JPH042145B2 - - Google Patents

Info

Publication number
JPH042145B2
JPH042145B2 JP60241048A JP24104885A JPH042145B2 JP H042145 B2 JPH042145 B2 JP H042145B2 JP 60241048 A JP60241048 A JP 60241048A JP 24104885 A JP24104885 A JP 24104885A JP H042145 B2 JPH042145 B2 JP H042145B2
Authority
JP
Japan
Prior art keywords
steel pipe
steel
pipe
guide
pipes
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP60241048A
Other languages
Japanese (ja)
Other versions
JPS62101736A (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP24104885A priority Critical patent/JPS62101736A/en
Publication of JPS62101736A publication Critical patent/JPS62101736A/en
Publication of JPH042145B2 publication Critical patent/JPH042145B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Mutual Connection Of Rods And Tubes (AREA)
  • Joining Of Building Structures In Genera (AREA)
  • Standing Axle, Rod, Or Tube Structures Coupled By Welding, Adhesion, Or Deposition (AREA)

Description

【発明の詳細な説明】 「産業上の利用分野」 この発明は充填鋼管コンクリート構造物の施工
方法に関するものである。
DETAILED DESCRIPTION OF THE INVENTION "Field of Industrial Application" This invention relates to a method of constructing a filled steel pipe concrete structure.

「従来の技術」 建築物の柱の構造として、鋼管の内部にコンク
リートを充填する充填鋼管コンクリート柱が知ら
れている。これは、柱にかかる鉛直荷重を主とし
て鋼管内のコンクリートに負担させ、鋼管はその
コンクリートを外側から締め付けてコンクリート
の圧縮耐力を増大させる(いわゆるコンフアイン
ド効果)ように作用するものである。
"Prior Art" A filled steel pipe concrete column, in which the inside of a steel pipe is filled with concrete, is known as a column structure for a building. This is because the vertical load on the column is mainly borne by the concrete inside the steel pipe, and the steel pipe tightens the concrete from the outside to increase the compressive strength of the concrete (the so-called confining effect).

この構造の柱は、第5図に示すように、複数階
(一般には3階程度)にわたる長さの鋼管aを順
次溶接等により接合して立設し、その後鋼管a内
にコンクリートを充填することにより構築され
る。そして、それらの鋼管aには予め梁の端部と
なる鉄骨bを所定の位置に取り付けておき、鋼管
aを立設した後、これに梁cを接合するようにす
ることが一般的である。
As shown in Figure 5, the columns of this structure are erected by sequentially joining steel pipes a that span multiple floors (generally about three floors) by welding, etc., and then filling the steel pipes a with concrete. It is constructed by Generally, a steel frame b, which will become the end of the beam, is attached to the steel pipe a at a predetermined position in advance, and after the steel pipe a is erected, the beam c is connected to it. .

ところで、このような柱を構築するに際して
は、先に立設された鋼管aの上方から他の鋼管a
をクレーン等を用いて徐々に降ろしていき、それ
らの端部同士を突き合わせた後、溶接により接合
して順次上方に延ばしていくのであるが、この鋼
管a同士を突き合わせるに際しては、両鋼管aに
それぞれ接合させる梁cの延びる方向を合わせる
必要があることから、正確な位置決めを行わねば
ならない。このため、従来、鋼管a同士の接合は
次のようになされている。すなわち、第6図およ
び第7図に示すように、鋼管aのそれぞれの端部
外面の所定箇所に、予め仮止め用のプレートdを
溶接して取り付けておき、これらのプレートd同
士を突き合わせることにより、鋼管aの位置決め
がなされるようにしておく。そして、プレートd
同士を突き合わせた後、これを添え板eにより挟
持してボルトfによつて固定した後、鋼管aの突
き合わせ部を溶接する。このようにすることによ
り、両鋼管aの位置決めを正確に行うことがで
き、また、溶接に先立つて鋼管a同士が固定(仮
止め)されるので、溶接作業が容易となる。
By the way, when constructing such a pillar, it is necessary to connect another steel pipe a from above the previously erected steel pipe a.
are gradually lowered using a crane, etc., and after their ends are butted together, they are joined by welding and extended upward one by one. Since it is necessary to align the extending directions of the beams c to be joined to the respective parts, accurate positioning must be performed. For this reason, conventionally, the steel pipes a are joined together as follows. That is, as shown in FIGS. 6 and 7, temporary fixing plates d are welded and attached to predetermined locations on the outer surface of each end of the steel pipe a, and these plates d are butted together. By doing so, the position of the steel pipe a can be determined. And plate d
After abutting them together, they are clamped by splints e and fixed with bolts f, and then the abutting portions of the steel pipes a are welded. By doing so, both steel pipes a can be accurately positioned, and the steel pipes a are fixed (temporarily fixed) to each other prior to welding, making the welding work easier.

「発明が解決しようとする問題点」 ところが、上記のようにして鋼管aを接合する
ことは、鋼管aに予めプレートdを取り付ける手
間や、添え板eを当ててボルト締めを行うという
作業を要するばかりでなく、鋼管同士を溶接した
後にはそのプレートdを溶断して取り除き、その
溶断部を研磨して平滑にするという作業をも要
し、接合作業が面倒であるとともに時間がかか
り、能率が良くないという問題があつた。
"Problem to be Solved by the Invention" However, joining the steel pipes a as described above requires the work of attaching the plate d to the steel pipe a in advance and applying the splint e and tightening the bolts. In addition, after welding steel pipes together, it is necessary to remove the plate d by fusing and polishing the welded part to make it smooth, which makes the joining process troublesome, time-consuming, and reduces efficiency. The problem was that it wasn't good.

この発明は上記の事情に鑑みてなされたもの
で、両鋼管の位置決めを正確に行うことのできる
とともに、接合作業の簡略化を図ることのできる
充填鋼管コンクリート構造物の施工方法を提供す
ることを目的とする。
This invention was made in view of the above circumstances, and aims to provide a construction method for a filled steel pipe concrete structure that can accurately position both steel pipes and simplify the joining work. purpose.

「問題点を解決するための手段」 この発明は、一方の鋼管の端部に、その鋼管の
径方向外側に突出する少なくとも一つの突起を設
け、他方の鋼管の端部には、上記一方の鋼管の端
部外側に嵌まり合うガイド管を取り付け、そのガ
イド管には、所定の位置に上記突起に係合する溝
を形成して鋼管柱を製作し、これら鋼管柱の端部
同士を突き合わせて継合した後に、上記鋼管に取
り付けられた鉄骨に梁を接合して建方を行い、し
かる後、鋼管柱内にコンクリートを打設すること
を特徴としている。
"Means for Solving the Problems" This invention provides at least one protrusion protruding outward in the radial direction of the steel pipe at the end of one steel pipe, and at least one protrusion protruding outward in the radial direction of the steel pipe. A guide tube that fits on the outside of the end of the steel pipe is attached, a groove is formed in the guide tube at a predetermined position to engage with the protrusion, a steel pipe column is manufactured, and the ends of these steel pipe columns are butted together. After the above-mentioned steel pipes are joined together, beams are joined to the steel frame attached to the steel pipes for erection, and then concrete is poured into the steel pipe columns.

「実施例」 以下、この発明の実施例について第1図ないし
第4図を参照して説明する。
"Embodiments" Hereinafter, embodiments of the present invention will be described with reference to FIGS. 1 to 4.

まず、第1図ないし第3図を参照して第1実施
例を説明する。これらの図は、充填鋼管コンクリ
ート柱Aの接合部を表すもので、第1図は接合さ
れる両鋼管の端部の形状を示す斜視図、第2図は
両鋼管が接合された状態を示す立面図、第3図は
その立断面図である。
First, a first embodiment will be described with reference to FIGS. 1 to 3. These figures show the joint of filled steel pipe concrete column A. Figure 1 is a perspective view showing the shape of the ends of both steel pipes to be joined, and Figure 2 shows the state in which both steel pipes are joined. Elevation view, FIG. 3 is an elevational sectional view thereof.

図中符号1は既に立設された鋼管、2はその鋼
管1の上端に接合される鋼管である。鋼管2の下
端部外面には、この鋼管2の径方向外側に突出す
る突起3が設けられている。また、鋼管1の上端
部にはガイド管4が取り付けられている。ガイド
管4は、その内径寸法が鋼管1,2の外径寸法と
ほぼ等しくされており、その下部内面を鋼管1の
外面に密着させ、上部を鋼管1の上端より上方に
突出させて、溶接等により鋼管1に固定されてお
り、その上部に、鋼管2の下端部が嵌まり合うこ
とができるものである。このガイド管4には、ガ
イド管4の側面を切り欠くことにより、鋼管2に
設けられている上記突起3に係合し得る溝5が、
ガイド管4の軸線方向(すなわち鋼管1,2の軸
線方向)に沿つて形成されている。上記の突起3
および溝5は、これらが係合した時に両鋼管1,
2が適正な向きで突き合わされるような位置に形
成されている。
In the figure, reference numeral 1 indicates a steel pipe that has already been erected, and reference numeral 2 indicates a steel pipe that is joined to the upper end of the steel pipe 1. A protrusion 3 that projects outward in the radial direction of the steel pipe 2 is provided on the outer surface of the lower end portion of the steel pipe 2 . Further, a guide pipe 4 is attached to the upper end of the steel pipe 1. The guide tube 4 has an inner diameter approximately equal to the outer diameter of the steel tubes 1 and 2, and has its lower inner surface in close contact with the outer surface of the steel tube 1, and its upper portion protrudes above the upper end of the steel tube 1, and is welded. etc., and the lower end of the steel pipe 2 can fit into the upper part thereof. This guide tube 4 has a groove 5 which can be engaged with the projection 3 provided on the steel tube 2 by cutting out the side surface of the guide tube 4.
It is formed along the axial direction of the guide tube 4 (that is, the axial direction of the steel pipes 1 and 2). Protrusion 3 above
and groove 5, when these are engaged, both steel pipes 1,
2 are formed in such a position that they abut against each other in the proper direction.

以上のように構成された鋼管1,2を接合する
手順について説明すると、クレーン等を用いて鋼
管2を鋼管1の上方に吊り上げ、両鋼管1,2の
軸線を合わせるとともに、鋼管2の突起3の位置
を鋼管1に固定されているガイド管4の溝5の位
置に合わせて(第1図に示す状態)、鋼管2を
徐々に降下させる。そして、鋼管2の下端をガイ
ド管4内に挿入し、突起3と溝5を係合させて、
鋼管1,2が突き合わされるまで降下させる。こ
れにより、鋼管2はガイド管4に支えられて鋼管
1上に立設される。
To explain the procedure for joining the steel pipes 1 and 2 configured as above, use a crane or the like to lift the steel pipe 2 above the steel pipe 1, align the axes of both the steel pipes 1 and 2, and connect the protrusion 3 of the steel pipe 2. The steel pipe 2 is gradually lowered by aligning the position with the groove 5 of the guide pipe 4 fixed to the steel pipe 1 (the state shown in FIG. 1). Then, insert the lower end of the steel pipe 2 into the guide pipe 4, engage the protrusion 3 and the groove 5,
Lower the steel pipes 1 and 2 until they butt each other. Thereby, the steel pipe 2 is supported by the guide pipe 4 and is erected on the steel pipe 1.

このとき、鋼管2に取り付けられた鉄骨(図示
略)は所定の方向を向くように鋼管2の周方向に
おける位置決めがされるとともに、軸方向の位置
決めがされる。
At this time, the steel frame (not shown) attached to the steel pipe 2 is positioned in the circumferential direction of the steel pipe 2 so as to face a predetermined direction, and also in the axial direction.

その後、ガイド管4の上端内周縁と鋼管2外面
とを溶接し、さらに、上記位置決めがされた鉄骨
に梁を接合して建方を行ない、しかる後に、鋼管
1,2内部にコンクリートを充填すれば、充填鋼
管コンクリート柱Aが構築される。
After that, the inner peripheral edge of the upper end of the guide pipe 4 and the outer surface of the steel pipe 2 are welded, and the beam is joined to the steel frame positioned above for erection. After that, the inside of the steel pipes 1 and 2 is filled with concrete. For example, a filled steel pipe concrete column A is constructed.

このように、この第1実施例の接合構造によれ
ば、突起3と溝5とを係合させることのみで、鋼
管2の位置決めすなわち、鋼管2に取り付けられ
た鉄骨の鋼管2の周方向および軸方向における位
置決めを正確に行うことができる。また、鋼管2
はガイド管4により支えられるから、従来のよう
に仮止め用の治具を用いることなく、したがつ
て、その治具を後で取り除くという手間も省くこ
とができ、作業が簡略化される。さらに、このガ
イド管4によつて鋼管1,2の接合部におけるコ
ンフアインド効果が高められるという効果も奏す
る。
As described above, according to the joining structure of the first embodiment, the positioning of the steel pipe 2 can be determined simply by engaging the protrusion 3 and the groove 5, that is, the positioning of the steel pipe 2 in the circumferential direction and direction of the steel pipe 2 of the steel frame attached to the steel pipe 2. Positioning in the axial direction can be performed accurately. Also, steel pipe 2
Since it is supported by the guide tube 4, there is no need to use a temporary fixing jig as in the conventional case, and therefore, the trouble of removing the jig later can be omitted, simplifying the work. Furthermore, the guide tube 4 also has the effect of enhancing the confining effect at the joint between the steel pipes 1 and 2.

なお、この柱Aに曲げ耐力を負担させない場合
等には、必ずしもガイド管4と鋼管2とを溶接す
ることはなく、単にガイド管4内に鋼管2を挿入
した状態のままで良い。また、鋼管1,2とコン
クリートとの間にそれらの付着を防ぐアンボンド
処理層を設けたり、鋼管1,2の軸方向の変形
(縮み)を吸収して軸応力が生じないようにする
ために、鋼管1,2の所定箇所に変形吸収部を形
成したりすることは任意である。
In addition, when the bending strength is not to be imposed on the column A, the guide pipe 4 and the steel pipe 2 are not necessarily welded, and the steel pipe 2 may simply be inserted into the guide pipe 4 as it is. In addition, an unbonding treatment layer is provided between the steel pipes 1 and 2 and concrete to prevent them from adhering, and the axial deformation (shrinkage) of the steel pipes 1 and 2 is absorbed to prevent axial stress from occurring. It is optional to form deformation absorbing portions at predetermined locations of the steel pipes 1 and 2.

次に、第4図を参照して第2実施例を説明す
る。この第2実施例では、ガイド管4の上端内周
部に、上方に向つて内径が漸次大きくなるように
拡径部6が形成されている。また、溝5の上部に
は、上方に向つてその幅が漸次広がるように拡幅
部7が形成されている。
Next, a second embodiment will be described with reference to FIG. In this second embodiment, an enlarged diameter portion 6 is formed at the inner peripheral portion of the upper end of the guide tube 4 so that the inner diameter thereof gradually increases upward. Furthermore, a widened portion 7 is formed in the upper part of the groove 5 so that the width thereof gradually increases upward.

この第2実施例では、鋼管2を鋼管1の上方か
ら降下させる際に、鋼管2の軸線が鋼管1の軸線
と若干ずれていたとしても、鋼管2はガイド管4
の拡径部6に案内されて容易にガイド部4内に導
かれる。また、鋼管2の突起3の位置がガイド管
4の溝5の位置と若干ずれて(すなわち、鋼管
1,2の向きが若干ずれている)いたとしても、
突起3が溝5の拡幅部7に案内されて、自ずと溝
5に係合できる(すなわち両鋼管の向きが合わさ
れる)から、鋼管1,2の突き合わせがさらに容
易となる。
In this second embodiment, when the steel pipe 2 is lowered from above the steel pipe 1, even if the axis of the steel pipe 2 is slightly deviated from the axis of the steel pipe 1, the steel pipe 2 is lowered into the guide pipe 1.
is easily guided into the guide part 4 by the enlarged diameter part 6 of the guide part 4. Furthermore, even if the position of the protrusion 3 of the steel pipe 2 is slightly shifted from the position of the groove 5 of the guide pipe 4 (that is, the orientation of the steel pipes 1 and 2 is slightly shifted),
Since the protrusion 3 is guided by the widened portion 7 of the groove 5 and can automatically engage with the groove 5 (that is, the directions of both steel pipes are matched), it becomes easier to butt the steel pipes 1 and 2 together.

なお、上記実施例ではいずれも突起3および溝
5を一組のみ設けたが、これは複数組設けるよう
にしても良い。また、突起3を下側の鋼管1に設
け、ガイド管4を上側の鋼管2に取り付けるよう
にしても良い。
In each of the above embodiments, only one set of protrusions 3 and grooves 5 is provided, but a plurality of sets may be provided. Alternatively, the projection 3 may be provided on the lower steel pipe 1 and the guide pipe 4 may be attached to the upper steel pipe 2.

「発明の効果」 以上詳細に説明したように、この発明によれ
ば、充填鋼管コンクリート構造物を施工するにあ
たり、鋼管同士を突き合わせるに際して一方の鋼
管に設けられた突起を、他方の鋼管に取り付けら
れたガイド管に形成された溝に係合させるだけで
鋼管に取り付けられた鉄骨の鋼管の周方向および
軸方向における位置決めが同時になされて、鉄骨
が所定の方向を向くとともに所定の高さに位置す
るので、鉄骨に梁を接合する建方を容易かつ正確
に行なうことができる。また、仮止め用の治具等
を用いることがないので、接合作業の簡略化を図
ることができるという効果を奏する。
"Effects of the Invention" As explained in detail above, according to the present invention, when constructing a filled steel pipe concrete structure, when the steel pipes are butted together, the protrusion provided on one steel pipe is attached to the other steel pipe. By simply engaging the groove formed in the guide tube, the steel frame attached to the steel pipe can be positioned simultaneously in the circumferential and axial directions, so that the steel frame faces the specified direction and is positioned at a specified height. This makes it possible to easily and accurately connect beams to steel frames. Furthermore, since no temporary fixing jig or the like is required, the joining work can be simplified.

【図面の簡単な説明】[Brief explanation of drawings]

第1図ないし第4図は、この発明の実施例を示
す図である。第1図ないし第3図は第1実施例を
示し、第1図は鋼管柱の接合部の斜視図、第2図
は接合された鋼管柱の立面図、第3図は第2図
−線視断面図である。第4図は第2実施例を示
す斜視図である。第5図は鋼管柱の構築手順を説
明するための立面図である。第6図および第7図
は従来の鋼管柱の接合構造を示し、第6図は平断
面図、第7図は立面図である。 A……充填鋼管コンクリート柱(鋼管柱)、1,
2……鋼管、3……突起、4……ガイド管、5…
…溝。
1 to 4 are diagrams showing embodiments of the present invention. Figures 1 to 3 show the first embodiment, where Figure 1 is a perspective view of the joint of steel pipe columns, Figure 2 is an elevation view of the joined steel pipe columns, and Figure 3 is Figure 2- FIG. FIG. 4 is a perspective view showing the second embodiment. FIG. 5 is an elevational view for explaining the construction procedure of the steel pipe column. FIGS. 6 and 7 show a conventional joint structure of steel pipe columns, with FIG. 6 being a plan sectional view and FIG. 7 being an elevational view. A...Filled steel pipe concrete column (steel pipe column), 1,
2...Steel pipe, 3...Protrusion, 4...Guide tube, 5...
…groove.

Claims (1)

【特許請求の範囲】[Claims] 1 一方の鋼管の端部に、その鋼管の径方向外側
に突出する少なくとも一つの突起を設け、他方の
鋼管の端部には、上記一方の鋼管の端部外側に嵌
まり合うガイド管を取り付け、そのガイド管に
は、所定の位置に上記突起に係合する溝を形成し
て鋼管柱を製作し、これら鋼管柱の端部同士を突
き合わせて継合した後に、上記鋼管に取り付けら
れた鉄骨に梁を接合して建方を行い、しかる後、
鋼管柱内にコンクリートを打設することを特徴と
する充填鋼管コンクリート構造物の施工方法。
1 At least one protrusion protruding outward in the radial direction of the steel pipe is provided at the end of one steel pipe, and a guide pipe that fits on the outside of the end of the one steel pipe is attached to the end of the other steel pipe. In the guide pipe, grooves that engage with the projections are formed at predetermined positions to create steel pipe columns, and after the ends of these steel pipe columns are butted together and joined, a steel frame attached to the steel pipe is formed. After joining the beams and constructing the building,
A construction method for a filled steel pipe concrete structure characterized by pouring concrete into steel pipe columns.
JP24104885A 1985-10-28 1985-10-28 Connection structure of steel pipe pillar Granted JPS62101736A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP24104885A JPS62101736A (en) 1985-10-28 1985-10-28 Connection structure of steel pipe pillar

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP24104885A JPS62101736A (en) 1985-10-28 1985-10-28 Connection structure of steel pipe pillar

Publications (2)

Publication Number Publication Date
JPS62101736A JPS62101736A (en) 1987-05-12
JPH042145B2 true JPH042145B2 (en) 1992-01-16

Family

ID=17068532

Family Applications (1)

Application Number Title Priority Date Filing Date
JP24104885A Granted JPS62101736A (en) 1985-10-28 1985-10-28 Connection structure of steel pipe pillar

Country Status (1)

Country Link
JP (1) JPS62101736A (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01142146A (en) * 1987-11-27 1989-06-05 Takenaka Komuten Co Ltd Connecting structure of molded steel pipe concrete post
JP2008164108A (en) * 2006-12-28 2008-07-17 Mitsubishi Electric Corp Piping connection mechanism
US8920200B2 (en) * 2009-10-27 2014-12-30 Atlantis Resources Corporation Pte Connector for mounting an underwater power generator
AU2012253228B2 (en) 2011-05-10 2013-07-11 Atlantis Resources Corporation Pte Limited Deployment apparatus and method of deploying an underwater power generator
JP6452972B2 (en) * 2014-07-09 2019-01-16 ユニプレス株式会社 Steering member

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4426357Y1 (en) * 1965-10-22 1969-11-05

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS51146806U (en) * 1975-05-20 1976-11-25

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4426357Y1 (en) * 1965-10-22 1969-11-05

Also Published As

Publication number Publication date
JPS62101736A (en) 1987-05-12

Similar Documents

Publication Publication Date Title
JPS62101735A (en) Connection structure of steel pipe pillar
JPH042145B2 (en)
JP3759665B2 (en) Corner joints between reinforcing bars or steel reinforced concrete structures and various columnar structures and joining methods thereof
JPH08144383A (en) Joint for building and construction structure and method for constructing joint
JPH0568585B2 (en)
JPH06316985A (en) Reinforced steel pipe concrete column
JP2003213796A (en) Joint method and joint structure of square steel pipe members
JPH08151648A (en) Joint structure for column beam of steel structure
JPS6366966B2 (en)
JPH02217544A (en) Constructing method for centrifugal forming steel bar reinforced concrete
JPH02225738A (en) Column/beam connection structure
JP2600194B2 (en) Lap joint of column main bar
JPH05214769A (en) Connecting structure of column and beam
JPH0598704A (en) Column beam joint structure
JPS6127365Y2 (en)
JPH0438040Y2 (en)
JP2022089295A (en) Joining method of steel column beam
JPH0426382B2 (en)
JPH02248558A (en) Centrifugal molding steel rod reinforced concrete
JPH04353149A (en) Precast reinforced concrete beam and its jointment
JPH04198536A (en) Jointing construction of beam member and column member, and joint member to be used for its construction
JPH03297557A (en) Field welding and connecting method for square steel tube pillars by thick plate assembly
JP3688052B2 (en) Construction method for underground beam formwork and foundation formwork
JPH07173883A (en) Metallic connector
JP2677159B2 (en) Structure using covered steel tube concrete columns