JPH05106352A - Construction method for structure - Google Patents

Construction method for structure

Info

Publication number
JPH05106352A
JPH05106352A JP10735991A JP10735991A JPH05106352A JP H05106352 A JPH05106352 A JP H05106352A JP 10735991 A JP10735991 A JP 10735991A JP 10735991 A JP10735991 A JP 10735991A JP H05106352 A JPH05106352 A JP H05106352A
Authority
JP
Japan
Prior art keywords
pca
pillar
column
foundation
beams
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP10735991A
Other languages
Japanese (ja)
Inventor
Susumu Watanabe
勧 渡辺
Tadao Yasui
忠生 安井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP10735991A priority Critical patent/JPH05106352A/en
Publication of JPH05106352A publication Critical patent/JPH05106352A/en
Pending legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

PURPOSE:To provide the construction method of the structure of a stand of a golf practice range, an event, and a stadium advantageous in structure, capable of improving the design, and capable of shortening the construction period. CONSTITUTION:A PCa pillar 4 is tilted on a foundation 2 at a preset angle, a pillar leg is fixed by steel bars 3 anchored to the foundation 2 to erect the slant pillar 4. PCa hanging beams 5 are suspended on the opposite side to the inclination direction of the slant pillar 4, frames integrally inserted and fastened with PC steels 7 through the beams 5 and the PCa pillar 4 are arranged at the preset interval, and PCa girder beams 10 are arranged between the frames. PC steels 11 are inserted and tightened between the girder beams 10 and the pillar 4, and slabs are constructed on the hanging beams 5.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明はゴルフ練習場、イベント
や競技場等のスタンド、駐車場等の構造物の構築法に係
るものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a structure such as a driving range, a stand for an event or a stadium, a parking lot or the like.

【0002】[0002]

【従来の技術】従来、この種の構造物は所定間隔毎に垂
直に立設された鉄骨柱を桁方向で連結するとともに、同
鉄骨柱より床スラブを支持する鉄骨梁をはね出して構成
されていた。
2. Description of the Related Art Conventionally, a structure of this type is constructed by vertically connecting vertically standing steel frame columns in a girder direction and projecting a steel beam supporting the floor slab from the steel column. It had been.

【0003】[0003]

【発明が解決しようとする課題】しかしながら3階建以
上の鉄骨造は耐火被覆が必要で、デザイン上問題があ
り、また鉄骨部材組立に多くの手間と時間を要し、鉄骨
柱と床スラブを支持するはね出し鉄骨梁の応力のバラン
スに問題があった。本発明は前記従来技術の有する問題
点に鑑みて提案されたもので、その目的とする処は、構
造上有利でデザインが向上され工期が短縮されるゴルフ
練習場、イベントや競技場のスタンド等の構造物の構築
法を提供する点ある。
However, a steel frame structure of three stories or more requires a fireproof coating, has a design problem, and requires a lot of labor and time for assembling the steel members, so that the steel column and the floor slab are required to be assembled. There was a problem in the balance of stress of the propelled steel beam supporting it. The present invention has been proposed in view of the above problems of the prior art, and an object thereof is to provide a golf driving range, a stand for use in an event or a stadium, which is structurally advantageous and has an improved design and a shortened construction period. There is a point to provide a construction method of the structure.

【0004】[0004]

【課題を解決するための手段】前記の目的を達成するた
め、本発明に係る構造物の構築法によれば、基礎上にP
Ca柱を所定角度をもたせて傾斜させ、前記基礎にアン
カーされた鋼棒によって柱脚を固定して斜柱を立設し、
同斜柱の傾斜方向と反対側にPCaはね出し梁を架設
し、同はね出し梁と前記柱に亘ってPC鋼材を挿貫、緊
張して一体化された架構を構築し、更に同架構を所定間
隔をおいて列設していくとともに、前記各架構間にPC
a桁梁を配設し、同各桁梁と前記各柱との間にPC鋼材
を挿貫、緊締しながら前記はね出し梁上に床スラブを施
工するものである。
In order to achieve the above-mentioned object, according to the method of constructing a structure according to the present invention, P is formed on the foundation.
The Ca column is inclined at a predetermined angle, the column base is fixed by the steel rod anchored to the foundation, and the diagonal column is erected.
A PCa protruding beam is erected on the side opposite to the slanting direction of the same slanted column, and a PC steel material is inserted through the protruding beam and the column, and a tensioned and integrated frame is constructed. Frames are lined up at predetermined intervals, and PCs are installed between the frames.
A girder beam is disposed, and a floor slab is constructed on the projecting beam while inserting and tightening a PC steel material between each girder beam and each column.

【0005】[0005]

【作用】本発明によれば前記したように、基礎上に傾斜
PCa柱を立設し、同PCa柱の傾斜方向と反対側には
床スラブを支承するPCaはね出し梁を突設し、且つP
Ca柱間にPCa桁梁を配設して構造物の構格を構成す
るようにしたものであって、柱を斜柱とすることによっ
て、長期荷重時に柱に生じる応力が低減されて、基礎を
含めた構造物の合理的設計が可能となる。
According to the present invention, as described above, the inclined PCa column is erected on the foundation, and the PCa ejection beam for supporting the floor slab is provided on the side opposite to the inclined direction of the PCa column. And P
PCa girder beams are arranged between Ca columns to form the structure of the structure. By making the columns oblique, the stress generated in the columns during long-term loading is reduced, and The rational design of the structure including is possible.

【0006】[0006]

【実施例】以下本発明を図示の実施例について説明す
る。基礎杭1を打設し、基礎2を施工するとともに同基
礎2よりPC鋼棒3を立上げておく。(図1参照) 次いで前記基礎2上に所定角度をもって外側上方に指向
して傾斜したPCa柱4を建込み、基礎2に定着された
PC鋼棒3によって固定して斜柱を立設するとともに、
基礎2から伸ばしたPC鋼材をPCa柱4に挿貫、緊締
して斜柱を立設する。(図2参照) 次いで前記PCa柱4の内側面に、PCaはね出し梁5
を取付ける。この際、同梁5の基端部を、前記PCa柱
4に設けた梁支持用欠込み6に支持するとともに、前記
梁5の自由端をサポート7で支持し、同梁5及び前記P
Ca柱4にPC鋼材8を横貫、緊張して、前記PCaは
ね出し梁5とPCa柱4とが一体化された架構を構築す
る。(図3参照) 前記架構を所定の間隔をおいて、平面上で平行または円
弧状に並列して構築していくとともに、相隣るPCa柱
4の対向面に仮設ブラケツト9を取付け、同ブラケツト
9間にPCa桁梁10を架渡し、同桁梁10と前記PC
a柱4とに亘ってPC鋼材11を挿貫、緊締して桁梁を
架設する。(図4参照)図中10′は立上り壁である。
The present invention will be described below with reference to the illustrated embodiments. The foundation pile 1 is placed, the foundation 2 is constructed, and the PC steel rod 3 is raised from the foundation 2. (See FIG. 1) Next, a PCa pillar 4 that is tilted outward at a predetermined angle is installed on the foundation 2 and is fixed by a PC steel rod 3 fixed to the foundation 2 to erect the oblique pillar. ,
The PC steel material extended from the foundation 2 is inserted into the PCa pillar 4 and tightened to erect the oblique pillar. (See FIG. 2) Next, on the inner surface of the PCa pillar 4, the PCa protrusion beam 5 is formed.
Install. At this time, the base end portion of the beam 5 is supported by the beam supporting notch 6 provided in the PCa column 4, and the free end of the beam 5 is supported by the support 7, and the beam 5 and the P
A PC steel material 8 is transversely passed through the Ca pillar 4 and tensioned to construct a frame in which the PCa protruding beam 5 and the PCa pillar 4 are integrated. (See FIG. 3) The frames are constructed in parallel or arcuately in parallel on a plane at a predetermined interval, and temporary brackets 9 are attached to the facing surfaces of adjacent PCa pillars 4, and the brackets are attached. A PCa girder beam 10 is bridged between 9 and the same girder beam 10 and the PC.
The girder beam is installed by inserting and tightening the PC steel material 11 across the a pillar 4. (See FIG. 4) In the figure, 10 'is a rising wall.

【0007】一方、前記PCaはね出し梁5上に亘って
半PCa床版12を架設し(図5参照)同床版12上に
スラブコンクリート13を打設する。(図6参照) 又、必要に応じてPCaはね出し梁5の下端においてP
Ca柱4に亘ってPC鋼材8´を横貫,緊張して、より
強度を高めることができる。(図7参照) なお桁方向はプレストレス応力によるクリープ、また乾
燥、収縮による影響のために、先に構築したPCa柱4
に強制変形が生起するので、適当なスパンで、PCa柱
4にPCaブラケツト14をPC鋼棒15を介して取付
け、相対する同ブラケツト14間にRC梁16を載架す
ることによってエキスパンシヨンジヨイントを設ける。
(図8参照) 図9及び図10は夫々柱に傾斜をとった前記実施例の工
法による架構、及び柱が植立した従来工法による架構の
曲げモーメント分布図を示し、前記各図から明らかなよ
うに、本実施例によれば柱に傾斜をとることによってキ
ヤンテレバーによる長期応力の柱及び基礎の設計が有利
となり、また柱の応力のみならず、柱脚での応力が低減
でき、全体的に応力バランスがよくなる。
On the other hand, a half-PCa floor slab 12 is laid over the PCa projection beam 5 (see FIG. 5), and a slab concrete 13 is placed on the floor slab 12. (See FIG. 6) In addition, if necessary, at the lower end of the PCa protrusion beam 5, P
The strength can be further increased by laterally passing through and tensioning the PC steel material 8 ′ across the Ca columns 4. (Refer to FIG. 7.) The girder direction is affected by creep due to pre-stress stress, and due to drying and shrinkage.
Since the PCa bracket 14 is attached to the PCa pillar 4 via the PC steel rod 15 with an appropriate span, the RC beam 16 is mounted between the opposing brackets 14 to expand the expansion joint. Provide an int.
(See FIG. 8) FIG. 9 and FIG. 10 show bending moment distribution diagrams of the frame structure by the construction method of the above-mentioned embodiment in which the columns are inclined and the frame structure by the conventional method in which the columns are erected, respectively. As described above, according to the present embodiment, by sloping the column, the design of the column and the foundation of long-term stress by the canter lever is advantageous, and not only the stress of the column but also the stress in the column base can be reduced, and the overall Improves stress balance.

【0008】[0008]

【発明の効果】本発明によれば前記したように従来鉄骨
造で設計されていたゴルフ練習場、イベントや競技場の
スタンド等の構造物の柱、梁、床をプレキヤストプレス
トレスコンクリートの組立工法で施工することによっ
て、従来3階建以上の鉄骨造では耐火被覆が必要で、デ
ザイン上問題があったのを、本発明によればこのような
必要がなくなり、デザインが向上し、また工期が短縮さ
れ鉄骨造よりも床振動が少なく、従来のRC造よりも解
体が容易となる。
As described above, according to the present invention, the pillars, beams, and floors of the structure such as the golf driving range, the stand of the event or the stadium, which are conventionally designed by the steel structure, are assembled into the precast concrete. By using the construction method, the conventional steel frame construction with three or more floors required a fireproof coating, which was problematic in design. According to the present invention, however, such a need is eliminated, the design is improved, and the construction period is increased. The floor vibration is shorter than that of the steel frame structure, and the dismantling is easier than that of the conventional RC structure.

【0009】更にまた柱をPCa斜柱としてこれにはね
出しPCa梁を架設することによって、キヤンテレバー
による長期応力時の柱及び基礎の設計が有利(従来の垂
直柱と比較して20〜30%の応力低減となる)にな
り、特に柱脚での応力が著しく低減でき、全体的に応力
バランスがよくなる。
Furthermore, by designing the column as a PCa sloping column and installing a protruding PCa beam on it, it is advantageous to design the column and foundation during long-term stress by the canister lever (20 to 30% compared to the conventional vertical column). Therefore, the stress in the column base can be remarkably reduced, and the stress balance is improved as a whole.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明に係る構造物の構築法の一実施例におけ
る基礎の施工工程を示す縦断面図である。
FIG. 1 is a vertical cross-sectional view showing a step of constructing a foundation in an example of a method for constructing a structure according to the present invention.

【図2】柱建方工法を示す縦断面図である。FIG. 2 is a vertical sectional view showing a pillar erection method.

【図3】PCaはね出し梁の取付工程を示す縦断面図で
ある。
FIG. 3 is a vertical cross-sectional view showing a mounting process of the PCa projection beam.

【図4】桁方向梁架設工程を示す縦断面図である。FIG. 4 is a vertical cross-sectional view showing a girder beam erection process.

【図5】床版の架設工程を示す縦断面図である。FIG. 5 is a vertical cross-sectional view showing a floor slab installation process.

【図6】スラブコンクリート打設工程を示す縦断面図で
ある。
FIG. 6 is a vertical sectional view showing a slab concrete placing step.

【図7】図6の拡大図である。FIG. 7 is an enlarged view of FIG.

【図8】桁梁架設工程の詳細を示す縦断面図である。FIG. 8 is a vertical cross-sectional view showing details of a girder erection process.

【図9】本発明の方法による架構の曲げモーメント分布
図である。
FIG. 9 is a bending moment distribution diagram of the frame according to the method of the present invention.

【図10】従来工法による架構の曲げモーメント分布図
である。
FIG. 10 is a bending moment distribution diagram of a frame constructed by a conventional method.

【符号の説明】[Explanation of symbols]

2 基礎 3 PC鋼棒 4 PCa柱 5 PCaはね出し梁 8 PC鋼材 10 PCa桁梁 11 PC鋼材 12 半PCa床版 13 スラブコンクリート 2 Foundation 3 PC steel rod 4 PCa pillar 5 PCa repelling beam 8 PC steel material 10 PCa girder beam 11 PC steel material 12 half PCa floor slab 13 slab concrete

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 基礎上にPCa柱を所定角度をもたせて
傾斜させ、前記基礎にアンカーされた鋼棒によって柱脚
を固定して斜柱を立設し、同斜柱の傾斜方向と反対側に
PCaはね出し梁を架設し、同はね出し梁と前記柱に亘
ってPC鋼材を挿貫、緊張して一体化された架構を構築
し、更に同架構を所定間隔をおいて列設していくととも
に、前記各架構間にPCa桁梁を配設し、同各桁梁と前
記各柱との間にPC鋼材を挿貫、緊締しながら前記はね
出し梁上に床スラブを施工することを特徴とする構造物
の構築法。
1. A PCa column is tilted on a foundation at a predetermined angle, and a column base is fixed by a steel rod anchored to the foundation to erect a slant column, and the side opposite to the slant direction of the slant column. A PCa protruding beam is erected on the PCa, the PC steel material is penetrated through the protruding beam and the pillar, and a tensioned and integrated frame is constructed. Further, the same frame is arranged at predetermined intervals. At the same time, a PCa girder beam is arranged between the frames, and a PC steel material is inserted and tightened between the girder beams and the columns, and a floor slab is constructed on the projecting beam while tightening. A method of constructing a structure characterized by:
JP10735991A 1991-05-13 1991-05-13 Construction method for structure Pending JPH05106352A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP10735991A JPH05106352A (en) 1991-05-13 1991-05-13 Construction method for structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP10735991A JPH05106352A (en) 1991-05-13 1991-05-13 Construction method for structure

Publications (1)

Publication Number Publication Date
JPH05106352A true JPH05106352A (en) 1993-04-27

Family

ID=14457078

Family Applications (1)

Application Number Title Priority Date Filing Date
JP10735991A Pending JPH05106352A (en) 1991-05-13 1991-05-13 Construction method for structure

Country Status (1)

Country Link
JP (1) JPH05106352A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113638490A (en) * 2021-08-25 2021-11-12 北京城建集团有限责任公司 Shuttle-shaped column of roof steel structure and construction method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113638490A (en) * 2021-08-25 2021-11-12 北京城建集团有限责任公司 Shuttle-shaped column of roof steel structure and construction method thereof
CN113638490B (en) * 2021-08-25 2022-07-12 北京城建集团有限责任公司 Shuttle-shaped column of roof steel structure and construction method thereof

Similar Documents

Publication Publication Date Title
CN111206768A (en) Light beam plate structure platform and construction method thereof
JPH0941666A (en) Concrete formwork construction method
JPH05106352A (en) Construction method for structure
JP3612600B2 (en) Unit anchor and structural steel foundation beam
JP2784450B2 (en) Reinforced concrete foundation
JP2867141B2 (en) Mounting and dismantling method of work scaffold in step-up method
JP3233822B2 (en) Earthquake-resistant wooden house structure
JPH10184005A (en) Construction method of diagonal building frame
JP2841252B2 (en) Construction method of arch concrete by arch form support.
JP2600531B2 (en) Foundation structure for steel column and its construction method
JP2004270377A (en) Column-beam preassembled reinforcement body, and preassembled reinforcement method using the same
JPH0684686B2 (en) Standing method for precast concrete columns
JP2583489Y2 (en) Anchor frame
JPH0598653A (en) Steel pipe concrete pillar in underground inverter construction method
JPH08158383A (en) Execution method of retaining wall, etc.
JPH0384119A (en) Construction of column erection of structure
JP2783993B2 (en) Embedded foundation for steel columns
RU2104375C1 (en) Suspended covering and method of its erection
JPH0345178B2 (en)
JPH0417718Y2 (en)
JP2914539B2 (en) Steel beam assembly method for large-scale RC structures
JP2989337B2 (en) Pre-assembly method of beam in steel reinforced concrete structure
JPH05280013A (en) Process for forming arch concrete with use of arch-like form timberwork
JPH1068132A (en) Anchor frame
JPH10121615A (en) Reinforcing structure under opening of exterior wall