JPH0144867B2 - - Google Patents

Info

Publication number
JPH0144867B2
JPH0144867B2 JP60049670A JP4967085A JPH0144867B2 JP H0144867 B2 JPH0144867 B2 JP H0144867B2 JP 60049670 A JP60049670 A JP 60049670A JP 4967085 A JP4967085 A JP 4967085A JP H0144867 B2 JPH0144867 B2 JP H0144867B2
Authority
JP
Japan
Prior art keywords
formwork
bolt
fixed
cone
support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP60049670A
Other languages
Japanese (ja)
Other versions
JPS60242256A (en
Inventor
Takao Suzuki
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nisso Sangyo Co Ltd
Original Assignee
Nisso Sangyo Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nisso Sangyo Co Ltd filed Critical Nisso Sangyo Co Ltd
Priority to JP4967085A priority Critical patent/JPS60242256A/en
Publication of JPS60242256A publication Critical patent/JPS60242256A/en
Publication of JPH0144867B2 publication Critical patent/JPH0144867B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Movable Scaffolding (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Description

【発明の詳細な説明】 本発明は鉄骨鉄筋コンクリート構造物におい
て、天井梁、床等の躯体を形成する際に使用する
型枠、吊り足場の荷重を支えるようにした型枠と
吊り足場の荷重を担持する支持装置に関する。
DETAILED DESCRIPTION OF THE INVENTION In steel reinforced concrete structures, the present invention is designed to support the formwork used to form the frame of ceiling beams, floors, etc., the formwork designed to support the load of the suspended scaffold, and the load of the suspended scaffold. The present invention relates to a supporting device for carrying.

一般にコンクリート打設用の型枠の設計は支保
工と関連し、荷重に対して十分安全で完成後の構
造物の形状、寸法の誤差と型枠の構造を考えてコ
ンクリート構造物が完成するまで狂いの起らない
ように堅固に設計しなければならない。型枠およ
び支保工が工事中にうける荷重は、型枠自体、コ
ンクリート、作業員、施工機械器具等からうける
荷重、衝撃による垂直方向荷重と、風圧、勾配、
流水圧、作業時の振動等に起因する横方向荷重
と、及びコンクリートの側圧とを有し、これらの
荷重を十分支えるだけの型枠支持装置の建設は非
常に困難である。
Generally, the design of formwork for concrete pouring is related to shoring, and it is necessary to ensure sufficient safety against the load until the concrete structure is completed, taking into consideration the shape and dimensional errors of the completed structure and the structure of the formwork. It must be designed firmly so that it does not go awry. The loads that formwork and shoring receive during construction include loads from the formwork itself, concrete, workers, construction equipment, etc., vertical loads due to impact, wind pressure, slope,
It is extremely difficult to construct a formwork support device that can sufficiently support the lateral loads caused by water pressure, vibrations during work, and the lateral pressure of concrete.

一方鉄骨鉄筋コンクリート構造物、例えば高層
ビルデイングに於ける梁施工工程は鉄骨加工作
業、鉄骨建方、仮止め作業の後吊り足場を仮設
し、この吊り足場を利用して溶接又はH.T.B締め
作業、配筋作業を行ない、この作業が終ると前記
吊り足場を解体撤去していた。次に脚立、梯子、
枠組足場を利用して型枠組立作業、型枠内へのコ
ンクリート打設、型枠解体、仕上げ作業を順次行
なつている。この為、上記の場合鉄骨組立、配筋
作業用の吊り足場と、型枠の組立、解体用の足場
は別々に行なつている為に作業性が悪く、部品点
数が多くコスト的に非常に不利であり省力化が特
に望まれているものである。
On the other hand, in the beam construction process for steel reinforced concrete structures, such as high-rise buildings, a suspended scaffold is temporarily erected after steel frame processing work, steel frame erection, and temporary fixing work, and this suspended scaffold is used for welding, HTB tightening work, and reinforcement work. After the work was completed, the suspended scaffolding was dismantled and removed. Next, a stepladder, a ladder,
Formwork assembly work, concrete pouring into the formwork, formwork dismantling, and finishing work are carried out in sequence using framed scaffolding. For this reason, in the above case, the suspended scaffolding for steel frame assembly and reinforcement work and the scaffolding for formwork assembly and dismantling are performed separately, resulting in poor work efficiency and a large number of parts, which is extremely costly. This is disadvantageous, and labor saving is particularly desired.

しかも型枠は上記のような荷重に耐えるべく縦
方向と横方向から支持部材で支えており、縦方向
の支持部材としては地表もしくは下段の床面より
型枠下部まで起立させたパイプサポート、枠組足
場、一本の四角支柱、タイハンガーを使用してお
り、これらの支持部材の組立、解体作業が非常に
面倒で困難であり、その高さが4.5m以上あるよ
うな場合には実際これらの支持部材の組立は不可
能に近く、使用中に揺れたり、傾斜したりした場
合には危険であるばかりか型枠に寸法誤差等の悪
影響をおよぼすものである。更に横方向からの締
め付け支持部材はフオームタイを使用しているが
その着脱作業が面倒で困難であり、部品点数も多
くコストアツプの原因となつており、着脱や構造
が簡単で費用の安価な支持装置の開発が望まれて
いる。
In addition, the formwork is supported by support members from both the vertical and horizontal directions in order to withstand the above loads, and the vertical support members include pipe supports and frameworks that stand up from the ground or lower floor to the bottom of the formwork. Scaffolding, a single square support, and a tie hanger are used, and the assembly and disassembly of these supporting members is extremely troublesome and difficult, and in cases where the height is 4.5 m or more, it is difficult to assemble and disassemble these supporting members. It is nearly impossible to assemble the support member, and if it shakes or tilts during use, it is not only dangerous, but also causes negative effects such as dimensional errors on the formwork. Furthermore, form ties are used as support members for tightening from the lateral direction, but the work of attaching and detaching them is cumbersome and difficult, and the number of parts is large, causing an increase in costs. development is desired.

この為に吊り足場を利用し、この足場で一連の
梁施工、即ち鉄骨組立からコンクリートの仕上げ
及び型枠の解体までの作業を続けて行なえ、又下
段の床や地表から特別な支持部材を組立てること
なく型枠の組立と支持ができ、着脱が容易で構造
が簡単でありコンクリート構造の梁および床等の
躯体の施工を著しい低コストで行なえるようにし
た躯体の成形装置が開発されている。
For this purpose, suspended scaffolding is used, on which a series of beam construction operations can be carried out, from erection of the steel frame to finishing of the concrete and dismantling of the formwork, and special supporting members can be erected from the lower floor or ground surface. A framework forming apparatus has been developed that allows for the assembly and support of formwork without any hassle, is easy to install and remove, has a simple structure, and allows construction of frameworks such as beams and floors of concrete structures at a significantly low cost.

例えばこの躯体の成形装置として、特開昭54−
9424号公報に開示されたものが知られているが、
この装置では型枠と吊り足場の荷重を支持する機
構が鉄骨に装着される四つの締付ボルトと、この
ボルトに装着される四つのライナーセパレータ
と、ライナーセパレーターの下部に設けたコーン
と、ライナーセパレーター及びコーンに螺合され
ると共に大引部材を担持する四つの締付ボルトと
からなつている為に部品点数が多いこと、各
部がばらばらで独立しているから各部品同志の位
置合せが困難であること、各部品の組み付け工
数が多く現場での組み付け作業が著しく低下する
こと、セパレーターを鉄骨に組み付けてもこの
位置が大引部材側から差し込まれるボルトと軸芯
が一致しない場合が多く、これを修正する作業が
大変であること、セパレーターとボルトとの軸
芯が一致しないまゝ強引に組み付けると大引部分
が傾斜したり、ボルトがまがつたり、大引部材を
破損させたりする場合が生じること、鉄骨にセ
パレーターを組み付けるには鉄骨に四つの孔を穿
ち、この孔からボルトを差し込む為、孔加工が大
変であり、併せて他の部品に対する芯出しが困難
であること、部品点数が多く、各部品がばらば
らであることから持ち運びが不便であること、
締付ボルトを差し込む時ガイドが無いから締め付
け時の方向性が悪いこと、締付ボルトに応力が
集中した時ボルトが曲つてしまうこと、等の欠点
を有するものである。
For example, as a molding device for this frame,
The one disclosed in Publication No. 9424 is known,
In this device, the mechanism that supports the load of the formwork and suspended scaffolding consists of four tightening bolts attached to the steel frame, four liner separators attached to these bolts, a cone installed at the bottom of the liner separator, and a liner. It consists of a separator and four tightening bolts that are screwed into the cone and supports the main tension member, so there are many parts, and each part is separate and independent, making it difficult to align each part. , the number of man-hours required to assemble each part is large, which significantly reduces the on-site assembly work, and even when the separator is assembled to the steel frame, this position often does not align with the axis of the bolt inserted from the main member side. The work to correct this is difficult, and if the axes of the separator and bolt are not aligned and the separator is forcibly assembled, the main part may be tilted, the bolt may become twisted, or the main part may be damaged. In order to assemble a separator to a steel frame, four holes are drilled in the steel frame and bolts are inserted through these holes, which makes hole machining difficult, and it is also difficult to center the parts with respect to other parts. There are many parts and each part is separated, making it inconvenient to carry.
This method has drawbacks such as the lack of a guide when inserting the tightening bolt, which causes poor directionality during tightening, and the bolt bending when stress is concentrated on the tightening bolt.

従つて本発明の目的は部品点数が少なく、位置
合せや芯出しが正確且つ容易であり、組み付け、
作業を著しく向上できる、ボルトの曲がりを防止
できる躯体の成形装置における型枠と吊り足場の
荷重を担持する支持装置を提供することである。
Therefore, the object of the present invention is to have a small number of parts, accurate and easy alignment and centering, and easy assembly.
To provide a support device for carrying the load of formwork and suspended scaffolding in a building frame forming device, which can significantly improve work and prevent bolts from bending.

本発明はこの目的を達成するため鉄骨梁に対し
て大引部材を着脱自在に連結させ、大引部材の下
方に吊り足場を連結し、吊り足場上で鉄骨の
鋲、溶接、配筋、型枠の組立、解体、コンクリー
トの打設及び仕上げ作業を連続して行なう躯体の
成形装置に於て、鉄骨梁の下部に少なくとも二つ
の連結桿を一体に設けた固定ピースを固定させこ
の連結桿の下部にはコーンが固定され、前記大引
部材には縦方向にカラーが挿入固定され、このカ
ラー内には大引部材を支持するボルトを着脱自在
に挿入させ、当該ボルトが大引部材を保持して前
記コーンに螺着されるようにしたことを特徴とす
るものである。
In order to achieve this object, the present invention connects a large tension member to a steel beam in a removable manner, connects a suspended scaffold below the large tension member, and connects the steel frame with rivets, welding, reinforcement, and molding on the suspended scaffold. In frame forming equipment that continuously performs frame assembly, disassembly, concrete pouring, and finishing work, a fixed piece with at least two connecting rods is fixed to the bottom of a steel beam, and the connecting rods are A cone is fixed to the lower part, a collar is inserted and fixed in the vertical direction into the Ohiki member, and a bolt that supports the Ohiki member is removably inserted into this collar, and the bolt holds the Ohiki member. It is characterized in that it is screwed onto the cone.

以下本発明の実施の態様を図面について説明す
る。
Embodiments of the present invention will be described below with reference to the drawings.

躯体の成形装置は第1図に示すように鉄骨鉄筋
コンクリート構造物、例えば高層ビルデイングに
於て、床1や梁2等の躯体をコンクリートを打設
して形成する場合、そのコンクリート打設用型枠
3,4,5を支持装置で支持させると同時に、こ
の支持装置に吊り下げた足場6上で鉄骨の組立、
配筋作業及び型枠の組立、解体、コンクリートの
打設、仕上げ作業も連続して行なえるようにした
ものである。
As shown in Fig. 1, the frame forming equipment is used to form a concrete-casting form when forming the frame of a steel-framed reinforced concrete structure, such as a high-rise building, by pouring concrete such as floors 1 and beams 2. 3, 4, and 5 are supported by a support device, and at the same time, the steel frame is assembled on a scaffold 6 suspended from this support device.
It is designed to allow reinforcement work, formwork assembly and dismantling, concrete pouring, and finishing work to be carried out continuously.

型枠支持装置7は水平なC型チヤンネル鋼から
なる梁用大引部材8と、この大引部材8の両サイ
ドに起立する端太部材9と、大引部材8と交叉す
る方向に延びる根太用支持桿10と、端太部材9
に着脱自在に連結した側板固定部材11と、大引
部材8を鉄骨12側に着脱させる取り付け部材1
3と、端太部材9の上部に設けた支保梁支持部材
14とからなつている。
The formwork support device 7 includes a beam extension member 8 made of horizontal C-shaped channel steel, thick members 9 standing on both sides of the extension member 8, and joists extending in a direction intersecting the extension member 8. support rod 10 and end member 9
A side plate fixing member 11 that is detachably connected to the side plate, and a mounting member 1 that attaches and detaches the large pull member 8 to the steel frame 12 side.
3, and a support beam support member 14 provided on the upper part of the thick member 9.

梁用大引部材8の両サイド上面には長孔15と
ボルト16を介して断面L字状のブラケツト17
が位置調整自在に着脱されるようにし、このブラ
ケツト17にはソケツト18が溶接等で固定さ
れ、このソケツト18には四角柱状端太部材9が
着脱自在に挿入されて上方に起立し、この端太部
材9の上部にはソケツトを介して支保梁支持部材
14の基端19が着脱自在に挿入されるようにな
つている。支保梁支持部材14は基端19の上部
には梁20を介してコ字状の支持枠21が固定さ
れ、この支持枠21にはピン孔を介して高さ調整
自在に引掛け片23が連結され、フロアー用型枠
3を支える支保梁24の端部がこの引掛け片23
に係合して支えられるようになつている。
Brackets 17 having an L-shaped cross section are attached to the upper surface of both sides of the beam extension member 8 through elongated holes 15 and bolts 16.
A socket 18 is fixed to this bracket 17 by welding or the like, and a rectangular column-shaped end member 9 is removably inserted into this socket 18 and stands upwardly, and this end The base end 19 of the support beam support member 14 is removably inserted into the upper part of the thick member 9 via a socket. A U-shaped support frame 21 is fixed to the upper part of the base end 19 of the support beam support member 14 via a beam 20, and a hook piece 23 is attached to the support frame 21 through a pin hole so that the height can be freely adjusted. The end of the supporting beam 24 that is connected and supports the floor formwork 3 is attached to this hook piece 23.
It is designed so that it can be engaged with and supported.

ソケツト18の前後側面にはコ字状に張出した
受け部材5が設けられ、他方側板固定部材11の
端部にはフツクが設けられ、このフツクを受け部
材5に差し込むことにより大引部材8と直角方向
に側板固定部材11が延長して保持される。側板
固定部材11は縦横に交叉する複数の四角柱状支
持桿26,27が形成されている。
A U-shaped receiving member 5 is provided on the front and rear sides of the socket 18, and a hook is provided at the end of the other side plate fixing member 11. By inserting this hook into the receiving member 5, the large pull member 8 and The side plate fixing member 11 is extended and held in the right angle direction. The side plate fixing member 11 is formed with a plurality of square column-shaped support rods 26 and 27 that intersect vertically and horizontally.

梁用大引部材8には一つもしくは複数の補強板
28が固定され、この補強板28の上面と大引部
材8の上面には下方に向けて溝29を切欠き、こ
の溝29には前記根太用支持桿10が挿入されて
大引部材8と直交する方向に延長し、これは梁底
型枠5の下部を支えるようになつている。但し根
太用支持桿10は溝29に挿入することなく、大
引部材8の上面に直接当接させても使用可能であ
る。支持桿10はパイプ状の単管でもよく、四角
柱その他の多角柱でもよく、外周に滑り止めを形
成したものでも使用可能である。
One or more reinforcing plates 28 are fixed to the beam tensioning member 8, and a groove 29 is cut downward in the upper surface of the reinforcing plate 28 and the upper surface of the tensioning member 8. The support rod 10 for the joist is inserted and extends in a direction perpendicular to the main drawer 8, so as to support the lower part of the beam bottom form 5. However, the joist support rod 10 can be used even if it is brought into direct contact with the upper surface of the tension member 8 without being inserted into the groove 29. The support rod 10 may be a single pipe, a square prism or other polygonal prism, or one with a non-slip surface formed on its outer periphery.

梁用大引部材8のほぼ中央には一つもしくは複
数のカラー30が縦方向に挿入固定され、このカ
ラー30内にボルト31が着脱自在に螺合され、
このカラー30とボルト31で取り付け部材13
を形成している。但しこの取り付け部材13はそ
の他同様の手段を使用しても良い。
One or more collars 30 are inserted and fixed in the vertical direction approximately in the center of the beam tension member 8, and bolts 31 are removably screwed into the collars 30.
Mounting member 13 with this collar 30 and bolt 31
is formed. However, other similar means may be used for this attachment member 13.

他方梁2内にうめ込まれる鉄骨梁12の下面に
は本発明の一実施例に係る型枠と吊り足場の荷重
を担持する支持装置が設けられている。即ち、鉄
骨梁12には固定ピース32が溶接等で一体に固
定され、この固定ピース32には二つの取り付け
部たるボルト等の連結桿33がねじもしくは溶接
等で固定され、この連結桿33の下部にはコーン
34が一体に固定され、このコーン34にはカラ
ー30に挿入された大引部材保持用のボルト31
の上端が着脱自在に螺着されるようになつてい
る。この時ボルト31は梁底型枠5に穿つた孔を
貫通するようになつている。
On the other hand, the lower surface of the steel beam 12 embedded in the beam 2 is provided with a support device for carrying the load of the formwork and suspended scaffolding according to an embodiment of the present invention. That is, a fixed piece 32 is integrally fixed to the steel beam 12 by welding or the like, and a connecting rod 33 such as a bolt, which is two attachment parts, is fixed to this fixed piece 32 by screws or welding. A cone 34 is integrally fixed to the lower part, and a bolt 31 for holding the tension member inserted into the collar 30 is attached to the cone 34.
The upper end is designed to be removably screwed on. At this time, the bolt 31 passes through a hole drilled in the beam bottom formwork 5.

但しコーン34を使用することなく連結桿33
にねじ溝を形成し、このねじ溝にボルト31を直
接螺合しても使用可能である。次に梁用大引部材
8の下面中央にはブラケツト35が一体に固定さ
れ、このブラケツト35には吊り足場6の支持ア
ーム36がボルト37を介して着脱自在に連結さ
れ、支持アーム36には水平な足場枠38が固定
され、更にこの足場枠38上には足場板39と手
摺40が固定されるようになつている。
However, the connecting rod 33 can be connected without using the cone 34.
It can also be used by forming a thread groove in the thread groove and directly screwing the bolt 31 into this thread groove. Next, a bracket 35 is integrally fixed to the center of the lower surface of the beam tension member 8, and a support arm 36 of the hanging scaffold 6 is detachably connected to this bracket 35 via a bolt 37. A horizontal scaffold frame 38 is fixed, and furthermore, a scaffold board 39 and a handrail 40 are fixed on this scaffold frame 38.

次に躯体の成形装置の組立から解体までの行程
について述べる。
Next, we will discuss the process from assembly to disassembly of the frame forming equipment.

鉄骨梁12が組立てられた状態に於て、先ず梁
用大引部材8に梁底型枠5を置いた上でこの大引
部材をボルト31を介してコーン34に固定させ
る。又併せて吊り足場6もブラケツト35に固定
して吊り下げる。この作業はリフター等によつて
簡単に行ない、この作業が終わればリフターは撤
去して良い。
When the steel beam 12 is assembled, first, the beam bottom form 5 is placed on the beam extension member 8, and then this extension member is fixed to the cone 34 via bolts 31. At the same time, the hanging scaffold 6 is also fixed to the bracket 35 and suspended. This work can be easily done using a lifter or the like, and once this work is finished, the lifter can be removed.

他方大引部材8と吊り足場6の取り付け方法の
別方法としては、先ず地表に於て鉄骨梁12にボ
ルト31とコーン34を介して大引部材8を連結
し、又この大引部材8のブラケツト35に吊り足
場6をあらかじめ連結しておき、鉄骨梁12と大
引部材8と吊り足場6の三者を一緒にクレーン等
で吊り上げ、この状態で鉄骨梁12を仮止めする
ことにより躯体成形位置に大引部材8と吊り足場
6を設置しても良い。
On the other hand, as another method for attaching the large tension member 8 and the suspended scaffold 6, first, the large tension member 8 is connected to the steel beam 12 on the ground surface via bolts 31 and cones 34, and the large tension member 8 is The suspended scaffold 6 is connected to the bracket 35 in advance, the steel beam 12, the main pull member 8, and the suspended scaffold 6 are lifted together by a crane, etc., and the steel beam 12 is temporarily fixed in this state to form the frame. A large pull member 8 and a hanging scaffold 6 may be installed at the position.

大引部材8と吊り足場6がコンクリート打設現
場に組立てられれば以後の作業は全て吊り足場6
上で行なえるものである。
Once the main pull member 8 and the suspended scaffolding 6 are assembled at the concrete pouring site, all subsequent work will be done on the suspended scaffolding 6.
It can be done above.

即ち、この足場6で鉄筋4の組立、鋲、溶接
作業及び配筋作業が行なえ、又型枠組立作業が行
なえる。即ち、大引部材8の溝29に根太用支持
桿10を挿入し、ブラケツト17を介してソケツ
ト18を起立させ、このソケツト18に端太部材
9を起立させ、この端太部材9には支保梁用支持
部材14を連結し、又側板固定部材11をフツク
を介して横方向に連結させる。
That is, the scaffolding 6 can be used to assemble the reinforcing bars 4, rivet, weld, and arrange the reinforcing bars, and also to assemble the formwork. That is, the support rod 10 for the joist is inserted into the groove 29 of the large tension member 8, the socket 18 is erected via the bracket 17, the end member 9 is erected in this socket 18, and this end member 9 is provided with a support. The beam support members 14 are connected, and the side plate fixing members 11 are laterally connected via hooks.

支保梁用支持部材14の引掛け片23には支保
梁24の端部を係合させ、この支持部材14上に
はフロア用の型枠3を置き、又側板固定部材11
の内側には梁側型枠4を配置させる。
The end of the support beam 24 is engaged with the hook piece 23 of the support beam support member 14, the floor formwork 3 is placed on this support member 14, and the side plate fixing member 11
A beam-side formwork 4 is placed inside.

この状態で型枠3,4,5上もしくは内にコン
クリートを打設させるとフロアー部1は支保梁2
4が担持し、又梁部2は梁底型枠5と側梁型枠を
介して大引部材8、根太用支持桿10及び端太部
材9と側板固定部材11がコンクリートの縦方向
荷重と横方向荷重を担持する。そして大引部材8
に作用する型枠からの荷重と吊り足場に係る荷重
はボルト31とコーン34と取り付け部たる連結
桿33と固定ピース32が鉄骨梁12と共に最終
的に担持することとなる。
In this state, when concrete is poured on or inside the formworks 3, 4, and 5, the floor part 1 is placed on the support beam 2.
4 is supported, and the beam part 2 is supported by the longitudinal load of the concrete through the beam bottom form 5 and the side beam form by the large tension member 8, the joist support rod 10, the end thick member 9, and the side plate fixing member 11. Carrying lateral loads. And large pull member 8
The load from the formwork and the load related to the suspended scaffolding acting on the structure will be ultimately carried by the bolts 31, the cones 34, the connecting rods 33 as attachment parts, and the fixing pieces 32 together with the steel beams 12.

次にコンクリートが固まると、同じく吊り足場
6上でコンクリートの仕上げ作業、及び型枠3,
4,5、根太用支持桿10、端太部材9、側板固
定部材11等の解体作業を行ない、その後リフタ
ー等によつてコーン34よりボルト31をはずし
大引部材8の撤去を行なう。この場合鉄骨12、
鉄筋41、コーン34等は梁2内にうめこまれて
しまう。
Next, when the concrete hardens, finishing work on the concrete is carried out on the hanging scaffold 6, and the formwork 3,
4, 5. Dismantle the support rod 10 for the joist, the end member 9, the side plate fixing member 11, etc., and then remove the bolt 31 from the cone 34 using a lifter or the like and remove the tension member 8. In this case, the steel frame 12,
The reinforcing bars 41, cone 34, etc. are buried inside the beam 2.

上記の躯体成形装置によれば、鉄骨組立と同時
に吊り足場が仮設され、この足場はH.T.B締付作
業、配筋作業、梁型枠の組立、コンクリートの打
設、型枠の解体等一連の作業が全て行なえる為に
従来工法における吊枠足場、サポート、大引き、
端太等が不要となり作業性が向上し、コストが安
価で工期の短縮化が著しいものである。
According to the above-mentioned frame forming equipment, a suspended scaffold is temporarily installed at the same time as the steel frame is assembled, and this scaffold performs a series of tasks such as HTB tightening work, reinforcement work, beam formwork assembly, concrete pouring, and formwork dismantling. In order to be able to perform all of
It eliminates the need for shafts, improves work efficiency, lowers costs, and significantly shortens the construction period.

又従来のように下段のフロアーや地表より足場
を組立てるのに比べて部品点数が少なく、安全で
あり、下段のフロアーを有効に利用できるもので
ある。更に実際の工事現場のメリツトとしては、
熟練を要しないために型枠組立大工の手不足を解
消し、現場における計画、施工、管理面での負担
の軽減、工期の短縮、確実性、安全性の強化、コ
ンクリート打上り精度の向上を達成し、省力化、
低コスト化に貢献できるものである。
In addition, compared to the conventional method of assembling scaffolding from the lower floor or the ground, it requires fewer parts, is safer, and allows the lower floor to be used more effectively. Furthermore, the merits of actual construction sites include:
Since no skill is required, it eliminates the shortage of formwork assembly carpenters, reduces the burden of planning, construction, and management on site, shortens construction time, strengthens reliability and safety, and improves the precision of concrete pouring. Achieve and save labor,
This can contribute to cost reduction.

本発明によれば次のような特有の効果を有す
る。即ち、 固定ピース32に対して連結桿33とコーン
34が一体に固定されているから、固定ピース
32を鉄骨梁12に固定すれば一度にこれらの
支持装置が組み付けられる。従つて組み付け工
数が著しく向上するものである。
The present invention has the following unique effects. That is, since the connecting rod 33 and the cone 34 are integrally fixed to the fixed piece 32, these supporting devices can be assembled at once by fixing the fixed piece 32 to the steel beam 12. Therefore, the number of assembly steps is significantly improved.

連結桿と固定ピース32は一体であり、これ
にあらかじめコーン34が固定されているとい
うことは、二つの連結桿間の巾及び二つのコー
ン34間の巾があらかじめ決められているとい
うことであり、これにより従来のようにいちい
ち位置合せをする必要が無い。
The connecting rod and the fixed piece 32 are integral, and the fact that the cone 34 is fixed in advance to this means that the width between the two connecting rods and the width between the two cones 34 are predetermined. This eliminates the need for positioning each time as in the conventional case.

連結桿及びコーン34の垂直度及び芯出しが
あらかじめ行なわれているからいちいち従来の
ように芯出しの微調整をする必要がない。
Since the verticality and centering of the connecting rod and the cone 34 have been determined in advance, there is no need to finely adjust the centering each time as in the conventional art.

連結桿及びコーンの位置と芯出しがあらかじ
め正確に行なわれていることから、コーン34
に結合されるボルト31の装着が容易であり、
これによりボルト31は常に垂直状態を保つと
同時に大引部材8も水平に設定される。この為
連結桿及びコーン34に偏荷重がかからず、連
結桿及びコーン34、ボルト31、大引部材8
の破損を防止できる。
Since the position and centering of the connecting rod and cone have been done accurately in advance, the cone 34
It is easy to install the bolt 31 connected to the
As a result, the bolt 31 is always maintained in a vertical state, and at the same time, the tension member 8 is also set horizontally. Therefore, an unbalanced load is not applied to the connecting rod and cone 34, and the connecting rod and cone 34, bolt 31, and large pull member 8
damage can be prevented.

固定ピース32、連結桿及びコーン34がば
らばらにならず、持ち運びが便利であり、部品
の紛失を防止できる。
The fixed piece 32, the connecting rod and the cone 34 do not come apart, making it convenient to carry and preventing loss of parts.

大引部材にカラーを縦方向に貫通固定してい
るから、ボルトの芯出しが可能であり、且つボ
ルトの着脱操作が簡単である。更にカラー自体
が大引部材に対する応力の集中する部分を補強
し、カラーと大引部材は一体に着脱できるから
組み付け、解体の作業性が向上する。
Since the collar is vertically fixed through the large tension member, it is possible to center the bolt, and the bolt can be easily attached and detached. Furthermore, the collar itself reinforces the areas where stress is concentrated on the tension member, and since the collar and the tension member can be attached and removed as a unit, the workability of assembly and disassembly is improved.

カラーは大引部材と一緒にはずすことが可能
であり、消耗品とならず反復継続して使用でき
る。しかも従来の埋め殺しとなつたコーンはこ
れを単独で取りはずした時コンクリートの後処
理が大変であつたが、本発明のカラーは埋め殺
しとならないからコンクリートの後処理が簡単
で綺麗にできる。
The collar can be removed together with the tension member, and it is not a consumable item and can be used repeatedly. In addition, the conventional cones that cause burying make post-treatment of concrete difficult when removed alone, but the color of the present invention does not cause burying, so post-treatment of concrete can be done easily and neatly.

カラーを設け、このカラーにボルトが挿入さ
れているから、カラーがボルトをガイドし、こ
れによりボルトの締め付け方向性を確実にする
と同時にボルトの曲がり等の変形を防止し、ボ
ルトの補強部材としての効用もある。
Since a collar is provided and the bolt is inserted into this collar, the collar guides the bolt, thereby ensuring the direction of tightening of the bolt, and at the same time preventing deformation such as bending of the bolt, and serves as a reinforcing member for the bolt. It also has benefits.

鉄骨梁の下部に固定ピースを固定させている
から、鉄骨梁の横巾や縦方向の長さに拘束され
ずそのまゝ結合でき、且つ短かい規格化された
固定ピースと連結桿とコーンとを使用できる。
Since the fixing piece is fixed to the bottom of the steel beam, it can be connected as is without being restricted by the width or vertical length of the steel beam, and short standardized fixing pieces, connecting rods and cones can be connected. can be used.

大引部材の下方に吊り足場が配設されている
から、この吊り足場上で鋲、溶接、配筋、型
枠の組立、解体、コンクリートの打設及び仕上
げ作業を連続して行なえる。
Since a suspended scaffold is disposed below the main member, riveting, welding, reinforcement, formwork assembly, dismantling, concrete pouring, and finishing operations can be performed continuously on this suspended scaffold.

【図面の簡単な説明】[Brief explanation of drawings]

添附図面は本発明の支持装置を使用した躯体成
形装置の実施の態様に係り、第1図は躯体成形装
置の縦断正面図、第2図は拡大斜視図、第3図は
一部拡大正面図、第4図は一部切欠き側面図であ
る。 6…吊り足場、7…型枠支持装置、8…大引部
材、12…鉄骨梁、30…カラー、31…ボル
ト、32…固定ピース、33…連結桿、34…コ
ーン。
The attached drawings relate to embodiments of a frame forming apparatus using the support device of the present invention, in which Fig. 1 is a longitudinal sectional front view of the frame forming apparatus, Fig. 2 is an enlarged perspective view, and Fig. 3 is a partially enlarged front view. , FIG. 4 is a partially cutaway side view. 6... Suspended scaffolding, 7... Formwork support device, 8... Large pull member, 12... Steel beam, 30... Collar, 31... Bolt, 32... Fixing piece, 33... Connecting rod, 34... Cone.

Claims (1)

【特許請求の範囲】 1 鉄骨梁に対して大引部材を着脱自在に連結さ
せ、大引部材の下方に吊り足場を連結し、吊り足
場上で鉄骨の鋲、溶接、配筋、型枠の組立、解
体、コンクリートの打設及び仕上げ作業を連続し
て行なう躯体の成形装置に於て、鉄骨梁の下部に
少なくとも二つの連結桿を一体に設けた固定ピー
スを固定させ、この連結桿の下部にはコーンが固
定され、前記大引部材には縦方向にカラーが挿入
固定され、このカラー内には大引部材を支持する
ボルトを着脱自在に挿入させ、当該ボルトが大引
部材を保持して前記コーンに螺着されるようにし
た型枠と吊り足場の荷重を担持する支持装置。 2 連結桿がボルトとからなり、このボルトの上
端が固定ピースに溶接又はねじ結合されている特
許請求の範囲第1項記載の型枠と吊り足場の荷重
を担持する支持装置。 3 ボルトの下部がコーンに固定されている特許
請求の範囲第2項記載の型枠と吊り足場の荷重を
担持する支持装置。
[Scope of Claims] 1. An Ohiki member is removably connected to a steel beam, a suspended scaffold is connected below the Ohiki member, and steel rivets, welding, reinforcing, and formwork are carried out on the suspended scaffold. In frame forming equipment that continuously performs assembly, demolition, concrete pouring, and finishing work, a fixed piece with at least two connecting rods is fixed to the bottom of a steel beam, and the lower part of the connecting rod is fixed to the bottom of a steel beam. A cone is fixed to the holder, a collar is inserted and fixed in the longitudinal direction into the holder, a bolt for supporting the holder is removably inserted into the collar, and the bolt holds the holder. A support device for carrying the load of the formwork and the suspended scaffold, which is screwed onto the cone. 2. A support device for supporting the load of formwork and suspended scaffolding according to claim 1, wherein the connecting rod is composed of a bolt, and the upper end of the bolt is welded or screwed to the fixed piece. 3. A support device for carrying the load of formwork and suspended scaffolding according to claim 2, wherein the lower part of the bolt is fixed to the cone.
JP4967085A 1985-03-13 1985-03-13 Support apparatus for supporting loads of mold frame and suspension scaffold Granted JPS60242256A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP4967085A JPS60242256A (en) 1985-03-13 1985-03-13 Support apparatus for supporting loads of mold frame and suspension scaffold

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP4967085A JPS60242256A (en) 1985-03-13 1985-03-13 Support apparatus for supporting loads of mold frame and suspension scaffold

Publications (2)

Publication Number Publication Date
JPS60242256A JPS60242256A (en) 1985-12-02
JPH0144867B2 true JPH0144867B2 (en) 1989-09-29

Family

ID=12837603

Family Applications (1)

Application Number Title Priority Date Filing Date
JP4967085A Granted JPS60242256A (en) 1985-03-13 1985-03-13 Support apparatus for supporting loads of mold frame and suspension scaffold

Country Status (1)

Country Link
JP (1) JPS60242256A (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS63261065A (en) * 1987-04-17 1988-10-27 株式会社竹中工務店 Mold frame for beam
JPH01182460A (en) * 1988-01-14 1989-07-20 Shimizu Corp Beam mold frame

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4933131A (en) * 1972-08-02 1974-03-27
JPS5217246U (en) * 1975-07-21 1977-02-07
JPS5268728A (en) * 1975-12-05 1977-06-07 Hasegawa Komuten Kk Method of causing reinforced bar itself to supporting concrete form

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4933131A (en) * 1972-08-02 1974-03-27
JPS5217246U (en) * 1975-07-21 1977-02-07
JPS5268728A (en) * 1975-12-05 1977-06-07 Hasegawa Komuten Kk Method of causing reinforced bar itself to supporting concrete form

Also Published As

Publication number Publication date
JPS60242256A (en) 1985-12-02

Similar Documents

Publication Publication Date Title
AU2020100657B4 (en) Methods and apparatus for constructing multi-storey buildings
CN108999394B (en) Construction process of floor type scaffold rotary cantilever type scaffold
JP7262277B2 (en) Installation method of jig using anchor member
US3175654A (en) Stair unit assemblies
JPH0144867B2 (en)
JPS638260B2 (en)
JPH0115799Y2 (en)
JPS6322269Y2 (en)
JPS6133174Y2 (en)
JPS6320985B2 (en)
CN217292740U (en) Cylinder design wood system template structure
CN109577632B (en) Suspended scaffold and construction method thereof
JPS6133172Y2 (en)
CN220868786U (en) Plastic formwork outer wall post outside template reinforcing system
CN218893957U (en) Temporary supporting and fixing device for butt joint of steel beams
JPH0447300Y2 (en)
KR102482154B1 (en) Concrete reinforcement connection device
JPS6133173Y2 (en)
JPH038740Y2 (en)
KR200219475Y1 (en) A clamp device for safety porch of gang form of construct
JPS6137426B2 (en)
JPH07119522B2 (en) Formwork device
JPS59465A (en) Method and beam for supporting mold frame
KR20220112055A (en) Temporary worktable
JP2023172647A (en) Reinforcement bar mount and construction method of wall