JPH0343540A JP17882089A JP17882089A JPH0343540A JP H0343540 A JPH0343540 A JP H0343540A JP 17882089 A JP17882089 A JP 17882089A JP 17882089 A JP17882089 A JP 17882089A JP H0343540 A JPH0343540 A JP H0343540A
Authority
JP
Japan
Prior art keywords
adhesive
hole
filling
insertion hole
filling adhesive
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP17882089A
Other languages
Japanese (ja)
Inventor
Masataka Oka
岡 正孝
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to JP17882089A priority Critical patent/JPH0343540A/en
Publication of JPH0343540A publication Critical patent/JPH0343540A/en
Pending legal-status Critical Current

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)
  • Standing Axle, Rod, Or Tube Structures Coupled By Welding, Adhesion, Or Deposition (AREA)
  • Adhesives Or Adhesive Processes (AREA)

Abstract

PURPOSE:To obtain a predetermined adhesive strength by drilling a hole in concrete and filling this hole with an inorganic water hardening adhesive fixedly embedding a bar steel. CONSTITUTION:A bar steel insertion hole is drilled in a predetermined position of a concrete surface 6 by using a drill. Cutting chips in the inside of the insertion hole are removed, and an internal wall is placed in a wet condition by washing with water. Next, an adhesive material 3, having expansibility of inorganic system water hard mold, is injected by an injection gun into the hole filled with the material 3. Then a steel bar 4 is fixedly embedded in the insertion hole. In this way, a method of construction of good execution workability can be obtained even in a wet condition.

Description

【発明の詳細な説明】 従来の穿孔による棒鋼の埋込固定工法には、エポキシ樹
脂系の接着材が主として採用されているが、以下述べる
ような問題点が指摘されていた。
DETAILED DESCRIPTION OF THE INVENTION In the conventional drilling method for embedding and fixing steel bars, epoxy resin-based adhesives have been mainly used, but the following problems have been pointed out.

(1)  エポキシ樹脂系の充填接着材は、夏期又は、
l孔当りの注入量が多いと硬化時に発熱し品質が劣化し
、所定の接着強度かえられない。
(1) Epoxy resin-based filling adhesives are used during summer or
If the injection amount per hole is too large, heat will be generated during curing, the quality will deteriorate, and it will not be possible to achieve the desired adhesive strength.

(2)  コンクリートが湿潤状態であると、エポキシ
系樹脂は接着性能が低下する。
(2) When concrete is wet, the adhesive performance of epoxy resin decreases.

(3)エポキシ樹脂系接着材は、60’C以上に上昇す
ると強度が低下し、かつ可燃性である。
(3) Epoxy resin adhesives lose their strength when the temperature rises above 60'C and are flammable.

(4)無醸セメント系の接着材に比べて非常に高価であ
る。
(4) It is much more expensive than non-breathing cement-based adhesives.

(5)二液混合後の可使時間が短い為に施工性に劣る。(5) Workability is poor due to short pot life after mixing the two components.

以上の点を考慮して、安価で、耐火性に優れ、かつa層
状態でも施工性の良い工法、及び材料が開発出来ないも
のかと言う声が現場では大であった。
Taking the above points into consideration, there were many voices in the field asking whether it would be possible to develop a construction method and material that is inexpensive, has excellent fire resistance, and has good workability even in the A-layer state.

本工法は、その要望に答えて開発した工法である。This construction method was developed in response to this request.

以下その工法について順を追って説明する。The construction method will be explained step by step below.

O埋込固定するコンクリート面6の所定の位置に、コン
クリートドリルを用いて棒鋼挿入孔1の穿孔を行う。
A concrete drill is used to drill a steel bar insertion hole 1 at a predetermined position on the concrete surface 6 where O is to be embedded and fixed.

■ 棒鋼挿入孔lの内部の削り屑を除去し、水洗いを行
うと同時に孔内壁を湿潤状態にする。
■ Remove the shavings inside the steel bar insertion hole l, wash it with water, and at the same time keep the hole inner wall moist.

■ 注入ガン先端パイプ2を棒鋼挿入孔lの奥部に挿入
し、先端部から無機系水硬型の膨張性を有する接着材を
3札内に注入充填する。
(2) Insert the injection gun tip pipe 2 into the deep part of the steel bar insertion hole 1, and inject and fill the inorganic hydraulic type expandable adhesive into the three tags from the tip.

■ 棒鋼4を挿入孔tに貫入し固定する。■ Insert the steel bar 4 into the insertion hole t and fix it.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は、棒鋼挿入孔の穿孔完了断面図である。 第2図は、棒鋼挿入孔に接着材を注入充填している途中
の断面図である。 第3図は、注入材が充填された挿入孔に棒鋼を貫入固定
した断面図である。 1は 棒鋼の挿入孔である 2は 充填接着材の注入ガンの先端パイプである 3は 孔内に充填された注入接着材である4は 挿入孔
内に貫入固定された棒鋼である5は コンクリート躯体
である 6は 棒鋼を埋込固定するコンクリートの表面である 第 図 第 図
FIG. 1 is a sectional view of the completed steel bar insertion hole. FIG. 2 is a cross-sectional view of the adhesive being injected and filled into the steel bar insertion hole. FIG. 3 is a sectional view of a steel bar inserted and fixed into an insertion hole filled with injection material. 1 is the insertion hole for the steel bar. 2 is the tip pipe of the injection gun for filling adhesive. 3 is the injection adhesive filled in the hole. 4 is the steel bar inserted into the insertion hole and fixed. 5 is the concrete. Figure 6, which is the frame, is the concrete surface where the steel bars are embedded and fixed.

Claims (4)

【特許請求の範囲】[Claims] (1)コンクリートに穿孔する工程、接着材を充填する
工程、及び棒状の鋼材を挿入設置する工程よりなる特許
請求範囲第1項記載の無機系水硬型の膨張性を有する充
填接着材を用いた棒鋼の埋込固定工法
(1) Using the inorganic hydraulic type expandable filling adhesive described in claim 1, which comprises the steps of drilling a hole in concrete, filling with adhesive, and inserting and installing a rod-shaped steel material. Embedded fixing method for steel bars
(2)充填接着材がセメント系で、水硬型で、かつ膨張
性を有する特許請求範囲第1項記載の無機系水硬型の膨
張性を有する充填接着材を用いた棒鋼の埋込固定工法
(2) Embedding and fixing of a steel bar using an inorganic hydraulic type expandable filling adhesive as set forth in claim 1, wherein the filling adhesive is cement-based, hydraulic type, and expandable. construction method
(3)充填接着材が孔内で適正な膨張固結を有すること
によって、棒鋼の引き抜き力に抵抗する機能を有する特
許請求範囲第1項記載の無機系水硬型の膨張性を有する
充填接着材を用いた棒鋼の埋込固定工法
(3) An inorganic hydraulic type expandable filling adhesive according to claim 1, which has the function of resisting the pull-out force of the steel bar by having the filling adhesive properly expand and solidify in the hole. Embedded fixing method for steel bars using
(4)充填接着材が膨張性の極めて零に近い殆ど無収縮
性の接着材を用いた特許請求範囲第1項記載の無機系水
硬型の膨張性を有する充填接着材を用いた棒鋼の埋込固
定工法
(4) A steel bar using an inorganic hydraulic type filler adhesive having expandability as described in claim 1, in which the filler adhesive is an expandable adhesive with almost no shrinkage, which is close to zero. Embedded fixing method
JP17882089A 1989-07-10 1989-07-10 Method of construction for fixedly embedding bar steel using filling adhesive having expansibility of inorganic system water mold Pending JPH0343540A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP17882089A JPH0343540A (en) 1989-07-10 1989-07-10 Method of construction for fixedly embedding bar steel using filling adhesive having expansibility of inorganic system water mold

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP17882089A JPH0343540A (en) 1989-07-10 1989-07-10 Method of construction for fixedly embedding bar steel using filling adhesive having expansibility of inorganic system water mold

Publications (1)

Publication Number Publication Date
JPH0343540A true JPH0343540A (en) 1991-02-25

Family

ID=16055234

Family Applications (1)

Application Number Title Priority Date Filing Date
JP17882089A Pending JPH0343540A (en) 1989-07-10 1989-07-10 Method of construction for fixedly embedding bar steel using filling adhesive having expansibility of inorganic system water mold

Country Status (1)

Country Link
JP (1) JPH0343540A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006249908A (en) * 2004-08-11 2006-09-21 Hamashima Bussan:Kk Cone-shaped hole cap and method of filling in cone-shaped hole
JP2010013858A (en) * 2008-07-03 2010-01-21 Kajima Corp Anchoring method for shear reinforcement material
JP2015040407A (en) * 2013-08-21 2015-03-02 住友大阪セメント株式会社 Post-installed anchor construction method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006249908A (en) * 2004-08-11 2006-09-21 Hamashima Bussan:Kk Cone-shaped hole cap and method of filling in cone-shaped hole
JP2010013858A (en) * 2008-07-03 2010-01-21 Kajima Corp Anchoring method for shear reinforcement material
JP2015040407A (en) * 2013-08-21 2015-03-02 住友大阪セメント株式会社 Post-installed anchor construction method

Similar Documents

Publication Publication Date Title
JP3604144B2 (en) Connector rod with high thermal insulation, its manufacturing method and application to composite wall with high thermal insulation
JPH0343540A (en) Method of construction for fixedly embedding bar steel using filling adhesive having expansibility of inorganic system water mold
JP6921536B2 (en) Construction method of anchors to be installed in existing masonry and post-construction anchors
DK431789A (en) PROCEDURE FOR THE PREPARATION OF A PLASTIC BUILDING
WO1992020901A1 (en) Injection means
RU2053336C1 (en) Fastening device
CN212249261U (en) Anchoring structure for embedded steel bar
CN114482296A (en) Novel pre-buried formula heat preservation nail
US4198793A (en) Method of planting rod-shaped member in foundation
JP5950724B2 (en) Anchor construction method
JPS6233447B2 (en)
JPS61196038A (en) Method for mounting anchor member to concrete product
JPS5820850A (en) Embedding of anchor bolt
KR20050031075A (en) Method reinforcing the ground with armatures having multiple projections in surface
JPS63315747A (en) Method for fixing adhesive systempost-execution anchor
FR2435625A1 (en) Embedded resin bonded ferrule for holding down bolt - is set in drilled hole and has smooth annular head and shaft with contrary spiral grooves
JPS5826165A (en) Repairing of water leakage of concrete structure
JPH06306957A (en) Method of installation construction of anchor reinforcement
JP2505815Y2 (en) Post-installation anchor device
KR200384038Y1 (en) Structure reinforced the ground with armatures having multiple projections in surface
JPH0412933Y2 (en)
JPH0796838B2 (en) FRP tension material tension fixing method in prestressed concrete structure
JPS61151399A (en) Fixing of adhesive anchor using improved diamond core
JPS6117115Y2 (en)
JPH05105555A (en) Method for improving freeze-resistance of inorganic building material