JPH0441206B2 - - Google Patents

Info

Publication number
JPH0441206B2
JPH0441206B2 JP29168685A JP29168685A JPH0441206B2 JP H0441206 B2 JPH0441206 B2 JP H0441206B2 JP 29168685 A JP29168685 A JP 29168685A JP 29168685 A JP29168685 A JP 29168685A JP H0441206 B2 JPH0441206 B2 JP H0441206B2
Authority
JP
Japan
Prior art keywords
hull
scrapped
constructed
earth
quay
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP29168685A
Other languages
Japanese (ja)
Other versions
JPS62148706A (en
Inventor
Kazunori Mitsuyasu
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Japan Industrial Land Development Co Ltd
Original Assignee
Japan Industrial Land Development Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Japan Industrial Land Development Co Ltd filed Critical Japan Industrial Land Development Co Ltd
Priority to JP29168685A priority Critical patent/JPS62148706A/en
Publication of JPS62148706A publication Critical patent/JPS62148706A/en
Publication of JPH0441206B2 publication Critical patent/JPH0441206B2/ja
Granted legal-status Critical Current

Links

Description

【発明の詳細な説明】 (イ) 技術分野 本発明は、不要となつた大型タンカー等の船体
を利用し、船舶を横付けするのに適した桟橋形式
の大水深用岸壁や護岸を築造する方法に関するも
のである。
[Detailed Description of the Invention] (a) Technical Field The present invention is a method of constructing a deep-water quay or seawall in the form of a pier suitable for berthing ships by using the hulls of large tankers or the like that are no longer needed. It is related to.

(ロ) 背景技術 近時、桟橋形式の岸壁等は船舶の大型化や立地
の面から沖合いの大水深でかつ地盤の軟弱な所に
構築することが多い。
(b) Background technology Recently, due to the increase in the size of ships and the location, many pier-type quays are constructed offshore in deep water and on soft ground.

しかるに、従来この種の岸壁を築造する場合に
は、鋼管矢板等により二重締切構造による護岸を
構築したり、大量の捨石によるマウンドを築造し
たのち、その上にコンクリート製ケーソンを据付
けて構築する方法が採られているが、鋼管矢板工
法は大水深の岸壁では外力や応力等により断面荷
重が大きくなつて不経済であると共に、その施工
も非常に難しい。また、捨石マウンド工法は捨石
を高く盛上げてから、その上に壁高の鉄筋コンク
リート製ケーソンを据付けるものであり、大水深
ではマウンドの均し精度が悪く、しかも壁高のコ
ンクリートケーソンはその製作が非常に面倒で工
費的にも不経済であつた。
However, conventionally, when constructing this type of quay, a revetment is constructed using a double cofferdam structure using steel pipe sheet piles, etc., or a mound is constructed using a large amount of rubble, and then a concrete caisson is installed on top of the revetment. However, the steel pipe sheet pile construction method is uneconomical on quay walls in deep water because the cross-sectional load increases due to external forces and stress, and it is also extremely difficult to construct. In addition, the rubble mound construction method involves piling up rubble to a high height and then installing a wall-height reinforced concrete caisson on top of it.The leveling accuracy of the mound is poor in deep water, and the fabrication of wall-height concrete caissons is difficult. It was extremely troublesome and uneconomical in terms of construction costs.

(ハ) 発明の開示 本発明は上述のような従来の問題点に鑑み、あ
らかじめ工場等で廃船となつた大型タンカー等の
船腹部を任意の大きさに切出して加工し、これを
岸壁築造個所に設置して桟橋形式の岸壁とする製
作、施工が簡単で、急速施工が可能な経済的な岸
壁築造法を提案するものである。
(c) Disclosure of the Invention In view of the above-mentioned conventional problems, the present invention involves cutting and processing the belly of a large tanker, etc., which has been decommissioned at a factory, into a desired size, and then constructing a wharf. This paper proposes an economical method of constructing quay walls that can be installed at individual locations to form pier-style quay walls that are easy to manufacture and construct, and that can be constructed quickly.

以下、本発明方法の実施例を図により説明す
る。
Examples of the method of the present invention will be described below with reference to the drawings.

(ニ) 実施例 1は廃船となつた大型タンカー等の船底及び船
側が比較的平行な部分を工場等で切出した例えば
幅が40〜60m、高さが20〜35m、長さが160〜
240mといつた大ブロツクの廃船体で、該廃船体
1の上面には該廃船体1を海底に沈設した場合の
海側に寄せてその長さ方向に多数本の鋼管等の支
持杭2を一列あるいは複数列(例えば図のように
外縁部に一列と海側の縦通隔壁に一列)立設固定
する。また、該廃船体1上面の中央より陸側に寄
せて(例えば図のように陸側の縦通隔壁上に)土
留壁3となる矢板壁を立設しあるいはコンクリー
トケーソン又は廃船体から切出した他の部分を設
置固定する。
(D) Example 1 is a part of an abandoned large tanker whose bottom and side are relatively parallel, cut out in a factory, etc. For example, the width is 40 to 60 m, the height is 20 to 35 m, and the length is 160 m to 160 m.
The scrapped hull is a large block with a length of 240 m. On the upper surface of the scrapped hull 1, a large number of support piles 2 such as steel pipes are installed in the length direction of the scrapped hull 1, which will be moved toward the sea side when the scrapped hull 1 is sunk on the seabed. One or more rows (for example, one row on the outer edge and one row on the longitudinal bulkhead on the sea side, as shown in the figure) are erected and fixed. In addition, a sheet pile wall that will become the retaining wall 3 is erected from the center of the top surface of the scrapped hull 1 toward the land side (for example, on the longitudinal bulkhead on the land side as shown in the figure), or is cut out from a concrete caisson or the scrapped hull. Install and fix other parts.

このようにして一体に構成された構造物は全て
陸上で製作され、これを岸壁築造個所まで曳航し
て来る。
All of the structures constructed in this way are built on land and towed to the quay construction site.

そこで、まず岸壁築造個所の海底地盤の状況に
より、必要に応じて低い基礎4を捨石により構成
する。次に、上記構造物を基礎4上に沈設し、廃
船体1内に中詰土砂5を充填する。また、該廃船
体1の陸側となる背部ならびに土留壁3背面に土
砂6を裏込めして、該廃船体1を安定させる。
Therefore, first, depending on the condition of the seabed ground where the quay is being constructed, a low foundation 4 is constructed of rubble as necessary. Next, the above-mentioned structure is placed on the foundation 4, and the inside of the scrapped hull 1 is filled with earth and sand 5. In addition, earth and sand 6 is backfilled on the land side back of the scrapped hull 1 and on the back of the retaining wall 3 to stabilize the scrapped hull 1.

次いで、海面上に突出した前記支持杭を利用し
て鉄筋を組み、廃船体1上方に上記裏込め土砂6
と同一面となるようにコンクリートスラブ7等を
施工設置し、これにより桟橋形式の岸壁が完成さ
れるのである。
Next, reinforcing bars are erected using the support piles protruding above the sea surface, and the backfill earth 6 is placed above the scrapped hull 1.
Concrete slabs 7, etc. are constructed and installed so that they are flush with the surface, and the pier-style quay wall is completed.

8は上記スラブ7上に敷設したレール9上を走
行する荷役用クレーンである。なお、該クレーン
8の荷重が極めて大き場合は前述の支持杭2を連
続させることも可能である。
8 is a cargo handling crane that runs on rails 9 laid on the slab 7. In addition, if the load of the crane 8 is extremely large, it is also possible to make the above-mentioned support piles 2 continuous.

また、本構造型式を護岸として利用する場合に
は、前述の支持杭2は不要となり、土留壁3を廃
船体1の端し圧が基礎地盤の許容支持力以内とな
るような任意な位置に設置し、基礎部分の工費を
低減することも考えられる。
In addition, when this structural type is used as a seawall, the above-mentioned support piles 2 are not required, and the retaining wall 3 can be placed at any position where the end pressure of the scrapped hull 1 is within the allowable bearing capacity of the foundation ground. It is also possible to reduce the construction cost of the foundation by installing it.

(ホ) 発明の効果 本発明方法は上記のようにしてなるもので、そ
の利点を挙げれば次の通りである。
(e) Effects of the invention The method of the present invention is achieved as described above, and its advantages are as follows.

(a) 沈設した大型廃船体の上面に支持杭及び土留
壁を立設するので、これら支持杭等の長さが大
水深の岸壁でも比較的短かくて済む。
(a) Since support piles and retaining walls are erected on the top of the sunken large abandoned ship, the length of these support piles can be relatively short even on quays in deep water.

(b) 沈設した廃船体の海側の上載荷重が小さいの
で、端し圧が均等化された安定した岸壁が築造
でき、かつ基礎の地盤改良費が低減できる。
(b) Since the overload on the sea side of the sunken scrap hull is small, a stable quay with equalized edge pressure can be constructed, and the cost of ground improvement for the foundation can be reduced.

(c) 廃船体、支持杭、土留壁からなる構造物を陸
上製作するので加工精度が高く、またコンクリ
ートケーソンに比較して海象や気象に左右され
ることがなく、製作期間が短縮されて製作費も
安価であり、しかも大型の廃船体を用いるので
工期も大幅に短縮することができる。
(c) Since the structure consisting of the scrap hull, supporting piles, and retaining walls is manufactured on land, processing accuracy is high, and compared to concrete caissons, it is less affected by sea conditions and weather, reducing the manufacturing period. The cost is low, and since a large scrap hull is used, the construction period can be significantly shortened.

(d) 大水深用岸壁であつても、海底基礎の捨石を
減少又は不要とすることができるので、海上の
汚濁防止や船舶の航行の面からも有利である。
(d) Even for deep-water quays, it is possible to reduce or eliminate the need for rubble on the seabed foundations, which is advantageous from the standpoint of marine pollution prevention and ship navigation.

(e) コンクリートケーソン堤等に比べて、堤体延
長が長いため、基礎地盤の不等沈下に対しても
有利で、上載構造物(例えばクレーン)に対す
る沈下補強対策等が不必要となる。
(e) Compared to concrete caisson embankments, etc., the embankment length is longer, so it is advantageous against uneven settlement of the foundation ground, and there is no need to take measures to strengthen the overlying structures (e.g. cranes).

【図面の簡単な説明】[Brief explanation of drawings]

図は本発明法により築造された岸壁の一例を示
す説明図である。 符号説明、1−廃船体、2−支持杭、3−土留
壁、4−海底基礎、5−中詰土砂、6−裏込土
砂、7−スラブ、8−クレーン、9−レール。
The figure is an explanatory diagram showing an example of a quay constructed by the method of the present invention. Explanation of symbols: 1 - Scraped ship hull, 2 - Support pile, 3 - Retaining wall, 4 - Seabed foundation, 5 - Filling earth and sand, 6 - Back filling earth and sand, 7 - Slab, 8 - Crane, 9 - Rail.

Claims (1)

【特許請求の範囲】[Claims] 1 不要となつた大型タンカー等の船腹部を切出
した廃船体の上面にその長さ方向に多数本の支持
杭を一列あるいは複数列立設固定すると共に矢板
等による土留壁を立設して構成された構造物を、
岸壁築造個所まで曳航して海底基礎上に沈設した
後、該廃船体内に中詰土砂を充填し、次に陸側と
なる上記廃船体の背面部ならびに土留壁の背部に
土砂を裏込めし、次いで海面上に突出した上記支
持杭上にコンクリートスラブを施工設置すること
を特徴とする廃船を利用した岸壁の築造方法。
1. Constructed by erecting and fixing a large number of support piles in one or more rows in the length direction on the upper surface of a discarded hull of a large tanker, etc. that is no longer needed, and also erecting an earth retaining wall made of sheet piles, etc. The structure that was
After being towed to the location where the quay is to be constructed and deposited on the undersea foundation, the scrapped hull is filled with earth and sand, and then earth and sand is backfilled into the back of the scrapped hull and the back of the retaining wall, which will be on the land side. and then constructing and installing a concrete slab on the support piles protruding above the sea surface.
JP29168685A 1985-12-24 1985-12-24 Construction of quaywall by utilizing scrap ship Granted JPS62148706A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP29168685A JPS62148706A (en) 1985-12-24 1985-12-24 Construction of quaywall by utilizing scrap ship

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP29168685A JPS62148706A (en) 1985-12-24 1985-12-24 Construction of quaywall by utilizing scrap ship

Publications (2)

Publication Number Publication Date
JPS62148706A JPS62148706A (en) 1987-07-02
JPH0441206B2 true JPH0441206B2 (en) 1992-07-07

Family

ID=17772098

Family Applications (1)

Application Number Title Priority Date Filing Date
JP29168685A Granted JPS62148706A (en) 1985-12-24 1985-12-24 Construction of quaywall by utilizing scrap ship

Country Status (1)

Country Link
JP (1) JPS62148706A (en)

Also Published As

Publication number Publication date
JPS62148706A (en) 1987-07-02

Similar Documents

Publication Publication Date Title
CN110382781B (en) Marine structure for laying the foundation of buildings, equipment and wind turbines by gravity in a marine environment
NO343178B1 (en) Seabed base structure and method for installation of same
Smith Types of marine concrete structures
US11787514B2 (en) Marine construction and a method for constructing the same
CN111485579B (en) Bridge-tunnel transition conversion structure between suspension tunnel and deepwater suspension bridge
JPH0441206B2 (en)
JP2815492B2 (en) How to build an underwater foundation
JP2676779B2 (en) Cylindrical caisson
CN212128811U (en) Main tower artificial island structure of deep open sea suspension bridge
KR102169627B1 (en) Installation method of concrete sinker for floating structure
JP2597878B2 (en) Weir structure
Roy Marine Projects
JPS58160420A (en) Levee body using king post
JPS622081B2 (en)
JP2004011142A (en) Sea area environment-coexistent quay structure
Tsinker Gravity-Type Quay Walls
Agerbæk et al. First Major US Offshore Wind Staging Terminal: Planning, Engineering, and Construction
JP2652026B2 (en) Quay construction method
BOKHOVEN RECENT QUAY WALL CONSTRUCTION AT ROTTERDAM HARBOUR.
Qian et al. Maryam Marani-Barzani4, Farnaz Rafat5 and Ali Hasantabar-Amiri6 1Civil & Environmental Engineering, Lamar University, Texas State University System, Beaumont, TX, USA
JPS6134534B2 (en)
JP2745097B2 (en) Construction method of low temperature liquefied gas underground tank
Wotton et al. 15. Cellular coffer dams as breakwaters and coastal structures
JPH0588326B2 (en)
JP2003003453A (en) Hybrid artificial ground constructed in ocean space and its construction method

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term