JPH04111696U - gas meter device - Google Patents

gas meter device

Info

Publication number
JPH04111696U
JPH04111696U JP1555991U JP1555991U JPH04111696U JP H04111696 U JPH04111696 U JP H04111696U JP 1555991 U JP1555991 U JP 1555991U JP 1555991 U JP1555991 U JP 1555991U JP H04111696 U JPH04111696 U JP H04111696U
Authority
JP
Japan
Prior art keywords
flow rate
gas
alarm
shut
control unit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP1555991U
Other languages
Japanese (ja)
Other versions
JP2522195Y2 (en
Inventor
正志 外山
敏正 鳥山
Original Assignee
矢崎総業株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 矢崎総業株式会社 filed Critical 矢崎総業株式会社
Priority to JP1555991U priority Critical patent/JP2522195Y2/en
Publication of JPH04111696U publication Critical patent/JPH04111696U/en
Application granted granted Critical
Publication of JP2522195Y2 publication Critical patent/JP2522195Y2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Measuring Volume Flow (AREA)
  • Emergency Alarm Devices (AREA)

Abstract

(57)【要約】 【目的】ガスメータ装置において、警報器からの警報信
号によってガスメータ内の弁を遮断できるようにしたシ
ステムでは、重大事故につながるガスの漏洩が起きた場
合にガス遮断できることに着目し、継続使用時間による
遮断を警報器の有無によって行わせることで、安全性を
確保した上で利便性を向上することを目的としている。 【構成】接続検出手段2dが警報器5の接続されていな
いことを検出している場合、遮断信号出力手段2eが各
流量区分に対してそれぞれ設定した一定時間の間流量に
変化がないとき直ちに電磁弁4を遮断する。また、警報
器5の接続されている場合、各流量区分に対してそれぞ
れ設定した一定時間の間流量に変化がないときそれから
一定時間後に、電磁弁4を遮断する遮断信号を出力す
る。
(57) [Summary] [Purpose] We focused on the fact that in a gas meter device, a system that allows the valve inside the gas meter to be shut off by an alarm signal from the alarm device can shut off the gas in the event of a gas leak that could lead to a serious accident. The aim is to ensure safety and improve convenience by having the system shut off depending on the length of continuous use, depending on the presence or absence of an alarm. [Structure] When the connection detection means 2d detects that the alarm 5 is not connected, the cutoff signal output means 2e immediately outputs a signal when there is no change in the flow rate for a certain period of time set for each flow rate category. The solenoid valve 4 is shut off. Further, when the alarm device 5 is connected, if there is no change in the flow rate for a predetermined time period set for each flow rate category, a cutoff signal is output to shut off the solenoid valve 4 after a predetermined time period.

Description

【考案の詳細な説明】[Detailed explanation of the idea]

【0001】0001

【産業上の利用分野】[Industrial application field]

本考案はガスの使用量を計測する計量機能を有するガスメータ装置に係り、特 に、ガス流路に流れるガスの流量を計量する計量部の他に、ガス流路に流れるガ スの流量を監視して各種の仕事を行う制御部とを有するガスメータ装置に関する ものである。 The present invention relates to a gas meter device having a metering function to measure the amount of gas used. In addition to the measuring section that measures the flow rate of gas flowing through the gas flow path, Gas meter device having a control unit that monitors the flow rate of gas and performs various tasks It is something.

【0002】0002

【従来の技術】[Conventional technology]

従来、この種のガスメータ装置として、図6に示すように構成されたものがあ った。同図において、ガスメータ本体1に内蔵された制御部2には、ガスメータ 1の計量部11の動作に連動して流量信号を発生する流量センサ3と、ガス流路 に設けられた電磁弁4と、宅内に設けられたガス漏れ警報器5とが信号線L1 乃 至L3 を介して接続されると共に、網制御ユニット(NCU)6及び電話回線L 4 を介して図示しないセンタに接続されている。なお、7はLPガスボンベ、8 はガス流路としてのガス配管、9はガス器具である。 Conventionally, this type of gas meter device has the configuration shown in Fig. 6. It was. In the figure, a control section 2 built into a gas meter body 1 includes a gas meter. A flow rate sensor 3 that generates a flow rate signal in conjunction with the operation of the measuring unit 11 of No. 1, and a gas flow path. The solenoid valve 4 installed in the house and the gas leak alarm 5 installed in the house are connected to the signal line L.1No To L3network control unit (NCU) 6 and telephone line L. Four It is connected to a center (not shown) via. In addition, 7 is an LP gas cylinder, 8 9 is a gas pipe serving as a gas flow path, and 9 is a gas appliance.

【0003】 以上の構成により、制御部2は流量センサ3からの流量信号によって一定流量 で一定時間を越えてガスが使用されたこと(継続使用時間オーバー)を検出する と、ガス器具9の消し忘れと判断して電磁弁4に対して遮断信号を出力してガス 遮断を行うようになっており、また上記一定時間から所定時間前に、例えば5分 前にガス漏れ警報器5に対して警告信号を出力して警告音を発生させ、ガス使用 者にガス器具の消し忘れについての注意を喚起するようになっている。0003 With the above configuration, the control unit 2 can control the flow rate at a constant flow rate based on the flow rate signal from the flow rate sensor 3. Detects when gas has been used for more than a certain period of time (continuous use time exceeded) It determines that the gas appliance 9 has been turned off and outputs a cutoff signal to the solenoid valve 4 to turn off the gas. It is designed to shut off, and also for example 5 minutes before the specified time above. A warning signal is output to the gas leak alarm 5 to generate a warning sound before the gas is used. Gas appliances are now being issued to remind people not to forget to turn off gas appliances.

【0004】 また、ガス漏れ警報器5がガス漏れを検知した場合は、ガス漏れ警報器5から 信号線L3 を介してガス漏れ信号が制御部2に送られ、制御部2はガス漏れ信号 を受けて電磁弁4に対して遮断信号をステップしてガス遮断を行うようになって いる。Further, when the gas leak alarm 5 detects a gas leak, a gas leak signal is sent from the gas leak alarm 5 to the control unit 2 via the signal line L 3 , and the control unit 2 receives the gas leak signal. In response to this, a cutoff signal is stepped to the solenoid valve 4 to shut off the gas.

【0005】 そして、電磁弁4が遮断したときには、NCU6及び電話回線L4 を介してガ ス供給業者のセンタに対して電磁弁4を遮断したことを通報し、電話回線L4 及 びNCU6を介してセンタから送られてくる遮断指令信号を受け取ると、電磁弁 4を遮断するようになっている。When the solenoid valve 4 is shut off, the gas supplier's center is notified via the NCU 6 and telephone line L 4 that the solenoid valve 4 has been shut off. When receiving a shutoff command signal sent from the center, the solenoid valve 4 is shut off.

【0006】 また一方、コスト的な理由によって図6のシステムを構築できない場合には、 制御部2はガス漏れ警報器、NCUは制御されず、メータ単独で流量異常を判断 して遮断を行わせるようにしたシステムも使用されている。ここで流量異常とは 上述した継続使用時間オーバーの他に、合計流量オーバー、増加流量オーバー、 微少漏洩などである。[0006] On the other hand, if the system shown in Figure 6 cannot be constructed due to cost reasons, Control unit 2 is a gas leak alarm, the NCU is not controlled, and the meter alone determines flow abnormality. Some systems are also in use that allow for shutoffs to occur. What is flow abnormality here? In addition to exceeding the continuous usage time mentioned above, exceeding the total flow rate, exceeding the increased flow rate, Such as minute leakage.

【0007】[0007]

【考案が解決しようとする課題】[Problem that the idea aims to solve]

上述したように従来のものでは、ガス漏れ警報器5が接続されていても接続さ れていなくても、一定時間がきたら電磁弁4を遮断するとようになっている。 As mentioned above, in the conventional system, even if the gas leak alarm 5 is connected, it is not connected. Even if the solenoid valve 4 is not turned off, the solenoid valve 4 is shut off after a certain period of time.

【0008】 なお、上記一定時間は、一定のガス器具の使用時間を調査し、統計的に決めた 値で、複数の流量監視区分の各々に対して予め定めたデータが制御部2を構成す るマイクロコンピュータ(CPU)内のメモリに格納されたものである。しかし 、ガス器具の開発状況やガス使用状態によっては、正常使用でも遮断する不用遮 断が発生する可能性がある。[0008] The above fixed time is determined statistically by investigating the usage time of certain gas appliances. The predetermined data for each of the plurality of flow rate monitoring categories constitutes the control unit 2. It is stored in the memory of a microcomputer (CPU). but Depending on the development status of gas appliances and gas usage conditions, unnecessary shields may be shut off even during normal use. There is a possibility that a disconnection may occur.

【0009】 このような不用遮断が頻繁に起こると、ユーザは正常使用中であったにも拘ら ず、ガス流路が遮断されてしまうため、屋外に出て遮断復帰操作をしなければな らなかったり、遮断原因が判らないためにガス供給業者に連絡して供給設備を点 検させたりすることが多くなるため、ユーザにとっては利便性が悪く、供給業者 にとってはユーザとのトラブルが多くなることで負担が大きくなるという問題が あった。[0009] If such unnecessary shutdowns occur frequently, users may be unable to use the device even though they are using it normally. However, the gas flow path will be blocked, and you will have to go outside to restore the shutoff. Contact your gas supplier and turn on the supply equipment if the problem is not clear or you do not know the cause of the shutoff. This is inconvenient for users, and it is difficult for suppliers to For users, the problem is that the burden increases due to more troubles with users. there were.

【0010】 よって本考案は、上述した従来の問題に鑑み、ガスメータの制御部に警報器が 接続されていて、警報器からの警報信号によってガスメータ内の弁を遮断できる ようにしたシステムにおいては、重大事故につながるガスの漏洩が起きた場合に は警報器によって遮断できることに着目し、継続使用時間による遮断を警報器の 有無によって行わせることで、安全性を確保した上で利便性を向上したガスメー タ装置を提供することを課題としている。0010 Therefore, in view of the above-mentioned conventional problems, the present invention has been developed by installing an alarm in the control section of the gas meter. connected, and the valve in the gas meter can be shut off by the alarm signal from the alarm In such a system, in the event of a gas leak that could lead to a serious accident, Focusing on the fact that the alarm can be used to shut off the alarm, the alarm can be shut off due to the continuous use time. A gas meter that ensures safety and improves convenience by making the The goal is to provide data storage equipment.

【0011】[0011]

【課題を解決するための手段】[Means to solve the problem]

上記課題を解決するため本考案により成されたガスメータ装置は、図1の基本 構成図に示すように、ガスメータ1の計量部11の動作に連動して流量センサ3 が発生する流量信号に基づいて流量の変化がないことを監視し、各流量区分に対 してそれぞれ設定した一定時間の所定時間前まで流量に変化がないとき、各流量 区分に対してそれぞれ設定した一定時間の間流量に変化がないときガス流路に設 けた電磁弁4を遮断する制御を行う制御部2を有するガスメータ装置において、 前記制御部2が、該制御部2への警報器5の接続の有無を検出する接続検出手段 2dと、前記接続検出手段2dによって警報器5の接続されていないことが検出 されている場合だけ各流量区分に対してそれぞれ設定した一定時間の間流量に変 化がないとき直ちに、前記電磁弁4を遮断する遮断信号を出力する遮断信号出力 手段2eとを有することを特徴としている。 The gas meter device created by this invention to solve the above problems is based on the basics shown in Figure 1. As shown in the configuration diagram, the flow rate sensor 3 operates in conjunction with the operation of the measuring section 11 of the gas meter 1. monitors for no change in flow rate based on the flow signal generated by the When there is no change in the flow rate until the specified time before the set time, each flow rate is When there is no change in the flow rate for a certain period of time set for each category, the In a gas meter device having a control unit 2 that performs control to shut off a solenoid valve 4, Connection detection means for the control unit 2 to detect whether or not the alarm device 5 is connected to the control unit 2 2d, and the connection detection means 2d detects that the alarm 5 is not connected. The flow rate changes for a certain period of time set for each flow rate category only when A cutoff signal output that outputs a cutoff signal to immediately cut off the solenoid valve 4 when there is no It is characterized by having means 2e.

【0012】 上記課題を解決するため本考案により成された図1のガスメータ装置において 、前記遮断信号出力手段2eが、該接続検出手段2dによって警報器5の接続さ れていないことが検出されている場合各流量区分に対してそれぞれ設定した一定 時間の間流量に変化がないとき直ちに、前記接続検出手段2dによって警報器5 の接続されていることが検出されている場合各流量区分に対してそれぞれ設定し た一定時間の間流量に変化がないときそれから一定時間後に、前記電磁弁4を遮 断する遮断信号を出力することを特徴としている。0012 In the gas meter device shown in Fig. 1, which was developed according to the present invention in order to solve the above problems, , the cutoff signal output means 2e detects whether the alarm 5 is connected by the connection detection means 2d. If it is detected that the As soon as there is no change in the flow rate for a period of time, the alarm 5 is activated by the connection detection means 2d. If it is detected that the When there is no change in the flow rate for a certain period of time, the solenoid valve 4 is shut off after a certain period of time. It is characterized by outputting a cutoff signal to disconnect.

【0013】[0013]

【作用】[Effect]

上記構成において、前記制御部2が有する接続検出手段2dが警報器5の接続 されていないことを検出している場合だけ、遮断信号出力手段2eが各流量区分 に対してそれぞれ設定した一定時間の間流量に変化がないとき直ちに前記電磁弁 4を遮断する遮断信号を出力して電磁弁4を遮断し、警報器5が接続されている 場合に、各流量区分に対してそれぞれ設定した一定時間の間流量に変化がなくて も電磁弁4を遮断しないので、安全性を確保した上で不用遮断をなくすることが できる。 In the above configuration, the connection detection means 2d of the control section 2 detects the connection of the alarm device 5. Only when the cutoff signal output means 2e detects that the Immediately when there is no change in the flow rate for a set period of time, the solenoid valve 4 is output to shut off the solenoid valve 4, and the alarm 5 is connected. When there is no change in the flow rate for a certain period of time set for each flow rate category, Since the solenoid valve 4 is not shut off, it is possible to eliminate unnecessary shutoffs while ensuring safety. can.

【0014】 また、遮断信号出力手段2eが、前記接続検出手段2dによって警報器5の接 続されていないことが検出されている場合各流量区分に対してそれぞれ設定した 一定時間の間流量に変化がないとき直ちに、前記接続検出手段2dによって警報 器5の接続されていることが検出されている場合各流量区分に対してそれぞれ設 定した一定時間の間流量に変化がないときそれから一定時間後、例えばユーザが 留守であると判断できる時間後に、前記電磁弁4を遮断する遮断信号を出力して 電磁弁4を遮断するので、安全性を確保した上で不用遮断をなくするとともに、 ユーザの留守中による大事故の発生を防止することができる。[0014] Further, the cutoff signal output means 2e is connected to the alarm 5 by the connection detection means 2d. If it is detected that the connection is not connected, the Immediately when there is no change in the flow rate for a certain period of time, the connection detection means 2d issues an alarm. If it is detected that the device 5 is connected, the settings are made for each flow rate category. If there is no change in the flow rate for a specified period of time, then after a certain period of time, e.g. After a period of time when it can be determined that the person is away, outputs a cutoff signal to cut off the solenoid valve 4. Since the solenoid valve 4 is shut off, safety is ensured and unnecessary shutoffs are eliminated. It is possible to prevent major accidents from occurring while the user is away.

【0015】[0015]

【実施例】【Example】

以下、本考案の実施例を図面に基づいて説明する。図2は本考案によるガスメ ータ装置の一実施例を示すブロック図であり、同図において、図6について上述 した従来のものと同一の部分には同一の符号を付してある。 Hereinafter, embodiments of the present invention will be described based on the drawings. Figure 2 shows the gas meter according to the present invention. 6 is a block diagram showing an embodiment of the computer device, in which The same parts as in the conventional one are given the same reference numerals.

【0016】 図2において、制御部2は予め定めた制御プログラムに従って動作するマイク ロコンピュータ(CPU)によって構成され、制御プログラムを格納するROM 2aと各種のデータを格納するデータエリアや信号処理の過程で使用するワーク エリアなどを有するRAM2bとを有する。[0016] In FIG. 2, the control unit 2 is a microphone that operates according to a predetermined control program. A ROM that is configured by a computer (CPU) and stores a control program 2a and the data area for storing various data and the workpiece used in the signal processing process. It has a RAM 2b having areas and the like.

【0017】 流量センサ3は信号線L1 を介して制御部2に接続されており、例えばガスメ ータの計量部を構成するダイアフラム又はこのダイアフラムの往復運動を指示部 に伝達するリンク機構に一部に設けた磁石と、この磁石の位置を検出するリード スイッチとを組み合わせたもので構成される。このガス流量センサ3はそのリー ドスイッチのオン・オフによって流量信号を発生し、この流量信号を受け取る制 御部2はリードスイッチのオンから次のオンまでの時間を計測することにより、 ガスの流量を知ることができる。The flow rate sensor 3 is connected to the control unit 2 via a signal line L1 , and is connected, for example, to a diaphragm constituting a measuring unit of a gas meter or a link mechanism that transmits the reciprocating motion of this diaphragm to an indicating unit. It consists of a combination of a magnet and a reed switch that detects the position of the magnet. This gas flow rate sensor 3 generates a flow rate signal by turning on and off the reed switch, and the control unit 2 that receives this flow rate signal measures the gas flow rate by measuring the time from one turn on of the reed switch to the next turn on. You can know.

【0018】 電磁弁4は信号線L2 を介して制御部2に接続されており、ガス流路中に設け た磁石と電磁コイルとを組み合わせた自己保持型のもので、制御部2からの遮断 信号によりガス流路を遮断する。この電磁弁4は、磁石によって開状態を自己保 持するようになっており、電源としての電池の消耗を少なくしている。また、遮 断動作は、その電磁コイルに電流を流すことによって生じる電磁力が磁石により 弁を開状態に保つ保持力に打ち勝つことによって、自己保持状態が解除されるこ とにより行われる。このようにして一度遮断状態になれば、磁石の保持力だけで は、開状態になることはなく、もはや電流を流す必要はない。開状態にすために は、手動で弁を開け、磁石で保持できる位置にする。The solenoid valve 4 is connected to the control unit 2 via a signal line L 2 , and is a self-holding type that combines a magnet and an electromagnetic coil provided in the gas flow path. The gas flow path is cut off by the cutoff signal. This electromagnetic valve 4 is configured to self-maintain in an open state using a magnet, thereby reducing consumption of a battery as a power source. Further, the shutoff operation is performed when the self-holding state is released as the electromagnetic force generated by passing a current through the electromagnetic coil overcomes the holding force of the magnet that keeps the valve open. Once the circuit is cut off in this way, the holding force of the magnet alone will not cause the circuit to open, and there is no longer a need for current to flow. To open the valve, open it manually and position it so that it can be held by a magnet.

【0019】 ガス漏れ警報器5はインターフェース10及び信号線L3 を介して双方向通信 可能なように制御部2と接続されており、COガスや燃焼ガスを検知する検知素 子からなるセンサ部とブザーなどの発音器からなる警報部とからなっている。ガ ス漏れ警報器5は所定濃度以上のガスを検知すると、警報部を作動させて警報音 を発生するとともにその旨を示すガス検知信号を信号線L3 及びインターフェー ス10を介して制御部2に送出して電磁弁4を遮断させる。また、制御部2から インターフェース10及び信号線L3 を介して入力される流量市場による遮断予 告信号及び遮断信号に基づいて警報部が作動されて警告音を発する。The gas leak alarm 5 is connected to the control unit 2 via an interface 10 and a signal line L 3 so as to be able to communicate bidirectionally, and has a sensor unit consisting of a detection element that detects CO gas or combustion gas. It consists of an alarm section consisting of a sounding device such as a buzzer. When the gas leak alarm 5 detects gas with a predetermined concentration or higher, it activates the alarm unit to generate an alarm sound and sends a gas detection signal indicating this to the control unit 2 via the signal line L 3 and the interface 10. to shut off the solenoid valve 4. Further, the alarm section is activated to emit a warning sound based on a cutoff notice signal and a cutoff signal from the flow rate market inputted from the control section 2 through the interface 10 and the signal line L3 .

【0020】 網制御ユニット(NCU)6は制御部2からセンタへの信号の送信とセンタか らの信号の受信とを制御するためのものであり、制御部2には、ガス漏れ警報器 5の接続の有無を設定する接続設定器12が接続されている。[0020] A network control unit (NCU) 6 transmits signals from the control unit 2 to the center and sends signals from the control unit 2 to the center. The controller 2 is equipped with a gas leak alarm. A connection setting device 12 is connected to the connection setting device 12 for setting the presence/absence of connection of 5.

【0021】 上記制御部2は、流量センサ3からの流量信号に基づいてガス流量を計測し、 この計測したガス流量の変化がないことを監視し、各流量区分に対してそれぞれ 設定した一定時間の所定時間前まで流量に変化がないと判断したとき、ガス漏れ 警報器5に対して遮断予告信号を出力すると共に網制御ユニット6及び電話回線 L4 を介してセンタにその旨を通報する。[0021] The control unit 2 measures the gas flow rate based on the flow rate signal from the flow rate sensor 3, monitors that there is no change in the measured gas flow rate, and waits for a certain period of time set for each flow rate category. When it is determined that there is no change in the flow rate until a predetermined time before the gas leak alarm 5, it outputs a cutoff warning signal to the gas leak alarm 5 and notifies the center via the network control unit 6 and telephone line L4 .

【0022】 その後、制御部2は、各流量区分に対してそれぞれ設定した一定時間の間流量 に変化がないと判断した場合、その流量相当のガス器具が通常使用時間よりも長 く使われていることになるので、このような状態は何らかの異常を示すものとし て、インターフェース10からの信号によってガス漏れ警報器5が接続されてい るかどうかを判断し、接続されていないと判断したときには直ちに遮断信号をイ ンターフェース10及び信号線L3 を介して電磁弁4に対して送出し、電磁弁4 を駆動してガス流路を遮断すると共に、電磁弁4を遮断したことを遠隔のセンタ に対して網制御ユニット6及び電話回線L4 を介してセンタに通報する。[0022] After that, if the control unit 2 determines that there is no change in the flow rate for a certain period of time set for each flow rate category, it determines that the gas appliance corresponding to that flow rate has been used for a longer time than the normal usage time. Therefore, such a state indicates some kind of abnormality, and it is determined whether the gas leak alarm 5 is connected based on the signal from the interface 10, and if it is determined that it is not connected, it immediately issues a cutoff signal. A signal is sent to the solenoid valve 4 via the interface 10 and the signal line L3 , and the solenoid valve 4 is driven to shut off the gas flow path, and a network control is sent to a remote center to notify that the solenoid valve 4 has been shut off. Notify the center via unit 6 and telephone line L4 .

【0023】 一方、制御部2がインターフェース10からの信号によってガス漏れ警報器5 が接続されていると判断したときには、ガス漏れ警報器5への警告信号は出力し 続けるが、電磁弁4は遮断しないか、或いはRAM2bに構成したタイマを起動 して一定時間、例えばユーザが留守中だと判断できる時間の計時を行い、この間 も依然ガス流量の変化がないときには遮断信号をインターフェース10及び信号 線L3 を介して電磁弁4に対して送出し、電磁弁4を駆動してガス流路を遮断す ると共に、電磁弁4を遮断したことを遠隔のセンタに対して網制御ユニット6及 び電話回線L4 を介してセンタに通報する。On the other hand, when the control unit 2 determines that the gas leak alarm 5 is connected based on the signal from the interface 10, the warning signal to the gas leak alarm 5 continues to be output, but the solenoid valve 4 is shut off. Otherwise, a timer configured in the RAM 2b is started to measure a certain period of time, for example, a period during which it can be determined that the user is away, and if there is still no change in the gas flow rate during this period, a cutoff signal is sent to the interface 10 and signal line L. 3 to the solenoid valve 4 to drive the solenoid valve 4 to shut off the gas flow path, and to notify the remote center that the solenoid valve 4 has been shut off via the network control unit 6 and telephone line L. Report to the center via 4 .

【0024】 制御部2において、流量センサ3からの流量信号によって計測したガス流量が 、一定値のままで所定時間を越えて流れ、その流量相当のガス器具が通常使用時 間よりも長く使われていると判断するために、制御部2には、ガスの種類を選択 すると共にガスメータの種類及び使用する設備の最大消費流量、ガスストーブの 有無などを選択する設定器11が接続されている。これは、爆発するに足る未燃 焼ガスの量がガスの種類によって異なるので、ガスメータを通過するガス量から 危険性を判断するときの所定時間をガス種類に応じて変える必要があり、またガ スメータのダイアフラムの一往復によりメータを通過するガス量がメータの種類 により異なるためであり、また使用される設備の燃焼器の種類や数によっても危 険性を判断するときの所定時間や流量が異なるからである。[0024] In the control unit 2, the gas flow rate measured by the flow rate signal from the flow rate sensor 3 is , the flow remains at a constant value for more than a specified time, and the gas appliance equivalent to that flow rate is in normal use. In order to judge that the gas has been used for a longer time than the In addition, the type of gas meter, the maximum flow rate of the equipment used, and the gas stove. A setting device 11 for selecting presence/absence is connected. This is enough unburned material to explode. Since the amount of burning gas varies depending on the type of gas, it is determined from the amount of gas passing through the gas meter. It is necessary to change the predetermined time for determining danger depending on the type of gas, and The type of meter is the amount of gas that passes through the meter with one round trip of the diaphragm. This is because the risk varies depending on the type and number of combustors in the equipment used. This is because the predetermined time and flow rate used to judge risk are different.

【0025】 なお、上述の実施例では、ガス漏れ警報器5の接続の有無を設定する接続設定 器12を制御部2に接続しているが、インターフェース10に信号線L3 を介し てガス漏れ警報器5が接続されていないことを検出して非接続状態を示す信号を 発生する機能を持たせ、制御部2がこの信号に基づいてガス漏れ警報器5が接続 されているか否かを判定することができるようにしてもよい。このようにするこ とで、ガス漏れ警報器5が接続されているシステムにおいても、何らかの理由に より信号線L3 が断線した場合にもガス漏れ警報器5が接続されていないと判断 するので、継続使用時間オーバーによる遮断を行うことができる。In the above-described embodiment, the connection setting device 12 for setting whether or not the gas leak alarm 5 is connected is connected to the control unit 2. A function is provided to detect that the alarm 5 is not connected and generate a signal indicating the disconnected state, and the control unit 2 determines whether or not the gas leak alarm 5 is connected based on this signal. It may be possible to do so. By doing this, even in a system where the gas leak alarm 5 is connected, even if the signal line L3 is disconnected for some reason, it will be determined that the gas leak alarm 5 is not connected, so the system will continue operating. It is possible to shut down the device when the usage time has exceeded.

【0026】 以上概略説明した装置の動作を、制御部2を構成するCPUが行う仕事を示す 図3及び図4のフローチャートを参照して以下説明する。[0026] The work performed by the CPU constituting the control unit 2 for the operation of the device outlined above is shown below. This will be explained below with reference to the flowcharts of FIGS. 3 and 4.

【0027】 CPUからなる制御部2は電源投入によって動作を開始し、図3のフローチャ ートのの最初のステップS1において流量センサ3からの流量信号によって流量 の計測を行ってからステップS2に進む。ステップS2においては、ステップS 1において計測した流量が所定の範囲内に入っているか否かを判定し、この判定 がNOのときにはステップS3に進んで継続使用時間オーバー異常以外の流量異 常処理を行ってから上記ステップS1に戻る。なお、この異常処理においては、 センタに異常を通報すると共に電磁弁4に遮断信号を出力するなどの仕事を行う 。[0027] The control unit 2 consisting of a CPU starts operating when the power is turned on, and the flowchart shown in FIG. In the first step S1 of the process, the flow rate is determined by the flow rate signal from the flow rate sensor 3. After measuring, the process proceeds to step S2. In step S2, step S Determine whether the flow rate measured in step 1 is within a predetermined range, and make this determination. If NO, proceed to step S3 and check the flow rate abnormality other than the continuous usage time over abnormality. After performing normal processing, the process returns to step S1. In addition, in this abnormality processing, Performs tasks such as notifying the center of abnormalities and outputting a cutoff signal to the solenoid valve 4. .

【0028】 上記ステップS2の判定がYESのとき、すなわち流量が所定の範囲内にある ときにはステップS4に進み、ここで流量がどの流量区分に入っているかを特定 してからステップS5に進み、ここで上記ステップS4において特定した流量区 分が前回特定した区分と変わっているかどうかによって流量変化の有無を判定す る。このステップS5の判定がYESのとき、すなわち流量変化があるときには ステップS6に進んでRAM2b中に形成した制限時間タイマをリセットしてか ら上記ステップS1に戻る。[0028] When the determination in step S2 is YES, that is, the flow rate is within a predetermined range. In some cases, the process proceeds to step S4, where it is specified which flow rate category the flow rate falls into. After that, the process proceeds to step S5, where the flow rate area specified in step S4 is The presence or absence of a flow rate change is determined based on whether the minutes have changed from the previously specified classification. Ru. When the determination in step S5 is YES, that is, when there is a change in flow rate, Proceed to step S6 and reset the time limit timer formed in RAM2b. Then, the process returns to step S1.

【0029】 上記ステップS5の判定がNO、すなわち流量変化がないときにはステップS 7の制限時間処理を行ってからステップS1に戻る。[0029] If the determination in step S5 is NO, that is, there is no change in flow rate, step S After carrying out the time limit processing in step 7, the process returns to step S1.

【0030】 ステップS7の継続使用時間処理は図4のフローチャートに示すように、その 最初のステップS7aにおいて、制限時間タイマの計時が現在の流量区分に対す る一定の制限時間の5分前であるか否かを判定する。ステップS7aの判定がN OのときにはステップS7bに進んで制限時間を経過したか否かを判定し、この ステップS7bの判定がNOのときには図3のフローチャートに戻り、以後S1 、S2、S4、S5を経てステップS7a、S7bを繰り返し実行する。[0030] The continuous use time processing in step S7 is as shown in the flowchart of FIG. In the first step S7a, the time limit timer measures the current flow rate. It is determined whether it is 5 minutes before the fixed time limit. The determination in step S7a is N. If the answer is O, the process proceeds to step S7b, where it is determined whether or not the time limit has elapsed. When the determination in step S7b is NO, the process returns to the flowchart of FIG. , S2, S4, and S5, and steps S7a and S7b are repeatedly executed.

【0031】 制限時間の5分前になってステップS7aの判定がYESになると、ステップ S7cに進んでガス漏れ警報器5に対する警告信号を出力し、続くステップS7 dにおいてセンタに対して制限時間の5分前でも流量が変化せずに流れているこ とを知らせる通報を行ってから図3のフローチャートに戻るが、その後再びステ ップS7aの判定を行うと、ステップS7aの判定がNOになってステップS7 bに進むようになり、以後ステップS7bに判定がYESになるまでステップS 1、S2、S4、S5を経てステップS7a、S7bを繰り返し実行する。なお 、ステップS7cの警告信号はリセットされるまで出力し続けるものであり、リ セットは異常がなくなったと判断されたときに行われるものである。[0031] If the determination in step S7a becomes YES five minutes before the time limit, step Proceeding to S7c, a warning signal to the gas leak alarm 5 is output, and the subsequent step S7 d, the flow rate is flowing to the center without changing even 5 minutes before the limit time. After making a report, the process returns to the flowchart in Figure 3. When the determination in step S7a is made, the determination in step S7a becomes NO and the process proceeds to step S7. Then, the process proceeds to step S until the determination becomes YES in step S7b. 1, S2, S4, and S5, and steps S7a and S7b are repeatedly executed. In addition , the warning signal in step S7c continues to be output until it is reset. Setting is performed when it is determined that the abnormality has disappeared.

【0032】 ステップS7bの判定がYESになったらステップS7eに進み、ここで接続 設定器12の設定に基づいてガス漏れ警報器5が接続れているか否かを判定し、 判定がNO、すなわちガス漏れ警報器5が接続されていないときにはステップS 7fに進んで電磁弁4に対して遮断信号を出力してガス流路を遮断してからステ ップS7gで遮断した旨をセンタに通報して図3のフローチャートに戻る。[0032] If the determination in step S7b is YES, proceed to step S7e, and connect here. Determine whether the gas leak alarm 5 is connected based on the setting of the setting device 12, If the determination is NO, that is, the gas leak alarm 5 is not connected, step S Proceed to step 7f, output a cutoff signal to solenoid valve 4 to cut off the gas flow path, and then return to step 7f. In step S7g, the center is notified of the interruption, and the process returns to the flowchart of FIG.

【0033】 一方、ステップS7eの判定がYESのとき、すなわちガス漏れ警報器5が接 続されているときにはステップS7hに進んでフラグFが1であるか否かを判定 し、このステップS7hの判定がNOのときにはステップS7iにおいてRAM 2b中に形成した例えば6時間タイマをスタートさせ、続くステップS7jにお いてフラグFを1にしてから図3のフローチャートに戻る。[0033] On the other hand, when the determination in step S7e is YES, that is, the gas leak alarm 5 is connected. If it is connected, the process advances to step S7h and it is determined whether flag F is 1 or not. However, when the determination in step S7h is NO, the RAM is For example, the 6-hour timer formed in step S7j is started, and the process proceeds to step S7j. After setting the flag F to 1, the process returns to the flowchart of FIG.

【0034】 その後再びステップS7hに戻るが、このときにはステップS7hの判定がY ESとなってステップS7kに進み、ここでステップS7iでスタートしたタイ マがタイムオーバとなったか否かを判定し、このステップS7kの判定がNOの ときには図3のフローチャートに戻る。ステップS7iに於けるタイマのスター トから6時間が経過し、ステップS7kの判定がYESになるとステップS7m に進み、ここでフラグFを0にしから上記ステップS7fに進んで電磁弁4に遮 断信号を出力してから図3のフローチャートに戻る。[0034] After that, the process returns to step S7h again, but at this time, the determination in step S7h is Y. It becomes ES and proceeds to step S7k, where the tie that started in step S7i is If the determination in step S7k is NO, Sometimes, the process returns to the flowchart in FIG. Timer star in step S7i If 6 hours have passed since the start and the determination in step S7k is YES, step S7m The process proceeds to step S7f, where the flag F is set to 0, and the process proceeds to step S7f, where the solenoid valve 4 is shut off. After outputting the disconnection signal, the process returns to the flowchart of FIG.

【0035】 なお、図4のフローチャートの実施例では、ガス漏れ警報器5が接続されてい るときに、制限時間の経過後6時間たっても依然流量変化がないときに自動的に 遮断信号を出力して電磁弁4を駆動してガス流路を遮断するようにしているが、 図5のフローチャートに示すように、ガス漏れ警報器5が接続されているときに は、遮断信号を出力しないようにするようにしてもよい。この場合には、ステッ プS7dの通報を受けたセンタ側からガス消費先に電話をかけて確認をとり、留 守であるような場合にはセンタ側から遮断指令信号を送出することによって電磁 弁4を遮断すればよい。[0035] In addition, in the embodiment of the flowchart in FIG. 4, the gas leak alarm 5 is not connected. automatically when there is still no change in flow rate 6 hours after the time limit has elapsed. Although a cutoff signal is output and the solenoid valve 4 is driven to cut off the gas flow path, As shown in the flowchart of FIG. 5, when the gas leak alarm 5 is connected, may be configured such that the cutoff signal is not output. In this case, step The center that received the notification of step S7d calls the gas consumer, confirms the situation, and then In such a case, the electromagnetic power can be removed by sending a cutoff command signal from the center side. All that is required is to shut off the valve 4.

【0036】 また、上述した実施例では、センタに通報できるシステムを前提にしているが 、センタに通報できないシステムにも本考案を等しく適用できることは言うまで もない。[0036] Furthermore, in the above-mentioned embodiment, a system that can report to the center is assumed. Needless to say, the present invention is equally applicable to systems that cannot report to the center. Nor.

【0037】[0037]

【考案の効果】[Effect of the idea]

以上説明したように本考案によれば、警報器が接続されていない場合だけ、各 流量区分に対してそれぞれ設定した一定時間の間流量に変化がないとき直ちに遮 断信号を出力して電磁弁を遮断し、警報器が接続されている場合には継続使用時 間オーバーによる遮断を行わないようにしているので、不用遮断が起こることが なく、更に安全性に対しても警報器の接続の有無によって遮断を行うかどうかを 決定しているので、警報器からの信号線の断線や、はじめから警報器が接続され ていないシステムに適用した場合でも安全性を損なうことがない。従って、安全 性を確保した上で利便性を向上させることができる。 As explained above, according to the present invention, each alarm is activated only when the alarm is not connected. Immediately shuts off when there is no change in flow rate for a certain period of time set for each flow rate category. Outputs a disconnection signal to shut off the solenoid valve, and if an alarm is connected, if continued use Since the system is designed not to shut down due to overtime, unnecessary shutoffs may occur. Furthermore, for safety reasons, it is necessary to determine whether or not to shut off the alarm depending on whether or not the alarm is connected. Since this has been determined, there is no possibility of disconnection of the signal line from the alarm or if the alarm was not connected from the beginning. Safety will not be compromised even when applied to a system that is not certified. Therefore, safety It is possible to improve convenience while ensuring functionality.

【0038】 また、警報器が接続されている場合において、各流量区分に対してそれぞれ設 定した一定時間の間流量に変化がないときそれから一定時間後に、遮断信号を出 力して電磁弁を遮断するようにすることにより、ユーザの留守を判断できるので 、センタへの通報ができないシステムに本考案を適用した場合にも安全性を損な うことはない。[0038] In addition, if an alarm is connected, the settings for each flow rate category can be set individually. When there is no change in the flow rate for a certain period of time, a cutoff signal is output after a certain period of time. By forcing the solenoid valve to shut off, you can determine whether the user is away. Even if this invention is applied to a system that cannot report to the center, safety will be compromised. There's nothing wrong with that.

【図面の簡単な説明】[Brief explanation of the drawing]

【図1】本考案によるガスメータ装置の基本構成を示す
ブロック図である。
FIG. 1 is a block diagram showing the basic configuration of a gas meter device according to the present invention.

【図2】本考案によるガスメータ装置の一実施例を示す
ブロック図である。
FIG. 2 is a block diagram showing an embodiment of a gas meter device according to the present invention.

【図3】図2中の制御部を構成するCPUが行う仕事を
示すメインフローチャートである。
FIG. 3 is a main flowchart showing the work performed by a CPU constituting the control section in FIG. 2;

【図4】図3中の一部分の詳細を示すフローチャートを
示す図である。
FIG. 4 is a flowchart showing details of a portion of FIG. 3;

【図5】本考案の変形例のフローチャートを示す図であ
る。
FIG. 5 is a diagram showing a flowchart of a modification of the present invention.

【図6】従来のガスメータ装置の一般的な構成を示す図
である。
FIG. 6 is a diagram showing a general configuration of a conventional gas meter device.

【符号の説明】[Explanation of symbols]

1 ガスメータ 11 計量部 2 制御部(CPU) 2d CPU(接続検出手段) 2e CPU(遮断信号出力手段) 3 流量センサ 4 電磁弁 5 ガス漏れ警報器(警報器) 1 Gas meter 11 Measuring part 2 Control unit (CPU) 2d CPU (connection detection means) 2e CPU (cutoff signal output means) 3 Flow rate sensor 4 Solenoid valve 5 Gas leak alarm (alarm)

Claims (2)

【実用新案登録請求の範囲】[Scope of utility model registration request] 【請求項1】 ガスメータの計量部の動作に連動して流
量センサが発生する流量信号に基づいて流量の変化がな
いことを監視し、各流量区分に対してそれぞれ設定した
一定時間の所定時間前まで流量に変化がないとき、各流
量区分に対してそれぞれ設定した一定時間の間流量に変
化がないときガス流路に設けた電磁弁を遮断する制御を
行う制御部を有するガスメータ装置において、前記制御
部が、前記制御部への警報器の接続の有無を検出する接
続検出手段と、該接続検出手段によって警報器の接続さ
れていないことが検出されている場合だけ各流量区分に
対してそれぞれ設定した一定時間の間流量に変化がない
とき直ちに、前記電磁弁を遮断する遮断信号を出力する
遮断信号出力手段とを有することを特徴とするガスメー
タ装置。
[Claim 1] Monitoring whether there is no change in the flow rate based on the flow rate signal generated by the flow rate sensor in conjunction with the operation of the measuring section of the gas meter, and monitoring the flow rate before a predetermined time period set for each flow rate category. In the gas meter device, the gas meter device has a control unit that performs control to shut off a solenoid valve provided in a gas flow path when there is no change in the flow rate for a certain period of time set for each flow rate category, respectively. The control unit includes connection detection means for detecting whether or not an alarm is connected to the control unit, and a connection detection means for each flow rate segment only when the connection detection means detects that the alarm is not connected. A gas meter device comprising a cutoff signal output means for outputting a cutoff signal to cut off the electromagnetic valve immediately when there is no change in the flow rate for a predetermined period of time.
【請求項2】 ガスメータの計量部の動作に連動して流
量センサが発生する流量信号に基づいて流量の変化がな
いことを監視し、各流量区分に対してそれぞれ設定した
一定時間の所定時間前まで流量に変化がないとき、各流
量区分に対してそれぞれ設定した一定時間の間流量に変
化がないときガス流路に設けた電磁弁を遮断する制御を
行う制御部を有するガスメータ装置において、前記制御
部が、前記制御部への警報器の接続の有無を検出する接
続検出手段と、該接続検出手段によって警報器の接続さ
れていないことが検出されている場合各流量区分に対し
てそれぞれ設定した一定時間の間流量に変化がないとき
直ちに、前記接続検出手段によって警報器の接続されて
いることが検出されている場合各流量区分に対してそれ
ぞれ設定した一定時間の間流量に変化がないときそれか
ら一定時間後に、前記電磁弁を遮断する遮断信号を出力
する遮断信号出力手段とを有することを特徴とするガス
メータ装置。
[Claim 2] Monitoring whether there is no change in the flow rate based on the flow rate signal generated by the flow rate sensor in conjunction with the operation of the measuring section of the gas meter, and monitoring the flow rate before a predetermined time period set for each flow rate category. In the gas meter device, the gas meter device has a control unit that performs control to shut off a solenoid valve provided in a gas flow path when there is no change in the flow rate for a certain period of time set for each flow rate category, respectively. The control unit includes a connection detection means for detecting whether or not an alarm is connected to the control unit, and a connection detection means for each flow rate classification when the connection detection means detects that the alarm is not connected. Immediately when there is no change in the flow rate for a certain period of time, the connection detection means detects that the alarm is connected. and a cutoff signal output means for outputting a cutoff signal to cut off the electromagnetic valve after a certain period of time.
JP1555991U 1991-03-18 1991-03-18 Gas meter device Expired - Lifetime JP2522195Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1555991U JP2522195Y2 (en) 1991-03-18 1991-03-18 Gas meter device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1555991U JP2522195Y2 (en) 1991-03-18 1991-03-18 Gas meter device

Publications (2)

Publication Number Publication Date
JPH04111696U true JPH04111696U (en) 1992-09-29
JP2522195Y2 JP2522195Y2 (en) 1997-01-08

Family

ID=31902737

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1555991U Expired - Lifetime JP2522195Y2 (en) 1991-03-18 1991-03-18 Gas meter device

Country Status (1)

Country Link
JP (1) JP2522195Y2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2020173125A (en) * 2019-04-09 2020-10-22 矢崎エナジーシステム株式会社 Gas meter and control method therefor

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6462395B2 (en) * 2015-02-12 2019-01-30 矢崎エナジーシステム株式会社 Gas meter and alarm

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2020173125A (en) * 2019-04-09 2020-10-22 矢崎エナジーシステム株式会社 Gas meter and control method therefor

Also Published As

Publication number Publication date
JP2522195Y2 (en) 1997-01-08

Similar Documents

Publication Publication Date Title
US6000931A (en) Gas safety control system
JP2007225129A (en) Security system
JP4028280B2 (en) Gas meter and its usage time cutoff function cancellation method and usage time cutoff notice method
JP4804955B2 (en) Alarm system
JPH1137459A (en) Gas meter with gas shutoff valve
JPH04111696U (en) gas meter device
JP3620438B2 (en) Gas shut-off device
JP5394017B2 (en) Gas meter with reporting function
JP2007298393A (en) Gas meter and remote monitoring system
JP2004019956A (en) Gas use information system, gas meter and gas leak alarm
JP2713835B2 (en) Shut-off valve abnormality judgment device
JP5856407B2 (en) Flow measurement device with learning function and flow measurement system
JP5085979B2 (en) Gas leak alarm and gas leak alarm system
JP2004279096A (en) Gas meter
JPH0664676B2 (en) Safety device
JP2570338Y2 (en) Gas leak alarm shutoff system and gas shutoff device
JP4966926B2 (en) Alarm system
JPS6086613A (en) Fluid controller
JPH0614744U (en) Fuel cutoff control device
JP2004205333A (en) Gas meter
JP3491742B2 (en) Adapter device for electronic gas meter
JP2676926B2 (en) Fuel cutoff control device
JPS62214499A (en) Gas security system
KR900002378B1 (en) The security device
JP2564783B2 (en) Gas security system

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 19960806