JPH05132939A - Installation method of underwater strut - Google Patents

Installation method of underwater strut

Info

Publication number
JPH05132939A
JPH05132939A JP32412091A JP32412091A JPH05132939A JP H05132939 A JPH05132939 A JP H05132939A JP 32412091 A JP32412091 A JP 32412091A JP 32412091 A JP32412091 A JP 32412091A JP H05132939 A JPH05132939 A JP H05132939A
Authority
JP
Japan
Prior art keywords
underwater
protection walls
struts
beams
landslide
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP32412091A
Other languages
Japanese (ja)
Other versions
JP2939777B2 (en
Inventor
Tetsuya Hirose
哲也 廣瀬
Kunihiro Ogasawara
邦洋 小笠原
Kiyoshi Onozawa
潔 小野沢
Kennosuke Watanabe
健之助 渡辺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP32412091A priority Critical patent/JP2939777B2/en
Publication of JPH05132939A publication Critical patent/JPH05132939A/en
Application granted granted Critical
Publication of JP2939777B2 publication Critical patent/JP2939777B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

PURPOSE:To facilitate underwater construction work by manufacturing temporary bearing beams capable of piling struts in a plurality of stages, suspending and installing them after land slide protection walls are constructed, and suspending the struts with the progress of excavation to indicate the landslide protection walls. CONSTITUTION:On the ground, temporary bearing beams 1 and 2 having two stages of up and down providing construction jacks 21 to the sides are manufactured. The temporary bearing beams 1 and 2 is so constructed that struts 4 can be piled up in a plurality of stages. After landslide-protection walls are constructed on the ground, suspension lanes 6 are installed, the temporary bearing beams 1 and 2 are suspended with cables 3, and the landslide protection walls are held by the construction jacks 21. After that, the struts 4,... are suspended in accordance with the progress of excavation of the landslide protection walls 5, the landslide protection walls 5 are temporarily held and, at the same time, the struts are provided between the landslide protection walls 5 from the top to the bottom. According to the constitution, underwater construction can be mechanically made, and underwater work by divers and others can be omitted.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、水中切梁の設置方法に
関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of installing an underwater girder.

【0002】[0002]

【従来の技術】近年、都市における大深度地下利用のニ
ーズが高まっており、そのため大深度掘削工法の開発が
急がれている。現在、大深度掘削に対して有効な方法の
一つとして、掘削を水中で行うことにより、山留め壁に
作用する土圧、水圧を低減させる方法がある。この水中
掘削は、図10に示すように、従来はダイバーが水中に
入り、一般立坑で切梁を設置するのと同様の方法で、水
中で山留め壁a間に切梁bを設置していた。
2. Description of the Related Art In recent years, there is an increasing need for deep underground use in cities, and therefore, the development of a deep depth excavation method is urgent. At present, as one of effective methods for deep-depth drilling, there is a method of reducing the earth pressure and water pressure acting on the retaining wall by performing the drilling underwater. In this underwater excavation, as shown in FIG. 10, conventionally, a diver enters the water and installs a crossbeam b between the mountain retaining walls a in water by the same method as installing a crossbeam in a general shaft. ..

【0003】[0003]

【発明が解決しようとする課題】上記の従来技術には、
次のような問題点が存在する。 <イ>水中での重量物の取扱いになるため、一般の切梁
設置方法よりも危険度が高い。 <ロ>水中作業のため、一般の切梁設置方法よりも施工
時間が掛かる。 <ハ>人が水中で作業するため、切梁設置の深さに限界
があり、大深度掘削のニーズに対応が困難である。
DISCLOSURE OF THE INVENTION Problems to be Solved by the Invention
There are the following problems. <B> Since heavy objects are handled underwater, the level of danger is higher than that of general cutting beam installation methods. <B> Since it is an underwater operation, it takes more time than the general method of installing a crossbeam. <C> Since people work underwater, there is a limit to the depth of cutting beams that can be installed, making it difficult to meet the needs for deep drilling.

【0004】[0004]

【課題を解決するための手段】本発明は、上記のような
問題点を解決するためになされたもので、水中における
切梁の設置作業を迅速かつ容易に行うことができる水中
切梁の設置方法を提供することを目的とする。即ち、本
発明は、山留め壁間の地盤を水中掘削する際に、山留め
壁間に設置する切梁の設置方法において、複数段に切梁
を積み重ねてケーブルで吊り下げ可能に連結し、山留め
壁間の掘削の進行に追従して切梁を吊り下ろし、最下段
及びその上段の切梁により盛替えながら山留め壁を仮支
持すると共に、際上段の切梁から順に下方に切梁を山留
め壁間に設置することを特徴とした、水中切梁の設置方
法である。
SUMMARY OF THE INVENTION The present invention has been made to solve the above-mentioned problems, and an installation of an underwater girder capable of quickly and easily performing an installation work of an underwater girder. The purpose is to provide a method. That is, the present invention, when excavating the ground between the mountain retaining walls underwater, in the method of installing the beams to be installed between the mountain retaining walls, stacking the beams in a plurality of stages and connecting them so that they can be suspended by a cable. The sill beams are suspended according to the progress of excavation in between, and the mountain retaining walls are temporarily supported while being rearranged by the lower and upper tier beams, and the sill beams are placed between the mountain retaining walls in descending order from the upper tier beam. It is a method of installing an underwater girder, which is characterized by being installed in.

【0005】[0005]

【実施例】以下、図面を参照しながら、本発明の一実施
例について説明する。 <イ>仮支持梁(図1、7) 仮支持梁は、図1に示すように、切梁群の最下段とその
上段の二段に設け、上段及び下段仮支持梁1、2とす
る。図7は上段仮支持梁1を示すが、下段仮支持梁2も
同じ構造である。これらの仮支持梁は、中空構造とし、
水中において浮力にて自重を小さく抑えられるよう構成
する。また、側面には架設用ジャッキ11、21を装備
し、これらを突出させることによって、周囲の山留め壁
を押さえて仮支持することができる。そして、上下仮支
持梁1、2は、吊下げケーブル3により上下方向に連結
する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the present invention will be described below with reference to the drawings. <B> Temporary Support Beams (FIGS. 1 and 7) Temporary support beams are provided at the lowermost stage and the upper stage of the beam group, as shown in FIG. 1, to form upper and lower temporary support beams 1 and 2. .. Although FIG. 7 shows the upper temporary support beam 1, the lower temporary support beam 2 has the same structure. These temporary support beams have a hollow structure,
It is constructed so that its own weight can be kept small by buoyancy in water. In addition, the side walls are provided with erection jacks 11 and 21, and by projecting these, the surrounding mountain retaining wall can be pressed and temporarily supported. Then, the upper and lower temporary support beams 1 and 2 are connected to each other in the vertical direction by the suspension cable 3.

【0006】<ロ>切梁(図1、8、9) 切梁4は、図1に示すように、上段仮支持梁1の上部に
積み重ねた部分であり、仮支持梁と同様に中空構造と
し、水中重量を小さくする。図8、9に切梁4の構造を
示す。この切梁4は、底面外周縁部に型枠チューブ41
を設置し、この型枠チューブ41内には、型枠チューブ
用注入管42を介して注入材を充填し、膨張させられる
よう構成する。また、切梁4の側面には、間詰めコンク
リート注入管43と連通する間詰めコンクリート注入口
44を適宜開設する。さらに、吊下げケーブル3を貫通
させるケーブル通し穴45を適宜開設する。
<B> Cut Beam (FIGS. 1, 8 and 9) The cut beam 4 is a portion stacked on the upper part of the upper temporary support beam 1 as shown in FIG. 1, and has a hollow structure similar to the temporary support beam. And reduce the underwater weight. 8 and 9 show the structure of the cross beam 4. The cutting beam 4 has a form tube 41 on the outer peripheral edge of the bottom surface.
The mold tube 41 is filled with an injection material through the mold tube injection pipe 42 so that the mold tube 41 can be expanded. In addition, a filling concrete injection port 44 communicating with the filling concrete injection pipe 43 is appropriately provided on the side surface of the girder 4. Further, a cable through hole 45 for penetrating the hanging cable 3 is appropriately opened.

【0007】<ハ>仮支持梁及びクレーンの配置(図
2、3) 先ず、図2に示すように、地盤に公知の方法により山留
め壁5を構築する。次に、図3に示すように、吊下げク
レーン6を設置し、陸上で作製した上下段仮支持梁1、
2を吊下げケーブル3により吊り下げる。
<C> Arrangement of Temporary Support Beam and Crane (FIGS. 2 and 3) First, as shown in FIG. 2, a mountain retaining wall 5 is constructed on the ground by a known method. Next, as shown in FIG. 3, the suspension crane 6 is installed, and the upper and lower temporary support beams 1, which are produced on land,
2 is suspended by the suspension cable 3.

【0008】<ニ>切梁の配置(図4、5) 次に、図4に示すように、ある程度水中掘削した後、下
段仮支持梁2を吊り下ろし、架設用ジャッキ21を突出
させて山留め壁5を仮支持する。そして、図5に示すよ
うに、上段仮支持梁1の上部に所要数の切梁4を積み重
ねて配置し、吊下げケーブル3により連結する。
<D> Arrangement of Girder (FIGS. 4 and 5) Next, as shown in FIG. 4, after underwater excavation to some extent, the lower stage temporary support beam 2 is hung and the erection jack 21 is projected to make a mountain clasp. Temporarily support the wall 5. Then, as shown in FIG. 5, a required number of cut beams 4 are stacked and arranged on the upper part of the upper temporary support beam 1, and are connected by the hanging cable 3.

【0009】<ホ>切梁の山留め壁間への設置(図1、
6、9) 水中掘削の進行に追従して、図6に示すように切梁群を
吊り下ろし、下段仮支持梁2と上段仮支持梁1を盛替え
ながら山留め壁5を仮支持すると共に、際上段の切梁4
から順に下方に山留め壁5間に設置する。切梁4の設置
に当たっては、図9に示すように、型枠チューブ41を
膨脹させて山留め壁5に密着させ、その上部に間詰めコ
ンクリート注入管43を介して、間詰めコンクリート4
6を打設して一体化を図る。以上の作業を繰り返すこと
によって、図1に示すように所定の深度まで切梁4を設
置し、作業を終了する。
<E> Installation of the girder between the mountain retaining walls (Fig. 1,
6, 9) Following the progress of the underwater excavation, the group of beams is suspended as shown in FIG. 6, and the mountain retaining wall 5 is temporarily supported while the lower temporary support beam 2 and the upper temporary support beam 1 are rearranged, Girder 4 on the upper stage
It is installed between the mountain retaining walls 5 in order from the bottom. When installing the girder 4, as shown in FIG. 9, the formwork tube 41 is inflated and brought into close contact with the mountain retaining wall 5, and the space-filled concrete 4 is inserted above the space-filled concrete injection pipe 43.
6 is placed to achieve integration. By repeating the above work, the crossbeam 4 is installed to a predetermined depth as shown in FIG. 1, and the work is completed.

【0010】[0010]

【本発明の効果】本発明は以上説明したようになるた
め、次のような効果を得ることができる。 <イ>切梁を陸上で作製し、かつ機械的に水中架設でき
るため、ダイバーによる水中作業が無くなり、安全に施
工できる。
Since the present invention is as described above, the following effects can be obtained. <B> Since the beams can be produced on land and can be erected mechanically underwater, there is no need for underwater work by divers and safe construction is possible.

【0011】<ロ>水中掘削及び切梁機械式架設により
施工全体の機械化が図られるため、施工能率が向上す
る。
<B> Since the entire construction is mechanized by the underwater excavation and the mechanical installation of the cross beam, the construction efficiency is improved.

【0012】<ハ>掘削及び切梁架設が一定のサイクル
で作業を行えるため、作業手順の変更が無くなり、工程
の短縮が可能となる。
<C> Since excavation and erection of beams can be performed in a fixed cycle, there is no need to change the work procedure and the process can be shortened.

【図面の簡単な説明】[Brief description of drawings]

【図1】 切梁設置完了状態の説明図[Fig. 1] An explanatory diagram of the completed installation of the cross beam

【図2】 山留め壁の構築工程の説明図FIG. 2 is an explanatory view of a construction process of a mountain retaining wall.

【図3】 仮支持梁及びクレーンの配置工程の説明図FIG. 3 is an explanatory diagram of a process of arranging a temporary support beam and a crane.

【図4】 切梁配置工程の説明図FIG. 4 is an explanatory diagram of a cutting beam arrangement process.

【図5】 切梁設置工程の説明図FIG. 5 is an explanatory diagram of a cutting beam installation process.

【図6】 切梁設置工程の説明図FIG. 6 is an explanatory diagram of a cutting beam installation process.

【図7】 仮支持梁の説明図FIG. 7 is an explanatory diagram of a temporary support beam.

【図8】 切梁の説明図FIG. 8 is an explanatory view of a cross beam

【図9】 切梁の説明図FIG. 9 is an explanatory view of a cross beam

【図10】従来技術の説明図FIG. 10 is an explanatory diagram of a conventional technique.

───────────────────────────────────────────────────── フロントページの続き (72)発明者 渡辺 健之助 東京都新宿区西新宿一丁目25番1号 大成 建設株式会社内 ─────────────────────────────────────────────────── ─── Continuation of front page (72) Inventor Kennosuke Watanabe 1-25-1 Nishishinjuku, Shinjuku-ku, Tokyo Taisei Corporation

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 山留め壁間の地盤を水中掘削する際に、
山留め壁間に設置する切梁の設置方法において、 複数段に切梁を積み重ねてケーブルで吊り下げ可能に連
結し、 山留め壁間の掘削の進行に追従して切梁を吊り下ろし、 最下段及びその上段の切梁により盛替えながら山留め壁
を仮支持すると共に、 際上段の切梁から順に下方に切梁を山留め壁間に設置す
ることを特徴とした、 水中切梁の設置方法。
1. When excavating the ground between the mountain retaining walls underwater,
In the method of installing the beams to be installed between the retaining walls, stacking the beams in multiple stages and connecting them so that they can be suspended with a cable, and suspending the beams in accordance with the progress of excavation between the retaining walls, An underwater truss installation method characterized by temporarily supporting the mountain retaining wall while reassembling with the upper beam, and installing the lower beam between the mountain retaining walls in order from the upper beam.
JP32412091A 1991-11-13 1991-11-13 How to install underwater beams Expired - Fee Related JP2939777B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP32412091A JP2939777B2 (en) 1991-11-13 1991-11-13 How to install underwater beams

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP32412091A JP2939777B2 (en) 1991-11-13 1991-11-13 How to install underwater beams

Publications (2)

Publication Number Publication Date
JPH05132939A true JPH05132939A (en) 1993-05-28
JP2939777B2 JP2939777B2 (en) 1999-08-25

Family

ID=18162381

Family Applications (1)

Application Number Title Priority Date Filing Date
JP32412091A Expired - Fee Related JP2939777B2 (en) 1991-11-13 1991-11-13 How to install underwater beams

Country Status (1)

Country Link
JP (1) JP2939777B2 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009074269A (en) * 2007-09-19 2009-04-09 Ohbayashi Corp Underwater structure reinforcing method and underwater structure
CN105155548A (en) * 2015-06-02 2015-12-16 谢纯 Cable double-row pile (wall) supporting structure
CN106592632A (en) * 2016-12-28 2017-04-26 郑倩 Underground supporting structure for reverse construction method and construction method
CN106759383A (en) * 2016-12-28 2017-05-31 郑倩 A kind of reverse construction short section borehole wall pouring structure and construction method
CN112343061A (en) * 2020-10-14 2021-02-09 中建三局第一建设工程有限责任公司 Ultra-deep silt foundation pit transverse support construction device and construction method

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009074269A (en) * 2007-09-19 2009-04-09 Ohbayashi Corp Underwater structure reinforcing method and underwater structure
CN105155548A (en) * 2015-06-02 2015-12-16 谢纯 Cable double-row pile (wall) supporting structure
CN106592632A (en) * 2016-12-28 2017-04-26 郑倩 Underground supporting structure for reverse construction method and construction method
CN106759383A (en) * 2016-12-28 2017-05-31 郑倩 A kind of reverse construction short section borehole wall pouring structure and construction method
CN112343061A (en) * 2020-10-14 2021-02-09 中建三局第一建设工程有限责任公司 Ultra-deep silt foundation pit transverse support construction device and construction method
CN112343061B (en) * 2020-10-14 2021-08-31 中建三局第一建设工程有限责任公司 Ultra-deep silt foundation pit transverse support construction device and construction method
US11280055B1 (en) 2020-10-14 2022-03-22 China Construction Third Bureau First Engineering Co., Ltd. Construction device and method for lateral bracing in ultra-deep foundation pit with silt

Also Published As

Publication number Publication date
JP2939777B2 (en) 1999-08-25

Similar Documents

Publication Publication Date Title
US20100296876A1 (en) Caisson structures and methods for precisely and stably sinking the caisson structures into ground
CN101736744B (en) Self-balancing sinking large-diameter tubular pile and construction method thereof
US3466878A (en) Rig for work at sea,in lakes,lagoons
US3736756A (en) Method and apparatus for assembling an offshore structure
US2236682A (en) Marine foundation and method of construction
CN108179735A (en) A kind of boulder bed large-sized deep water foundation construction platform and method
US3624702A (en) Offshore platform support
JPS6149029A (en) Underwater foundation fixer
CN112195779A (en) Multifunctional trestle construction method suitable for thick pebble layer
JPH05132939A (en) Installation method of underwater strut
CN212926126U (en) Mountain land large-volume arch foundation
CA1075022A (en) Equipment for extracting oil or gas from under the sea bed and method of installing such equipment
JPH07268885A (en) Method of drive construction used for construction of subsurface structure
CN111719581B (en) Building anti-seismic structure and processing technology
CN111236310B (en) Construction method of connecting channel of existing underground structure in weak water-rich stratum
JPS61216915A (en) Construction of breakwater structure
CN209798803U (en) suction cylinder type single pile foundation structure
JPH0381422A (en) Caisson method
JPS6237172B2 (en)
RU2063497C1 (en) Method for erecting foundation
CN212561593U (en) Deep water shallow overburden steel pipe anchor construction equipment
CN113356220B (en) Super high-rise building deep foundation pit and construction method thereof
US3107495A (en) Method of erecting an offshore structure
JP2939776B2 (en) How to install underwater beams
JPH1046597A (en) Execution work method of steel shell caisson

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees