JPH01295994A - Excavating work of long and large space - Google Patents

Excavating work of long and large space

Info

Publication number
JPH01295994A
JPH01295994A JP63123348A JP12334888A JPH01295994A JP H01295994 A JPH01295994 A JP H01295994A JP 63123348 A JP63123348 A JP 63123348A JP 12334888 A JP12334888 A JP 12334888A JP H01295994 A JPH01295994 A JP H01295994A
Authority
JP
Japan
Prior art keywords
excavation
conveyer
belt conveyor
shaft
bucket
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP63123348A
Other languages
Japanese (ja)
Other versions
JP2620111B2 (en
Inventor
Yutaka Nagata
豊 永田
Masaaki Tsujii
辻井 政明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Nippon Conveyor Co Ltd
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Nippon Conveyor Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp, Nippon Conveyor Co Ltd filed Critical Shimizu Construction Co Ltd
Priority to JP63123348A priority Critical patent/JP2620111B2/en
Publication of JPH01295994A publication Critical patent/JPH01295994A/en
Application granted granted Critical
Publication of JP2620111B2 publication Critical patent/JP2620111B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

PURPOSE:To prevent the occurrence of noise by a method in which a belt conveyer connecting the end of excavation with a vertical pit is hung down in a lowerable manner by hangers, the excavation muck is dropped from the conveyer into the bucket of the vertical pit, and the conveyer is lowered as excavation proceeds. CONSTITUTION:A power-driven hanger 10 is attached to a beam 2a right below a ceiling part 2, a long and large belt conveyer 12 is provided to the hook of the hanger 10 to a vertical pit 3, and a truss-type base 12a to support the conveyer 12 is hung down from a wire 13. The excavation muck is put on any place of the conveyer 12 by bulldozer, small-size belt conveyer, and back hoe and carried along to the pit 3. The muck is dropped into a bucket 15 in the pit 3 and discharged to a hopper 17 by a bucket elevator 16. When the conveyer 12 is lowered by a guide 12b, it is lowered along a guide steel 14. The limit to discharging distance can thus be eliminated.

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は、上部空間に制限のある地上に、大空間となる
例えば地下鉄の車庫、地下駐車場、地下街などの長大空
間の掘削方法に関するものである。
[Detailed Description of the Invention] [Industrial Application Field] The present invention relates to a method for excavating large spaces such as subway garages, underground parking lots, underground malls, etc. on the ground where the upper space is limited. It is.

(従来の技術) 従来から地下に大空間となる例えば地下鉄の車庫、地下
駐車場あるいは地下街などの大断面でかつ深い位置まで
掘削する長大空間の掘削施工法においては一般に次のよ
うに行なわれている。
(Prior Art) Conventionally, the excavation method for large underground spaces, such as subway garages, underground parking lots, or underground malls, has been generally carried out as follows: There is.

第5図ないし第8図に示すように、まず、土の崩壊を防
止するための坑(土留め工)1が設置され、掘削施工の
安全性を確保する点から天井部材(上床板)2を先行築
造することによって、これを強力な上留め切ばっとして
利用し、土留め坑1の変形を拘束し、周辺地盤の沈下を
防いでいる。
As shown in Figures 5 to 8, first, a pit (earth retaining work) 1 was installed to prevent the soil from collapsing, and a ceiling member (upper floor plate) 2 was installed to ensure safety during excavation work. By constructing this in advance, it is used as a strong upper retaining bar, restraining deformation of the earth retaining shaft 1, and preventing subsidence of the surrounding ground.

次に掘削は、天井部材のF付近とか坑の周辺では手掘り
で掘削されるが、それ以上に掘削深さが深くなるにつれ
てバックボーBやタラムシエルなどが使用されている。
Next, excavation is carried out by hand near F of the ceiling member and around the pit, but as the excavation depth becomes deeper, tools such as Backbow B and Taramsiel are used.

土砂の切くずしや運搬、集積には小型のブルドーザ−D
やパワショベルが用いられる。
A small bulldozer-D is used for cutting, transporting, and accumulating earth and sand.
or power shovels are used.

掘削した土砂や岩石破片などのいわゆる「ずり」はふつ
う−度坑内に集結してそれからバケットポツパーなどに
よって立坑3を通って路十に運ばれ、ホッパHからダン
プに積込まれて積出される。
The excavated earth, sand, rock fragments, and other so-called "sludge" usually collect in the pit, and are then transported by bucket dropper etc. through the shaft 3 to the road, where they are loaded from hopper H onto a dump truck and shipped. .

上記の坑内に集結するまでのずり搬出方法として次の各
方法がとられている。
The following methods are used to transport the materials until they are collected in the mine.

■ブルドーザー、パワショベル等によりすりの搬出を行
う。
■Remove pickpockets using bulldozers, power shovels, etc.

■また、通常利用されるベルトコンベアC(長さ7m〜
10m)の継ぎ足しによりすりの搬出を行う。
■Also, the commonly used belt conveyor C (length 7m ~
The pickpockets will be carried out by adding 10 m).

■さらにまた、第5図ないし第8図に示すように、事前
に掘削底部に作業導坑4を設け、その中にベルトコンベ
ア5を設置し、そこに向けてずり投入用立坑6を設け、
この立坑6にヂリを投入しベルトコンベア5で横取り搬
出を行う。
■Furthermore, as shown in Figs. 5 to 8, a working shaft 4 is provided in advance at the bottom of the excavation, a belt conveyor 5 is installed therein, and a shaft 6 for shedding is provided toward the shaft.
Dirt is thrown into this vertical shaft 6 and is picked up and carried out by a belt conveyor 5.

〔発明が解決しようとする課題〕[Problem to be solved by the invention]

しかし、上記掘削り法のうち、ずりの搬出については次
のような問題がある。すなわら、■の場合、プルドーヂ
ー、パワショベル等によるずりの搬出には騒名、振動、
排気ガス等で環境が悪化する。また、ブルドーザ−、パ
ワショベルが移動し回っているのでは効率的な移送距離
に制限がある。
However, among the above-mentioned excavation methods, there are the following problems regarding removal of shear. In other words, in the case of ■, transporting shear using pull doges, power shovels, etc. may cause a lot of noise, vibration,
The environment deteriorates due to exhaust gas, etc. Furthermore, since bulldozers and power shovels are moving around, there is a limit to the distance that can be efficiently transported.

■の場合、コンベアの継ぎ足しによるずり搬出には1基
列に何本ものベルトコンベアを使用するので、1本のベ
ルトコンベアが故障を起すと1基列すべてが作業を中止
することになる。また、ベルトコンベアの乗継部での問
題としてずりの混泥化、ずりのはみ出し、異物による損
傷等が多い。■の場合、事前に作業導坑、立坑の設備工
$費が必要である。そして立坑底部に投入したずりがス
ムーズにベルトコンベア上に移る装置が必要である。
In the case of (2), since multiple belt conveyors are used in one row for shear conveyance by adding conveyors, if one belt conveyor breaks down, all of the rows will stop working. In addition, there are many problems at the transfer section of the belt conveyor, such as mixing of shear, shear sticking out, and damage due to foreign objects. In the case of ■, the cost of equipment work for the shaft and shaft will be required in advance. A device is needed to smoothly transfer the scraps thrown into the bottom of the shaft onto the belt conveyor.

また、ずり投入箇所が立坑に制限されるといった問題が
あった。
Another problem was that the shear input location was limited to the vertical shaft.

本発明は、上記従来の方法における問題点を解決するた
めになされたものであって、長大空間の掘削施工法にお
いて、大月部材から降゛l−司能な懸垂装置により吊り
下げられた1基の長大ベルトコンベアを設け、掘削した
ずりの搬出を長距離横取りすることのできる長大空間の
掘削施工法を提供することを目的としている。
The present invention has been made in order to solve the problems in the conventional methods described above. The purpose of the present invention is to provide a method for excavating a long space by installing a long belt conveyor at the base and allowing excavated waste to be transported over a long distance.

〔課題を解決するための手段〕[Means to solve the problem]

上記の目的を達成するため、本発明は、掘削端部から立
坑の位置までを結ぶ長さの1基のベルトコンベアを、天
井部材に支持させた複数の懸垂装置により降下可能に吊
り下げ、掘削したずりを前記ベルトコンベアで横取りし
、前記立坑のバケットに落し込み、この立坑を通して地
上に搬出を行い、掘削の進行に併せて、前記ベルトコン
ベアを降下させる掘削施工法どしたものである。
In order to achieve the above object, the present invention has a belt conveyor with a length connecting the end of the excavation to the shaft position, which is suspended so as to be descendable by a plurality of suspension devices supported by a ceiling member. This is an excavation construction method in which the belt conveyor intercepts the drippings, drops it into a bucket in the shaft, carries it out to the ground through the shaft, and lowers the belt conveyor as excavation progresses.

〔作 用〕[For production]

掘削したずりはブルドー’f−、パワショベル等で集積
され先行築造された天井部材(上床板)から吊り下げら
れた掘削端部からすり排出の立坑の位置までを結ぶ1基
のベルトコンベアに人力、小型ベルトコンベア、バック
ホー等で乗せられて、立坑のバケットに移され、ここか
ら地上に排出される。そして、掘削の進行にともない、
掘削面が深くなるに従って、天井部材に適当間隔をおい
て設けられた懸垂装置にてベルコンベアを順次降下させ
るごとにより、前記と同じ依領で掘削施工を連続的に行
うことができる。
The excavated slag is collected using a bulldozer, a power shovel, etc., and is manually transferred to a belt conveyor that connects the end of the excavation suspended from the previously constructed ceiling member (upper floor board) to the position of the shaft for discharging the slag. It is loaded onto a small conveyor belt, backhoe, etc., and transferred to a bucket in a shaft, from where it is discharged to the ground. As the excavation progresses,
As the excavation surface becomes deeper, the bell conveyor is lowered one by one using suspension devices provided at appropriate intervals on the ceiling member, so that excavation work can be performed continuously in the same manner as described above.

〔実施例〕〔Example〕

以下、添付の第1図ないし第4図を参照し本発明の一実
施例について詳述する。
Hereinafter, one embodiment of the present invention will be described in detail with reference to the accompanying FIGS. 1 to 4.

第1図は本発明の概要を示す縦断面図である。FIG. 1 is a longitudinal sectional view showing an outline of the present invention.

図中の符号1は土留め工として設置された坑である。2
は天井部材(上床板)であり、この天井部材2は大断面
掘削に先行して築造され、前記坑の変形を拘束している
。この天井部材2直下に設けられた梁2aに降下可能な
電動懸垂装置10が掘削端部よりすり搬出用立坑3の位
置まで適当間隔をおいて取付けられている。前記の各電
動懸垂装置10の電動チェーンブロック11の先端のフ
ック11aに1本のベルトコンベア12を支持している
トラス状の架台12aが吊りクイ1フ13でもりてmり
下げられている。また、ベルトコンベア12のトラス状
の架台12aにはガイド12bがついていて、ベルトコ
ンベア12が降下するときはこのガイド12bがガイド
鋼材14に沿って降下するようになっている。15は前
記ベルトコンベア12に乗ってぎたすりを受けるバケッ
トであり、16はバケット15を路上に搬出するバグッ
トエレベーターである。、17はポツパーで路上に設け
られている。
Reference numeral 1 in the figure is a pit installed as a retaining structure. 2
is a ceiling member (upper floor plate); this ceiling member 2 is constructed prior to large-section excavation, and restrains deformation of the shaft. An electric suspension device 10 that can be lowered to a beam 2a provided directly below the ceiling member 2 is attached at an appropriate interval from the excavation end to the position of the shaft 3 for sliding and carrying out. A truss-shaped pedestal 12a supporting one belt conveyor 12 is suspended by a hook 13 from a hook 11a at the tip of an electric chain block 11 of each electric suspension device 10. Further, a guide 12b is attached to the truss-shaped pedestal 12a of the belt conveyor 12, and the guide 12b descends along the guide steel material 14 when the belt conveyor 12 descends. Reference numeral 15 is a bucket that rides on the belt conveyor 12 and receives scratches, and reference numeral 16 is a bagut elevator that carries the bucket 15 out onto the street. , 17 are installed on the road in Potsupur.

上記構造の長大空間の掘削施工法について述べる。天井
部材2の下に4TrL前後の空間ができた段階で、掘削
端部から立坑3の位置までの長さの1本の長大ベルトコ
ンベア12を設置する。この−本のベルトコンベアの間
隔は40〜60m程度とし、掘削面積によっては複数本
のベルトコンベアを設ける。、掘削したずりはブルドー
ザ−Dで集積され、人力、小型ベルトコンベアCまたは
バックホーB等でこの長大ベルトコンベア12の任意の
位置に乗せられる。ベルトコンベア12に乗ったずりは
立坑3に運ばれ、立坑3内のバケット15に落し込まれ
る。バケットエレベータ16によりバケット15を路上
に上昇さゼ、ホッパー17にバケット15内のずりを排
出する。そしてダンプに積込まれて埋立地や宅地造成地
に運搬される。
This section describes the excavation method for the long space in the above structure. When a space of about 4 TrL is created under the ceiling member 2, one long belt conveyor 12 with a length from the excavation end to the position of the shaft 3 is installed. The interval between these belt conveyors is about 40 to 60 m, and depending on the excavation area, a plurality of belt conveyors may be provided. The excavated waste is accumulated by a bulldozer D, and placed at any position on this long belt conveyor 12 by hand, by a small belt conveyor C, by a backhoe B, or the like. The scraps on the belt conveyor 12 are carried to the shaft 3 and dropped into a bucket 15 inside the shaft 3. The bucket 15 is raised onto the road by a bucket elevator 16, and the shear in the bucket 15 is discharged into a hopper 17. It is then loaded onto a dump truck and transported to a landfill or residential development site.

掘削の進行に従って、長大ベルトコンベア12を10〜
20m毎に設置された降下可能な懸垂装置10の電動チ
ェーンブロック11により降下させる。この長大ベルト
コンベア12の降下に併せて、立坑5部のバケットエレ
ベータ16等のずり揚重ti置も継ぎ足しを行う。そし
て、上記と同様の掘削作業を所定の深さになるまで繰り
返し行う。
As the excavation progresses, the long belt conveyor 12 is
It is lowered by an electric chain block 11 of a suspension device 10 that can be lowered and installed every 20 m. In conjunction with the descent of the long belt conveyor 12, the shear lifts of the bucket elevators 16 and the like in the shaft 5 section will also be supplemented. Then, the same excavation work as above is repeated until a predetermined depth is reached.

以上のように上空制限のある箇所における長大空間のす
り掘削]工法どして、すり搬出の降下装置を持った長大
距離横取り可能な工法であり、騒音、振動、排気ガス等
も少なく、長大ベルトコンベアであるため乗継部での問
題もなく、事前の作業導坑、ずり投入用立坑も不用であ
る。掘削深さが深くなるに従ってベルトコンベアを降下
させるだけの簡単な作業であるので作業能率もよい。
As mentioned above, it is a construction method that allows long distances to be intercepted, with a lowering device for carrying out the slide, and there is less noise, vibration, exhaust gas, etc., and there is a long belt. Since it is a conveyor, there are no problems at the transfer section, and there is no need for a preliminary work shaft or a vertical shaft for shedding. The work efficiency is high because it is a simple operation that involves lowering the belt conveyor as the excavation depth increases.

〔発明の効果〕〔Effect of the invention〕

本発明は、以上説明したような工法としているので、以
下に記載されているような効果を奏する。
Since the present invention uses the construction method as explained above, it produces the effects as described below.

■掘削端部からすり排出の立坑の位置まで1本の長大ベ
ルトコンベアによるすり搬出であるので、プルドープ−
やパワーショベル等によるずり搬出のような騒音、撮動
、排気ガス等の発生が無い。
■Pull dope is transported from the excavation end to the position of the shaft for discharging the scrap by one long belt conveyor.
There is no noise, no photography, no exhaust gas, etc., which is caused by shearing and transporting with a power shovel or the like.

■ブルドーザーやパワーショベル等によるずり搬出と違
い、搬出距離の制限を受けない。
■Unlike removal by shearing using bulldozers, power shovels, etc., there are no restrictions on removal distance.

■1基1本のベルトコンベアになっているので、何本も
のベルトコンベアを使用するような場合の乗継部での問
題の発生が避けられる。
■Since each belt conveyor is one, it is possible to avoid problems at the transfer section when multiple belt conveyors are used.

■上部からの電動懸垂8置でベルトコンベアを支えるこ
とができるので、ベルト」ンベアの降ド作業がスムーズ
で、降下作業の為の作業中止期間がほとんど無い。
■Since the belt conveyor can be supported by 8 electric suspensions from the top, lowering the belt conveyor is smooth and there is almost no work stoppage for lowering.

■上部からの電動懸垂装置でベルトコンベアを支え、掘
削の進行に併せてベルトコンベアを降下させるの(゛、
作業導坑の設置、投入用の立坑の設置が不要である。
■The belt conveyor is supported by an electric suspension system from above, and the belt conveyor is lowered as excavation progresses (゛,
There is no need to install a working shaft or a vertical shaft for input.

■ベルトコンベアーヒへのずりの投入箇所の制限が無く
、各所で積込作業が行なうことができる。
■There are no restrictions on where the shear can be loaded onto the belt conveyor, and loading work can be done at any location.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明の長大空間の掘削施工を示す縦断面図、
第2図はベルトコンベアにずり投入の状態を示1断面図
、第3図は天井部材から吊■ζげられた懸垂装置とベル
トコンベアの状態を示す断面図、第4図は第3図の側面
図である。 また、第5図ないし第8図はそれぞれ従来の施工例を示
す説明図である。 2・・・・・・天井部材、 3・・・・・・立坑、 10・・・・・・懸垂装置、 12・・・・・・(長大)ベルトコンベア、15・・・
・・・バケット。
FIG. 1 is a longitudinal sectional view showing the excavation construction of a long space according to the present invention;
Figure 2 is a sectional view showing the state of shear being fed into the belt conveyor, Figure 3 is a sectional view showing the state of the belt conveyor and the suspension device suspended from the ceiling member, and Figure 4 is the same as in Figure 3. FIG. Moreover, FIGS. 5 to 8 are explanatory diagrams showing conventional construction examples, respectively. 2... Ceiling member, 3... Vertical shaft, 10... Suspension device, 12... (long) belt conveyor, 15...
···bucket.

Claims (1)

【特許請求の範囲】[Claims] 掘削端部から立坑の位置までを結ぶ長さの1基のベルト
コンベアを、天井部材に支持させた複数の懸垂装置によ
り降下可能に吊り下げ、掘削したずりを前記ベルトコン
ベアで横取りし、前記立坑のバケットに落し込み、この
立坑を通して地上に搬出を行い、掘削の進行に併せて、
前記ベルトコンベアを降下させることを特徴とする長大
空間の掘削施工法。
A belt conveyor with a length connecting the excavation end to the shaft position is suspended so that it can be lowered by a plurality of suspension devices supported by a ceiling member, and the excavated shear is intercepted by the belt conveyor and transported to the shaft. It is dropped into a bucket and carried out to the ground through this shaft, and as the excavation progresses,
An excavation construction method for a long space characterized by lowering the belt conveyor.
JP63123348A 1988-05-20 1988-05-20 Excavation construction method for long space Expired - Lifetime JP2620111B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP63123348A JP2620111B2 (en) 1988-05-20 1988-05-20 Excavation construction method for long space

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP63123348A JP2620111B2 (en) 1988-05-20 1988-05-20 Excavation construction method for long space

Publications (2)

Publication Number Publication Date
JPH01295994A true JPH01295994A (en) 1989-11-29
JP2620111B2 JP2620111B2 (en) 1997-06-11

Family

ID=14858343

Family Applications (1)

Application Number Title Priority Date Filing Date
JP63123348A Expired - Lifetime JP2620111B2 (en) 1988-05-20 1988-05-20 Excavation construction method for long space

Country Status (1)

Country Link
JP (1) JP2620111B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017125321A (en) * 2016-01-13 2017-07-20 鉄建建設株式会社 Belt conveyor lifting device

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5869232B2 (en) * 2011-04-27 2016-02-24 大成建設株式会社 Excavation soil transport system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017125321A (en) * 2016-01-13 2017-07-20 鉄建建設株式会社 Belt conveyor lifting device

Also Published As

Publication number Publication date
JP2620111B2 (en) 1997-06-11

Similar Documents

Publication Publication Date Title
US10082025B2 (en) System for the reduction in applied energy, improved efficiencies and reduced costs in open pit mining
AU2015100066A4 (en) A System for the Reduction in Applied Energy, Improved Efficiencies and Reduced Costs in Open Pit Mining
CN106276056A (en) Multi-segmental combination type earthwork perpendicular lifting apparatus
CN106315118A (en) Single chain type earthwork vertical lifting device
JPH01295994A (en) Excavating work of long and large space
JP3151116B2 (en) Tunnel excavation method and gantry used for this method
JP2516133B2 (en) Transport system for underground excavation work
JP2572214Y2 (en) Vertical transfer guide for underground excavation work
JPS59185236A (en) Method and apparatus for continuous and vertical excavation and soil-moving work
JP3357654B2 (en) Gantry used for tunnel excavation method
JP2516132B2 (en) Excavation soil removal method and system for underground excavation work
JPH05287999A (en) Equipment and materials transportation method in underground excavation work
SU1642011A1 (en) Method of mining steep coal seams
KR950007008B1 (en) Method for installation of truck lifter
SU1765414A1 (en) Open-cast rock transfer station
JPS6115212B2 (en)
JP4138184B2 (en) Material input method
JPH05272289A (en) Shaft drilling device and method
JPS62148795A (en) Method and maching for excavating vertical pit
JPS5839980B2 (en) Excavation conveyor device
JPH0882185A (en) Tunnel execution device
JPS591857B2 (en) Safety device for excavation conveyor equipment
JPS5947778B2 (en) "Shear" device
JPH0882184A (en) Method and appliance for execution of tunnel
JPH05208793A (en) Excavated earth conveyance control device