JPH05246651A - Hoisting guide device for elevator guide rail - Google Patents

Hoisting guide device for elevator guide rail

Info

Publication number
JPH05246651A
JPH05246651A JP4935692A JP4935692A JPH05246651A JP H05246651 A JPH05246651 A JP H05246651A JP 4935692 A JP4935692 A JP 4935692A JP 4935692 A JP4935692 A JP 4935692A JP H05246651 A JPH05246651 A JP H05246651A
Authority
JP
Japan
Prior art keywords
guide rail
guide
pulley
roller
lifting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP4935692A
Other languages
Japanese (ja)
Inventor
Yoshio Nishida
善雄 西田
Katsuhiko Okabe
勝彦 岡部
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toshiba Corp
Toshiba Elevator and Building Systems Corp
Original Assignee
Toshiba Corp
Toshiba Elevator Technos KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toshiba Corp, Toshiba Elevator Technos KK filed Critical Toshiba Corp
Priority to JP4935692A priority Critical patent/JPH05246651A/en
Publication of JPH05246651A publication Critical patent/JPH05246651A/en
Pending legal-status Critical Current

Links

Abstract

PURPOSE:To erect a guide rail which obviates the need of the guiding work by an operator's hand when a guide rail to be connected is hoisted, and obviates the need of the guide work in the operation for shifting the guide rail which is hoisted to a prescribed height, to a prescribed position on an elevator passage wall, and improves the safety, by the easy operation. CONSTITUTION:A hoisting guide device is constituted of an installation plate 1 which can be installed on a working floor, pulley device 12 which is installed in the upper part of the installation plate 11, held in a nearly horizontal state, can be turned to the installation plate 11, side, and supports a pulley 18, and a guide roller device 13 which is installed on the lower part of the installation plate 11 and has a roller 23 engaged with the tooth flank of a guide rail.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、エレベータのガイドレ
ールの揚重用ガイド装置に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a lifting guide device for an elevator guide rail.

【0002】[0002]

【従来の技術】通常、エレベータは、図4に示すように
昇降路に、かご1,つり合い重り2が上昇,下降する際
それぞれをガイドするガイドレール3,4がそれぞれ一
対ずつ設けられている。このガイドレール3,4は、据
付時において、昇降路の下部より順に上方に立設され
る。
2. Description of the Related Art Generally, an elevator is provided with a pair of guide rails 3 and 4 for guiding a car 1 and a counterweight 2 as they ascend and descend, respectively, in a hoistway as shown in FIG. At the time of installation, the guide rails 3 and 4 are erected upright in order from the lower part of the hoistway.

【0003】ところで、この立設作業は、昇降路の下部
より順にガイドレールを立設し、あるピッチで昇降路壁
(鉄骨構造の場合にはファスナ)に芯出し固定していく
ようにしている。最下部のガイドレールは、足場(図示
しない)などを使用して立設・芯出し固定するが、それ
より上部のガイドレールは、昇降路の上部より吊り下げ
られたゴンドラまたはかごを支持するかご枠に作業床を
設けたものを、上昇させながら順次吊り上げ、昇降路壁
に芯出し固定していく。
By the way, in this erection work, guide rails are erected in order from the lower part of the hoistway, and centered and fixed to the hoistway wall (fastener in the case of a steel frame structure) at a certain pitch. .. The bottom guide rail is erected and centered and fixed using a scaffold (not shown), while the guide rails above it support the gondola or car suspended above the hoistway. A frame with a work floor is lifted in sequence while being raised, and centered and fixed to the hoistway wall.

【0004】次に、この立設作業におけるガイドレール
の吊り上げ方法を、図5を参照して説明する。既に立設
固定された左右のガイドレール5間にガイドされ、かご
枠に組立てられた作業床6に作業者7が乗り込み、ガイ
ドレール揚重用ウインチ(図示しない)に連結されたロ
ープ8に次に接続しようとするガイドレール9(以下、
ガイドレール9という)を吊り下げ、作業床6とガイド
レール揚重用ウインチ双方を稼働させてほぼ両者が同速
度になるように制御し、ガイドレール9が昇降路に設置
されている他機器に衝突しないように作業者7が手で軽
く支えて上昇させる。この上昇時において、一方の速度
が他方の速度より早くなった場合には、まず、双方を一
旦停止させ、遅れた方を上昇させて所望の位置に達した
とき停止させ、その後今度は双方を運転して、ガイドレ
ール9を所定の位置まで上昇させる。
Next, a method of hoisting the guide rails in this standing work will be described with reference to FIG. The operator 7 is guided by the left and right guide rails 5 that have been already fixed upright, and is mounted on the work floor 6 assembled to the car frame, and then the rope 8 connected to the guide rail lifting winch (not shown) Guide rail 9 to be connected (hereinafter,
(The guide rail 9) is hung, and both the work floor 6 and the guide rail lifting winch are operated to control them so that they have almost the same speed, and the guide rail 9 collides with other equipment installed in the hoistway. To prevent this, the operator 7 lightly supports and raises. When one speed becomes faster than the other speed during this ascending, first stop both, then raise the delayed one and stop when reaching the desired position, and then both By driving, the guide rail 9 is raised to a predetermined position.

【0005】このようにして所定の位置まで上昇した後
双方を停止させ、ガイドレール9の底部9aが既に立設
されたガイドレール5の上端5aの上端に合う位置まで
ガイドレール揚重用ウインチにより上昇させる。この
後、作業者7の手作業により、既に立設されたガイドレ
ール5の上端5aにガイドレール9を移動させ、締結用
ボルトにより両者を締結する。
After ascending to the predetermined position in this way, both of them are stopped, and the bottom 9a of the guide rail 9 is lifted by the guide rail lifting winch to a position where the bottom 9a of the guide rail 9 is aligned with the upper end of the upper end 5a of the guide rail 5 which has already been set up. Let Thereafter, the worker 7 manually moves the guide rail 9 to the upper end 5a of the guide rail 5 which has been erected upright, and fastens the two with fastening bolts.

【0006】[0006]

【発明が解決しようとする課題】しかしながら、従来の
ガイドレールの吊り上げ方法は、上述したようにガイド
レールを上昇させる際に作業者がガイドレールを手で支
えていなければならず、非常に危険である。特に、作業
床の速度とガイドレール揚重用の速度を全く同一にする
ことは実際上困難である。相対的にガイドレールが上下
することになり、ガイドレールを手で支えながら、具合
よく停止,稼働を繰返して所定の位置まで上昇させるの
は非常に困難であり、かつ危険である。また、何らかの
原因でガイドレールから作業者の手が離れてもガイドレ
ールが他機器に衝突しないようにするため、ガイドレー
ルを吊り上げる昇降路上部の吊元の位置は既に立設され
たガイドレールの重心位置には設定することができない
という不具合があり、所定の位置までガイドレールを吊
り上げた後、既に立設されたガイドレールの上に移動し
ようとするときに容易に移動させることができないとい
う不具合が発生するとともに、接続作業もスムースに行
うことができないという不具合が発生していた。
However, in the conventional method of hoisting the guide rail, the worker must support the guide rail by hand when raising the guide rail as described above, which is very dangerous. is there. In particular, it is practically difficult to make the speed of the work floor and the speed for lifting the guide rails exactly the same. Since the guide rails move up and down relatively, it is very difficult and dangerous to stop and operate the guide rails repeatedly by hand to lift them up to a predetermined position while supporting them by hand. In order to prevent the guide rail from colliding with other equipment even if the operator's hand is separated from the guide rail for some reason, the position of the hoisting part above the hoistway where the guide rail is hoisted is There is a problem that it can not be set to the center of gravity position, and after lifting the guide rail to a predetermined position, it can not be easily moved when trying to move it on the already installed guide rail. In addition, there was a problem that the connection work could not be performed smoothly.

【0007】本発明は、上述した課題を解決すべくなさ
れたもので、その目的とするところは接続するガイドレ
ールを吊り上げるときには、作業者が手で案内する作業
を不要とし、また、所定の高さまで吊り上げたこのガイ
ドレールを昇降路壁の所定の位置に移動させる際にも、
作業者の手で案内する作業も殆ど不要として、非常に容
易でかつ安全にガイドレールの立設を行うことができる
ようにしたエレベータのガイドレールの揚重用ガイド装
置を提供することにある。
The present invention has been made to solve the above-mentioned problems. The purpose of the present invention is to eliminate the need for the operator to manually guide when the guide rail to be connected is hoisted and to have a predetermined height. When moving this guide rail that was hoisted up to a predetermined position on the hoistway wall,
It is an object of the present invention to provide a guide device for lifting a guide rail of an elevator, which enables the guide rail to be erected very easily and safely with almost no need for the work of guiding by a worker.

【0008】[0008]

【課題を解決するための手段】本発明は、上述した目的
を達成するために、昇降路内を昇降する枠組に装着可能
とした基板と、この基板の上部に回動可能に装着され、
ガイドレールを吊り上げるロープを案内する滑車を回転
自在に支持した滑車装置と、この滑車装置より下部で基
板に装着され、吊り上げるガイドレールの歯面に係合す
るローラを回転自在に支持したガイドローラ装置とによ
り構成したものである。
In order to achieve the above-mentioned object, the present invention provides a substrate mountable on a frame that moves up and down in a hoistway, and is rotatably mounted on the upper part of the substrate.
A pulley device that rotatably supports a pulley that guides a rope that lifts a guide rail, and a guide roller device that rotatably supports a roller that is mounted on a substrate below the pulley device and that engages with the tooth surface of the guide rail that is lifted. It is composed of and.

【0009】[0009]

【作用】昇降路壁にガイドレールを下から順次立設して
いく場合、昇降路内を昇降する作業床またはゴンドラの
ような枠組に揚重用ガイド装置を装着することにより、
ガイドレール揚重用のウインチを立設するガイドレール
の重心位置の上部に設置することができる。また、次に
接続するガイドレールを吊り上げる際には、滑車装置を
基板側に回動させておくことにより、ガイドレールの歯
面にガイドローラ装置のローラが係合するので、吊り上
げ中のガイドローラを作業者が手で支える必要がなく、
ガイドローラと枠組の相対速度に差が生じてもローラの
回転で吸収するから、枠組とガイドレールの双方を支障
なく上昇させることができる。さらに、吊り上げたガイ
ドレールを既に立設されているガイドレールの上部に位
置させる際には、ロープを滑車から外すことにより、こ
のガイドレールが重心の作用で既に立設されているガイ
ドレールの上部に移動する。したがって、この際にも作
業者はガイドレールを案内することが不要となる。
[Operation] When the guide rails are sequentially erected from the bottom on the hoistway wall, by attaching the lifting guide device to the work floor or gondola-like frame that hoists in the hoistway,
The winch for lifting the guide rail can be installed above the center of gravity of the guide rail for standing upright. Further, when the guide rail to be connected next is lifted, the pulley of the guide roller device is engaged with the tooth surface of the guide rail by rotating the pulley device toward the substrate side. The operator does not have to support it by hand,
Even if there is a difference in the relative speed between the guide roller and the frame, it is absorbed by the rotation of the roller, so that both the frame and the guide rail can be raised without any trouble. Furthermore, when positioning the hoisted guide rail above the guide rail that has already been erected, remove the rope from the pulley so that the guide rail is above the guide rail that has already been erected by the action of the center of gravity. Move to. Therefore, also in this case, the operator does not need to guide the guide rail.

【0010】[0010]

【実施例】以下、本発明の一実施例を図面を参照して説
明する。図1は本発明の一実施例を示す斜視図である。
同図において、10はエレベータのガイドレールの揚重用
ガイド装置で、この揚重用ガイド装置10は、取付板11
と、この取付板11の上部側に回動可能に取付けられ、ガ
イドレールを吊り上げるロープ8を案内する滑車装置12
と、取付板11の下部側に取付けられ、吊り上げられるガ
イドレールの歯面に係合して案内するガイドローラ装置
13で構成されている。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the present invention will be described below with reference to the drawings. FIG. 1 is a perspective view showing an embodiment of the present invention.
In the figure, 10 is a lifting guide device for an elevator guide rail, and this lifting guide device 10 includes a mounting plate 11
And a pulley device 12 which is rotatably mounted on the upper side of the mounting plate 11 and which guides the rope 8 for lifting the guide rail.
And a guide roller device which is attached to the lower side of the mounting plate 11 and engages with and guides the tooth surface of the guide rail to be lifted.
It consists of 13.

【0011】しかして、滑車装置12は、取付板11に固着
された支持板14にピン15を介して回動可能に取付けられ
た一対のアーム16,16と、この一対のアーム16,16にピ
ン17を介して回動自在に支持された滑車18と、支持板14
に固着され、一対のアーム16,16を所定の位置(ほぼ水
平状態)に保持するためのストッパ19と、一対のアーム
16,16と支持板14に着脱可能に挿入され、一対のアーム
16,16がストッパ19によりほぼ水平状態に保持されてい
るときに、この状態を固定するストッパピン20で構成さ
れている。なお、取付板11には、上記した作業床6に取
付けるためのボルト貫通穴11aが設けられている。
Therefore, the pulley device 12 has a pair of arms 16 and 16 rotatably attached to the support plate 14 fixed to the attachment plate 11 via pins 15, and the pair of arms 16 and 16. A pulley 18 rotatably supported via a pin 17 and a support plate 14
And a stopper 19 for holding the pair of arms 16 at a predetermined position (almost horizontal state) and a pair of arms.
16 and 16 and the support plate 14 are detachably inserted into a pair of arms.
When the stoppers 16 and 16 are held in a substantially horizontal state by the stopper 19, the stopper pin 20 fixes the state. The mounting plate 11 is provided with bolt through holes 11a for mounting on the work floor 6 described above.

【0012】また、ガイドローラ装置13は、コ字状に形
成され、取付板11に固着またはボルトを介して取付けら
れた支持金具21と、この支持金具21の対向辺21a,21a
の内面にそれぞれブラケット22,22を介して回転自在に
支持されたローラ23,23と、支持金具21の他の辺21bの
内面にブラケット22を介して回転自在に支持されたロー
ラ23で構成され、各ローラ23はガイドレールの歯面(3
面がある)にそれぞれ係合するように配置されている。
なお、必要に応じ、ブラケット22の大きさ、またはスペ
ーサ等によりローラ23の相互の位置を変化させ、形状の
相違する複数のガイドレールに対応させるようにしても
よい。
Further, the guide roller device 13 is formed in a U-shape, and has a support fitting 21 fixed to the mounting plate 11 or attached via bolts, and opposing sides 21a, 21a of the support fitting 21.
Rollers 23 and 23 rotatably supported on the inner surfaces of the brackets 22 and 22, respectively, and rollers 23 rotatably supported on the inner surface of the other side 21b of the support fitting 21 via the brackets 22. , Each roller 23 has a tooth flank (3
Surface) and are each arranged to engage.
If necessary, the size of the bracket 22 or the mutual position of the rollers 23 may be changed by a spacer or the like so as to correspond to a plurality of guide rails having different shapes.

【0013】さらに、以上の構成において、滑車装置12
は、ストッパピン20を抜いて矢印24方向に回動(取付板
11側に傾斜)させると、滑車18は下部のローラ23より引
込み、挿入されるガイドレールの歯面と干渉しないよう
になっている。
Further, in the above structure, the pulley device 12
Remove the stopper pin 20 and rotate in the direction of arrow 24 (mounting plate
When it is tilted to the 11 side), the pulley 18 is pulled in from the lower roller 23 and does not interfere with the tooth surface of the guide rail to be inserted.

【0014】次に、以上の構成による実施例を用いたガ
イドレールの立設作業について説明する。予め、ガイド
レールを吊り上げる昇降路最上部の吊元の位置を、既に
立設したガイドレールの重心の位置となるようにしてお
く。また、作業床6には上述した実施例の揚重用ガイド
装置10を装着する。
Next, the work of standing up the guide rails using the embodiment having the above construction will be described. In advance, the position of the top of the hoistway for hoisting the guide rails should be set to the position of the center of gravity of the guide rails that have already been erected. Further, the lifting guide device 10 of the above-described embodiment is mounted on the work floor 6.

【0015】まず、図2に示すように滑車装置12を図1
に矢印24で示す方向に回動させて引込め、ガイドローラ
装置13の各ローラ23をガイドレール9の各歯面に係合さ
せて挟む状態とし、作業床6とガイドレール揚重用ウイ
ンチを同時に稼働させて上昇させる。このとき、両者の
速度差により、相対的にガイドレール9が矢印25の方向
に上下するが、ローラ23が回転することによりこれを容
易に吸収することができ、また、ガイドレール9が同図
に示すように傾斜し、ガイドローラ装置13の中央のロー
ラ23を押圧するようにしているので、ガイドレール9の
吊り上げ中にガイドレール9がガイドローラ装置13から
外れないように保つことは容易である。作業床6が既に
立設されているガイドレール5の最上部近くまで上昇し
たとき停止する。さらに、ガイドレール揚重用ウインチ
を稼働してガイドレール9を所定位置まで吊り上げた
後、既に立設されたガイドレール5の上に移動させる。
この移動は、ガイドレール9を吊り上げる昇降路最上部
の吊元の位置が、既に立設されたガイドレール5の重心
の位置になっているので、重心の作用があり容易かつ安
全に行うことができる。
First of all, as shown in FIG.
And is retracted by rotating in the direction indicated by an arrow 24, and each roller 23 of the guide roller device 13 is engaged with each tooth surface of the guide rail 9 so as to be sandwiched, and the working floor 6 and the winch for lifting the guide rail simultaneously. Operate and raise. At this time, the guide rail 9 moves up and down relatively in the direction of the arrow 25 due to the speed difference between the two, but it can be easily absorbed by the rotation of the roller 23. Since it is inclined so as to press the central roller 23 of the guide roller device 13, it is easy to keep the guide rail 9 from coming off the guide roller device 13 while the guide rail 9 is being lifted. is there. It stops when the work floor 6 has risen to near the top of the guide rail 5 that has already been erected. Further, the guide rail lifting winch is operated to lift the guide rail 9 to a predetermined position, and then the guide rail 9 is moved onto the guide rail 5 which has already been erected.
This movement can be performed easily and safely because there is an action of the center of gravity because the position of the uppermost hoistway of the hoistway for hoisting the guide rail 9 is the position of the center of gravity of the guide rail 5 that has already been erected. it can.

【0016】また、図3は、作業床6を既に立設された
ガイドレール5の最上部まで上昇させておき、この状態
で次に接続しようとするガイドレール9を吊り上げ、ガ
イドレール5に接続しようとする方法を示したものであ
る。
Further, in FIG. 3, the work floor 6 is lifted up to the uppermost part of the guide rail 5 which has already been erected, and in this state, the guide rail 9 to be connected next is lifted and connected to the guide rail 5. It shows how to try.

【0017】まず、滑車装置12をほぼ水平状態に回動
し、ストッパピン20を挿入してこの状態を固定してお
く。この滑車装置12の滑車18にロープ8を掛け、このロ
ープ8の下端にガイドレール9を連結し、ガイドレール
揚重用ウインチを稼働させる。ガイドレール9は、同図
に示すようにほぼ鉛直状態で吊り上げられる。ガイドレ
ール9が作業床6の位置近くまで上昇したとき、ガイド
レール揚重用ウインチを一旦停止させ、滑車装置12をス
トッパピン20を抜いて取付板11側に回動する。この後再
びガイドレール揚重用ウインチを稼働させてガイドレー
ル9を吊り上げるが、これ以降の手順は上述した手順と
同様であり、同様の効果を得られる。
First, the pulley device 12 is rotated in a substantially horizontal state, and the stopper pin 20 is inserted to fix this state. The rope 8 is hung on the pulley 18 of the pulley device 12, and the guide rail 9 is connected to the lower end of the rope 8 to operate the guide rail lifting winch. The guide rail 9 is lifted in a substantially vertical state as shown in the figure. When the guide rail 9 rises to a position near the work floor 6, the winch for lifting the guide rail is temporarily stopped, and the pulley device 12 is pulled out of the stopper pin 20 and rotated to the mounting plate 11 side. After that, the guide rail lifting winch is operated again to lift the guide rail 9, but the procedure after this is the same as the procedure described above, and the same effect can be obtained.

【0018】[0018]

【発明の効果】以上説明したように本発明によれば、基
板に、上部には回動可能に装着されるとともにロープを
案内する滑車を回転自在に支持した滑車装置と、この滑
車装置の下部に吊り上げるガイドレールの歯面に係合す
るローラを回転自在に支持したガイドローラ装置を設け
ているので、昇降路壁に立設するガイドローラの吊り上
げ作業と、所定の高さまで上昇させた後の所定位置への
移動作業が非常に容易となり、かつ安全性を大幅に向上
させることができるエレベータのガイドレールの揚重用
ガイド装置を提供できる。
As described above, according to the present invention, a pulley device, which is rotatably mounted on an upper portion of a substrate and rotatably supports a pulley for guiding a rope, and a lower portion of the pulley device. Since a guide roller device that rotatably supports a roller that engages with the tooth surface of the guide rail to be lifted is provided, the guide roller that is erected on the hoistway wall is lifted, and after the guide roller is raised to a predetermined height. It is possible to provide a guide device for lifting a guide rail of an elevator, which makes it extremely easy to move to a predetermined position and can greatly improve safety.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の一実施例を示す斜視図。FIG. 1 is a perspective view showing an embodiment of the present invention.

【図2】本発明の一実施例の作用を示す説明図。FIG. 2 is an explanatory view showing the operation of one embodiment of the present invention.

【図3】図2と異なる本発明の一実施例の作用を示す説
明図。
FIG. 3 is an explanatory view showing an operation of an embodiment of the present invention different from that of FIG.

【図4】本発明に関連するエレベータのかごとガイドレ
ールの配置を示す説明図。
FIG. 4 is an explanatory view showing an arrangement of elevator cars and guide rails related to the present invention.

【図5】従来のエレベータのガイドレールを立設する作
業の説明図。
FIG. 5 is an explanatory view of the work of standing up the guide rails of the conventional elevator.

【符号の説明】[Explanation of symbols]

1…かご、2…つり合い重り、3,4,5,9…ガイド
レール、7…作業者、8…ロープ、11…取付板、12…滑
車装置、13…ガイドローラ装置、15,17…ピン、16…ア
ーム、18…滑車、20…ストッパピン、21…支持金具、22
…ブラケット、23…ローラ。
1 ... Basket, 2 ... Counterweight, 3, 4, 5, 9 ... Guide rail, 7 ... Worker, 8 ... Rope, 11 ... Mounting plate, 12 ... Pulley device, 13 ... Guide roller device, 15, 17 ... Pin , 16 ... Arms, 18 ... Pulleys, 20 ... Stopper pins, 21 ... Support brackets, 22
… Brackets, 23… Laura.

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 昇降路内を昇降する枠組に装着可能とし
た基板と、この基板の上部に回動可能に装着され、ガイ
ドレールを揚重するロープを案内する滑車を回転自在に
支持した滑車装置と、この滑車装置より下部で前記基板
に装着され、揚重する前記ガイドレールの歯面に係合す
るローラを回転自在に支持したガイドローラ装置とから
構成したことを特徴とするエレベータのガイドレールの
揚重用ガイド装置。
1. A pulley that rotatably supports a base plate that can be mounted on a frame that moves up and down in a hoistway, and a pulley that is rotatably mounted on an upper part of the base plate and that guides a rope for lifting a guide rail. A guide for an elevator comprising: a device and a guide roller device that is rotatably supported on a roller below the pulley device and is engaged with a tooth surface of the guide rail to be lifted. Guide device for lifting rails.
JP4935692A 1992-03-06 1992-03-06 Hoisting guide device for elevator guide rail Pending JPH05246651A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP4935692A JPH05246651A (en) 1992-03-06 1992-03-06 Hoisting guide device for elevator guide rail

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP4935692A JPH05246651A (en) 1992-03-06 1992-03-06 Hoisting guide device for elevator guide rail

Publications (1)

Publication Number Publication Date
JPH05246651A true JPH05246651A (en) 1993-09-24

Family

ID=12828742

Family Applications (1)

Application Number Title Priority Date Filing Date
JP4935692A Pending JPH05246651A (en) 1992-03-06 1992-03-06 Hoisting guide device for elevator guide rail

Country Status (1)

Country Link
JP (1) JPH05246651A (en)

Similar Documents

Publication Publication Date Title
AU2007321143B2 (en) Method and apparatus for installing an elevator without machine room during construction of a building, and use of a hoisting machine
JP4191331B2 (en) Elevator equipment
JP4828084B2 (en) How to install the hoist
JP2000044146A5 (en)
JP6422570B2 (en) Machine room-less elevator
JP2007210703A (en) Device and method for installing hoist machine in machine-room-less elevator
JP2620123B2 (en) Temporary lifting equipment for construction work
JP2001097649A (en) Elevator device
JP7224532B2 (en) elevator pit ladder equipment
JPH05340085A (en) Scaffold device for elevator shaft work
JPH09151053A (en) Fixing device for car of elevator
JPH05246651A (en) Hoisting guide device for elevator guide rail
JP4251921B2 (en) Elevator equipment
JP2846528B2 (en) Guide rail installation method for hydraulic elevator
JP3209931B2 (en) Elevator car fixing device
JP3348018B2 (en) Elevator installation method
JP4804144B2 (en) Top sheave device in climbing method for construction elevators
JP2001335255A (en) Elevator installation construction method, and elevator installation unit
JP4245315B2 (en) Moving scaffold for elevator installation and elevator installation method
JP2530834Y2 (en) Equipment for loading and unloading elevators for construction
JP2000335847A (en) Elevator installation device
JP2930911B2 (en) Elevator installation method
JP2536878Y2 (en) Opening / closing device for transport doors of construction elevators
JP2004142853A (en) Elevator device
JPS625439Y2 (en)