JPH0519436U - Hanging scaffold fixing bracket - Google Patents

Hanging scaffold fixing bracket

Info

Publication number
JPH0519436U
JPH0519436U JP1819591U JP1819591U JPH0519436U JP H0519436 U JPH0519436 U JP H0519436U JP 1819591 U JP1819591 U JP 1819591U JP 1819591 U JP1819591 U JP 1819591U JP H0519436 U JPH0519436 U JP H0519436U
Authority
JP
Japan
Prior art keywords
plate
holes
mounting base
flange
slide plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP1819591U
Other languages
Japanese (ja)
Other versions
JP2510605Y2 (en
Inventor
正人 岡
Original Assignee
株式会社ケイ・ケイ・エル
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社ケイ・ケイ・エル filed Critical 株式会社ケイ・ケイ・エル
Priority to JP1991018195U priority Critical patent/JP2510605Y2/en
Publication of JPH0519436U publication Critical patent/JPH0519436U/en
Application granted granted Critical
Publication of JP2510605Y2 publication Critical patent/JP2510605Y2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Movable Scaffolding (AREA)

Abstract

(57)【要約】 (修正有) 【目的】 鉄骨梁に取付ける作業足場を簡単に吊せ、然
も取外しが鉄筋、連接鉄筋の存在下にても容易である吊
足場固定金具。 【構成】 鉄骨梁のフランジ下面に寸法に合わせる如
く、取付基盤1とスライド板3によって取付巾をスライ
ド出来るように構成し、スライド板3の側板8にフラン
ジに係止する鉤状部9を有する係止板7を螺子止めし、
上下左右からフランジを締め付けて固定出来るようにし
た。又、取付基盤1とスライド板3は側板8に挿通した
ボルト12の抜去りにより下方へ動かすだけで取外せ
る。
(57) [Summary] (Modified) [Purpose] A hanging scaffold fixing bracket that can easily hang a work scaffold attached to a steel beam and can be easily removed even in the presence of reinforcing bars and connecting reinforcing bars. [Structure] The mounting width can be slid by a mounting base 1 and a slide plate 3 so as to match the dimensions of the lower surface of the flange of the steel frame beam, and a side plate 8 of the slide plate 3 has a hook-shaped portion 9 that engages with the flange. Screw the locking plate 7,
The flanges can be tightened from the top, bottom, left and right to be fixed. Further, the mounting base 1 and the slide plate 3 can be removed by simply moving the mounting plate 1 and the slide plate 3 downward by removing the bolt 12 inserted into the side plate 8.

Description

【考案の詳細な説明】[Detailed description of the device]

【0001】[0001]

【産業上の利用分野】[Industrial applications]

本考案は、建築現場に於て使用する吊足場固定金具に関するものである。 The present invention relates to a hanging scaffold fixing metal fitting used in a construction site.

【0002】[0002]

【従来の技術】[Prior Art]

建築現場に於て、H型鋼、I型鋼等鉄骨梁を組立て、その外側に鉄筋を巻回し て行き、その周囲をコンクリートにて固め、いわゆる梁を形成することが行われ ている。然して、その作業及びそれに続く作業の必要上吊足場を使用している。 At construction sites, steel beams such as H-shaped steel and I-shaped steel are assembled, the reinforcing bars are wound around the steel beams, and the surroundings are solidified with concrete to form so-called beams. However, the suspended scaffolding is used for the purpose of the work and the following work.

【0003】 従来、吊足場には、前記鉄骨梁の下端面に吊足場固定用の取付ピースを溶接し 、該取付ピースに設けた透孔に吊足場の吊部を係架固定していた。 然し、この溶接は面倒であるため、取付ピースとそれに摺動自在に設けたボル ト・ナットを有するクランプ部により取付ピースとクランプ部により鉄骨梁のフ ランジをクランプし着脱自在にしたもの或は又クランプ部を取付ピース上を摺動 自在に設け、取付ピースとクランプ部に設けた透孔にボルトを挿通し、クランプ の移動によりクランプ部間に鉄骨梁のフランジを挾持するように構成したもの、 又は吊部を交叉するように設け吊部の先端につかみ部を設けて鉄骨梁のフランジ に固定し、交叉部にクリップを通してロックする如く構成したものがある。Conventionally, a mounting piece for fixing the hanging scaffold is welded to the lower end surface of the steel frame beam on the hanging scaffold, and the hanging portion of the hanging scaffold is fixed to the through hole provided in the mounting piece. However, since this welding is troublesome, it is possible to attach or detach the flange of the steel beam by the attachment piece and the clamp portion, which has a bolt and nut slidably mounted on the attachment piece. In addition, the clamp part is slidably mounted on the mounting piece, the bolt is inserted into the through hole provided in the mounting piece and the clamp part, and the flange of the steel beam is clamped between the clamp parts by the movement of the clamp. Alternatively, there is a structure in which a hanging portion is provided so as to cross, a grip portion is provided at the tip of the hanging portion to fix the hanging portion to the flange of the steel frame beam, and a clip is locked at the crossing portion.

【0004】[0004]

【考案が解決しようとする問題点】[Problems to be solved by the device]

然して、鉄骨梁に取付の場合には問題はないが、吊足場を外し、固定金具を外 す際に、上記の如き構成の場合、前二者に於てはクランプ部を摺動させて取付ピ ースから外さんとする場合、既に鉄骨梁の周囲を囲繞するごとく設置した鉄筋間 を連結する鉄筋に当り、外せない状況になっている。 However, there is no problem when mounting on steel beams, but when removing the suspension scaffold and removing the fixing bracket, in the case of the above configuration, in the former two cases, the clamp part is slid and mounted. When it is removed from the peas, it cannot be removed because it hits the reinforcing bars that connect the reinforcing bars that have already been installed around the steel beam.

【0005】 又、吊部を交叉する構成の場合でもつかみ部を有する上方を拡開しなければな らないが、その節、連結鉄筋に当り拡げられない為、取外し不能となり、連設鉄 筋を切断したり、固定金具を付けたまゝにしたりしなければならず、強度上の問 題が生じたり、経済的な損失を生じることがあった。Further, even in the case of the structure in which the suspension parts are crossed, the upper part having the grip part must be expanded, but it cannot be removed because it cannot be expanded because it hits the node or the connecting reinforcing bar. It had to be cut off or left attached to the metal fittings, which could cause problems with strength and economic loss.

【0006】 更に、従来の吊足場固定金具に於ては、鉄鋼梁のフランジの巾に応じて対応す る巾の固定金具が必要であった。この為、多種類の固定金具を用意しなければな らず、経済的負担も大で、且在庫管理も面倒であった。Further, in the conventional hanging scaffold fixing bracket, a fixing bracket having a width corresponding to the width of the flange of the steel beam is required. For this reason, it was necessary to prepare many types of fixing fittings, which imposes a heavy financial burden and makes inventory management troublesome.

【0007】[0007]

【問題点を解決するための手段】[Means for solving problems]

そこで本考案に於ては、固定金具は、鉄筋、連結鉄筋の存在に邪魔されること なく取外すことが出来ると共に、各種類のフランジの巾に対応して使用すること が出来る構成とすることにより、少数を用意するだけでたり、経済的にも有利で 、且在庫管理も容易である等実用効果大なる吊足場金具を提案せんとするもので 、取付基盤に適宜数の透孔を穿設すると共に、該透孔に対応する透孔を有する二 枚のスライド板を、取付基盤の所望位置に透孔同志を挿通するボルトにて固定す る一方、両スライド板の外側方に側板を設け、該側板には鉤状板を両者の挿通孔 に挿通するボルトにて締着させ、且鉤状板状部には締付固定部を設けたことを特 徴とする。 Therefore, in the present invention, the fixing metal fittings can be removed without being disturbed by the presence of the reinforcing bars and connecting reinforcing bars, and can be used according to the width of each type of flange. It is an idea to propose a hanging scaffolding metal fitting with great practical effects such as preparing only a small number, economical advantage, and easy inventory management. An appropriate number of through holes are drilled in the mounting base. At the same time, the two slide plates that have through holes corresponding to the through holes are fixed to the desired position of the mounting base with bolts that insert the through holes, while side plates are provided on the outer sides of both slide plates. The characteristic feature is that a hook-shaped plate is fastened to the side plate with a bolt which is inserted into both insertion holes, and a fastening fixing portion is provided on the hook-shaped plate-shaped portion.

【0008】[0008]

【実施例】【Example】

以下、図に示す一実施例により本考案を詳細に説明する。 は取付基盤で適宜数の透孔2,2,……を設けておく。この透孔2,2,… …は左右対称的に設けるのがよい。はスライド板で適宜の透孔4,4,… …を穿設し、その各外側端には側板5を固定乃至折曲形成して略直角方向に設け てある。6は天板で、スライド板の上端に、上端を折曲し或は固定して必要に 応じ形成してある。Hereinafter, the present invention will be described in detail with reference to an embodiment shown in the drawings. Reference numeral 1 is a mounting base, and an appropriate number of through holes 2, 2, ... Are provided. It is preferable that the through holes 2, 2, ... Are symmetrically provided. Reference numerals 3 and 3 are slide plates provided with appropriate through holes 4, 4, ..., And side plates 5 are fixed or bent at their outer ends to be provided in a substantially right angle direction. A top plate 6 is formed on the upper end of the slide plate 3 by bending or fixing the upper end as required.

【0009】 は係止板で、側板8と鉤状板9により一体的に構成されるが、溶接しても、 一板体を折曲形成してもよい。該側板8はスライド板より高く形成してあり、 又、そこには透孔10を穿設し、前記側板5に穿設した透孔11をボルト12に て挿通し、ナット13にて緊締重合する如くしてある。14はボルトで、鉤状板 9に設けたナット15と透孔16を螺通し締付固定部17を形成してある。 その他図中18は足場、19はその吊部、20は鉄筋、21は連結鉄筋、22 はコンクリートである。 取付基盤に設けた透孔2とスライド板に設けた透孔4は個別の透孔でもよ いが、一方乃至両方を横方向の長孔を形成させてもよい。Reference numeral 7 denotes a locking plate, which is integrally formed by the side plate 8 and the hook plate 9, but may be welded or a single plate may be bent and formed. The side plate 8 is formed to be higher than the slide plate 3 , and a through hole 10 is formed in the side plate 8. The through hole 11 formed in the side plate 5 is inserted with a bolt 12 and tightened with a nut 13. It seems to polymerize. Reference numeral 14 is a bolt, and a nut 15 and a through hole 16 provided in the hook-shaped plate 9 are screwed through to form a tightening and fixing portion 17 . In the figure, 18 is a scaffold, 19 is a suspended portion, 20 is a reinforcing bar, 21 is a connecting reinforcing bar, and 22 is concrete. The through holes 2 provided in the mounting base 1 and the through holes 4 provided in the slide plate 3 may be separate through holes, or one or both of them may be formed as lateral long holes.

【0010】 次いで、その使用について説明すれば、スライド板を取付基盤に重合 させ、その位置をスライドさせて、取付基盤1とスライド板とによって形 成される巾が取付けるフランジ26の巾と略同じにさせる。そこで取付基盤と スライド板両者の透孔2,2,……、透孔4,4,……を選びボルト23 ,23,……を挿通し、ナット24,24,……にて緊締する。この様に形成し たスライド板を設けた取付基盤1を鉄骨梁25のフランジ26下面に持来 す。そして、フランジ26の両側から係止板を当て、スライド板の側板 5に係止板の側板8を合せ、ボルト12を両者の透孔11、同10に挿通して ナット13にて固定させ、側板8,8間にフランジ26を挾持させる。Next, the use thereof will be described. The slide plates 3 and 3 are superposed on the mounting base 1 , and the positions are slid to attach the width formed by the mounting base 1 and the slide plates 3 and 3. The width of the flange 26 is made substantially the same. Therefore, select the through holes 2, 2, ..., through holes 4, 4, ... of both the mounting base 1 and the slide plates 3 , 3 , and insert the bolts 23, 23, ... into the nuts 24, 24, .... Tighten. The mounting base 1 provided with the slide plates 3 and 3 thus formed is brought to the lower surface of the flange 26 of the steel beam 25 . Then, against the locking plate 7, 7 from both sides of the flange 26, the side plate 5 of the sliding plate 3 combined side plate 8 of the retaining plate 7, through-holes 11 of both the bolts 12, nuts 13 are inserted in the 10 Then, the flange 26 is clamped between the side plates 8 and 8.

【0011】 次いで、ボルト14をナット15に螺入りさせることにより、天板6或は天板 6を設けないときには取付基盤とスライド板間にフランジ26を上下か ら締付固定する。取付基盤とスライド板の透孔2,2,……、透孔4, 4,……のうちボルト23を挿通していない透孔2,2、透孔4,4の適宜箇処 により吊部19,19を固定し、足場18をフランジ26に吊下げ固定する。Next, by screwing the bolt 14 into the nut 15, the top plate 6 or the flange 26 is vertically fixed between the mounting base 1 and the slide plates 3 and 3 when the top plate 6 is not provided. . Of the through holes 2, 2, ..., through holes 4, 4, ... of the mounting base 1 and the slide plates 3 , 3 , the through holes 2, 2 and the through holes 4, 4 in which the bolts 23 are not inserted are appropriately selected. The suspension parts 19 and 19 are fixed by the process, and the scaffold 18 is suspended and fixed to the flange 26.

【0012】 足場18の撤去に際しては、吊り部19,19により足場18を取付基盤と スライド板より取外し、次いでボルト12,12を抜くことにより、取付 基盤とスライド板を取外す。この取外しは、下方に移動させるだけで左 右の移動はなく、連結鉄筋21に当たることなく行われる。又、係止板も上方 へ引上げるだけであり、左右に動かすことなく取去ることが出来る。[0012] In removal of the scaffold 18, the hanging portion mounting base 1 a scaffold 18 by 19, 19 and the slide plate 3, 3 from removal, followed by removing the bolts 12, 12, mounting base 1 and the slide plate 3, 3 Remove. This removal is performed without moving to the left or right, only by moving it downward, and without hitting the connecting rebar 21. Further, the locking plate 7 is also only pulled up, and can be removed without moving it to the left or right.

【0013】 上記の如き、本考案によれば、取付基盤に適宜数の透孔を穿設すると共に、該 透孔に対応する透孔を有する二枚のスライド板を、取付基盤の所望位置に透孔同 志を挿通するボルトにて固定する一方、両スライド板の外側方に側板を設け、該 側板には鉤状板を両者の挿通孔に挿通するボルトにて締着させ、且鉤状板状部に は締付固定部を設けたので、ボルトを螺脱して係止板とスライド板の側板の固定 をとくだけで、取付基盤とスライド板は取外すことが出来、連結連結鉄筋、鉄筋 に接触することなく取外せる。As described above, according to the present invention, the mounting base is provided with an appropriate number of through holes, and two slide plates having through holes corresponding to the through holes are provided at desired positions of the mounting base. While fixing the bolts through the through holes, side plates are provided on the outer sides of both slide plates, and hook plates are fastened to the side plates with bolts that pass through the through holes. Since the plate-shaped part is provided with a tightening and fixing part, the mounting base and slide plate can be removed by simply unscrewing the bolts and fixing the locking plate and the side plate of the slide plate. Can be removed without touching.

【0014】 又、取付基盤とスライド痛によって取付箇処のフランジ等の巾に対応して適宜 の巾にスライド変換することが出来、少量の数にて多種類の寸法に対応して使用 することが出来、経済的であり、管理にも便利である。 更に、その構成は極めて簡単で、製造取扱いが容易で、その上廉価に提供でき る等実用効果は著大である。Also, depending on the mounting base and sliding pain, it can be slide-converted to an appropriate width according to the width of the flange, etc. at the mounting location, and it should be used in a small number to accommodate various sizes. It is economical and convenient to manage. Furthermore, its structure is extremely simple, its manufacturing and handling are easy, and it can be provided at a low price.

【図面の簡単な説明】[Brief description of drawings]

【図1】 本考案一実施例要部の取付基正面図FIG. 1 is a front view of a mounting base of an essential part of one embodiment of the present invention.

【図2】 本考案一実施例要部のスラスド板正面図FIG. 2 is a front view of a thrust plate of an essential part of one embodiment of the present invention.

【図3】 本考案一実施例要部の組立正面図FIG. 3 is an assembled front view of essential parts of one embodiment of the present invention.

【図4】 本考案一実施例組立平面図FIG. 4 is an assembly plan view of an embodiment of the present invention.

【図5】 本考案一実施例組立平面図FIG. 5 is an assembly plan view of an embodiment of the present invention.

【図6】 本考案一実施例組立平面図FIG. 6 is an assembly plan view of one embodiment of the present invention.

【図6】 本考案一実施例使用状態正面説明図FIG. 6 is a front explanatory view of the usage state of one embodiment of the present invention.

【符号の説明】 取付基盤 2 透孔 スライド板 4 透孔 係止板 9 鉤状部17 締付固定部18 足場[Explanation of reference numerals] 1 mounting base 2 through hole 3 slide plate 4 through hole 7 locking plate 9 hook-like portion 17 tightening and fixing portion 18 scaffolding

─────────────────────────────────────────────────────
─────────────────────────────────────────────────── ───

【手続補正書】[Procedure amendment]

【提出日】平成4年9月4日[Submission date] September 4, 1992

【手続補正1】[Procedure Amendment 1]

【補正対象書類名】明細書[Document name to be amended] Statement

【補正対象項目名】図面の簡単な説明[Name of item to be corrected] Brief description of the drawing

【補正方法】変更[Correction method] Change

【補正内容】[Correction content]

【図面の簡単な説明】[Brief description of drawings]

【図1】本考案一実施例要部の取付基盤正面図。FIG. 1 is a front view of a mounting base of an essential part of one embodiment of the present invention.

【図2】本考案一実施例要部のスライド板正面図。FIG. 2 is a front view of a slide plate of an essential part of one embodiment of the present invention.

【図3】本考案一実施例要部の組立正面図。FIG. 3 is an assembled front view of the essential parts of one embodiment of the present invention.

【図4】本考案一実施例組立平面図。FIG. 4 is an assembly plan view of an embodiment of the present invention.

【図5】本考案一実施例組立平面図。FIG. 5 is an assembly plan view of an embodiment of the present invention.

【図6】本考案一実施例組立平面図。FIG. 6 is an assembly plan view of an embodiment of the present invention.

【図7】本考案一実施例使用状態正面説明図。FIG. 7 is a front explanatory view of the usage state of one embodiment of the present invention.

【符号の説明】 取付基盤 2 透孔 スライド板 4 透孔 係止板 9 鉤状部17 締付固定具18 足場[Explanation of symbols] 1 mounting base 2 through hole 3 slide plate 4 through hole 7 locking plate 9 hook-like portion 17 tightening fixture 18 scaffold

Claims (1)

【実用新案登録請求の範囲】[Scope of utility model registration request] 【請求項1】取付基盤に適宜数の透孔を穿設すると共
に、該透孔に対応する透孔を有する二枚のスライド板
を、取付基盤の所望位置に透孔同志を挿通するボルトに
て固定する一方、両スライド板の外側方に側板を設け、
該側板には鉤状板を両者の挿通孔に挿通するボルトにて
締着させ、且鉤状板状部には締付固定部を設けたことを
特徴とする吊足場固定金具。
1. A mounting base having a proper number of through holes and two slide plates having through holes corresponding to the through holes used as bolts for inserting the through holes at desired positions of the mounting base. While fixing with the side plate on the outside of both slide plates,
A hanging scaffolding fixing metal fitting, characterized in that a hook-like plate is fastened to the side plate with a bolt which is inserted into both insertion holes, and a fastening fixing portion is provided on the hook-like plate-like portion.
JP1991018195U 1991-02-25 1991-02-25 Hanging scaffold fixing bracket Expired - Lifetime JP2510605Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1991018195U JP2510605Y2 (en) 1991-02-25 1991-02-25 Hanging scaffold fixing bracket

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1991018195U JP2510605Y2 (en) 1991-02-25 1991-02-25 Hanging scaffold fixing bracket

Publications (2)

Publication Number Publication Date
JPH0519436U true JPH0519436U (en) 1993-03-12
JP2510605Y2 JP2510605Y2 (en) 1996-09-18

Family

ID=11964852

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1991018195U Expired - Lifetime JP2510605Y2 (en) 1991-02-25 1991-02-25 Hanging scaffold fixing bracket

Country Status (1)

Country Link
JP (1) JP2510605Y2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2020159114A (en) * 2019-03-27 2020-10-01 清水建設株式会社 Suspension tool for suspension scaffold and suspension scaffold

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS50151529U (en) * 1974-05-31 1975-12-17

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS50151529U (en) * 1974-05-31 1975-12-17

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2020159114A (en) * 2019-03-27 2020-10-01 清水建設株式会社 Suspension tool for suspension scaffold and suspension scaffold

Also Published As

Publication number Publication date
JP2510605Y2 (en) 1996-09-18

Similar Documents

Publication Publication Date Title
US5897088A (en) Retaining strap
US5104079A (en) Supporting clamp for mounting constructional components, for example tubes or the like
JPH0519436U (en) Hanging scaffold fixing bracket
JPH0752887Y2 (en) Formwork panel support device
JP2924659B2 (en) Construction method of assembling scaffold
JP2510604Y2 (en) Hanging scaffold fixing bracket
JP2716686B2 (en) Hanging equipment such as ducts
JPH051059Y2 (en)
GB2057547A (en) Clamping apparatus
JPH0312107Y2 (en)
JP2000073579A (en) Free-shaped fixing metal fitting
JP2967977B2 (en) Combination device of support and wall plate
JPH0541157Y2 (en)
JPH0240687Y2 (en)
JP3443190B2 (en) Work stage mounting bracket and work stage
JPH11303382A (en) Scaffolding board holder for pipe scaffolding frame
JPH0527631Y2 (en)
JPH0618991Y2 (en) Reinforcing bar support for construction
JPH074283Y2 (en) Clamp device for fixing formwork
JPH0448275Y2 (en)
JPS58191850A (en) Joint method of reinforcing steel wire
JPH0217237Y2 (en)
JPH0627848Y2 (en) Supporting bracket for hanging rod members
JPH0626196A (en) Anchoring method of concrete form and holding hardware used therefor
JPH0451371Y2 (en)

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 19960312