JPH03186594A - Lifting device - Google Patents

Lifting device

Info

Publication number
JPH03186594A
JPH03186594A JP32674389A JP32674389A JPH03186594A JP H03186594 A JPH03186594 A JP H03186594A JP 32674389 A JP32674389 A JP 32674389A JP 32674389 A JP32674389 A JP 32674389A JP H03186594 A JPH03186594 A JP H03186594A
Authority
JP
Japan
Prior art keywords
rail
tool
traveling device
traveling
piece
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP32674389A
Other languages
Japanese (ja)
Inventor
Tomio Ishikawa
石川 登美夫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
National House Industrial Co Ltd
Original Assignee
National House Industrial Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by National House Industrial Co Ltd filed Critical National House Industrial Co Ltd
Priority to JP32674389A priority Critical patent/JPH03186594A/en
Publication of JPH03186594A publication Critical patent/JPH03186594A/en
Pending legal-status Critical Current

Links

Abstract

PURPOSE:To facilitate laying of floor panels by moving a winch up and down, and leftward and rightward by means of a second traveling device hung by a first traveling device, which travels in a hanging arm, detachably mounted on the horizontal beam of a house frame body. CONSTITUTION:A freely attachable and detachable hanging arm 4 is mounted on a horizontal beam 3 which constructs a frame body 2. The hanging arm 4 is provided with a first traveling device 6 which moves along a first rail 5 at right angles to a paper face. There is provided a second traveling device 9 which travels leftwards and rightwards in a second rail 7 hung from the traveling device 6. The winch of the traveling device 9 hangs each floor panel PS, and sets and fixes the floor panels PS on given positions by means of the traveling devices 6 and 9. Consequently, the floor panels PS are laid effectively.

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は、家屋の架構体に、例えばコンクリートパネル
等の床パネルを効率よく敷込みでき床パネルの敷込み施
工能率を大巾に向上しうる吊上げ用具に関する。
[Detailed Description of the Invention] [Field of Industrial Application] The present invention enables efficient laying of floor panels, such as concrete panels, on the frame structure of a house, and greatly improves the efficiency of laying floor panels. Regarding Uru lifting equipment.

〔従来の技術〕[Conventional technology]

例えば乾式1法の建築物にあっては、その床体は、予め
骨組した家屋架構体の床梁間に、例えばコンクリートパ
ネル等の床パネルを順次散逸むことにより形成される。
For example, in a building using the dry method method, the floor is formed by sequentially dispersing floor panels, such as concrete panels, between the floor beams of a pre-framed house frame structure.

一方このような敷込み作業は、架構体内で行われるため
クレーン等を用いた床パネルの各敷込み位置への移動、
吊上げが困難であり、従って従来床パネルは作業者によ
る手作業によってその移動及び位置合わせが行われてい
る。
On the other hand, since this type of laying work is done inside the frame structure, it requires moving the floor panels to each laying position using a crane, etc.
Lifting is difficult, so floor panels have traditionally been moved and aligned manually by workers.

〔発明か解決しようとする課題〕[Invention or problem to be solved]

しかしながら敷込み作業は、床パネルを端部を突き合わ
せて精度よくかつ床面全体に亘って広範囲に行う必要が
あり、しかも床パネル自体大型かつ重量物であるため、
手作業による従来のものにあっては、多大な労力と時間
を要するなど、作業能率を大巾に低下する。又このもの
は高所作業でありしかも足場が不安定であるため安全性
に劣り、従って近年このような敷込み作業における施工
能率を向上できかつ労力の軽減化を計るとともに安全性
を高めうる新規な用具の出現が強く望まれていた。
However, the laying work needs to be carried out over a wide area over the entire floor surface, with the edges of the floor panels butted together, and also because the floor panels themselves are large and heavy.
Conventional manual methods require a great deal of labor and time, which greatly reduces work efficiency. In addition, this method requires work at heights and has unstable scaffolding, making it less safe.Therefore, in recent years, new technologies have been developed that can improve construction efficiency in this type of laying work, reduce labor, and improve safety. There was a strong desire for a new tool to emerge.

本発明は、梁材に取付く吊りアーム間に跨る第1のレー
ル具と、該第1のレール具を梁材方向に移動する第1の
走行具を介して第1のレール具と直角に支持される第2
のレール具と、ウィンチを有しかつ第2のレール具を移
動する第2の走行具とを用いることを基本として、床パ
ネルの敷込み施工能率を大巾に向上でき前記問題点を解
決しうる吊上げ用具の提供を目的としている。
The present invention provides a first rail tool that straddles between hanging arms attached to a beam material, and a first rail tool that moves the first rail tool in the direction of the beam material at right angles to the first rail tool. Second supported
The above-mentioned problems can be solved by basically using a second rail tool and a second traveling tool that has a winch and moves the second rail tool, and the efficiency of laying floor panels can be greatly improved. The purpose is to provide lifting equipment.

〔課題を解決するための手段〕[Means to solve the problem]

前記目的を遠戚するため本発明の吊上げ用具は、家屋架
構体の水平な梁材に脱着自在に取付けできかつレール受
を有する吊りアームと、複数の吊りアームを跨がり前記
梁材の方向に配されるとともに前記レール受に支持され
る長尺の第1のレール具と、該第1のレール具に保持さ
れ前記梁材の方向に移動しうるとともに第1のレール具
と直角な長尺の第2のレール具を取付は可能な第1の走
行具と、第2のレール具を移動できかつウィンチを有す
る第2の走行具とを具えている。
In order to achieve the above object, the lifting tool of the present invention includes a lifting arm that can be detachably attached to a horizontal beam of a house frame structure and has a rail receiver, and a lifting tool that straddles a plurality of lifting arms in the direction of the beam. a long first rail tool arranged and supported by the rail receiver; and a long rail tool that is held by the first rail tool, movable in the direction of the beam material, and perpendicular to the first rail tool. The present invention includes a first traveling implement capable of attaching a second rail implement, and a second traveling implement capable of moving the second rail implement and having a winch.

〔作用〕[Effect]

このように構成する吊上げ用具は、梁材に吊りアームを
介して支持される第1のレール具と、該第1のレール具
に沿って移動する第1の走行具を介して第1のレール具
と直角に支持される第2のレール具とを設ける一方、該
第2のレール具にウィンチを有する第2の走行具を走行
可能に配しているため、前記ウィンチを縦横自在に移動
することができる。
The lifting tool configured in this way includes a first rail tool that is supported by a beam member via a lifting arm, and a first rail tool that moves along the first rail tool. A second rail tool supported at right angles to the tool is provided, and a second traveling tool having a winch is movably disposed on the second rail tool, so that the winch can be moved vertically and horizontally. be able to.

従って架構体に便宜に装着しうる一方、該ウィンチを用
いて床パネルを、各敷込み位置に労力を要することなく
かつ迅速に吊下げしつつ移動でき、敷込み作業を能率よ
くかつ高精度で行ないうるとともに、作業全般に亘り床
パネルの落下等を防止でき安全性を大巾に向上しうる。
Therefore, while it can be conveniently attached to the frame structure, the winch can be used to quickly suspend and move floor panels to each laying position without requiring any effort, making the laying work efficient and highly accurate. In addition, it is possible to prevent floor panels from falling during the entire operation, greatly improving safety.

〔実施例〕〔Example〕

以下本発明の一実施例を図面に基づき説明する。 An embodiment of the present invention will be described below based on the drawings.

第1〜2図において吊上げ用具1は、架構体2の水平な
梁材3に着脱自在に取付く吊りアーム4と、複数の吊り
アーム4−・・を跨って支持される第1のレール具5と
、該第1のレール具5に保持されかつ梁材3方向に移動
する第1の走行具6と、S亥第1の走行具6に前記第1
のレール具5と直角に取付けられる第2のレール具7と
、該第2のレール具7を移動できかつウィンチ8を有す
る第2の走行具9とを具える。
In FIGS. 1 and 2, a lifting tool 1 includes a hanging arm 4 that is detachably attached to a horizontal beam 3 of a frame structure 2, and a first rail tool that is supported across a plurality of hanging arms 4. 5, a first traveling implement 6 held by the first rail implement 5 and moving in the direction of the beam 3, and a first traveling implement 6 held by the first rail implement 5;
A second rail tool 7 is mounted perpendicularly to the rail tool 5 of the second rail tool 7, and a second running tool 9 which can move the second rail tool 7 and has a winch 8 is provided.

なお前記架構体2は、柱10間に、床梁等である梁材3
−を水平に架は渡した骨組状をなし、本例では、外壁に
沿いかつ例えば桁行方向にのびる一方の上の梁材3Aに
取付く吊上げ用具1を用いて、陸梁方向にのびる下の梁
材3B、3B間に、床パネルP−をその長手方向の各端
面Psを互いに突き合わせて敷設する。
Note that the frame structure 2 has beam materials 3 such as floor beams between the columns 10.
In this example, using the lifting tool 1 attached to the upper beam material 3A along the outer wall and extending, for example, in the direction of the girder, the lower beam extending in the direction of the land beam is A floor panel P- is laid between the beams 3B, 3B with each end face Ps in the longitudinal direction butted against each other.

なお前記梁材3A、3Bは、本例ではウェブ11の上下
端に上、下のフランジ12.13を水平に設けたI型鋼
が用いられる。
In this example, the beam members 3A and 3B are I-type steels in which upper and lower flanges 12 and 13 are provided horizontally at the upper and lower ends of the web 11.

前記吊りアーム4は、第2〜3図に示すように、本例で
は、前記梁材3Aの下フランジ13に着脱自在に取付く
基体15と、該基体15に継ぎ体16を介して連結され
るレール受17とを具える。
As shown in FIGS. 2 and 3, in this example, the hanging arm 4 includes a base body 15 that is detachably attached to the lower flange 13 of the beam member 3A, and is connected to the base body 15 via a joint body 16. A rail receiver 17 is provided.

基体15は、本例では、前記下フランジ13の上、下面
に沿う上、下片19A、19Bの内端間を継ぎ片19C
で継ぐコ字状をなすことにより、前記フランジ13内縁
13aを囲んで下フランジ13に係着される取付部19
と、該下片19B外端に強固に溶着される短寸かつ垂直
な基部20とを有する。又前記取付部19には、下片1
9Bに、その下面から螺入する螺大端が下フランジ13
下面を押圧する取付ボルト21が螺回用のレバーを有し
て付設され、基体15を梁材3Aに着脱自在にかつ強固
に固定する。又基体15は下片19Bと基部20とを継
ぐステーにより補強されるとともに、該基部20内面に
は、上、下開放のコ字枠状をなし前記継ぎ体16を連結
する係止部22を形成する。
In this example, the base body 15 has a joint piece 19C between the inner ends of the upper and lower pieces 19A and 19B along the upper and lower surfaces of the lower flange 13.
The mounting portion 19 is connected to the lower flange 13 by surrounding the inner edge 13a of the flange 13 by forming a U-shape.
and a short and vertical base 20 that is firmly welded to the outer end of the lower piece 19B. Further, the lower piece 1 is attached to the mounting portion 19.
The large end of the screw that is screwed into 9B from the bottom surface is the lower flange 13.
A mounting bolt 21 that presses the lower surface is attached with a lever for screwing, and removably and firmly fixes the base body 15 to the beam member 3A. The base body 15 is reinforced by a stay that connects the lower piece 19B and the base portion 20, and the base portion 20 has a locking portion 22 on the inner surface thereof in the shape of a U-shaped frame with an open top and bottom and connecting the joint body 16. Form.

前記継ぎ体16は、前記係止部22内に上方から嵌着さ
れる嵌合片24を外端に有しかつ前記梁材3Aの下方を
通って略水平に内向きにのびる胴部23の内端に、小径
な連結部25Aを上方に突出した段付状の連結軸25を
固着している。
The joint body 16 has a body portion 23 that has a fitting piece 24 at its outer end that is fitted into the locking portion 22 from above, and extends inward substantially horizontally passing below the beam member 3A. A stepped connecting shaft 25 with a small diameter connecting portion 25A projecting upward is fixed to the inner end.

又前記継ぎ体16には、胴部23の下面内方に一端が取
付きかつ外方に向かって斜め下方にのびる他端に前記基
部20内面を受ける受は片26Aを形成した斜片26を
設けており、継ぎ体16は基体15にワンタッチでかつ
係脱自在に連結されるとともに、基体15とともに強固
な三角トラス構造を形成する。
The joint body 16 has a diagonal piece 26 having one end attached to the inside of the lower surface of the body part 23 and a receiving piece 26A formed at the other end extending diagonally downward toward the outside to receive the inner surface of the base part 20. The joint body 16 is detachably connected to the base body 15 with one touch, and forms a strong triangular truss structure together with the base body 15.

又レール受17は、前記連結部25Aに嵌着する基筒2
9と、該基筒29側面から内方にのびる上部片30A内
端に基筒29と平行な側部片30Bを下に折曲げたL字
枠30とから形成される基枠体31を具え、該基枠体3
1には、前記第1のレール具5を支持するレール受部3
3が、本例では前記基枠体31の内面に溶着される下地
枠32を介して形成される。
Moreover, the rail receiver 17 is connected to the base cylinder 2 that fits into the connecting portion 25A.
9, and an L-shaped frame 30 formed by bending a side piece 30B parallel to the base tube 29 downward at the inner end of an upper piece 30A extending inward from the side surface of the base tube 29. , the base frame body 3
1 includes a rail receiving portion 3 that supports the first rail tool 5.
3 is formed via a base frame 32 which is welded to the inner surface of the base frame body 31 in this example.

レール受部33は、前記下地枠32の各内側面にボルト
止めされることにより前記梁材3Aに沿って互いに平行
に向き合う例えば三角板状の一対の案内板35.35を
具える。又該案内板35の各内側面には、その下端近傍
に位置して水平に並びかつ第1のレール具5の下面を支
持するローラ36.36が互いに向かい合って枢支され
るとともに、ローラ36上方には、例えばフッ素系樹脂
等の低摩擦材からなる当り片37.37が取換え可能に
かつ水平に設けられる。
The rail receiving portion 33 includes a pair of guide plates 35, 35 in the shape of triangular plates, for example, which are bolted to each inner side of the base frame 32 and face each other in parallel along the beam 3A. Further, on each inner surface of the guide plate 35, rollers 36 and 36 are pivoted to face each other and are arranged horizontally near the lower end of the guide plate 35 and support the lower surface of the first rail member 5. At the top, replaceable contact pieces 37, 37 made of a low friction material such as fluororesin are provided horizontally.

なお吊りアーム4を基体15と継ぎ体16とレール受1
7とに分割する本例の構造は、その保管、持ち運び、取
付は等の取扱いを便宜とする。
Note that the hanging arm 4 is connected to the base body 15, joint body 16, and rail holder 1.
The structure of this example, which is divided into 7 parts, facilitates handling such as storage, transportation, and installation.

そしてレール受17は案内板35.35間を通る第1の
レール具5を前記ローラ36.36上に載置することに
より該第1のレール具5を支持する。
The rail receiver 17 supports the first rail tool 5 by placing the first rail tool 5 passing between the guide plates 35.35 on the rollers 36.36.

なお第1のレール具5は、第6図に示すように前記吊り
アーム4の配設間隔L゛の2倍以上の長さを有する長尺
な鋼管材からなる基体42を具え、本例では少なくとも
3つの吊りアーム4を跨がりかつ各吊りアーム4のレー
ル受17を挿通することにより前記梁材3Aと平行かつ
水平に支持される。
As shown in FIG. 6, the first rail fixture 5 includes a base body 42 made of a long steel pipe material having a length that is at least twice as long as the spacing L' between the hanging arms 4. By spanning over at least three hanging arms 4 and passing through the rail receivers 17 of each hanging arm 4, it is supported horizontally and parallel to the beam 3A.

又前記基体42は、第3.5図に示すように、前記レー
ル受17の当り片37内面に沿う側片43上縁間を上片
44で継ぐコ字状体の前記側片43下端に、前記ローラ
36上に!6!置される受片45を内向きに配するとと
もに、譲受片45内端にはリップ片46が上方に突出す
る。
As shown in FIG. 3.5, the base body 42 has a U-shaped body at the lower end of the side piece 43, which connects the upper edges of the side piece 43 along the inner surface of the contact piece 37 of the rail receiver 17 with an upper piece 44. , on said roller 36! 6! The receiving piece 45 to be placed is arranged facing inward, and a lip piece 46 projects upward from the inner end of the receiving piece 45.

従って第1のレール具5は、本例では側片43と当り片
37とが摺接することにより中方向にガタ付くことなく
ローラ36上を前記梁材3Aと平行にかつ滑らかに移動
しうるとともに、第1のレール具5は少なくとも3つの
吊りアーム4を跨る長さを有することにより他の隣り合
うレール受17Aに安定して乗継ぎできる。
Therefore, in this example, the side piece 43 and the contact piece 37 are in sliding contact with each other, so that the first rail tool 5 can smoothly move on the roller 36 parallel to the beam member 3A without rattling in the middle direction. Since the first rail fixture 5 has a length spanning at least three hanging arms 4, it can stably transfer to another adjacent rail receiver 17A.

なお本例では前記乗継ぎを滑らかに行ないうるよう基体
42両端下面を斜面で形成している。
In this example, the lower surfaces of both ends of the base body 42 are formed with slopes so that the transfer can be carried out smoothly.

又第1のレール具5両端には各位置度え位置で該レール
具5を吊りアーム4に移動不能に係止する係止金具47
がガイド孔49を用いて付設される。
Further, at both ends of the first rail tool 5, there are locking fittings 47 for immovably locking the rail tool 5 to the hanging arm 4 at each position.
is attached using the guide hole 49.

又該第1のレール具5には、該レール具5を移動する第
1の走行具6が取付く。
Further, a first traveling tool 6 for moving the rail tool 5 is attached to the first rail tool 5.

第1の走行具6は、第2のレール具7支持用の取付片5
5を設けた主部58の走行方向前後端部に、車輪56−
・−を有する走行部57を設けている。
The first running tool 6 has a mounting piece 5 for supporting the second rail tool 7.
Wheels 56-
A running portion 57 having - is provided.

前記主部58は、第7図に示すように、−本例では前記
走行方向の前後に配されかつ垂直に向く円筒状の一対の
保持管60.60と該保持管60間を継ぐ平板状の基片
61と、該基片61の中央に下段される円環状の前記取
付片55とを有し、該保持片60によって前記走行部5
7を固着する。
As shown in FIG. 7, the main portion 58 is, in this example, a pair of cylindrical holding tubes 60, 60 disposed at the front and back of the running direction and facing vertically, and a flat plate connecting between the holding tubes 60. , and the annular mounting piece 55 placed below the center of the base piece 61.
Fix 7.

又走行部57は、前記第1のレール具5のリップ片46
.46間を通りかつ保持片6oに挿入される下端がナツ
ト止めされる段付きネジ状の保持軸65と、該保持軸6
5上端にT字に固着される支軸66両端に枢着されかつ
前記第1のレール具5の受片45上を転勤する車輪56
.56とを具える。従って第1の走行具6は主部58の
前後端部に配する車輪56・−が受片45上を転勤する
ことによって例えば床パネルPを吊上げた負荷状態にお
いても円滑にかつ安定して第1のレール具5をその略全
長に亘って走行しうる。
Further, the running portion 57 is connected to the lip piece 46 of the first rail tool 5.
.. 46 and which is inserted into the holding piece 6o and whose lower end is secured with a nut, and the holding shaft 6.
5 A support shaft 66 fixed to the upper end of the shaft 66 in a T-shape; a wheel 56 pivotally connected to both ends and moving on the receiving piece 45 of the first rail device 5;
.. 56. Therefore, the first traveling implement 6 moves smoothly and stably even in a loaded state where the floor panel P is lifted, for example, by moving the wheels 56. 1 rail tool 5 can be run over substantially its entire length.

又第1の走行具6には、その取付片55に吊設される保
持金具69を介して第2のレール具7が前記第1のレー
ル具5と直角に向けて支持される・なお保持金具69は
、前記取付片55に係止されるフック状の係止片70下
端に、前記第2のレール具7を遊挿しうる内孔71Aを
第1のレール具5と直角方向に開口させた角筒状の保持
体71を具え、前記内孔71Aに第2のレール具7を挿
通することによりその一端を支持している。なお保持体
71の一側壁には内孔71Aに通じるボルト等の固着金
具72が取付き第2のレール具7を適宜の挿通位置で抜
は止めしている。
Further, a second rail tool 7 is supported on the first running tool 6 so as to be perpendicular to the first rail tool 5 via a holding metal fitting 69 suspended from the mounting piece 55 thereof. The metal fitting 69 has an inner hole 71A opened in a direction perpendicular to the first rail fitting 5, into which the second rail fitting 7 can be loosely inserted, at the lower end of a hook-shaped locking piece 70 that is locked to the mounting piece 55. The second rail 7 is inserted into the inner hole 71A to support one end thereof. A fixing metal fitting 72 such as a bolt that communicates with the inner hole 71A is attached to one side wall of the holding body 71 to prevent the second rail fitting 7 from being removed at an appropriate insertion position.

又第2のレール具7は、本例では前記第1のレール具5
と断面略同形の長尺な鋼管材から形成され、その他端は
、前記梁材3Aと向かい合う他方の上の梁材に取付く適
宜の支持手段(図示しない)により支持される。なお該
支持手段として本例では、本発明と同構成のものが用い
られる。すなわち前記他方の梁材に取付く吊りアーム4
・・・間に、第1のレール具5を梁材方向に跨設すると
ともに、該第1のレール具5に走行自在に配される第1
の走行具6に吊設する他方の保持金具69を用いて支持
している。なお支持手段としては、他に前記他方の梁材
に沿って走行しうる走行具を具えるものであれば種々の
構造のものを採用することができる。
Further, in this example, the second rail tool 7 is the same as the first rail tool 5.
The other end is supported by appropriate support means (not shown) attached to the other beam member facing the beam member 3A. Note that in this example, a support means having the same structure as the present invention is used. That is, the hanging arm 4 attached to the other beam material
. . . In between, a first rail tool 5 is installed to straddle the beam direction, and a first rail tool 5 that is movably disposed on the first rail tool 5 is provided between the first rail tool 5 and the first rail tool 5.
It is supported using the other holding fitting 69 which is suspended from the running tool 6. In addition, as the supporting means, various structures can be adopted as long as they include a running tool that can run along the other beam member.

そしてこのように両端を支持される水平な第2のレール
具7には、該第2のレール具7の全長に亘り前記梁材3
Aと直角な方向に走行しうる第2の走行具9が配される
The horizontal second rail fixture 7, which is supported at both ends in this manner, has the beam material 3 over the entire length of the second rail fixture 7.
A second traveling implement 9 that can travel in a direction perpendicular to A is arranged.

該第2の走行具9は、本例では前記第1の走行具6と同
構成をなす走行体75下端の取付片76にウィンチ8を
吊設しており、該ウィンチ8を用いて前記床パネルPを
昇降自在に吊上げうる。なお床パネルPは、例えば軽量
コンクリートを用いて形成したコンクリートパネルであ
って、本例では長手方向に貫通するパイプ状補強材の内
孔77を用いて吊上げ用の玉掛けが行われる。
In this example, the second traveling implement 9 has a winch 8 suspended from a mounting piece 76 at the lower end of a traveling body 75 having the same configuration as the first traveling implement 6, and uses the winch 8 to attach the floor to the floor. Panel P can be lifted up and down freely. Note that the floor panel P is a concrete panel formed using lightweight concrete, for example, and in this example, a sling for lifting is performed using an inner hole 77 of a pipe-shaped reinforcing material that penetrates in the longitudinal direction.

なお第8図に本発明の吊りアームの他の実施例を又第9
図に第2のレール具7及び第2の走行具9の他の実施例
を開示する。
In addition, FIG. 8 shows another embodiment of the hanging arm of the present invention, and FIG.
The figure discloses another embodiment of the second rail tool 7 and the second traveling tool 9.

第8図において吊りアーム4は、梁材3Aの下フランジ
13に取付く取付部19の継ぎ片19C内面に基部20
を設は胴部23を短寸化することにより、基体15と継
ぎ体16とを一体固着した吊りアーム4の小型化を計っ
ている。なお継ぎ体16とレール受17とをさらに一体
に形成してもよい。
In FIG. 8, the hanging arm 4 has a base 20 attached to the inner surface of the joint piece 19C of the attachment part 19 attached to the lower flange 13 of the beam member 3A.
By shortening the body portion 23, the suspension arm 4, in which the base body 15 and the joint body 16 are integrally fixed, is made smaller. Note that the joint body 16 and the rail receiver 17 may be further formed integrally.

又第9図において第2のレール具7は、互いに平行な円
筒状の一対のレール片79.79を上下に連結した複合
体からなり、又第2の走行具9は、第2のレール具7の
側面及び下面を覆うコ字枠状の主部57に第2のレール
具7の上面に沿う糸巻き状の車輪56を枢着している。
Further, in FIG. 9, the second rail tool 7 is composed of a composite body in which a pair of mutually parallel cylindrical rail pieces 79, 79 are vertically connected, and the second running tool 9 is the second rail tool 7. A spool-shaped wheel 56 along the upper surface of the second rail tool 7 is pivotally attached to a U-shaped frame-shaped main portion 57 that covers the side and lower surfaces of the second rail tool 7.

〔発明の効果〕〔Effect of the invention〕

叙上のごとく本発明の吊上げ用具は、梁材に沿って配さ
れる第1のレール具を移動する第1の走行具と、該第1
の走行具に支持されかつ梁材と直角に配される第2のレ
ール具を移動する第2の走行具とを具えるため、床パネ
ルを各敷込み位置に労力を要することなく容易にかつ迅
速に移動することができ敷込み作業を能率よくかつ精度
よく行ないうるとともに、床パネル等の落下を予防でき
作業の安全性を大巾に向上しうる。
As described above, the lifting tool of the present invention includes a first traveling tool that moves a first rail tool arranged along a beam material, and a first traveling tool that moves a first rail tool arranged along a beam material.
and a second running tool that moves the second rail tool that is supported by the running tool and arranged at right angles to the beam, it is possible to easily and easily move the floor panels to each laying position without requiring any effort. It can be moved quickly and the laying work can be carried out efficiently and accurately, and it can also prevent floor panels etc. from falling, greatly improving the safety of the work.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本発明の一実施例を示す断面図、第2図はその
一部を拡大して示す斜視図、第3図はその分解斜視図、
第4図は梁材と吊りアームの取付き状態を示す断面図、
第5図はレール受と第1のレール具との取付き状態を示
す断面図、第6図は第1のレール具の支持状態を示す断
面図、第7図は第1の走行具を示す斜視図、第8図は吊
りアームの他の実施例を示す断面図、第9図は第2のレ
ール具と第2の走行具との他の実施例を示す断面図であ
る。 2−・〜架構体、 3.3A・・・梁材、4−・吊りア
ーム、 5・−・第1のレール具、6−第1の走行具、
 7・−・・−第2のレール具、8−・・ウィンチ、 
 9・・−・第2の走行具。 1!4 図 I5 図 第7図 第8 図 A7.i−
FIG. 1 is a cross-sectional view showing one embodiment of the present invention, FIG. 2 is a perspective view showing an enlarged part of the same, and FIG. 3 is an exploded perspective view thereof.
Figure 4 is a sectional view showing how the beam material and hanging arm are installed.
Fig. 5 is a sectional view showing the mounting state of the rail receiver and the first rail tool, Fig. 6 is a sectional view showing the supporting state of the first rail tool, and Fig. 7 shows the first running tool. A perspective view, FIG. 8 is a sectional view showing another embodiment of the hanging arm, and FIG. 9 is a sectional view showing another embodiment of the second rail tool and the second traveling tool. 2-.~ Frame structure, 3.3A... Beam material, 4-- Hanging arm, 5-- First rail tool, 6- First traveling tool,
7--Second rail tool, 8--Winch,
9...Second running tool. 1!4 Figure I5 Figure 7 Figure 8 Figure A7. i-

Claims (1)

【特許請求の範囲】[Claims] 1 家屋架構体の水平な梁材に脱着自在に取付けできか
つレール受を有する吊りアームと、複数の吊りアームを
跨がり前記梁材の方向に配されるとともに前記レール受
に支持される長尺の第1のレール具と、該第1のレール
具に保持され前記梁材の方向に移動しうるとともに第1
のレール具と直角な長尺の第2のレール具を取付け可能
な第1の走行具と、第2のレール具を移動できかつウイ
ンチを有する第2の走行具とを有する吊上げ用具。
1. A hanging arm that can be detachably attached to a horizontal beam of a house frame structure and has a rail holder, and a long length that straddles the plurality of hanging arms and is arranged in the direction of the beam and is supported by the rail holder. a first rail tool held by the first rail tool and movable in the direction of the beam material;
A lifting tool having a first traveling tool to which a long second rail tool can be attached at right angles to the rail tool, and a second traveling tool capable of moving the second rail tool and having a winch.
JP32674389A 1989-12-15 1989-12-15 Lifting device Pending JPH03186594A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP32674389A JPH03186594A (en) 1989-12-15 1989-12-15 Lifting device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP32674389A JPH03186594A (en) 1989-12-15 1989-12-15 Lifting device

Publications (1)

Publication Number Publication Date
JPH03186594A true JPH03186594A (en) 1991-08-14

Family

ID=18191187

Family Applications (1)

Application Number Title Priority Date Filing Date
JP32674389A Pending JPH03186594A (en) 1989-12-15 1989-12-15 Lifting device

Country Status (1)

Country Link
JP (1) JPH03186594A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111217108A (en) * 2020-04-17 2020-06-02 湖南中矿金禾机器人研究院有限公司 A single track robot system of patrolling and examining for extreme environment band conveyer

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111217108A (en) * 2020-04-17 2020-06-02 湖南中矿金禾机器人研究院有限公司 A single track robot system of patrolling and examining for extreme environment band conveyer

Similar Documents

Publication Publication Date Title
CN212773624U (en) Hanging, hanging and pulling supporting device suitable for steel bar truss floor bearing plate
JP2007046356A (en) Scaffold in bridge structure and its assembling method
JP6101556B2 (en) Material transfer device
JPH03186594A (en) Lifting device
JPH0372165A (en) Lifting fixture
CN111704058B (en) Hoisting and lifting device
CN212101770U (en) Double-rail device convenient to install and detach quickly and used for hoisting curtain wall unit plate
CN211257761U (en) Lifting type elevator shaft operating platform
JPH03186595A (en) Lifting device
CN208648517U (en) Cladding glass installation self-control electric hoist hanger system
JP2612435B2 (en) Overhead crane
CN107916790B (en) System and method for dismantling guide pipe of assembled construction steel bar of building block
JPH0765396B2 (en) Lifting equipment
CN216471907U (en) Assembled movable multidirectional adjusting hoisting platform
CN218758647U (en) High altitude steel truss annular track electric hanging basket structure of encorbelmenting
CN218205793U (en) Steel structure air accumulation traction sliding device
JPH0629366Y2 (en) Rails for transporting panels, etc. and their connecting devices at construction sites
JPH0442322Y2 (en)
JPS5812990Y2 (en) Building loading platform
JPH0629365Y2 (en) Support device for rails for transporting panels etc. at construction sites
CN214423737U (en) Adjustable ceiling keel mounting assembly
CN215760543U (en) Gravity type sliding rail non-manned unloading platform
JPH0978842A (en) Crane for scaffold
CN216105745U (en) A construction equipment for isolation bearing transportation and hoist and mount
CN213710115U (en) Can have enough to meet need stirrup