JPH0355702Y2 - - Google Patents

Info

Publication number
JPH0355702Y2
JPH0355702Y2 JP7691185U JP7691185U JPH0355702Y2 JP H0355702 Y2 JPH0355702 Y2 JP H0355702Y2 JP 7691185 U JP7691185 U JP 7691185U JP 7691185 U JP7691185 U JP 7691185U JP H0355702 Y2 JPH0355702 Y2 JP H0355702Y2
Authority
JP
Japan
Prior art keywords
floor
bolt
flange
floor plate
bolts
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP7691185U
Other languages
Japanese (ja)
Other versions
JPS61192033U (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP7691185U priority Critical patent/JPH0355702Y2/ja
Priority to US06/864,851 priority patent/US4736555A/en
Publication of JPS61192033U publication Critical patent/JPS61192033U/ja
Application granted granted Critical
Publication of JPH0355702Y2 publication Critical patent/JPH0355702Y2/ja
Expired legal-status Critical Current

Links

Landscapes

  • Floor Finish (AREA)

Description

【考案の詳細な説明】 (産業上の利用分野) 本考案は組立式床材、特に、複数枚の床板を同
一平面上に密接して連結・固定し仮床を構成し得
る組立式床材に関する。
[Detailed description of the invention] (Field of industrial application) The present invention is a prefabricated flooring material, in particular a prefabricated flooring material that can form a temporary floor by closely connecting and fixing multiple floorboards on the same plane. Regarding.

(従来の技術) オフイスオートメーシヨンの進歩に伴いオフイ
ス内に多数の事務機器や通信機器が設置される機
会が増大している。そのために、床上に配線や配
管が敷設されなばならない。この敷設作業をより
簡便にするために床上に適度のスペースをもつて
仮床が架設されることが行われている。このよう
な仮床は、従来、位置決め用シートなどでなるラ
ンナーを支柱と組み合せて床上に配置し、この支
柱に床板を置き、各床板を固定用フアスナーによ
り固定するように構成されている。このような従
来の組立式床材によれば、ランナーの製品公差や
施工の優劣により支柱の位置が所期の床上位置か
らずれる場合があるため、設計上の仕上がり寸法
どおりに納まらず組立が円滑になされ得ない。
(Prior Art) With the advancement of office automation, the chances of installing a large number of office equipment and communication equipment in an office are increasing. For this purpose, wiring and piping must be laid on the floor. In order to make this installation work easier, a temporary floor is constructed with a suitable space above the floor. Conventionally, such a temporary floor is constructed such that a runner made of a positioning sheet or the like is combined with pillars and placed on the floor, floorboards are placed on the pillars, and each floorboard is fixed with fixing fasteners. With such conventional prefabricated flooring, the position of the pillars may be shifted from the intended upper level of the floor due to the product tolerances of the runners or the quality of the construction. It cannot be done.

このため、床板を、床に対してねじ固定された
ボルトの頂部に係合させ、ボルトの回転により床
板の高さ調整可能に固定することが考えられてい
る。しかしながら、ボルトにより床板を固定する
場合には、床板上の歩行等による振動によりボル
トが回転し、床板の高さが変化するおそれがあ
る。このような欠点を解消するために、床板の高
さ調整後にボルトのねじ部に接着剤を充填して固
定する方法が考えられている。この方法では床板
の破損等により床板を取換える場合には、板厚の
相違による高さ変化の調整ができず、床板を高さ
の不揃いのない同一平面に構成することができな
い。
For this reason, it has been considered to engage the tops of bolts that are screwed to the floor to fix the floorboard so that the height of the floorboard can be adjusted by rotating the bolts. However, when fixing the floorboards with bolts, there is a risk that the bolts will rotate due to vibrations caused by walking on the floorboards, and the height of the floorboards will change. In order to eliminate such drawbacks, a method has been considered in which the threaded portions of the bolts are filled with adhesive and fixed after the height of the floorboard is adjusted. With this method, when replacing the floorboards due to damage or the like, it is not possible to adjust height changes due to differences in board thickness, and it is not possible to construct the floorboards on the same plane without irregularities in height.

また、床板の高さ調整後にボルトを側方からロ
ツクボルトにて締め付け固定する方法も考えられ
るが、床板の振動によりロツクボルト自体が弛緩
するおそれがあり、そのため、確実にボルトを固
定することができない。
Another possible method is to tighten and fix the bolts from the sides with lock bolts after adjusting the height of the floor plate, but there is a risk that the lock bolts themselves may loosen due to the vibration of the floor plate, so the bolts cannot be securely fixed.

(考案が解決しようとする問題点) 本考案は上述の問題点を解決するものであり、
その目的とするところは、床板を支持するボルト
を確実に固定することができる組立式床材を提供
するにある。本考案の他の目的は、床板の高さ調
整が常時容易にできる組立式床材を提供するにあ
る。
(Problems to be solved by the invention) This invention solves the above-mentioned problems.
The purpose is to provide a prefabricated flooring material that can securely fix the bolts that support the floorboards. Another object of the present invention is to provide a prefabricated flooring material that allows the height of the floorboard to be easily adjusted at any time.

(問題点を解決するための手段) 本考案の組立式床材は、床上に仮床を形成する
床板と;該床板の少なくとも各コーナーに設けら
れた係合穴と;床に固設されたナツト部材に螺合
するつば付ボルトと;該ボルトのつば部と前記ナ
ツト部材との間に外嵌された押ばねと、を具備
し、前記床板の係合穴が該つば付ボルトのつば部
上側に係合してなり、そのことにより上記目的が
達成される。
(Means for Solving the Problems) The prefabricated flooring of the present invention includes: a floor plate forming a temporary floor on the floor; an engaging hole provided at least at each corner of the floor plate; a bolt with a flange that is screwed into the nut member; and a push spring fitted externally between the flange of the bolt and the nut member, and the engagement hole of the floor plate is connected to the flange of the bolt with the flange. The above object is achieved by engaging the upper side.

(実施例) 以下に本考案を実施例について述べる。(Example) The present invention will be described below with reference to embodiments.

本考案の組立式床材は、第1図に示すように、
複数枚の床板1と、この床板1同士を密接して床
101上に支持するための支持体2とを有する。
該支持体2は、第2図、第3図a及びbに示すよ
うに、ナツト部材21と、これに係合するつば付
きボルト22と、このナツト部材21のつば部2
11とつば付ボルト22のつば部221との間に
外嵌された押しばね23とを有する。ナツト部材
21は床101上に固設されている。床板1のコ
ーナーには係合穴10が設けられ、つば部221
上に載置される形で係合穴10を介して、つば付
きボルト22の頭部と係合している。ボルト22
の頂端部には、ねじ溝222が形成されており、
ボルト22を回転操作することによりボルト22
自体がナツト部材21に対して移動し、床101
に対するつば部221の高さ位置が変更される。
押しばね23は、つば部221を上方へ押圧する
ことによりボルト22全体を上方へ付勢し床板1
の振動等を吸収している。その結果ボルト22の
弛緩が防止される。
As shown in Figure 1, the prefabricated flooring of the present invention has the following features:
It has a plurality of floorboards 1 and a support body 2 for supporting the floorboards 1 in close contact with each other on the floor 101.
As shown in FIGS. 2 and 3a and 3b, the support body 2 includes a nut member 21, a flanged bolt 22 that engages with the nut member 21, and a collar portion 2 of the nut member 21.
11 and a flange portion 221 of the flange bolt 22. The nut member 21 is fixed on the floor 101. An engagement hole 10 is provided at the corner of the floor plate 1, and a collar portion 221
It is placed on top and engaged with the head of the flanged bolt 22 through the engagement hole 10. bolt 22
A thread groove 222 is formed at the top end of the
By rotating the bolt 22, the bolt 22
itself moves relative to the nut member 21, and the floor 101
The height position of the flange portion 221 relative to the flange portion 221 is changed.
The push spring 23 presses the collar portion 221 upward, thereby urging the bolt 22 as a whole upward, so that the floor plate 1
absorbs vibrations, etc. As a result, loosening of the bolt 22 is prevented.

押しばね23は、強度、耐久性等から金属性の
ものが望ましい。また、例えば、ピアノ線を用い
た場合には、その径は、0.5〜2.0mmとすることが
高さ調整の容易さ、固定の確実さから望ましい。
The push spring 23 is preferably made of metal in terms of strength, durability, and the like. For example, when piano wire is used, it is desirable that its diameter be 0.5 to 2.0 mm for ease of height adjustment and secure fixation.

床板1の係合穴10をボルト22のつば部22
1上側に嵌合させた状態にてボルト22を回転さ
せることにより床板1を上下動させて床面の不陸
を吸収する。このようにして各床板1は同一平面
上に密接して連結配置され、仮床100を構成す
る。この仮床100はこのように本来の床101
から適度のスペースをもつて床101上に架設さ
れる。
Connect the engagement hole 10 of the floor plate 1 to the collar 22 of the bolt 22.
By rotating the bolt 22 while fitted on the upper side of the floor plate 1, the floor plate 1 is moved up and down to absorb unevenness of the floor surface. In this way, each floorboard 1 is closely connected and arranged on the same plane to form a temporary floor 100. This temporary floor 100 is like the original floor 101.
It is constructed on the floor 101 with a suitable space.

(考案の効果) 本考案の組立式床材は、このようにボルトのつ
ば部と床上に固設されたナツト部材との間に押ば
ねを外嵌して、常時ボルトを上方へ押圧している
ために、ボルトは確実に回り止めされる。従つて
床板の振動等によつてボルトが回転するおそれが
なく、仮床は常に一定の高さとされる。ボルトの
回転操作は容易に行えるため、床板の高さ調整が
常時簡単に行える。
(Effects of the invention) The prefabricated flooring of the present invention has a compression spring fitted between the collar of the bolt and the nut member fixed on the floor to constantly press the bolt upward. This ensures that the bolt does not turn. Therefore, there is no risk of the bolts rotating due to vibrations of the floorboard, and the temporary floor is always kept at a constant height. Since the bolts can be easily rotated, the height of the floorboard can be easily adjusted at any time.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は、本考案の組立式床材を用いて形成さ
れる仮床100の一例を示す部分斜視図、第2図
は支持体2の一例を示す斜視図、第3図a及びb
は床板1と支持体2との係合状態の一例を示す平
面図及び断面図である。 1……床板、2……支持体、21……ナツト部
材、22……ボルト、23……押ばね、221…
…つば部、101……床。
Fig. 1 is a partial perspective view showing an example of a temporary floor 100 formed using the prefabricated flooring material of the present invention, Fig. 2 is a perspective view showing an example of a support 2, and Figs. 3 a and b.
1 is a plan view and a sectional view showing an example of an engaged state between a floor plate 1 and a support body 2. FIG. DESCRIPTION OF SYMBOLS 1... Floor plate, 2... Support body, 21... Nut member, 22... Bolt, 23... Pressing spring, 221...
...Brim, 101...Floor.

Claims (1)

【実用新案登録請求の範囲】[Scope of utility model registration request] 床上に仮床を形成する床板と;該床板の少なく
とも各コーナーに設けられた係合穴と;床に固設
されたナツト部材に螺合するつば付ボルトと;該
ボルトのつば部と前記ナツト部材との間に外嵌さ
れた押ばねと、を具備し、前記床板の係合穴が該
つば付ボルトのつば部上側に係合した組立式床
材。
A floor plate that forms a temporary floor on the floor; an engagement hole provided at least at each corner of the floor plate; a bolt with a flange that screws into a nut member fixed to the floor; a flange of the bolt and the nut. and a push spring externally fitted between the members, and the engagement hole of the floor plate engages with the upper side of the flange of the flange bolt.
JP7691185U 1985-05-22 1985-05-22 Expired JPH0355702Y2 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
JP7691185U JPH0355702Y2 (en) 1985-05-22 1985-05-22
US06/864,851 US4736555A (en) 1985-05-22 1986-05-20 Free access type floor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP7691185U JPH0355702Y2 (en) 1985-05-22 1985-05-22

Publications (2)

Publication Number Publication Date
JPS61192033U JPS61192033U (en) 1986-11-29
JPH0355702Y2 true JPH0355702Y2 (en) 1991-12-12

Family

ID=30619487

Family Applications (1)

Application Number Title Priority Date Filing Date
JP7691185U Expired JPH0355702Y2 (en) 1985-05-22 1985-05-22

Country Status (1)

Country Link
JP (1) JPH0355702Y2 (en)

Also Published As

Publication number Publication date
JPS61192033U (en) 1986-11-29

Similar Documents

Publication Publication Date Title
US4736555A (en) Free access type floor
JP2001049855A (en) Floor panel-bearing leg device
JPH0355702Y2 (en)
JPH0243142Y2 (en)
JPH0334441Y2 (en)
JPH0546418B2 (en)
JPH074264Y2 (en) Floor bundle structure
JP2535056B2 (en) Floor panel fixing device
JP4046432B2 (en) Floor panel support leg unit
JPH0334442Y2 (en)
JPH0131693Y2 (en)
JP3493325B2 (en) Panel corner connecting device for floor panel supporting leg device
KR200264104Y1 (en) Apparatus for supporting floor plate
JP4684491B2 (en) Bunch of floor panels
JPS6224667Y2 (en)
JPS6362536U (en)
JPH083594Y2 (en) Leveling bracket for pouring concrete on slopes
JPH0740026Y2 (en) Double floor support
JPS6316763Y2 (en)
JPS6126518Y2 (en)
JPH0532586Y2 (en)
JPS588825Y2 (en) flooring equipment
JPH0227071Y2 (en)
JP2763918B2 (en) Floorboard panel board support legs
JPH1054131A (en) Floor panel base