JPH0313503Y2 - - Google Patents

Info

Publication number
JPH0313503Y2
JPH0313503Y2 JP1984078177U JP7817784U JPH0313503Y2 JP H0313503 Y2 JPH0313503 Y2 JP H0313503Y2 JP 1984078177 U JP1984078177 U JP 1984078177U JP 7817784 U JP7817784 U JP 7817784U JP H0313503 Y2 JPH0313503 Y2 JP H0313503Y2
Authority
JP
Japan
Prior art keywords
control operation
indicator light
input
earthquake
contact
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP1984078177U
Other languages
Japanese (ja)
Other versions
JPS60190777U (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP7817784U priority Critical patent/JPS60190777U/en
Publication of JPS60190777U publication Critical patent/JPS60190777U/en
Application granted granted Critical
Publication of JPH0313503Y2 publication Critical patent/JPH0313503Y2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Indicating And Signalling Devices For Elevators (AREA)
  • Maintenance And Inspection Apparatuses For Elevators (AREA)

Description

【考案の詳細な説明】 [産業上の利用分野] この考案は、エレベータを監視する装置の改良
に関するものである。
[Detailed Description of the Invention] [Industrial Application Field] This invention relates to an improvement of a device for monitoring elevators.

[従来の技術] 第1図及び第2図により、従来のエレベータの
監視装置を説明する。
[Prior Art] A conventional elevator monitoring device will be explained with reference to FIGS. 1 and 2.

第1図は、管理人室等に設けられた監視盤を示
す図で、図中、WBは監視盤、AKは地震管制運
転用のキースイツチ、ALはその表示灯、BKは
火災管制運転用のキースイツチ、BLはその表示
灯、CKは停電時の自家発管制運転用のキースイ
ツチ、CLはその表示灯、ULは上昇運転時の方向
灯、DLは下降運転時の方向灯、PLはかご位置の
表示灯である。なおここでは4台のエレベータが
並設されている場合を例にとつて示している。
Figure 1 shows a monitoring panel installed in a manager's room, etc. In the figure, WB is the monitoring panel, AK is the key switch for earthquake control operation, AL is the indicator light, and BK is the one for fire control operation. The key switch, BL is the indicator light, CK is the key switch for private power generation control operation during power outage, CL is the indicator light, UL is the direction light during upward operation, DL is the direction light during downward operation, PL is the direction light for car position. It is an indicator light. Here, an example is shown in which four elevators are installed in parallel.

第2図は、管制運転表示灯の点灯回路で、図
中、(+)及び(−)は制御用の電源母線、Aaは
地震管制運転指令が入力されると付勢し、管制運
転を終了すると消勢する地震管制運転リレー(図
示省略)の常開接点、Baは同様な動作を行なう
火災管制運転リレー(図示省略)の常開接点、
Caは同様に自家発管制運転リレー(図示省略)
の常開接点である。
Figure 2 shows the lighting circuit for the control operation indicator light. In the figure, (+) and (-) are power supply buses for control, and Aa is energized when an earthquake control operation command is input, ending control operation. Then, Ba is the normally open contact of the earthquake control operation relay (not shown), which de-energizes, and Ba is the normally open contact of the fire control operation relay (not shown), which performs the same operation.
Similarly, Ca is a private power generation control operation relay (not shown)
It is a normally open contact.

以上の構成において、例えばキースイツチAK
が操作され地震管制運転指令が入力されると、地
震管制運転リレーが付勢されて接点Aaが閉路し、
地震管制運転の表示灯ALが点灯される。また、
この状態でキースイツチBKを操作すると、接点
Baの閉路により火災管制運転用の表示灯BLも点
灯される。
In the above configuration, for example, the key switch AK
When is operated and an earthquake control operation command is input, the earthquake control operation relay is energized and contact Aa is closed.
The earthquake control operation indicator light AL is lit. Also,
If you operate key switch BK in this state, the contacts will
By closing Ba, the fire control operation indicator light BL is also lit.

[発明が解決しようとする問題点] 従来の構成では、表示灯の点灯回路は各管制運
転で互いに独立しているため、例えば停電時に火
災や地震が発生して複数の管制運転指令が入力さ
れると、エレベータは予め定められた優先順位に
従つて管制運転を行なうにも拘わらず、表示灯の
方は管制運転指令が入力されたものはすべて点灯
するため、管理人等は果してどの管制運転が行な
われているのか分らず、無用な混乱を招く原因と
なつていた。
[Problems to be Solved by the Invention] In the conventional configuration, the lighting circuits for the indicator lights are independent of each other for each control operation, so for example, if a fire or earthquake occurs during a power outage, multiple control operation commands may be input. In this case, even though the elevator performs controlled operation according to a predetermined priority order, the indicator lights will light up for all control operation commands input, so the manager etc. will not know which control operation is being performed. It was unclear whether the system was being implemented, causing unnecessary confusion.

[問題点を解決するための手段] 本考案は上記問題点を解決するため、各管制運
転の表示灯に関連を持たせ、複数の管制運転指令
が入力された場合には、予め定められた優先順位
に従つて行われる管制運転のうち、その時点で最
も優先する管制運転の表示灯のみ点灯し、他は消
灯させるか、或いは運転指令の入力された管制運
転の表示灯はすべて点灯し、その時点で最優先の
表示灯のみをフリツカさせるなどのように、管制
運転指令の入力数に拘らず、その時点で最も優先
する管制運転すなわち実際に行われている管制運
転を、他の管制運転とは異なる態様で表示する手
段を備えたことを特徴とする。
[Means for Solving the Problems] In order to solve the above problems, the present invention relates the indicator lights for each control operation, and when multiple control operation commands are input, a predetermined Among the control operations carried out according to the priority order, only the indicator light of the control operation with the highest priority at that time is turned on and the others are turned off, or all the indicator lights of the control operation to which the operation command has been input are turned on. Regardless of the number of input control operation commands, such as flickering only the highest priority indicator light at that time, the control operation that has the highest priority at that time, that is, the control operation that is actually being carried out, can be set aside from other control operations. It is characterized by comprising means for displaying in a manner different from that of the above.

[実施例] 第3図は、本考案における表示灯の点灯回路の
一実施例を示す図で、図中、Abは前述の地震管
制運転リレーの常閉接点、Bbは火災管制運転リ
レーの常閉接点、その他は第2図と同様である。
ここでは管制運転の優先順位としては、地震管制
運転、火災管制運転、自家発管制運転の順である
場合を示している。
[Example] Fig. 3 is a diagram showing an example of the indicator light lighting circuit according to the present invention. The closing contacts and others are the same as in FIG. 2.
Here, a case is shown in which the order of priority for control operation is earthquake control operation, fire control operation, and private generation control operation.

以上の構成において、いまキースイツチAK〜
CKが操作され、すべての管制運転指令が入力さ
れたとすると、接点Aa〜Caはすべて閉路すると
共に図示しない回路により最も優先される地震管
制運転が開始される。この時、表示灯ALが点灯
し地震管制運転中であることが表示されるが、接
点Abが開路しているため、他の表示灯BL及び
CLは消灯している。やがて地震管制運転が終了
すると接点Aaは開路し表示灯ALが消灯すると共
に、接点Abは閉路し今度は次に優先される火災
管制運転の表示灯BLが点灯される。火災管制運
転が終了すると同様にして、今度は自家発管制運
転が行なわれ、表示灯CLのみが点灯する。こう
して管制運転指令が複数入力されていても、常に
現在行なわれている管制運転の表示灯のみが点灯
する。
In the above configuration, the key switch AK~
When CK is operated and all control operation commands are input, all contacts Aa to Ca are closed, and the most prioritized earthquake control operation is started by a circuit not shown. At this time, indicator light AL lights up to indicate that earthquake control operation is in progress, but since contact AB is open, other indicator lights BL and
CL is off. When the earthquake control operation is eventually completed, the contact Aa is opened and the indicator light AL is turned off, while the contact Ab is closed and the indicator light BL for the fire control operation, which has the next priority, is turned on. When the fire control operation is completed, a private fire control operation is carried out in the same way, and only the indicator light CL lights up. In this way, even if a plurality of control operation commands are input, only the indicator light for the control operation currently being performed is always lit.

第4図は、本考案における表示灯の点灯回路の
他の一実施例を示す図で、図中、Aa1〜Aa4は前
述の地震管制運転リレーの常開接点、Ba1〜Ba3
は同様に火災管制運転リレーの常開接点、Ca1
びCa2は自家発管制運転リレーの常開接点、Fは
フリツカリレー、F1〜F3はその接点である。
FIG. 4 is a diagram showing another embodiment of the indicator lamp lighting circuit according to the present invention. In the figure, Aa 1 to Aa 4 are normally open contacts of the earthquake control operation relay described above, and Ba 1 to Ba 3
Similarly, Ca 1 and Ca 2 are normally open contacts of the fire control operation relay, F is a flicker relay, and F 1 to F 3 are their contacts.

以上の構成において、いまキースイツチAK〜
CKが操作され、すべての管制運転指令が入力さ
れたとすると、接点Aa〜Aa4、Ba1〜Ba3、Ca1
〜Ca2が閉路し、フリツカリレーFは付勢され、
地震管制運転が開始される。この時、表示灯AL
〜CLはすべて点灯されるが、接点F1により表示
灯ALのみがフリツカし地震管制運転が行なわれ
ていることを知らせる。やがて地震管制運転が終
了すると接点Aa2の開路により表示灯ALは消灯
し、また接点Aa3の開路により接点F2を介して今
度は表示灯BLがフリツカし、火災管制運転が行
なわれていることを表示する。同様にして火災管
制運転終了後は、自家発管制運転が行なわれ表示
灯CLのみがフリツカする。こうして管制運転指
令の入力されて表示灯はすべて点灯すると共に、
そのうち現在行なわれている管制運転の表示灯の
みがフリツカする。
In the above configuration, the key switch AK~
Assuming that CK is operated and all control operation commands are input, contacts Aa to Aa 4 , Ba 1 to Ba 3 , Ca 1
~Ca 2 is closed, the flickering relay F is energized,
Earthquake control operation begins. At this time, the indicator light AL
~CL are all lit, but only the indicator light AL flickers due to contact F1 , indicating that earthquake control operation is in progress. Eventually, when the earthquake control operation ends, the indicator light AL goes out due to the opening of contact Aa 2 , and the indicator light BL flickers through contact F 2 due to the opening of contact Aa 3 , indicating that fire control operation is being performed. Show that. Similarly, after the fire control operation is completed, the private fire control operation is performed and only the indicator light CL flickers. In this way, the control operation command is input and all the indicator lights turn on, and
Of these, only the indicator light for the currently underway controlled operation flickers.

[考案の効果] 本考案によれば、万が一異常事態の発生が重な
り複数の管制運転の指令が入力されても、どの管
制運転が実際に行なわれているかを管理人等は明
確に知ることができ、無用な混乱や操作ミスを防
止することができる。
[Effects of the invention] According to the invention, even if an abnormal situation occurs and multiple control operation commands are input, the manager etc. will be able to clearly know which control operation is actually being carried out. This can prevent unnecessary confusion and operational errors.

なお、管制運転中の表示灯とともに管制運転の
完了を示す表示灯を別に設けたものもあるが、こ
の完了を示す表示灯についても同様に本考案を適
用することができる。
It should be noted that some vehicles are equipped with a separate indicator light indicating the completion of the controlled operation along with an indicator light indicating the completion of the controlled operation, and the present invention can be similarly applied to the indicator light indicating the completion of the controlled operation.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図及び第2図は従来のエレベータ監視装置
の説明図、第3図は本考案における表示灯の点灯
回路の一例を示す図、第4図は本考案における表
示灯の点灯回路の他の実施例を示す図である。 WB……監視盤、AK……地震管制運転用のキ
ースイツチ、BK……火災管制運転用のキースイ
ツチ、CK……自家発管制運転用のキースイツチ、
AL〜CL……表示灯、Aa,Ab……地震管制運転
リレーの接点、Ba,Bb……火災管制運転リレー
の接点、Ca……自家発管制運転リレーの接点。
1 and 2 are explanatory diagrams of a conventional elevator monitoring device, FIG. 3 is a diagram showing an example of the indicator light lighting circuit according to the present invention, and FIG. 4 is a diagram showing another example of the indicator light lighting circuit according to the present invention. It is a figure showing an example. WB...Monitoring board, AK...key switch for earthquake control operation, BK...key switch for fire control operation, CK...key switch for private power generation control operation,
AL~CL... Indicator light, Aa, Ab... Earthquake control operation relay contact, Ba, Bb... Fire control operation relay contact, Ca... Private generation control operation relay contact.

Claims (1)

【実用新案登録請求の範囲】[Scope of utility model registration request] 管制運転指令が入力されるとそれを監視盤に表
示するエレベータの監視装置において、複数の管
制運転指令が入力されると、予め定められた優先
順位に従つて行われる管制運転のうち、その時点
で最も優先する管制運転を他の管制運転とは異な
る態様で表示する手段を備えたことを特徴とする
エレベータの監視装置。
When a controlled operation command is input, the elevator monitoring device displays it on the monitoring panel.When multiple controlled operation commands are input, one of the controlled operations performed according to a predetermined priority order is displayed at that moment. 1. An elevator monitoring device characterized by comprising means for displaying a controlled operation given highest priority in a manner different from other controlled operations.
JP7817784U 1984-05-28 1984-05-28 Elevator monitoring device Granted JPS60190777U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP7817784U JPS60190777U (en) 1984-05-28 1984-05-28 Elevator monitoring device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP7817784U JPS60190777U (en) 1984-05-28 1984-05-28 Elevator monitoring device

Publications (2)

Publication Number Publication Date
JPS60190777U JPS60190777U (en) 1985-12-17
JPH0313503Y2 true JPH0313503Y2 (en) 1991-03-27

Family

ID=30621917

Family Applications (1)

Application Number Title Priority Date Filing Date
JP7817784U Granted JPS60190777U (en) 1984-05-28 1984-05-28 Elevator monitoring device

Country Status (1)

Country Link
JP (1) JPS60190777U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2003076323A1 (en) * 2002-03-13 2003-09-18 Toshiba Elevator Kabushiki Kaisha Elevator control device

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS57120558U (en) * 1981-01-14 1982-07-27
JPS58123871U (en) * 1982-02-17 1983-08-23 三菱電機株式会社 Elevator abnormality display device

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2003076323A1 (en) * 2002-03-13 2003-09-18 Toshiba Elevator Kabushiki Kaisha Elevator control device
CN1294064C (en) * 2002-03-13 2007-01-10 东芝电梯株式会社 Elevator control device

Also Published As

Publication number Publication date
JPS60190777U (en) 1985-12-17

Similar Documents

Publication Publication Date Title
JPH0313503Y2 (en)
CN100475680C (en) Operating unit of elevator at the time of power interruption
JPS6126303Y2 (en)
JPS5926591B2 (en) Elevator control operation display
JPS606059Y2 (en) Construction shutter open/close confirmation device
JPH0219914Y2 (en)
JPS6331193Y2 (en)
JPS5925812Y2 (en) Interlocking electric lifting device
JPH0638059Y2 (en) Elevator operation control panel
JPH06329364A (en) Elevator troubled condition display device
JPH072446A (en) Inspecting device for elevator display lamp
JPS61282280A (en) Maintaining device for elevator
JPS6326375Y2 (en)
JPH0638057Y2 (en) Elevator monitoring equipment
JPS6031306B2 (en) Remote monitoring control device
JPH01264538A (en) Home controller
JPS5937881Y2 (en) indicator light circuit
KR920001000Y1 (en) Display devices of elevator message
JPS62205976A (en) Annunciator for elevator
JPH0455651A (en) Remote control device for air conditioner
JPH0247582U (en)
JPH0749254B2 (en) Railway vehicle light control device
JPS59158774A (en) Controller for elevator
JPS63217498A (en) Control center
JPH04327475A (en) Power source cut-off preventing device for elevator