JPH03260297A - Replacing method of center column in lining of multiple connected tunnel - Google Patents
Replacing method of center column in lining of multiple connected tunnelInfo
- Publication number
- JPH03260297A JPH03260297A JP2058357A JP5835790A JPH03260297A JP H03260297 A JPH03260297 A JP H03260297A JP 2058357 A JP2058357 A JP 2058357A JP 5835790 A JP5835790 A JP 5835790A JP H03260297 A JPH03260297 A JP H03260297A
- Authority
- JP
- Japan
- Prior art keywords
- tunnel
- temporary
- lining
- joint members
- segments
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 title claims description 8
- 230000002093 peripheral effect Effects 0.000 claims abstract description 7
- 238000010276 construction Methods 0.000 description 11
- 238000009412 basement excavation Methods 0.000 description 9
- 239000002131 composite material Substances 0.000 description 8
- 229910000831 Steel Inorganic materials 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000005553 drilling Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
Landscapes
- Lining And Supports For Tunnels (AREA)
Abstract
Description
【発明の詳細な説明】
[産業上の利用分野]
本発明は、断面略円形の掘削穴を複合してなる多連形ト
ンネルを覆工するにあたり、複合部の間にわたって建て
込んだ仮設中柱に代えて本設中柱に受け替えていく工法
に関する。[Detailed Description of the Invention] [Industrial Application Field] The present invention is directed to a temporary center pillar erected between the composite sections when lining a multiple tunnel consisting of a composite of excavated holes having a substantially circular cross section. Concerning the construction method of replacing the pillar with a permanent central pillar.
[発明がなされた技術背景]
近年、地下鉄道用トンネルなどの大断面トンネル構造物
を構築するための大断面シールド工法として、後円形特
殊断面シールド工法とよばれるものが行なわれるように
なった。[Technical Background of the Invention] In recent years, as a large-section shield construction method for constructing large-section tunnel structures such as underground railway tunnels, a method called a rear circular special section shield construction method has been used.
この工法は、円筒状のシールド掘削機を複数基連結した
構造のシールド掘削機を用いて、断面略円形の掘削穴が
一部複合した状態で連なる断面形状に地山を掘削し、こ
の掘削穴の周壁に、互いに連結されるRCセグメント等
のセグメントを据え付けて筒状壁体を構築するとともに
、この筒状壁体を掘削穴に沿って複数連結しく一次覆工
)、この−法覆工の内面にコンクリートを巻き立て(二
次覆工)、それらによって地山を支持して所定の内空を
構成するというものである。そして、通常上記筒状壁体
の複合部には、この複合部に応じた分岐部セグメントが
配され、さらに、この分岐部セグメント間には、支柱と
して中柱を建て込んでいる。This construction method uses a shield excavator with a structure in which multiple cylindrical shield excavators are connected to excavate the ground into a cross-sectional shape in which several approximately circular cross-sectional excavation holes are connected. A cylindrical wall is constructed by installing segments such as RC segments that are connected to each other on the peripheral wall of the tunnel, and a plurality of these cylindrical walls are connected along the excavated hole (primary lining). The inner surface is covered with concrete (secondary lining), which supports the ground and forms a predetermined inner space. Usually, the composite part of the cylindrical wall body is provided with branch segments corresponding to the composite part, and furthermore, between the branch segments, a central column is installed as a support.
ところで、たとえば地下鉄トンネルにおいて、3基のシ
ールド掘削機を横に連結して掘削穴を形成し、その中央
の掘削穴をプラットホーム、その両側の掘削穴を鉄道と
して利用する形式の駅部を構築する際、前記中柱は中央
の掘削穴の両側にあって分岐部セグメントごとに建て込
まれており、これら中柱がこのままの状態では、乗客の
乗降やプラットホームの通行の邪魔となる。したがって
、これら中柱の代わりに、前記筒状壁体を支えつつも、
乗降やプラットホームの通行の邪魔にならないような間
隔をおいて、本設の中柱を建て込む必要がある。By the way, for example, in a subway tunnel, three shield excavators are connected horizontally to form an excavation hole, and the central excavation hole is used as a platform, and the excavations on both sides are used as a railway station to construct a station. In this case, the middle pillars are located on both sides of the central excavated hole and are built for each branch segment, and if these middle pillars remain as they are, they will obstruct passengers getting on and off and passing through the platform. Therefore, in place of these central pillars, while supporting the cylindrical wall,
It is necessary to erect the permanent center pillars at intervals that do not interfere with boarding and alighting or platform traffic.
しかしながら、このように最初にセグメントごとに建て
込んだ中柱を撤去しつつ、本設の中柱を所定間隔をおい
て建て込んでいくにあたっての効率的な工法は未だ開発
されておらず、要望されているのが現状である。However, an efficient construction method has not yet been developed for removing the center pillars that were initially erected for each segment and then erecting the main center pillars at predetermined intervals. The current situation is that
本発明は上記事情に鑑みてなされたもので、その目的と
するところは、多連形トンネルの覆工にあたり、セグメ
ントごとに建て込んだ仮設の中柱に代えて、本設の中柱
を所定間隔おきに効率的に建て込むことを可能とする多
連形トンネルの覆工における中柱の受け替え工法を提供
することにある。The present invention has been made in view of the above circumstances, and its purpose is to install permanent center pillars in place of temporary center pillars erected for each segment when lining multiple tunnels. An object of the present invention is to provide a method for replacing center pillars in lining a multiple tunnel, which enables efficient construction at intervals.
[課題を解決するための手段]
本発明は上記目的を達成するため、断面略円形の掘削穴
を略水平方向に複数複合してなる多連形トンネルの周壁
に、セグメントによる覆工体を組み付けかつトンネル軸
方向に連結しながら、上下の複合部に配されるセグメン
ト間に継手部材を介して所定間隔おきに本設中柱を建て
込むとともにその間に仮設中柱を建て込んでいき、次い
で、隣合う前記継手部材どうしを、これらの間にわたっ
て架け渡した添接板によって相互に連結し、この後、前
記仮設中柱を撤去することを特徴としている。[Means for Solving the Problems] In order to achieve the above object, the present invention assembles a lining body made of segments to the peripheral wall of a multiple tunnel formed by combining a plurality of excavated holes with a substantially circular cross section in a substantially horizontal direction. While connecting in the axial direction of the tunnel, permanent center pillars are erected at predetermined intervals via joint members between the segments arranged in the upper and lower composite parts, and temporary center pillars are erected between them, and then, It is characterized in that the adjacent joint members are interconnected by a splicing plate extending between them, and then the temporary center pillar is removed.
[作用]
本発明の多連形トンネルの覆工における中柱の受け替え
工法は、添接板により分岐部セグメントどうしを連結し
て一体化させた後、本設中柱を残して仮設中柱を撤去し
ていくもので、本設中柱を所定間隔おきに受け替えてい
く作業を効率的に行うことが可能となる。この工法にお
いては、使用して撤去した仮設中柱を、その前方におい
て新たに筒状壁体を構築して中柱を建て込むときに転用
できる利点を有する。[Function] The method of replacing the center pillar in the lining of a multiple tunnel according to the present invention is to connect and integrate the branch segments with a splicing plate, and then replace the temporary center pillar with the permanent center pillar remaining. By removing the main pillars, it becomes possible to efficiently replace the main pillars at predetermined intervals. This construction method has the advantage that the used and removed temporary center pillar can be reused when constructing a new cylindrical wall in front of it and erecting the center pillar.
し実施例]
以下、本発明の一実施例を第1図ないし第6図を参照し
て説明する。Embodiment] An embodiment of the present invention will be described below with reference to FIGS. 1 to 6.
第1図および第2図は、3基のシールド掘削機を略水平
に連結した構造のシールド掘削機により、隣り合う3つ
の掘削穴IA、IB、ICの一部が複合した大断面の掘
削穴1を地山Gに掘削形成し、その周壁2を、互いに連
結される円弧板状セグメント3A、分岐部セグメント3
Bにより覆工して筒状壁体(覆工体)3を構築し、さら
に、掘削穴lの掘進にともない、この筒状壁体3を掘削
穴1に沿って連結して地下鉄の駅部のトンネルを構築し
ている状態を示している。このトンネルは、中央の掘削
穴IAがプラットホーム、その両側の掘削穴IB、Ic
が鉄道として利用される形式のものである。Figures 1 and 2 show a large cross-section excavation hole made by combining parts of three adjacent excavation holes IA, IB, and IC using a shield excavator with a structure in which three shield excavators are connected approximately horizontally. 1 is excavated into the ground G, and its peripheral wall 2 is made up of arcuate plate-like segments 3A and branch segments 3 that are connected to each other.
A cylindrical wall body (lining body) 3 is constructed by lining B, and as the excavation hole 1 is excavated, this cylindrical wall body 3 is connected along the excavation hole 1 to form a subway station area. The tunnel is being constructed. In this tunnel, the central drill hole IA is the platform, and the drill holes IB and Ic on both sides are the platform.
is of the type used as a railway.
前記分岐部セグメン1−3Bは断面Y字状であって筒状
壁体3における上下2カ所の複合部4にそれぞれ配され
ており、軸方向に隣合う分岐部セグメント3Bどうしは
、継手金具5により相互に連結される。The branch segment 1-3B has a Y-shaped cross section and is arranged in two upper and lower composite parts 4 of the cylindrical wall 3, and the branch segments 3B adjacent to each other in the axial direction are connected to a joint fitting 5. are interconnected by.
次いで、本発明に係る筒状壁体3に対して本設中柱を建
て込んでい(工程の手順を説明する。Next, a permanent center pillar is built into the cylindrical wall body 3 according to the present invention (the procedure of the process will be explained below).
まず、第1図および第2図に示すように、前記筒状壁体
3を構築するごとに、上下の分岐部セグメン)3Bの互
いの対向面3bに、継手部材6を固定する。この継手部
材6は、厚いウェブ6aの両端にフランジ6bが一体化
されたH型鋼からできており、分岐部セグメン)3Bの
対向面3bに、一方のフランジ6bを合わせて固定する
。First, as shown in FIGS. 1 and 2, each time the cylindrical wall body 3 is constructed, the joint members 6 are fixed to the mutually opposing surfaces 3b of the upper and lower branch segment 3B. This joint member 6 is made of H-shaped steel with flanges 6b integrated at both ends of a thick web 6a, and is fixed with one flange 6b aligned with the opposing surface 3b of the branch segment 3B.
そして、この継手部材6の分岐部セグメント3Bに対す
る固定とともに、上下の継手部材6の間に、仮設中柱7
あるいは本設中柱8を建て込み、これらを継手部材6に
固定する。In addition to fixing the joint member 6 to the branch segment 3B, a temporary middle pillar 7 is installed between the upper and lower joint members 6.
Alternatively, the main pillars 8 are built in and fixed to the joint member 6.
その場合、筒状壁体3の構築にともない、本設中柱8の
間隔が一定の間隔となるようにする。本実施例では、第
2図に示すように、本設中柱8の間に仮設中柱7を3本
建て込む割合としている。In that case, as the cylindrical wall body 3 is constructed, the intervals between the main pillars 8 are made to be constant. In this embodiment, as shown in FIG. 2, three temporary middle pillars 7 are erected between permanent middle pillars 8.
また、この作業と平行して、第3図および第4図に示す
ように、隣合う継手部材6どうしを、これらの間にわた
って架け渡した添接板9によって相互に連結し、さらに
、隣合う分岐部セグメント3Bどうしを、これらの間に
わたって架け渡した補助板10によって相互に連結する
。In addition, in parallel with this operation, as shown in FIGS. 3 and 4, adjacent joint members 6 are connected to each other by a splicing plate 9 spanning between them, and furthermore, adjacent joint members 6 are The branch segments 3B are interconnected by an auxiliary plate 10 spanning between them.
添接板9は、長方形状の板材であって、継手部材6の上
下のフランジ6bの両側の内面にそれぞれ合わせてボル
ト止めによって固定する。また、補助板10も同様に長
方形状の板材からなるもので、分岐部セグメント3Bの
両側面に合わせてボルト止めによって固定する。これに
より、各分岐部セグメント3B・・・は、各添接板9・
・・および各補助板10・・・を介して一体化する。The attachment plate 9 is a rectangular plate material, and is fixed to the inner surfaces of both sides of the upper and lower flanges 6b of the joint member 6 by bolting. Further, the auxiliary plate 10 is similarly made of a rectangular plate, and is fixed by bolts to both sides of the branch segment 3B. As a result, each branch segment 3B... is connected to each connecting plate 9.
. . . and each auxiliary plate 10 .
次に、上記添接板9と補助板10とによる分岐部セグメ
ント3Bどうしの連結が完了した区間において、第5図
および第6図に示すように、仮設中柱7を継手部材6か
ら外して撤去する。仮設中柱7が建て込まれている分岐
部セグメンl−3B・・・は、上記のように添接板9と
補助板10とによる一体化により、互いに支持し合う構
造となっているから、仮設中柱7を撤去できるわけであ
る。Next, as shown in FIGS. 5 and 6, in the section where the connection between the branch segments 3B by the attachment plate 9 and the auxiliary plate 10 has been completed, the temporary middle pillar 7 is removed from the joint member 6. Remove. The branch segment 1-3B... in which the temporary middle pillar 7 is installed has a structure in which they support each other by integrating the attachment plate 9 and the auxiliary plate 10 as described above. This means that the temporary middle pillar 7 can be removed.
以上の手順を、掘削穴lの形成と筒状壁体3の構築にと
もなって順次行い、所定の間隔をおいて本設中柱8を、
継手部材6を介して分岐部セグメント3B間に建て込ん
でいく。The above steps are performed sequentially as the excavation hole l is formed and the cylindrical wall body 3 is constructed, and the main pillars 8 are installed at predetermined intervals.
It is installed between the branch segments 3B via the joint member 6.
なお、本設中柱8は、所定の間隔がおかれた状態で筒状
壁体3・・・を支持し得る強度を有し、またその間隔は
、乗客の乗降やプラットホームの通行に邪魔とならない
距離に設定される。The main pillars 8 have the strength to support the cylindrical walls 3 at predetermined intervals, and the intervals are such that they do not interfere with passengers getting on and off or passing through the platform. The distance is set to a distance that cannot be exceeded.
以上のような工法により、筒状壁体3・・・に対し、本
設中柱8を仮設中柱7から所定間隔おきに受け替えてい
(作業を効率的に行うことが可能となる。By the construction method described above, the permanent center pillars 8 are replaced with the temporary center pillars 7 at predetermined intervals for the cylindrical wall body 3 (this work can be carried out efficiently).
この工法においては、ある一定の区間の作業が完了した
ら、その際に使用して撤去した仮設中柱7を、その前方
において新たに筒状壁体を構築して中柱を建て込むとき
に転用できる。In this construction method, once the work in a certain section is completed, the temporary center pillar 7 that was used and removed at that time is reused when constructing a new cylindrical wall in front of it and erecting the center pillar. can.
第7図および第8図は、上記継手部材6に代えて継手部
材11を用いた状態を示している。7 and 8 show a state in which a joint member 11 is used in place of the joint member 6 described above.
この継手部材11は、長方形状の枠11a内に十字状の
補強材11bが固定されたもので、枠11aを分岐部セ
グメント3Bに固定するようになっている。そして、先
の継手部材6と同様に、枠11aの上下の内面に添接板
9が架け渡されて固定される。また、継手部材11は分
岐部セグメン)3Bに固定された状態で隣合うものどう
しが合わせられ、その接合部をボルト等によって固定す
ることにより、分岐部セグメント3Bの連結強度を向上
させることができる。This joint member 11 has a cross-shaped reinforcing member 11b fixed within a rectangular frame 11a, and is adapted to fix the frame 11a to the branch segment 3B. Then, like the joint member 6 described above, splice plates 9 are bridged and fixed to the upper and lower inner surfaces of the frame 11a. In addition, the joint members 11 are fixed to the branch segment 3B, and adjacent parts are brought together, and the joints are fixed with bolts or the like, thereby improving the connection strength of the branch segment 3B. .
なお、上記添接板9は、単なる長方形状の板材でできて
いるが、第9図の符号12で示す添接板のように、上下
に配されるものを一体化したような断面コ字状のものを
用いることもできる。この添接板12は、上記各継手部
材6.11の内面に合うよう構成され、断面二字状であ
ることから剛性が高く、分岐部セグメン)3Bどうしの
連結強度も増す利点を備える。The splicing plate 9 is made of a simple rectangular plate, but it has a U-shaped cross section, like the splicing plate indicated by the reference numeral 12 in FIG. It is also possible to use a This splice plate 12 is configured to fit the inner surface of each of the joint members 6.11, and has a double-shaped cross section, so it has the advantage of being high in rigidity and increasing the connection strength between the branch segments 3B.
[発明の効果]
本発明の多連形トンネルの覆工における中柱の受け替え
工法によれば、断面略円形の掘削穴を略水平方向に複数
複合してなる多連形トンネルの周壁に、セグメントによ
る覆工体を組み付けかつトンネル軸方向に連結しながら
、上下の複合部に配されるセグメント間に継手部材を介
して所定間隔おきに本設中柱を建て込むとともにその間
に仮設中柱を建て込んでいき、次いで、隣合う前記継手
部材どうしを、これらの間にわたって架け渡した添接板
によって相互に連結し、この後、前記仮設中柱を撤去す
ることを特徴とするので、仮設中柱から本設中柱を所定
間隔おきに受け替えていく作業を効率的に行うことが可
能となる。また、この工法においては、使用して撤去し
た仮設中柱を、その前方において新たに筒状壁体を構築
して中柱を建て込むときに転用できる。[Effects of the Invention] According to the method for replacing the center pillar in lining of multiple tunnels of the present invention, a plurality of excavated holes having a substantially circular cross section are combined in a substantially horizontal direction on the peripheral wall of a multiple tunnel, While assembling the lining made up of segments and connecting them in the axial direction of the tunnel, permanent center pillars are erected at predetermined intervals between the segments arranged in the upper and lower composite parts via joint members, and temporary center pillars are installed between them. The structure is characterized in that the adjacent joint members are connected to each other by a splicing plate that spans between them, and then the temporary middle pillar is removed, so that the temporary construction It becomes possible to efficiently perform the work of replacing the main pillars from the pillars at predetermined intervals. Furthermore, in this construction method, the used and removed temporary center pillar can be reused when constructing a new cylindrical wall in front of it and erecting the center pillar.
第1図ないし第6図は本発明の一実施例を示す図であっ
て、第1図は仮設中柱を建て込んだ状態の筒状壁体の正
面図、第2図は第1図の■−■線矢視図夜回3図は継手
部材の連結状態を示す側面図、第4図は第3図のIV−
IV線矢視夜回第5図は仮設中柱を撤去した状態の筒状
壁体の正面図、第6図は第5図のVI−Vl線矢視夜回
第7図は継手部材の変形例を示す側面図、第8図は第7
図の■−■線矢視図夜回9図は添接板の変形例を示す正
面図である。
1、IA、IB、IC・・・・・・掘削穴、2・・・・
・・周壁、3・・・・・・筒状壁体(覆工体)、3A・
・・・・・セグメント、3B・・・・・・分岐部セグメ
ント、4・・・・・・複合部、6.11・・・・・・継
手部材、7・・・・・・仮設中柱、8・・・・・・本設
中柱、9.12・・・・・・添接板、G・・・・・・地
山。1 to 6 are diagrams showing an embodiment of the present invention, in which FIG. 1 is a front view of a cylindrical wall with temporary central pillars installed, and FIG. 2 is a view similar to that of FIG. ■-■ line arrow view night view Figure 3 is a side view showing the connected state of the joint members, and Figure 4 is the IV-- of Figure 3.
Fig. 5 shows the front view of the cylindrical wall with the temporary center pillar removed, and Fig. 6 shows the night view taken from the VI-Vl line in Fig. 5. Fig. 7 shows the deformation of the joint member. Side view showing an example, FIG.
Figure 9, which is a view taken along the line ■-■ in the figure, is a front view showing a modified example of the attachment plate. 1, IA, IB, IC...Drilling hole, 2...
... Peripheral wall, 3... Cylindrical wall body (lining body), 3A.
... Segment, 3B ... Branch segment, 4 ... Composite section, 6.11 ... Joint member, 7 ... Temporary middle pillar , 8...Main pillar, 9.12...Applicable plate, G...Ground.
Claims (1)
多連形トンネルの周壁に、セグメントによる覆工体を組
み付けかつトンネル軸方向に連結しながら、上下の複合
部に配されるセグメント間に継手部材を介して所定間隔
おきに本設中柱を建て込むとともにその間に仮設中柱を
建て込んでいき、次いで、隣合う前記継手部材どうしを
、これらの間にわたって架け渡した添接板によって相互
に連結し、この後、前記仮設中柱を撤去することを特徴
とする多連形トンネルの覆工における中柱の受け替え工
法。A lining made of segments is assembled on the peripheral wall of a multiple tunnel made up of a plurality of excavated holes with a substantially circular cross section in a substantially horizontal direction, and connected in the axial direction of the tunnel. Permanent center pillars are erected at predetermined intervals via joint members, and temporary center pillars are erected in between, and then the adjacent joint members are connected by connecting plates that span between them. A method for replacing center pillars in lining a multiple tunnel, characterized in that the temporary center pillars are interconnected and then removed.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2058357A JP2799353B2 (en) | 1990-03-09 | 1990-03-09 | Replacement method of middle pillar in lining of multiple tunnels |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2058357A JP2799353B2 (en) | 1990-03-09 | 1990-03-09 | Replacement method of middle pillar in lining of multiple tunnels |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH03260297A true JPH03260297A (en) | 1991-11-20 |
JP2799353B2 JP2799353B2 (en) | 1998-09-17 |
Family
ID=13082070
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2058357A Expired - Fee Related JP2799353B2 (en) | 1990-03-09 | 1990-03-09 | Replacement method of middle pillar in lining of multiple tunnels |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2799353B2 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107178378A (en) * | 2017-06-28 | 2017-09-19 | 西南交通大学 | A kind of three targes structure builds the pipe sheet assembling structure and construction method of subway station |
CN114352326A (en) * | 2022-01-24 | 2022-04-15 | 中铁工程装备集团有限公司 | Assembled subway station and construction method thereof |
-
1990
- 1990-03-09 JP JP2058357A patent/JP2799353B2/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107178378A (en) * | 2017-06-28 | 2017-09-19 | 西南交通大学 | A kind of three targes structure builds the pipe sheet assembling structure and construction method of subway station |
CN114352326A (en) * | 2022-01-24 | 2022-04-15 | 中铁工程装备集团有限公司 | Assembled subway station and construction method thereof |
Also Published As
Publication number | Publication date |
---|---|
JP2799353B2 (en) | 1998-09-17 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105604091B (en) | A kind of cap excavation method cover system construction method | |
JP2004169474A (en) | Connecting structure for tunnel cutting and enlarging section | |
CN111270685A (en) | Recyclable support truss, foundation pit support system and subway station construction method | |
JP4104781B2 (en) | Construction method of underground joint structure | |
JPH03260297A (en) | Replacing method of center column in lining of multiple connected tunnel | |
JP7213154B2 (en) | Top slab construction method for shaft and top slab structure | |
JPS6137692Y2 (en) | ||
JP2799343B2 (en) | Replacement method of middle pillar in lining of multiple tunnels | |
JPH11140892A (en) | Method for excavating ground and method for constructing underground structure using the same | |
JP2725972B2 (en) | Underground structure construction method and segment piece used therefor | |
RU2044836C1 (en) | Underground structure and method for erecting the same | |
JP2020079490A (en) | Lining skeleton structure and construction method thereof | |
JP2747487B2 (en) | Replacement method of middle pillar in lining of multiple tunnels | |
JPH03257300A (en) | Center pillar bearing/replacing construction method in multiple-connected tunnel lining | |
CN214459268U (en) | Assembled overpass channel structure for transportation of strip mine | |
JP2005126917A (en) | Bamboo split type entrance of steel construction | |
JPH03253696A (en) | Changing method of center column in lining of multiple connected tunnel | |
JP7214445B2 (en) | Joint structure of panel structure | |
JP2002038889A (en) | Segment for constructing passage and door of multiple tunnel and construction method for passage and door | |
JPH03253699A (en) | Changing method of center column in lining of multiple connected tunnel | |
JP2691156B2 (en) | Tubular wall for excavation hole lining | |
JP2577439B2 (en) | Construction method of branch support in tubular wall for excavation hole lining | |
JP2683642B2 (en) | Tubular wall for digging hole lining | |
JP2000220400A (en) | Construction method for underground structure | |
JPH035599A (en) | Cylindrical wall for covering boring hole |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees |