- Publication number
- JPH0366850A JPH0366850A JP20286689A JP20286689A JPH0366850A JP H0366850 A JPH0366850 A JP H0366850A JP 20286689 A JP20286689 A JP 20286689A JP 20286689 A JP20286689 A JP 20286689A JP H0366850 A JPH0366850 A JP H0366850A
- Authority
- JP
- Japan
- Prior art keywords
- reinforcement
- cavity
- column
- concrete
- support bracket
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims abstract description 9
- 239000011178 precast concrete Substances 0.000 title claims description 7
- 230000002787 reinforcement Effects 0.000 claims abstract description 36
- 239000004567 concrete Substances 0.000 claims abstract description 16
- 238000010276 construction Methods 0.000 claims abstract description 12
- 230000003014 reinforcing effect Effects 0.000 abstract 1
- 238000003466 welding Methods 0.000 description 2
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 230000002452 interceptive effect Effects 0.000 description 1
Landscapes
- Rod-Shaped Construction Members (AREA)
Abstract
Description
【発明の詳細な説明】
(産業上の利用分野)
本発明はプレキャストコンクリート造軸組構造における
柱梁の複合方法に係るものである。DETAILED DESCRIPTION OF THE INVENTION (Field of Industrial Application) The present invention relates to a method for combining columns and beams in a precast concrete frame structure.
(従来の技術)
従来のプレキャストコンクリート造軸組構造においては
、PC柱に取合うPC梁のレベルが大幅にくい違う場合
は、PC梁による施工を取り止め、柱も含めた場所打ち
コンクリート工法とするのが一般的であった。(Conventional technology) In conventional precast concrete framework structures, if the level of the PC beams that connect to the PC columns is significantly different, it is necessary to cancel construction using the PC beams and use a cast-in-place concrete construction method that includes the columns. was common.
(発明が解決しようとする課題)
床にレベル差が必要な場合には、前記したように在来の
場所打ちコンクリート工法とするので、PC工法の適用
比率が減少し、同PC工法の利点を十分に発揮できない
場合が生しる。(Problem to be solved by the invention) When a level difference is required for the floor, the conventional cast-in-place concrete construction method is used as described above, so the application ratio of the PC construction method is reduced, and the advantages of the PC construction method are reduced. There may be cases where you are not able to perform to your full potential.
本発明は前記従来技術の有する問題点に鑑みて提案され
たもので、PC梁のレベルが異なる場合、同PC梁の梁
主筋が柱梁接合部内に定着され、床高の違った躯体をP
C工法によって構築しうるプレキャストコンクリート造
における柱梁接合方法を提供する点にある。The present invention was proposed in view of the problems of the prior art, and when the levels of the PC beams are different, the beam main reinforcement of the same PC beam is fixed in the column-beam joint, and the P.S.
The object of the present invention is to provide a method for joining beams and columns in a precast concrete structure that can be constructed using the C method.
(課題を解決するための手段)
前記の目的を達成するため、本発明に係るプレキャスト
コンクリート造における柱梁接合方法は、PC柱の柱頭
に頂面及び側面が開放された空洞部を設けるとともに、
同空洞部の下底面に連接する梁受ブラケットを設け、且
つ前記空洞部における側面開放部に帯筋を露出せしめ、
梁下端筋の梁端面突出端部を切断してなるPC梁を前記
梁受ブラケットに載架したのち、前記空洞部に同空洞部
の側面開放部の帯筋を貫通する定着筋を配設するととも
に、同定着筋を前記PC梁の梁下端部切断部に溶着した
のち、前記空洞部に上部パネルゾーンと一体にコンクリ
ートを打設するように構成されている。(Means for Solving the Problems) In order to achieve the above object, the method for joining beams and columns in precast concrete construction according to the present invention includes providing a hollow portion with an open top surface and side surfaces in the capital of a PC column, and
Providing a beam support bracket connected to the lower bottom surface of the hollow portion, and exposing the straps to the open side portion of the hollow portion,
After a PC beam formed by cutting the protruding end of the beam end face of the beam lower end reinforcement is mounted on the beam support bracket, a fixing reinforcement is provided in the cavity that passes through the tie reinforcement of the open side portion of the cavity. In addition, after the fixing reinforcement is welded to the cut portion of the lower end of the PC beam, concrete is poured into the cavity integrally with the upper panel zone.
(作用)
本発明によれば前記したように、PC柱の柱頭に頂面及
び側面が開放されたPC柱接合用の空洞部を設け、同空
洞部に柱の帯筋を露出せしめるとともに、前記空洞部の
下底面に連設する梁受ブラケットを設け、梁下端筋の梁
端面からの突出端部を切断してなるPC梁を前記梁受ブ
ラケットに載架して、同PC梁の梁下端筋の突出端部を
、前記PC柱における空洞部の側面開口部に露出する柱
の帯筋に干渉しないようにし、しかるのち前記空洞部内
に、同空洞部の側面開口部の露出帯筋を貫通ずる定着筋
を配設して、同定着筋を前記PC粱における梁下端筋の
突出端切断部に溶着し、前記PC粱の梁下端筋と一体化
された定着筋を前記空洞部内に配設し、同空洞部に上部
パネルゾーンと一体にコンクリートを打設することによ
って、前記梁下端筋及びこれに接続された定着筋並に打
設コンクリートを介して、前記PC梁をPC柱の側面に
一体に接合するものである。(Function) According to the present invention, as described above, a hollow part for connecting the PC pillar is provided in the capital of the PC pillar, and the top surface and side surfaces are open, and the ties of the pillar are exposed in the hollow part, and the A beam support bracket is provided continuously on the lower bottom surface of the cavity, and a PC beam formed by cutting the protruding end of the beam bottom reinforcement from the beam end surface is mounted on the beam support bracket, and the beam bottom end of the PC beam is mounted on the beam support bracket. The protruding end of the reinforcement is made not to interfere with the reinforcement of the column exposed at the side opening of the cavity in the PC column, and then penetrated into the cavity through the exposed reinforcement of the side opening of the cavity. Arranging a sliding anchor reinforcement, welding the anchor reinforcement to the protruding end cut portion of the beam lower end reinforcement of the PC wire, and arranging the anchor reinforcement integrated with the beam lower end reinforcement of the PC wire in the hollow portion. By pouring concrete into the hollow part together with the upper panel zone, the PC beam can be placed on the side of the PC column via the beam bottom reinforcement, the anchor reinforcement connected thereto, and the poured concrete. It is to be joined together.
(実施例) 以下本発明を図示の実施例について説明する。(Example) The present invention will be described below with reference to the illustrated embodiments.
いはPC柱で、柱頭部に頂面及び側面に開放された空洞
部(1)を設けるとともに、同空洞部(1)の下底面に
連接する梁受ブラケット(2)を設け、前記空洞部(1
)の側面開放部には柱の帯筋(3)を露出せしめておく
。In other words, it is a PC column, and the column head is provided with a hollow part (1) that is open to the top and side surfaces, and a beam support bracket (2) that is connected to the bottom surface of the hollow part (1) is provided, and the hollow part (1
) The braces (3) of the columns are exposed in the open side parts.
図中(4)は社主筋、(5)は柱頭部に設けた頂部梁受
ブラケットである。In the figure, (4) is the main reinforcement, and (5) is the top beam support bracket installed on the column head.
+Blは前記PC柱(4)頂部の梁(B′)より段差を
以って接合されるPC梁で、梁端面からの梁下端筋(6
)の突出端部が切断されている。+Bl is a PC beam connected with a step from the beam (B') at the top of the PC column (4), and the beam bottom reinforcement (6
) has been cut off.
而して前記PC梁(81を梁受ブラケット(2)上に載
架すると、梁下端筋(6)の突出端部は切断されている
ので、PC柱いの空洞部(1)における側面開口部の帯
筋(3)に干渉しない。これと同時にPC柱(4)の柱
頭部にPC梁(B′)を載架する。When the PC beam (81) is mounted on the beam support bracket (2), since the protruding end of the beam bottom reinforcement (6) has been cut off, the side opening in the hollow part (1) of the PC beam will open. At the same time, the PC beam (B') is mounted on the head of the PC column (4).
この状態で前記空洞部(1)内に帯筋(3)を貫通する
定着筋(7)を挿入し、同定着筋(7)の端部を前記P
C梁囚の梁下端筋(6)の切断端部に(a)で示すよう
にガス圧接、その他機械的継手によって接合したのち、
前記空洞部(1)内に、開部上方のパネルゾーンと一体
にコンクリ−HCI(C’lを打設し、前記PC梁をP
C柱(4)の空洞部(1)に確固と接合し、PC柱□の
柱頭部にパネルゾーンコンクリート(C′)を介してP
C梁(B′)を接合したことと相俟って、レベルに段差
のあるPC梁(Bl(B’lをPC柱(4)に一体に接
合するものである。In this state, insert the fixing bar (7) that passes through the tie bar (3) into the hollow part (1), and connect the end of the fixing bar (7) to the P
After joining the cut end of the beam bottom reinforcement (6) of the C beam frame by gas pressure welding or other mechanical joints as shown in (a),
Inside the cavity (1), concrete HCI (C'l) is poured integrally with the panel zone above the opening, and the PC beam is
It is firmly connected to the hollow part (1) of the C column (4), and the P is connected to the column head of the PC column □ through the panel zone concrete (C').
Together with the joining of the C beam (B'), the PC beam (B'l) with a level difference is integrally joined to the PC column (4).
(発明の効果)
このように本発明によれば、PC柱の柱頭に頂面及び側
面が開放されたPC梁接合用空洞部を設けるとともに、
同空洞部の側面開放部に柱の帯筋を露出せしめ、且つ前
記空洞部の下底面に連設する梁受ブラケットを設け、P
C梁における梁下端筋の梁端面突出端部を切断し、同P
C梁を前記梁受ブラケットに載架したとき、同PC粱の
梁下端筋の突出端部が前記PC柱の空洞部における側面
開放部の帯筋に干渉しないようにする。しかるのち同帯
筋を貫通する定着筋を前記空洞部に配設し、同定着筋を
前記PC梁の梁下端筋を溶着したことによって、同PC
梁の梁下端筋を前記PC柱の空洞部内にセットし、この
状態で前記空洞部にコンクリートを打設することによっ
て、前記PC梁を前記空洞部を介してPC柱の柱頭側面
に接合する。一方、前記上方パネルゾーンに打設された
コンクリートを介して柱頭部にPC柱を一体に接合する
ことと相俟って、レベル差のくい違ったPC梁を現場打
ちコンクリート工法によらずPC工法によってPC柱に
架設することができ、現場施工を簡略化し、省力化と工
程の短縮を図り、工費を節減しうるちのである。(Effects of the Invention) As described above, according to the present invention, a hollow portion for connecting a PC beam with an open top surface and side surfaces is provided in the capital of a PC column, and
The reinforcement of the column is exposed in the open side part of the hollow part, and a beam support bracket is provided continuously on the lower bottom surface of the hollow part,
Cut the protruding end of the beam end surface of the beam bottom reinforcement in beam C, and
When the C-beam is mounted on the beam support bracket, the protruding end of the beam lower end reinforcement of the PC beam is prevented from interfering with the tie reinforcement of the side opening in the hollow part of the PC column. Thereafter, a fixing bar passing through the same band reinforcement was placed in the hollow part, and the fixing bar was welded to the lower end bar of the PC beam, thereby making the PC beam
The beam bottom reinforcement of the beam is set in the hollow part of the PC column, and in this state, concrete is poured into the hollow part, thereby joining the PC beam to the column capital side surface of the PC column via the hollow part. On the other hand, in conjunction with integrally joining the PC column to the column head via the concrete poured in the upper panel zone, it is possible to use the PC construction method instead of using the cast-in-place concrete construction method to construct PC beams with different levels. This allows for installation on PC columns, which simplifies on-site construction, saves labor and shortens the process, and reduces construction costs.
第1図は本発明の方法によって施工されたプレキャスト
コンクリート造における柱梁接合部を示す縦断面図、第
2図は第1図の矢視■−■図、第3図はPC柱の斜視図
である。
□□□・・・PC柱、 (Bl・・・PC
梁、(B′)・・・柱頭部のPC梁、
(0・・・空洞部コンクリート、
(C′)・・・パネルゾーンコンクリート、(1)・・
・空洞部、 (2)・・・梁受ブラケット、(
3)・・・帯筋、 (6)・・・梁下端筋、
(7)・・・定着筋、
(a)・・・梁下梁筋と定着筋との接合部。Fig. 1 is a longitudinal cross-sectional view showing a column-beam joint in a precast concrete structure constructed by the method of the present invention, Fig. 2 is a view taken along arrows ■-■ in Fig. 1, and Fig. 3 is a perspective view of a PC column. It is. □□□・・・PC pillar, (BL・・・PC
Beam, (B')...PC beam at column head, (0...Cavity concrete, (C')...Panel zone concrete, (1)...
・Cavity part, (2)...beam support bracket, (
3)...Stirrup, (6)...Beam bottom reinforcement,
(7)...Fixed reinforcement, (a)...Joint part between the lower beam reinforcement and the anchored reinforcement.
Claims (1)
るとともに、同空洞部の下底面に連接する梁受ブラケッ
トを設け、且つ前記空洞部における側面開放部に帯筋を
露出せしめ、梁下端筋の梁端面突出端部を切断してなる
PC梁を前記梁受ブラケットに載架したのち、前記空洞
部に同空洞部の側面開放部の帯筋を貫通する定着筋を配
設するとともに、同定着筋を前記PC梁の梁下端筋切断
部に溶着したのち、前記空洞部に上部パネルゾーンと一
体にコンクリートを打設することを特徴とするプレキャ
ストコンクリート造における柱梁接合方法。A hollow section with open top and side surfaces is provided in the capital of the PC column, a beam support bracket is provided connected to the bottom surface of the hollow section, and a tie bar is exposed at the open side section of the hollow section. After a PC beam formed by cutting the protruding end of the beam end face of the lower end reinforcement is mounted on the beam support bracket, a fixing reinforcement is provided in the hollow portion to pass through the tie reinforcement of the open side portion of the hollow portion, and A method for joining columns and beams in precast concrete construction, characterized in that the fixing reinforcement is welded to the cut portion of the beam lower end reinforcement of the PC beam, and then concrete is poured into the cavity integrally with the upper panel zone.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP20286689A JPH0366850A (en) | 1989-08-07 | 1989-08-07 | Colum/beam joining method in precast concrete structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP20286689A JPH0366850A (en) | 1989-08-07 | 1989-08-07 | Colum/beam joining method in precast concrete structure |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH0366850A true JPH0366850A (en) | 1991-03-22 |
Family
ID=16464496
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP20286689A Pending JPH0366850A (en) | 1989-08-07 | 1989-08-07 | Colum/beam joining method in precast concrete structure |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH0366850A (en) |
-
1989
- 1989-08-07 JP JP20286689A patent/JPH0366850A/en active Pending
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2001342679A (en) | CONNECTING METHOD FOR PCa BEAM MEMBER AT COLUMN/BEAM JUNCTION AND PCa BEAM MEMBER FOR IT | |
JPH0366850A (en) | Colum/beam joining method in precast concrete structure | |
JP2698545B2 (en) | Connection method between precast concrete columns and steel beams | |
JPH02300439A (en) | Prefabricating method | |
JP3284391B2 (en) | Reinforced concrete frame and construction method | |
JPH0366849A (en) | Colum/beam joining method in precast concrete structure | |
JP2910551B2 (en) | Lap joint method of main reinforcement of SRC column | |
JP2506294Y2 (en) | Structure of column / beam connection | |
JP2592224Y2 (en) | Structure of joint between RC beam and steel structure | |
JPH05302361A (en) | Joining structure between column and beam | |
JP2973009B2 (en) | Connection method between synthetic steel beams and steel bars or steel reinforced concrete columns | |
JPS5846970B2 (en) | Connection method between RC columns, Pca girders in the column direction, and cast-in-place girders in the span direction | |
JPH01137032A (en) | Method of lap joint construction of main reinforcement in post and beam joining section | |
JPH084107A (en) | Connecting method for column/beam connection | |
JPH02236328A (en) | Construction method for super-highrice building | |
JP2516820B2 (en) | Frame of SRC structure | |
JPH05231002A (en) | Reinforcing steel preassembled body with form and reinforcing steel preassembly construction method with form | |
JPH0673788A (en) | Junction of pc beam in joint of pillar and beam | |
JPH04237735A (en) | Constructing method for pillar and beam of building | |
JPH04368529A (en) | Joint structure of column and beam | |
JPS58204246A (en) | Construction of reinforced concrete structure | |
JPH0366852A (en) | Construction method for complex structure of precast reinforced concrete column and steel beam | |
JPH0688393A (en) | Flat plate construction | |
JPH09177239A (en) | Precast reinforced concrete beam and its framing method | |
JPH02132236A (en) | Column and beam joint section unit |