JPH05108656A - Production schedule planning device - Google Patents

Production schedule planning device

Info

Publication number
JPH05108656A
JPH05108656A JP26576891A JP26576891A JPH05108656A JP H05108656 A JPH05108656 A JP H05108656A JP 26576891 A JP26576891 A JP 26576891A JP 26576891 A JP26576891 A JP 26576891A JP H05108656 A JPH05108656 A JP H05108656A
Authority
JP
Japan
Prior art keywords
production
unit
load
time
lot
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP26576891A
Other languages
Japanese (ja)
Inventor
Mariko Hashimoto
真理子 橋本
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NEC Corp
Original Assignee
NEC Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NEC Corp filed Critical NEC Corp
Priority to JP26576891A priority Critical patent/JPH05108656A/en
Publication of JPH05108656A publication Critical patent/JPH05108656A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • General Factory Administration (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Multi-Process Working Machines And Systems (AREA)

Abstract

PURPOSE:To simultaneously produce the production schedule plans through all processes in consideration of process load by displaying simultaneously the load piling graphs calculated for each process and changing the scheduled starting date of the necessary lot to be changed. CONSTITUTION:A scheduled production date deciding part 2 calculates the scheduled starting date of each process based on the information on the plan stored in a production plan storage part 1. This decided scheduled date is stored in a production schedule information storage part 3. Based on this information, the load of each time mesh is calculated at a load pliling executing part 4. Then all process loads are displayed at a load piling graph display part 6 together with the auxiliary data. The information on the necessary lot to be changed based on the display result of the part 6 is received at a change information input part 8. Then the information on the part 3 is updated at a corrected result updating part 9, and both parts 4 and 6 are carried out. Based on these results, 8 process-based schedule plan production part 1.0 produces the schedule plan of each process.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は生産日程計画作成装置、
特に、複数の工程で処理を行う製造現場において各工程
別の負荷山積みの結果を同時に表示し、製造現場の管理
者が工程別の負荷の違いを同時に考慮した生産日程計画
を作成することのできる生産日程計画作成装置に関す
る。
The present invention relates to a production schedule planning device,
In particular, at the manufacturing site where processing is performed in multiple processes, the results of load stacking for each process can be displayed at the same time, and the manager of the manufacturing site can create a production schedule plan that simultaneously considers the difference in the load for each process. A production schedule planning device.

【0002】[0002]

【従来の技術】従来の生産計画立案装置では、次の通り
で行われている。 (1)特定の工程の負荷のみを算出・表示し、製造現場
の管理者がその負荷を考慮した日程変更を行い、その情
報を基に生産計画を作成していた。その他の工程に関し
ては前記特定工程の生産計画を基にした計画を作成して
いた。 (2)工程手順に基づき先頭あるいは最終工程の負荷を
算出・表示し、その負荷を考慮した日程変更を行い、そ
の情報を基に生産計画を立案し、次工程あるいは前工程
の負荷を算出するといったように、各工程の生産計画を
順次段階的に作成していた。
2. Description of the Related Art A conventional production planning apparatus is operated as follows. (1) Only the load of a specific process is calculated and displayed, the manager of the manufacturing site changes the schedule in consideration of the load, and the production plan is created based on the information. As for the other processes, a plan was created based on the production plan of the specific process. (2) Calculate or display the load of the first or last process based on the process procedure, change the schedule considering the load, make a production plan based on that information, and calculate the load of the next process or the previous process As described above, the production plan for each process was created step by step.

【0003】[0003]

【発明が解決しようとする課題】上述した従来の生産日
程計画作成装置は、平均的な負荷あるいは特定の工程に
ついての負荷だけを考慮した生産計画を立案していたた
め、同一品名でも工程別に負荷が大きく異なる場合に
は、立案した生産計画通りにものが生産できないといっ
たような欠点をもっていた。
The above-mentioned conventional production schedule planning apparatus, which has made a production plan considering only the average load or the load for a specific process, has the same product name but different load for each process. If there is a big difference, it has the drawback that the product cannot be produced according to the planned production plan.

【0004】[0004]

【課題を解決するための手段】本発明の生産日程計画作
成装置は、(A) 生産対象の個々のロットについて、製品
名、生産数量、着手予定日、納期、価、製品の工程手順
及び、前記工程における単位数量当りの処理時間の情報
を記憶する生産計画記憶部と、(B) 製造現場の工程及び
設備別の能力、作業予定時間、停止予定時刻を記憶する
程情報記憶部と、(C) 前記生産計画記憶部で記憶してい
る前記着手予定日、前記工程手順、各工程前記処理時
間、前記生産数量を基に各ロット単位に各工程の前記処
理時間と生産数量の積をとった工程別負荷時間を算出す
るとともに、着手予定日より前記工程手順にそって負荷
時間を順次加算し各工程別着手時刻を算出し、生産日程
情報記憶部に格納する生産予定日決定部と、(D) 前記生
産日程情報記憶部で記憶されている前記工程別負荷時間
を工程ごとにらかじめ与えられた時間メッシュ単位に集
計し、各工程の負荷を算出する負荷山積み実行部と、
(E) 前記負荷山積み実行部の結果から工程ごとの山積み
グラフを作成し、複数の程のグラフを同時に表示する山
積みグラフ表示部と、(F) 前記生産日程情報記憶部の情
報と、前記生産計画記憶部で記憶しているロッ単位の生
産数量から前記ロットの最終工程を完了する時刻と完了
数量を算出しあらかじめ与えられた時間メッシュ単位に
集計するとともに、前記生産計画記憶部の単価データと
前記完了数量の積から売上高を算出し、前記山積みグラ
フ表示部の結果と同時にグラフ表示を行う、補足データ
算出・表示部と、(G) 変更対象となるロット、工程名、
工程別着手時刻を入力する、変更情報入力と、(H) 前記
変更情報入力部で入力された情報に基づき、前記生産日
程情報記憶部で憶している対象ロットの対象工程の工程
別着手時刻を変更し、その変更に合わせて対象ロットの
他の工程の工程別着手時刻を平行移動し、前記山積み実
行部及び前記負荷山積みグラフ表示部へ再実行の命令を
出す、修正結果更新部と、(I) 前記生産日程情報記憶部
の情報から全工程について工程ごとに各ロットの工別着
手時刻を抽出し、時刻順に表示する工程別日程計画作成
部と、とを含んで構成される。
The production schedule planning apparatus of the present invention is (A) for each lot to be produced, product name, production quantity, planned start date, delivery date, price, process step of product, and A production plan storage unit that stores information on the processing time per unit quantity in the above process, and (B) an information storage unit that stores the capabilities of each process and facility at the manufacturing site, scheduled work time, scheduled stop time, C) The product of the processing time and the production quantity of each process is calculated for each lot based on the scheduled start date, the process procedure, the processing time of each process, and the production quantity stored in the production plan storage unit. Along with calculating the process-specific load time, the load time is sequentially added from the planned start date according to the process procedure to calculate the start time for each process, and the planned production date determination unit is stored in the production schedule information storage unit, (D) It is stored in the production schedule information storage unit. A load heap execution unit that calculates the load of each process by aggregating the load time for each process that is given for each process in a given time mesh unit,
(E) a pile graph for each process is created from the result of the load pile execution unit, and a pile graph display unit for simultaneously displaying a plurality of graphs, (F) information in the production schedule information storage unit, and the production The time and completion quantity for completing the final process of the lot are calculated from the production quantity in the lot unit stored in the plan storage unit, and the unit price data in the production plan storage unit is calculated together with the time mesh unit given in advance. Sales are calculated from the product of the completed quantity, and a graph is displayed at the same time as the result of the piled-up graph display unit, supplementary data calculation / display unit, and (G) lot to be changed, process name,
Input process start time, change information input, and (H) process start time of the target process of the target lot stored in the production schedule information storage unit based on the information input in the change information input unit. Change, the process-based start time of the other process of the target lot is moved in parallel according to the change, and a re-execution command is issued to the pile execution unit and the load pile graph display unit, and a correction result update unit, (I) A process-based schedule planning unit that extracts the process-specific start time of each lot for each process from the information in the production schedule information storage unit and displays it in chronological order.

【0005】[0005]

【実施例】次に、本発明について図面を参照して詳細に
説明する。
The present invention will be described in detail with reference to the drawings.

【0006】図1は、本発明の一実施例を示すブロック
図である。図1に示す生産日程計画作成装置は、生産対
象の個々のロットについて製品名、生産数量、着手予定
日、納期、単価、製品の工程手順及び、各工程における
単位数量当りの処理時間の情報を記憶する生産計画記憶
部1、前記生産計画記憶部1の情報をもとに各ロットの
工程手順にそって着手予定日を決定する生産予定日決定
部2、前記生産予定日決定部2の情報を格納する生産日
程情報記憶部3、前記生産日程情報記憶部3で記憶され
ている情報をもとに各設備の時間メッシュ当りの負荷を
算出する負荷山積み実行部4、工程の保有能力を記憶す
る工程情報記憶部5、負荷山積みの結果をグラフとして
表示する際に工程の保有能力を山積みグラフ表示部5、
前記工程情報記憶部5と前記負荷山積み実行部4の結果
から負荷山積み結果をグラフとして表示する負荷山積み
グラフ表示部6、山積み結果を評価する際に使用する補
足データを算出・表示する補足データ算出・表示部7、
山積みグラフからロットの着手予定時刻を変更する際に
変更情報を入力する変更情報入力部8、前記変更情報入
力部8の情報をもとに前記生産日程情報記憶部3のデー
タの更新を行う修正結果更新部9、前記生産日程情報記
憶部3の情報から工程別の日程計画を作成する工程別日
程計画作成部10から構成されている。
FIG. 1 is a block diagram showing an embodiment of the present invention. The production schedule planning device shown in FIG. 1 provides information on the product name, production quantity, scheduled start date, delivery date, unit price, process procedure of the product, and processing time per unit quantity in each process for each production target lot. Information on the planned production date storage unit 1 and the planned production date determination unit 2 that determines the scheduled start date according to the process procedure of each lot based on the information stored in the production plan storage unit 1 Storing a production schedule information storage unit 3, a load stacking execution unit 4 for calculating a load per time mesh of each facility based on the information stored in the production schedule information storage unit 3, and a process holding capacity The process information storage unit 5, which displays the load stacking result as a graph, shows the process possession capacity,
A load pile graph display unit 6 that displays a load pile result as a graph from the results of the process information storage unit 5 and the load pile execution unit 4, and a supplemental data calculation that calculates / displays supplementary data used when evaluating the pile result.・ Display unit 7,
A modification information input section 8 for inputting modification information when changing a scheduled start time of a lot from a stacking graph, and a modification for updating data in the production schedule information storage section 3 based on the information in the modification information input section 8. The result updating unit 9 and the process-based schedule planning unit 10 that creates a schedule plan for each process from the information in the production schedule information storage unit 3 are configured.

【0007】図2は、図1で示した負荷山積みグラフ表
示部6の表示例を示す図である。負荷山積み実行部4の
結果から工程別の負荷をあらかじめ与えられた時間メッ
シュ単位に集計し、同一画面上に表示したものである。
本グラフ内の波線は工程情報記憶部5で記憶された設備
別能力、作業予定時間、停止予定時刻から算出した工程
内の保有能力である。本波線を負荷が超えている場合に
は能力オーバを示し、着手予定時刻の変更の必要があ
る。
FIG. 2 is a diagram showing a display example of the load pile graph display unit 6 shown in FIG. From the result of the load stacking execution unit 4, the load for each process is aggregated in a time mesh unit given in advance and displayed on the same screen.
The wavy line in this graph is the holding capacity in the process calculated from the facility-specific capability, the scheduled work time, and the scheduled stop time stored in the process information storage unit 5. If the load exceeds the main line, the capacity is exceeded and it is necessary to change the scheduled start time.

【0008】図3(a),(b)は、図1で示した変更
情報入力部8、修正結果更新部9、生産日程情報記憶部
3、負荷山積み実行部4、負荷山積みグラフ表示部6の
関連性を示した図である。図3(a)は変更情報入力部
8の入力例、図3(b)は負荷山積みグラフ表示部6の
再表示を示す。図2で示すような負荷山積みグラフ表示
部6の結果を人間が判断し、図3(a)に示す変更情報
入力部8に変更対象ロット名、工程、着手予定時刻を入
力する。この結果を基に修正結果更新部9で指定された
ロット名の各工程の着手予定時刻を変更し、変更情報を
生産日程情報記憶部3に格納する。格納後負荷山積み実
行部4及び負荷山積みグラフ表示部6に再実行の命令を
して、図3(b)に示すように負荷山積みグラフの再表
示を行う。
3A and 3B are a change information input unit 8, a correction result updating unit 9, a production schedule information storage unit 3, a load pile execution unit 4, and a load pile graph display unit 6 shown in FIG. It is a figure showing the relevance of. FIG. 3A shows an input example of the change information input unit 8, and FIG. 3B shows redisplay of the load pile graph display unit 6. A person judges the result of the load pile graph display unit 6 as shown in FIG. 2, and inputs the change target lot name, process, and scheduled start time into the change information input unit 8 shown in FIG. 3A. Based on this result, the scheduled start time of each process of the lot name designated by the correction result update unit 9 is changed, and the change information is stored in the production schedule information storage unit 3. After the storage, the load pile execution unit 4 and the load pile graph display unit 6 are instructed to re-execute, and the load pile graph is displayed again as shown in FIG. 3B.

【0009】[0009]

【発明の効果】本発明の生産日程計画作成装置は、工程
により負荷の異なる生産現場において複数の工程の負荷
を同時に考慮した生産計画を作成できるため、生産計画
の負荷の平準化をさらに細かいレベルまで考慮すること
ができるため、生産計画の質の向上を図ることが可能と
なり、より実現可能な生産計画を作成することができる
という効果を有する。
The production schedule planning apparatus of the present invention can create a production plan that simultaneously considers the loads of a plurality of processes at a production site where the load varies depending on the process, so that the leveling of the load of the production plan can be performed at a finer level. Since the above can be taken into consideration, the quality of the production plan can be improved, and a more feasible production plan can be created.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の一実施例を示すブロック図である。FIG. 1 is a block diagram showing an embodiment of the present invention.

【図2】図1で示した負荷山積みグラフ表示部6の表示
例を示す図である。
FIG. 2 is a diagram showing a display example of a load pile graph display unit 6 shown in FIG.

【図3】(a),(b)は、図1で示した変更情報入力
部8、修正結果更新部9、生産日程情報記憶部3、負荷
山積み実行部4、負荷山積みグラフ表示部6の関連性を
示した図である。
3 (a) and 3 (b) are a change information input unit 8, a correction result updating unit 9, a production schedule information storage unit 3, a load pile execution unit 4, and a load pile graph display unit 6 shown in FIG. It is the figure which showed the relevance.

【符号の説明】[Explanation of symbols]

1 生産計画記憶部 2 生産予定決定部 3 生産日程情報記憶部、 4 負荷山積み実行部 5 工程情報記憶部 6 負荷山積みグラフ表示部 7 補足データ算出・表示部 8 変更情報入力部 9 修正結果更新部 10 工程別日程計画作成部 1 Production plan storage unit 2 Production schedule determination unit 3 Production schedule information storage unit, 4 Load pile execution unit 5 Process information storage unit 6 Load pile graph display unit 7 Supplemental data calculation / display unit 8 Change information input unit 9 Correction result update unit 9 10 Process schedule planning department

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】(A) 生産対象の個々のロットについて、製
品名、生産数量、着手予定日、納期、価、製品の工程手
順及び、前記工程における単位数量当りの処理時間の情
報を記憶する生産計画記憶部と、 (B) 製造現場の工程及び設備別の能力、作業予定時間、
停止予定時刻を記憶する程情報記憶部と、 (C) 前記生産計画記憶部で記憶している前記着手予定
日、前記工程手順、各工程前記処理時間、前記生産数量
を基に各ロット単位に各工程の前記処理時間と生産数量
の積をとった工程別負荷時間を算出するとともに、着手
予定日より前記工程手順にそって負荷時間を順次加算し
各工程別着手時刻を算出し、生産日程情報記憶部に格納
する生産予定日決定部と、 (D) 前記生産日程情報記憶部で記憶されている前記工程
別負荷時間を工程ごとにらかじめ与えられた時間メッシ
ュ単位に集計し、各工程の負荷を算出する負荷山積み実
行部と、 (E) 前記負荷山積み実行部の結果から工程ごとの山積み
グラフを作成し、複数の程のグラフを同時に表示する山
積みグラフ表示部と、 (F) 前記生産日程情報記憶部の情報と、前記生産計画記
憶部で記憶しているロッ単位の生産数量から前記ロット
の最終工程を完了する時刻と完了数量を算出しあらかじ
め与えられた時間メッシュ単位に集計するとともに、前
記生産計画記憶部の単価データと前記完了数量の積から
売上高を算出し、前記山積みグラフ表示部の結果と同時
にグラフ表示を行う、補足データ算出・表示部と、 (G) 変更対象となるロット、工程名、工程別着手時刻を
入力する、変更情報入力と、 (H) 前記変更情報入力部で入力された情報に基づき、前
記生産日程情報記憶部で憶している対象ロットの対象工
程の工程別着手時刻を変更し、その変更に合わせて対象
ロットの他の工程の工程別着手時刻を平行移動し、前記
山積み実行部及び前記負荷山積みグラフ表示部へ再実行
の命令を出す、修正結果更新部と、 (I) 前記生産日程情報記憶部の情報から全工程について
工程ごとに各ロットの工別着手時刻を抽出し、時刻順に
表示する工程別日程計画作成部と、 を備えることを特徴とする生産日程計画作成装置。
1. A product name, production quantity, scheduled start date, delivery date, price, process procedure of a product, and processing time per unit quantity in the process are stored for each lot to be produced. Production plan storage, (B) Production site process and facility-specific capabilities, scheduled work time,
An information storage unit that stores scheduled stop times, and (C) each lot unit based on the scheduled start date, the process procedure, each process, the processing time, and the production quantity stored in the production plan storage unit. The load time for each process is calculated by multiplying the processing time of each process by the production quantity, and the load time is sequentially added from the scheduled start date according to the process procedure to calculate the start time for each process. An estimated production date determination unit to be stored in the information storage unit, and (D) the process-based load times stored in the production schedule information storage unit are aggregated in a given time mesh unit for each process. A load heap execution unit that calculates the load of the process, and (E) A heap graph display unit that creates a heap graph for each process from the results of the load heap execution unit, and that simultaneously displays multiple graphs, and (F) Information of the production schedule information storage section And the time and completion quantity for completing the final process of the lot are calculated from the production quantity in the lot unit stored in the production plan storage unit, and are aggregated in a time mesh unit given in advance. The sales amount is calculated from the product of the unit price data and the completed quantity, and a graph is displayed at the same time as the result of the piled graph display unit, and a supplementary data calculation / display unit, and (G) a lot to be changed, a process name, Change information input to enter the process start time, and (H) the process start time of the target process of the target lot stored in the production schedule information storage unit based on the information input in the change information input unit. Change the start time of each process of the other process of the target lot in parallel according to the change, and issue a re-execution command to the pile execution unit and the load pile graph display unit. And (I) a process-based schedule planning section that extracts the process-specific start time of each lot for each process from the information in the production schedule information storage unit and displays it in order of time. Production schedule planning device.
JP26576891A 1991-10-15 1991-10-15 Production schedule planning device Pending JPH05108656A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP26576891A JPH05108656A (en) 1991-10-15 1991-10-15 Production schedule planning device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP26576891A JPH05108656A (en) 1991-10-15 1991-10-15 Production schedule planning device

Publications (1)

Publication Number Publication Date
JPH05108656A true JPH05108656A (en) 1993-04-30

Family

ID=17421761

Family Applications (1)

Application Number Title Priority Date Filing Date
JP26576891A Pending JPH05108656A (en) 1991-10-15 1991-10-15 Production schedule planning device

Country Status (1)

Country Link
JP (1) JPH05108656A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1015786A (en) * 1996-06-28 1998-01-20 Nec Corp Production planning simulation apparatus

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1015786A (en) * 1996-06-28 1998-01-20 Nec Corp Production planning simulation apparatus

Similar Documents

Publication Publication Date Title
EP0467597A2 (en) Production plan modification and display apparatus
JP2005301894A (en) Work progress management method, work progress management device and program
CN101510277A (en) Method for rolling computation of material requirement in production management process
JPH08314526A (en) Manufacture management system
JP6754823B2 (en) Production planning support equipment and methods
JPH05108656A (en) Production schedule planning device
JPS62224562A (en) Display device for process control data
JPH0748227B2 (en) Construction process planning and process management system
JP4318162B2 (en) Production schedule planning management method and production schedule planning management program
JPS62224561A (en) Work load display system
JP2014197320A (en) System and method for preparing production plan
JP4831827B2 (en) Project scheduling system
JPH07182420A (en) Production planning device
JP2001318714A (en) Object development type production management system
JPH06332909A (en) Plan managing system
JPH05108655A (en) Production schedule planning controller
JPH0710486B2 (en) Multi-product production schedule creation device
JP2007156988A (en) Work distribution device, work distribution method, work distribution program and recording medium with work distribution program recorded thereon
JP2014135003A (en) Production schedule adjustment support system, production schedule adjustment support apparatus, production schedule adjustment support method, and program
JPH0573107A (en) System and method for planning production
JPH0935103A (en) Device for managing production planning information
JP2003036105A (en) System and method for built-to-order production planning, and built-to-order production planning program
JP4665587B2 (en) Supply and demand plan creation device, supply and demand plan creation method, and supply and demand plan creation program
JPH1177492A (en) Production limit making device
JPH0584374A (en) Allocation time calculating system for each process in sewing factory and device therefor