JPH05179899A - Construction method of underground cavity - Google Patents

Construction method of underground cavity

Info

Publication number
JPH05179899A
JPH05179899A JP3359643A JP35964391A JPH05179899A JP H05179899 A JPH05179899 A JP H05179899A JP 3359643 A JP3359643 A JP 3359643A JP 35964391 A JP35964391 A JP 35964391A JP H05179899 A JPH05179899 A JP H05179899A
Authority
JP
Japan
Prior art keywords
lining
tunnel
underground cavity
rock
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP3359643A
Other languages
Japanese (ja)
Other versions
JP2514514B2 (en
Inventor
Yukinobu Ujimoto
幸伸 氏本
Kenzo Mizuhara
憲三 水原
Tetsuo Shimamoto
哲郎 島本
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Okumura Corp
Original Assignee
Okumura Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Okumura Corp filed Critical Okumura Corp
Priority to JP3359643A priority Critical patent/JP2514514B2/en
Publication of JPH05179899A publication Critical patent/JPH05179899A/en
Application granted granted Critical
Publication of JP2514514B2 publication Critical patent/JP2514514B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

PURPOSE:To construct an underground cavity of large cross section for an underground power plant, an oil storage tank, or the like efficiently in the rock-bed. CONSTITUTION:In the rock-bed A, tunnels 2a, 2b... of rectangular cross section and desired height, and closed ring-shape linkings 3a, 3b... formed by concrete placing to the inside of the tunnels are formed successively in the stacked state along the border line of a planned underground cavity B from its lower end part to its top part, thus constructing a dome lining C to be the wall body of the planned underground cavity B. The rock-bed D surrounded by the dome lining C is then excavated down from the top side to construct the underground cavity D.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は岩盤中に、地下発電所や
石油貯蔵用地下タンクなどの直径が数十m〜100 m程度
の半球状ないしはドーム状の大規模な地下空洞を構築す
る方法に関するものである。
The present invention relates to a method for constructing a large-scale hemispherical or dome-shaped underground cavity having a diameter of several tens to 100 m, such as an underground power plant or an underground tank for oil storage, in bedrock. It is about.

【0002】[0002]

【従来の技術】従来から、岩盤中にこのような大規模な
地下空洞を構築する方法としては、まず、岩盤中に計画
地下空洞の上端部に相当する部分を掘削したのち、その
掘削壁面にコンクリート覆工を施し、次いで、ベンチカ
ット工法によって計画地下空洞内の岩盤を適宜深さずつ
掘り下げながら、順次、掘削壁面にコンクリート覆工を
施す構築方法が採用されている。
2. Description of the Related Art Conventionally, as a method of constructing such a large-scale underground cavern in bedrock, first, a portion corresponding to the upper end of the planned underground cavern is excavated in the bedrock, and then the excavated wall surface is excavated. A construction method is used in which concrete lining is applied, and then the bench cut method is used to sequentially dig the rock in the planned underground cavity at appropriate depths while sequentially lining the excavated wall.

【0003】[0003]

【発明が解決しようとする課題】しかしながら、このよ
うな方法によれば、計画地下空洞内の適宜高さ部分の広
い岩盤区域を掘削する毎にコンクリート覆工を順次施し
ていくものであるから、岩盤掘削作業に著しい手間を要
して、その作業が終了しなければ次の覆工作業に移るこ
とができないために、作業能率が悪くて工期が著しく長
期化するという問題点がある。
However, according to such a method, concrete lining is sequentially performed every time a wide rock area having a suitable height in the planned underground cavity is excavated. Since the rock excavation work requires a great deal of work and cannot be moved to the next lining work unless the work is completed, there is a problem that the work efficiency is poor and the construction period is significantly prolonged.

【0004】さらに、ベンチカットによって掘削する際
に、発破をかけて岩盤の破壊を行うが、その発破時にお
ける振動が構築中のコンクリート覆工に伝達して該覆工
に亀裂が生じ、また、周囲の地域に振動公害を及ぼす等
の問題点があった。本発明はこのような問題点を全面的
に解消し得る新規な地下空洞の構築方法の提供を目的と
するものである。
Further, when excavating by bench cut, the rock is destroyed by blasting, but the vibration at the time of blasting is transmitted to the concrete lining under construction and the lining is cracked. There were problems such as vibration pollution in the surrounding area. It is an object of the present invention to provide a novel method for constructing an underground cavern capable of completely eliminating such problems.

【0005】[0005]

【課題を解決するための手段】上記目的を達成するため
に、本発明の地下空洞の構築方法は、岩盤中に形成すべ
き計画地下空洞の輪郭線の下端部に沿って閉鎖環状トン
ネルを掘削したのち、このトンネル内にコンクリートを
打設して覆工を形成し、次に、該覆工の上側に前記閉鎖
環状トンネルと同様にして計画地下空洞の輪郭線に沿っ
て閉鎖環状トンネルを掘削したのち、該トンネル内にコ
ンクリートを打設することにより上記覆工上に連続する
覆工を形成し、この作業を計画地下空洞の輪郭線に沿っ
て順次上方に向かって繰り返し施工することにより計画
地下空洞の覆工を形成し、しかるのち、該覆工内の岩盤
を掘削することを特徴とするものである。
In order to achieve the above object, the method for constructing an underground cavity of the present invention is to excavate a closed annular tunnel along the lower end of the contour line of a planned underground cavity to be formed in bedrock. After that, concrete is poured into this tunnel to form a lining, and then a closed annular tunnel is excavated along the contour line of the planned underground cavity on the upper side of the lining in the same manner as the closed annular tunnel. After that, a concrete lining is placed in the tunnel to form a continuous lining on the lining, and this work is repeatedly carried out upward along the contour line of the planned underground cavity. The method is characterized by forming a lining of an underground cavity, and then excavating the bedrock in the lining.

【0006】又、本発明方法において、上記請求項2に
記載しているように、前記閉鎖環状トンネル内にコンク
リート覆工を形成するに際して、トンネルの内周側に空
間部を存した状態となるように該トンネル内に前記コン
クリート覆工を施し、その内周側空間に掘削ずり又は発
泡コンクリートを打設しておくことが望ましい。
Further, in the method of the present invention, when the concrete lining is formed in the closed annular tunnel as described in claim 2, a space is present on the inner peripheral side of the tunnel. As described above, it is desirable that the concrete lining is provided in the tunnel, and excavated shear or foam concrete is placed in the space on the inner peripheral side thereof.

【0007】[0007]

【作用】計画地下空洞の輪郭線に沿って下方から上方に
向かって所定高さと幅を有する閉鎖環状トンネルを順次
掘削しながら該トンネル内にコンクリート覆工を施して
いくものであるから、計画地下空洞の内部岩盤を掘削す
ることなく、該計画地下空洞の全覆工が形成される。次
いで、この覆工で囲まれた岩盤をベンチカット工法等に
よって連続的に掘削、除去することによって、地下空洞
が形成される。この際、覆工形成時に、該覆工の内面側
に、予め、掘削ずり又は発泡コンクリートを被覆してお
くことによって、発破時における振動等が覆工に直接作
用するのを防止することができ、また、周囲の地域に振
動公害を及ぼすこともない。
[Operation] Concrete lining is performed inside the tunnel while excavating a closed annular tunnel with a predetermined height and width from the bottom to the top along the contour line of the planned underground cavity. The entire lining of the planned underground cavern is formed without excavating the internal rock mass of the cavern. Then, the rock surrounded by this lining is continuously excavated and removed by a bench cut method or the like to form an underground cavity. At this time, when the lining is formed, the inner surface of the lining can be covered with excavation shearing or foam concrete in advance to prevent vibration or the like at the time of blast from directly acting on the lining. Also, it does not cause vibration pollution in the surrounding area.

【0008】[0008]

【実施例】本発明の実施例を図面について説明すると、
岩盤Aの所望個所に石油貯溜タンク等の大断面の地下空
洞を築造するに際して、まず、図1に示すように、外部
から計画地下空洞Bの下端部に達するアクセストンネル
1を掘削したのち、該アクセストンネル1から計画地下
空洞Bの輪郭線の下端部に沿って水平方向に所定の湾曲
度で屈曲させながら3〜4m角の断面矩形状の閉鎖環状
トンネル2aを掘削する。この閉鎖環状トンネル2aは図に
示すように円形状に限らず、矩形状その他の適宜な形状
であってもよい。
Embodiments of the present invention will now be described with reference to the drawings.
When constructing a large-section underground cavern such as an oil storage tank at a desired location on the bedrock A, first, as shown in FIG. 1, after excavating the access tunnel 1 reaching the lower end of the planned underground cavern B from the outside, A closed annular tunnel 2a having a rectangular cross section of 3 to 4 m square is excavated from the access tunnel 1 along the lower end of the contour line of the planned underground cavity B while being horizontally bent at a predetermined curvature. The closed annular tunnel 2a is not limited to a circular shape as shown in the figure, but may be a rectangular shape or any other suitable shape.

【0009】又、掘削手段としては、適宜な溝孔掘削機
を使用して、図2に示すように、岩盤面にトンネル断面
形状の外周に沿ってトンネル長さ方向に適宜深さの溝孔
11を連続形成すると共にこの外周溝孔11で囲まれた岩盤
面を同じく縦横の溝孔12、13で分割し、これらの溝孔11
〜13で囲まれた岩盤部分に発破孔14を穿設して爆薬を装
填、爆破させることにより掘削する。又、必要に応じて
適宜な岩盤掘削機を採用することもできる。掘削した岩
石はアクセストンネル1を使用して外部に排出する。
Further, as the excavation means, an appropriate slot excavator is used, and as shown in FIG. 2, a slot having an appropriate depth in the tunnel length direction is formed along the outer circumference of the tunnel cross-section on the rock surface.
11 is continuously formed, and the rock surface surrounded by the outer peripheral slot 11 is also divided by vertical and horizontal slots 12, 13 to form the slot 11
A blast hole 14 is bored in a rock part surrounded by 13 to load explosives and explode to excavate. Further, an appropriate rock excavator can be adopted as needed. The excavated rock is discharged to the outside using the access tunnel 1.

【0010】このように計画地下空洞Bの輪郭線の下端
部に沿って順次、適宜長さのトンネル部分を掘削して一
連に連通させることにより、上記のような閉鎖環状トン
ネル2aを形成する。この閉鎖環状トンネル2aの掘削に後
続しながら、或いは掘削後において、該トンネル2a内に
型枠を組立て、図3に示すように、配筋15したのちコン
クリートを打設してコンクリート覆工3aを形成する。こ
の際、トンネル2a内にコンクリートが全体的に充満する
ように打設してもよいが、トンネル内周部分に空間部4
がトンネル長さ方向に連続的に設けるようにして、該空
間部4以外のトンネル2a内にコンクリートを打設するこ
とにより覆工3aを形成することが望ましい。
Thus, the closed annular tunnel 2a as described above is formed by sequentially excavating a tunnel portion of an appropriate length along the lower end of the contour line of the planned underground cavity B and connecting them in series. Subsequent to or after excavation of the closed annular tunnel 2a, a formwork is assembled in the tunnel 2a, and as shown in FIG. Form. At this time, the concrete may be poured into the tunnel 2a so that the concrete is entirely filled, but the space 4
It is desirable to form the lining 3a by placing concrete in the tunnel 2a other than the space 4 so that the lining 3a is continuously provided in the tunnel length direction.

【0011】一方、前記アクセストンネル1に連通して
計画地下空洞Bの輪郭線の内周側に沿って、図5に示す
ように、作業トンネル5を上方に向かって螺旋傾斜状に
掘削し、その上端を計画地下空洞Bの頂部内周面にまで
設けると共に該頂部から垂直方向に立坑6を掘削する。
これらの作業トンネル5及び立坑6は、コンクリート覆
工の施工と前後して別個に行ってもよいが、該コンクリ
ート覆工に先行しながら並行して行うことが好ましい。
On the other hand, as shown in FIG. 5, the working tunnel 5 is excavated in an upward spiral shape so as to communicate with the access tunnel 1 along the inner peripheral side of the contour line of the planned underground cavity B, The upper end is provided up to the inner peripheral surface of the top of the planned underground cavity B, and the vertical shaft 6 is excavated in the vertical direction from the top.
The work tunnel 5 and the vertical shaft 6 may be separately performed before and after the construction of the concrete lining, but it is preferable to perform the work tunnel 5 in parallel with the concrete lining.

【0012】そして、上記計画地下空洞Bの輪郭線の最
下端部に設けた上記閉鎖環状トンネル2a内に打設したコ
ンクリートが硬化した後に、このコンクリート覆工3a上
に重なるようにして図3、図4に示すように、計画地下
空洞Bの輪郭線に沿う次の閉鎖環状トンネル2bを、該閉
鎖環状トンネル2bの高さ位置に対応する上記螺旋傾斜作
業トンネル5の一部から連続的に掘削する。この際、コ
ンクリート覆工3aが全体的に硬化するのを待つことなく
硬化した部分の上にトンネル2bを上記掘削手段によって
掘削すればよい。
Then, after the concrete placed in the closed annular tunnel 2a provided at the lowermost end of the contour line of the planned underground cavity B is hardened, the concrete is lined up on the concrete lining 3a as shown in FIG. As shown in FIG. 4, the next closed annular tunnel 2b along the contour line of the planned underground cavity B is continuously excavated from a part of the spiral inclined work tunnel 5 corresponding to the height position of the closed annular tunnel 2b. To do. At this time, the tunnel 2b may be excavated by the excavation means above the hardened portion without waiting for the concrete lining 3a to be entirely hardened.

【0013】この掘削時において破砕された岩盤のずり
の一部がその下方に連通する前記コンクリート覆工3aの
内周側の空間部4内に落下し、該空間部4がずり7によ
って充填され、後の岩盤破砕時における発破によるコン
クリート覆工の破損等を防止する。なお、このずり7を
空間部4内に充満させる代わりに、該空間部に発泡モル
タルなどの緩衝材を充填させてもよい。次いで、閉鎖環
状に掘削されたトンネル2b内に前記同様にしてその内周
側に空間部4を残こしてコンクリート覆工3bを形成し、
下方側のコンクリート覆工3a上に一体化させる。
A part of the shear of the rock mass crushed during this excavation falls into the space 4 on the inner peripheral side of the concrete lining 3a communicating therewith, and the space 4 is filled with the shear 7. Prevent damage to concrete linings due to blasting during subsequent rock crushing. Instead of filling the space 7 with the shear 7, the space may be filled with a cushioning material such as foamed mortar. Then, a concrete lining 3b is formed in the tunnel 2b excavated in a closed ring, leaving the space 4 on the inner peripheral side in the same manner as described above.
It is integrated on the lower concrete lining 3a.

【0014】このようにして、計画地下空洞Bの輪郭線
に沿って該空洞頂部まで、所定高さ毎に順次コンクリー
ト覆工3a、3b、3c・・・を積み重ね状に形成し、図5に
示すように、計画地下空洞Bの壁体となるドーム形状の
覆工Cを形成する。なお、コンクリート覆工3a、3b、3c
・・・は、上述したように、その高さ位置の内周面側に
位置する螺旋傾斜作業トンネル5を利用して各覆工形成
用トンネルを掘削したが、各トンネル2a、2b、2c・・・
にはコンクリート覆工を施工しない空間部4を形成して
おくので、この空間部4を使用して上側のトンネルを掘
削してもよい。
In this way, concrete linings 3a, 3b, 3c ... are sequentially formed in a stack at predetermined heights along the contour line of the planned underground cavern B to the top of the cavern, as shown in FIG. As shown, a dome-shaped lining C that forms the wall of the planned underground cavity B is formed. In addition, concrete lining 3a, 3b, 3c
As described above, the lining formation tunnels were excavated by using the spiral inclined work tunnel 5 located on the inner peripheral surface side of the height position, but each tunnel 2a, 2b, 2c.・ ・
Since the space portion 4 in which no concrete lining is constructed is formed in this, the space portion 4 may be used to excavate the upper tunnel.

【0015】計画地下空洞Bの覆工Cの形成後、該覆工
Cの頂部から覆工Cの形成中、或いは形成後に掘削され
た立坑6の周囲の岩盤を、図6に示すように、発破によ
る破砕を使用したベンチカット工法によって所定深さず
つ、順次掘り下げていく。なお、掘削したずりの搬出や
機材の搬入等は、作業トンネル5と立坑6を使用して行
う。発破の際に、覆工Cと計画地下空洞B内の岩盤Dと
は上記のように空間部4内に充填しているずり7又は発
泡モルタルによって縁切りされているので、発破振動が
該ずり7や発泡モルタルで吸収、遮断されて覆工Cに伝
達するのを防止することができる。
After the formation of the lining C of the planned underground cavity B, the rock mass around the shaft 6 excavated from the top of the lining C during the formation of the lining C or after the formation of the lining C is shown in FIG. A bench cut method that uses crushing by blasting is used to sequentially dig a specified depth. The work tunnel 5 and the shaft 6 are used to carry out the excavated skid and carry in the equipment. At the time of blasting, since the lining C and the bedrock D in the planned underground cavity B are edged by the shear 7 or foam mortar filling the space 4 as described above, the blasting vibration is caused by the shear 7. It is possible to prevent the oil from being absorbed or blocked by the foamed mortar and transmitted to the lining C by being blocked.

【0016】こうして、覆工Cで囲まれている計画地下
空洞Bの岩盤Dを最下部のコンクリート覆工3aの位置ま
で掘削、除去することによって図7に示すような地下空
洞を構築し、構築後、必要に応じて、その底面にコンク
リート覆工3aに連なる床壁をコンクリートの打設によっ
て形成してもよい。
In this way, by excavating and removing the bedrock D of the planned underground cavity B surrounded by the lining C to the position of the concrete lining 3a at the bottom, an underground cavity as shown in FIG. 7 is constructed and constructed. Thereafter, if necessary, a floor wall connected to the concrete lining 3a may be formed on the bottom surface by pouring concrete.

【0017】[0017]

【発明の効果】以上のように本発明の地下空洞の構築方
法によれば、計画地下空洞の輪郭線に沿ってその下端部
から頂部に向かって順次一定高さの断面形状を有するト
ンネルと該トンネル内に対するコンクリート打設による
閉鎖環状の覆工とを積み重ね状態に形成するものである
から、計画地下空洞内の岩盤を掘削することなく、まず
計画地下空洞の壁体となるドーム状の覆工を能率よく築
造することができ、次いで、このドーム状の覆工内に囲
まれた岩盤を掘削するものであるから、大容積の岩盤を
連続的に掘削することができて作業能率が著しく向上
し、工期の短縮を図ることができる。
As described above, according to the method for constructing an underground cavern of the present invention, a tunnel having a cross-sectional shape of a constant height sequentially from the lower end to the top along the contour line of the planned underground cavern is provided. Since the closed annular lining by placing concrete in the tunnel is formed in a stacked state, the dome-shaped lining that will become the wall of the planned underground cavity without first excavating the rock in the planned underground cavity Can be constructed efficiently, and then the rock bed surrounded by this dome-shaped lining is to be excavated, so a large volume of rock bed can be continuously excavated, and work efficiency is significantly improved. However, the construction period can be shortened.

【0018】さらに、覆工内で岩盤の掘削、破砕作業を
頂部から下方に向かって行うので、岩盤崩落の危険性も
なく、安全に作業し得ると共に、空洞周辺の岩盤を弛緩
させることがないから、大断面の無支柱地下空洞の構築
が可能となるものである。また、順次積み重ね状に形成
される各コンクリート覆工の内周面側に、ずりや発泡コ
ンクリート等の緩衝材を充填しておくことによって、覆
工内の岩盤を発破により破砕させる際に生じる振動を覆
工側に殆ど伝達させることなく、覆工の損傷を防止して
強固な地下空洞を築造することができると共に周囲の地
域に振動公害を及ぼすこともない。
Furthermore, since the rock excavation and crushing work is performed from the top downward in the lining, there is no risk of rock collapse, safe work is possible, and rock around the cavity is not relaxed. Therefore, it is possible to construct a pillarless underground cavity with a large cross section. In addition, by filling the inner peripheral side of each concrete lining that is sequentially stacked with a cushioning material such as shear or foam concrete, the vibration that occurs when the rock in the lining is crushed by blasting With almost no transmission to the lining side, damage to the lining can be prevented, a strong underground cavity can be built, and vibration pollution is not given to the surrounding area.

【図面の簡単な説明】[Brief description of drawings]

【図1】計画地下空洞の簡略透視図、[Figure 1] Simplified perspective view of the planned underground cavity,

【図2】トンネル掘削手段を説明するためのトンネル切
羽面の正面図、
FIG. 2 is a front view of a tunnel face for explaining the tunnel excavating means,

【図3】最下部のトンネル内にコンクリート覆工を形成
した状態の断面図、
FIG. 3 is a cross-sectional view of a concrete lining formed in the lowermost tunnel,

【図4】コンクリート覆工を上方に向かって順次形成し
た状態の断面図、
FIG. 4 is a cross-sectional view showing a state in which concrete linings are sequentially formed upwards,

【図5】立坑及び螺旋傾斜作業トンネルを設けた状態の
簡略断面図、
FIG. 5 is a simplified sectional view showing a state in which a vertical shaft and a spiral inclined work tunnel are provided,

【図6】覆工内の岩盤の掘削状態を示す簡略断面図、FIG. 6 is a simplified cross-sectional view showing an excavated state of rock in the lining,

【図7】地下空洞の断面図。FIG. 7 is a sectional view of an underground cavity.

【符号の説明】[Explanation of symbols]

2a 閉鎖環状トンネル 2b 閉鎖環状トンネル 3a コンクリート覆工 3b コンクリート覆工 4 空間部 5 螺旋傾斜作業トンネル 6 立坑 7 緩衝材 A 岩盤 B 計画地下空洞 C 覆工 D 岩盤 2a Closed circular tunnel 2b Closed circular tunnel 3a Concrete lining 3b Concrete lining 4 Space 5 Spiral inclined work tunnel 6 Vertical shaft 7 Buffer material A Rock B Planned underground cavity C Lining D Rock

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 岩盤中に形成すべき計画地下空洞の輪郭
線の下端部に沿って閉鎖環状トンネルを掘削したのち、
このトンネル内にコンクリートを打設して覆工を形成
し、次に、該覆工の上側に前記閉鎖環状トンネルと同様
にして計画地下空洞の輪郭線に沿って閉鎖環状トンネル
を掘削したのち、該トンネル内にコンクリートを打設す
ることにより上記覆工上に連続する覆工を形成し、この
作業を計画地下空洞の輪郭線に沿って順次上方に向かっ
て繰り返し施工することにより計画地下空洞の覆工を形
成し、しかるのち、該覆工内の岩盤を掘削することを特
徴とする地下空洞の構築方法。
1. After excavating a closed annular tunnel along the lower end of the contour line of a planned underground cavity to be formed in rock,
After placing concrete in this tunnel to form a lining, and then excavating the closed annular tunnel along the contour line of the planned underground cavity in the same manner as the closed annular tunnel above the lining, A continuous lining is formed on the lining by placing concrete in the tunnel, and this work is repeatedly performed in the upward direction along the contour line of the planned underground cavity. A method for constructing an underground cavity, which comprises forming a lining, and then excavating rock in the lining.
【請求項2】 前記閉鎖環状トンネル内にコンクリート
覆工を形成するに際して、トンネルの内周側に空間部を
存した状態となるように該トンネル内に前記コンクリー
ト覆工を施し、その内周側空間に掘削ずり又は発泡コン
クリートを打設しておくことを特徴とする請求項1記載
の地下空洞の構築方法。
2. When forming a concrete lining in the closed annular tunnel, the concrete lining is applied to the inside of the tunnel so that there is a space on the inside of the tunnel, and the inside of the tunnel is covered. The method for constructing an underground cavity according to claim 1, wherein excavation shearing or foam concrete is placed in the space.
JP3359643A 1991-12-26 1991-12-26 How to build an underground cavity Expired - Fee Related JP2514514B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3359643A JP2514514B2 (en) 1991-12-26 1991-12-26 How to build an underground cavity

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3359643A JP2514514B2 (en) 1991-12-26 1991-12-26 How to build an underground cavity

Publications (2)

Publication Number Publication Date
JPH05179899A true JPH05179899A (en) 1993-07-20
JP2514514B2 JP2514514B2 (en) 1996-07-10

Family

ID=18465554

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3359643A Expired - Fee Related JP2514514B2 (en) 1991-12-26 1991-12-26 How to build an underground cavity

Country Status (1)

Country Link
JP (1) JP2514514B2 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107288654A (en) * 2017-06-27 2017-10-24 长江勘测规划设计研究有限责任公司 Super-span dome hollow ring in underground nuclear reactor cavern excavates structure and excavation method
CN111594269A (en) * 2020-05-18 2020-08-28 中铁第一勘察设计院集团有限公司 Underground oil gas tunnel storage tank structure and construction method thereof
CN113389579A (en) * 2021-07-30 2021-09-14 中铁十一局集团第五工程有限公司 Excavation method of underground large-space vertical tank body
CN113863243A (en) * 2021-10-23 2021-12-31 中电建十一局工程有限公司 Construction method for quickly excavating underground powerhouse of hydropower station
CN114109449A (en) * 2021-11-22 2022-03-01 中国电建集团成都勘测设计研究院有限公司 Large-span underground cavern dome supporting structure

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02229399A (en) * 1989-02-28 1990-09-12 Hitachi Constr Mach Co Ltd Construction method of underground structure

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02229399A (en) * 1989-02-28 1990-09-12 Hitachi Constr Mach Co Ltd Construction method of underground structure

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107288654A (en) * 2017-06-27 2017-10-24 长江勘测规划设计研究有限责任公司 Super-span dome hollow ring in underground nuclear reactor cavern excavates structure and excavation method
CN111594269A (en) * 2020-05-18 2020-08-28 中铁第一勘察设计院集团有限公司 Underground oil gas tunnel storage tank structure and construction method thereof
CN113389579A (en) * 2021-07-30 2021-09-14 中铁十一局集团第五工程有限公司 Excavation method of underground large-space vertical tank body
CN113863243A (en) * 2021-10-23 2021-12-31 中电建十一局工程有限公司 Construction method for quickly excavating underground powerhouse of hydropower station
CN114109449A (en) * 2021-11-22 2022-03-01 中国电建集团成都勘测设计研究院有限公司 Large-span underground cavern dome supporting structure
CN114109449B (en) * 2021-11-22 2023-08-08 中国电建集团成都勘测设计研究院有限公司 Large-span underground cavern dome supporting structure

Also Published As

Publication number Publication date
JP2514514B2 (en) 1996-07-10

Similar Documents

Publication Publication Date Title
AU726015B2 (en) Undercut excavation with protection against seismic events or excessive ground movement
US20090269146A1 (en) Method for Construction of Piles and Caissons and Soil Improvement by Using Rubber Hoses
CA2079694C (en) Undercut excavation method
JP2514514B2 (en) How to build an underground cavity
KR100289256B1 (en) Tunnel construction method in shallow toffee area
CN105019431B (en) Crush and complete alternate steep dip stratified rock masses Large Diameter Super-long Bored Piles construction method
US3921410A (en) System and method of permafrost pile forming
SU946409A3 (en) Method for driving lower ends of sheet piles into base soil in erecting sheet piling wall
US3336760A (en) Construction of support columns in soil
JP2604210B2 (en) Construction method of underground large-scale spatial structure
US2952130A (en) Pile
JPS5810532B2 (en) Concrete structure destruction method
JP3142883B2 (en) Method of forming a rock cavity with a spherical rock cavity or partial spherical portion
JP3486103B2 (en) How to blast rock
JPH0726406B2 (en) How to construct an underground structure
CN114482091B (en) Construction method of slope anchoring pile
CN113405420B (en) Boundary control cutter and blasting device and method for nuclear power foundation pit energy-gathered cutting
US2203978A (en) Means and method of shoring bell bottom pile holes
KR102492406B1 (en) Steel pipe piling method using vibro hammer
JPH02112600A (en) Excavating and constructing method of underground large-sized cavity
JPH0317398A (en) Construction of roof for underground structure
JPH0562170B2 (en)
JPS62158690A (en) Underground storage facility and execution method thereof
US1665797A (en) Method of excavating and producing foundations
JPH09328999A (en) Method for excavating large scale underground cavity

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees