JPH011822A - Continuous water-stop wall construction method - Google Patents

Continuous water-stop wall construction method

Info

Publication number
JPH011822A
JPH011822A JP62-156451A JP15645187A JPH011822A JP H011822 A JPH011822 A JP H011822A JP 15645187 A JP15645187 A JP 15645187A JP H011822 A JPH011822 A JP H011822A
Authority
JP
Japan
Prior art keywords
water
frame
wall
underground structure
extra length
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP62-156451A
Other languages
Japanese (ja)
Other versions
JPS641822A (en
JPH0432167B2 (en
Inventor
阿部 照男
Original Assignee
株式会社大林組
Filing date
Publication date
Application filed by 株式会社大林組 filed Critical 株式会社大林組
Priority to JP62-156451A priority Critical patent/JPH011822A/en
Publication of JPS641822A publication Critical patent/JPS641822A/en
Publication of JPH011822A publication Critical patent/JPH011822A/en
Publication of JPH0432167B2 publication Critical patent/JPH0432167B2/ja
Granted legal-status Critical Current

Links

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 (産業上の利用分野) この発明は連続止水壁(山留壁)構築工法に関する。[Detailed description of the invention] (Industrial application field) The present invention relates to a continuous water-stop wall (mountain retaining wall) construction method.

(従来技術とその問題点) 従来、連続止水壁(山留壁)を構築する場合、自硬性安
定液を注入しながら溝孔を掘削し、フレーム(応力材)
をその溝孔に挿入してフレームとともに自硬性安定液を
固まらせ、以上の操作を繰り返しながら止水壁を延長し
て所定の長さ、形状とし、その後、地下構造物予定地側
を掘削し、その際、止水壁の表面を削りフレームの地下
構造物予定地側の面を露出した状態で地下構漬物構榮用
空間を形成している。
(Conventional technology and its problems) Conventionally, when constructing a continuous water-stop wall (mountain retaining wall), a groove was excavated while a self-hardening stabilizing liquid was injected, and a frame (stressed material) was constructed.
was inserted into the groove to solidify the self-hardening stabilizing liquid together with the frame, and by repeating the above operations, the water stop wall was extended to the specified length and shape, and then excavated on the side where the underground structure was planned. At that time, the surface of the water-stop wall was scraped to expose the surface of the frame on the side where the underground structure was planned, forming a space for the underground pickle structure.

しかし自硬性安定液の固化不良、自硬性安定液内への土
塊の混入笠により止水壁の止水性が不十分な場所が生じ
るという問題があった。
However, there were problems in that the water-stopping properties of the water-stopping wall were insufficient in some areas due to insufficient solidification of the self-hardening stabilizing liquid and the incorporation of soil clods into the self-hardening stabilizing liquid.

このような問題に対して、壁に沿って拡がるプラスチッ
ク材料の連続板を壁区画内に埋め込むという方法(特公
昭53−22367号公報)も提示されているが、これ
においても、プラスチック材料の連続板をいかに壁区画
内に埋め込むか、壁区画内に埋め込まれたプラスチック
材料の連続板同士をいかに接続するかについては明らか
にされておらず実施困難であった。またプラスチック材
料の連続板を壁区画内に適合するよう製作しなければな
らず、材料費、加工費が高価になるという問題があった
To solve this problem, a method has been proposed in which a continuous plate of plastic material that spreads along the wall is embedded in the wall section (Japanese Patent Publication No. 53-22367); It was not clear how to embed the plates in the wall sections and how to connect the continuous plates of plastic material embedded in the wall sections, making it difficult to implement. Furthermore, continuous plates of plastic material must be manufactured to fit within the wall section, resulting in high material and processing costs.

この発明はこのような問題点に鑑みてなされたものであ
って、その目的とするところは、フレームを強化のため
に溝孔に挿入してなる連続止水壁構築工法において、安
価な材料を用いて壁区画内に埋め込みかつ接続する方法
を捉供し、より簡単かつ安価に止水壁の止水性を完全な
らしめることにある。
This invention was made in view of these problems, and its purpose is to use inexpensive materials in a continuous water-stop wall construction method in which a frame is inserted into a groove for reinforcement. It is an object of the present invention to provide a method of embedding and connecting a water-stopping wall in a wall section using the water-stopping method, thereby making the water-stopping property of a water-stopping wall more simple and inexpensive.

(問題点を解決するための手段) 上記目的を達成するために本発明は、安定液を満たしな
がら掘削した一区画の溝孔内に予め組立てたフレームを
挿入し、該安定液を硬化させた模、該区画に連続する区
画に同様の施工を繰り返して止水壁を形成し、地下構造
物構築側の地面を掘削し該止水壁を該フレームの該地下
構造物構築側の面まで削る連続止水壁構築工法において
、該予め組立てるフレームの該地下構造物構築側と反対
の面に不透水性シー!へを張り付けてかつ該不透水性シ
ートの端部に余長部をとり該余長部をフレーム喘に沿っ
て該地下構造物構築側の面に廻し部面に係止させておき
、該止水壁を該フレームの該地下構造物構築側の面まで
削った後、該フレームの該地下構造物構築側の面に係止
されている該余長部を係止から解放し、隣に位置する該
余長部と接合した。
(Means for Solving the Problems) In order to achieve the above object, the present invention involves inserting a pre-assembled frame into a section of trench that is excavated while filling it with a stabilizing liquid, and allowing the stabilizing liquid to harden. Then, repeat the same construction in a section that is continuous with the section to form a water cutoff wall, excavate the ground on the underground structure construction side, and cut the water cutoff wall down to the surface of the frame on the underground structure construction side. In the continuous water-stop wall construction method, an impermeable seam is placed on the surface of the pre-assembled frame opposite to the underground structure construction side! At the same time, take an extra length at the end of the water-impermeable sheet, turn the extra length along the frame to the surface on the underground structure construction side, and lock it to the surface of the underground structure. After cutting the water wall down to the surface of the frame on the underground structure construction side, release the extra length that is locked to the surface of the frame on the underground structure construction side, and place it next to it. It was joined to the extra length.

(実施例) 以下、本発明の好適な一実施例を第1図および第2図を
用いて説明する。
(Embodiment) A preferred embodiment of the present invention will be described below with reference to FIGS. 1 and 2.

第1図は本実施例の施工順序を示す平面図である。FIG. 1 is a plan view showing the construction order of this embodiment.

この施工順序としては、まず同図(a)に示すように地
上から矩形断面の一区画の溝孔12を、自硬性安定液1
4を注入しながら所定深度まで掘削する。
In this construction order, first, as shown in FIG.
Excavate to a predetermined depth while injecting 4.

この状態において、地上部では同図(b)に示すように
、H型鋼を並べた形のフレーム16を組立、用意してお
く。このフレーム16は連繋部材(図示省略)が横方向
に配設されておりこれにより全体が一体化している。
In this state, a frame 16 in which H-beams are arranged side by side is assembled and prepared in the above-ground part, as shown in FIG. 2(b). This frame 16 has connecting members (not shown) disposed laterally, thereby making the whole frame 16 integral.

そして、同図(C)に示すようにフレーム16の溝孔1
2に挿入後、地下構造物構築側の反対側となる面には不
透水性シート18をフレーム16の全面に渡って張り付
けておく。その際、不透水性シート18はその端部に余
長部20をとっておき、この余長部20をフレーム16
の端部に位置する1−1型!$122にその型形状に沿
って外側から曲げて固着し、最終的には余長部20は、
溝孔12に挿入後地下構造物構築側となる面のト1型鋼
22のフランジ部23に至らしめておく。そしてこの[
]型鋼22のフランジ部23に位置する余長部20は容
易にフランジ部23に対する固着から解放し得る状態に
しておき、またその長さは溝孔12に挿入後、隣接して
挿入されたフレームに張り付けられたシートの余長部と
接合することができる長さとしておく。不透水性シー]
−18は水を通さずかつ柔軟性がある材質のものであれ
ばよく、例えばビニールシート、ポリエチレンシート等
の合成樹脂シートが考えられる。
Then, as shown in the same figure (C), the slot 1 of the frame 16 is
2, an impermeable sheet 18 is pasted over the entire surface of the frame 16 on the surface opposite to the underground structure construction side. At that time, the water-impermeable sheet 18 has an extra length 20 at its end, and this extra length 20 is attached to the frame 16.
1-1 type located at the end of! The extra length 20 is bent and fixed from the outside along the shape of the mold, and finally the extra length 20 is
After being inserted into the groove hole 12, it is brought to the flange portion 23 of the T1 type steel 22 on the surface that will be the underground structure construction side. And this [
] The extra length part 20 located at the flange part 23 of the shaped steel 22 is made to be in a state where it can be easily released from the fixation to the flange part 23, and its length is set so that after it is inserted into the slot 12, the frame inserted adjacently The length should be such that it can be joined to the extra length of the sheet pasted on. Impermeable sea]
-18 may be made of a material that does not allow water to pass through and is flexible, such as a synthetic resin sheet such as a vinyl sheet or a polyethylene sheet.

次に同図(d)に示す如く、前記自硬性安定液14が硬
化する前にフレーム16を溝孔12内に挿入する。
Next, as shown in FIG. 4(d), the frame 16 is inserted into the slot 12 before the self-hardening stabilizer 14 hardens.

以上のフレーム16の挿入が終り、自硬性安定液14が
硬化した後は第1図(e)に示すように、前記溝孔12
に連続する区画の溝孔12を掘削しフレーム16を挿入
することを繰返す。
After the frame 16 has been inserted and the self-hardening stabilizing liquid 14 has hardened, as shown in FIG.
The process of excavating slots 12 in consecutive sections and inserting frames 16 is repeated.

このようにして所定の長さ、形状の溝孔12を掘削し自
硬性安定液14をフレーム16とともに硬化させた後、
同図(f)に示す如く、地下構造物予定地側の地面を掘
削し、その際、止水壁24の表面を削りフレーム16の
地下構造物予定地側の而を露出した状態で地下構造物構
築用空間を形成する。フレーム16の地下構造物予定地
側の面を露出するのは、後においてこの面に腹起し、切
梁等をI!)渡すためであり、その必要がない場合には
、ト(型鋼22のフランジ部23の部分の表面を削るだ
けでもよい。
After drilling the groove hole 12 of a predetermined length and shape in this way and hardening the self-hardening stabilizing liquid 14 together with the frame 16,
As shown in FIG. 2(f), the ground on the side where the underground structure is planned is excavated, and at that time, the surface of the water stop wall 24 is scraped to expose the part of the frame 16 on the side where the underground structure is planned. Create a space for building things. The surface of the frame 16 on the side where the underground structure is planned will be exposed later by standing up on this surface and attaching struts, etc. ), and if it is not necessary, it is sufficient to simply scrape the surface of the flange portion 23 of the shaped steel 22.

次に、余長部20のH型鋼22のフランジ部23に位置
する部分は、フランジ部23に対する固着から解放して
反対側に折り曲げ、硬化した自硬性安定液14の削り面
に沿わせ、一方この余長部20とジヨイント部26を挟
んで隣り合う余長部20も同様に自硬性安定液14の削
り面に沿わせ、これら余長部20の重なり合った部分を
止水壁24の全高さに渡って高さ方向に連続的に溶着し
、溶着部28を形成する。第2図は隣り合う不透水性シ
ート18の余長部20を溶着した状態を示す斜視図であ
る。
Next, the portion of the extra length portion 20 located at the flange portion 23 of the H-shaped steel 22 is released from the fixation to the flange portion 23 and bent to the opposite side, and is placed along the shaved surface of the hardened self-hardening stabilizer 14. The extra length portions 20 adjacent to each other with the joint portion 26 in between are also aligned along the scraped surface of the self-hardening stabilizer 14, and the overlapping portions of these extra length portions 20 are adjusted to the total height of the water stop wall 24. The welded portion 28 is formed by continuously welding in the height direction. FIG. 2 is a perspective view showing a state in which the extra lengths 20 of adjacent water-impermeable sheets 18 are welded together.

止水壁24のすべてのジヨイント部において不透水性シ
ート18の余長部20同士を溶着して本実施例の加工を
完了する。
The processing of this embodiment is completed by welding the extra lengths 20 of the water-impermeable sheet 18 to each other at all joints of the water-stopping wall 24.

本発明に係る連続止水壁構築工法により連続止水壁24
の全面に連続的に不透水性シート18が張り渡されるた
め、自硬性安定液の固化不良、自硬性安定液内への土塊
の混入等により止水壁の止水性が不十分な場所が生じて
も、その場所に張られている不透水性シートにより水の
流れが阻止されて止水壁の止水性が十分となる。
Continuous water cutoff wall 24 by the continuous water cutoff wall construction method according to the present invention
Since the water-impermeable sheet 18 is continuously stretched over the entire surface of the wall, there may be places where the water-stopping properties of the water-stopping wall are insufficient due to failure of solidification of the self-hardening stabilizing liquid or the mixing of soil clods into the self-hardening stabilizing liquid. However, the water-stopping properties of the water-stopping wall are sufficient because the water flow is blocked by the water-impermeable sheet stretched at that location.

また、不透水性シート18の端部は隣接する不透水性シ
ート18の端部と余長部20において溶着されるため不
透水性シート18の端部と隣接する不透水性シート18
の端部との間の止水性も十分となる。
In addition, since the end portion of the water-impermeable sheet 18 is welded to the end portion of the adjacent water-impermeable sheet 18 at the extra length portion 20, the end portion of the water-impermeable sheet 18 and the adjacent water-impermeable sheet 18
The water-tightness between the ends of the pipe is also sufficient.

また不透水性シートはプラスチック材料の連続板に比し
安価に入手でき、加工もフレーム面に合わせて鋏等で切
断すればよく容易であり、切断した不透水性シートがフ
レーム面より大きい場合においても不透水性シートは柔
軟性があり容易に曲がるためその誤差を包容することが
できる。
In addition, water-impermeable sheets can be obtained at a lower cost than continuous plates made of plastic materials, and can be easily processed by cutting them with scissors to match the frame surface. Water-impermeable sheets are flexible and bend easily, so they can accommodate this error.

本実施例では余長部と余長部の接合は溶着としたが、接
着剤による接合等、止水壁の全高さに渡って高さ方向に
連続的に接合しつればよい。
In this embodiment, the extra length portions are joined by welding, but they may be joined continuously in the height direction over the entire height of the water stop wall, such as by using an adhesive.

また、本実施例では安定液を自硬性安定液としたが、非
自硬性安定液を使用し、フレームを挿入した後に固化剤
を注入撹拌して安定液を固化してもよい。
Further, in this embodiment, a self-hardening stabilizer was used as the stabilizing liquid, but a non-self-hardening stabilizer may be used, and after inserting the frame, a solidifying agent may be injected and stirred to solidify the stable liquid.

なお、フレーム16の端部[1型鋼22のフランジ部2
3に位置する不透水性シート18の余長部20の上にカ
バーをかけておくことにより、この不透水性シート18
の余長部20を傷つけずに、地下構造物予定地側の止水
壁24の表面を削りフレーム16の而を露出することが
できる。
Note that the end of the frame 16 [the flange portion 2 of the type 1 steel 22]
By placing a cover over the extra length 20 of the water-impermeable sheet 18 located at 3, this water-impermeable sheet 18
The surface of the water-stop wall 24 on the side of the planned underground structure can be scraped to expose the frame 16 without damaging the extra length 20 of the frame 16.

(発明の効果) この発明は、不透水性シートをフレームの片面に張り何
け、不透水性シートに余長部を残しておき、地下構造物
予定地側の止水壁の表面を削り取った後、不透水性シー
トの余長部同士を溶着するものであるため、より安価な
費用でより簡単に止水壁の止水性の完全化が図られ、ま
た不透水性シート端部と隣接する不透水性シート端部と
の間の止水性も完全となる。
(Effects of the invention) In this invention, a water-impermeable sheet is stretched on one side of the frame, an extra length is left on the water-impermeable sheet, and the surface of the water-stop wall on the side where the underground structure is planned is scraped off. After that, the extra length of the water-impermeable sheet is welded to each other, so the water-stopping properties of the water-stopping wall can be more easily achieved at a lower cost. The watertightness between the ends of the water-impermeable sheet is also perfect.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本発明の一実施例における施工順序を示す平面
図であり、第2図は第1図に示す実施例においで隣り合
う不透水性シートの余長部を溶着した状態を示す斜視図
である。 12・・・・・・溝孔     14・・・・・・自硬
性安定液16・・・・・・フレーム   18・・・・
・・不透水性シー1〜20・・・・・・余長部    
24・・・・・・止水壁28・・・・・・溶着部
FIG. 1 is a plan view showing the construction order in one embodiment of the present invention, and FIG. 2 is a perspective view showing a state in which the extra lengths of adjacent water-impermeable sheets are welded together in the embodiment shown in FIG. It is a diagram. 12... Slot 14... Self-hardening stabilizer 16... Frame 18...
...Water-impermeable sea 1-20...excess length
24...Water stop wall 28...Welded part

Claims (1)

【特許請求の範囲】[Claims]  安定液を満たしながら掘削した一区画の溝孔内に予め
組立てたフレームを挿入し、該安定液を硬化させた後、
該区画に連続する区画に同様の施工を繰り返して止水壁
を形成し、地下構造物構築側の地面を掘削し該止水壁を
該フレームの該地下構造物構築側の面まで削る連続止水
壁構築工法において、該予め組立てるフレームの該地下
構造物構築側と反対の面に不透水性シートを張り付けて
かつ該不透水性シートの端部に余長部をとり該余長部を
フレーム端に沿って該地下構造物構築側の面に廻し該面
に係止させておき、該止水壁を該フレームの該地下構造
物構築側の面まで削つた後、該フレームの該地下構造物
構築側の面に係止されている該余長部を係止から解放し
、隣に位置する該余長部と接合してなることを特徴とす
る連続止水壁構築工法。
The pre-assembled frame is inserted into a section of trench that has been excavated while being filled with stabilizing liquid, and after the stabilizing liquid has hardened,
A continuous stop is formed by repeating similar construction in a section that is continuous with the section to form a water stop wall, excavating the ground on the underground structure construction side, and cutting the water cut wall down to the surface of the frame on the underground structure construction side. In the water wall construction method, a water-impermeable sheet is pasted on the opposite side of the underground structure construction side of the pre-assembled frame, and an extra length is taken at the end of the water-impermeable sheet, and the extra length is used as a frame. After turning the water stop wall along the edge to the surface on the underground structure construction side and locking it to the surface, and cutting the water stop wall to the surface on the underground structure construction side of the frame, A method for constructing a continuous water-stop wall, characterized in that the extra length that is locked to a surface on the building side is released from the lock and joined to the extra length that is located next to it.
JP62-156451A 1987-06-25 Continuous water-stop wall construction method Granted JPH011822A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP62-156451A JPH011822A (en) 1987-06-25 Continuous water-stop wall construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP62-156451A JPH011822A (en) 1987-06-25 Continuous water-stop wall construction method

Publications (3)

Publication Number Publication Date
JPS641822A JPS641822A (en) 1989-01-06
JPH011822A true JPH011822A (en) 1989-01-06
JPH0432167B2 JPH0432167B2 (en) 1992-05-28

Family

ID=

Similar Documents

Publication Publication Date Title
JP6869198B2 (en) Synthetic underground outer wall and its construction method
US4585678A (en) Steel sheet pile, sheet pile assembly thereof and the method of constructing the assembly
JP2005023570A (en) Pile for underpass side wall and water cut-off method of underpass side wall
JPH011822A (en) Continuous water-stop wall construction method
JP2003027462A (en) Construction method of underground continuous wall, and construction method of underground structure
JP3712602B2 (en) Joint pipe water blocking structure
JPH0432167B2 (en)
JPH07109096B2 (en) Impermeable method for underground wall
JPH11158865A (en) Underground structure having wall using steel sheet pile as core and method for constructing the same
JPS6011178B2 (en) How to install standard piles for continuous underground wall construction
JP2005256571A (en) Continuous wall body and its construction method
JPS6011179B2 (en) Construction method of underground wall
JPH041811B2 (en)
JP2565452B2 (en) Construction method of self-supporting retaining wall
JPH0433326B2 (en)
JPS6017898B2 (en) Construction method of pile foundation with underground wall
JP3586744B2 (en) Construction method of impermeable wall
JPH0211477Y2 (en)
JPH03295926A (en) Execution of underground continuous wall
JPS6019369B2 (en) How to build a diaphragm wall
JPH01235715A (en) Underground continuous impermeable wall method
JPS60250119A (en) Construction work of pipe-type underground concrete structure
JPH0786229B2 (en) Impermeable wall using impermeable sheet, construction method thereof, and impermeable sheet used for impermeable wall
JPS6225809B2 (en)
JPH03244711A (en) Preventing ground sinking due to extraction of earth holding member