JPH0447184Y2 - - Google Patents

Info

Publication number
JPH0447184Y2
JPH0447184Y2 JP17138487U JP17138487U JPH0447184Y2 JP H0447184 Y2 JPH0447184 Y2 JP H0447184Y2 JP 17138487 U JP17138487 U JP 17138487U JP 17138487 U JP17138487 U JP 17138487U JP H0447184 Y2 JPH0447184 Y2 JP H0447184Y2
Authority
JP
Japan
Prior art keywords
jack
plunger
centering
semicircular
semicircular recess
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP17138487U
Other languages
Japanese (ja)
Other versions
JPH0176875U (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP17138487U priority Critical patent/JPH0447184Y2/ja
Publication of JPH0176875U publication Critical patent/JPH0176875U/ja
Application granted granted Critical
Publication of JPH0447184Y2 publication Critical patent/JPH0447184Y2/ja
Expired legal-status Critical Current

Links

Landscapes

  • Types And Forms Of Lifts (AREA)
  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)

Description

【考案の詳細な説明】 〔産業上の利用分野〕 本考案は、油圧エレベータのジヤツキ据付装置
に関する。
[Detailed Description of the Invention] [Industrial Application Field] The present invention relates to a jack installation device for a hydraulic elevator.

〔従来の技術〕[Conventional technology]

油圧エレベータは、第5図に示すように、プラ
ンジヤ9とシリンダ10とを備えたジヤツキ11
がジヤツキ受台13上に据付けられ、このジヤツ
キ11のプランジヤ9の上端部には、図示せぬロ
ープが巻装されるプーリ17と、プランジヤ9の
突出方向に対して直角に延びる腕部16とが取り
付けられている。また、昇降路壁面20にはガイ
ドレール8a,8bが芯出し固定されており、上
記腕部16の先端に装着されたガイド部15a,
15bが、これらのガイドレール8a,8bに沿
つて移動自在となつている。したがつて、ジヤツ
キ11が油圧操作されてプランジヤ9のシリンダ
10からの突出長が変化すると、このプランジヤ
9はガイドレール8a,8bに案内されて昇降路
内を移動し、上記プーリ17に巻装されたロープ
を介して図示せぬ乗かごが昇降するようになつて
いる。
As shown in FIG. 5, the hydraulic elevator has a jack 11 equipped with a plunger 9 and a cylinder 10.
is installed on the jack holder 13, and the upper end of the plunger 9 of the jack 11 has a pulley 17 around which a rope (not shown) is wound, and an arm 16 extending at right angles to the direction in which the plunger 9 projects. is installed. Further, guide rails 8a and 8b are centered and fixed on the hoistway wall surface 20, and guide portions 15a and 8b mounted on the tips of the arm portions 16,
15b is movable along these guide rails 8a, 8b. Therefore, when the jack 11 is hydraulically operated to change the protrusion length of the plunger 9 from the cylinder 10, the plunger 9 is guided by the guide rails 8a and 8b and moves within the hoistway, and is wound around the pulley 17. A car (not shown) is raised and lowered via the rope.

さて、このような構成の油圧エレベータにあつ
ては、プランジヤ9の突出長の変化を正しく乗か
ごに伝達するために、ジヤツキ11のシリンダ1
0をジヤツキ受台13上の所定位置に鉛直姿勢を
維持して立設する必要がある。すなわち、第6図
に示すように、ジヤツキ受台13の中心Pとプラ
ンジヤ9の中心Qとが一致し、かつ、この中心位
置P(Q)がガイドレール8a,8bを結ぶ中心
線Rの線上に位置することが望ましい。このた
め、据付過程の油圧エレベータにおいて、ジヤツ
キ11を高精度に芯出し固定するための技術が、
従来より種々提案されている。
Now, in a hydraulic elevator having such a configuration, in order to correctly transmit the change in the protrusion length of the plunger 9 to the car, the cylinder 1 of the jack 11 is
0 must be placed upright at a predetermined position on the jack holder 13 while maintaining a vertical posture. That is, as shown in FIG. 6, the center P of the jack holder 13 and the center Q of the plunger 9 are aligned, and this center position P (Q) is on the center line R connecting the guide rails 8a and 8b. It is desirable to be located in For this reason, the technology for centering and fixing the jack 11 with high precision in the hydraulic elevator during the installation process is
Various proposals have been made in the past.

例えば、実開昭58−54458号公報に開示されて
いるジヤツキ据付方法は、シリンダ上部にシリン
ダ本体より大径なヘツドカバーを形成し、シリン
ダ下部にはヘツドカバーと同径のケガキ線を描線
した基板を持つて選定した2個所の位置から鉛直
度基準紐を垂下し、この鉛直度基準紐の先端に吊
した錘がケガキ線と合致するようにシリンダの姿
勢を修正することによつて、ジヤツキの芯出しを
行うというものである。
For example, in the jack installation method disclosed in Japanese Utility Model Application No. 58-54458, a head cover with a diameter larger than the cylinder body is formed on the top of the cylinder, and a board with a marking line of the same diameter as the head cover is placed on the bottom of the cylinder. By hanging a verticality reference string from the two selected positions and correcting the posture of the cylinder so that the weight suspended at the tip of this verticality reference string matches the marking line, the center of the jack can be adjusted. This means making a contribution.

しかし、上記従来技術は、ヘツドカバーから垂
下した鉛直度基準紐がシリンダの姿勢を修正する
たびに揺れるので、この揺れを止めることが煩雑
であるとともに、錘の揺れが測定誤差を生じてジ
ヤツキの芯出し精度が低下するという不具合があ
つた。また、この従来技術はあくまでもジヤツキ
の鉛直度の修正であり、鉛直度を求める前にジヤ
ツキの立設位置を別の方法で求めねばならないの
で、作業効率も悪かつた。
However, in the above-mentioned conventional technology, the verticality reference string hanging from the head cover shakes every time the posture of the cylinder is corrected, so it is troublesome to stop this shaking, and the shaking of the weight causes measurement errors, causing the center of the jack to swing. There was a problem that the output accuracy decreased. In addition, this prior art technique only corrects the verticality of the jack, and the position of the jack must be determined by another method before determining the verticality, resulting in poor work efficiency.

これに対し、本出願人が先に提案したジヤツキ
据付方法(特開昭61−295981号公報)では、昇降
路壁面にガイドレールを芯出し固定した後、ジヤ
ツキのプランジヤの外周面のほぼ半周が嵌入可能
な半円状凹所を所定位置に形成したジヤツキ芯出
し雇を上記ガイドレール間に装着し、この芯出し
雇の半円状凹所を跨いで取り付けたセンターゲー
ジから、先端に錘を吊した鉛直度基準紐を垂下し
てジヤツキ受台にケガキ線を描線し、しかる後、
このケガキ線に軸心位置を合わせてジヤツキ受台
上にジヤツキを立設し、次いで、このジヤツキの
プランジヤを上記芯出し雇の半円状凹所内に嵌入
して鉛直姿勢を確保するというものである。この
従来提案によれば、ジヤツキの立設位置を定める
作業と鉛直姿勢を定める作業とがジヤツキ芯出し
雇を用いた一連の作業工程の中で行えるので、作
業効率が良好であるとともに、ジヤツキ芯出し雇
の半円状凹所内にプランジヤを嵌入すれば自動的
に鉛直姿勢が確保できるので、鉛直度基準紐の錘
の揺れに起因する測定誤差は発生せず、高精度な
芯出しが行える。
In contrast, in the jack installation method previously proposed by the present applicant (Japanese Patent Laid-Open No. 61-295981), after centering and fixing the guide rail to the hoistway wall, approximately half of the outer circumference of the jack's plunger is A jack centering rod with a fittable semicircular recess formed in a predetermined position is installed between the guide rails, and a weight is attached to the tip from the center gauge attached across the semicircular recess of the centering rod. Draw a marking line on the jack holder by hanging the verticality reference string, and then
A jack is set upright on the jack holder with its axis aligned with this marking line, and then the plunger of this jack is inserted into the semicircular recess of the centering hole to ensure a vertical position. be. According to this conventional proposal, since the work of determining the standing position of the jack and the work of determining the vertical posture can be performed in a series of work processes using jack centering, the work efficiency is good and the work of determining the jack center By inserting the plunger into the semicircular recess of the plunger, a vertical posture can be automatically ensured, so there is no measurement error caused by the swinging of the weight of the verticality reference string, and highly accurate centering can be performed.

〔考案が解決しようとする問題点〕[Problem that the invention attempts to solve]

しかしながら、ジヤツキ芯出し雇を用いる上記
従来提案は、ジヤツキのプランジヤの外径に応じ
てそれぞれ異なる芯出し雇を用意しなしければな
らず、この芯出し雇は軽量化とプランジヤへの傷
付け防止を考慮して一般にアルミニウムで製作さ
れるので、プランジヤの外径に応じた芯出し雇を
用意するということはコスト面で問題があつた。
However, in the above-mentioned conventional proposal using a jack centering method, different centering methods must be prepared depending on the outer diameter of the plunger of the jack, and this centering method reduces weight and prevents damage to the plunger. Taking this into consideration, the plunger is generally made of aluminum, so preparing a centering tool that corresponds to the outer diameter of the plunger poses a problem in terms of cost.

本考案は叙上の点に鑑みてなされたものであ
り、その目的は、ジヤツキ据付時の作業効率およ
び芯出し精度が良好であるとともに、外径が異な
る複数種類のプランジヤに対応させることができ
てコストダウンが図れる油圧エレベータのジヤツ
キ据付装置を提供することにある。
The present invention was developed in view of the above points, and its purpose is to improve work efficiency and centering accuracy during plunger installation, and to be able to accommodate multiple types of plungers with different outer diameters. To provide a jack installation device for a hydraulic elevator that can reduce costs.

〔問題点を解決するための手段〕[Means for solving problems]

上記目的は、プランジヤの外周面のほぼ半周が
嵌入可能な半円状凹所を有し、昇降路壁面に芯出
し固定されたガイドレール間に装着されるジヤツ
キ芯出し雇として、互いに内径の異なる大小2種
類の上記半円状凹所を形成し、かつ各半円状凹所
の両側にそれぞれロープを逃がすための切欠を形
成してなる板状体を用いることによつて、達成さ
れる。
The purpose of the above is to have a semicircular recess into which approximately half of the outer circumferential surface of the plunger can be fitted, and to be used as a centering rod for a jack that is installed between guide rails that are centered and fixed on the hoistway wall. This is achieved by using a plate-shaped body formed with two types of semicircular recesses, large and small, and cutouts for letting the rope escape on both sides of each semicircular recess.

〔作用〕[Effect]

上記手段によれば、ジヤツキ芯出し雇に内径の
異なる2種類の半円状凹所が形成してあり、各半
円状凹所内にそれぞれ外径の異なるプランジヤを
嵌入することができるので、少なくとも2種類の
プランジヤに対し同一の芯出し雇を用いてジヤツ
キの据付作業を行うことができる。また、このジ
ヤツキ芯出し雇の一方の半円状凹所に、当該半円
状凹所よりも小径な半円状凹所を有する補助板を
取り付ければ、外径の異なるもう1種類のプラン
ジヤにも対応させることができる。
According to the above means, two types of semicircular recesses with different inner diameters are formed in the centering hole of the jack, and plungers with different outer diameters can be fitted into each semicircular recess, so that at least The jack installation work can be performed using the same centering method for two types of plungers. In addition, if an auxiliary plate having a semicircular recess with a smaller diameter than the semicircular recess is attached to one of the semicircular recesses of this plunger, it can be used as another type of plunger with a different outer diameter. can also be made compatible.

〔実施例〕〔Example〕

以下、本考案の実施例を図に基づいて説明す
る。
Hereinafter, embodiments of the present invention will be described based on the drawings.

第1図はジヤツキ芯出し雇たる板状体の平面
図、第2図はこの板状体を用いてジヤツキ受台に
基準線を描線する際の作業工程図、第3図はこの
板状体の半円状凹所内にプランジヤを嵌入した状
態を示す作業工程図であり、第5図、第6図と対
応する部分には同一符号が付してある。
Figure 1 is a plan view of the plate-shaped body used for centering the jack, Figure 2 is a work process diagram for drawing reference lines on the jack holder using this plate-shaped body, and Figure 3 is the plate-shaped body used for centering the jack. FIG. 6 is a work process diagram showing a state in which a plunger is fitted into a semicircular recess of FIG.

第1図〜第3図において、ジヤツキ芯出し雇た
る板状体1は略長方形状のアルミニウム板からな
り、この板状体1の両側角部にはそれぞれ、一対
のガウドレール8a,8bに固定するための係合
部2a,2bが設けてあり、板状体1の両辺中央
部にはそれぞれ、互いに内径の異なる半円状凹所
3a,3bが形成してある。これらの半円状凹所
3a,3bは、それぞれの内径に合致する外径を
有するプランジヤのほぼ半周分を嵌入することが
でき、各半円状凹所3a,3bの両側には、プラ
ンジヤ上端部に設けられるプーリに巻装されて乗
かごを昇降させるロープ(図示せず)を逃がすた
めの切欠4a,4bまたは切欠4c,4dが形成
してある。また、この実施例では、一方の半円状
凹所3aの周縁部に補助板7が取り付けてあり、
この補助板7に形成した半円状凹所7aを上記半
円状凹所3a内に臨出させてある。
In Figures 1 to 3, a plate-like body 1 used for centering the jack is made of a substantially rectangular aluminum plate, and is fixed to a pair of gaudle rails 8a and 8b at both corners of the plate-like body 1, respectively. Engaging portions 2a and 2b are provided for this purpose, and semicircular recesses 3a and 3b having different inner diameters are formed in the central portions of both sides of the plate-shaped body 1, respectively. These semicircular recesses 3a, 3b can fit approximately half the circumference of a plunger having an outer diameter matching the respective inner diameters, and an upper end of the plunger is provided on both sides of each semicircular recess 3a, 3b. Cutouts 4a and 4b or cutouts 4c and 4d are formed for letting out a rope (not shown) that is wound around a pulley provided at the part and raises and lowers the car. Further, in this embodiment, an auxiliary plate 7 is attached to the peripheral edge of one semicircular recess 3a,
A semicircular recess 7a formed in this auxiliary plate 7 projects into the semicircular recess 3a.

板状体1の半円状凹所3a近傍に突設した回転
軸20aには、中心位置に指標6が明示されてい
る幅狭なセンターゲージ5の一端が回動自在に取
り付けてあり、このセンターゲージ5の他端に形
成した係合用切込5aを板状体1の係合軸21a
に係合させることにより、センターゲージ5は半
円状凹所3aを跨いで板状体1に固定され、この
とき指標6は半円状凹所3aの形成する円の中心
と合致している。同様に、センターゲージ5の一
端を回転軸20bに取り付けて、他端の係合用切
込5aを係合軸21bに係合させると、このセン
ターゲージ5は他方の半円状凹所3b跨いで板状
体1に固定される。
One end of a narrow center gauge 5 with a mark 6 clearly marked at the center position is rotatably attached to a rotary shaft 20a protruding near the semicircular recess 3a of the plate-like body 1. The engagement notch 5a formed on the other end of the center gauge 5 is connected to the engagement shaft 21a of the plate-like body 1.
By engaging with the center gauge 5, the center gauge 5 is fixed to the plate-like body 1 across the semicircular recess 3a, and at this time, the index 6 is aligned with the center of the circle formed by the semicircular recess 3a. . Similarly, when one end of the center gauge 5 is attached to the rotating shaft 20b and the engagement notch 5a at the other end is engaged with the engagement shaft 21b, the center gauge 5 straddles the other semicircular recess 3b. It is fixed to the plate-like body 1.

さて、ジヤツキ据付作業を行う際には、まず、
板状体1をガイドレール8a,8b間に装着し、
昇降路底部にジヤツキ受台13を仮固定した後、
第2図に示すように、センターゲージ5の指標6
の位置から鉛直度基準紐23を垂下し、この鉛直
度基準紐23の先端に吊した円すい状の錘12の
突端を基準として、ジヤツキ受台13の表面に基
準線14を描線する。次いで、鉛直度基準紐23
を取り外し、基準線14に軸心位置を合わせて、
ジヤツキ11のシリンダ10をジヤツキ受台13
上に立設する。しかる後、第3図に示すように、
シリンダ10から突出しているプランジヤ9を、
板状体1に取り付けた補助板7の半円状凹所7a
内に嵌入し、このプランジヤ9の外周面のほぼ半
周を半円状凹所7aに合致させる。ここで、補助
板7は、その半円状凹所7aが半円状凹所3aと
同心の半円を形成するような位置に取り付けてあ
るので、プランジヤ9を半円状凹所7a内に嵌入
すると、ジヤツキ11の軸心は、センターゲージ
5の指標6から垂下した鉛直度基準紐23と完全
に一致することになり、ジヤツキ11の鉛直姿勢
が確保される。したがつて、ジヤツキ受台13上
でのジヤツキ11の立設位置を定める作業と、立
設したジヤツキ11の鉛直姿勢を定める作業と
が、板状体1を用いた一連の作業工程の中で行
え、作業効率が良好であるとともに、半円状凹所
7a内にプランジヤ9を嵌入すれば自動的にジヤ
ツキ11の鉛直姿勢が確保されるので、高精度な
芯出しが行える。
Now, when performing jack installation work, first of all,
Attach the plate-shaped body 1 between the guide rails 8a and 8b,
After temporarily fixing the jack cradle 13 to the bottom of the hoistway,
As shown in FIG. 2, the indicator 6 of the center gauge 5
A verticality reference string 23 is suspended from the position, and a reference line 14 is drawn on the surface of the jack holder 13 using the tip of the conical weight 12 suspended from the tip of the verticality reference string 23 as a reference. Next, the verticality reference string 23
Remove it, align the shaft center position with the reference line 14,
Place the cylinder 10 of the jack 11 on the jack holder 13
erected above. After that, as shown in Figure 3,
The plunger 9 protruding from the cylinder 10,
Semicircular recess 7a of auxiliary plate 7 attached to plate-shaped body 1
The plunger 9 is inserted into the inside of the plunger 9 so that approximately half the circumference of the outer peripheral surface of the plunger 9 matches the semicircular recess 7a. Here, since the auxiliary plate 7 is attached at a position such that its semicircular recess 7a forms a semicircle concentric with the semicircular recess 3a, the plunger 9 is inserted into the semicircular recess 7a. When inserted, the axis of the jack 11 completely coincides with the verticality reference string 23 hanging from the index 6 of the center gauge 5, and the vertical posture of the jack 11 is ensured. Therefore, the work of determining the erected position of the jack 11 on the jack holder 13 and the work of determining the vertical posture of the erected jack 11 are performed in a series of work processes using the plate-shaped body 1. In addition, since the vertical position of the jack 11 is automatically secured by inserting the plunger 9 into the semicircular recess 7a, highly accurate centering can be performed.

そして、ジヤツキ受台13上の所定位置に鉛直
姿勢を維持してジヤツキ11を立設したなら、昇
降路底部にジヤツキ受台13を固定し、このジヤ
ツキ受台13上にジヤツキ11のシリンダ10を
固定する。このように、ジヤツキ受台13上で立
設位置および鉛直姿勢が高精度に設定されたジヤ
ツキ11は、油圧操作に伴うプランジヤ9の移動
が鉛直線に沿つて行われるので、乗かごの円滑な
運行や停止位置精度が保障される。
After the jack 11 is set upright while maintaining a vertical posture at a predetermined position on the jack cradle 13, the jack cradle 13 is fixed to the bottom of the hoistway, and the cylinder 10 of the jack 11 is placed on the jack cradle 13. Fix it. In this way, the jack 11 whose upright position and vertical posture are set with high precision on the jack cradle 13 allows the plunger 9 to move along the vertical line in response to hydraulic operation, so that the car can be moved smoothly. Operation and stopping position accuracy are guaranteed.

また、上記実施例では板状体1の半円状凹所3
a,3bが共にプランジヤ9の外径と合致しない
ため、所望の大きさに形成された半円状凹所7a
を有する補助板7を板状体1に取り付けて使用し
ているが、プランジヤの外径が半円状凹所3a,
3bのいずれかと合致する場合には、補助板7を
取り付けることなく板状体1を使用できる。例え
ば、第4図に示すように、ジヤツキ11′のシリ
ンダ10′から突出しているプランジヤ9′の外径
が、板状体1の半円状凹所3aの内径と合致する
場合には、このプランジヤ9′を半円状凹所3a
内に嵌入することでジヤツキ11′の鉛直姿勢が
確保でき、同様に、半円状凹所3bの内径と合致
する小径のプランジヤを備えたジヤツキを据付け
る場合には、このプランジヤを半円状凹所3b内
に嵌入すればよい。なお、半円状凹所3bを利用
する場合には、この半円状凹所3bを跨ぐ位置に
取り付けたセンターゲージ5から鉛直度基準紐2
3を垂下して基準線14を描線する。結局、同一
の板状体1を用いて、外径の異なる3種類のプラ
ンジヤに対応させることができ、前記した従来技
術のようにプランジヤの外径に応じた多種類のジ
ヤツキ芯出し雇を用意する必要がなくなり、コス
トダウンが実現されている。
Further, in the above embodiment, the semicircular recess 3 of the plate-like body 1
Since both a and 3b do not match the outer diameter of the plunger 9, the semicircular recess 7a is formed to a desired size.
The auxiliary plate 7 having a diameter of
3b, the plate-like body 1 can be used without attaching the auxiliary plate 7. For example, as shown in FIG. 4, when the outer diameter of the plunger 9' protruding from the cylinder 10' of the jack 11' matches the inner diameter of the semicircular recess 3a of the plate-like body 1, The plunger 9' is inserted into the semicircular recess 3a.
By fitting the jack 11' into the inside, the vertical posture of the jack 11' can be secured. Similarly, when installing a jack equipped with a small diameter plunger that matches the inside diameter of the semicircular recess 3b, this plunger can be installed in a semicircular shape. What is necessary is just to fit into the recess 3b. In addition, when using the semicircular recess 3b, the verticality reference string 2 is connected to the center gauge 5 attached at a position straddling the semicircular recess 3b.
3 and draw the reference line 14. In the end, the same plate-like body 1 can be used to accommodate three types of plungers with different outer diameters, and unlike the prior art described above, many types of plungers can be set according to the outer diameter of the plunger. This eliminates the need to do so, resulting in cost reductions.

〔考案の効果〕[Effect of idea]

以上説明したように、本考案に係る油圧エレベ
ータのジヤツキ据付装置は、内径の異なる2種類
の半円状凹所を形成した板状のジヤツキ芯出し雇
を用い、必要に応じて補助板を取り付けることに
よつて、外径の異なる複数種類のプランジヤに同
一のジヤツキ芯出し雇を対応させることができ、
そのため、作業効率および芯出し精度が良好であ
ることに加えて、ジヤツキ芯出し雇の員数が低域
できてコストダウンが図れるという顕著な効果を
奏する。
As explained above, the jack installation device for hydraulic elevators according to the present invention uses a plate-shaped jack centering device with two types of semicircular recesses with different inner diameters, and by attaching an auxiliary plate as necessary, the same jack centering device can be used for multiple types of plungers with different outer diameters.
Therefore, in addition to improving the work efficiency and centering accuracy, the number of personnel required for centering the jack can be reduced, resulting in significant effects in reducing costs.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図はジヤツキ芯出し雇たる板状体の平面
図、第2図はこの板状体を用いてジヤツキ受台に
基準線を描線する際の作業工程図、第3図はこの
板状体の半円状凹所内にプランジヤを嵌入した状
態を示す作業工程図、第4図はこの板状体の他の
使用例を示す作業工程図、第5図は油圧エレベー
タの要部構成図、第6図は第5図のA−A線断面
図である。 1……板状体(ジヤツキ芯出し雇)、2a,2
b……係合部、3a,3b,7a……半円状凹
所、4a,4b,4c,4d……切欠、5……セ
ンターゲージ、7……補助板、8a,8b……ガ
イドレール、9……プランジヤ、10……シリン
ダ、11……ジヤツキ、13……ジヤツキ受台、
14……基準線、23……鉛直度基準紐。
Figure 1 is a plan view of the plate-shaped body used for centering the jack, Figure 2 is a work process diagram for drawing reference lines on the jack holder using this plate-shaped body, and Figure 3 is the plate-shaped body used for centering the jack. Fig. 4 is a work process diagram showing a state in which the plunger is fitted into a semicircular recess, Fig. 4 is a work process diagram showing another example of the use of this plate-like body, Fig. 5 is a diagram showing the main part configuration of a hydraulic elevator, Fig. FIG. 6 is a sectional view taken along line A--A in FIG. 5. 1... Plate-shaped body (jatsuki centering), 2a, 2
b...Engaging portion, 3a, 3b, 7a...Semicircular recess, 4a, 4b, 4c, 4d...Notch, 5...Center gauge, 7...Auxiliary plate, 8a, 8b...Guide rail , 9... plunger, 10... cylinder, 11... jack, 13... jack cradle,
14...Reference line, 23...Verticality reference string.

Claims (1)

【実用新案登録請求の範囲】 (1) ジヤツキのプランジヤ上端部に設けられたプ
ーリの上下動を案内するためのガイドレールを
昇降路壁面に芯出し固定した後、上記プランジ
ヤの外周面のほぼ半周が嵌入可能な半円状凹所
を備えたジヤツキ芯出し雇を上記ガイドレール
間に装着し、この芯出し雇の上記半円状凹所を
跨いで取り付けたセンターゲージから鉛直度基
準紐を垂下してジヤツキ受台に基準線を描線
し、しかる後、この基準線に基づいて上記ジヤ
ツキ受台にジヤツキを立設するとともに、この
ジヤツキのプランジヤを上記芯出し雇の半円状
凹所内に嵌入してジヤツキを芯出し固定するよ
うにした据付過程の油圧エレベータのジヤツキ
据付装置において、上記ジヤツキ芯出し雇とし
て、互いに内径の異なる大小2種類の上記半円
状凹所を形成し、かつ各半円状凹所の両側にそ
れぞれ上記プーリに巻装されるロープを逃がす
ための切欠を形成してなる板状体を用いたこと
を特徴とする油圧エレベータのジヤツキ据付装
置。 (2) 実用新案登録請求の範囲第(1)項の記載におい
て、上記板状体に、いずれか一方の上記半円状
凹所内に臨出して当該半円状凹所よりも小径な
半円状凹所を有する補助板を取り付けたことを
特徴とする油圧エレベータのジヤツキ据付装
置。
[Scope of Claim for Utility Model Registration] (1) After centering and fixing the guide rail for guiding the vertical movement of the pulley provided at the upper end of the plunger of the jack to the shaft wall surface, approximately half the circumference of the outer circumferential surface of the plunger. A jack centering rod equipped with a semicircular recess into which the centering rod can be inserted is installed between the guide rails, and a verticality reference string is hung from the center gauge attached across the semicircular recess of the centering rod. Then, draw a reference line on the jack holder, and then erect the jack on the jack holder based on this reference line, and fit the plunger of this jack into the semicircular recess of the centering hole. In the jack installation device for a hydraulic elevator during the installation process, which centers and fixes the jack, two types of semicircular recesses, large and small, with different inner diameters are formed as the jack centering part, and each semicircular recess is 1. A jack installation device for a hydraulic elevator, characterized in that a plate-like body is used in which cutouts are formed on both sides of a circular recess to allow the ropes wound around the pulley to escape. (2) In the statement in paragraph (1) of claims for utility model registration, the plate-shaped body has a semicircular shape that projects into one of the semicircular recesses and has a diameter smaller than that of the semicircular recess. A jack installation device for a hydraulic elevator, characterized in that an auxiliary plate having a shaped recess is attached.
JP17138487U 1987-11-11 1987-11-11 Expired JPH0447184Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP17138487U JPH0447184Y2 (en) 1987-11-11 1987-11-11

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP17138487U JPH0447184Y2 (en) 1987-11-11 1987-11-11

Publications (2)

Publication Number Publication Date
JPH0176875U JPH0176875U (en) 1989-05-24
JPH0447184Y2 true JPH0447184Y2 (en) 1992-11-06

Family

ID=31463172

Family Applications (1)

Application Number Title Priority Date Filing Date
JP17138487U Expired JPH0447184Y2 (en) 1987-11-11 1987-11-11

Country Status (1)

Country Link
JP (1) JPH0447184Y2 (en)

Also Published As

Publication number Publication date
JPH0176875U (en) 1989-05-24

Similar Documents

Publication Publication Date Title
JPH0447184Y2 (en)
CN204657826U (en) A kind of lifting deflector roll shelf
CN212170211U (en) Automatic change airtight detection anchor clamps for wire machine tool
JPS632870B2 (en)
JPS6458435A (en) C-ring assembling device
JPS62181841A (en) Industrial robot device
CN215467211U (en) Automatic socket roundness correcting machine
JPS5854458Y2 (en) Hydraulic cylinder for elevator
JPS627660Y2 (en)
JPH0529298Y2 (en)
JPH092760A (en) Jack stand positioning device for hydraulic elevator
JPS5813823A (en) Static load type pile driver
JPH052259Y2 (en)
CN114220643B (en) Transformer assembling device
CN115597472B (en) Iron tower foundation eccentric measurement device for preventing tower from falling based on center distance
JP2526298Y2 (en) Hanging tools
CN216991775U (en) Clearance adjustment instrument
JP2603733B2 (en) Elevator guide rail centering device
JPH01285574A (en) Centering device for hydraulic jack
JPS6114518Y2 (en)
SU589359A1 (en) Device for connecting drilling mast with gantry
JPH03186586A (en) Alignment device for guide rail
JPS6116560Y2 (en)
JP2746019B2 (en) Automatic positioning coil lifter
CN117845757A (en) Bridge support rapid leveling method