JPH0123632B2 - - Google Patents

Info

Publication number
JPH0123632B2
JPH0123632B2 JP800582A JP800582A JPH0123632B2 JP H0123632 B2 JPH0123632 B2 JP H0123632B2 JP 800582 A JP800582 A JP 800582A JP 800582 A JP800582 A JP 800582A JP H0123632 B2 JPH0123632 B2 JP H0123632B2
Authority
JP
Japan
Prior art keywords
precast wall
floor
slab
slabs
precast
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP800582A
Other languages
Japanese (ja)
Other versions
JPS58123975A (en
Inventor
Naoshi Myazaki
Mitsuo Kitamura
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP800582A priority Critical patent/JPS58123975A/en
Publication of JPS58123975A publication Critical patent/JPS58123975A/en
Publication of JPH0123632B2 publication Critical patent/JPH0123632B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Load-Bearing And Curtain Walls (AREA)
  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Description

【発明の詳細な説明】 この発明は、プレハブ建築物の耐震壁構築工法
に関し、とくに、中高層プレハブ建築物の建築工
法において、構造物躯体の上下方向に連続して建
込むプレキヤスト壁版に、組立鉄骨梁の弦材とラ
チスバーおよびガセツトプレートを内蔵させ、上
下階のプレキヤスト壁版を接合して組立鉄骨梁を
形成し、その対接部を現場打ちコンクリートの床
版により埋設して一体の鉄骨コンクリート梁とす
ることにより、耐震性にすぐれた構造物を能率的
に構築するようにしたものである。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method for constructing earthquake-resistant walls for prefabricated buildings, and in particular, in a construction method for mid- to high-rise prefabricated buildings, precast wall slabs that are built continuously in the vertical direction of a structure frame are assembled. The chord members, lattice bars, and gusset plates of the steel beam are built in, and the precast wall slabs on the upper and lower floors are joined to form an assembled steel beam, and the opposing parts are buried with cast-in-place concrete floor slabs to form an integrated steel beam. By using concrete beams, a structure with excellent earthquake resistance can be constructed efficiently.

従来、プレハブ建築物の壁体は、床版を造成し
た後にプレキヤスト壁版を建込む工法であるた
め、壁と床との接合工事に多大の工費と工期とを
要し、また、プレキヤスト壁版と床版との間に充
填したジヨイントコンクリート、モルタルグラウ
トが硬化後に収縮するため、完全に一体化しない
という問題があり、このような問題に対処する工
法として、上端部にスタツドボルトあるいは鉄筋
等のシヤーコネクターを鉄骨から突出させ、下端
部に凹部を設けた鉄骨コンクリート梁を一体に構
成してなる壁プレキヤスト版を上下に連続して建
込み、その対接部に床型枠を設置し、床配筋後こ
の床型枠に現場打ちコンクリートを打設し、打設
した現場打ちコンクリートによつて上階の壁プレ
キヤスト版の下端部と下階の壁プレキヤスト版の
上端部とを同時に埋設して一体化するようにした
工法が知られている(特公昭52−7647号公報参
照)。
Conventionally, the walls of prefabricated buildings have been built using a construction method in which precast wall slabs are erected after creating floor slabs, which requires a large amount of construction cost and time to join the walls and floors. There is a problem that the joint concrete and mortar grout filled between the floor slab and the floor slab shrink after hardening, so they are not completely integrated.As a construction method to deal with this problem, stud bolts or reinforcing bars etc. are installed at the upper end. Shear connectors protrude from the steel frame, and wall precast slabs made up of a steel-framed concrete beam with a recess at the lower end are erected in a continuous manner vertically, and a floor formwork is installed at the opposing part. After floor reinforcement is placed, cast-in-place concrete is poured into this floor form, and the lower end of the pre-cast wall plate on the upper floor and the upper end of the pre-cast wall plate on the lower floor are simultaneously buried using the cast-in-place concrete. A construction method is known in which the two parts are integrated (see Japanese Patent Publication No. 7647/1983).

しかしながら、上記の工法では、上下階に連続
して建込まれる壁プレキヤスト版は、相互に現場
打ちコンクリート床版のみによつて一体化されて
いるに過ぎず、壁プレキヤスト版の上端部に一体
に埋設されている鉄骨梁は、相互に連結されるこ
となく各階ごとに単独に梁としての機能を営むよ
うになつているから、全体としての剛性、靭性が
十分とはいえず、地震発生によつて大きな水平力
が作用した場合に曲げ変形が生じ、耐震壁として
は必ずしも満足すべき安全性、信頼性が得られな
いという問題があつた。
However, in the above construction method, the wall precast slabs built continuously on the upper and lower floors are only integrated with each other by the cast-in-place concrete floor slab, and the upper end of the wall precast slab is integrated with the wall precast slabs. The buried steel beams are not connected to each other and function as beams independently on each floor, so their overall rigidity and toughness are not sufficient, making them susceptible to earthquakes. There was a problem in that bending deformation occurred when a large horizontal force was applied to the wall, making it impossible to obtain satisfactory safety and reliability as a seismic wall.

この発明は、上記の問題を解決するためになさ
れたものであり、この発明の目的は、組立鉄骨梁
の構成部材を内蔵するプレキヤスト壁版を用いて
上下階に連続する組立鉄骨梁を形成する耐震壁構
築工法を提供することにあり、またこの発明の目
的は、上下階のプレキヤスト壁版の対接部に現場
打ちコンクリートを打設して鉄骨コンクリート梁
を形成する耐震壁構築工法を提供することにあ
り、さらに、この発明の目的は、耐震性にすぐれ
たプレハブ建築物を能率的に構築する工法を提供
することにある。
This invention was made in order to solve the above-mentioned problem, and the purpose of this invention is to form an assembled steel beam that is continuous between upper and lower floors using a precast wall slab that incorporates the constituent members of the assembled steel beam. It is an object of the present invention to provide a shear wall construction method in which cast-in-place concrete is cast in the opposing parts of precast wall slabs on upper and lower floors to form steel concrete beams. In particular, a further object of the present invention is to provide a construction method for efficiently constructing a prefabricated building with excellent earthquake resistance.

すなわち、この発明は、図示する実施例のよう
に、上端面の長さ方向に沿つて同一平面上に、鉄
骨梁の弦材12がその上面を露出して内蔵され、
下端面には、ガセツトプレート16がその下端縁
を突出して内蔵され、前記弦材12とガセツトプ
レート16との間にラチスバー18を取付けて一
体に成形してなるプレキヤスト壁版10,10a
を上下方向に連続して建込み、上階のプレキヤス
ト壁版10のガセツトプレート16の下端縁をこ
れに対接する下階のプレキヤスト壁版10aの弦
材12aの上面に接合して組立鉄骨梁を構成し、
上下階のプレキヤスト壁版10,10aの対接部
に床型枠36を設置した後、上階のプレキヤスト
壁版10の下端部と下階のプレキヤスト壁版10
aの上端部とを現場打ちコンクリートにより埋設
して一体とすることを特徴とするプレハブ建築物
の耐震壁構築工法に係る。
That is, in the present invention, as in the illustrated embodiment, the chord members 12 of the steel beam are built in with their upper surfaces exposed on the same plane along the length direction of the upper end surface,
A gusset plate 16 is built into the lower end surface with its lower edge protruding, and a lattice bar 18 is attached between the chord material 12 and the gusset plate 16, and the precast wall slabs 10 and 10a are integrally formed.
The lower end edge of the gusset plate 16 of the precast wall slab 10 on the upper floor is connected to the upper surface of the chord member 12a of the precast wall slab 10a on the lower floor that faces it, and the assembled steel beam is constructed continuously in the vertical direction. constitutes,
After installing the floor formwork 36 at the opposing parts of the precast wall slabs 10 and 10a on the upper and lower floors, the lower ends of the precast wall slabs 10 on the upper floor and the precast wall slabs 10 on the lower floor are installed.
This relates to a method for constructing a shear wall for a prefabricated building, characterized in that the upper end of the a is buried in cast-in-place concrete and integrated.

以下、この発明の実施例について、図面を参照
して説明する。
Embodiments of the present invention will be described below with reference to the drawings.

第1図ないし第3図において、プレキヤスト壁
版10は、その上端部の長さ方向に沿つてT形鋼
からなる弦材12を内蔵し、該弦材12の上面は
プレキヤスト壁版10の上端面と同一平面上に露
出させる。この弦材12の上面には、一部分を除
いてスタツドボルト14を溶接等により複数本固
着して突出させる。プレキヤスト壁版10の下端
面は凹部20を形成し、下端面よりも下方のガセ
ツトプレート16の下端縁を突出させて内蔵させ
る。上記弦材12とガセツトプレート16との間
には、ラチスバー18を溶接により取付けて、こ
れらの各部材を一体として成形する。プレキヤス
ト壁版10の左右両側の端面にも、下端面と同様
に凹部22が形成してある。符号24はアンカー
筋、26は補強筋、28は縦筋を、30は横筋を
それぞれ示す。
In FIGS. 1 to 3, the precast wall slab 10 has a built-in chord member 12 made of T-beam steel along its upper end, and the upper surface of the chord member 12 is located above the precast wall slab 10. Expose on the same plane as the end face. A plurality of stud bolts 14 are fixed and protruded from the upper surface of the chord member 12 by welding or the like except for a portion thereof. The lower end surface of the precast wall slab 10 forms a recess 20, and the lower end edge of the gusset plate 16 below the lower end surface projects and is housed therein. A lattice bar 18 is attached by welding between the chord member 12 and the gusset plate 16, and these members are integrally molded. Recesses 22 are also formed on both left and right end faces of the precast wall slab 10, similar to the lower end face. Reference numeral 24 indicates an anchor reinforcement, 26 a reinforcing reinforcement, 28 a vertical reinforcement, and 30 a horizontal reinforcement.

上記構成のプレキヤスト壁版10を、その弦材
12の両端部を鉄骨柱32の各階毎に設けてある
取付部34に緊結して上下方向に連続して建込ん
で、上階のプレキヤスト壁版10のガセツトプレ
ート16を下階のプレキヤスト壁版10aの弦材
12aの上面に載せ、該ガセツトプレート16の
上端縁を弦材12aの上面に溶接して接合する。
建込まれた上階のプレキヤスト壁版10の上端面
は、これに対接する下階のプレキヤスト壁版10
aの弦材12aの上端面に突設したスタツドボル
ト14aの頭部と接触しないようにその高さを設
定して、適宜の間隔のすき間を保つようにしてあ
る。
The precast wall slabs 10 having the above structure are erected continuously in the vertical direction by tightly connecting both ends of the chord members 12 to the attachment portions 34 provided for each floor of the steel column 32, and the precast wall slabs on the upper floors are installed. Ten gusset plates 16 are placed on the upper surface of the chord members 12a of the precast wall slab 10a on the lower floor, and the upper edges of the gusset plates 16 are welded and joined to the upper surface of the chord members 12a.
The upper end surface of the built precast wall slab 10 on the upper floor is the precast wall slab 10 on the lower floor that is opposite to this.
The height of the stud bolt 14a is set so as not to come into contact with the head of the stud bolt 14a protruding from the upper end surface of the chord member 12a of the string member 12a, and an appropriate gap is maintained.

次いで、上下階のプレキヤスト壁版10,10
aの対接部に、床型枠を兼ねるプレキヤスト床版
36を設置し、第4図に示すように、プレキヤス
ト壁版10の凹部20に鉄筋38を挿通して配筋
して、隣接する床と連続させ、プレキヤスト床版
36内に現場打ちコンクリートを打設して床版4
0を造成する。この現場打ちコンクリートは、プ
レキヤスト壁版10の下端部が凹部20の底面よ
りも上方の位置まで埋没するように打設して、コ
ンクリートが対接部相互間のすき間および凹部2
0内にも行きわたるようにする。
Next, precast wall plates 10 and 10 on the upper and lower floors
A precast floor slab 36, which also serves as a floor formwork, is installed in the opposing part of a, and as shown in FIG. Continuing with the pre-cast floor slab 36, cast-in-place concrete is poured into the floor slab 4.
Create 0. This cast-in-place concrete is cast so that the lower end of the precast wall slab 10 is buried above the bottom of the recess 20, and the concrete is poured into the gaps between the contact parts and into the recess 20.
Make sure to spread it even within 0.

かくして、プレキヤスト壁版10と床版40と
が接続すると同時に、上階のプレキヤスト壁版1
0の下端部と下階のプレキヤスト壁版10aの上
端面とが結合して一体化される。
Thus, at the same time that the precast wall slab 10 and the floor slab 40 are connected, the precast wall slab 1 on the upper floor
0 and the upper end surface of the precast wall slab 10a on the lower floor are combined and integrated.

また、プレキヤスト壁版10と左右両側の鉄骨
柱32との間にも型枠(図示せず)を設置して、
第2図に示すように鉄筋42を配筋して、この型
枠内に現場打ちコンクリートを打設して鉄骨鉄筋
コンクリート柱44を造成する。この現場打ちコ
ンクリートは、第5図に示すように、プレキヤス
ト壁版10の左右両側の凹部22の底面よりも内
側の位置まで埋没するように打設して、プレキヤ
スト壁版10の両側部を鉄骨鉄筋コンクリート柱
44に埋め込んで一体にする。
In addition, formwork (not shown) is also installed between the precast wall slab 10 and the steel columns 32 on both the left and right sides,
As shown in FIG. 2, reinforcing bars 42 are arranged, and cast-in-place concrete is poured into the formwork to construct a steel reinforced concrete column 44. As shown in FIG. 5, this cast-in-place concrete is poured so that it is buried inside the bottom of the recesses 22 on both the left and right sides of the precast wall slab 10, and both sides of the precast wall slab 10 are covered with steel frames. It is embedded in a reinforced concrete column 44 and integrated.

上記の手順を繰返して下階から上階にプレキヤ
スト壁版を連続して建込むことにより、この発明
の耐震壁が完成する。
The shear wall of the present invention is completed by repeating the above procedure and continuously erecting precast wall slabs from the lower floor to the upper floor.

上記のように、この発明の耐震壁は、上階のプ
レキヤスト壁版の弦材とこれに対接する下階のプ
レキヤスト壁版の弦材とが、上階のプレキヤスト
壁版に取付けたラチスバーのガセツトプレートを
介して一体に接合されて、上下階のプレキヤスト
壁版の弦材をそれぞれ上弦材、下弦材とする組立
鉄骨梁を構成し、さらに上階のプレキヤスト壁版
の下端部と下階のプレキヤスト壁版の上端部とが
現場打ちコンクリートによつて埋設されて鉄骨コ
ンクリート梁を構成することになり、これによつ
て、上下方向に連続するプレキヤスト壁版が、き
わめて強固に結合することになる。
As described above, in the shear wall of the present invention, the chord members of the precast wall slab on the upper floor and the chord members of the precast wall slab on the lower floor that are opposite to the chord members of the precast wall slab on the upper floor are connected to They are joined together via set plates to form an assembled steel beam with the chords of the precast wall slabs on the upper and lower floors as the upper and lower chord members, respectively, and the lower end of the precast wall slabs on the upper floor and the lower end of the precast wall slabs on the lower floor. The upper ends of the precast wall slabs will be buried with cast-in-place concrete to form a steel-framed concrete beam, which will connect the vertically continuous precast wall slabs extremely firmly. .

上記実施例では、プレキヤスト壁版の弦材の上
面にスタツドボルトを突設して、下端面には凹部
を形成し、対接するプレキヤスト壁版のすき間に
床配筋を施して現場打ちコンクリートを打設する
こととしているが、必ずしもこのようにする必要
はなく、これらの構成部材の一部もしくは全部を
省略して現場打ちコンクリートを打設することも
できる。また、プレキヤスト壁版の左右両側の凹
部についてもこれを省略することができる。
In the above example, stud bolts are provided protruding from the upper surface of the chord members of the precast wall slabs, a recess is formed on the lower end surface, floor reinforcement is placed between the gaps between the opposing precast wall slabs, and cast-in-place concrete is poured. However, it is not necessary to do so, and it is also possible to omit some or all of these structural members and place cast-in-place concrete. Furthermore, the recesses on both the left and right sides of the precast wall slab can also be omitted.

以上説明したところから明らかなように、この
発明は、プレキヤスト壁版に組立鉄骨梁の構成部
材となる弦材、ガセツトプレートおよびラチスバ
ーを内蔵させ、このプレキヤスト壁版を上下方向
に連続して建込み、上階のプレキヤスト壁版とこ
れに対接する下階のプレキヤスト壁版とをガセツ
トプレートにより接合して高い剛性をもつ組立鉄
骨梁を構成し、さらに、上下階のプレキヤスト壁
版の対接部を現場打ちコンクリートにより一体に
埋設して鉄骨コンクリート梁を構成するようにし
ている。したがつて、この発明によれば、上下方
向に強固に一体化された靭性の高い壁体を構築す
ることが可能となり、曲げ変形に対する追随性能
が一段と向上するから、地震発生によつて大きな
水平力が作用した場合においても、耐震壁として
の機能を十分に発揮することができる。
As is clear from the above explanation, the present invention incorporates chord members, gusset plates, and lattice bars, which are the constituent members of an assembled steel beam, in a precast wall slab, and builds the precast wall slab continuously in the vertical direction. The precast wall slabs on the upper floor and the opposing precast wall slabs on the lower floor are connected by gusset plates to form an assembled steel beam with high rigidity, and the precast wall slabs on the upper and lower floors are connected by The sections are integrally buried with cast-in-place concrete to form a steel-framed concrete beam. Therefore, according to the present invention, it is possible to construct a wall body with high toughness that is firmly integrated in the vertical direction, and the ability to follow bending deformation is further improved. Even when force is applied, it can fully perform its function as a seismic wall.

また、この発明によれば、床版のコンクリート
打設と同時にその階のプレキヤスト壁版がコンク
リートの中に埋め込まれるから、壁体と床版との
接続が同時作業によつて完成し、工程の節減と工
期の短縮とが可能となり、耐震性にすぐれたプレ
ハブ建築物を能率的に短期間で構築することがで
きる効果が併せて得られる。
Furthermore, according to this invention, since the precast wall slab of the floor is embedded in the concrete at the same time as the concrete of the floor slab is poured, the connection between the wall and the floor slab is completed at the same time, and the process is completed. It is possible to save money and shorten the construction period, and it also has the effect of being able to efficiently construct prefabricated buildings with excellent earthquake resistance in a short period of time.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は、この発明の工法によるプレキヤスト
壁版と床版および鉄骨柱との接合状態の実施例を
示す一部正面図、第2図は、その平面図、第3図
は、その縦断面図、第4図は、上下階のプレキヤ
スト壁版の対接部を示す拡大正面図、第5図は、
プレキヤスト壁版と鉄骨柱との接合部分を示す拡
大正面図である。 図中、10,10aはプレキヤスト壁版、1
2,12aは弦材、16はガセツトプレート、1
8はラチスバー、36は床型枠である。
Fig. 1 is a partial front view showing an example of the joint state of precast wall slabs, floor slabs and steel columns by the construction method of the present invention, Fig. 2 is a plan view thereof, and Fig. 3 is a vertical cross section thereof. Figure 4 is an enlarged front view showing the contact parts of the precast wall slabs on the upper and lower floors, and Figure 5 is
FIG. 2 is an enlarged front view showing a joint between a precast wall slab and a steel column. In the figure, 10 and 10a are precast wall plates, 1
2, 12a are string members, 16 is a gusset plate, 1
8 is a lattice bar, and 36 is a floor formwork.

Claims (1)

【特許請求の範囲】[Claims] 1 上端面の長さ方向に沿つて同一平面上に、鉄
骨梁の弦材がその上面を露出して内蔵され、下端
面にはガセツトプレートがその下端縁を突出して
内蔵され、前記弦材とガセツトプレートとの間に
ラチスバーを取付けて一体に成形してなるプレキ
ヤスト壁版を上下方向に連続して建込み、上階の
プレキヤスト壁版のガセツトプレートの下端縁を
これに対接する下階のプレキヤスト壁版の弦材の
上面に接合して組立鉄骨梁を構成し、上下階のプ
レキヤスト壁版の対接部に床型枠を設置した後、
上階のプレキヤスト壁版の下端部と下階のプレキ
ヤスト壁版の上端部とを現場打ちコンクリートに
より埋設して一体とすることを特徴とするプレハ
ブ建築物の耐震壁構築工法。
1. The chord members of the steel beam are built in on the same plane along the length direction of the upper end face with their upper faces exposed, and the gusset plate is built in the lower end face with its lower edge protruding, and the chord members A precast wall slab formed integrally with a lattice bar attached between the upper floor precast wall slab and the gusset plate is installed continuously in the vertical direction, and the lower edge of the gusset plate of the upper floor precast wall slab is connected to the After joining the upper surface of the chord members of the precast wall slabs on the floor to form an assembled steel beam, and installing the floor formwork at the opposing parts of the precast wall slabs on the upper and lower floors,
A method for constructing a shear wall for a prefabricated building, characterized in that the lower end of the precast wall slab on the upper floor and the upper end of the precast wall slab on the lower floor are buried and integrated with cast-in-place concrete.
JP800582A 1982-01-21 1982-01-21 Construction of earthquake-proof wall of prefabricated building Granted JPS58123975A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP800582A JPS58123975A (en) 1982-01-21 1982-01-21 Construction of earthquake-proof wall of prefabricated building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP800582A JPS58123975A (en) 1982-01-21 1982-01-21 Construction of earthquake-proof wall of prefabricated building

Publications (2)

Publication Number Publication Date
JPS58123975A JPS58123975A (en) 1983-07-23
JPH0123632B2 true JPH0123632B2 (en) 1989-05-08

Family

ID=11681239

Family Applications (1)

Application Number Title Priority Date Filing Date
JP800582A Granted JPS58123975A (en) 1982-01-21 1982-01-21 Construction of earthquake-proof wall of prefabricated building

Country Status (1)

Country Link
JP (1) JPS58123975A (en)

Also Published As

Publication number Publication date
JPS58123975A (en) 1983-07-23

Similar Documents

Publication Publication Date Title
JP2622013B2 (en) Reinforced concrete shear wall structure
JPH0480444A (en) Connection unit of reinforced concrete pole and steel framed beam
JPH02300439A (en) Prefabricating method
JPH0123632B2 (en)
JP2758208B2 (en) Joint method between column and steel reinforced concrete beam
JPH0270850A (en) Pc coupled beam and execution of construction using same
JP2516808B2 (en) Construction method of ramen type precast concrete structure
JPH0366878A (en) Construction method for precast column and beam and precast anti-seismic wall
JPH0781307B2 (en) How to build a skyscraper
JPS6335773B2 (en)
JPH0781355B2 (en) Construction method of joist slab using precast concrete girder
JPS6347201Y2 (en)
JPH02236328A (en) Construction method for super-highrice building
JPH0448143B2 (en)
JP3122739B2 (en) Frame consisting of precast RC columns and precast RC beams
JPS605748B2 (en) Construction method for walls using unit steel formwork
JPH0350846B2 (en)
JPS60510B2 (en) construction method
JPS6362623B2 (en)
JPH0250262B2 (en)
JPH0481011B2 (en)
JPH0781315B2 (en) Construction method of composite structure with precast reinforced concrete columns and steel beams
JPH0349331B2 (en)
JPH11264189A (en) Constructing method of steel-framed and steel reinforced concrete composite building
JPH0463356B2 (en)