JPH04122581U - sling - Google Patents

sling

Info

Publication number
JPH04122581U
JPH04122581U JP3665191U JP3665191U JPH04122581U JP H04122581 U JPH04122581 U JP H04122581U JP 3665191 U JP3665191 U JP 3665191U JP 3665191 U JP3665191 U JP 3665191U JP H04122581 U JPH04122581 U JP H04122581U
Authority
JP
Japan
Prior art keywords
lifted
hanging
linear member
hanging tool
insertion hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP3665191U
Other languages
Japanese (ja)
Inventor
善雅 宮崎
修次 大芦
Original Assignee
ミサワホーム株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ミサワホーム株式会社 filed Critical ミサワホーム株式会社
Priority to JP3665191U priority Critical patent/JPH04122581U/en
Publication of JPH04122581U publication Critical patent/JPH04122581U/en
Withdrawn legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Load-Engaging Elements For Cranes (AREA)

Abstract

(57)【要約】 【目的】 被吊り上げ物を吊り上げた後に、容易に外す
ことができる吊り具を提供すること。 【構成】 被吊り上げ物3を掛止する掛止具1と、この
掛止具1に繋がれたロープ2とからなる。そして、ロー
プ2の途中には、リング部13が設けられている。一
方、掛止具1には、ロープ2を挿通する挿通孔11a
と、ロープ2のリング部13を掛ける突出部12が設け
られている。そして、掛止具1の挿通孔11aにロープ
2を挿通させ、かつリング部13を突出部に掛けた状態
で、被吊り上げ物3を吊り上げるようになっている。こ
の状態で、被吊り上げ物3を設置した後に、ロープ2の
下端を引くと、突出部12からリング部13が外れ、掛
止具1が下方に下がり、被吊り上げ物3から掛止具1が
外れるようになっている。
(57) [Summary] [Purpose] To provide a lifting device that can be easily removed after lifting an object to be lifted. [Structure] Consists of a hanging tool 1 for hanging an object 3 to be lifted, and a rope 2 connected to the hanging tool 1. A ring portion 13 is provided in the middle of the rope 2. On the other hand, the hanging tool 1 has an insertion hole 11a through which the rope 2 is inserted.
A protrusion 12 on which a ring portion 13 of the rope 2 is hung is provided. Then, the rope 2 is inserted through the insertion hole 11a of the hanging device 1, and the object 3 to be lifted is lifted up with the ring portion 13 hung on the protrusion. In this state, when the lower end of the rope 2 is pulled after installing the object 3 to be lifted, the ring part 13 comes off from the protrusion 12, the hanging tool 1 is lowered, and the hanging tool 1 is removed from the object 3 to be lifted. It is designed to come off.

Description

【考案の詳細な説明】[Detailed explanation of the idea]

【0001】0001

【産業上の利用分野】[Industrial application field]

本考案は、被吊り上げ物、特にB梁などを吊り上げる際に使用される吊り具に 関し、設置後に容易にB梁から取り外すことが可能な吊り具に関するものである 。 This invention is suitable for lifting equipment used when lifting objects to be lifted, especially B-beams, etc. This relates to a hanging device that can be easily removed from the B beam after installation. .

【0002】0002

【従来の技術】[Conventional technology]

従来より一般に、工場から運ばれたB梁などの部材を、トラックより荷卸して 所定位置に設置する際には、現場で作業員がB梁の両端部にワイヤーやアントク ランプやスリングベルト等を掛けた後、これをクレーンにより玉掛け、吊り上げ るという方法が採用されている。そして、B梁を所定位置に設置した後には、該 B梁から前記ワイヤーやアントクランプやスリングベルト等を外すという作業が 行なわれる。 Conventionally, parts such as B-beams transported from factories are unloaded from trucks. When installing it in the specified position, workers on site should attach wires or anchors to both ends of the B beam. After hanging lamps, sling belts, etc., it is slung and lifted by a crane. The method is adopted. After installing the B beam in the specified position, The work of removing the wires, ant clamps, sling belts, etc. from the B beam is It is done.

【0003】0003

【考案が解決しようとする課題】[Problem that the idea aims to solve]

しかしながら、B梁からワイヤーを外す作業は、必然的に建物の小屋組み部分 等の高所において行わなくてはならなず、熟練した作業員がこの小屋組み部分の 上に乗ってこの作業を行うことが通常であり、このようにB梁からワイヤーを外 す作業は、作業性の悪いものである。 However, the work of removing the wire from the B-beam necessarily involves the roof frame of the building. The work must be carried out at a high place such as It is normal to perform this work by climbing on top of the This work is difficult to work with.

【0004】 本考案は、このような事情に鑑みてなされたものであって、被吊り上げ物、特 にB梁などを吊り上げて設置した後に容易にB梁から取り外すことが可能な吊り 具を提供することを目的としている。0004 The present invention was developed in view of these circumstances, and it A suspension that can be easily removed from the B beam after it has been lifted and installed. The purpose is to provide tools.

【0005】[0005]

【課題を解決するための手段】[Means to solve the problem]

本考案に係る吊り具は、被吊り上げ物を掛止する掛止具と、該掛止具に繋がれ て前記被吊り上げ物を吊り上げるための線状部材とを具備してなり、前記掛止具 は、被吊り上げ物の底面に当接される底面支持部と、該底面支持部の両端部から それぞれ上方に延出され、かつ前記被吊り上げ物の両側面を支持する側面支持部 と、一方の側面支持部上端から上方に延出された延出部と、前記底面支持部底面 より下方に突出する突出部とを具備してなり、前記延出部の上端部には、前記線 状部材を挿通するための挿通孔が設けられ、前記線状部材は、その途中に環状の リング部が設けられ、前記延出部の挿通孔に前記リング部が該挿通孔より下方に くるように挿通され、前記リング部が前記掛止具の突出部に着脱自在に掛止され ていることことを特徴とするものである。 The hanging device according to the present invention includes a hanging device for hanging an object to be lifted, and a hanging device that is connected to the hanging device. and a linear member for hoisting the object to be lifted, the hanging tool is from the bottom support part that comes into contact with the bottom of the object to be lifted, and from both ends of the bottom support part. side support parts each extending upward and supporting both sides of the object to be lifted; an extending portion extending upward from the upper end of one side support portion; and a bottom surface of the bottom support portion. and a protruding part that protrudes further downward, and the upper end of the extending part is provided with the line. An insertion hole is provided for inserting the linear member, and the linear member has an annular hole in the middle thereof. A ring portion is provided in the insertion hole of the extension portion, and the ring portion is located below the insertion hole. the ring portion is removably latched onto the protruding portion of the latching tool. It is characterized by the fact that

【0006】[0006]

【作用】[Effect]

本考案の吊り具によれば、掛止具の側面支持部同士の間に、B梁等の被吊り上 げ物を挟み込むようにして底面支持部上に載置する。この際には、線状部材を延 出部の挿通孔より下に引き出しておき、邪魔にならにようにしておく。もしくは 、被吊り上げ物の端部側から掛止具を取付けるようにする。 According to the hanging device of the present invention, between the side support parts of the hanging device, there is a Place the product on the bottom support part so that it is sandwiched between the objects. At this time, extend the linear member. Pull it out below the insertion hole of the exit part and keep it out of the way. or , Attach the hanging device from the end of the object to be lifted.

【0007】 次に線状部材を引き上げる。この際に線状部材は、延出部が設けられた一方の 側面支持部が支持する被吊り上げ物の側面の反対側の側面側にまわしておく。そ して、被吊り上げ物を設置位置に載置もしくは設置する。[0007] Next, pull up the linear member. At this time, the linear member is attached to one side where the extending portion is provided. Turn it to the side opposite to the side of the object to be lifted supported by the side support. So Then, place or install the object to be lifted at the installation position.

【0008】 この状態で、線状部材の下端を下方に引くと、底面支持部の底面に設けられた 突出部からリング部が外れる。リング部が突出部から外れた状態になると、掛止 部を支持する物がなくなり、掛止具は、延出部の挿通孔にロープが挿通された状 態で自重により、被吊り上げ物から外れて挿通孔がリング部に達するまで下方に 移動する。 したがって、地上からの線状部材を下方に引くことによって容易に吊り具を取 り外すことができる。[0008] In this state, when the lower end of the linear member is pulled downward, the The ring part comes off from the protrusion. When the ring part comes off the protrusion, it will not be latched. There is no longer anything to support the part, and the hanging tool remains in the state where the rope is inserted through the insertion hole of the extension part. In this state, it will come off the object being lifted due to its own weight and move downward until the insertion hole reaches the ring part. Moving. Therefore, the lifting equipment can be easily removed by pulling the linear member downward from the ground. It can be removed.

【0009】[0009]

【実施例】【Example】

以下、図面を参照して、本考案の実施例について説明する。 図1および図2は、本考案の吊り具の一実施例を示すもので、図中符号1は掛 止具を示し、符号2は、線状部材を示し、符号3は、被吊り上げ物としてのB梁 を示している。 Embodiments of the present invention will be described below with reference to the drawings. Figures 1 and 2 show an embodiment of the hanging device of the present invention, and the reference numeral 1 in the figures shows a hanging device. The reference numeral 2 indicates a linear member, and the reference numeral 3 indicates a B beam as an object to be lifted. It shows.

【0010】 掛止具1は、図1に示すように、B梁3の底面5が当接する底面支持部6と、 この底面支持部6の両端部から上方に延出され、かつB梁3の両側面7、8を挟 み込んで支持する側面支持部9、10と、一方の側面支持部9上端から上方に延 出する延出部11と、底面支持部6の下面から突出する突出部12とを主体とし て構成されている。0010 As shown in FIG. 1, the hanging tool 1 includes a bottom support portion 6, which the bottom surface 5 of the B beam 3 comes into contact with; It extends upward from both ends of this bottom support part 6 and pinches both side surfaces 7 and 8 of the B beam 3. Side support parts 9 and 10 that are embedded in the support part 9 and 10 that extend upward from the upper end of one side support part 9. The main body includes an extending portion 11 that extends out, and a protruding portion 12 that protrudes from the lower surface of the bottom support portion 6. It is composed of

【0011】 そして、掛止具1は、鋼材により底面支持部6と側面支持部9、10と延出部 11とが略フック状に、一体に形成され、その底面5の他方の側面支持部10の 下方部分に突出部12が設けられている。 底面支持部6は、その上面が水平に形成されるととも該上面に滑り止めのため の多数の爪6aが設けられ、B梁3の底面5を掛止するようになっている。[0011] The hanging tool 1 includes a bottom support portion 6, side support portions 9 and 10, and an extension portion made of steel. 11 are integrally formed in a substantially hook shape, and the other side support portion 10 of the bottom surface 5 A protrusion 12 is provided in the lower part. The bottom support portion 6 has a horizontal upper surface and a non-slip surface on the upper surface. A large number of claws 6a are provided to hook the bottom surface 5 of the B beam 3.

【0012】 前記一方の側面支持部9は、その上端部がそのまま一体に延出部11の下端部 に接続され、B梁3の上面よりも上方に延出している。そして、延出部11の上 部は、他方の側面支持部10側に傾いた状態で上方に延出し、上端部分は、また 略垂直に上方に延出している。そして、この上端部分には、線状部材2が挿通さ れる挿通孔11aが設けられている。0012 The upper end of the one side support part 9 is integrally formed with the lower end of the extending part 11. , and extends above the upper surface of the B beam 3. Then, on the extension part 11 The portion extends upward while being inclined toward the other side support portion 10, and the upper end portion also extends upwardly. It extends upward almost vertically. The linear member 2 is inserted into this upper end portion. An insertion hole 11a is provided.

【0013】 前記他方の側面支持部10は、B梁3の高さよりも短く成形されている。また 、他方の側面支持部10の上端と延出部11との間には、容易にB梁3を出し入 れできる間隔が形成されている。 前記突出部12は、後述する線状部材2のリング部13が容易に掛止できるよ うにリング部13の穴13aよりも細く形成されている。[0013] The other side support portion 10 is formed shorter than the height of the B beam 3. Also , the B beam 3 can be easily inserted and removed between the upper end of the other side support part 10 and the extension part 11. There is a gap that allows for easy movement. The protruding portion 12 allows a ring portion 13 of a linear member 2, which will be described later, to be easily hooked thereto. The hole 13a of the sea urchin ring portion 13 is formed thinner than the hole 13a.

【0014】 前記線状部材2は、例えば、ロープ、ワイヤーロープ、鎖等であり、本実施例 ではワイヤーロープを使用している。 また、線状部材2の途中には、前記突出部12に掛止される環状のリング部1 3が設けられている。該リング部13には、外周の対向する二箇所に線状部材2 を繋ぐ係止部13b、13bが設けられ、それぞれに線状部材2の端部を繋ぐよ うになっている。そして、一方の線状部材2は、前記掛止具1の挿通孔11aに 挿通されている。そして、他方の線状部材2は、前記リング部13を突出部12 に掛止してB梁3を吊り上げた状態で、リング部13から下方に垂れ下がるよう になっている。またリング部13は、挿通孔11aの径より大きく形成されてい る。[0014] The linear member 2 is, for example, a rope, a wire rope, a chain, etc. I'm using wire rope. Further, in the middle of the linear member 2, an annular ring portion 1 that is hooked to the protruding portion 12 is provided. 3 is provided. The ring portion 13 has linear members 2 at two opposing locations on the outer periphery. Locking portions 13b, 13b are provided to connect the ends of the linear member 2, respectively. The sea urchin is turning. Then, one linear member 2 is inserted into the insertion hole 11a of the hanging tool 1. It is inserted. Then, the other linear member 2 connects the ring portion 13 to the protruding portion 12. so that it hangs downward from the ring part 13 with the B beam 3 suspended. It has become. Further, the ring portion 13 is formed larger than the diameter of the insertion hole 11a. Ru.

【0015】 また、線状部材2のリング部より上方には、ストッパー14が設けられている 。このストッパー14とリング部13の間の線状部材2に、掛止具1を挿通する ことにより、吊り具の保管の際などに、線状部材2から掛止具1が外れるのを防 止するようになっている。 本実施例においては、図2に示すように、2つの掛止具1を用い、それぞれの 掛止具1に繋がれた2本の線状部材2の上端が一つにまとめられて、クレーン等 のフックに掛止されるようになっている。そして、2つの掛止具1が、B梁3の 左右両端部を掛止するようになっている。[0015] Further, a stopper 14 is provided above the ring portion of the linear member 2. . The hook 1 is inserted into the linear member 2 between the stopper 14 and the ring part 13. This prevents the hanging tool 1 from coming off the linear member 2 when storing the hanging tool. It is designed to stop. In this embodiment, as shown in FIG. 2, two latches 1 are used, and each The upper ends of the two linear members 2 connected to the hanging tool 1 are combined into one, and the crane, etc. It is designed to be hung on a hook. Then, the two latches 1 are attached to the B beam 3. Both left and right ends are hooked.

【0016】 次に、本実施例の吊り具の作用について説明する。 ここで、被吊り上げ物としてのB梁3は、主に、寄棟屋根などに用いられる梁 材であって、図2に示すように、略矩形板状の上部板状体22と、略矩形板状の 下部板状体23とが、互いに所定の角度を有するように、それぞれの端部を突き 合わせて接合され、両者の接合部が両面側から補強板24、24によって補強さ れた構成を有するものである。そして、通常、上部板状体22の長さが、下部板 状体23の長さより短く設定されていることにより、その重心が定めにくく左右 が不均等荷重形状を有している。そして、このB梁3は、通常、その上部板状体 22を水平に配置した状態で、寄棟屋根の小屋裏に配設されて用いられるもので ある。[0016] Next, the operation of the suspender of this embodiment will be explained. Here, the B beam 3 as an object to be lifted is mainly a beam used for a hipped roof etc. As shown in FIG. The ends of the lower plate-shaped body 23 are pushed together so that they form a predetermined angle with each other. They are joined together, and their joints are reinforced from both sides by reinforcing plates 24, 24. It has a unique configuration. Usually, the length of the upper plate-like body 22 is the same as that of the lower plate. Since it is set shorter than the length of the shaped body 23, it is difficult to determine the center of gravity of the body 23. has an uneven loading shape. This B beam 3 usually has an upper plate-like body. 22 is placed horizontally in the attic of a hipped roof. be.

【0017】 まず、工場より現場へ運搬されてきた前記構成のB梁3の一方の端部付近に、 吊り具の掛止具1を固定する。具体的には、掛止具1の2つの側面支持部9、1 0間にB梁3をその端部側から挿入して、底面支持部6上に載置する。また、底 面支持部6上にB梁3を載置することにより、B梁3底面5に底面支持部6の爪 6aが僅かに食い込みB梁3底面5を係止する。 また、B梁3の他方の端部付近にも、同様にして掛止具1を取り付ける。[0017] First, near one end of the B beam 3 having the above configuration, which has been transported from the factory to the site, Fix the hanging tool 1 of the hanging tool. Specifically, the two side supports 9, 1 of the hanging tool 1 The B beam 3 is inserted from the end side between the holes and placed on the bottom support part 6. Also, the bottom By placing the B beam 3 on the surface support part 6, the claws of the bottom support part 6 are attached to the bottom surface 5 of the B beam 3. 6a bites in slightly and locks the bottom surface 5 of the B beam 3. Furthermore, the hook 1 is similarly attached near the other end of the B beam 3.

【0018】 そして、線状部材2は、予め、両方の掛止具1の挿通孔11aに挿通され、か つリング部13が掛止具1の突出部12に掛止されている。この状態で、線状部 材2をクレーンによって引き上げて、建物の小屋裏の所定位置まで運んで設置す る。[0018] Then, the linear member 2 is inserted into the insertion hole 11a of both the hooks 1 in advance, and then A ring portion 13 is hooked onto the protrusion 12 of the hook 1. In this state, the linear part Material 2 is lifted up by a crane, transported to a designated location in the attic of the building, and installed. Ru.

【0019】 B梁3の設置が終了した後には、掛止具1の突出部12に掛止されたリング部 13から垂れ下がる線状部材2を地上より引っ張る。これにより、リング部13 が突出部12から外され、リング部によって支持されていた掛止具1が、線状部 材2を挿通孔11aに挿通した状態で下方に移動し、掛止具1がB梁3から外れ る。そして、掛止具1は、挿通孔11aの部分が線状部材2のリング部13に引 っ掛かり止る。この状態で、B梁3を避けて、線状部材2を引き上げて、吊り具 を取り除く。[0019] After the installation of the B beam 3 is completed, the ring portion hooked on the protrusion 12 of the hook 1 is The linear member 2 hanging down from 13 is pulled from the ground. As a result, the ring portion 13 is removed from the protruding part 12, and the hook 1 that was supported by the ring part is removed from the linear part. With the material 2 inserted into the insertion hole 11a, move it downward, and the latch 1 comes off the B beam 3. Ru. The hook 1 has the insertion hole 11a pulled into the ring portion 13 of the linear member 2. It gets stuck and stops. In this state, avoid the B beam 3, pull up the linear member 2, and remove.

【0020】 以上、述べたことから容易に理解できるように、本実施例の吊り具によれば、 下側から抱え込まれるようにB梁3が底面5を吊り具の底面支持部6に当接させ 、両側面7、8が側面支持部9、10に挟み込まれた状態で挿入され、さらに底 面支持部6の爪19がB梁3の底面5に僅かに食い込まされてB梁3の移動を規 制することができるので、吊り上げ中に風などによって横振れが生じた場合でも 、B梁3をしっかりと保持してこの横振れから防護することができる。[0020] As can be easily understood from the above description, according to the hanging tool of this embodiment, The B-beam 3 brings the bottom surface 5 into contact with the bottom support part 6 of the hanging tool so as to be held from below. , both sides 7 and 8 are inserted between side support parts 9 and 10, and the bottom The claw 19 of the surface support part 6 is slightly bitten into the bottom surface 5 of the B beam 3 to regulate the movement of the B beam 3. Even if lateral vibration occurs due to wind etc. during lifting, , it is possible to firmly hold the B beam 3 and protect it from this lateral vibration.

【0021】 また、B梁3に固定してB梁3を所定位置に設置した後、地上からの操作、す なわち、線状部材2を引っ張ることによって、簡単にB梁3から掛止具1を取り 外すことができる。したがって、建物の小屋組みの上に載って作業を行っていた 従来の施工法に比べて、安全性が向上し、また作業性も良くなる。[0021] In addition, after fixing to the B beam 3 and installing the B beam 3 in a predetermined position, all operations from the ground can be performed. That is, by pulling the linear member 2, the hook 1 can be easily removed from the B beam 3. It can be removed. Therefore, work was carried out while standing on top of the building's roof frame. Compared to conventional construction methods, safety is improved and workability is also improved.

【0022】 図3は、本考案の吊り具の別の実施例を示す物であり、符号30で示すのが、 この実施例の掛止具である。 該掛止具30は、上記掛止具1と同様にB梁3の底面5が当接する底面支持部 31と、この底面支持部31の両端部から上方に延出され、かつB梁3の両側面 7、8を挟み込んで支持する側面支持部32、33と、一方の側面支持部32上 端から上方に延出する延出部34と、底面支持部31の下面から突出する突出部 35とを主体として構成されている。[0022] FIG. 3 shows another embodiment of the hanging device of the present invention, in which the reference numeral 30 shows This is the hanging tool of this example. The latching tool 30 has a bottom surface support portion on which the bottom surface 5 of the B beam 3 comes into contact, similar to the above-mentioned latching tool 1. 31, which extends upward from both ends of the bottom support part 31, and which extends from both sides of the B beam 3. Side support parts 32 and 33 sandwich and support 7 and 8, and one side support part 32 top An extending portion 34 extending upward from the end and a protruding portion protruding from the lower surface of the bottom support portion 31 It is mainly composed of 35.

【0023】 前記底面支持部31及び側面支持部32、33は、角型鋼管から形成され、一 方の側縁支持部32と延出部34とは、一体の角型鋼管から形成されている。そ して、底面支持部31と側面支持部32、33とは、端部が付き合わされて熔接 により接合されるとともに、この接合部分に2枚の鉄製の補強板36が左右両方 の側面からそれぞれ熔接されている。 また、延出部34の上端には、線状部材2を挿通するための挿通孔37aを有 する挿通部37が設けられている。該掛止部37は、角型鋼管からなり、延出部 34に対して直角、かつ底面支持部31に沿って延出部34に熔接されている。 そして、左右両側面からそれぞれ鉄製の補強板38が熔接されている。前記挿通 孔37aは、挿通部37の角型鋼管及び補強板38を貫通して設けられている。[0023] The bottom support portion 31 and the side support portions 32 and 33 are made of square steel pipes, and are made of square steel pipes. The side edge support portion 32 and the extension portion 34 are formed from an integral square steel pipe. So The bottom support portion 31 and the side support portions 32 and 33 are welded with their ends brought together. At the same time, two iron reinforcing plates 36 are installed on both the left and right sides of this joint. are welded from each side. Further, the upper end of the extending portion 34 has an insertion hole 37a through which the linear member 2 is inserted. An insertion portion 37 is provided. The hooking part 37 is made of a square steel pipe, and has an extending part. 34 and is welded to the extension part 34 along the bottom support part 31. Iron reinforcing plates 38 are welded to both the left and right sides, respectively. said insertion The hole 37a is provided to penetrate the square steel pipe of the insertion portion 37 and the reinforcing plate 38.

【0024】 さらに、底面支持部31の両側面には、爪を形成する釘部39が熔接されてい る。この釘部39は、矩形の鉄板39aに、その長さ方向に対して直角に2本の 溝を設け、この溝に釘39bを熔接したものである。 前記突出部35は、底面支持部31に、該底面支持部31に対して直角に、ボ ルトが熔接されたものである。 このような掛止具30は、前記実施例の掛止具1と同様に使用されるものであ り、掛止具30を用いた吊り具も、前記実施例と同様な効果を奏するものである 。[0024] Further, nail portions 39 forming claws are welded to both side surfaces of the bottom support portion 31. Ru. This nail part 39 is attached to a rectangular iron plate 39a with two nails perpendicular to its length direction. A groove is provided and a nail 39b is welded to this groove. The protruding portion 35 is provided with a bolt on the bottom support portion 31 at right angles to the bottom support portion 31. The bolts are welded together. Such a hanging tool 30 is used in the same way as the hanging tool 1 of the above embodiment. In addition, a hanging device using the hanging device 30 also has the same effect as the above embodiment. .

【0025】 なお、本考案の吊り具は、これら実施例に限られるものではなく、各部材の形 状、寸法、材質等の具体的構成要件は、実施に当たり適宜変更可能である。 また、これら実施例では、被吊り上げ物としてB梁3を吊り上げる場合を例に 挙げて説明したが、B梁3以外の屋根梁等の建築用部材などを吊り上げる場合に も使用可能であることはもちろんである。[0025] Note that the hanging device of the present invention is not limited to these examples, and the shape of each member can be changed. Specific structural requirements such as shape, dimensions, material, etc. can be changed as appropriate for implementation. In addition, in these embodiments, the case where the B beam 3 is lifted as an object to be lifted is taken as an example. As explained above, when lifting architectural members such as roof beams other than B beam 3, Of course, it is also possible to use

【0026】[0026]

【考案の効果】[Effect of the idea]

以上説明したように、本考案の吊り具によれば、被吊り上げ物に固定して被吊 り上げ物を所定位置に設置した後、地上からの線状部材の操作によって、簡単に 被吊り上げ物から吊り具を取り外すことができる。したがって、建物の小屋組み の上に載って作業を行う必要がなくなり、作業性の向上を図ることができる。 As explained above, according to the hanging device of the present invention, it can be fixed to the object to be lifted. After installing the raised item in the specified position, it can be easily lifted by operating the linear member from the ground. The lifting device can be removed from the object to be lifted. Therefore, the roof frame of the building It is no longer necessary to work while standing on top of the machine, improving work efficiency.

【図面の簡単な説明】[Brief explanation of drawings]

【図1】上記実施例の吊り具の一実施例を示す側面図で
ある。
FIG. 1 is a side view showing an embodiment of the hanging device of the above embodiment.

【図2】上記吊り具を使用した被吊り上げ物の吊り上げ
状態を示す斜視図である。
FIG. 2 is a perspective view showing a state in which an object to be lifted is lifted using the above-mentioned lifting tool.

【図3】上記吊り具とは、別の実施例の掛止具を示す斜
視図である。
FIG. 3 is a perspective view showing a hanging device of another embodiment.

【符号の説明】[Explanation of symbols]

1、30 掛止具 2 線状部材 3 B梁(被吊り上げ物) 5 B梁の底面 6、31 吊り具の底面支持部 7 B梁の側面 8 B梁の側面 9、32 吊り具の側面支持部 10、33 吊り具の側面支持部 11、34 吊り具の延出部 11a、37a 吊り具の挿通孔 12、35 吊り具の突出部 13 線状部材のリング部 1,30 Hanging tool 2 Linear member 3 B beam (object to be lifted) 5 Bottom of B beam 6, 31 Bottom support part of hanging device 7 Side of B beam 8 Side of B beam 9, 32 Side support part of hanging device 10, 33 Side support part of hanging device 11, 34 Extending part of hanging tool 11a, 37a Hanging tool insertion hole 12, 35 Projecting part of hanging tool 13 Ring part of linear member

Claims (1)

【実用新案登録請求の範囲】[Scope of utility model registration request] 【請求項1】 被吊り上げ物を掛止する掛止具と、該掛
止具に繋がれて前記被吊り上げ物を吊り上げるための線
状部材とを具備してなり、前記掛止具は、被吊り上げ物
の底面に当接される底面支持部と、該底面支持部の両端
部からそれぞれ上方に延出され、かつ前記被吊り上げ物
の両側面を支持する側面支持部と、一方の側面支持部上
端から上方に延出された延出部と、前記底面支持部底面
より下方に突出する突出部とを具備してなり、前記延出
部の上端部には、前記線状部材を挿通するための挿通孔
が設けられ、前記線状部材は、その途中に環状のリング
部が設けられ、前記延出部の挿通孔に前記リング部が該
挿通孔より下方にくるように挿通され、前記リング部が
前記掛止具の突出部に着脱自在に掛止されていることを
特徴とする吊り具。
Claim 1: A hanging tool for hanging an object to be lifted; and a linear member connected to the hanging tool for lifting the object to be lifted; A bottom support part that comes into contact with the bottom surface of the object to be lifted, a side support part that extends upward from both ends of the bottom support part and supports both sides of the object to be lifted, and one side support part. an extending portion extending upward from the upper end; and a protruding portion protruding downward from the bottom surface of the bottom support portion; the extending portion has an upper end portion for inserting the linear member; The linear member is provided with an annular ring portion in the middle thereof, and is inserted into the insertion hole of the extension portion such that the ring portion is below the insertion hole, and the ring A hanging device, characterized in that the hanging device is removably hooked to a protruding portion of the hanging device.
JP3665191U 1991-04-22 1991-04-22 sling Withdrawn JPH04122581U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3665191U JPH04122581U (en) 1991-04-22 1991-04-22 sling

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3665191U JPH04122581U (en) 1991-04-22 1991-04-22 sling

Publications (1)

Publication Number Publication Date
JPH04122581U true JPH04122581U (en) 1992-11-04

Family

ID=31918567

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3665191U Withdrawn JPH04122581U (en) 1991-04-22 1991-04-22 sling

Country Status (1)

Country Link
JP (1) JPH04122581U (en)

Similar Documents

Publication Publication Date Title
US3765543A (en) System for lifting and handling panels
JP2004250188A (en) Hoisting fixture
JPH05116881A (en) Plate-shaped lifting tool
JPS6317791A (en) Lifting conveying method of panel
JPH04122581U (en) sling
JP2007113193A (en) Lifting method for pc floor slab and hanging tool used therein
JP6661142B1 (en) Hanging scaffold
JP2892952B2 (en) Connection method of steel pipe piles
JP2014020157A (en) Erecting method of post
JP2009121018A (en) Hanging implement
JP7444751B2 (en) Wall material unit and wall construction method
JPH0437168Y2 (en)
JP2004308155A (en) Method and implement for hanging pc slab
JP2001354374A (en) Lifting device in hoistway of elevator
JPH04107773U (en) sling
JP2001107567A (en) Concrete panel for building, method for laying it, lifting anchor fitting, and lifting tool
JPH0585478B2 (en)
JPH061581Y2 (en) Crane lifting equipment
JP7254628B2 (en) Floor panel transportation method, hanging bracket and floor panel fixing method
JPH035547A (en) Outer wall half pc plate and mounting method thereof
JP3084325U (en) Concrete pole reinforcement
JPH07157274A (en) Hanging jig for alc plate
JP2569898Y2 (en) Jig for building long steel
JPH0516786U (en) Hanging equipment
JPH072549Y2 (en) Crane lifting equipment

Legal Events

Date Code Title Description
A300 Application deemed to be withdrawn because no request for examination was validly filed

Free format text: JAPANESE INTERMEDIATE CODE: A300

Effective date: 19950713