JPH01146058A - Framework scaffold - Google Patents

Framework scaffold

Info

Publication number
JPH01146058A
JPH01146058A JP30476387A JP30476387A JPH01146058A JP H01146058 A JPH01146058 A JP H01146058A JP 30476387 A JP30476387 A JP 30476387A JP 30476387 A JP30476387 A JP 30476387A JP H01146058 A JPH01146058 A JP H01146058A
Authority
JP
Japan
Prior art keywords
side frame
scaffolding
building
frame
net
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP30476387A
Other languages
Japanese (ja)
Other versions
JPH055985B2 (en
Inventor
Shigeyuki Nakatani
中谷 重幸
Shoji Shibuya
渋谷 正二
Shinji Yoshida
信二 吉田
Akira Kenjo
見上 彰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sumikin Kozai Kogyo KK
Sumitomo Metal Steel Products Inc
Original Assignee
Sumikin Kozai Kogyo KK
Sumitomo Metal Steel Products Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sumikin Kozai Kogyo KK, Sumitomo Metal Steel Products Inc filed Critical Sumikin Kozai Kogyo KK
Priority to JP30476387A priority Critical patent/JPH01146058A/en
Publication of JPH01146058A publication Critical patent/JPH01146058A/en
Publication of JPH055985B2 publication Critical patent/JPH055985B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Movable Scaffolding (AREA)

Abstract

PURPOSE: To maintain the strength of a scaffolding while improving the safety and reducing labor and time by arranging H-type standards in parallel, building up the standards in a plurality of stages to lay scaffolding boards between horizontal posts, and fitting side frames to both side face sides of each stage. CONSTITUTION: H-type standards 1 with horizontal members 11 disposed between the nearly middle parts of each pair of upright-posts 10, 10, are arranged in parallel and built up in a plurality of stages, and a scaffolding board 2 is laid between the adjacent horizontal ports 11, 11 of each stage. A rectangular side frame body 30 with an outer width W2 almost coinciding with inside measurement W between the vertical posts 10, 10 is fitted with a rectangular net of almost the same size as the side frame body 30 to constitute a side frame 3 which is a reinforcing member serving also as a handrail. The side frame bodies 3 on the outer side face side of each stage are fitted between the vertical posts 10, 10 on the inner side face side so as to cover the whole scaffolding with the nets 31 to constitute a prefabricated scaffolding. The strength of the scaffolding is therefore maintained, and protection against fallen objects can be secured from the beginning of building up while heightening the safety of workers.

Description

【発明の詳細な説明】 〔産業上の利用分野〕 この発明は、建造物等の外壁面に沿って仮設される枠組
足場に係り、とくに紐払しが合理的かつ安全容易に行う
ことが出来る枠組足場に関する。
[Detailed Description of the Invention] [Industrial Application Field] The present invention relates to a framework scaffold that is temporarily installed along the outer wall surface of a building, etc., and in particular allows for the removal of strings in a rational, safe and easy manner. Regarding framework scaffolding.

〔従来の技術〕[Conventional technology]

この種の枠組足場としては、現在第7図のようなものが
汎用されている。すなわち、図のものは鳥居型の建枠9
0が所定の間隔で複数並置されるとともに、上下方向に
所要数が連結され、相隣れる建枠と建枠との間に交叉筋
違91が取付けられる。そしてその隣り合う建枠の横地
90a、90a間には足場板2がかけ渡され、作業床A
、、A8・・・が確保される。最上段の建枠90には支
柱92を立てて手摺93がセットされる。
As this type of framework scaffold, the one shown in Fig. 7 is currently in general use. In other words, the one in the picture is a torii-shaped building frame 9.
A plurality of 0's are arranged side by side at predetermined intervals, a required number are connected in the vertical direction, and cross braces 91 are installed between adjacent building frames. Scaffolding boards 2 are stretched between the horizontal areas 90a and 90a of the adjacent building frames, and the work floor A
, , A8... are secured. Supports 92 are erected on the uppermost building frame 90, and handrails 93 are set.

〔発明が解決しようとする問題点〕[Problem that the invention seeks to solve]

ところが、上記公知の枠組足場には次のような問題があ
る。
However, the above-mentioned known framework scaffolds have the following problems.

■ 組立或いは解体(組払し)作業途中において、各段
の足場板2の上に立つ作業者に対し安全確保のための手
摺がなく、甚だ危険な作業を余儀なくされる。
- During assembly or disassembly (reassembly), workers standing on the scaffolding boards 2 at each stage are not provided with handrails to ensure their safety, and are forced to perform extremely dangerous work.

■ 枠組足場は通常、落下物の養生を目的としてその外
側面に養生枠(枠付金属網)または養生ネット(メツシ
ュシート)が張られる。
■ Framed scaffolding usually has a curing frame (metal mesh with frame) or curing net (mesh sheet) placed on its outer surface for the purpose of curing fallen objects.

かかる養生は、足場全段を組上げた後に実施されるが、
実際には組上げ時においても落下物の事故がおこる危険
があり、十分な対策とは言い難い。
Such curing is carried out after all stages of scaffolding have been erected, but
In reality, there is a risk of falling object accidents occurring even during assembly, and this cannot be said to be a sufficient countermeasure.

また、養生枠、′ネットとも取付けが面倒で、相当の手
間を必要とする。ネットの方は、一般に長さ5100n
のものが使用され、建枠3段分を1枚で覆うようになっ
ているが、建枠への取付けはその建地にひもでくくりつ
けるという面倒なものである。養生枠については、建枠
、建地の2ケ所に養生クランプを取付け、これに備わる
ジヨイント部に養生枠の孔部を嵌込む構造になっており
、やはりその取付けには手間のかかる作業が必要となる
Furthermore, both the curing frame and the net are troublesome to install and require considerable effort. The length of the net is generally 5100n.
A single sheet of paper is used to cover three levels of the building frame, but attaching it to the building frame is a cumbersome process that involves tying it to the building site with a string. The curing frame has a structure in which curing clamps are attached to two places, the building frame and the building site, and the holes in the curing frame are fitted into the joints provided on these clamps, which requires time-consuming work to install. becomes.

その上ネットについては、建地への固定を確実にしてお
かないと、風に煽られてバタつき、また騒音の発生源と
もなる。また−個所破損しただけでも大きな一枚全体を
取替える必要があり、コスト的にも不利であるばかりか
、1枚のサイズが大きいことは、取付け、取外し、保管
や清掃等に際しての取扱いをも困難にしている。
Furthermore, if the net is not securely fixed to the building site, it will flap in the wind and become a source of noise. In addition, even if only one part is damaged, the whole large piece needs to be replaced, which is not only disadvantageous in terms of cost, but the large size of each piece also makes it difficult to handle when installing, removing, storing, cleaning, etc. I have to.

本発明は、上記従来の足場の問題点を解決した枠組足場
の提供を目的とする。
The present invention aims to provide a framework scaffold that solves the problems of the conventional scaffolds described above.

〔問題点を解決するための手段〕[Means for solving problems]

本発明の枠組足場は、第1図に示す如く、一対の建地1
0,10の略中位部位間に横地11を配したH型建枠l
が並列状に配置されかつ複数段に組上げられ、その各段
の隣接横地11.11間に足場板2が架け渡される一方
、各段の外側面側および内側面側の隣接建地10,10
間に側枠が取付けられる。
As shown in FIG. 1, the framework scaffolding of the present invention has a pair of
H-shaped building frame l with horizontal land 11 arranged between the approximately middle parts of 0 and 10
are arranged in parallel and assembled into multiple tiers, and the scaffolding boards 2 are spanned between the adjacent horizontal lots 11 and 11 of each tier, while the adjacent building lots 10, 10 on the outer side and inner side of each tier
A side frame is installed in between.

そして、足場板2レベルの上方側および下方側に取付け
られる外側面側の側枠3は、第3図および第4図に詳示
されるように、方形状で剛性を有する側枠本体30と、
同じく方形状で側枠本体30とほぼ同じ大きさのネット
31との組合せからなり、側枠本体30は前記隣接建地
10.10間の内のりW5寸法に略一致する外巾Wt寸
法を有し、側枠本体30の四隅付近に付設された取合片
302・・・によって前記隣接建地10.10間に隙間
なく納まる状態で支持され、ネット31は側枠本体30
に付設されたネン)31との係合手段32によって側枠
本体30に脱着可能に装着されている。
The outer side frame 3 attached to the upper and lower sides of the scaffold board 2 level has a rectangular and rigid side frame main body 30, as shown in detail in FIGS. 3 and 4.
The side frame body 30 is also rectangular in shape and consists of a combination of a side frame body 30 and a net 31 of approximately the same size, and the side frame body 30 has an outer width Wt dimension that approximately matches the inner width W5 dimension between the adjacent building lots 10 and 10. , the net 31 is supported by the connecting pieces 302 attached near the four corners of the side frame body 30 so that it fits between the adjacent buildings 10 and 10 without any gaps, and the net 31 is attached to the side frame body 30.
It is removably attached to the side frame main body 30 by means of engagement means 32 with a frame 31 attached to the side frame body 30.

〔作  用〕[For production]

本発明の枠組足場では、ネット31を備えた側枠3が足
場の外側面全体に建込まれた形になっている。
In the framework scaffold of the present invention, the side frame 3 provided with the net 31 is built over the entire outer surface of the scaffold.

この側枠3は、自身の枠間性により水平力に対する強度
を足場に与える、つまり筋違に代わる機能を担う、そし
てこの場合ネット31は、足場の外側面側の開口の全面
を塞ぎ、落下物に対する養生の機能を果たすことになる
This side frame 3 provides the scaffold with strength against horizontal forces due to its interframe nature, that is, it has the function of replacing braces, and in this case, the net 31 closes the entire opening on the outer side of the scaffold and It will fulfill the function of curing things.

側枠3は、隣接建地10.10間に完全に嵌り込む状態
に取付けられ、側枠本体30は隣接建地間の内のりW、
に略一致する外巾Wtを有するために、各建地との間に
隙間ができずネッ)31を備えることとあいまって確実
な養生を達成するのである。
The side frame 3 is installed so that it completely fits between the adjacent buildings 10 and 10, and the side frame main body 30 is attached to the inner wall W between the adjacent buildings.
Since it has an outer width Wt that substantially matches the width Wt, there is no gap between the building site and the building site, and together with the provision of the net 31, reliable curing is achieved.

また側枠3は、枠組足場組上げ時、建枠lの組み上げと
並行して各段積み上げ毎にセントしてゆくもので、これ
により足場組上時においても落下物の養生が可能となる
。しかも、足場が組上ると同時に落下物養生対策の実施
が完了することになり、従来の養生ネット等のように足
場を組上げてから養生対策を別の作業として実施する必
要がなく、足場仮設に要する手間、時間が節減できる。
In addition, the side frames 3 are stacked at each level in parallel with the assembling of the building frame 1 when the scaffolding is assembled, and this makes it possible to protect fallen objects even when the scaffolding is being erected. Moreover, the implementation of falling object protection measures is completed at the same time the scaffolding is erected, so there is no need to carry out protection measures as a separate task after the scaffolding is erected, unlike with conventional protection nets. The required effort and time can be saved.

のみならず、枠体3そのものが手摺になり、H型建枠l
の使用と関連して足場組払しの過程においても作業者の
安全が確保されることになる。
Not only that, the frame body 3 itself becomes a handrail, and the H-shaped building frame l
The safety of workers will also be ensured during the scaffolding process.

更にまた、ネット31は1枚当りのサイズが小さいので
、養生ネットのようにバタついたり騒音を発するような
ことがない上、側枠本体30に着脱可能に構成され、清
掃に当たっては本体30から取外し作業すればよい。ま
た運搬、保管時等には、側枠本体に取付けたまま扱うこ
とができ、嵩ぼらず扱い易いものである。
Furthermore, since each net 31 is small in size, it does not flap or make noise unlike a curing net, and is configured to be removable from the side frame body 30, so that it can be removed from the main body 30 during cleaning. All you have to do is remove it. Furthermore, during transportation, storage, etc., it can be handled while attached to the side frame body, and is not bulky and easy to handle.

(実施例〕 前出第1図は本発明の一実施例を示している。(Example〕 FIG. 1 above shows an embodiment of the present invention.

本足場は、全体としては複数段の作業床A1゜A2・・
・を形成する作業床ユニットυ1からなっている0作業
床ユニットυ、の基本構成要素は、建枠1と足場板2と
外側面側の側枠3と内側面側(躯体側)の側枠とである
。まず各々の構成を要素毎に説明する。
This scaffolding has multiple tiers of work floors A1゜A2...
The basic components of the 0 work floor unit υ, which is composed of the work floor unit υ1 that forms That is. First, each configuration will be explained element by element.

O建枠l 第2図に正面図を示す。O building frame l Figure 2 shows a front view.

同図によると、建枠lはH型の枠であり、一対の建地i
o、ioと、その上下2分割点で再建地間をつなぐ横地
11と、該横地11の下側、両建地10.10間に配さ
れた逆U字形の補強材12とで基本の部分が構成されて
いる。構成部材はすべて丸鋼管である。
According to the figure, building frame l is an H-shaped frame, and a pair of building sites i
o, io, a horizontal lot 11 that connects the reconstruction site at the upper and lower division points, and an inverted U-shaped reinforcing material 12 placed below the horizontal lot 11 between both building lots 10 and 10. is configured. All structural members are round steel tubes.

両建地io、toの上端には、建枠どうしを連結するた
めの連結ピン13が付設されている。また、建地10.
10のそれぞれには、バ享式抜止片150付の係合ピン
15、上端および下端付近、横地11取付位置を挟んで
その直上、直下の計4個所に設けられている。アームロ
ツタ、側枠を係止するための係合ピン15はすべて枠自
身の内部側に突き出ず形になっている。各建地lOの横
地11取付位置直下の部位には、横地長手方向の貫通孔
100が設けられている。この貫通孔100はアサガオ
等の足場付帯設備を設けるときなどに利用される。
Connecting pins 13 for connecting the building frames to each other are attached to the upper ends of both building sites io and to. Also, construction site 10.
10, engagement pins 15 with bar-type retaining pieces 150 are provided at a total of four locations near the upper and lower ends, directly above and directly below the mounting position of the horizontal strip 11. The arm rotor and the engaging pins 15 for locking the side frame are all shaped so that they do not protrude inside the frame itself. A through hole 100 extending in the longitudinal direction of the horizontal lot is provided in a portion directly below the attachment position of the horizontal lot 11 on each building lot IO. This through hole 100 is used when installing scaffolding equipment such as morning glory.

両建地10.10間にまたがる補強材12は、その中央
部において連結プレー)120により横地11につなぎ
止められている。連結プレート120には透孔120a
があけられているが、これは上記貫通孔100を使って
アサガオ等を取付けるときに、支持補強のためのタイロ
ッドをとる場合などに利用できる。
The reinforcing material 12 extending between the two building lots 10 and 10 is connected to the horizontal lot 11 by a connecting play 120 at its center. The connection plate 120 has a through hole 120a.
This can be used to attach tie rods for support and reinforcement when attaching morning glories or the like using the through hole 100.

なお、建枠中としては、仮設対象i′i築物一般とする
なら、「簡易わく」である900f1未満で十分である
。高さHlについては、人の背丈を基準に作業上必要な
スペースを確保する立場から、1700〜2000ms
程度が適当である。
In addition, as for the building frame, less than 900 f1, which is a "simple frame", is sufficient for temporary construction i'i buildings in general. The height Hl is set at 1,700 to 2,000 ms based on the height of the person and from the standpoint of securing the necessary space for work.
The degree is appropriate.

○ 足場板2 足場板2は、通常使用されるもので、両端に建枠横地1
1に対する係合爪20.20を具備する。
○ Scaffolding board 2 Scaffolding board 2 is the one that is normally used.
1 is provided with an engaging claw 20.20.

○側枠3 第3図および第4図にその構造を示す。○Side frame 3 Its structure is shown in FIGS. 3 and 4.

第3図の側枠3は、(イ)図図示の如く全体が方形で、
側枠本体30とネット31との組合せからなる。側枠本
体30は周囲を巡る丸パイプからなり、その内部に配さ
れた補強材301と、側枠本体30の四隅付近に設けら
れた取合片302・・・とを備える。
The side frame 3 in Fig. 3 is (a) entirely rectangular as shown in the figure;
It consists of a combination of a side frame body 30 and a net 31. The side frame main body 30 is made of a round pipe that goes around the circumference, and includes a reinforcing member 301 disposed inside the side frame main body 30, and connecting pieces 302 provided near the four corners of the side frame main body 30.

側枠本体30は上述したように丸パイプで構成され、そ
の内面側には、ネット31を取付けるための係合手段3
2・・・が設けられている。(ロ)図に拡大して示され
る係合手段32は、側枠本体30にフックを別途取り付
けたものであり、(ハ)図に拡大して示される係合手段
32は、側枠本体30にスリットを入れ、その周囲を嵌
没させてフック部が側枠本体30の外周面より外側に突
出しないように構成したものである。係合手段32はい
ずれも枠自身の内部側に外周側へ向けて屈曲するよう形
成されている。
The side frame main body 30 is composed of a round pipe as described above, and the engagement means 3 for attaching the net 31 is provided on the inner side of the side frame main body 30.
2... is provided. (b) The engaging means 32 shown enlarged in the figure is a hook attached separately to the side frame main body 30, and (c) The engaging means 32 shown enlarged in the figure is attached to the side frame main body 30. A slit is formed in the side frame body 30, and the periphery thereof is fitted so that the hook portion does not protrude outside the outer circumferential surface of the side frame main body 30. Each of the engaging means 32 is formed inside the frame itself so as to be bent toward the outer periphery.

側枠本体30の寸法は、外巾W2が、後述のように並列
する建枠l・・・の隣接建地(以下、単に隣接建地とい
う)10.10間の内のり寸法W、に略々一致している
。高さH2は建地lOの高さHlのT度半分のサイズと
なっている。
The dimensions of the side frame body 30 are such that the outer width W2 is approximately equal to the inner dimension W between adjacent building lots (hereinafter simply referred to as adjacent building lots) 10. Match. The height H2 is half the height Hl of the building site IO by T degrees.

補強材301は、この側枠本体30内で丁度「水」の字
のような形を形成し、側枠本体30に高い剛性を与えて
いる。いうまでもないが、補強材301の取り方はこれ
に限定されるものではなく、種々の変形が可能である。
The reinforcing material 301 forms a water-like shape within the side frame body 30 and provides high rigidity to the side frame body 30. Needless to say, the method of taking the reinforcing material 301 is not limited to this, and various modifications are possible.

バリエーションのいくつかを第5図に示しておく。Some of the variations are shown in Figure 5.

取合片302は、側枠本体30の両紙部材の上下端部近
くに設けられている。この取合片302により徊°捧本
体30は、隣接建地10.10間に嵌り込む状態に取付
けられる。
The joining pieces 302 are provided near the upper and lower ends of both paper members of the side frame main body 30. With this connecting piece 302, the swinging body 30 is attached so as to fit between the adjacent buildings 10 and 10.

ネット31は、クロスで始末した周縁部311aにあけ
た孔311bにひもを通し枠310にくくりつけて固定
しである。ネソl−311の取付は方としてはこの他、
孔3iibにひもを通し、側枠本体30にくくりつける
方法、ネット31を一旦方形状の枠に固定し、この枠を
側枠本体3oに取付ける方法等が可能である。
The net 31 is fixed by passing a string through a hole 311b made in a peripheral edge 311a made of cloth and attaching it to the frame 310. In addition to this, there are other ways to install Neso l-311.
Possible methods include passing a string through the hole 3iib and attaching it to the side frame body 30, or fixing the net 31 to a rectangular frame and attaching this frame to the side frame body 3o.

第4図の側枠3は、側枠本体30をアングル材で構成し
、アングル材の立フランジ部内面側に、ネット31を取
付けるための係合手段32・・・を設けたものである。
In the side frame 3 shown in FIG. 4, the side frame main body 30 is made of an angle material, and engagement means 32 for attaching a net 31 are provided on the inner surface of the vertical flange portion of the angle material.

係合手段32・・・としては、第3図の側枠3と同様、
側枠本体30にフックを別途取付けたもの(同図(ロ)
)、側枠本体30の一部を内側に突出させたもの(同図
(ハ))などが可能である。
As the engaging means 32..., similar to the side frame 3 in FIG.
A hook is attached separately to the side frame main body 30 (same figure (b))
), or one in which a part of the side frame main body 30 protrudes inward (see (c) in the same figure).

この側枠3によると、ネット31が、側枠本体30を構
成するアングル材の立フランジ部と、立フランジ部から
枠内側に折れる平フランジ部とが囲む空間内に収容され
る。
According to this side frame 3, the net 31 is housed in a space surrounded by the vertical flange portion of the angle member constituting the side frame main body 30 and the flat flange portion bent from the vertical flange portion toward the inside of the frame.

ネッ)31は、上記係合手段32に直接取付ける他、ネ
ット31を一旦方形状の枠に固定し、この枠を側枠本体
30に取付けるものであってもよい。
In addition to attaching the net 31 directly to the engaging means 32, the net 31 may be temporarily fixed to a rectangular frame, and this frame may be attached to the side frame body 30.

他の構成は、第3図の側枠3と同じであるので、詳しい
説明を省略する。
The other configurations are the same as the side frame 3 in FIG. 3, so detailed explanation will be omitted.

○ 内側面側(Ili1体側)の側枠 手摺兼強度部材として、一般に使用されるもので、第6
図(イ)に示されるような手摺用枠35、あるいは同図
(ロ)に示されるような手摺材36と斜材37との組合
せ等が用いられる。
○ It is generally used as a side frame handrail and strength member on the inner side (Ili 1 side), and is
A handrail frame 35 as shown in Figure (A) or a combination of a handrail member 36 and diagonal member 37 as shown in Figure (B) is used.

各要素の構成は以上のとおりであるが、次にこれらの配
置組合せ状態を説明する。
The configuration of each element is as described above, and next, the arrangement and combination state of these elements will be explained.

まず建枠lは、その所要数が所定間隔lをおいて並列状
に配置され、かつ上下方向にも所要段数継ぎ足し設置さ
れている。最下段の建枠の建地下端には、ジヤツキベー
ス8が装着されている。配置間隔lはインチサイズの場
合182Ln、1524mm、1219m、914fi
程度に設定される。
First, the required number of building frames 1 are arranged in parallel at a predetermined interval 1, and the required number of stages are also added in the vertical direction. A jack base 8 is attached to the bottom end of the lowest building frame. The arrangement spacing l is 182Ln, 1524mm, 1219m, 914fi for inch size.
It is set to a certain degree.

上下方向の連結は、前記した建地lO上端の連結ピン1
3により、ロックはアームロック等で行われる。
The connection in the vertical direction is made using the connection pin 1 at the upper end of the building site lO.
3, locking is performed by arm lock or the like.

足場板2は、このような建枠l・・・各段の、互いに隣
り合う横地11.11間に接続してかけ渡され、建枠の
組上げ段数分の作業床A+ = At・・・を形成して
いる。
The scaffolding board 2 is connected and spanned between the adjacent horizontal areas 11 and 11 of each tier of the building frame l, and provides working floors A+ = At for the number of assembled tiers of the building frame. is forming.

横地11との取合は、足場板2両端の係合片20.20
による。
The engagement with the horizontal ground 11 is done using the engagement pieces 20.20 at both ends of the scaffolding board 2.
by.

側枠3は、上記建枠1・・・の各段において、外側面側
の各隣接建地10.10間に設けられている。
The side frame 3 is provided between each adjacent building site 10 and 10 on the outer surface side in each stage of the building frame 1 .

側枠3の高さH2は建枠−つの高さHlの略々半分であ
り、側枠3は各段において、作業床Aレベルを境にその
上方側と下方側に一枚ずつ建込まれている。第1図では
表示の都合上一部省略されているが、側枠3は外側面全
体を覆うように設けられるものである。
The height H2 of the side frame 3 is approximately half the height Hl of the building frame, and one side frame 3 is erected on each level above and below the work floor A level as a boundary. ing. Although a portion is omitted in FIG. 1 for convenience of illustration, the side frame 3 is provided so as to cover the entire outer surface.

側枠3の固定は、側枠の4つの取合片302・・・を建
地10、10の抜止片付係合ピン15・・・に嵌着させ
ることによる。
The side frame 3 is fixed by fitting the four connecting pieces 302 of the side frame into the engagement pins 15 with retaining pieces of the building lots 10, 10.

各側枠3は、上記取付状態において、両側の建地10.
10の間に嵌め込んで建込まれた形となり、かつその各
建地との間にほとんど隙間を生じない。
In the above-mentioned installed state, each side frame 3 is attached to the building area 10 on both sides.
It is built by being fitted in between 10 buildings, and there is almost no gap between it and each building site.

内側面側(l1体側)の側枠は第1図には図示されてい
ないが、その高さは建枠−つの高さHlの略々半分で、
建枠l・・・の各段に対しlユニットが作業床Aレベル
の上方側に建込まれる。
Although the side frame on the inner side (L1 body side) is not shown in Fig. 1, its height is approximately half of the height Hl of the building frame.
For each stage of the building frame l..., l units are built above the work floor A level.

なお、図の例では最下段の作業床A1の下側については
、斜材5が側枠に代えて取付けられている。
In the illustrated example, diagonal members 5 are attached to the lower side of the lowermost work floor A1 instead of the side frames.

以上のような構成になる足場は、作業床ユニットυ1の
各段に配された側枠3・・・が自身の段を水平方向に固
める機能を果たし、結果として全体を堅牢にする。
In the scaffold configured as described above, the side frames 3 arranged at each stage of the work floor unit υ1 serve to strengthen the own stage in the horizontal direction, and as a result, the whole becomes solid.

また、各側枠3は隣接建地10.10間に嵌り込み、各
建地10.60との間に実質的に隙間を生じない。この
ため側枠に備わるネット31により落下物の養生が確実
に行われることになる。
Moreover, each side frame 3 fits between adjacent building lots 10.10, and substantially does not create a gap between each side frame 3 and each building lot 10.60. Therefore, the net 31 provided on the side frame will surely protect the fallen objects.

次に、上記足場の組払しは以下のように行われまず、作
業床ユニットU1の最下段の建枠l・・・を設置し、そ
の各建枠間の下方側に斜材5をセットするとともに、隣
接横地ii、tt間に足場板2をかけ渡す、このように
したのち、ユニットυ1の足場板2上にあがって最下段
上側の外側面側側枠3および内側面側側枠を取付ける。
Next, the above-mentioned scaffolding is assembled as follows. First, the lowest building frame l of the work floor unit U1 is installed, and the diagonal members 5 are set on the lower side between each of the building frames. At the same time, cross the scaffolding board 2 between the adjacent horizontal lots ii and tt. After doing this, go up on the scaffolding board 2 of the unit υ1 and install the outer side frame 3 and the inner side side frame on the upper side of the bottom row. Install.

こうして最下段ができれば、この上に第2段目の建枠1
・・・を継ぎ足し、2段目の下側側枠3を取付けて、足
場板2をかける。このような要領で作業ユニットυ1を
並行して下方から一段ずつ順に組上げてゆく。解体する
ときは、これと全く逆の手順を踏んで最上段から順次下
方へ作業を進める。
Once the bottom tier is completed in this way, the second tier building frame 1 is placed on top of this.
..., attach the lower side frame 3 of the second stage, and hang the scaffold board 2. In this manner, the work units υ1 are assembled step by step in parallel from the bottom. When dismantling, follow the exact opposite procedure and work your way down from the top.

このような組立て、解体の作業は、作業者が各段毎に足
場板2の上に立って、■当該段建枠lへの上側外側面側
側枠3および内側面側側枠の取付は−■直上段の建枠l
の継ぎ足し→■建建枠への下側外側面側側枠3および足
場板2の設置を順に行うことにより進められるが、この
場合、■以降の作業は、つねにその作業中の段に外側面
側、内側面側とも側枠がある状態で行われるこ匪になり
、安全に作業ができる。
During such assembly and disassembly work, the worker stands on the scaffolding board 2 for each tier and attaches the upper outer side frame 3 and inner side frame to the tiered frame l. -■ Building frame directly above
The process proceeds by adding the lower outer side frame 3 and the scaffolding board 2 to the construction frame in order, but in this case, the work after ■ always attaches the outer side to the step being worked on. The work is done safely with side frames on both the side and inner sides.

〔発明の効果〕〔Effect of the invention〕

以上に説明した本発明の枠組足場は、次のような特徴・
利点を存している。
The framework scaffold of the present invention explained above has the following characteristics.
It has advantages.

○ 足場に組込まれた外側面側の側枠3は、その枠間性
により水平力に対し抵抗し、足場全体に高い強度を保有
させることになる。
○ The side frame 3 on the outer surface side incorporated into the scaffold resists horizontal force due to its interframe nature, and the entire scaffold has high strength.

○ 側枠3はまた、隣接建地10,10間に隙間なく嵌
り込む状態で建て込まれ、それに備わるネット31が全
体として足場外側面全体を隙間なく覆い、落下物の養生
を確実に達成することになる。
○ The side frame 3 is also built so that it fits between the adjacent buildings 10, 10 without any gaps, and the net 31 provided thereon covers the entire outer surface of the scaffold without any gaps, thereby ensuring the protection of fallen objects. It turns out.

○ そして側枠3は、足場組上げ時、建枠の組上げと並
行して各段毎にセットしてゆくから、足場組上の過程に
おいても落下物養生対策として有効に機能する。のみな
らず、足場組上ると同時に全体に対する落下物養生対策
が完了するという合理性があり、足場仮設に要する手間
、時間が大巾に節減できる。
○ And since the side frames 3 are set for each tier in parallel with the erection of the building frame when the scaffolding is being erected, it functions effectively as a countermeasure against falling objects during the scaffolding process as well. In addition, it is reasonable to complete measures to protect the entire structure from falling objects at the same time as the scaffolding is erected, and the effort and time required for temporary scaffolding can be greatly reduced.

O更にまたH型建枠lの採用と関連して側枠3は、足場
組法し時に作業者の安全を守る有効な手交てとなる。
Furthermore, in conjunction with the adoption of the H-shaped building frame 1, the side frames 3 serve as an effective means of protecting the safety of workers during scaffolding.

Oかつまた、ネット31は1枚当りのサイズが小さいこ
とから、従来の養生ネットのように大きくバタついたり
、騒音を発したりするようなことがない、その上、側枠
本体30に着脱可能に構成され、清掃に当たっては本体
30から取外して作業すれば楽であり、運搬、保管に際
しては、本体30に取付けたまま扱うようにすれば嵩ぼ
らず取扱い易いものとなる。
Additionally, since each net 31 is small in size, it does not flap around or make noise unlike conventional curing nets, and is also removable from the side frame body 30. When cleaning, it is easy to remove it from the main body 30, and when carrying and storing it, it can be handled while attached to the main body 30, making it less bulky and easier to handle.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明の一実施例に係る枠組足場を示す斜視図
、第2図は同上枠組足場に使用する建枠を示す正面図、
第3図(イ)および第4図(イ)は同じく外側面側の側
枠を示す分解斜視図、両図(ロ)(ハ)はその側枠の部
分詳細図、第5図は同側枠について補強材の取り方のバ
リエーションを示す模式図、第6図(イ)(ロ)は内側
面側の側枠を示す正面図、第7図は従来の枠組足場を示
す模式説明図である。 回申、l:建枠、2:足場板、3:側枠。 第  2  図 第  6  図 (イ) 第  5  図 第  7121
FIG. 1 is a perspective view showing a framework scaffolding according to an embodiment of the present invention, FIG. 2 is a front view showing a building frame used for the same framework scaffolding,
Figures 3 (A) and 4 (A) are exploded perspective views showing the side frame on the outer side, both figures (B) and (C) are partial detailed views of the side frame, and Figure 5 is the same side. A schematic diagram showing variations in how to take reinforcing materials for the frame, Figures 6 (a) and (b) are front views showing the side frames on the inner side, and Figure 7 is a schematic explanatory diagram showing a conventional frame scaffold. . Circular, l: building frame, 2: scaffolding board, 3: side frame. Figure 2 Figure 6 (A) Figure 5 Figure 7121

Claims (1)

【特許請求の範囲】[Claims] (1)一対の建地(10)、(10)の略中位部位間に
横地(11)を配したH型建枠(1)が並列状に配置さ
れかつ複数段に組上げられ、その各段の隣接横地(11
)、(11)間に足場板(2)が架け渡される一方、各
段の外側面側および内側面側の隣接建地(10)、(1
0)間に側枠が取付けられ、足場板(2)レベルの上方
側および下方側に取付けられる外側面側の側枠(3)は
方形状で剛性を有する側枠本体(30)と、同じく方形
状で側枠本体(30)とほぼ同じ大きさのネット(31
)との組合せからなり、側枠本体(30)は前記隣接建
地(10)、(10)間の内のり(W_1)寸法に略一
致する外巾(W_2)寸法を有し、側枠本体(30)の
四隅付近に付設された取合片(302)・・・によって
前記隣接建地(10)、(10)間に隙間なく納まる状
態で支持され、ネット(31)は側枠本体(30)に付
設されたネット(31)との係合手段(32)によって
側枠本体(30)に脱着可能に装着されていることを特
徴とする枠組足場。
(1) H-shaped building frames (1) with a horizontal lot (11) arranged between a pair of building sites (10) and (10) are arranged in parallel and assembled in multiple stages, each of which Land adjacent to the step (11
), (11), while the scaffolding board (2) is installed between the adjacent buildings (10), (1) on the outside and inside sides of each step.
0) A side frame is attached between them, and the side frame (3) on the outer surface side attached to the upper and lower sides of the scaffold board (2) level is the same as the side frame main body (30) which has a rectangular shape and has rigidity. A square net (31) that is approximately the same size as the side frame body (30).
), the side frame main body (30) has an outer width (W_2) dimension that substantially matches the inner width (W_1) dimension between the adjacent building lots (10), (10), and the side frame main body ( The net (31) is supported by the connecting pieces (302) attached near the four corners of the side frame body (30) so that it fits between the adjacent building lots (10), (10) without any gaps. ) A frame scaffolding characterized in that it is removably attached to a side frame body (30) by means of engagement (32) with a net (31) attached to the frame.
JP30476387A 1987-12-02 1987-12-02 Framework scaffold Granted JPH01146058A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP30476387A JPH01146058A (en) 1987-12-02 1987-12-02 Framework scaffold

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP30476387A JPH01146058A (en) 1987-12-02 1987-12-02 Framework scaffold

Publications (2)

Publication Number Publication Date
JPH01146058A true JPH01146058A (en) 1989-06-08
JPH055985B2 JPH055985B2 (en) 1993-01-25

Family

ID=17936935

Family Applications (1)

Application Number Title Priority Date Filing Date
JP30476387A Granted JPH01146058A (en) 1987-12-02 1987-12-02 Framework scaffold

Country Status (1)

Country Link
JP (1) JPH01146058A (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS443471Y1 (en) * 1965-07-01 1969-02-07
JPS60115331U (en) * 1984-01-10 1985-08-05 住金鋼材工業株式会社 Side frames for temporary scaffolding

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS443471Y1 (en) * 1965-07-01 1969-02-07
JPS60115331U (en) * 1984-01-10 1985-08-05 住金鋼材工業株式会社 Side frames for temporary scaffolding

Also Published As

Publication number Publication date
JPH055985B2 (en) 1993-01-25

Similar Documents

Publication Publication Date Title
JPH01146058A (en) Framework scaffold
JPH055984B2 (en)
JPH0458866B2 (en)
JPH01146059A (en) Side frame for framework scaffold
JP3854123B2 (en) Frame scaffolding
JPH047317Y2 (en)
JP2575796Y2 (en) External curing frame
JP2996385B2 (en) Assembling scaffold
JPH0118753Y2 (en)
JP2000179187A (en) Tent for storing building materials
JP3177905B2 (en) Installation structure and installation method of external curing coating
JPH0321568Y2 (en)
JPH0323943Y2 (en)
JPH0718841A (en) Method for assembling scaffold and assembling stand used therein
JPH0472023B2 (en)
JP3078389B2 (en) Temporary scaffolding method
JP2841239B2 (en) External framework scaffolding for curved exterior walls
JPH047318Y2 (en)
JP3084321B2 (en) Railing frame for scaffolding
JPH0694722B2 (en) Side frame for frame scaffolding
JP2998583B2 (en) Curing method of atrium in building site
GB1565498A (en) Portable buildings
JP2002227404A (en) Scaffolding device for shape steel material
JP2595922Y2 (en) Curing sheet for scaffold
JPH071464Y2 (en) Temporary enclosure