraint plate 6 Wire rope 5, 6 Plate anchor type reinforced soil device S Middle filling sand X Shear deformation

───────────────────────────────────────────────────── フロントページの続き (72)発明者 岩淵 常太郎 東京都千代田区三番町22−7 三番町関野 ビル3階 社団法人 日本建設業経営協会 内 ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor Tsunetaro Iwabuchi 22-7 Sanbancho, Chiyoda-ku, Tokyo Sanbancho Sekino Building 3rd Floor Japan Construction Industry Management Association

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 矢板を平行2連に打設して二重の矢板列
に建て込み、両矢板列の上部間をタイロツドで連結し
て、両矢板列の間に中詰土砂を充填するとともに、一方
の前記矢板列の内側下部にプレートアンカーを中詰土砂
の変形方向に対向させて埋設し、同プレートアンカーと
他方の前記矢板列の上部との間をワイヤロープで連結し
て中詰土砂の剪断変形を抑制するプレートアンカー式補
強土装置として組み込み構築することを特徴とする二重
締切堤のプレートアンカー式補強土工法。
1. Pile piles are piled in parallel to form double piles, and the upper portions of both piles are connected by a tie rod to fill the middle piles with sand. , Embedding a plate anchor in the lower part of the inside of one of the sheet pile rows so as to face the deformation direction of the filling soil, and connecting the plate anchor and the upper portion of the other sheet pile row with a wire rope Plate anchor type reinforced earth construction method for double anchorage, which is built as a plate anchor type reinforced earth device that suppresses shear deformation.
【請求項2】 請求項1記載の二重締切堤のプレートア
ンカー式補強土工法において、前記二重締切堤の解体に
際し前記ワイヤロープにより前記プレートアンカーを撤
去して回収することを特徴とする二重締切堤のプレート
アンカー式補強土工法。
2. The plate anchor type reinforced earth work method for a double dyke according to claim 1, wherein the plate anchor is removed by the wire rope when the double dyke is dismantled and recovered. Plate anchor type reinforced earth method for heavy dykes.
【請求項3】 請求項1又は請求項2記載の二重締切堤
のプレートアンカー式補強土工法に適用されるプレート
アンカー式補強土装置において、前記中詰土砂の下部に
埋設され同中詰土砂の圧縮及び剪断の変形方向に対向し
て配置される複数枚の抑止プレートを具備したプレート
アンカーと、同プレートアンカーと前記矢板列の上部と
の間に連結されるワイヤロープからなることを特徴とす
る二重締切堤のプレートアンカー式補強土装置。
3. A plate anchor type reinforced earth device applied to the plate anchor type reinforced earth method for a double levee according to claim 1 or 2, wherein the medium anchored earth and sand is buried under the middle stuffed earth and sand. A plate anchor having a plurality of restraint plates arranged to face each other in the deformation direction of compression and shear, and a wire rope connected between the plate anchor and the upper part of the sheet pile row. Double anchorage plate anchor type reinforced soil device.
JP10235392A 1992-03-30 1992-03-30 Reinforcement soil method and device of plate anchor type for double shut embankment Pending JPH05280054A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP10235392A JPH05280054A (en) 1992-03-30 1992-03-30 Reinforcement soil method and device of plate anchor type for double shut embankment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP10235392A JPH05280054A (en) 1992-03-30 1992-03-30 Reinforcement soil method and device of plate anchor type for double shut embankment

Publications (1)

Publication Number Publication Date
JPH05280054A true JPH05280054A (en) 1993-10-26

Family

ID=14325117

Family Applications (1)

Application Number Title Priority Date Filing Date
JP10235392A Pending JPH05280054A (en) 1992-03-30 1992-03-30 Reinforcement soil method and device of plate anchor type for double shut embankment

Country Status (1)

Country Link
JP (1) JPH05280054A (en)

Similar Documents

Publication Publication Date Title
JP4863268B2 (en) Bridge construction method and its bridge structure
AU2004101058A4 (en) Earth Retention and Piling Systems
JP4663541B2 (en) Seismic reinforcement method for existing concrete pier
JP7149919B2 (en) Improvement structure and improvement method of existing wharf
JP3448629B2 (en) Seismic retrofitting method for existing structure foundation
JP2016156147A (en) Construction method of anti-gigantic tsunami seacoast earth structure with highly rigid geosynthetic reinforced earth retaining wall having rigid integral wall surface
JPS6140914A (en) Erosion control dam and its construction
JP4188811B2 (en) Reinforced soil protection retaining wall
JP6292028B2 (en) Embankment reinforcement structure
JPH05280054A (en) Reinforcement soil method and device of plate anchor type for double shut embankment
JP3770665B2 (en) Ground improvement composite foundation
JP2018154997A (en) Wall body structure with filling material
JPH0913343A (en) Revetment structure and its construction method
JPH05280055A (en) Reinforcement soil method and device of plate anchor type for double shut embankment
JPH04302612A (en) Double sheet pile type cofferdam construction and plate anchor device for deformation inbition of fill-in sand
JP2020117959A (en) Levee body reinforcement structure
JPH01226921A (en) Earthquake-proof reinforced revetment construction
AU2012202472B2 (en) Earth Retention and Piling Systems
JP2876471B2 (en) Lateral flow countermeasure structure
JP7396331B2 (en) Improvement structure of existing quay wall and construction method of the improvement structure
JP7396332B2 (en) Improvement structure of existing quay wall and construction method of the improvement structure
JP7489350B2 (en) Improvement structure and method of existing wharf
JPH01226920A (en) Earthquake-proof construction of river embankment
JPH04228714A (en) Water area construction using member to be driven into water bottom ground
JP3678290B2 (en) High earthquake resistance foundation