JPH01290899A - Intermittent stanchion construction in composite-cross section shield tunnel - Google Patents
Intermittent stanchion construction in composite-cross section shield tunnelInfo
- Publication number
- JPH01290899A JPH01290899A JP63120049A JP12004988A JPH01290899A JP H01290899 A JPH01290899 A JP H01290899A JP 63120049 A JP63120049 A JP 63120049A JP 12004988 A JP12004988 A JP 12004988A JP H01290899 A JPH01290899 A JP H01290899A
- Authority
- JP
- Japan
- Prior art keywords
- rings
- stanchions
- strut
- sheath
- assembled
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title claims abstract description 9
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 7
- 239000000463 material Substances 0.000 claims abstract description 7
- 239000010959 steel Substances 0.000 claims abstract description 7
- 239000002131 composite material Substances 0.000 claims description 7
- 238000009412 basement excavation Methods 0.000 claims description 4
- 150000001875 compounds Chemical class 0.000 description 3
- 238000000034 method Methods 0.000 description 2
- 238000009434 installation Methods 0.000 description 1
Landscapes
- Lining And Supports For Tunnels (AREA)
Abstract
Description
【発明の詳細な説明】
「産業上の利用分野」
この発明は、複合断面シールドトンネルにおいて、左右
のリング間に設置する支柱を相互間に充分な空間を保持
するように間隔を置いて築造し、地下駅や地下鉄道の切
換交差路などを構築するための工法に関するものである
。[Detailed Description of the Invention] "Industrial Application Field" This invention is a composite section shield tunnel in which the supports installed between the left and right rings are constructed at intervals so as to maintain sufficient space between them. , Concerning construction methods for constructing underground stations, underground railway switching intersections, etc.
「従来の技術、発明が解決せんとする問題点」最近、円
形リングを左右に二連、二連に重合して復円形とした複
合断面のトンネルを一体に構築するシールト工法か開発
されつつあるか、この工法においては左右のリング間の
セグメントにおける上下の支柱接合部間に各前後のリン
グ毎ε中柱を組立ててゆくものであるため、前後の中柱
間に充分な空間か保持されておらず、地下駅や地下鉄道
の切換交差路などを構築する場合、密に配置した中柱が
その妨げになるという課題かあった。``Prior art and problems to be solved by the invention'' Recently, a seal construction method has been developed in which a tunnel with a composite cross-section is constructed by combining two circular rings on the left and right sides to form a double circular ring. In this construction method, a center column is assembled for each front and rear ring between the upper and lower column joints in the segment between the left and right rings, so sufficient space is maintained between the front and rear center columns. However, when constructing underground stations or interchanges for underground railroads, there was a problem in that the densely placed central pillars would get in the way.
「問題点を解決するだめの手段」
この発明は前記従来の課題を解決子るために左右のリン
グ間のセグメントにおける支柱接合部に、予め掘進方向
の複数リングを一組として一連に連通するシースを埋設
し、この一組のリングの内その前後端に位置するリング
における上下の支柱接合部間に本設支柱を、かつ中間部
に位置するリングにおける上下の支柱接合部間に仮設支
柱を組立て、一組のリングの各支柱接合部に連通ずるシ
ース内に挿通したPC鋼材によりプレストレスを導入し
て一体化した後、仮設支柱を撤去することにより、各一
組のリング間における支柱接合部か一体化した合成梁を
構成し、撤去した中間の仮設支柱か受は持っていた軸力
をこの梁を介して本設支柱に作用させ、これによって本
設支柱間に充分な空間を保持させて人や車輌などが余裕
をもって通行可能な地下駅や地下鉄道の切換交差路など
を構築し得るようにした複合断面シールドトンネルにお
ける隔設支柱築造工法を提案するものである。``Means for Solving the Problems'' In order to solve the above-mentioned conventional problems, the present invention provides a sheath in which a plurality of rings in the excavation direction are connected in series as a set in advance at the strut joint in the segment between the left and right rings. of this set of rings, a permanent strut is assembled between the upper and lower strut joints of the ring located at the front and rear ends of the set, and a temporary strut is assembled between the upper and lower strut joints of the ring located in the middle. After introducing prestress and integrating the prestress by inserting the PC steel material through the sheath that communicates with each strut joint of a set of rings, the strut joints between each set of rings are removed by removing the temporary struts. The structure consists of an integrated composite beam, and the axial force of the removed intermediate temporary support supports is applied to the permanent support columns through this beam, thereby maintaining sufficient space between the permanent support supports. This paper proposes a construction method for constructing separate supports in complex cross-section shield tunnels, which enables the construction of underground stations and subway switching intersections that allow people and vehicles to pass through with ease.
「実施例」
以下この発明を図面に示す実施例について説明すると、
復円掘削カッターを備えた複合断面シールド掘進機lに
より掘進しながら順次後方にセグメントを組立て、複数
のセグメントリング2か左右に重合した複合断面のシー
ルドトンネルを構築し、各リング2.2間には箱型フロ
ック状の支柱接合部3を形成したセグメントを組立て、
前後に組立られるリング毎に上下の支柱接合部3.3間
に本設支柱4又は仮設支柱5をボルト接合などにより組
立てて支持する(第2図(a))。"Embodiments" Below, embodiments of the present invention shown in the drawings will be described.
While excavating with a compound section shield excavator l equipped with a circular excavation cutter, assemble the segments backward one by one to construct a compound section shield tunnel in which a plurality of segment rings 2 overlap on the left and right, and between each ring 2. Assemble the segments forming the box-shaped flock-like column joint 3,
A permanent support 4 or a temporary support 5 is assembled and supported between the upper and lower support support joints 3.3 by bolt connection or the like for each ring assembled in the front and rear directions (FIG. 2(a)).
左右のリング2.2間のセグメントに形成する支柱接合
部3には、前後方向に組立てられる複数リング2.2・
・(図示の実施例ては5リング)を一組として、これら
に一連に連通ずるシース6を予め埋設しておく。The strut joint 3 formed in the segment between the left and right rings 2.2 has a plurality of rings 2.2 and 2 assembled in the front and back direction.
- (In the illustrated embodiment, 5 rings) are set as a set, and a sheath 6 that communicates with these rings is buried in advance.
そして、これら一組のリング2の内その前後端に位置す
るリング2における上下の支柱接合部3,3間に本設支
柱4を、かつ中間部に位置するリング2における上下の
支柱接合部3.3間に仮設支柱5を組立てる。A main strut 4 is installed between the upper and lower strut joints 3, 3 of the ring 2 located at the front and rear ends of the set of rings 2, and the upper and lower strut joints 3 of the ring 2 located at the intermediate portion are provided. Assemble the temporary support 5 between .3 and 3.
次いで、各一組のリング2の各支柱接合部3間に一連を
なすシース6内にPC鋼材7によりプレストレスを導入
して支柱接合部3を一体化しく第2図(b)、第3図)
、これらか連結一体化した合成梁を構成した後、中間の
仮設支柱5を撤去し、これらが受は持っていた軸力なこ
の合成梁を介して本設支柱4に作用させ、これによって
本設支柱4,4に充分な空間を保持させる(第2図(C
))。Next, prestress is introduced into the sheath 6 that forms a series between each strut joint 3 of each set of rings 2 using a PC steel material 7 to integrate the strut joint 3, as shown in FIGS. 2(b) and 3. figure)
After constructing a composite beam that connects and integrates these, the intermediate temporary support 5 is removed, and the axial force that these supports is applied to the main support 4 through this composite beam, and thereby the main support Maintain sufficient space for the installation supports 4, 4 (see Figure 2 (C)
)).
以上の工程を先行の本設支柱4の先端部分を含んで新た
な組のリング2に順次連続して施工し、先行工程て撤去
した仮設支柱5は順次転用する。The above steps are sequentially performed on a new set of rings 2 including the tip portions of the previous permanent supports 4, and the temporary supports 5 removed in the previous process are sequentially repurposed.
この結果、本設支柱4,4間を人や車輌などが余裕をも
って通行回旋な地下駅や地下鉄道の切換交差路などを構
築することか可能となる。As a result, it becomes possible to construct an underground station, a switching intersection for an underground railroad, etc., where people and vehicles can pass between the main supports 4 and 4 with sufficient margin.
「発明の効果」
以上の通りこの発明によれば、左右のリング間のセグメ
ントにおける支柱接合部に、予め掘進方向の複数リング
を一組として一連に連通ずるシースを埋設し、この一組
のリングの内その前後端に位置するリングにおける上下
の支柱接合部間に本設支柱を、かつ中間部に位置するり
ングにおける上下の支柱接合部間に仮設支柱を組立て、
一組のリングの各支柱接合部に連通ずるシース内に挿通
したPC鋼材によりプレストレスを導入して一体化した
後、仮設支柱を撤去するので、各一組のリング間におけ
る支柱接合部か一体化した梁を構成し、撤去した中間の
仮設支柱が受は持っていた軸力をこの梁を介して本設支
柱に作用させ、これによって本設支柱間に充分な空間を
保持させて人や車輌などが余裕をもって通行可能な地下
駅や地下鉄道の切換交差路などを構築することか可能と
なる。"Effects of the Invention" As described above, according to the present invention, a sheath is embedded in advance in the strut joint in the segment between the left and right rings, and the sheath is connected in series with a plurality of rings in the excavation direction as a set. Assemble a permanent strut between the upper and lower strut joints of the ring located at the front and rear ends of the ring, and a temporary strut between the upper and lower strut joints of the ring located in the middle,
After introducing prestress and integrating the pre-stressed steel material inserted into the sheath that communicates with each strut joint of a set of rings, the temporary struts are removed, so that the strut joints between each set of rings are integrated. The axial force that the removed middle temporary support had was applied to the permanent support via this beam, thereby maintaining sufficient space between the main supports to prevent people from entering the building. It will be possible to construct underground stations and interchanges for underground railways that allow vehicles to pass through with plenty of time.
第1図はこの発明により構築した複1合断面シールドト
ンネルの斜視図、第2図(a) 、 (b) 、 (c
)はこの発明の工程を示す縦断側面図、第3図はこの発
明における支柱接合部のプレストレス導入状態を示す横
断面図である。
l・・複合断面シールド掘進機、
2・・セグメントリング、3・・支柱接合部、4・・本
設支柱、5・・仮設支柱、
6・・シース、7・・PC鋼材。
第3図
第2図Figure 1 is a perspective view of a compound cross-section shield tunnel constructed according to the present invention, and Figures 2 (a), (b), (c)
) is a vertical sectional side view showing the process of this invention, and FIG. 3 is a cross sectional view showing a state in which prestress is introduced to the column joint in this invention. 1. Composite section shield excavator, 2. Segment ring, 3. Support column joint, 4. Permanent support, 5. Temporary support, 6. Sheath, 7. PC steel material. Figure 3Figure 2
Claims (1)
、予め掘進方向の複数リングを一組として一連に連通す
るシースを埋設し、前記一組のリングの内その前後端に
位置するリングにおける上下の支柱接合部間に本設支柱
を、かつ中間部に位置するリングにおける上下の支柱接
合部間に仮設支柱を組立て、前記一組のリングの各支柱
接合部に連通するシース内に挿通したPC鋼材によりプ
レストレスを導入して一体化した後、前記仮設支柱を撤
去することを特徴とする複合断面シールドトンネルにお
ける隔設支柱築造工法。1) A sheath that connects a plurality of rings in the excavation direction as a set is buried in advance at the strut joint in the segment between the left and right rings, and the upper and lower A permanent strut is assembled between the strut joints, and a temporary strut is assembled between the upper and lower strut joints of the ring located in the middle, and the PC steel material is inserted into a sheath that communicates with each strut joint of the set of rings. 1. A construction method for constructing separate supports in a composite cross-section shield tunnel, characterized in that the temporary supports are removed after the temporary supports are integrated by introducing prestress.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP63120049A JPH0791957B2 (en) | 1988-05-16 | 1988-05-16 | Construction method of separated pillars in shield tunnel with composite section |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP63120049A JPH0791957B2 (en) | 1988-05-16 | 1988-05-16 | Construction method of separated pillars in shield tunnel with composite section |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH01290899A true JPH01290899A (en) | 1989-11-22 |
JPH0791957B2 JPH0791957B2 (en) | 1995-10-09 |
Family
ID=14776626
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP63120049A Expired - Lifetime JPH0791957B2 (en) | 1988-05-16 | 1988-05-16 | Construction method of separated pillars in shield tunnel with composite section |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH0791957B2 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH01312196A (en) * | 1988-06-13 | 1989-12-15 | Taisei Corp | Construction of flat tunnel |
JP2020079491A (en) * | 2018-11-12 | 2020-05-28 | 清水建設株式会社 | Double circle circumferential shield excavator, shield starting base, and outer shell shielding method using a circumferential tunnel |
-
1988
- 1988-05-16 JP JP63120049A patent/JPH0791957B2/en not_active Expired - Lifetime
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH01312196A (en) * | 1988-06-13 | 1989-12-15 | Taisei Corp | Construction of flat tunnel |
JP2020079491A (en) * | 2018-11-12 | 2020-05-28 | 清水建設株式会社 | Double circle circumferential shield excavator, shield starting base, and outer shell shielding method using a circumferential tunnel |
Also Published As
Publication number | Publication date |
---|---|
JPH0791957B2 (en) | 1995-10-09 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JPH01290899A (en) | Intermittent stanchion construction in composite-cross section shield tunnel | |
DE2739079A1 (en) | Multiple tunnel construction system - uses intermediate wall of pilot tunnel to support and guide measuring ring for adjacent tunnel | |
JPH08184290A (en) | Structure of subway station and construction thereof | |
JPH07107360B2 (en) | Station construction method using multi-connection shield method | |
JPS62182398A (en) | Shielded tunnel | |
JP3908978B2 (en) | Junction structure and junction construction method for large-section tunnel segments | |
JP2799343B2 (en) | Replacement method of middle pillar in lining of multiple tunnels | |
JP3972633B2 (en) | Tunnel and its construction method | |
JP2747487B2 (en) | Replacement method of middle pillar in lining of multiple tunnels | |
DE3900431A1 (en) | Underground gallery support | |
JPH02153196A (en) | Tunnel excavation method and shield excavation | |
US3710581A (en) | Tubular construction | |
JP4418123B2 (en) | Junction structure of large-section tunnel segment | |
JPH077438Y2 (en) | Cylindrical wall for lining drill holes | |
JPH084491A (en) | Segment having gull part projection in multi-circular shield construction and installation thereof | |
JP3988652B2 (en) | Tunnel branch and junction structure | |
JP2670484B2 (en) | Method for lining double drill holes | |
JP2683642B2 (en) | Tubular wall for digging hole lining | |
SU1564275A1 (en) | Method of constructing deep laid underground station on its operative line | |
JP3646698B2 (en) | Construction method for underground structures | |
JP2003138897A (en) | Tunnel and its construction method | |
JPH03253696A (en) | Changing method of center column in lining of multiple connected tunnel | |
JPH03253699A (en) | Changing method of center column in lining of multiple connected tunnel | |
JPH03247894A (en) | Method and device for excavation of compound tunnel for station and track between stations | |
JP2662638B2 (en) | Composite section shield tunnel structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20071009 Year of fee payment: 12 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20081009 Year of fee payment: 13 |
|
EXPY | Cancellation because of completion of term | ||
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20081009 Year of fee payment: 13 |