JPH0336403A - Automatic control of number of boilers including blow instruction operation - Google Patents

Automatic control of number of boilers including blow instruction operation

Info

Publication number
JPH0336403A
JPH0336403A JP17070589A JP17070589A JPH0336403A JP H0336403 A JPH0336403 A JP H0336403A JP 17070589 A JP17070589 A JP 17070589A JP 17070589 A JP17070589 A JP 17070589A JP H0336403 A JPH0336403 A JP H0336403A
Authority
JP
Japan
Prior art keywords
blow
boiler
boilers
steam
time
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP17070589A
Other languages
Japanese (ja)
Inventor
Toshihiro Kayahara
敏広 茅原
Yasuhiro Miyagawa
宮川 泰寛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Miura Co Ltd
Original Assignee
Miura Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Miura Co Ltd filed Critical Miura Co Ltd
Priority to JP17070589A priority Critical patent/JPH0336403A/en
Publication of JPH0336403A publication Critical patent/JPH0336403A/en
Pending legal-status Critical Current

Links

Landscapes

  • Control Of Steam Boilers And Waste-Gas Boilers (AREA)

Abstract

PURPOSE:To supply stably a required amount of steam without hindrance in copying with load by issuing in due order a blow instruction signal only to a number of boilers which have no effect on a required amount of steam supply even if many boilers reach the time of blow simultaneously. CONSTITUTION:An electrically powered valve 8 for whole blow which is connected to the bottom section of a boiler controls the discharge of boiler water. In order to detect the time of whole blow an electric conductivity sensor 9 is provided in the boiler at its lower section and it judges whether or not the boiler water is too much thickened, or the combustion times are summed up and the sum is compared with the set value to judge the time of whole blow. A soot blow pipe 10 which has many injection holes is installed to face against the heat transfer face of the boiler, and it is connected by an electrically powered valve 11 for soot blowing which controls the supply of a cleaning medium for high pressure water, steam, etc. In order to detect the time of soot blowing the temperature of the exhaust gas is measured by a temperature sensor 13 that is provided in the flue in order to judge the degree of soot attachment. In carrying out the blow operation blow instruction signal is issued to one or a limited number of boilers in due order so that a required amount of steam supply is not affected.

Description

【発明の詳細な説明】 〔産業上の利用分野〕 この発明は、ボイラーの多缶設置システムにおける自動
台数制御方法に関するもので、全ブロー及びスートブロ
ーを自動的に行うのに好適なブロー指示操作を含むもの
である。
[Detailed Description of the Invention] [Field of Industrial Application] The present invention relates to a method for automatically controlling the number of boilers in a multi-boiler installation system. It includes.

〔従来の技術〕[Conventional technology]

一般に、ボイラーを長時間運転すると、缶水が濃縮して
キャリーオーバーが生じたり、缶底にスラッジなどの堆
積物が溜まってくるので、定期的に缶水を全て排出する
全ブロー操作を行うようにしている。また、ボイラー運
転に伴って、伝熱面に煤が付着、堆積して熱伝達を阻害
し、ボイラー効率が低下してくるので、伝熱面に付着し
た煤を高圧水或いは蒸気などで洗い流すスートブロー操
作も適宜に行う必要がある。
Generally, when a boiler is operated for a long time, the canned water becomes concentrated and carryover occurs, and deposits such as sludge accumulate at the bottom of the can, so it is recommended to periodically perform a full blow operation to drain all the canned water. I have to. Additionally, as the boiler operates, soot adheres to and accumulates on the heat transfer surface, obstructing heat transfer and reducing boiler efficiency. It is also necessary to perform the operations appropriately.

〔発明が解決しようとする課題〕[Problem to be solved by the invention]

而るに、これらのブロー作業は、ボイラーの運転管理者
が手動で行うのが通例で、煩雑で時間がかかるため、ボ
イラーの保守管理を複雑なものにしている。特に、ボイ
ラーを複数台設置した多缶設置システムでは作業量も多
くなり、ボイラー運転管理者にとってかなりの負担にな
っている。
However, these blowing operations are usually performed manually by a boiler operation manager, which is cumbersome and time-consuming, making boiler maintenance management complicated. In particular, in a multi-can installation system where multiple boilers are installed, the amount of work increases, placing a considerable burden on the boiler operation manager.

従って、これらのブロー作業は自動化するのが望ましい
が、ブロー作業を行う際にはボイラーの運転を停止させ
る必要があるため、多缶設置システムにおいて複数台の
ボイラーが同時にブロー時期に達しブロー作業を行うと
、蒸気量が急減したり或いは全くストップしてしまう等
、安定した蒸気の供給ができなくなる。
Therefore, it is desirable to automate these blowing operations, but since it is necessary to stop boiler operation when performing blowing operations, in a multi-can installation system, multiple boilers reach the blowing time at the same time and cannot be used for blowing operations. If this is done, the amount of steam will suddenly decrease or stop completely, making it impossible to provide a stable supply of steam.

〔課題を解決するための手段〕[Means to solve the problem]

この発明は、上述の問題点に鑑み、ボイラーの多缶設置
システムにおいてブロー作業を自動化する際、適切なブ
ロー動作を行うことができるようにしたもので、具体的
には、複数台のボイラーを負荷量に応して燃焼、停止さ
せる自動台数制御方法において、いずれかのボイラーが
ブロー時期に達したときに、そのボイラーを含めて予め
設定した台数以上のボイラーが同時にブローしないよう
ブロー指示信号を抑制することを特徴としている。
In view of the above-mentioned problems, this invention enables appropriate blowing operations to be performed when automating blowing operations in a multi-boiler installation system. In an automatic number control method that starts and stops combustion according to the load, when any boiler reaches its blowing time, a blow instruction signal is sent to prevent more than a preset number of boilers, including that boiler, from blowing at the same time. It is characterized by suppression.

〔作用〕 この発明によれば、同時に多数のボイラーがブロー時期
に達しても、そのうちの1台にのみ、或いは蒸気供給量
に影響に出ない台数に対してのみブロー指示信号を出す
ことができ、負荷への対応に支障が生じない。又、蒸気
使用量の少ない時間帯を選択してブロー指示信号を出す
ことにより、必要蒸気量に対して安定した蒸気の供給を
行うことができる。
[Function] According to the present invention, even if a large number of boilers reach their blowing time at the same time, a blow instruction signal can be issued to only one of them or only to a number of boilers that does not affect the amount of steam supplied. , there is no problem in handling the load. Further, by selecting a time period when the amount of steam used is small and issuing the blow instruction signal, it is possible to stably supply steam to the required amount of steam.

〔実施例〕〔Example〕

以下、この発明の好ましい実施例を図面に基づいて説明
する。
Preferred embodiments of the present invention will be described below with reference to the drawings.

図中(1)はボイラーで、それぞれ燃焼装置(2)、ブ
ロー制御器(3)を備えており、蒸気管(4)にて共通
のスチームヘッダー(5)に連結しである。このスチー
ムヘッダーには、内部の蒸気圧力を検出するための圧力
センサー(6)を設けてあって、その圧力検出信号に基
づき、台数制御器(7)により各ボイラーの燃焼・停止
を制御するようになっている。尚、ブロー制御器(3)
は台数制御器(7)内に組み込むようにしてもよい。
In the figure, (1) is a boiler, each of which is equipped with a combustion device (2) and a blow controller (3), and is connected to a common steam header (5) through a steam pipe (4). This steam header is equipped with a pressure sensor (6) to detect the internal steam pressure, and based on the pressure detection signal, the number controller (7) controls combustion and shutdown of each boiler. It has become. In addition, blow controller (3)
may be incorporated into the number controller (7).

第2図にボイラー(1)周りの詳細を示すが、(8)は
ボイラー底部に接続した全ブロー用電動弁であり、缶水
の排出を制御する。全ブロー時期を検出するには、缶内
下部に電気伝導度センサー(9)を設けて缶水が過濃縮
になっているかどうかを判別したり、或いは燃焼時間を
積算して設定値と比較し全ブロー時期を判断する方法な
どがある。
Figure 2 shows the details around the boiler (1). (8) is an electric valve for full blowing connected to the bottom of the boiler, which controls the discharge of canned water. To detect the full blow period, install an electrical conductivity sensor (9) at the bottom of the can to determine whether the can water is overconcentrated, or integrate the combustion time and compare it with a set value. There are methods for determining when it is time for a complete blowout.

00は多数の噴出孔を有するスートブロー管であり、ボ
イラー内の伝熱面に対向して配置し、高圧水や蒸気など
の洗浄媒体の供給を制御するスートブロー用電動弁(1
0を接続しである。スートブロー時期を検出するには、
例えば煙道qカに設けた温度センサー03)により排ガ
ス温度を測定し、その上昇の程度により煤の付着度合を
判断する。
00 is a soot blow pipe with a large number of ejection holes, and is placed opposite the heat transfer surface in the boiler, and is equipped with a soot blow electric valve (1) that controls the supply of cleaning media such as high-pressure water and steam.
Connect 0. To detect the soot blow time,
For example, the exhaust gas temperature is measured by a temperature sensor 03) installed in the flue q, and the degree of soot adhesion is determined based on the degree of rise.

第3図は、自動台数制御の一例を示すもので、ボイラー
がNo、1. No、2. No、3の順に優先的に稼
動するように設定している。制御圧力を7つの蒸気圧力
帯(a−g)に分け、下限の蒸気圧力帯aでは全缶高燃
焼Hの状態で、スチームへラダー内の蒸気圧力が蒸気圧
力帯すまで上昇するとボイラーNo、3が低燃焼りに移
行し、さらに蒸気圧力帯辷まで上昇すると停止し、蒸気
圧力の上昇に伴って全缶の燃焼状態がHHH−+HHL
−4HH−+HL→H→Lのように移行し、上限の蒸気
圧力帯gでは全缶停止の状態になる。又、蒸気圧力下降
時にはボイラーがNo、1. No、2. No、、3
の順に稼動し、L−H→HL−HH−HHL→HHHの
ように燃焼状態が移行する。ボイラーの稼動時間が平均
化するように優先順位は適宜ローテーションを行い、異
常ボイラーが発生した場合は次の順位のボイラーを稼動
させてバックアップ制御を行う。
FIG. 3 shows an example of automatic number control, where boilers are No. 1, 1. No, 2. It is set to operate preferentially in the order of No. and No. 3. The control pressure is divided into seven steam pressure zones (a-g), and in the lower limit steam pressure zone a, all boilers are in a state of high combustion H, and when the steam pressure in the ladder rises to the steam pressure zone, boiler No. 3 shifts to low combustion, and then stops when the steam pressure rises to the edge of the steam pressure zone, and as the steam pressure increases, the combustion state of all cans changes to HHH-+HHL.
-4HH-+HL→H→L, and at the upper steam pressure zone g, all the vessels are stopped. Also, when the steam pressure decreases, the boiler is No. 1. No, 2. No, 3
The combustion state changes as follows: LH→HL-HH-HHL→HHH. Priorities are rotated as appropriate so that the operating time of the boilers is averaged, and if an abnormal boiler occurs, the next ranked boiler is operated for backup control.

以上のような構成において、各ボイラーからブロー時期
に達した旨の信号が発せられたときは、次のように制御
する。ブロー作業を行う際は、そのボイラを停止させる
必要があるので、同時に多数のボイラーがブロー時期に
達しても負荷に必要な蒸気供給量に影響が出ないように
、1台或いは限られた台数にだけ順番にブロー指示信号
を出す。
In the above configuration, when each boiler issues a signal indicating that the blowing time has been reached, control is performed as follows. When performing blowing work, it is necessary to stop the boiler, so in order to avoid affecting the amount of steam supplied to the load even if many boilers reach their blowing time at the same time, one boiler or a limited number of boilers may be used. A blow instruction signal is issued only in sequence.

そして、燃焼中のボイラーにブロー指示信号を出すとき
には、そのボイラーのブロー作業生別のボイラーをバッ
クアップ起動させたり、優先順位が上位のボイラーがブ
ロー時期に達したときは、ローテーション後優先順位が
下位になったときにブロー指示信号を出すようにする。
When issuing a blow instruction signal to a boiler that is currently burning, the boiler that is assigned to the blowing operation of that boiler is activated as a backup, or when a boiler with a higher priority reaches its blowing time, after rotation, a boiler with a lower priority is activated. A blow instruction signal is issued when this happens.

また、ブロー指示信号を出す時間帯についても、過去の
ボイラーの稼動実績を曜日毎及び時間毎に記憶しておき
、負荷に余裕のある蒸気使用量の少ない時間帯にのみブ
ロー指示信号を出すようにし、予めブロー可能時間帯と
ブロー禁止時間帯を選択して指定しておく。
In addition, regarding the time period when the blow instruction signal is issued, past boiler operation results are memorized by day of the week and hourly, and the blow instruction signal is issued only during times when the steam usage is low and there is sufficient load. , and select and specify the blow-allowed time period and blow-prohibited time period in advance.

〔発明の効果〕〔Effect of the invention〕

この発明は、以上のような構成であり、同時に多数のボ
イラーがブロー時期に達しても、必要蒸気供給量に影響
が出ない台数のボイラーにだけ順番にブロー指示信号を
出すようにし、又、必要蒸気供給量に影響が出ない時間
帯にブロー指示信号を出すようにしたので、負荷への対
応に支障がなく、必要蒸気量に対して安定した蒸気の供
給を行うことができる。従って、ブロー作業を円滑に自
動化して、ボイラー運転管理者の負担を大幅に軽減する
ことができる。
This invention has the above configuration, and even if a large number of boilers reach their blowing time at the same time, a blow instruction signal is sequentially issued to only the number of boilers that does not affect the required amount of steam supply, and Since the blow instruction signal is issued during a time period when the required amount of steam supply is not affected, there is no problem in responding to the load, and it is possible to stably supply steam with respect to the required amount of steam. Therefore, the blowing work can be smoothly automated and the burden on the boiler operation manager can be significantly reduced.

【図面の簡単な説明】[Brief explanation of drawings]

第1図はこの発明の一実施例を示す系統図、第2図はそ
の要部拡大系統図、第3図は自動台数制御における蒸気
圧力変化に伴うボイラーの燃焼パターンの変化の一例を
示すグラフである。 (1)・・・ボイラー     (2)・・・燃焼装置
(3)・・・ブロー制御器   (4)・・・蒸気管(
5)・・・スチームヘッダー (6)・・・圧力センサ
ー(7)・・・台数制御器    (8)・・・全ブロ
ー用電動弁(9)・・・電気伝導度センサー (+01・・・スートブロー管 00・・・スートブロー用電動弁
Fig. 1 is a system diagram showing an embodiment of the present invention, Fig. 2 is an enlarged system diagram of its main parts, and Fig. 3 is a graph showing an example of a change in boiler combustion pattern due to a change in steam pressure in automatic number control. It is. (1)...Boiler (2)...Combustion device (3)...Blow controller (4)...Steam pipe (
5)...Steam header (6)...Pressure sensor (7)...Number of units controller (8)...Electric conductivity sensor (+01...) Soot blow pipe 00...Electric valve for soot blow

Claims (2)

【特許請求の範囲】[Claims] (1)複数台のボイラー(1)を負荷量に応じて燃焼、
停止させる自動台数制御方法において、いずれかのボイ
ラーがブロー時期に達したときに、そのボイラーを含め
て予め設定した台数以上のボイラーが同時にブローしな
いようブロー指示信号を抑制することを特徴とするブロ
ー指示操作を含むボイラーの自動台数制御方法。
(1) Combustion of multiple boilers (1) according to the load amount,
In the method for automatically controlling the number of boilers to be stopped, when any boiler reaches the blowing time, a blowing instruction signal is suppressed so that a preset number or more of boilers including that boiler do not blow at the same time. A method for automatically controlling the number of boilers including instruction operation.
(2)複数台のボイラー(1)を負荷量に応じて燃焼、
停止させる自動台数制御方法において、前記ボイラーが
ブロー時期に達したとき、所定の時間帯にのみブロー指
示信号を出すことを特徴とするブロー指示操作を含むボ
イラーの自動台数制御方法。
(2) Combustion of multiple boilers (1) according to the load amount,
A method for automatically controlling the number of boilers to be stopped, including a blow instruction operation, characterized in that when the boiler reaches its blowing time, a blow instruction signal is issued only during a predetermined time period.
JP17070589A 1989-06-30 1989-06-30 Automatic control of number of boilers including blow instruction operation Pending JPH0336403A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP17070589A JPH0336403A (en) 1989-06-30 1989-06-30 Automatic control of number of boilers including blow instruction operation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP17070589A JPH0336403A (en) 1989-06-30 1989-06-30 Automatic control of number of boilers including blow instruction operation

Publications (1)

Publication Number Publication Date
JPH0336403A true JPH0336403A (en) 1991-02-18

Family

ID=15909869

Family Applications (1)

Application Number Title Priority Date Filing Date
JP17070589A Pending JPH0336403A (en) 1989-06-30 1989-06-30 Automatic control of number of boilers including blow instruction operation

Country Status (1)

Country Link
JP (1) JPH0336403A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011064358A (en) * 2009-09-15 2011-03-31 Samson Co Ltd Steam supply system
JP2011099600A (en) * 2009-11-05 2011-05-19 Samson Co Ltd Multiple can installed boiler
CN102207285A (en) * 2010-03-29 2011-10-05 三浦工业株式会社 Program, controller, and boiler system

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011064358A (en) * 2009-09-15 2011-03-31 Samson Co Ltd Steam supply system
JP2011099600A (en) * 2009-11-05 2011-05-19 Samson Co Ltd Multiple can installed boiler
CN102207285A (en) * 2010-03-29 2011-10-05 三浦工业株式会社 Program, controller, and boiler system

Similar Documents

Publication Publication Date Title
JP2754212B2 (en) Boiler automatic unit control system including blow operation
US10754331B2 (en) Cloud-based analytics for water heaters
US20070207422A1 (en) A low contamination rate flame detection arrangement
JPH0336403A (en) Automatic control of number of boilers including blow instruction operation
US20200209112A1 (en) Failure mode determination means
JP3998812B2 (en) How to control the number of boilers with multiple cans
JP3956083B2 (en) Control device for hot water heater
KR102403783B1 (en) Steam boiler monitoring system
EP1607820B1 (en) Heating control system
JPH06272802A (en) Device for controlling the number of heat equipment
JP2003130304A (en) Method of quantity control for boilers
JP2000018503A (en) Automatic number of operating set control method of boiler
US20230085869A1 (en) Hot water supplier monitoring system
JP3697910B2 (en) Secondary pressure adjustment method for gas combustor
CN1114789C (en) Combustion controlling circuit
JPH073126Y2 (en) Boiler automatic number control system
JP3964603B2 (en) Data complementing method for hot water supply apparatus and hot water supply apparatus
US20220196290A1 (en) Hot water supply device
JPH09101059A (en) Hot-water supply system
JPH01155114A (en) Operating method for soot blower
JPH0439539A (en) Central hot water feeding device
JPH0749318Y2 (en) Control device for operating number of hot water boilers
JPH01252801A (en) Automatic control for the number of boilers
KR100361150B1 (en) Apparatus for controlling temperature of midnight-boiler and the method thereof
JP2553000Y2 (en) Multi-can installation of vacuum hot water boiler