JPH04231785A - Pipeline laying method - Google Patents

Pipeline laying method

Info

Publication number
JPH04231785A
JPH04231785A JP2409078A JP40907890A JPH04231785A JP H04231785 A JPH04231785 A JP H04231785A JP 2409078 A JP2409078 A JP 2409078A JP 40907890 A JP40907890 A JP 40907890A JP H04231785 A JPH04231785 A JP H04231785A
Authority
JP
Japan
Prior art keywords
pipeline
pipe
welding
base end
joining
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2409078A
Other languages
Japanese (ja)
Inventor
Tomoya Fujimoto
智也 藤本
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JFE Steel Corp
Original Assignee
Kawasaki Steel Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kawasaki Steel Corp filed Critical Kawasaki Steel Corp
Priority to JP2409078A priority Critical patent/JPH04231785A/en
Publication of JPH04231785A publication Critical patent/JPH04231785A/en
Pending legal-status Critical Current

Links

Landscapes

  • Butt Welding And Welding Of Specific Article (AREA)

Abstract

PURPOSE:To lessen an occupation area required for joining work of a base end portion of a pipeline to a new pipe and to facilitate welding for the joining. CONSTITUTION:A post 2 is erected straight on a bank 7 on one side and a pipe supporting base 1 including a welding stand 3, which can be raised and lowered, provided on the said post 2. A new pipe 5, which is lifted up with a crane 6, is welded to a base end portion 4 of a pipeline 10, which is solidified by means of the said supporting base 1, and join together with the axis in a vertical condition. The pipeline 10 formed by joining is moved to a specified location. The pipeline 10 is laid by repeating the process.

Description

【発明の詳細な説明】[Detailed description of the invention]

【0001】0001

【産業上の利用分野】本発明は、複数のパイプを接合し
てなるパイプラインを敷設するパイプラインの敷設方法
に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a pipeline installation method for installing a pipeline formed by joining a plurality of pipes.

【0002】0002

【従来の技術】従来のパイプラインの敷設方法は、例え
ば特開平2−8108号公報に記載されているように、
パイプラインを敷設する河川や海等の一方の陸地におい
て、パイプをパイプ供給元から傾斜状送給路へ、転がし
たりジャッキ付き台車等を使用して水平に移動して、前
記傾斜状送給路に軸を水平にして設置されているパイプ
ラインの基端部に前記パイプの一端部を当接し、その当
接部を溶接により接合すると共に、パイプラインの先端
部を所定位置に向けて引っ張り、前記接合したパイプの
他端部を新たなパイプラインの基端部とする。
BACKGROUND OF THE INVENTION A conventional pipeline laying method is as described in, for example, Japanese Unexamined Patent Publication No. 2-8108.
On one land such as a river or sea where a pipeline is to be laid, the pipe is moved horizontally from the pipe supply source to the inclined feeding path by rolling it or using a truck with a jack, etc. one end of the pipe is brought into contact with the base end of a pipeline installed with its axis horizontal, the abutting part is joined by welding, and the tip of the pipeline is pulled toward a predetermined position; The other end of the joined pipe is the base end of a new pipeline.

【0003】そして、前記パイプの接合と移動の工程を
繰り返して河川や海等の一方の岸から所定位置までパイ
プラインを敷設している。
[0003]The steps of joining and moving the pipes are repeated to construct a pipeline from one shore of a river or sea to a predetermined position.

【0004】0004

【発明が解決しようとする課題】しかしながら、前記従
来のパイプラインの敷設方法では、接合するパイプライ
ンの基端部とパイプの軸を水平に保持した状態で接合す
るため、前記接合作業をする陸地には広大な作業面積が
必要であり、特に接合するパイプが長尺になるほど前記
接合作業をするために広大な作業面積を必要とするとい
う問題がある。
[Problems to be Solved by the Invention] However, in the conventional pipeline laying method, since the base end of the pipeline to be joined and the axis of the pipe are held horizontally, the land area where the joining work is performed is difficult. This method requires a large working area, and there is a problem in that the longer the pipes to be joined, the larger the working area is required to carry out the joining work.

【0005】また、接合するパイプラインの基端部とパ
イプの軸とを水平状態に固定して溶接を施工するために
、高度な技量が要求される全姿勢での溶接技術を必要と
するという問題もある。本発明は、前記のような問題点
に着目してなされたもので、パイプラインの基端部に新
たなパイプを接合するために使用する占有面積を少なく
し、さらに前記接合のための溶接施工作業を容易にする
ことを目的としている。
[0005] Furthermore, in order to carry out welding while fixing the base end of the pipeline to be joined and the axis of the pipe in a horizontal state, it is said that welding techniques in all positions that require a high level of skill are required. There are also problems. The present invention has been made with attention to the above-mentioned problems, and it reduces the area occupied by joining a new pipe to the base end of a pipeline, and further reduces the welding work required for the joining. The purpose is to make your work easier.

【0006】[0006]

【課題を解決するための手段】上記目的を達成するため
に、本発明のパイプラインの敷設方法は、パイプライン
の基端部に新たなパイプを継ぎ足すとともに、パイプラ
インの先端部を所定位置に向けて引き延ばすパイプライ
ン敷設方法において、パイプラインの基端部を上に向け
て支持するとともに、前記基端部の上端に、軸を上下の
向けた新たなパイプの下端を溶接して接合することを特
徴としている。
[Means for Solving the Problems] In order to achieve the above object, the pipeline laying method of the present invention includes adding a new pipe to the base end of the pipeline and moving the distal end of the pipeline to a predetermined position. In a pipeline laying method in which the base end of the pipeline is stretched upward, the base end of the pipeline is supported upward, and the lower end of a new pipe whose axis is oriented vertically is welded and joined to the upper end of the base end. It is characterized by

【0007】[0007]

【作用】軸を上下に向けたパイプラインの基端部に新た
なパイプの下端を接合しながら、前記接合により形成さ
れる一連のパイプラインを接合位置の下方においては所
定の曲率半径を持たせて撓ませつつ所定位置に向けて移
動する。このとき、前記所定の曲率半径はパイプライン
敷設位置から前記基端部までの高さが低いほど小さく取
る必要があるので、パイプの管径や管厚等に応じて前記
基端部の高さを決定し、使用するパイプの弾性変形以上
に撓まないようにする。
[Operation] While joining the lower end of a new pipe to the base end of the pipeline with its axis facing up and down, the series of pipelines formed by the joining has a predetermined radius of curvature below the joining position. move it toward a predetermined position while bending it. At this time, the predetermined radius of curvature needs to be set smaller as the height from the pipeline installation position to the base end is lower. to ensure that the pipe does not bend beyond the elastic deformation of the pipe being used.

【0008】また、パイプラインの基端部と新たなパイ
プを軸を上下にして接合するため、前記接合作業で占有
する作業面積は、パイプの長さや管径等に影響されずに
、前記基端部及び該新たなパイプを上下に支持する装置
を設置するだけの面積だけで済む。さらに、前記接合の
ために行う溶接施工は、軸を上下にした前記パイプライ
ンの基端部と新たなパイプとの水平になった当接部に対
して実施するため、水平姿勢からの溶接施工だけで済み
、鋼管杭を溶接するための周知技術をそのまま適用でき
る。
[0008] Furthermore, since the base end of the pipeline and the new pipe are joined with their axes up and down, the working area occupied by the joining work is not affected by the length or diameter of the pipe, and is Only the area necessary to install the end and the device for vertically supporting the new pipe is required. Furthermore, since the welding work performed for the above-mentioned joining is performed on the horizontal abutting part between the base end of the pipeline with the axis up and down and the new pipe, the welding work is performed from a horizontal position. The well-known technology for welding steel pipe piles can be applied as is.

【0009】[0009]

【実施例】以下、本発明の実施例を図面に基づいて説明
する。本実施例は河川の底にパイプラインを敷設する例
である。まず、図1に示すように、パイプライン10を
敷設する河川の一方の岸7側に、パイプ支持台1を設置
する。前記パイプ支持台1は、ポスト2,溶接スタンド
及び補助スタンド9からなり、前記岸7側の陸地に軸を
上下にしたポスト2を建て、そのポスト2に溶接スタン
ド3の一端部3aを上下へ移動可能に固定して、その溶
接スタンド3をパイプライン敷設方向へ水平に延設し、
さらに前記溶接スタンド3の他端部3bに、パイプライ
ン10の基端をなす第1のパイプ4を上下に把持する把
持部3cを設け、また、該溶接スタンド3の上方に、新
たなパイプ5を軸を上下にして支持する保持部を有する
補助スタンド9を、一端部を前記ポスト2に昇降可能に
固定してパイプライン敷設方向に延設している。
Embodiments Hereinafter, embodiments of the present invention will be explained based on the drawings. This embodiment is an example in which a pipeline is laid at the bottom of a river. First, as shown in FIG. 1, a pipe support stand 1 is installed on one bank 7 side of a river where a pipeline 10 is to be laid. The pipe support stand 1 consists of a post 2, a welding stand, and an auxiliary stand 9. The post 2 is built on land on the shore 7 side with its axis vertically, and one end 3a of the welding stand 3 is mounted vertically on the post 2. The welding stand 3 is movably fixed and extended horizontally in the pipeline laying direction,
Further, the other end 3b of the welding stand 3 is provided with a gripping part 3c for vertically gripping the first pipe 4 forming the base end of the pipeline 10, and a new pipe 5 is provided above the welding stand 3. An auxiliary stand 9 having a holding part for supporting the shaft with its axis up and down is fixed at one end to the post 2 so as to be movable up and down, and extends in the pipeline laying direction.

【0010】前記のようにパイプ支持台1を設置した後
、図3の流れ図に示すように、図示しないパイプ供給元
からクレーン6を使用してパイプを吊り込み移動させ、
該パイプを溶接スタンド3の把持部3cに軸を上下にし
て把持させて、そのパイプの上端部をパイプライン10
の基端部4とする(ステップ1)。このとき、前もって
前記溶接スタンド3をポスト2に沿って上下させて、接
合するパイプ4,5の弾性変形による撓みの範囲内で、
敷設する川底に沿って接合したパイプによるパイプライ
ン10が所定の曲率半径を有するように溶接スタンド3
設置位置の高さを決定する。例えば、前記パイプの肉厚
が厚く弾性変形が小さい場合には前記曲率半径が大きく
なるように、前記溶接スタンド3の設置位置を高くする
(図1中点線にて示した位置)。なお、パイプ成形時に
、敷設に使用される全パイプの両端外周の角は溶接のた
めに面取りされている。
After installing the pipe support 1 as described above, as shown in the flowchart of FIG. 3, the pipe is lifted and moved from a pipe supply source (not shown) using a crane 6.
The pipe is held by the gripping part 3c of the welding stand 3 with the axis up and down, and the upper end of the pipe is attached to the pipeline 10.
(Step 1). At this time, the welding stand 3 is moved up and down along the post 2 in advance within the range of flexure due to elastic deformation of the pipes 4 and 5 to be joined.
Welding stand 3 is installed so that pipeline 10 made of pipes joined along the river bed to be laid has a predetermined radius of curvature.
Determine the height of the installation location. For example, if the wall thickness of the pipe is thick and the elastic deformation is small, the welding stand 3 is installed at a higher position (the position indicated by the dotted line in FIG. 1) so that the radius of curvature becomes larger. Note that during pipe forming, the corners of the outer periphery of both ends of all pipes used for laying are chamfered for welding.

【0011】次に、図示しないパイプ供給元から吊り手
段であるクレーン6により新たなパイプ5を吊り上げ、
そのパイプ5を前記溶接スタンド3に固定した前記基端
部4の上方に移動する(ステップ2)。続けて、図2に
示すように、吊り上げている新たなパイプ5を下降させ
て前記基端部4に前記パイプ5の下端を当接させる(ス
テップ3)。このとき、前記新たなパイプ5を補助スタ
ンド9に設けられた保持部で支持させて前記当接状態を
保持する。
Next, a new pipe 5 is lifted from a pipe supply source (not shown) by a crane 6 serving as a lifting means.
The pipe 5 is moved above the base end 4 fixed to the welding stand 3 (step 2). Subsequently, as shown in FIG. 2, the newly lifted pipe 5 is lowered to bring the lower end of the pipe 5 into contact with the base end portion 4 (step 3). At this time, the new pipe 5 is supported by a holding portion provided on the auxiliary stand 9 to maintain the abutting state.

【0012】次に、前記パイプ5の下端部外周に、その
外周に沿って水平に移動可能な自動溶接装置11を設置
して、該溶接装置11の先端部11aを、前記当接した
パイプライン10の基端部4と新たなパイプ5との当接
部分に向け、該当接部分に沿って前記溶接装置11の先
端部11aを移動させることで、水平姿勢を維持しなが
ら前記当接部を溶接して前記基端部4と新たなパイプ5
を接合する(ステップ4)。なお、前記水平溶接法は、
特開昭51−26315号公報や実開昭55−1657
85号公報等に記載されている公知の水平溶接法が採用
可能である。
Next, an automatic welding device 11 that can move horizontally along the outer circumference of the pipe 5 is installed on the outer circumference of the lower end of the pipe 5, and the tip 11a of the welding device 11 is attached to the abutted pipeline. By moving the distal end portion 11a of the welding device 11 along the corresponding contact portion toward the contact portion between the base end portion 4 of the pipe 10 and the new pipe 5, the contact portion is moved while maintaining a horizontal posture. Weld the base end 4 and the new pipe 5
(Step 4). Note that the horizontal welding method is
Japanese Unexamined Patent Publication No. 51-26315 and Utility Model Application No. 55-1657
A known horizontal welding method described in Japanese Patent No. 85 and the like can be employed.

【0013】前記基端部4と新たなパイプ5の当接部の
接合が終了したら、前記溶接装置11を外し、さらにク
レーン6でパイプ5の上端を支持しながら溶接スタンド
3の把持部3cを緩めて、パイプ5の上部を溶接スタン
ド3が把持可能な位置までパイプ5を下方に移動させ、
続けて前記把持部3cで前記パイプ5の上部を把持させ
て該パイプ5の上端部をパイプライン10の基端部4と
する(ステップ5)。このとき、パイプライン10の先
端部8を、図示しない対岸に設置されているウィンチ等
によって底引きして対岸に向けて移動する。なお、先端
部8は予め閉塞されていて異物の侵入を防止している。
When the connection between the base end 4 and the abutting part of the new pipe 5 is completed, the welding device 11 is removed, and while the upper end of the pipe 5 is supported by the crane 6, the gripping part 3c of the welding stand 3 is lifted. Loosen the pipe 5 and move the pipe 5 downward to a position where the welding stand 3 can grip the upper part of the pipe 5.
Subsequently, the upper part of the pipe 5 is gripped by the gripping part 3c, so that the upper end of the pipe 5 becomes the base end 4 of the pipeline 10 (step 5). At this time, the tip end 8 of the pipeline 10 is bottomed out by a winch or the like (not shown) installed on the opposite shore and moved toward the opposite shore. Note that the distal end portion 8 is closed in advance to prevent foreign matter from entering.

【0014】前記工程を全てのパイプの接合が終了(ス
テップ6)するまで繰り返して、接合した所定数のパイ
プの列からなるパイプライン10を川底に敷設する。以
上のように本実施例では、パイプライン10の基端部4
と新たなパイプ5とを接合するために必要とする作業面
積は、パイプの長さや管径等に関係なくパイプを支持す
るパイプ支持台1とパイプを吊り上げるクレーン6を設
置するだけの面積があれば良く、パイプラインの長さに
応じた広大な占有面積を必要としない。
The above process is repeated until all the pipes are joined (step 6), and a pipeline 10 consisting of a predetermined number of rows of joined pipes is laid on the riverbed. As described above, in this embodiment, the base end 4 of the pipeline 10
The work area required to join the new pipe 5 to the new pipe 5 should be large enough to install the pipe support stand 1 that supports the pipe and the crane 6 that lifts the pipe, regardless of the length or diameter of the pipe. It does not require a large area to occupy depending on the length of the pipeline.

【0015】また、パイプを接合するための溶接施工も
、溶接部位が全て水平方向を向くことにより水平姿勢で
の溶接施工だけで済むためにその溶接が容易になり、前
記溶接のための技量も短い時間で容易に修得できる。 なお、前記実施例ではパイプを支持するパイプ支持台1
を、一方の岸7側の陸地部分に設置しているが、川底の
地盤が強固であれば、岸7側の川辺部分に設置してもよ
い。また、パイプ支持台1はパイプライン10の基端部
4と新たなパイプ5とを上下に支持する一手段を示した
もので、他の公知の手段を使用してもよい。
[0015] Also, welding for joining pipes is easier because all welding parts are oriented horizontally, so welding only needs to be carried out in a horizontal position, and the welding technique is also reduced. It can be easily learned in a short period of time. In addition, in the above embodiment, the pipe support stand 1 that supports the pipe is
is installed on the land area on one bank 7 side, but it may be installed on the riverside area on the bank 7 side if the river bottom is strong. Further, the pipe support stand 1 shows one means for vertically supporting the base end portion 4 of the pipeline 10 and the new pipe 5, and other known means may be used.

【0016】さらに、前記実施例では、新たなパイプ5
の揺動を防止するために補助スタンド9を用いたが、溶
接時にパイプ5下端がパイプ4上端に対して移動するこ
とを防止できれば他の手段を採用することもできるし、
さらに、クレーン6はポスト2の上端に設置するタワー
クレーンであってもよい。
Furthermore, in the above embodiment, a new pipe 5
Although the auxiliary stand 9 was used to prevent the pipe from swinging, other means may be used as long as the lower end of the pipe 5 can be prevented from moving relative to the upper end of the pipe 4 during welding.
Furthermore, the crane 6 may be a tower crane installed at the upper end of the post 2.

【0017】[0017]

【発明の効果】以上説明してきたように、本発明のパイ
プラインの敷設方法は、パイプラインの基端部と新たな
パイプを接合する作業に要する占有面積がパイプライン
の長さや管径等に関係なく、前記基端部と新たなパイプ
を上下に支持する装置を設置する面積だけの少ない占有
面積で済み、さらに、前記接合のための溶接施工が水平
姿勢での溶接だけで済むために該溶接施工が容易になる
という効果がある。
[Effects of the Invention] As explained above, in the pipeline laying method of the present invention, the area required for joining the base end of the pipeline to a new pipe depends on the length of the pipeline, the pipe diameter, etc. Regardless, it occupies only a small area for installing the device that supports the base end and the new pipe vertically, and furthermore, the welding for the connection only requires welding in a horizontal position. This has the effect of making welding work easier.

【図面の簡単な説明】[Brief explanation of the drawing]

【図1】本実施例のパイプラインの敷設方法を示す側面
図である。
FIG. 1 is a side view showing the pipeline installation method of this embodiment.

【図2】パイプラインの基端部と新たなパイプとの接合
を示す側面断面図である。
FIG. 2 is a side cross-sectional view showing the connection between the base end of the pipeline and a new pipe.

【図3】本実施例のパイプラインの敷設方法の流れを示
す流れ図である。
FIG. 3 is a flowchart showing the flow of the pipeline installation method of this embodiment.

【符号の説明】[Explanation of symbols]

1    パイプ支持台 4    パイプラインの基端部 5    新たなパイプ 8    パイプラインの先端部 10  パイプライン 11  溶接装置 1 Pipe support stand 4 Base end of pipeline 5. New pipe 8. Tip of the pipeline 10 Pipeline 11 Welding equipment

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】  パイプラインの基端部に新たなパイプ
を継ぎ足すとともに、パイプラインの先端部を所定位置
に向けて引き延ばすパイプライン敷設方法において、パ
イプラインの基端部を上に向けて支持するとともに、前
記基端部の上端に、軸を上下に向けた新たなパイプの下
端を溶接して接合することを特徴とするパイプラインの
敷設方法。
Claim 1: In a pipeline laying method in which a new pipe is added to the base end of the pipeline and the distal end of the pipeline is stretched toward a predetermined position, the base end of the pipeline is supported with the base end facing upward. At the same time, a method for laying a pipeline, characterized in that the lower end of a new pipe with its axis facing up and down is joined to the upper end of the base end by welding.
JP2409078A 1990-12-28 1990-12-28 Pipeline laying method Pending JPH04231785A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2409078A JPH04231785A (en) 1990-12-28 1990-12-28 Pipeline laying method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2409078A JPH04231785A (en) 1990-12-28 1990-12-28 Pipeline laying method

Publications (1)

Publication Number Publication Date
JPH04231785A true JPH04231785A (en) 1992-08-20

Family

ID=18518454

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2409078A Pending JPH04231785A (en) 1990-12-28 1990-12-28 Pipeline laying method

Country Status (1)

Country Link
JP (1) JPH04231785A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101358145B1 (en) * 2012-02-22 2014-02-10 삼성중공업 주식회사 Pipe laying system and pipe laying ship having the same
KR101497453B1 (en) * 2013-03-06 2015-03-02 삼성중공업 주식회사 Structure used for pipe laying in subsea
WO2018002964A1 (en) * 2016-06-27 2018-01-04 川崎重工業株式会社 Pipeline welding system, pipe managing device, and pipe-shape measuring device

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101358145B1 (en) * 2012-02-22 2014-02-10 삼성중공업 주식회사 Pipe laying system and pipe laying ship having the same
KR101497453B1 (en) * 2013-03-06 2015-03-02 삼성중공업 주식회사 Structure used for pipe laying in subsea
WO2018002964A1 (en) * 2016-06-27 2018-01-04 川崎重工業株式会社 Pipeline welding system, pipe managing device, and pipe-shape measuring device

Similar Documents

Publication Publication Date Title
JPH04231785A (en) Pipeline laying method
CN103243928B (en) Inclined in two-way V-type column construction method
JP5252228B2 (en) Hoisting device for dredging piping construction and dredging piping construction method using the same
CN112663583A (en) Construction method for total assembly and closure of pile stabilizing platform
CN208328884U (en) A kind of auxiliary locator built for offshore platform
CN113800411A (en) Method for hoisting FPSO torch tower by using floating crane
CN111395397B (en) Construction method of bending type immersed tube anti-deformation structure
CN211395632U (en) Jacket positioning device and jacket
CN108930260A (en) The installation method of jack-up unit spud leg
JPS5948239B2 (en) Jacking device
JPS5832520A (en) Manufacture of cylindrical sheel having thin wall and large diameter and device thereof
CN217150316U (en) Island type guiding high-precision lowering construction structure in special-shaped bottomless double-wall steel cofferdam
CN209704041U (en) Large-span truss segmental hoisting high-altitude closes up bracket die
JP5458378B2 (en) Connection jig for pipe welding
CN218712914U (en) Dig a steel reinforcement cage soon and hang and put hole guider
CN108591615B (en) Pipeline rotating compensator installation structure on large-area water area and construction method thereof
CN212986274U (en) Municipal administration water supply pipeline special stand
CN207775916U (en) The steel wall assembly moulding bed of steel wall root key combination stake
CN115012678A (en) Space positioning and mounting method for cantilever steel column of spherical steel structure
CN210684703U (en) Adjusting device and pile equipment for pile
CN108914717B (en) Method for in-situ overhead installation of auxiliary support by using reinforcing steel bars of integral ballast bed
CN211596728U (en) Complicated karst area ground treatment structure
JP3941200B2 (en) Installation method of pump barrel piping
JP2001049663A (en) Steel pipe holder for driving steel pipe pile
JPS5829915A (en) Constructing method for ocean structure