JPH0122806Y2 - - Google Patents

Info

Publication number
JPH0122806Y2
JPH0122806Y2 JP9889783U JP9889783U JPH0122806Y2 JP H0122806 Y2 JPH0122806 Y2 JP H0122806Y2 JP 9889783 U JP9889783 U JP 9889783U JP 9889783 U JP9889783 U JP 9889783U JP H0122806 Y2 JPH0122806 Y2 JP H0122806Y2
Authority
JP
Japan
Prior art keywords
anchor
column base
anchor material
main body
base
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP9889783U
Other languages
Japanese (ja)
Other versions
JPS608304U (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP9889783U priority Critical patent/JPS608304U/en
Publication of JPS608304U publication Critical patent/JPS608304U/en
Application granted granted Critical
Publication of JPH0122806Y2 publication Critical patent/JPH0122806Y2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Description

【考案の詳細な説明】 本考案は、建造物の柱脚等の固定に使用するア
ンカーに関するものである。
[Detailed Description of the Invention] The present invention relates to an anchor used for fixing pillar bases of buildings.

従来、建造物等の柱脚を基礎構造物に固定する
には、例えば第1図に示したように、基礎コンク
リート1に埋め込んだアンカーボルト2,2の露
出された上端部に、柱脚3の下端に固着したベー
スプレート4のボルト孔5を通して、ナツト6を
締め込んで固定し、更にベースプレート4の囲り
に別のアンカー材7,7…を配設して、これをフ
ープ筋8で結合し、その露出した上端部と柱脚の
下部とをベースコンクリート9を施設するという
方法が採られている。このように複雑な構造を用
いなければならないのは、従来使用されているア
ンカー材が単純な棒材で構成されているためで、
アンカー材の引抜力に対して信頼性に欠けること
と、アンカー材を取り付ける施工精度も悪いた
め、鉄骨柱脚に働く応力を、アンカー材のみから
基礎コンクリートに伝達させられなかつた。この
ため、第1図のように、ベースプレート4の外周
に別のアンカー材7を配設し、コンクリートによ
り、柱脚部分を一体化させ、柱脚に働く応力をア
ンカー材7で基礎コンクリートに伝達させるとい
う方法であつた。また、柱脚3にせん断力が働く
場合、(柱脚の横移動)第1図のような従来の方
法であれば、アンカーボルト2のネジ部はコンク
リート1の中まで埋め込まれてしまう場合が多
く、この場合、このネジ部にせん断力が働くと、
この部分が非常に破断しやすくなり、脆性破壊を
生じやすく、構造物にとつては、危険な状態とな
る。したがつて、施工が面倒で多額の工費を要す
ることになる。
Conventionally, in order to fix a column base of a building or the like to a foundation structure, for example, as shown in FIG. Pass through the bolt hole 5 of the base plate 4 fixed to the lower end and tighten the nut 6 to fix it, and further arrange other anchor materials 7, 7, etc. around the base plate 4, and connect them with a hoop muscle 8. However, a method is adopted in which the exposed upper end and the lower part of the column base are covered with base concrete 9. The reason why such a complicated structure has to be used is because the anchor materials used in the past are made of simple rods.
Due to the lack of reliability with respect to the pull-out force of the anchor materials and the poor construction accuracy for attaching the anchor materials, it was not possible to transmit the stress acting on the steel column base from the anchor materials alone to the foundation concrete. For this reason, as shown in Figure 1, another anchor material 7 is placed around the outer periphery of the base plate 4, the column base is integrated with concrete, and the stress acting on the column base is transferred to the foundation concrete by the anchor material 7. The method was to let him do it. In addition, when shear force is applied to the column base 3, if the conventional method (lateral movement of the column base) as shown in Figure 1 is used, the threaded part of the anchor bolt 2 may be embedded deep into the concrete 1. In most cases, when shear force is applied to this thread,
This part becomes extremely susceptible to breakage and brittle fracture, creating a dangerous situation for the structure. Therefore, construction is troublesome and requires a large amount of construction cost.

本考案は、前記従来のアンカーボルトによる柱
脚取付構造の改善を図るためなされたもので、柱
脚のベースプレートに設けられたボルト孔と対応
して複数の異形鉄筋アンカー材を配置し、各異形
鉄筋アンカーの上端部に、その本体部分より小径
とした雄ネジ部と、そのネジ部に連続して、かな
りの軸部(ベースプレート厚さの半分以上)を設
けると共に、この軸部を本体部分より小径とする
ことにより、添プレートが、軸部と本体部分との
境で止まり、添プレート以下の本体部分(異形鉄
筋)がコンクリート中に埋つて、軸部がコンクリ
ートに埋まることなく、確実にコンクリートの表
面から出る施工ができ、更に各異形鉄筋アンカー
の本体部分をフープ筋で拘束することにより、異
形鉄筋の大きな表面積によつて、アンカー材とコ
ンクリートとの付着力を増大すると共に、各異形
鉄筋アンカーのフープ筋による拘束で基礎コンク
リートの剪断抵抗を増大させて、全体として引抜
抵抗力の大きなものとし、簡単な構造で経済的に
施工のできる柱脚等固定用アンカーを提供しよう
とするものである。
The present invention was made to improve the above-mentioned conventional column base mounting structure using anchor bolts, and a plurality of irregularly shaped reinforcing bar anchors are arranged in correspondence with the bolt holes provided in the base plate of the column base, and each irregularly shaped At the upper end of the reinforcing bar anchor, there is a male screw part with a diameter smaller than the main body part, and a considerable shaft part (more than half the thickness of the base plate) is provided continuous to the thread part, and this shaft part is larger than the main body part. By making the diameter small, the attachment plate stops at the boundary between the shaft and the main body, and the body part (deformed reinforcing bar) below the attachment plate is buried in the concrete, ensuring that the shaft does not become buried in the concrete. Furthermore, by restraining the main body of each deformed rebar anchor with hoop reinforcement, the large surface area of the deformed rebar increases the adhesion force between the anchor material and concrete, and each deformed rebar anchor The aim is to increase the shear resistance of the foundation concrete by restraining it with the hoop reinforcement of the anchor, thereby increasing the pull-out resistance as a whole, and to provide an anchor for fixing column bases, etc., which has a simple structure and can be constructed economically. be.

以下、本考案アンカーの実施例を第2図を参照
して説明する。なお、第1図に示した従来のもの
と同様の部材については同一の符号を付して説明
する。
Hereinafter, an embodiment of the anchor of the present invention will be described with reference to FIG. Note that members similar to those of the conventional one shown in FIG. 1 will be described with the same reference numerals.

第2図において、10は基礎コンクリート1上
において柱脚3のベースプレート4を載置する添
プレートで、ベースプレート4に設けられたボル
ト孔5,5…と対応した位置に、それぞれ貫通孔
11,11…が設けられている。12は柱脚3を
固定するため基礎コンクリート1に埋設するアン
カー材で、異形鉄筋を使用し、その上部には前記
の貫通孔11に合致するテーパー部13を介し
て、テーパー部13より下部の本体部14より小
径の軸部17と雄ネジ部15が形成されている。
そして、各アンカー材12は貫通孔11に挿入し
て嵌合し、雄ネジ部15を添プレート10上に突
出させ、その突出した雄ネジ部15にナツト6が
螺合されている。また、各アンカー材12の本体
部14は、互にフープ筋16,16…により結合
されている。
In FIG. 2, reference numeral 10 denotes an attachment plate on which the base plate 4 of the column base 3 is placed on the foundation concrete 1, and through holes 11, 11 are provided at positions corresponding to the bolt holes 5, 5, . . . provided in the base plate 4, respectively. ...is provided. Reference numeral 12 denotes an anchor material buried in the foundation concrete 1 to fix the column base 3. The anchor material is made of deformed reinforcing bars, and the upper part is connected to the lower part of the tapered part 13 through the tapered part 13 that matches the through hole 11. A shaft portion 17 and a male screw portion 15 having a diameter smaller than that of the main body portion 14 are formed.
Each anchor material 12 is inserted into the through hole 11 and fitted, causing the male threaded portion 15 to protrude above the attachment plate 10, and the nut 6 is screwed into the protruded male threaded portion 15. Further, the main body portions 14 of each anchor material 12 are connected to each other by hoop lines 16, 16, . . . .

本考案のアンカーは上述のように構成されてお
り、基礎コンクリート1の打設時に、添プレート
10を基礎コンクリート1の上面に表出するよう
にして埋設する。そして、柱脚3を固定するに
は、ナツト6をはずしてベースプレート4の各ボ
ルト孔5を各アンカー材12の雄ネジ部15に嵌
め合せ、ベースプレート4より上方へ突出した雄
ネジ部15に座金18を介してナツト6を締め込
むのである。
The anchor of the present invention is constructed as described above, and when the foundation concrete 1 is placed, the attachment plate 10 is buried so as to be exposed on the upper surface of the foundation concrete 1. To fix the column base 3, remove the nuts 6, fit each bolt hole 5 of the base plate 4 into the male threaded part 15 of each anchor material 12, and insert a washer into the male threaded part 15 protruding upward from the base plate 4. The nut 6 is tightened through the nut 18.

以上説明したように本考案のアンカーは、アン
カー材として異形鉄筋を用いたので、コンクリー
トとの付着力、摩擦力が極めて大きく、各アンカ
ー材の引抜抵抗力を著しく増大することになると
共に、各アンカー材はフープ筋によつて一体的に
拘束されるので、各アンカー材に相乗して全体的
に一層顕著な抗力を発揮することになり、その結
果、従来のような補強のためのアンカーを更に施
設するという必要がなく、しかも、引抜抵抗力が
大であることにより、各アンカー材の長さを短縮
でき、したがつて基礎コンクリートの厚さをそれ
に応じて節減することができる。また、アンカー
の埋設施工にあたつては、各アンカー材は添プレ
ートによつて埋設時の位置決めが簡易であると共
に、基礎コンクリートの打設時に各個に移動する
ことが防止され、精度の高い施工を行うことがで
きる等、多くの利点を有するものである。
As explained above, the anchor of the present invention uses deformed reinforcing bars as the anchor material, so the adhesion force and frictional force with concrete are extremely large, which significantly increases the pull-out resistance of each anchor material. Since the anchor materials are integrally restrained by the hoop reinforcement, each anchor material synergizes and exerts a more pronounced drag force as a whole.As a result, it is difficult to use conventional anchors for reinforcement. Due to the fact that there is no need for further installations and the pull-out resistance is high, the length of each anchor member can be shortened and the thickness of the foundation concrete can therefore be reduced accordingly. In addition, when burying anchors, each anchor material can be easily positioned using an attached plate, and it also prevents each anchor from moving when the foundation concrete is poured, allowing for highly accurate construction. It has many advantages, such as being able to perform

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は従来のアンカーによる柱脚の取付構造
を示す側断面図、第2図は本考案の一実施例のア
ンカーによる柱脚の取付状態を示した側断面図で
ある。 1……基礎コンクリート、3……柱脚、4……
ベースプレート、5……ボルト孔、6……ナツ
ト、10……添プレート、11……貫通孔、12
……アンカー材、13……テーパー部、14……
本体部、15……雄ネジ部、16……フープ筋、
17……軸部。
FIG. 1 is a side sectional view showing a structure for attaching a column pedestal using a conventional anchor, and FIG. 2 is a side sectional view showing a state in which a column pedestal is attached to an anchor according to an embodiment of the present invention. 1...Foundation concrete, 3...Column base, 4...
Base plate, 5...Bolt hole, 6...Nut, 10...Additional plate, 11...Through hole, 12
... Anchor material, 13 ... Tapered part, 14 ...
Main body part, 15...Male thread part, 16...Hoop muscle,
17...Shaft part.

Claims (1)

【実用新案登録請求の範囲】[Scope of utility model registration request] 上部に本体部より小径とした雄ネジ部と軸部を
形成してなる異形鉄筋によるアンカー材の上部
を、柱脚のベースプレートの各ボルト孔に対応し
て設けた添プレートの各貫通孔に挿通して、その
各アンカー材の上部を連携すると共に、各アンカ
ー材の本体部をフープ筋により一体的に結合した
ことを特徴とする、建造物等の柱脚固定用アンカ
ー。
Insert the upper part of the anchor material made of deformed reinforcing bars, which has a male screw part with a smaller diameter than the main body part and a shaft part, into each through hole of the attachment plate, which corresponds to each bolt hole of the base plate of the column base. An anchor for fixing a column base of a building, etc., characterized in that the upper part of each anchor material is linked together, and the main body of each anchor material is integrally connected by a hoop muscle.
JP9889783U 1983-06-28 1983-06-28 Anchor for fixing column bases of buildings, etc. Granted JPS608304U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP9889783U JPS608304U (en) 1983-06-28 1983-06-28 Anchor for fixing column bases of buildings, etc.

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP9889783U JPS608304U (en) 1983-06-28 1983-06-28 Anchor for fixing column bases of buildings, etc.

Publications (2)

Publication Number Publication Date
JPS608304U JPS608304U (en) 1985-01-21
JPH0122806Y2 true JPH0122806Y2 (en) 1989-07-11

Family

ID=30234604

Family Applications (1)

Application Number Title Priority Date Filing Date
JP9889783U Granted JPS608304U (en) 1983-06-28 1983-06-28 Anchor for fixing column bases of buildings, etc.

Country Status (1)

Country Link
JP (1) JPS608304U (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5464689B2 (en) * 2009-07-31 2014-04-09 日立機材株式会社 Column base structure
JP5522775B2 (en) * 2009-07-31 2014-06-18 日立機材株式会社 Column base structure
JP6026794B2 (en) * 2011-06-27 2016-11-16 岡部株式会社 Column base structure of steel column
JP6390747B1 (en) * 2017-04-18 2018-09-19 積水ハウス株式会社 Building foundation and anchor bolt support

Also Published As

Publication number Publication date
JPS608304U (en) 1985-01-21

Similar Documents

Publication Publication Date Title
US4408940A (en) Bolt anchor assembly
JPH0122806Y2 (en)
JP3078732B2 (en) Fixing method of base plate and anchor bolt of steel column base
JPS639622Y2 (en)
JPH0266852U (en)
JPH046458Y2 (en)
JPH019847Y2 (en)
JP2570085B2 (en) Anchor bolt construction method
JPH072828Y2 (en) Hollow concrete slab mounting structure
JPH0125130Y2 (en)
JPS62183120U (en)
JP2813367B2 (en) Mounting hardware and precast concrete panels
JPH1025747A (en) Fixing structure of steel-framed column base
JP2000110175A (en) Individual footing for mat foundation
JPS5851243Y2 (en) Steel pipe column end fixing device
JP2961405B2 (en) How to tighten anchor bolts for earthquake resistance
JPH0330424Y2 (en)
JP2587684Y2 (en) Concrete block
JPH0637166Y2 (en) Form support for concrete wall thickening
JPS5826252Y2 (en) concrete panel anchor
JP2600114Y2 (en) Plate fastener for PC board mounting
JP2913597B2 (en) Corrosion-resistant movable anchor type fall prevention device and anchor bar used therefor
JPH0452332Y2 (en)
JPH0431939Y2 (en)
JP2732244B2 (en) Seismic installation of equipment