JP7537330B2 - Process control system and process control method - Google Patents

Process control system and process control method Download PDF

Info

Publication number
JP7537330B2
JP7537330B2 JP2021046757A JP2021046757A JP7537330B2 JP 7537330 B2 JP7537330 B2 JP 7537330B2 JP 2021046757 A JP2021046757 A JP 2021046757A JP 2021046757 A JP2021046757 A JP 2021046757A JP 7537330 B2 JP7537330 B2 JP 7537330B2
Authority
JP
Japan
Prior art keywords
work
time
processes
additional
work time
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2021046757A
Other languages
Japanese (ja)
Other versions
JP2022145993A (en
Inventor
洋平 佐野
暁 大野
大耀 齋藤
大樹 西吉
駿 佐藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toyota Motor Corp
Original Assignee
Toyota Motor Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toyota Motor Corp filed Critical Toyota Motor Corp
Priority to JP2021046757A priority Critical patent/JP7537330B2/en
Priority to CN202210267794.2A priority patent/CN115113589A/en
Publication of JP2022145993A publication Critical patent/JP2022145993A/en
Application granted granted Critical
Publication of JP7537330B2 publication Critical patent/JP7537330B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B19/00Programme-control systems
    • G05B19/02Programme-control systems electric
    • G05B19/418Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS] or computer integrated manufacturing [CIM]
    • G05B19/41865Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS] or computer integrated manufacturing [CIM] characterised by job scheduling, process planning, material flow
    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B2219/00Program-control systems
    • G05B2219/30Nc systems
    • G05B2219/32Operator till task planning
    • G05B2219/32252Scheduling production, machining, job shop

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Manufacturing & Machinery (AREA)
  • Quality & Reliability (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Automation & Control Theory (AREA)
  • General Factory Administration (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Description

本発明は、工程管理システム及び工程管理方法に関し、特に、複数の工程を含む生産ラインを管理する工程管理システム及び工程管理方法に関する。 The present invention relates to a process management system and a process management method, and in particular to a process management system and a process management method for managing a production line that includes multiple processes.

生産ラインにおいて、不具合処置などの追加作業が発生した場合、生産性を高く保つためには、その追加作業をインラインで実施することが好ましい。このような技術に関連し、特許文献1は、複数の人的作業エリアと、複数の機械作業エリアと、ワークの外観画像を取得する画像取得エリアとを具備し、作業内容の正誤をワークの外観画像に基づいて判定する検査を実施可能とする製造ラインを開示する。特許文献1にかかる製造ラインは、画像取得エリアに搬入されたワークを撮像する撮像手段と、撮像手段で撮像して得た画像を表示する表示手段とをさらに具備する。そして、表示手段が、複数の人的作業エリアのうち、タクトタイムから人的作業に必要な時間を差し引いた際に、検査に必要な時間が余るタクト余剰エリアに配設される。 When additional work such as defect repair occurs on a production line, it is preferable to perform the additional work in-line in order to maintain high productivity. In relation to such technology, Patent Document 1 discloses a production line that includes multiple manual work areas, multiple machine work areas, and an image acquisition area that acquires an external image of the work, and that is capable of performing an inspection that determines whether the work content is correct based on the external image of the work. The production line according to Patent Document 1 further includes an imaging means that images the work brought into the image acquisition area, and a display means that displays the image captured by the imaging means. The display means is disposed in a takt surplus area, among the multiple manual work areas, that is the time required for inspection remaining when the time required for manual work is subtracted from the takt time.

特開2013-210822号公報JP 2013-210822 A

特許文献1にかかる技術では、生産ラインにおいてタクトタイムからの余剰がある工程に、検査工程を設けている。しかしながら、特許文献1にかかる技術では、タクトタイムからの余剰がある程度大きくないと、検査工程を設けることができないおそれがある。言い換えると、検査工程に要する時間よりも余剰が大きな工程がないと、検査工程を適切に設けることができないおそれがある。したがって、特許文献1にかかる技術では、追加作業が発生した場合に生産ラインの生産性が適正化されないおそれがある。 In the technology disclosed in Patent Document 1, an inspection process is provided for a process in a production line that has a surplus from the takt time. However, with the technology disclosed in Patent Document 1, there is a risk that an inspection process cannot be provided unless there is a certain amount of surplus from the takt time. In other words, if there is no process that has a larger surplus than the time required for the inspection process, there is a risk that the inspection process cannot be provided appropriately. Therefore, with the technology disclosed in Patent Document 1, there is a risk that the productivity of the production line will not be optimized when additional work occurs.

本発明は、追加作業が発生した場合であっても生産ラインの生産性を適正化することが可能な工程管理システム及び工程管理方法を提供するものである。 The present invention provides a process management system and a process management method that can optimize the productivity of a production line even when additional work occurs.

本発明にかかる工程管理システムは、所定の作業が行われる既存の複数の工程を含む生産ラインを管理する工程管理システムであって、前記生産ラインにおいて追加で実施される追加作業に必要な作業時間である追加作業時間と、前記工程内の1つ以上の要素作業それぞれに必要な作業時間である要素作業時間とを取得する取得部と、取得された前記追加作業時間及び前記要素作業時間に基づいて、前記追加作業を前記工程の少なくとも1つに追加して工程間で前記要素作業を再配置したときの複数の前記工程それぞれの作業時間のうちの最大作業時間がより小さくなるように、前記複数の工程についての前記追加作業及び複数の前記要素作業の組み合わせを算出する算出部と、を有する。 The process management system according to the present invention is a process management system that manages a production line including multiple existing processes in which predetermined work is performed, and has an acquisition unit that acquires additional work time, which is the work time required for additional work performed in the production line, and element work time, which is the work time required for each of one or more element works in the process, and a calculation unit that calculates a combination of the additional work and multiple element works for the multiple processes based on the acquired additional work time and element work time, so that the maximum work time among the work times of each of the multiple processes is reduced when the additional work is added to at least one of the processes and the element works are rearranged between the processes.

また、本発明にかかる工程管理方法は、所定の作業が行われる既存の複数の工程を含む生産ラインを管理する工程管理方法であって、前記生産ラインにおいて追加で実施される追加作業に必要な作業時間である追加作業時間と、前記工程内の1つ以上の要素作業それぞれに必要な作業時間である要素作業時間とを取得し、取得された前記追加作業時間及び前記要素作業時間に基づいて、前記追加作業を前記工程の少なくとも1つに追加して工程間で前記要素作業を再配置したときの複数の前記工程それぞれの作業時間のうちの最大作業時間がより小さくなるように、前記複数の工程についての前記追加作業及び複数の前記要素作業の組み合わせを算出する。 The process management method according to the present invention is a process management method for managing a production line including a plurality of existing processes in which predetermined work is performed, and obtains additional work time, which is the work time required for additional work performed in the production line, and element work time, which is the work time required for each of one or more element work within the process, and calculates a combination of the additional work and the element work for the plurality of processes based on the obtained additional work time and element work time, so that the maximum work time among the work times of each of the plurality of processes is reduced when the additional work is added to at least one of the processes and the element work is rearranged between the processes.

本発明は、このような構成により、要素作業及び追加作業が再配置された各工程の作業時間が、より平滑化されるようになる。そして、各工程の作業時間がより平滑化されることによって、生産ラインの生産性が良好となり得る。したがって、本発明は、追加作業が発生した場合であっても、生産ラインの生産性を適正化することが可能となる。 With this configuration, the present invention makes it possible to smooth out the work time of each process in which element work and additional work have been rearranged. By smoothing out the work time of each process, the productivity of the production line can be improved. Therefore, the present invention makes it possible to optimize the productivity of the production line even when additional work occurs.

また、好ましくは、前記複数の工程のうちの、前記要素作業が再配置される工程である再配置工程を決定する決定部、をさらに有する。
このような構成により、要素作業の再配置を適切に行うことが可能となる。
In a preferred embodiment, the system further comprises a determination section for determining a rearrangement process, which is a process in which the element work is rearranged, among the plurality of processes.
With this configuration, it becomes possible to appropriately rearrange the work elements.

また、好ましくは、前記算出部によって算出された前記最大作業時間が予め定められた時間を超える場合に、前記決定部は、前記再配置工程を変更し、前記算出部は、変更された前記再配置工程について、前記組み合わせを算出する。
このような構成により、要素作業が再配置される再配置工程を限定しつつ、最大作業時間が予め定められた時間以下となるような、要素作業の組み合わせを算出することが可能となる。これにより、追加作業が生産ラインに追加された場合であっても、生産計画に影響を及ぼすことを抑制することができる。
Also, preferably, when the maximum operation time calculated by the calculation unit exceeds a predetermined time, the determination unit changes the rearrangement process, and the calculation unit calculates the combination for the rearrangement process that has been changed.
With this configuration, it is possible to calculate a combination of element tasks that limits the rearrangement process to which the element tasks are rearranged, while keeping the maximum operation time below a predetermined time. This makes it possible to suppress the impact on the production plan even when an additional task is added to the production line.

また、好ましくは、前記取得部は、さらに、前記工程における作業を行う作業者に関する作業者情報を取得し、前記算出部は、前記作業者情報に基づいて、前記組み合わせを算出する。
このような構成により、作業者のスキルに応じた要素作業の組み合わせが算出されるので、要素作業の組み合わせの算出をより適切に行うことが可能となる。
In a preferred embodiment, the acquisition unit further acquires worker information related to a worker performing work in the process, and the calculation unit calculates the combination based on the worker information.
With this configuration, a combination of elemental tasks is calculated according to the skills of the workers, so that the combination of elemental tasks can be calculated more appropriately.

また、好ましくは、前記取得部は、さらに、前記要素作業に関する制限を示す制限情報を取得し、前記算出部は、前記制限情報に基づいて、前記組み合わせを算出する。
このような構成により、要素作業の制限に応じた要素作業の組み合わせが算出されるので、要素作業の組み合わせの算出をより適切に行うことが可能となる。
In a preferred embodiment, the acquisition section further acquires restriction information indicating restrictions on the element operations, and the calculation section calculates the combination based on the restriction information.
With this configuration, a combination of element tasks is calculated according to the limitations of the element tasks, so that the combination of element tasks can be calculated more appropriately.

本発明によれば、追加作業が発生した場合であっても生産ラインの生産性を適正化することが可能な工程管理システム及び工程管理方法を提供できる。 The present invention provides a process management system and a process management method that can optimize the productivity of a production line even when additional work occurs.

本実施の形態の概要を説明するための図である。FIG. 1 is a diagram for explaining an overview of the present embodiment. 実施の形態1にかかる工程管理システムのハードウェア構成を示す図である。FIG. 1 is a diagram illustrating a hardware configuration of a process control system according to a first embodiment. 実施の形態1にかかる工程管理システムの構成を示す機能ブロック図である。FIG. 1 is a functional block diagram showing a configuration of a process control system according to a first embodiment. 実施の形態1にかかる工程情報格納部によって格納される工程情報を例示する図である。4 is a diagram illustrating an example of process information stored by a process information storage unit according to the first embodiment; FIG. 実施の形態1にかかる各要素作業の標準作業時間を例示する図である。FIG. 2 is a diagram illustrating an example of standard work times for each element work according to the first embodiment. 図5の例において、工程ごとに要素作業時間を積み上げて各工程の作業時間を示した図である。In the example of FIG. 5, the element work time for each process is accumulated to show the work time for each process. 実施の形態1にかかる作業者情報格納部によって格納される作業者情報を例示する図である。4 is a diagram illustrating an example of worker information stored by a worker information storage unit according to the first embodiment; FIG. 実施の形態1にかかる工程決定部の処理を説明するための図である。4 is a diagram for explaining a process of a process determination unit according to the first embodiment; FIG. 実施の形態1にかかる工程管理システムによって実行される工程管理方法を示すフローチャートである。4 is a flowchart showing a process management method executed by the process management system according to the first embodiment; 実施の形態1にかかる工程管理システムが、追加作業が発生した場合に再配置処理を行う方法を説明するための図である。1 is a diagram for explaining a method in which the process control system according to the first embodiment performs a rearrangement process when an additional task occurs; FIG. 実施の形態1にかかる工程管理システムが、追加作業が発生した場合に再配置処理を行う方法を説明するための図である。1 is a diagram for explaining a method in which the process control system according to the first embodiment performs a rearrangement process when an additional task occurs; FIG. 実施の形態1にかかる工程管理システムが、追加作業が発生した場合に再配置処理を行う方法を説明するための図である。1 is a diagram for explaining a method in which the process control system according to the first embodiment performs a rearrangement process when an additional task occurs; FIG. 実施の形態1にかかる工程管理システムが、追加作業が発生した場合に再配置処理を行う方法を説明するための図である。1 is a diagram for explaining a method in which the process control system according to the first embodiment performs a rearrangement process when an additional task occurs; FIG. 実施の形態1にかかる工程管理システムが、追加作業が発生した場合に再配置処理を行う方法を説明するための図である。1 is a diagram for explaining a method in which the process control system according to the first embodiment performs a rearrangement process when an additional task occurs; FIG.

(実施の形態1)
以下、図面を参照して本発明の実施の形態について説明する。説明の明確化のため、以下の記載及び図面は、適宜、省略、及び簡略化がなされている。また、各図面において、同一の要素には同一の符号が付されており、必要に応じて重複説明は省略されている。
(Embodiment 1)
Hereinafter, an embodiment of the present invention will be described with reference to the drawings. For clarity of explanation, the following description and drawings are omitted and simplified as appropriate. In addition, in each drawing, the same elements are given the same reference numerals, and duplicate explanations are omitted as necessary.

<概要>
実施の形態1について説明する前に、実施の形態の概要について説明する。
図1は、本実施の形態の概要を説明するための図である。図1は、工場における生産ライン50を示す図である。生産ライン50は、複数の工程を含んでいる。図1の例では、生産ライン50は、工程A、工程B、工程C、工程D、工程E、工程F及び工程Gを含んでいる。生産ライン50では、通常、工程Aから順に、工程B、工程C、工程D、・・・の順で、作業が進められる。したがって、図1の例では、工程Aから工程Gに向かって生産ライン50のフローが流れている。
<Overview>
Before describing the first embodiment, an overview of the embodiments will be described.
Fig. 1 is a diagram for explaining an outline of the present embodiment. Fig. 1 is a diagram showing a production line 50 in a factory. The production line 50 includes a plurality of processes. In the example of Fig. 1, the production line 50 includes a process A, a process B, a process C, a process D, a process E, a process F, and a process G. In the production line 50, operations are usually carried out in the order of process A, process B, process C, process D, .... Therefore, in the example of Fig. 1, the flow of the production line 50 runs from process A to process G.

生産ライン50における各工程において、ライン作業が実行されている。ここで、各工程A~Gでは、同時に、それぞれの工程について所定の作業が実行されている。つまり、工程Aの作業が終了するまで工程B~工程Gの作業が実行されないわけでなく、工程Aで作業が実行されている間、工程B~工程Gそれぞれについて定められた作業が実行される。工程A~工程Gでは、それぞれ、生産計画によって予め定められた時間であるタクトタイムを超えないような作業時間で作業が実行されるように、作業計画がなされている。タクトタイムは、生産計画に応じて定められ得る。 Line work is being carried out at each process in the production line 50. Here, at each of processes A to G, predetermined work is being carried out simultaneously for each process. In other words, work at processes B to G is not suspended until work at process A is completed, but rather, while work at process A is being carried out, the work defined for each of processes B to G is being carried out. Work plans are made for each of processes A to G so that work is carried out within a work time that does not exceed the takt time, which is a time predetermined by the production plan. The takt time can be determined according to the production plan.

ここで、生産ライン50において、突発的に、品質不具合に対する処置などの追加作業が発生した場合、工場の稼働を止めないように追加作業を実行することが求められる。ここで、追加作業を生産ライン50の外で実行すると、生産ライン50の外にワークを運び出して追加作業を行い、追加作業が終わったらワークを生産ライン50に戻すといった作業が必要となるので、工場稼働率が低下してしまうおそれがある。したがって、インラインで追加作業を行うことが望まれる。すなわち、生産ライン50に追加作業を組み込むことが望まれる。 Here, if additional work, such as dealing with a quality defect, suddenly arises on the production line 50, it is necessary to perform the additional work without stopping the operation of the factory. Here, if the additional work is performed outside the production line 50, it will be necessary to carry the work outside the production line 50 to perform the additional work, and then return the work to the production line 50 once the additional work is completed, which may reduce the factory operation rate. Therefore, it is desirable to perform the additional work inline. In other words, it is desirable to incorporate the additional work into the production line 50.

しかしながら、単に、ある工程に追加作業を追加してその工程で追加作業を実行するようにすると、その工程の作業時間が他の工程の作業時間と比較して大きくなってしまい、その工程がボトルネックとなるおそれがある。例えば、生産ライン50において、工程Cで不具合が発生したとすると、工程Cで追加作業を行うことが効率的である。しかしながら、単純に工程Cに追加作業を追加するのみであると、工程Cの作業時間が、他の工程の作業時間と比較してかなり大きくなる可能性がある。その場合、工程Cの作業時間と他の工程の作業時間との差があまりにも大きくなると、工程Cがボトルネックとなるため、生産ライン50の全体の生産効率が低下するおそれがある。さらに、この場合、工程Cの作業時間がタクトタイムを超えてしまうと、生産計画に影響を及ぼすおそれがある。 However, simply adding additional work to a certain process and performing the additional work in that process may result in the work time of that process being longer than the work time of other processes, causing the process to become a bottleneck. For example, if a malfunction occurs in process C in production line 50, it is efficient to perform the additional work in process C. However, simply adding additional work to process C may result in the work time of process C being significantly longer than the work time of the other processes. In that case, if the difference between the work time of process C and the work time of the other processes becomes too large, process C may become a bottleneck, causing the overall production efficiency of production line 50 to decrease. Furthermore, in this case, if the work time of process C exceeds the takt time, this may affect the production plan.

ここで、各工程には、その工程で実行される複数の要素作業がある。つまり、各工程は、複数の要素作業で構成される。本実施の形態では、以下に説明するように、追加作業を工程に追加して、各工程における要素作業を工程間で再配置する(組み換える)ように構成されている。つまり、本実施の形態では、各工程における1つ以上の要素作業を、他の工程に再配置するように構成されている。そして、本実施の形態では、その際に、要素作業が再配置された各工程の作業時間が、できるだけ平滑化されるように構成されている。すなわち、本実施の形態では、再配置後の各工程の作業時間のうちの最大作業時間がより小さくなるように、要素作業及び追加作業を再配置するように構成されている。これにより、追加作業が発生した場合であっても、生産ラインの生産性を適正化することが可能となる。つまり、追加作業が発生した場合であっても、生産ラインの生産性の低下を抑制することができる。したがって、生産ラインに追加作業を組み込んでも、工場の稼働に対する影響を少なくすることが可能となる。 Here, each process has a plurality of elemental operations that are executed in that process. That is, each process is composed of a plurality of elemental operations. In this embodiment, as described below, an additional operation is added to the process, and the elemental operations in each process are rearranged (recombined) between processes. That is, in this embodiment, one or more elemental operations in each process are rearranged to another process. In this embodiment, the operation time of each process in which the elemental operations are rearranged is smoothed as much as possible. That is, in this embodiment, the elemental operations and the additional operations are rearranged so that the maximum operation time of the operation time of each process after the rearrangement is smaller. This makes it possible to optimize the productivity of the production line even when additional operations occur. That is, even when additional operations occur, it is possible to suppress a decrease in the productivity of the production line. Therefore, even if additional operations are incorporated into the production line, it is possible to reduce the impact on the operation of the factory.

<工程管理システム>
次に、実施の形態1にかかる工程管理システムについて説明する。
図2は、実施の形態1にかかる工程管理システム1のハードウェア構成を示す図である。ここで、工程管理システム1は、1つ又は複数のコンピュータ等の情報処理装置によって実現され得る。工程管理システム1は、例えばクラウドシステムによって実現されてもよい。また、工程管理システム1は、複数の装置(例えばサーバ)によって実現されてもよい。この場合、複数の装置それぞれが、図2に示したハードウェア構成を有し得る。
<Process control system>
Next, the process control system according to the first embodiment will be described.
2 is a diagram showing a hardware configuration of the process control system 1 according to the first embodiment. Here, the process control system 1 can be realized by one or more information processing devices such as computers. The process control system 1 can also be realized by, for example, a cloud system. The process control system 1 can also be realized by multiple devices (for example, servers). In this case, each of the multiple devices can have the hardware configuration shown in FIG. 2.

工程管理システム1は、主要なハードウェア構成として、CPU12(Central Processing Unit)と、ROM14(Read Only Memory)と、RAM16(Random Access Memory)と、インタフェース部18(IF;Interface)とを有する。CPU12、ROM14、RAM16及びインタフェース部18は、データバスなどを介して相互に接続されている。 The process control system 1 has, as its main hardware components, a CPU 12 (Central Processing Unit), a ROM 14 (Read Only Memory), a RAM 16 (Random Access Memory), and an interface unit 18 (IF; Interface). The CPU 12, ROM 14, RAM 16, and interface unit 18 are interconnected via a data bus or the like.

CPU12は、制御処理及び演算処理等を行う演算装置(処理デバイスまたはプロセッサ)としての機能を有する。ROM14は、CPU12によって実行される制御プログラム及び演算プログラム等を記憶するストレージとしての機能を有する。ROM14は、データベースを含み得る。RAM16は、処理データ等を一時的に記憶するメモリとしての機能を有する。 The CPU 12 functions as a calculation device (processing device or processor) that performs control processing and calculation processing. The ROM 14 functions as storage that stores control programs and calculation programs executed by the CPU 12. The ROM 14 may include a database. The RAM 16 functions as a memory that temporarily stores processing data, etc.

インタフェース部18は、有線又は無線を介して外部と信号の入出力を行う。したがって、インタフェース部18は、通信装置としての機能を有する。また、インタフェース部18は、ユーザによるデータの入力の操作を受け付け、ユーザに対して情報を表示するための処理を行う。インタフェース部18は、例えばキーボード等の入力デバイスと、例えばディスプレイ等の出力デバイスとを有してもよい。また、インタフェース部18は、入力デバイスと出力デバイスとが一体となったタッチパネルを有してもよい。また、インタフェース部18は、マイク及びスピーカを有してもよい。例えば、インタフェース部18は、再配置された要素作業を示す情報を表示してもよい。また、インタフェース部18は、カメラ等の撮像装置を有してもよい。また、インタフェース部18は、上述した情報処理装置とは物理的に別個の装置として実現されてもよい。 The interface unit 18 inputs and outputs signals from and to the outside via wired or wireless communication. Therefore, the interface unit 18 functions as a communication device. The interface unit 18 also accepts data input operations by the user and performs processing to display information to the user. The interface unit 18 may have an input device such as a keyboard and an output device such as a display. The interface unit 18 may also have a touch panel in which the input device and the output device are integrated. The interface unit 18 may also have a microphone and a speaker. For example, the interface unit 18 may display information indicating the rearranged element work. The interface unit 18 may also have an imaging device such as a camera. The interface unit 18 may also be realized as a device that is physically separate from the above-mentioned information processing device.

図3は、実施の形態1にかかる工程管理システム1の構成を示す機能ブロック図である。工程管理システム1は、構成要素として、情報格納部100と、取得部120と、工程決定部130と、算出部140と、判定部150と、表示制御部160とを有する。情報格納部100は、工程情報格納部102と、作業者情報格納部104と、追加作業情報格納部106とを有する。取得部120は、追加作業情報取得部122と、既存作業情報取得部124とを有する。 Figure 3 is a functional block diagram showing the configuration of the process management system 1 according to the first embodiment. The process management system 1 has, as components, an information storage unit 100, an acquisition unit 120, a process determination unit 130, a calculation unit 140, a judgment unit 150, and a display control unit 160. The information storage unit 100 has a process information storage unit 102, a worker information storage unit 104, and an additional work information storage unit 106. The acquisition unit 120 has an additional work information acquisition unit 122 and an existing work information acquisition unit 124.

ここで、上述した工程管理システム1の各構成要素は、物理的に1つの装置によって実現されることに限定されず、例えばクラウドコンピューティング等により複数の装置によって実現されてもよい。つまり、工程管理システム1は、物理的に複数の装置で構成されてもよい。例えば、情報格納部100は、他の構成要素とは別の装置で実現されてもよい。 Here, each component of the process control system 1 described above is not limited to being realized by one physical device, but may be realized by multiple devices, for example, by cloud computing. In other words, the process control system 1 may be physically composed of multiple devices. For example, the information storage unit 100 may be realized by a device separate from the other components.

なお、これらの構成要素は、例えば、CPU12がROM14に記憶されたプログラムを実行することによって実現可能である。また、各構成要素は、必要なプログラムを任意の不揮発性記録媒体に記録しておき、必要に応じてインストールするようにして、実現されるようにしてもよい。なお、各構成要素は、上記のようにソフトウェアによって実現されることに限定されず、何らかの回路素子等のハードウェアによって実現されてもよい。また、各構成要素は、例えばFPGA(field-programmable gate array)又はマイコン等の、ユーザがプログラミング可能な集積回路を用いて実現してもよい。この場合、この集積回路を用いて、上記の各構成要素から構成されるプログラムを実現してもよい。また、上記構成要素の1つ以上は、物理的に別個のハードウェアによってそれぞれ実現されてもよい。 These components can be realized, for example, by the CPU 12 executing a program stored in the ROM 14. Each component may be realized by recording the necessary program on any non-volatile recording medium and installing it as needed. Each component is not limited to being realized by software as described above, but may be realized by hardware such as some kind of circuit element. Each component may be realized by using an integrated circuit that can be programmed by the user, such as an FPGA (field-programmable gate array) or a microcomputer. In this case, the integrated circuit may be used to realize a program composed of each of the above components. One or more of the above components may be realized by physically separate hardware.

情報格納部100は、生産ラインに関する情報を格納する。なお、情報格納部100は、1つのデータベースで実現されてもよい。あるいは、情報格納部100は、複数のデータベースで実現されてもよい。その場合、情報格納部100の各構成要素は、互いに別のデータベースで実現されてもよい。 The information storage unit 100 stores information about the production line. The information storage unit 100 may be realized as one database. Alternatively, the information storage unit 100 may be realized as multiple databases. In that case, each component of the information storage unit 100 may be realized as a separate database.

さらに、情報格納部100の各構成要素は、互いに別の装置で実現されてもよい。例えば、工程情報格納部102は、生産管理部門等によって管理されるデータベース又はサーバ等によって実現されてもよい。また、作業者情報格納部104は、人事管理部門等によって管理されるデータベース又はサーバ等によって実現されてもよい。また、追加作業情報格納部106は、品質管理部門等によって管理されるデータベース又はサーバ等によって実現されてもよい。 Furthermore, each component of the information storage unit 100 may be realized by a separate device. For example, the process information storage unit 102 may be realized by a database or a server managed by a production management department or the like. The worker information storage unit 104 may be realized by a database or a server managed by a human resources management department or the like. The additional work information storage unit 106 may be realized by a database or a server managed by a quality control department or the like.

工程情報格納部102及び作業者情報格納部104は、追加作業が発生しているか否かに関わらず、既存の作業に関する情報である既存作業情報を格納し得る。一方、追加作業情報格納部106は、追加作業が発生した場合に、追加作業に関する情報を格納してもよい。 The process information storage unit 102 and the worker information storage unit 104 may store existing work information, which is information about existing work, regardless of whether additional work has occurred. On the other hand, the additional work information storage unit 106 may store information about additional work when additional work has occurred.

工程情報格納部102は、既存作業情報である工程情報を格納する。工程情報は、既存の各工程に関する情報である。工程情報は、各工程の要素作業に関する情報を含む。工程情報は、予め格納されていてもよい。工程情報は、予め、管理者によってインタフェース部18を用いて入力されてもよい。 The process information storage unit 102 stores process information, which is existing work information. The process information is information about each existing process. The process information includes information about the elemental work of each process. The process information may be stored in advance. The process information may be input in advance by an administrator using the interface unit 18.

図4は、実施の形態1にかかる工程情報格納部102によって格納される工程情報を例示する図である。工程情報は、タクトタイムと、工程設備情報と、作業種別情報と、標準作業時間と、前後作業制限情報とを示す。タクトタイムは、各工程に共通して要求される時間である。上述したように、タクトタイムは、生産計画に応じて予め定められ得る。なお、上述したように、通常、各工程の作業時間は、タクトタイム以下とする必要がある。 Figure 4 is a diagram illustrating process information stored by the process information storage unit 102 according to the first embodiment. The process information indicates the takt time, process equipment information, task type information, standard work time, and pre- and post-task restriction information. The takt time is the time commonly required for each process. As described above, the takt time can be determined in advance according to the production plan. Note that, as described above, the work time for each process usually needs to be less than or equal to the takt time.

工程設備情報は、各工程で使用可能な設備の種類を示す。なお、工程設備情報は、その設備の識別情報を示してもよい。また、各工程の要素作業によって使用可能な設備が異なる場合、工程設備情報は、要素作業ごとに、使用可能な設備に関する情報を示してもよい。なお、工程設備情報は、要素作業を実行可能な設備を示しているので、要素作業に関する制限を示す制限情報であるといえる。 The process equipment information indicates the type of equipment that can be used in each process. The process equipment information may also indicate identification information for that equipment. Furthermore, if the equipment that can be used differs depending on the element work of each process, the process equipment information may indicate information on the equipment that can be used for each element work. Furthermore, since the process equipment information indicates the equipment that can perform the element work, it can be said to be restriction information that indicates restrictions on the element work.

作業種別情報は、要素作業ごとの作業種別を示す。作業種別は、例えば、「締め付け作業」、「組付け作業」、及び「部品入れ替え作業」等を含む。なお、1つの工程の複数の要素作業において、作業種別は互いに異なっていてもよい。つまり、1つの工程は、互いに異なる作業種別の複数の要素作業を含み得る。 The work type information indicates the work type for each element work. Work types include, for example, "tightening work," "assembly work," and "part replacement work." Note that the work types may be different for multiple element works in one process. In other words, one process may include multiple element works with different work types.

標準作業時間は、要素作業ごとの標準的な作業時間を示す。ここで、標準作業時間は、タクトタイムに応じて予め定められた、要素作業の作業時間である。ここで、要素作業に必要な作業時間を「要素作業時間」と称することがある。なお、標準作業時間は、各要素作業の作業内容(作業種別)に応じて定められてもよい。つまり、標準作業時間は、各要素作業の作業内容(作業種別)に応じて定められてもよい。また、標準作業時間は、例えば、ある作業者が代表してその要素作業を行ったときの作業時間であってもよい。あるいは、標準作業時間は、その要素作業の過去の実績から、管理者等によって定められてもよい。 Standard work time indicates the standard work time for each element work. Here, the standard work time is the work time for an element work that is determined in advance according to the takt time. Here, the work time required for an element work is sometimes referred to as "element work time". The standard work time may be determined according to the work content (work type) of each element work. In other words, the standard work time may be determined according to the work content (work type) of each element work. Furthermore, the standard work time may be, for example, the work time when a certain worker performs the element work on behalf of the others. Alternatively, the standard work time may be determined by a manager, etc., based on the past performance of the element work.

図5は、実施の形態1にかかる各要素作業の標準作業時間を例示する図である。また、図6は、図5の例において、工程ごとに要素作業時間を積み上げて各工程の作業時間を示した図である。図5及び図6には、図1に例示した複数の工程のうち、工程A~工程Dの各要素作業の標準作業時間(標準となる要素作業時間)が例示されている。ここで、図5及び図6には、各工程が5つの要素作業で構成されている例が示されている。しかしながら、各工程の要素作業の数は、5つでなくてもよい。また、各工程の要素作業の数は、互いに同じである必要はない。なお、図5及び図6の例では、タクトタイムが32秒であるとする。また、図6において、各工程の各要素作業の長さは、その要素作業の要素作業時間(標準作業時間)に対応する。 Figure 5 is a diagram illustrating the standard work time of each element work according to the first embodiment. Figure 6 is a diagram showing the work time of each process by accumulating the element work time for each process in the example of Figure 5. Figures 5 and 6 illustrate the standard work time (standard element work time) of each element work of processes A to D among the multiple processes illustrated in Figure 1. Here, Figures 5 and 6 show an example in which each process is composed of five element works. However, the number of element works in each process does not have to be five. Also, the number of element works in each process does not have to be the same. In the examples of Figures 5 and 6, the takt time is 32 seconds. Also, in Figure 6, the length of each element work in each process corresponds to the element work time (standard work time) of that element work.

工程Aの1つ目の要素作業A1の標準作業時間(要素作業時間)は、5秒である。また、工程Aの2つ目の要素作業A2の標準作業時間(要素作業時間)は、7秒である。また、工程Aの3つ目の要素作業A3の標準作業時間(要素作業時間)は、5秒である。また、工程Aの4つ目の要素作業A4の標準作業時間(要素作業時間)は、8秒である。また、工程Aの5つ目の要素作業A5の標準作業時間(要素作業時間)は、7秒である。そして、要素作業A1~要素作業A5の標準作業時間の合計、つまり工程Aの作業時間は、タクトタイムに対応する32秒である。 The standard work time (element work time) of the first element work A1 in process A is 5 seconds. The standard work time (element work time) of the second element work A2 in process A is 7 seconds. The standard work time (element work time) of the third element work A3 in process A is 5 seconds. The standard work time (element work time) of the fourth element work A4 in process A is 8 seconds. The standard work time (element work time) of the fifth element work A5 in process A is 7 seconds. The sum of the standard work times of element work A1 to A5, that is, the work time of process A, is 32 seconds, which corresponds to the takt time.

工程Bの1つ目の要素作業B1の標準作業時間(要素作業時間)は、2秒である。また、工程Bの2つ目の要素作業B2の標準作業時間(要素作業時間)は、10秒である。また、工程Bの3つ目の要素作業B3の標準作業時間(要素作業時間)は、8秒である。また、工程Bの4つ目の要素作業B4の標準作業時間(要素作業時間)は、6秒である。また、工程Bの5つ目の要素作業B5の標準作業時間(要素作業時間)は、6秒である。そして、要素作業B1~要素作業B5の標準作業時間の合計、つまり工程Bの作業時間は、タクトタイムに対応する32秒である。 The standard work time (element work time) of the first element work B1 in process B is 2 seconds. The standard work time (element work time) of the second element work B2 in process B is 10 seconds. The standard work time (element work time) of the third element work B3 in process B is 8 seconds. The standard work time (element work time) of the fourth element work B4 in process B is 6 seconds. The standard work time (element work time) of the fifth element work B5 in process B is 6 seconds. The sum of the standard work times of element work B1 to B5, that is, the work time of process B, is 32 seconds, which corresponds to the takt time.

工程Cの1つ目の要素作業C1の標準作業時間(要素作業時間)は、5秒である。また、工程Cの2つ目の要素作業C2の標準作業時間(要素作業時間)は、8秒である。また、工程Cの3つ目の要素作業C3の標準作業時間(要素作業時間)は、3秒である。また、工程Cの4つ目の要素作業C4の標準作業時間(要素作業時間)は、11秒である。また、工程Cの5つ目の要素作業C5の標準作業時間(要素作業時間)は、5秒である。そして、要素作業C1~要素作業C5の標準作業時間の合計、つまり工程Cの作業時間は、タクトタイムに対応する32秒である。 The standard work time (element work time) of the first element work C1 in process C is 5 seconds. The standard work time (element work time) of the second element work C2 in process C is 8 seconds. The standard work time (element work time) of the third element work C3 in process C is 3 seconds. The standard work time (element work time) of the fourth element work C4 in process C is 11 seconds. The standard work time (element work time) of the fifth element work C5 in process C is 5 seconds. The sum of the standard work times of element work C1 to C5, that is, the work time of process C, is 32 seconds, which corresponds to the takt time.

工程Dの1つ目の要素作業D1の標準作業時間(要素作業時間)は、6秒である。また、工程Dの2つ目の要素作業D2の標準作業時間(要素作業時間)は、6秒である。また、工程Dの3つ目の要素作業D3の標準作業時間(要素作業時間)は、5秒である。また、工程Dの4つ目の要素作業D4の標準作業時間(要素作業時間)は、5秒である。また、工程Dの5つ目の要素作業D5の標準作業時間(要素作業時間)は、10秒である。そして、要素作業D1~要素作業D5の標準作業時間の合計、つまり工程Dの作業時間は、タクトタイムに対応する32秒である。なお、他の工程についても同様に、要素作業の標準作業時間(要素作業時間)の合計、つまり各工程の作業時間は、タクトタイムに対応する32秒となる。 The standard work time (element work time) of the first element work D1 in process D is 6 seconds. The standard work time (element work time) of the second element work D2 in process D is 6 seconds. The standard work time (element work time) of the third element work D3 in process D is 5 seconds. The standard work time (element work time) of the fourth element work D4 in process D is 5 seconds. The standard work time (element work time) of the fifth element work D5 in process D is 10 seconds. The sum of the standard work times of the element work D1 to D5, that is, the work time of process D, is 32 seconds, which corresponds to the takt time. Similarly, for the other processes, the sum of the standard work times (element work times) of the element works, that is, the work time of each process, is 32 seconds, which corresponds to the takt time.

図4の説明に戻る。前後作業制限情報は、各工程の複数の要素作業それぞれの、作業順序の制限(前後作業制限)を示す。例えば、前後作業制限は、各工程の複数の要素作業それぞれについて、その要素作業の前に実行されていなければならない作業(要素作業又は工程)を示してもよい。また、例えば、前後作業制限は、各工程の複数の要素作業それぞれについて、その要素作業の後に実行されなければならない作業(要素作業又は工程)を示してもよい。例えば、図5及び図6の例において、前後作業制限は、要素作業C2の前に、要素作業A1が実行されていなければならないことを示してもよい。なお、前後作業制限情報は、要素作業を実行する順序の制限を示しているので、要素作業に関する制限を示す制限情報であるといえる。 Returning to the explanation of FIG. 4, the pre- and post-task restriction information indicates restrictions on the order of work (pre- and post-task restrictions) for each of the multiple element work tasks in each process. For example, the pre- and post-task restriction may indicate the work (element work task or process) that must be performed before each of the multiple element work tasks in each process. Also, for example, the pre- and post-task restriction may indicate the work (element work task or process) that must be performed after each of the multiple element work tasks in each process. For example, in the examples of FIG. 5 and FIG. 6, the pre- and post-task restriction may indicate that element work task A1 must be performed before element work task C2. Note that the pre- and post-task restriction information indicates restrictions on the order in which element work tasks are performed, and thus can be said to be restriction information indicating restrictions on element work tasks.

図3の説明に戻る。作業者情報格納部104は、既存作業情報である作業者情報を格納する。作業者情報は、各工程における作業を行う作業者に関する情報である。作業者情報は、各作業者の要素作業に関する情報を含む。作業者情報は、予め格納されていてもよい。その場合、作業者情報は、予め、管理者によってインタフェース部18を用いて入力されてもよい。あるいは、作業者情報は、後述するように、各作業者が要素作業を実際に行う様子を撮影することによって、取得されてもよい。 Returning to the explanation of FIG. 3, the worker information storage unit 104 stores worker information, which is existing work information. The worker information is information about the workers who perform the work in each process. The worker information includes information about the elemental work of each worker. The worker information may be stored in advance. In that case, the worker information may be input in advance by an administrator using the interface unit 18. Alternatively, the worker information may be obtained by photographing each worker actually performing the elemental work, as described below.

図7は、実施の形態1にかかる作業者情報格納部104によって格納される作業者情報を例示する図である。図7には、作業者#1、作業者#2、作業者#3及び作業者#4に関する作業者情報が例示されている。作業者情報は、作業者ごとに、例えば、作業可能工程と、工程スキルレベルと、実作業時間と、作業種別スキルレベルと、を示すデータを含む。 Figure 7 is a diagram illustrating an example of worker information stored by the worker information storage unit 104 according to the first embodiment. Figure 7 illustrates examples of worker information relating to worker #1, worker #2, worker #3, and worker #4. The worker information includes data indicating, for each worker, the possible work processes, the process skill level, the actual work time, and the work type skill level.

作業可能工程は、対応する作業者が作業を行うことが可能な工程を示す。例えば、図5及び図6の例において、作業者#1に関する作業可能工程は、作業者#1が作業を行うことが可能な工程として、「工程A」、「工程C」及び「工程D」を示してもよい。また、作業者#2に関する作業可能工程は、作業者#2が作業を行うことが可能な工程として、「工程B」、「工程C」及び「工程D」を示してもよい。また、作業者#3に関する作業可能工程は、作業者#3が作業を行うことが可能な工程として、「工程A」、「工程B」及び「工程C」を示してもよい。また、作業者#4に関する作業可能工程は、作業者#4が作業を行うことが可能な工程として、「工程A」、「工程C」及び「工程D」を示してもよい。 The available processes indicate processes that the corresponding worker can work on. For example, in the examples of Figures 5 and 6, the available processes for worker #1 may indicate "Process A", "Process C", and "Process D" as processes that worker #1 can work on. Furthermore, the available processes for worker #2 may indicate "Process B", "Process C", and "Process D" as processes that worker #2 can work on. Furthermore, the available processes for worker #3 may indicate "Process A", "Process B", and "Process C" as processes that worker #3 can work on. Furthermore, the available processes for worker #4 may indicate "Process A", "Process C", and "Process D" as processes that worker #4 can work on.

工程スキルレベルは、対応する作業者の、各工程の作業を行うスキルのレベルを示す。なお、工程スキルレベルは、対応する作業者が作業を行うことが可能な工程についてのスキルレベルを示してもよい。工程スキルレベルは、例えば、10段階の数値で示されてもよいし、「レベル高」、「レベル中」及び「レベル低」といったように、3段階で示されてもよい。 The process skill level indicates the skill level of the corresponding worker to perform the work of each process. The process skill level may also indicate the skill level for the process at which the corresponding worker can perform the work. The process skill level may be indicated, for example, by a numerical value on a 10-point scale, or may be indicated by three levels, such as "high level," "medium level," and "low level."

例えば、上述の例において、作業者#1に関する工程スキルレベルは、「工程A:高」、「工程C:低」及び「工程D:中」を示してもよい。また、作業者#2に関する工程スキルレベルは、「工程B:高」、「工程C:低」及び「工程D:中」を示してもよい。また、作業者#3に関する工程スキルレベルは、「工程A:高」、「工程B:高」及び「工程C:低」を示してもよい。また、作業者#4に関する工程スキルレベルは、「工程A:高」、「工程C:中」及び「工程D:中」を示してもよい。 For example, in the above example, the process skill levels for worker #1 may indicate "Process A: High", "Process C: Low", and "Process D: Medium". The process skill levels for worker #2 may indicate "Process B: High", "Process C: Low", and "Process D: Medium". The process skill levels for worker #3 may indicate "Process A: High", "Process B: High", and "Process C: Low". The process skill levels for worker #4 may indicate "Process A: High", "Process C: Medium", and "Process D: Medium".

実作業時間は、対応する作業者が各工程の要素作業を実行する際に実際に要する作業時間である。したがって、実作業時間は、要素作業の作業時間であるから、要素作業時間である。一方、上述した標準作業時間がタクトタイムから定まる作業時間であるのに対し、実作業時間は、作業者のスキルレベル等に応じて定まり得る。したがって、例えば、各作業者に関する工程Aの各要素作業の実作業時間は、対応する作業者の工程Aについての工程スキルレベルが高ければ短く、対応する作業者の工程Aについての工程スキルレベルが低ければ長くなり得る。また、実作業時間は、標準作業時間以下であり得る。そして、ある作業者について、ある工程の工程スキルレベルが「低」である場合、その工程の要素作業の実作業時間は、それぞれ、対応する要素作業の標準作業時間と略同じであってもよい。なお、実作業時間は、対応する作業者が作業を行うことが可能な工程の要素作業についての作業時間を示してもよい。 The actual work time is the work time actually required for the corresponding worker to perform the element work of each process. Therefore, the actual work time is the work time of the element work, and therefore the element work time. On the other hand, while the above-mentioned standard work time is the work time determined from the takt time, the actual work time can be determined according to the skill level of the worker. Therefore, for example, the actual work time of each element work of process A for each worker can be shorter if the corresponding worker's process skill level for process A is high, and longer if the corresponding worker's process skill level for process A is low. In addition, the actual work time can be less than the standard work time. And, for a certain worker, if the process skill level of a certain process is "low", the actual work time of the element work of that process may be approximately the same as the standard work time of the corresponding element work. Note that the actual work time may indicate the work time of the element work of the process that the corresponding worker can perform.

作業種別スキルレベルは、対応する作業者の作業種別ごとのスキルレベルを示す。作業種別スキルレベルは、例えば、10段階の数値で示されてもよいし、「レベル高」、「レベル中」及び「レベル低」といったように、3段階で示されてもよい。例えば、作業者#1に関する作業種別スキルレベルは、「締め付け作業:高」、「組付け作業:中」、及び「部品入れ替え作業:中」を示してもよい。他の作業者についても同様である。 The task type skill level indicates the skill level of the corresponding worker for each task type. The task type skill level may be indicated, for example, by a 10-level numerical scale, or by three levels such as "high level," "medium level," and "low level." For example, the task type skill levels for worker #1 may indicate "fastening work: high," "assembly work: medium," and "part replacement work: medium." The same applies to the other workers.

なお、作業者情報は、例えば、モーションキャプチャによって、要素作業を実行している作業者の動作を捉えることによって、生成されてもよい。その際に、捉えられた動作を示す情報を入力として、例えばニューラルネットワーク等の機械学習アルゴリズムにより、作業可能工程、工程スキルレベル、実作業時間、及び作業種別スキルレベルを取得してもよい。また、例えば、上述したように、作業者情報は、作業者が要素作業を実際に行う様子を撮影することによって、生成されてもよい。例えば、各工程の作業場所に設置されたカメラにより、実際に各要素作業を実行している作業者の骨格情報を取得してもよい。そして、骨格情報を分析して得られた要素作業ごとの作業時間、作業姿勢及び作業動線から、各作業者について、作業可能工程、工程スキルレベル、実作業時間、及び作業種別スキルレベルを取得してもよい。 The worker information may be generated, for example, by capturing the movements of a worker performing an elemental task using motion capture. At that time, the information indicating the captured movements may be used as input to obtain the available work processes, the process skill level, the actual work time, and the work type skill level using a machine learning algorithm such as a neural network. For example, as described above, the worker information may be generated by photographing the worker actually performing the elemental task. For example, skeletal information of the worker actually performing each elemental task may be obtained using a camera installed at the work location of each process. Then, the available work processes, the process skill level, the actual work time, and the work type skill level for each worker may be obtained from the work time, work posture, and work flow for each elemental task obtained by analyzing the skeletal information.

追加作業情報格納部106は、追加作業に関する追加作業情報を格納する。追加作業情報は、追加作業時間と、作業種別とを示す。追加作業時間は、追加作業に必要な作業時間である。ここで、追加作業情報格納部106に格納される追加作業で示される追加作業時間は、標準的な作業時間、つまり標準作業時間であってもよい。作業種別は、追加作業に対応する作業(要素作業)の種別を示す。追加作業の作業種別は、例えば、「締め付け作業」、「組付け作業」、及び「部品入れ替え作業」等を含む。なお、追加作業情報において、ある追加作業について、複数の作業種別が対応付けられていてもよい。つまり、追加作業は、複数の要素作業を含んでもよい。 The additional work information storage unit 106 stores additional work information related to additional work. The additional work information indicates the additional work time and the work type. The additional work time is the work time required for the additional work. Here, the additional work time indicated for the additional work stored in the additional work information storage unit 106 may be a standard work time, that is, a standard work time. The work type indicates the type of work (element work) corresponding to the additional work. The work types of the additional work include, for example, "tightening work," "assembly work," and "part replacement work." Note that in the additional work information, multiple work types may be associated with a certain additional work. In other words, the additional work may include multiple element works.

追加作業情報は、追加作業が発生したときに生成され得る。例えば、追加作業情報は、追加作業が発生したときに、ある作業者が代表して追加作業を実行することによって、生成されてもよい。具体的には、代表作業者が実際に追加作業を実行し、その追加作業に要した時間を計測することによって、追加作業時間が取得されてもよい。ここで、追加作業時間が標準作業時間である場合、追加作業の標準作業時間は、計測された時間を代表作業者のスキルレベルに応じて補正することによって、取得されてもよい。例えば、代表作業者のスキルレベルが高いほど計測された時間から増加するようにして、追加作業の標準作業時間を取得してもよい。また、追加作業の作業種別は、管理者が作業種別を判断してインタフェース部18によって入力されることによって、取得されてもよい。 The additional work information may be generated when additional work occurs. For example, the additional work information may be generated when additional work occurs by having a certain worker perform the additional work on behalf of the other workers. Specifically, the additional work time may be obtained by having a representative worker actually perform the additional work and measuring the time required for the additional work. Here, if the additional work time is a standard work time, the standard work time for the additional work may be obtained by correcting the measured time according to the skill level of the representative worker. For example, the standard work time for the additional work may be obtained by increasing the measured time as the skill level of the representative worker increases. In addition, the work type of the additional work may be obtained by the administrator determining the work type and inputting it through the interface unit 18.

あるいは、追加作業情報は、作業者情報と同様の方法によって、生成されてもよい。すなわち、追加作業情報は、例えば、モーションキャプチャによって、追加作業を実行している代表作業者の動作を捉えることによって、取得されてもよい。その際に、捉えられた動作を示す情報を入力として、例えばニューラルネットワーク等の機械学習アルゴリズムにより、追加作業時間及び作業種別を取得してもよい。また、例えば、追加作業情報は、代表作業者が追加作業を実際に行う様子を撮影することによって、取得されてもよい。例えば、カメラにより、実際に追加作業を実行している代表作業者の骨格情報を取得してもよい。そして、骨格情報を分析することによって、追加作業の作業時間及び作業種別を取得してもよい。 Alternatively, the additional work information may be generated in the same manner as the worker information. That is, the additional work information may be obtained, for example, by capturing the movements of the representative worker performing the additional work using motion capture. At that time, the additional work time and work type may be obtained using information indicating the captured movements as input, for example, using a machine learning algorithm such as a neural network. Also, for example, the additional work information may be obtained by photographing the representative worker actually performing the additional work. For example, skeletal information of the representative worker actually performing the additional work may be obtained using a camera. Then, the work time and work type of the additional work may be obtained by analyzing the skeletal information.

取得部120は、情報格納部100に格納される情報を取得する。追加作業情報取得部122は、追加作業情報を取得する。したがって、追加作業情報取得部122を有する取得部120は、追加作業時間を取得する。具体的には、追加作業情報取得部122は、上述した方法によって生成された追加作業情報を、インタフェース部18によって取得する。また、追加作業情報取得部122は、取得された追加作業情報を、追加作業情報格納部106に格納する。そして、追加作業情報取得部122は、後述する算出部140による処理が行われる際に、追加作業情報格納部106に格納された追加作業情報を抽出(取得)する。なお、追加作業情報取得部122は、上述したモーションキャプチャ及び機械学習アルゴリズム等を実行することによって、追加作業情報を生成してもよい。 The acquisition unit 120 acquires information stored in the information storage unit 100. The additional work information acquisition unit 122 acquires the additional work information. Thus, the acquisition unit 120 having the additional work information acquisition unit 122 acquires the additional work time. Specifically, the additional work information acquisition unit 122 acquires the additional work information generated by the above-mentioned method by the interface unit 18. The additional work information acquisition unit 122 also stores the acquired additional work information in the additional work information storage unit 106. Then, when processing is performed by the calculation unit 140 described later, the additional work information acquisition unit 122 extracts (acquires) the additional work information stored in the additional work information storage unit 106. Note that the additional work information acquisition unit 122 may generate the additional work information by executing the above-mentioned motion capture and machine learning algorithms, etc.

既存作業情報取得部124は、既存作業情報を取得する。つまり、既存作業情報取得部124は、既存作業情報である工程情報及び作業者情報を取得する。したがって、既存作業情報取得部124を有する取得部120は、要素作業時間を取得する。また、既存作業情報取得部124を有する取得部120は、作業者情報及び制限情報を取得する。 The existing work information acquisition unit 124 acquires existing work information. That is, the existing work information acquisition unit 124 acquires process information and worker information, which are existing work information. Therefore, the acquisition unit 120 having the existing work information acquisition unit 124 acquires element work time. In addition, the acquisition unit 120 having the existing work information acquisition unit 124 acquires worker information and restriction information.

具体的には、既存作業情報取得部124は、上述した方法によって生成された工程情報及び作業者情報を、インタフェース部18によって取得する。また、既存作業情報取得部124は、取得された工程情報及び作業者情報を、それぞれ、工程情報格納部102及び作業者情報格納部104に格納する。そして、既存作業情報取得部124は、後述する工程決定部130及び算出部140による処理が行われる際に、工程情報格納部102及び作業者情報格納部104にそれぞれ格納された工程情報及び作業者情報を抽出(取得)する。なお、既存作業情報取得部124は、上述したモーションキャプチャ及び機械学習アルゴリズム等を実行することによって、作業者情報を生成してもよい。 Specifically, the existing work information acquisition unit 124 acquires the process information and worker information generated by the above-mentioned method through the interface unit 18. The existing work information acquisition unit 124 also stores the acquired process information and worker information in the process information storage unit 102 and the worker information storage unit 104, respectively. Then, when processing is performed by the process determination unit 130 and the calculation unit 140 described below, the existing work information acquisition unit 124 extracts (acquires) the process information and worker information stored in the process information storage unit 102 and the worker information storage unit 104, respectively. Note that the existing work information acquisition unit 124 may generate worker information by executing the above-mentioned motion capture and machine learning algorithms, etc.

工程決定部130は、複数の工程のうちの、要素作業が再配置される工程である再配置工程を決定する。算出部140は、追加作業時間及び要素作業時間に基づいて、追加作業を複数の工程の少なくとも1つの工程に追加して工程間で要素作業を再配置して、追加作業及び複数の要素作業の組み合わせを算出する。その際に、算出部140は、複数の工程それぞれの作業時間のうちの最大作業時間がより小さくなるように、追加作業及び複数の要素作業の組み合わせを算出する。なお、好ましくは、算出部140は、最大作業時間が最小となるように、追加作業及び複数の要素作業の組み合わせを算出する。 The process determination unit 130 determines a rearrangement process, which is a process among the multiple processes to which element work is rearranged. The calculation unit 140 adds the additional work to at least one of the multiple processes based on the additional work time and the element work time, and rearranges the element work between the processes to calculate a combination of the additional work and the multiple element work. In this case, the calculation unit 140 calculates the combination of the additional work and the multiple element work so that the maximum work time among the work times of each of the multiple processes is smallest. Preferably, the calculation unit 140 calculates the combination of the additional work and the multiple element work so that the maximum work time is smallest.

判定部150は、算出された組み合わせが適切であるか否かを判定する。具体的には、判定部150は、算出部140によって算出された組み合わせにおける最大作業時間がタクトタイム以下であるか否かを判定する。そして、判定部150は、最大作業時間がタクトタイム以下である場合に、その組み合わせが適切であると判定する。一方、判定部150は、最大作業時間がタクトタイムを超える場合に、その組み合わせが適切でないと判定する。その場合、工程決定部130は、再配置工程を変更する。そして、算出部140は、変更された再配置工程について、上述したように、追加作業及び複数の要素作業の組み合わせを算出する。詳しくは後述する。 The determination unit 150 determines whether the calculated combination is appropriate. Specifically, the determination unit 150 determines whether the maximum work time in the combination calculated by the calculation unit 140 is equal to or less than the takt time. Then, if the maximum work time is equal to or less than the takt time, the determination unit 150 determines that the combination is appropriate. On the other hand, if the maximum work time exceeds the takt time, the determination unit 150 determines that the combination is inappropriate. In that case, the process determination unit 130 changes the rearrangement process. Then, the calculation unit 140 calculates a combination of additional work and multiple elemental work for the changed rearrangement process, as described above. This will be described in detail later.

表示制御部160は、算出された各工程の要素作業が表示されるように、制御を行う。具体的には、表示制御部160は、インタフェース部18を制御して、工程ごとに、算出された組み合わせの要素作業を提示する。これにより、出力デバイスであるインタフェース部18に、各工程の要素作業が表示(出力)される。 The display control unit 160 controls the display so that the calculated element work for each process is displayed. Specifically, the display control unit 160 controls the interface unit 18 to present the calculated combination of element work for each process. This causes the element work for each process to be displayed (output) on the interface unit 18, which is an output device.

ここで、工程決定部130及び算出部140について、具体的に説明する。
工程決定部130は、複数の工程のうち、要素作業が再配置される工程である再配置工程を決定する。つまり、工程決定部130は、再配置がなされる工程の範囲を決定する。ここで、複数の工程が、再配置工程となり得る。そして、再配置工程は、後述する算出部140における処理の対象となる工程となる。つまり、複数の工程の間で、要素作業が再配置される。詳しくは後述する。
Here, the process determination unit 130 and the calculation unit 140 will be specifically described.
The process determination unit 130 determines, among the multiple processes, a rearrangement process, which is a process to which element work is rearranged. In other words, the process determination unit 130 determines the range of processes to be rearranged. Here, multiple processes can become rearrangement processes. The rearrangement processes become processes that are the targets of processing by the calculation unit 140, which will be described later. In other words, element work is rearranged between multiple processes. This will be described in detail later.

工程決定部130は、まず、基準工程を決定する。基準工程は、追加作業が配置される工程に対応する。基準工程は、例えば、不具合が発生した工程に対応してもよい。つまり、例えば図1等の例において工程Cで不具合が発生して追加作業が必要となった場合、工程決定部130は、工程Cを基準工程と決定してもよい。 The process determination unit 130 first determines a reference process. The reference process corresponds to a process in which additional work is assigned. The reference process may correspond to, for example, a process in which a defect occurs. That is, for example, in the example of FIG. 1, if a defect occurs in process C and additional work becomes necessary, the process determination unit 130 may determine process C as the reference process.

工程決定部130は、次に、基準工程を含む再配置工程を決定する。具体的には、工程決定部130は、基準工程を含む連続する2つ以上の数(Nとする)の工程を、再配置工程と決定する。例えば、工程数Nの初期値を3とすると、工程決定部130は、図1等の例において工程Cが基準工程である場合に、工程B、工程C及び工程Dを、再配置工程と決定してもよいし、工程A、工程B及び工程Cを、再配置工程と決定してもよい。なお、Nの初期値は、2であってもよいし、4以上であってもよい。 The process determination unit 130 then determines rearrangement processes including the reference process. Specifically, the process determination unit 130 determines two or more consecutive processes (defined as N) including the reference process as rearrangement processes. For example, if the initial value of the number of processes N is 3, then in the example shown in FIG. 1 etc., when process C is the reference process, the process determination unit 130 may determine processes B, C, and D as rearrangement processes, or may determine processes A, B, and C as rearrangement processes. Note that the initial value of N may be 2, or 4 or more.

そして、決定された再配置工程について、後述する算出部140によって、要素作業の再配置が行われて、追加作業及び複数の要素作業の組み合わせが算出される。そして、判定部150によって、算出された組み合わせが適切でないと判定された場合に、工程決定部130は、再配置工程を変更する。この場合、工程決定部130は、まずは、以前の決定処理で決定された再配置工程における工程数(N)を変えないで、基準工程を含む再配置工程を変更する。例えば、上記の例において、工程決定部130は、工程C、工程D及び工程Eを、再配置工程と決定してもよい。 Then, for the determined rearrangement process, the calculation unit 140, which will be described later, rearranges the element work and calculates a combination of additional work and multiple element work. Then, if the judgment unit 150 determines that the calculated combination is not appropriate, the process determination unit 130 changes the rearrangement process. In this case, the process determination unit 130 first changes the rearrangement process including the reference process without changing the number of processes (N) in the rearrangement process determined in the previous determination process. For example, in the above example, the process determination unit 130 may determine processes C, D, and E as the rearrangement processes.

そして、基準工程を含む連続するN個の工程からなる再配置工程の全ての取り得るパターンについて、算出部140によって算出された組み合わせが、判定部150によって適切でないと判定されたとする。この場合、工程決定部130は、再配置工程の工程数Nを1つインクリメントする。つまり、工程決定部130は、基準工程を含む連続するN+1個の工程を、再配置工程と決定する。例えば、上記の例において、工程決定部130は、4個の工程A、工程B、工程C及び工程Dを、再配置工程と決定してもよい。以後、判定部150によって組み合わせが適切でないと判定されるごとに、工程決定部130は、同様の処理を繰り返すことによって、再配置工程を変更する。 Then, assume that the combinations calculated by the calculation unit 140 for all possible patterns of rearrangement processes consisting of N consecutive processes including the reference process are determined by the determination unit 150 to be inappropriate. In this case, the process determination unit 130 increments the number of processes N of the rearrangement processes by one. In other words, the process determination unit 130 determines the N+1 consecutive processes including the reference process as the rearrangement processes. For example, in the above example, the process determination unit 130 may determine the four processes A, B, C, and D as the rearrangement processes. Thereafter, each time the determination unit 150 determines that the combination is inappropriate, the process determination unit 130 changes the rearrangement processes by repeating the same process.

図8は、実施の形態1にかかる工程決定部130の処理を説明するための図である。図8の例において、工程決定部130は、工程Cを基準工程と決定する。そして、再配置工程の工程数Nの初期値を3とする。この場合、まず、工程決定部130は、基準工程である工程Cとその前の2つの工程とを含む、N=3個の工程A、工程B及び工程Cを、パターン#1-1の再配置工程と決定する。 Figure 8 is a diagram for explaining the processing of the process determination unit 130 according to the first embodiment. In the example of Figure 8, the process determination unit 130 determines process C as the reference process. The initial value of the number of processes N of the rearrangement process is set to 3. In this case, the process determination unit 130 first determines N = 3 processes A, B, and C, including the reference process C and the two processes preceding it, as the rearrangement processes of pattern #1-1.

そして、このパターン#1-1の再配置工程について算出された要素作業の組み合わせが適切でないと判定されたとする。この場合、工程決定部130は、基準工程である工程Cとその前の1つの工程及び工程Cの後の1つの工程とを含む、N=3個の工程B、工程C及び工程Dを、パターン#1-2の再配置工程と決定する。つまり、工程決定部130は、パターン#1-1の再配置工程から後工程に工程範囲を1つシフトした、3個の工程B、工程C及び工程Dを、パターン#1-2の再配置工程と決定する。 And then, suppose that it is determined that the combination of element tasks calculated for the rearrangement process of this pattern #1-1 is inappropriate. In this case, the process determination unit 130 determines N=3 processes B, C, and D, including the reference process C, one process before it, and one process after process C, as the rearrangement processes of pattern #1-2. In other words, the process determination unit 130 determines the three processes B, C, and D, which are shifted one process range from the rearrangement process of pattern #1-1 to the subsequent process, as the rearrangement processes of pattern #1-2.

そして、このパターン#1-2の再配置工程について算出された要素作業の組み合わせが適切でないと判定されたとする。この場合、工程決定部130は、基準工程である工程Cとその後の2つの工程とを含む、N=3個の工程C、工程D及び工程Eを、パターン#1-3の再配置工程と決定する。つまり、工程決定部130は、パターン#1-2の再配置工程から後工程に工程範囲を1つシフトした、3個の工程C、工程D及び工程Eを、パターン#1-3の再配置工程と決定する。 And then, suppose that it is determined that the combination of element tasks calculated for the rearrangement process of pattern #1-2 is inappropriate. In this case, the process determination unit 130 determines N=3 processes C, D, and E, including the reference process C and the two processes following it, as the rearrangement processes of pattern #1-3. In other words, the process determination unit 130 determines the three processes C, D, and E, which are shifted one process range from the rearrangement process of pattern #1-2 to the subsequent process, as the rearrangement processes of pattern #1-3.

そして、このパターン#1-3の再配置工程について算出された要素作業の組み合わせが適切でないと判定されたとする。この場合、工程決定部130は、工程数N=3の取り得る全てのパターンの再配置工程について、要素作業の組み合わせが適切とはならなかったと判定する。この場合、工程決定部130は、工程数Nを1つインクリメントして、工程数N=4とする。そして、工程決定部130は、基準工程である工程Cとその前の2つの工程及び工程Cの後の1つの工程とを含む、N=4個の工程A、工程B、工程C及び工程Dを、パターン#2-1の再配置工程と決定する。 Then, suppose that it is determined that the combination of element tasks calculated for the rearrangement process of this pattern #1-3 is inappropriate. In this case, the process determination unit 130 determines that the combination of element tasks is not appropriate for the rearrangement processes of all possible patterns with the number of processes N=3. In this case, the process determination unit 130 increments the number of processes N by one to make the number of processes N=4. The process determination unit 130 then determines N=4 processes A, B, C, and D, including the reference process C, the two processes before it, and the one process after process C, as the rearrangement processes of pattern #2-1.

そして、このパターン#2-1の再配置工程について算出された要素作業の組み合わせが適切でないと判定されたとする。この場合、工程決定部130は、基準工程である工程Cとその前の1つの工程及び工程Cの後の2つの工程とを含む、N=4個の工程B、工程C、工程D及び工程Eを、パターン#2-2の再配置工程と決定する。つまり、工程決定部130は、パターン#2-1の再配置工程から後工程に工程範囲を1つシフトした、4個の工程B、工程C、工程D及び工程Eを、パターン#2-2の再配置工程と決定する。なお、工程Aが最初の工程なので、パターン#2-1から前工程に工程範囲をシフトすることはできない。 And then, suppose that it is determined that the combination of element tasks calculated for the rearrangement process of this pattern #2-1 is inappropriate. In this case, the process determination unit 130 determines N=4 processes B, C, D, and E, including the reference process C, the one process before it, and the two processes after process C, as the rearrangement processes of pattern #2-2. In other words, the process determination unit 130 determines the four processes B, C, D, and E, which are obtained by shifting the process range from the rearrangement process of pattern #2-1 by one to the subsequent process, as the rearrangement processes of pattern #2-2. Note that since process A is the first process, it is not possible to shift the process range from pattern #2-1 to the previous process.

そして、このパターン#2-2の再配置工程について算出された要素作業の組み合わせが適切でないと判定されたとする。この場合、工程決定部130は、基準工程である工程Cとその後の3つの工程とを含む、N=4個の工程C、工程D、工程E及び工程Fを、パターン#2-3の再配置工程と決定する。つまり、工程決定部130は、パターン#2-2の再配置工程から後工程に工程範囲を1つシフトした、4個の工程C、工程D、工程E及び工程Fを、パターン#2-3の再配置工程と決定する。 And then, suppose that it is determined that the combination of element tasks calculated for the rearrangement process of pattern #2-2 is inappropriate. In this case, the process determination unit 130 determines N=4 processes C, D, E, and F, including the reference process C and the three processes following it, as the rearrangement processes of pattern #2-3. In other words, the process determination unit 130 determines the four processes C, D, E, and F, which are shifted one process range from the rearrangement process of pattern #2-2 to the subsequent process, as the rearrangement processes of pattern #2-3.

そして、このパターン#2-3の再配置工程について算出された要素作業の組み合わせが適切でないと判定されたとする。この場合、工程決定部130は、工程数N=4の取り得る全てのパターンの再配置工程について、要素作業の組み合わせが適切とはならなかったと判定する。この場合、工程決定部130は、工程数Nを1つインクリメントして、工程数N=5とする。そして、工程決定部130は、基準工程である工程Cとその前の2つの工程及び工程Cの後の2つの工程とを含む、N=5個の工程A、工程B、工程C、工程D及び工程Eを、パターン#3-1の再配置工程と決定する。以後同様にして、工程決定部130は、判定部150によって組み合わせが適切でないと判定されるごとに、再配置工程を変更する。 Then, suppose that the combination of element tasks calculated for the rearrangement process of this pattern #2-3 is determined to be inappropriate. In this case, the process determination unit 130 determines that the combination of element tasks is not appropriate for the rearrangement processes of all possible patterns with the number of processes N=4. In this case, the process determination unit 130 increments the number of processes N by one to make the number of processes N=5. The process determination unit 130 then determines N=5 processes A, B, C, D, and E, including the reference process C, the two processes before it, and the two processes after process C, as the rearrangement processes of pattern #3-1. Thereafter, the process determination unit 130 similarly changes the rearrangement processes each time the determination unit 150 determines that the combination is inappropriate.

なお、工程決定部130が再配置工程のパターンを決定する順序は、図8の例に限られない。例えば、工程数が同じ再配置工程のパターンであれば、これらのパターンの順序は、任意であってもよい。また、図8の例では、工程決定部130は、再配置工程の工程範囲を後工程に1つずつシフトしているが、再配置工程の工程範囲を前工程に1つずつシフトしてもよい。 The order in which the process determination unit 130 determines the rearrangement process patterns is not limited to the example in FIG. 8. For example, if the rearrangement process patterns have the same number of processes, the order of these patterns may be arbitrary. In addition, in the example in FIG. 8, the process determination unit 130 shifts the process range of the rearrangement process one by one to the later process, but the process range of the rearrangement process may also be shifted one by one to the earlier process.

算出部140(図3)は、上述したように、追加作業が基準工程に追加された再配置工程において工程間で要素作業を再配置して、各工程の作業時間の最大作業時間がより小さくなるような要素作業の組み合わせを算出する。つまり、算出部140は、再配置工程において工程間で要素作業を再配置して、各工程の作業時間が平滑化されるような要素作業の組み合わせを算出する。以下、算出部140が、各工程の作業時間のうちの最大作業時間が最小となるような要素作業の組み合わせを算出する具体的な方法について、説明する。 As described above, the calculation unit 140 (FIG. 3) rearranges the element tasks between processes in the rearrangement process in which the additional task is added to the reference process, and calculates a combination of element tasks that reduces the maximum task time of each process. In other words, the calculation unit 140 rearranges the element tasks between processes in the rearrangement process, and calculates a combination of element tasks that smooths the task time of each process. Below, a specific method is described in which the calculation unit 140 calculates a combination of element tasks that minimizes the maximum task time of the task time of each process.

算出部140は、再配置工程における各工程に割り当てられた作業者の、対応する工程の各要素作業の実作業時間(要素作業時間)から、再配置工程における各工程の作業時間を算出する。具体的には、算出部140は、割り当てられた作業者について対応する工程の各要素作業の実作業時間を合計することにより、各工程の作業時間を算出する。例えば、再配置工程が工程A~工程Cであり、工程Aに作業者#1が割り当てられたとすると、算出部140は、作業者#1の工程Aの各要素作業A1~A5に関する実作業時間を合計することによって、工程Aの作業時間を算出する。なお、算出部140は、各工程に割り当てられた作業者のスキルに合わせて、各工程の各要素作業の標準作業時間を変更することによって、各工程の作業時間を算出してもよい。 The calculation unit 140 calculates the work time of each process in the rearrangement process from the actual work time (element work time) of each element work of the corresponding process by the worker assigned to each process in the rearrangement process. Specifically, the calculation unit 140 calculates the work time of each process by summing up the actual work time of each element work of the corresponding process for the assigned worker. For example, if the rearrangement process is process A to process C, and worker #1 is assigned to process A, the calculation unit 140 calculates the work time of process A by summing up the actual work time of worker #1 for each element work A1 to A5 of process A. Note that the calculation unit 140 may calculate the work time of each process by changing the standard work time of each element work of each process to match the skill of the worker assigned to each process.

そして、算出部140は、追加作業が配置された基準工程の作業時間を算出する。具体的には、算出部140は、上記の方法により算出された、追加作業の配置前の基準工程の作業時間に、追加作業時間を加算することによって、追加作業が配置された基準工程の作業時間を算出する。例えば、算出部140は、工程Cが基準工程である場合、工程Cの作業時間に追加作業時間を加算して、追加作業が配置された工程Cの作業時間を算出する。 Then, the calculation unit 140 calculates the work time of the reference process in which the additional work has been assigned. Specifically, the calculation unit 140 calculates the work time of the reference process in which the additional work has been assigned by adding the additional work time to the work time of the reference process before the additional work has been assigned, which is calculated by the above method. For example, when process C is the reference process, the calculation unit 140 calculates the work time of process C in which the additional work has been assigned by adding the additional work time to the work time of process C.

なお、追加作業が配置された基準工程の作業時間がタクトタイム以下である場合、算出部140は、再配置処理を行わなくてもよい。つまり、追加作業が配置されていない各工程の作業時間はタクトタイム以下であるので、追加作業が配置された基準工程の作業時間がタクトタイム以下であれば、各工程の作業時間は、全て、タクトタイム以下となる。したがって、この場合、算出部140は、単に基準工程に追加作業を配置するだけで、要素作業の組み合わせが適切であるとして、処理を終了してもよい。この場合、算出部140が再配置処理を行う前に、判定部150が、追加作業が配置された基準工程の作業時間がタクトタイム以下であるか否かを判定してもよい。 Note that if the operation time of the reference process in which the additional work is placed is equal to or less than the takt time, the calculation unit 140 does not need to perform the rearrangement process. In other words, since the operation time of each process in which no additional work is placed is equal to or less than the takt time, if the operation time of the reference process in which the additional work is placed is equal to or less than the takt time, the operation time of each process will all be equal to or less than the takt time. Therefore, in this case, the calculation unit 140 may simply place the additional work in the reference process and terminate the process, determining that the combination of element operations is appropriate. In this case, before the calculation unit 140 performs the rearrangement process, the determination unit 150 may determine whether the operation time of the reference process in which the additional work is placed is equal to or less than the takt time.

一方、各工程の作業時間がタクトタイムよりもかなり短い、つまり、作業時間とタクトタイムとの間に余裕があると、その工程ではアイドル時間が発生してしまう。したがって、工程における実際の作業時間とタクトタイムとの差があまりない方が、生産性は向上することが多い。したがって、既存の生産ラインでは、ある工程に余裕があるようには計画されていないことが多い。したがって、追加作業が基準工程に配置された場合の基準工程の作業時間は、追加作業時間があまりにも小さくない限り、タクトタイムを超える可能性が高い。 On the other hand, if the working time of each process is much shorter than the takt time, that is, if there is a margin between the working time and the takt time, idle time will occur in that process. Therefore, productivity often improves when there is little difference between the actual working time in a process and the takt time. For this reason, existing production lines are often not planned so that certain processes have margins. Therefore, when additional work is placed in a reference process, the working time of the reference process is likely to exceed the takt time, unless the additional work time is too small.

そして、算出部140は、再配置工程において工程間で要素作業を再配置して、要素作業の組み合わせを算出する。このとき、算出部140は、後述する制約条件(制限)の下で、再配置工程の要素作業の再配置処理(組み合わせの算出)を行う。その際に、算出部140は、制約条件の下で取り得る全ての組み合わせについて、再配置工程の要素作業の再配置処理を行ってもよい。再配置処理は、例えば、工程間で2つ以上の要素作業を互いに入れ替える(交換する)処理と、ある工程の要素作業を他の工程に移動させる(移転する)処理とを含む。 The calculation unit 140 then rearranges the element tasks between processes in the rearrangement process to calculate a combination of element tasks. At this time, the calculation unit 140 performs a rearrangement process (calculation of combinations) of the element tasks of the rearrangement process under the constraint conditions (restrictions) described below. At this time, the calculation unit 140 may perform a rearrangement process of the element tasks of the rearrangement process for all combinations that are possible under the constraint conditions. The rearrangement process includes, for example, a process of swapping (exchanging) two or more element tasks between processes and a process of moving (transferring) an element task of one process to another process.

ここで、算出部140は、制限情報に示される制約条件に反するような再配置を行わないようにする。つまり、算出部140は、以下のように、制限情報(工程設備情報及び前後作業制限情報)に基づいて、要素作業の組み合わせを算出する。 Here, the calculation unit 140 avoids rearrangement that violates the constraints indicated in the restriction information. In other words, the calculation unit 140 calculates the combination of element tasks based on the restriction information (process equipment information and pre- and post-task restriction information) as follows:

算出部140は、工程設備情報を用いて、各要素作業を実行可能な設備を判定する。そして、算出部140は、再配置処理(組み合わせの算出)において、ある要素作業を実行可能な設備が使用されていない工程に、その要素作業を再配置(移転)しないようにする。例えば、図5及び図6の例において、要素作業C5が工程Bで使用されている設備で実行できない場合、算出部140は、要素作業C5を工程Bに移転しないようにし、要素作業C5を工程Bの要素作業と交換しないようにする。 The calculation unit 140 uses the process equipment information to determine the equipment capable of performing each element work. Then, in the rearrangement process (combination calculation), the calculation unit 140 prevents an element work from being rearranged (transferred) to a process where equipment capable of performing that element work is not being used. For example, in the examples of Figures 5 and 6, if element work C5 cannot be performed by the equipment used in process B, the calculation unit 140 prevents element work C5 from being transferred to process B and prevents element work C5 from being exchanged with an element work of process B.

また、算出部140は、前後作業制限情報を用いて、各要素作業に前後作業制限が設定されているか否かを判定する。そして、算出部140は、再配置処理(組み合わせの算出)において、前後作業制限が設定されている要素作業については、前後作業制限に反するような要素作業の配置となるように再配置を行わないようにする。例えば、ある要素作業について、その要素作業よりも前に実行されていなければならない要素作業又は工程(前作業)が設定されている場合、算出部140は、その要素作業を、前作業よりも前に再配置(移転)しないようにする。例えば、図5及び図6の例において、要素作業C4よりも前に要素作業A4が実行されていなければならない場合、算出部140は、要素作業C4を、前作業である要素作業A4よりも前に再配置しないようにする。 The calculation unit 140 also uses the pre- and post-task restriction information to determine whether or not a pre- and post-task restriction is set for each element task. In the rearrangement process (combination calculation), the calculation unit 140 does not rearrange an element task for which a pre- and post-task restriction is set, so that the element task is arranged in a manner that violates the pre- and post-task restriction. For example, when an element task or process (previous task) that must be performed before a certain element task is set, the calculation unit 140 does not rearrange (move) the element task before the previous task. For example, in the examples of Figures 5 and 6, when element task A4 must be performed before element task C4, the calculation unit 140 does not rearrange element task C4 before the previous task, element task A4.

また、例えば、ある要素作業について、その要素作業よりも後に実行されなければならない要素作業又は工程(後作業)が設定されている場合、算出部140は、その要素作業を、後作業よりも後に再配置(移転)しないようにする。例えば、図5及び図6の例において、要素作業B3よりも後に要素作業C2が実行されなければならない場合、算出部140は、要素作業B3を要素作業C2よりも後に再配置しないようにする。なお、算出部140は、前後作業制限が設定されている要素作業を、再配置の対象としないようにしてもよい。つまり、上記の例では、算出部140は、要素作業C4及び要素作業A4、並びに、要素作業B3及び要素作業C2を、再配置の対象としない、つまり移転しないようにしてもよい。 For example, when an element task or process (post-task) is set for a certain element task that must be executed after the element task, the calculation unit 140 does not rearrange (move) the element task after the post-task. For example, in the examples of Figures 5 and 6, when element task C2 must be executed after element task B3, the calculation unit 140 does not rearrange element task B3 after element task C2. Note that the calculation unit 140 may not treat element tasks for which pre- or post-task restrictions are set as targets for rearrangement. In other words, in the above example, the calculation unit 140 may not treat element tasks C4 and A4, as well as element tasks B3 and C2 as targets for rearrangement, i.e., may not relocate them.

また、制約条件として、再配置される要素作業の数に制限を設けてもよい。つまり、算出部140は、設定された数よりも多い数の要素作業を、再配置の対象としないようにしてもよい。例えば、再配置される要素作業の数の制限が「6」である場合、算出部140は、7個以上の要素作業を再配置(移転)しないようにしてもよい。このような構成により、なるべく要素作業を再配置しないで、適切な組み合わせを算出することが可能となる。ここで、再配置される要素作業の数が多いと、作業者が要素作業を行うにあたり困惑するおそれがある。したがって、なるべく要素作業を再配置しないようにすることにより、作業者の困惑を抑制することが可能となる。 In addition, a limit may be set on the number of element tasks to be rearranged as a constraint. In other words, the calculation unit 140 may not rearrange a number of element tasks greater than a set number. For example, if the limit on the number of element tasks to be rearranged is "6", the calculation unit 140 may not rearrange (transfer) seven or more element tasks. With this configuration, it becomes possible to calculate an appropriate combination without rearranging element tasks as much as possible. Here, if there are a large number of element tasks to be rearranged, there is a risk that the worker will be confused when performing the element tasks. Therefore, by avoiding rearranging element tasks as much as possible, it becomes possible to reduce worker confusion.

そして、算出部140は、1つの組み合わせが算出されると、その組み合わせについて、要素作業が再配置された各工程の作業時間のうちの最大作業時間を算出する。具体的には、算出部140は、要素作業が再配置された各工程について、その工程に含まれる要素作業(及び追加作業)の実作業時間(要素作業時間)の合計を算出することによって、その工程の作業時間を算出する。 When one combination is calculated, the calculation unit 140 calculates the maximum work time of each process in which the element work has been rearranged for that combination. Specifically, the calculation unit 140 calculates the work time of each process in which the element work has been rearranged by calculating the sum of the actual work times (element work times) of the element work (and additional work) included in that process.

なお、各工程の作業時間を算出する際に、算出部140は、要素作業が再配置された工程の作業を行う作業者のスキルに合わせて、再配置された要素作業の要素作業時間(実作業時間)を変更してもよい。つまり、算出部140は、要素作業が再配置された工程の作業時間を算出する際に、その工程の作業を行う作業者の、再配置された要素作業に関する実作業時間を加算してもよい。例えば、図5及び図6の例において、要素作業A5と要素作業C5とが交換された場合、算出部140は、工程Aの作業時間を算出する際に、工程Aに割り当てられた作業者の、要素作業C5の実作業時間を用いてもよい。同様に、算出部140は、工程Cの作業時間を算出する際に、工程Cに割り当てられた作業者の、要素作業A5の実作業時間を用いてもよい。 When calculating the work time of each process, the calculation unit 140 may change the element work time (actual work time) of the rearranged element work in accordance with the skill of the worker performing the work of the process to which the element work has been rearranged. In other words, when calculating the work time of a process to which an element work has been rearranged, the calculation unit 140 may add the actual work time of the rearranged element work of the worker performing the work of the process. For example, in the examples of Figures 5 and 6, if element work A5 and element work C5 are exchanged, the calculation unit 140 may use the actual work time of element work C5 of the worker assigned to process A when calculating the work time of process A. Similarly, the calculation unit 140 may use the actual work time of element work A5 of the worker assigned to process C when calculating the work time of process C.

そして、算出部140は、上述した方法と同様にして、次の組み合わせを算出して、その組み合わせについての最大作業時間を算出する。そして、取り得る全ての組み合わせが算出されると、算出部140は、算出された全ての組み合わせのうち、最大作業時間が最小となる組み合わせを決定する。このようにして、算出部140は、各工程の作業時間のうちの最大作業時間が最小となるような要素作業の組み合わせを算出する。 Then, the calculation unit 140 calculates the next combination in the same manner as described above, and calculates the maximum work time for that combination. Then, when all possible combinations have been calculated, the calculation unit 140 determines the combination that has the smallest maximum work time from among all the calculated combinations. In this way, the calculation unit 140 calculates a combination of element tasks that will minimize the maximum work time among the work times of each process.

なお、上述した方法では、算出部140は、各工程の作業時間のうちの最大作業時間が最小となるような要素作業の組み合わせを算出するとしたが、このような構成に限られない。算出部140は、ある組み合わせについて、その組み合わせにおける最大作業時間がタクトタイム以下である場合に、組み合わせ算出処理(再配置処理)を終了してもよい。そして、算出部140は、その、最大作業時間がタクトタイム以下である組み合わせを、表示制御部160によって表示される要素作業の組み合わせと決定してもよい。この場合、判定部150は、処理を行わなくてもよい。 In the above-described method, the calculation unit 140 calculates a combination of element tasks that minimizes the maximum task time of each process, but this is not limited to the above configuration. The calculation unit 140 may end the combination calculation process (rearrangement process) when the maximum task time for a certain combination is equal to or less than the takt time. The calculation unit 140 may then determine that the combination whose maximum task time is equal to or less than the takt time is the combination of element tasks to be displayed by the display control unit 160. In this case, the determination unit 150 does not need to perform any processing.

また、算出部140は、ある組み合わせについて、その組み合わせにおける最大作業時間と各工程の作業時間の平均値との差が予め定められた閾値以下である場合に、組み合わせ算出処理(再配置処理)を終了してもよい。そして、算出部140は、その、最大作業時間と平均値との差が閾値以下である組み合わせを、判定部150による判定対象の組み合わせと決定してもよい。この場合、閾値は、例えば、数秒(1~2秒等)であってもよい。 The calculation unit 140 may also terminate the combination calculation process (relocation process) when the difference between the maximum work time in a certain combination and the average work time of each process is equal to or less than a predetermined threshold. The calculation unit 140 may then determine that the combination in which the difference between the maximum work time and the average is equal to or less than the threshold is the combination to be judged by the judgment unit 150. In this case, the threshold may be, for example, a few seconds (1 to 2 seconds, etc.).

上述したように、最大作業時間が最小となるような要素作業の組み合わせを算出するためには、制約条件の下で算出可能な全ての組み合わせを算出する必要がある。その場合、全ての組み合わせを算出するために、多くの時間及び多くの処理負荷を要する可能性がある。これに対し、最大作業時間がタクトタイム以下である組み合わせ、又は、最大作業時間と平均値との差が閾値以下である組み合わせが算出された時点で処理を終了することによって、処理負荷を低減することが可能となる。すなわち、なるべく少ない再配置回数で、適切な組み合わせを算出することが可能となる。一方、最大作業時間が最小となるような要素作業の組み合わせを算出することによって、最適な組み合わせが算出され得る。すなわち、各工程の作業時間がより平滑化された組み合わせが算出され得る。 As described above, in order to calculate a combination of element tasks that minimizes the maximum work time, it is necessary to calculate all combinations that are calculable under the constraints. In that case, it may take a lot of time and a large processing load to calculate all the combinations. In contrast, it is possible to reduce the processing load by terminating the process when a combination is calculated in which the maximum work time is equal to or less than the takt time, or a combination in which the difference between the maximum work time and the average work time is equal to or less than a threshold value. In other words, it is possible to calculate an appropriate combination with as few rearrangements as possible. On the other hand, an optimal combination can be calculated by calculating a combination of element tasks that minimizes the maximum work time. In other words, a combination in which the work time of each process is more smoothed can be calculated.

なお、算出部140は、要素作業の組み合わせを算出する際に、組み合わせ最適化を実現可能な人工知能(AI:Artificial Intelligence)を用いてもよい。例えば、算出部140は、強化学習アルゴリズムを用いて、要素作業の組み合わせを算出してもよい。また、算出部140は、遺伝的アルゴリズム又は貪欲法等のアルゴリズムを用いて、要素作業の組み合わせを算出してもよい。 When calculating the combination of elemental tasks, the calculation unit 140 may use artificial intelligence (AI) capable of achieving combinatorial optimization. For example, the calculation unit 140 may use a reinforcement learning algorithm to calculate the combination of elemental tasks. The calculation unit 140 may also use an algorithm such as a genetic algorithm or a greedy algorithm to calculate the combination of elemental tasks.

なお、再配置工程の各工程の作業時間の合計が、タクトタイムを再配置工程の工程数Nで乗算して得られた値(タクトタイム×N)を超える場合、どのような要素作業の組み合わせであっても、最大作業時間がタクトタイム以下となることはない。したがって、この場合、算出部140は、再配置処理を行わないで、工程決定部130は、工程を変更してもよい。 Note that if the total working time of each process in the rearrangement process exceeds the value obtained by multiplying the takt time by the number of processes N in the rearrangement process (takt time x N), the maximum working time will never be less than the takt time, regardless of the combination of element tasks. Therefore, in this case, the calculation unit 140 may not perform the rearrangement process, and the process determination unit 130 may change the process.

図9は、実施の形態1にかかる工程管理システム1によって実行される工程管理方法を示すフローチャートである。取得部120は、追加作業情報及び既存作業情報を取得する。つまり、追加作業情報取得部122は、追加作業の作業時間及び作業種別を取得する(ステップS102)。また、既存作業情報取得部124は、工程情報及び作業者情報を取得する(ステップS104)。 Figure 9 is a flowchart showing a process management method executed by the process management system 1 according to the first embodiment. The acquisition unit 120 acquires additional work information and existing work information. That is, the additional work information acquisition unit 122 acquires the work time and work type of the additional work (step S102). In addition, the existing work information acquisition unit 124 acquires process information and worker information (step S104).

工程決定部130は、上述したように、再配置工程を決定する(ステップS106)。算出部140は、上述したように、追加作業時間及び要素作業時間に基づいて、追加作業及び複数の要素作業の組み合わせを算出する(ステップS108)。その際に、上述したように、算出部140は、各工程の作業時間のうちの最大作業時間が最小となるように、要素作業の組み合わせを算出する。つまり、算出部140は、各工程の作業時間のうちの最大作業時間が最小となるように、要素作業の組み合わせの算出を繰り返す。 The process determination unit 130 determines the rearrangement process as described above (step S106). The calculation unit 140 calculates a combination of the additional work and multiple element work based on the additional work time and the element work time as described above (step S108). In doing so, as described above, the calculation unit 140 calculates a combination of element work so that the maximum work time among the work times of each process is minimized. In other words, the calculation unit 140 repeatedly calculates the combination of element work so that the maximum work time among the work times of each process is minimized.

判定部150は、上述したように、算出された組み合わせについての最大作業時間がタクトタイム以下であるか否かを判定する(ステップS110)。最大作業時間がタクトタイム以下である場合(S110のYES)、表示制御部160は、S108で算出された組み合わせに関する各工程の要素作業を表示するように、制御を行う(ステップS112)。一方、最大作業時間がタクトタイム以下でない、つまり最大作業時間がタクトタイムを超える場合(S110のNO)、処理フローはS106に戻る。そして、工程決定部130は、上述したように、再配置工程を変更する、つまり、他の再配置工程を決定する(S106)。そして、算出部140は、変更された再配置工程について、追加作業及び複数の要素作業の組み合わせを算出する(S108)。そして、判定部150は、再度、算出された組み合わせについての最大作業時間がタクトタイム以下であるか否かを判定する(S110)。以下、同様の処理が繰り返される。 As described above, the determination unit 150 determines whether the maximum work time for the calculated combination is equal to or less than the takt time (step S110). If the maximum work time is equal to or less than the takt time (YES in S110), the display control unit 160 controls the display of the element work of each process related to the combination calculated in S108 (step S112). On the other hand, if the maximum work time is not equal to or less than the takt time, that is, if the maximum work time exceeds the takt time (NO in S110), the process flow returns to S106. Then, the process determination unit 130 changes the rearrangement process, that is, determines another rearrangement process (S106), as described above. Then, the calculation unit 140 calculates a combination of additional work and multiple element works for the changed rearrangement process (S108). Then, the determination unit 150 again determines whether the maximum work time for the calculated combination is equal to or less than the takt time (S110). The same process is repeated thereafter.

<具体例>
次に、具体例を用いて、実施の形態1にかかる工程管理システム1の処理について説明する。
図10~図14は、実施の形態1にかかる工程管理システム1が、追加作業が発生した場合に再配置処理を行う方法を説明するための図である。図10~図14は、図5及び図6の例における生産ラインにおいて、工程Cに追加作業が発生した場合の例について示している。この場合、工程決定部130は、工程Cを基準工程と決定する。
<Specific examples>
Next, the processing of the process control system 1 according to the first embodiment will be described using a specific example.
10 to 14 are diagrams for explaining a method in which the process control system 1 according to the first embodiment performs a rearrangement process when additional work occurs. Figures 10 to 14 show an example in which additional work occurs in process C in the production line in the examples of Figures 5 and 6. In this case, the process determination unit 130 determines process C as the reference process.

図10は、各工程に作業者が割り当てられた場合の各要素作業の実作業時間を例示する図である。また、図11は、図10の例において、工程ごとに要素作業時間を積み上げて各工程の作業時間を示した図である。なお、図5及び図6の例と同様に、タクトタイムは32秒である。また、図6の場合と同様に、図11において、各工程の各要素作業の長さは、その要素作業の要素作業時間(実作業時間)に対応する。 Figure 10 is a diagram illustrating the actual work time of each element work when a worker is assigned to each process. Also, Figure 11 is a diagram showing the work time of each process in the example of Figure 10 by accumulating the element work time for each process. Note that, as with the examples of Figures 5 and 6, the takt time is 32 seconds. Also, as with the case of Figure 6, in Figure 11, the length of each element work of each process corresponds to the element work time (actual work time) of that element work.

図11に示すように、工程Aには、工程Aの工程スキルレベルが「高」である作業者#1が割り当てられる。また、工程Bには、工程Bの工程スキルレベルが「高」である作業者#2が割り当てられる。また、工程Cには、工程Cの工程スキルレベルが「低」である作業者#3が割り当てられる。また、工程Dには、工程Dの工程スキルレベルが「中」である作業者#4が割り当てられる。 As shown in FIG. 11, worker #1, whose process skill level for process A is "high," is assigned to process A. Worker #2, whose process skill level for process B is "high," is assigned to process B. Worker #3, whose process skill level for process C is "low," is assigned to process C. Worker #4, whose process skill level for process D is "medium," is assigned to process D.

図10に示すように、作業者#1が割り当てられた工程Aの要素作業A1の実作業時間(要素作業時間)は、5秒である。また、工程Aの要素作業A2の実作業時間(要素作業時間)は、6秒である。また、工程Aの要素作業A3の実作業時間(要素作業時間)は、5秒である。また、工程Aの要素作業A4の実作業時間(要素作業時間)は、6秒である。また、工程Aの要素作業A5の実作業時間(要素作業時間)は、7秒である。そして、要素作業A1~要素作業A5の実作業時間の合計、つまり工程Aの作業時間は、29秒である。つまり、工程Aの作業時間は、タクトタイム(32秒)よりも3秒短い。工程Aには、工程Aの工程スキルレベルが「高」である作業者#1が割り当てられたので、工程Aの作業時間は、タクトタイムよりも短くなっている。 As shown in FIG. 10, the actual work time (element work time) of element work A1 of process A, to which worker #1 is assigned, is 5 seconds. The actual work time (element work time) of element work A2 of process A is 6 seconds. The actual work time (element work time) of element work A3 of process A is 5 seconds. The actual work time (element work time) of element work A4 of process A is 6 seconds. The actual work time (element work time) of element work A5 of process A is 7 seconds. The total of the actual work times of element work A1 to A5, that is, the work time of process A, is 29 seconds. In other words, the work time of process A is 3 seconds shorter than the takt time (32 seconds). Since worker #1, whose process skill level for process A is "high", is assigned to process A, the work time of process A is shorter than the takt time.

作業者#2が割り当てられた工程Bの要素作業B1の実作業時間(要素作業時間)は、2秒である。また、工程Bの要素作業B2の実作業時間(要素作業時間)は、8秒である。また、工程Bの要素作業B3の実作業時間(要素作業時間)は、8秒である。また、工程Bの要素作業B4の実作業時間(要素作業時間)は、5秒である。また、工程Bの要素作業B5の実作業時間(要素作業時間)は、6秒である。そして、要素作業B1~要素作業B5の実作業時間の合計、つまり工程Bの作業時間は、29秒である。つまり、工程Bの作業時間は、タクトタイム(32秒)よりも3秒短い。工程Bには、工程Bの工程スキルレベルが「高」である作業者#2が割り当てられたので、工程Bの作業時間は、タクトタイムよりも短くなっている。 The actual work time (element work time) of element work B1 of process B, to which worker #2 is assigned, is 2 seconds. The actual work time (element work time) of element work B2 of process B is 8 seconds. The actual work time (element work time) of element work B3 of process B is 8 seconds. The actual work time (element work time) of element work B4 of process B is 5 seconds. The actual work time (element work time) of element work B5 of process B is 6 seconds. The total actual work time of element work B1 to B5, that is, the work time of process B, is 29 seconds. In other words, the work time of process B is 3 seconds shorter than the takt time (32 seconds). Since worker #2, whose process skill level for process B is "high," is assigned to process B, the work time of process B is shorter than the takt time.

作業者#3が割り当てられた工程Cの要素作業C1の実作業時間(要素作業時間)は、5秒である。また、工程Cの要素作業C2の実作業時間(要素作業時間)は、8秒である。また、工程Cの要素作業C3の実作業時間(要素作業時間)は、3秒である。また、工程Cの要素作業C4の実作業時間(要素作業時間)は、11秒である。また、工程Cの要素作業C5の実作業時間(要素作業時間)は、5秒である。また、追加作業時間が5秒である追加作業が、工程Cに配置されている。 The actual work time (element work time) of element work C1 in process C, to which worker #3 is assigned, is 5 seconds. The actual work time (element work time) of element work C2 in process C is 8 seconds. The actual work time (element work time) of element work C3 in process C is 3 seconds. The actual work time (element work time) of element work C4 in process C is 11 seconds. The actual work time (element work time) of element work C5 in process C is 5 seconds. An additional work with an additional work time of 5 seconds has been placed in process C.

なお、この追加作業時間は、実作業時間であってもよい。その場合、追加作業時間は、追加作業の標準作業時間と、追加作業の作業種別と、追加作業を実行する作業者の作業種別スキルレベルとに応じて決定されてもよい。例えば、追加作業を行う作業者の、追加作業の作業種別に対応する作業種別スキルレベルが「低」であれば、追加作業時間(実作業時間)は、追加作業の標準作業時間と同じであってもよい。また、追加作業を行う作業者の、追加作業の作業種別に対応する作業種別スキルレベルが「中」であれば、追加作業時間(実作業時間)は、追加作業の標準作業時間よりも少し(例えば1秒)短くてもよい。また、追加作業を行う作業者の、追加作業の作業種別に対応する作業種別スキルレベルが「高」であれば、追加作業時間(実作業時間)は、追加作業の標準作業時間よりもさらに(例えば3秒)短くてもよい。 Note that this additional work time may be the actual work time. In this case, the additional work time may be determined according to the standard work time of the additional work, the work type of the additional work, and the work type skill level of the worker performing the additional work. For example, if the work type skill level corresponding to the work type of the additional work of the worker performing the additional work is "low", the additional work time (actual work time) may be the same as the standard work time of the additional work. Also, if the work type skill level corresponding to the work type of the additional work of the worker performing the additional work is "medium", the additional work time (actual work time) may be slightly shorter (for example, 1 second) than the standard work time of the additional work. Also, if the work type skill level corresponding to the work type of the additional work of the worker performing the additional work is "high", the additional work time (actual work time) may be even shorter (for example, 3 seconds) than the standard work time of the additional work.

そして、要素作業C1~要素作業C5の実作業時間及び追加作業時間の合計、つまり工程Cの作業時間は、37秒である。つまり、工程Cの作業時間は、タクトタイム(32秒)よりも5秒長い。工程Cには、工程Cの工程スキルレベルが「低」である作業者#3が割り当てられたので、追加作業時間を除く工程Cの作業時間は、タクトタイムと同じである。そして、工程Cにはさらに追加作業が配置されたので、工程Cの作業時間は、タクトタイムを超えてしまっている。 The total of the actual work time and additional work time of element tasks C1 to C5, that is, the work time of process C, is 37 seconds. In other words, the work time of process C is 5 seconds longer than the takt time (32 seconds). Because worker #3, whose process skill level for process C is "low," was assigned to process C, the work time of process C excluding the additional work time is the same as the takt time. And because additional tasks have been assigned to process C, the work time of process C exceeds the takt time.

作業者#4が割り当てられた工程Dの要素作業D1の実作業時間(要素作業時間)は、5秒である。また、工程Dの要素作業D2の実作業時間(要素作業時間)は、6秒である。また、工程Dの要素作業D3の実作業時間(要素作業時間)は、5秒である。また、工程Dの要素作業D4の実作業時間(要素作業時間)は、5秒である。また、工程Dの要素作業D5の実作業時間(要素作業時間)は、10秒である。そして、要素作業D1~要素作業D5の実作業時間の合計、つまり工程Dの作業時間は、31秒である。つまり、工程Dの作業時間は、タクトタイム(32秒)よりも1秒短い。工程Dには、工程Dの工程スキルレベルが「中」である作業者#4が割り当てられたので、工程Dの作業時間は、タクトタイムよりも少し短くなっている。 The actual work time (element work time) of element work D1 of process D, to which worker #4 is assigned, is 5 seconds. The actual work time (element work time) of element work D2 of process D is 6 seconds. The actual work time (element work time) of element work D3 of process D is 5 seconds. The actual work time (element work time) of element work D4 of process D is 5 seconds. The actual work time (element work time) of element work D5 of process D is 10 seconds. The total of the actual work times of element work D1 to D5, that is, the work time of process D, is 31 seconds. In other words, the work time of process D is 1 second shorter than the takt time (32 seconds). Since worker #4, whose process skill level for process D is "medium," is assigned to process D, the work time of process D is slightly shorter than the takt time.

この例において、基準工程(工程C)を含む再配置工程の工程数をN=2とする。この場合、再配置工程を工程B及び工程Cとすると、再配置工程の各工程の作業時間の合計は、29+37=66となり、タクトタイムを再配置工程の工程数Nで乗算した値(32×2=64)を超える。また、再配置工程を工程C及び工程Dとすると、再配置工程の各工程の作業時間の合計は、37+31=68となり、タクトタイムを再配置工程の工程数Nで乗算した値(32×2=64)を超える。したがって、再配置工程の工程数がN=2の場合、どの要素作業の組み合わせでも最大作業時間がタクトタイム以下となることはないので、適切な組み合わせは算出されない。 In this example, the number of steps in the rearrangement process, including the reference process (process C), is N = 2. In this case, if the rearrangement processes are processes B and C, the total work time for each process in the rearrangement process is 29 + 37 = 66, which exceeds the value obtained by multiplying the takt time by the number of processes N in the rearrangement process (32 x 2 = 64). Furthermore, if the rearrangement processes are processes C and D, the total work time for each process in the rearrangement process is 37 + 31 = 68, which exceeds the value obtained by multiplying the takt time by the number of processes N in the rearrangement process (32 x 2 = 64). Therefore, when the number of steps in the rearrangement process is N = 2, the maximum work time will never be less than the takt time for any combination of element tasks, and therefore no appropriate combination can be calculated.

したがって、工程決定部130は、再配置工程の工程数をN=3とする。そして、工程決定部130は、図8に例示した、パターン#1-1に対応する工程A、工程B及び工程Cを、再配置工程と決定する(S106)。なお、この場合、再配置工程の各工程の作業時間の合計は、29+29+37=95となり、タクトタイムを再配置工程の工程数Nで乗算した値(32×3=96)以下である。したがって、この場合、要素作業の組み合わせによっては再配置工程の最大作業時間がタクトタイム以下となる可能性がある。 Therefore, the process determination unit 130 sets the number of processes in the rearrangement process to N = 3. Then, the process determination unit 130 determines that processes A, B, and C corresponding to pattern #1-1 illustrated in FIG. 8 are the rearrangement processes (S106). In this case, the total working time of each process in the rearrangement process is 29 + 29 + 37 = 95, which is less than the takt time multiplied by the number of processes N in the rearrangement process (32 x 3 = 96). Therefore, in this case, depending on the combination of element tasks, the maximum working time of the rearrangement process may be less than the takt time.

図12~図14は、図10及び図11の例における要素作業の再配置を例示する図である。図12に例示するように、算出部140は、再配置処理において、再配置工程である工程Cと工程Bとの間で、要素作業C1を要素作業B1と交換する。また、算出部140は、再配置処理において、再配置工程である工程Cと工程Aとの間で、要素作業C3を、工程Aの先頭に移動する。これにより、図13に例示するように、要素作業C1が工程Bに再配置され、要素作業C3が工程Aに再配置され、要素作業B1が工程Cに再配置される。このように、算出部140は、再配置工程である工程A、工程B及び工程Cの間で、要素作業を再配置する。なお、工程Aにおいて、要素作業C3は、前後作業制限を満たす限り、任意のタイミングで実行されてもよい。つまり、要素作業C3は、工程Aの最初に実行されてもよいし、工程Aの途中(例えば要素作業A2の後など)で実行されてもよいし、工程Aの最後に実行されてもよい。 Figures 12 to 14 are diagrams illustrating the rearrangement of element tasks in the examples of Figures 10 and 11. As illustrated in Figure 12, in the rearrangement process, the calculation unit 140 exchanges element task C1 with element task B1 between process C and process B, which are rearrangement processes. In addition, in the rearrangement process, the calculation unit 140 moves element task C3 to the beginning of process A between process C and process A, which are rearrangement processes. As a result, as illustrated in Figure 13, element task C1 is rearranged to process B, element task C3 is rearranged to process A, and element task B1 is rearranged to process C. In this way, the calculation unit 140 rearranges element tasks between process A, process B, and process C, which are rearrangement processes. Note that in process A, element task C3 may be performed at any timing as long as the preceding and following task restrictions are satisfied. In other words, element task C3 may be performed at the beginning of process A, in the middle of process A (e.g., after element task A2), or at the end of process A.

ここで、図14に例示するように、再配置後の工程Aについては、実作業時間が3秒である要素作業C3が追加作業として追加されている。したがって、再配置後の工程Aの作業時間は、再配置前から3秒増加して、32秒となる。なお、工程Aに割り当てられた作業者#1の工程Cに関する工程スキルレベルは、工程Cに割り当てられた作業者#3の工程Cに関する工程スキルレベルと同じ「低」であるとする。したがって、要素作業C3の実作業時間は、変更されない。一方、作業者#1の工程Cに関する工程スキルレベルが「高」又は「中」である場合、工程Aに再配置された要素作業C3の実作業時間を、3秒から短くしてもよい。 As shown in FIG. 14, after the rearrangement, an element task C3 with an actual work time of 3 seconds has been added as an additional task to the process A. Therefore, the work time of the process A after the rearrangement increases by 3 seconds from before the rearrangement to 32 seconds. Note that the process skill level of the process C of the worker #1 assigned to the process A is "low", the same as the process skill level of the process C of the worker #3 assigned to the process C. Therefore, the actual work time of the element task C3 is not changed. On the other hand, if the process skill level of the worker #1 for the process C is "high" or "medium", the actual work time of the element task C3 rearranged to the process A may be shortened from 3 seconds.

また、再配置後の工程Bについては、実作業時間が2秒である要素作業B1が、実作業時間が5秒である要素作業C1に置き換えられている。したがって、再配置後の工程Bの作業時間は、再配置前から3秒増加して、32秒となる。なお、工程Bに割り当てられた作業者#2の工程Cに関する工程スキルレベルは、工程Cに割り当てられた作業者#3の工程Cに関する工程スキルレベルと同じ「低」であるとする。したがって、要素作業C1の実作業時間は、変更されない。一方、作業者#2の工程Cに関する工程スキルレベルが「高」又は「中」である場合、工程Bに再配置された要素作業C1の実作業時間を、3秒から短くしてもよい。 Furthermore, for process B after the rearrangement, element work B1, whose actual work time is 2 seconds, has been replaced with element work C1, whose actual work time is 5 seconds. Therefore, the work time of process B after the rearrangement increases by 3 seconds from before the rearrangement to 32 seconds. Note that the process skill level of worker #2 assigned to process B for process C is "low", the same as the process skill level of worker #3 assigned to process C for process C. Therefore, the actual work time of element work C1 does not change. On the other hand, if worker #2's process skill level for process C is "high" or "medium", the actual work time of element work C1 rearranged to process B may be shortened from 3 seconds.

また、再配置後の工程Cについては、実作業時間が5秒である要素作業C1が、実作業時間が2秒である要素作業B1に置き換えられている。さらに、実作業時間が3秒である要素作業C3が、工程Cからなくなっている。したがって、再配置後の工程Cの作業時間は、再配置前から6秒減少して、31秒となる。なお、工程Cに割り当てられた作業者#3の工程Bに関する工程スキルレベルは、工程Bに割り当てられた作業者#2の工程Cに関する工程スキルレベルと同じ「高」であるとする。したがって、要素作業B1の実作業時間は、変更されない。一方、作業者#3の工程Bに関する工程スキルレベルが「低」又は「中」である場合、工程Cに再配置された要素作業B1の実作業時間を、2秒から長くしてもよい。 In addition, for process C after the rearrangement, element work C1, whose actual work time is 5 seconds, has been replaced with element work B1, whose actual work time is 2 seconds. Furthermore, element work C3, whose actual work time is 3 seconds, has disappeared from process C. Therefore, the work time of process C after the rearrangement is reduced by 6 seconds from before the rearrangement to 31 seconds. Note that the process skill level of worker #3 assigned to process C for process B is "high", the same as the process skill level of worker #2 assigned to process B for process C. Therefore, the actual work time of element work B1 is not changed. On the other hand, if the process skill level of worker #3 for process B is "low" or "medium", the actual work time of element work B1 rearranged to process C may be increased from 2 seconds.

算出部140は、図12~図14の例における要素作業の組み合わせについて、各工程の作業時間のうちの最大作業時間が、32秒であると判定する。そして、算出部140は、他の組み合わせにおける最大作業時間と比較して、この例における最大作業時間(32秒)が、最小であると判定する。したがって、算出部140は、図12~図14に例示するような、最大作業時間が最小となるような、要素作業の組み合わせを算出する(S108)。 The calculation unit 140 determines that the maximum work time of each process for the combination of element tasks in the example of Figures 12 to 14 is 32 seconds. The calculation unit 140 then compares the maximum work time in this example with the maximum work time in other combinations and determines that the maximum work time (32 seconds) is the smallest. Therefore, the calculation unit 140 calculates a combination of element tasks such as those illustrated in Figures 12 to 14 that will minimize the maximum work time (S108).

そして、判定部150は、最大作業時間がタクトタイム以下であるか否かを判定する(S110)。ここで、最大作業時間は32秒であるので、判定部150は、最大作業時間がタクトタイム以下であると判定する(S110のYES)。したがって、表示制御部160は、図13に例示したような、各工程の要素作業を、インタフェース部18に表示させる(S112)。 Then, the determination unit 150 determines whether the maximum work time is equal to or less than the takt time (S110). Here, since the maximum work time is 32 seconds, the determination unit 150 determines that the maximum work time is equal to or less than the takt time (YES in S110). Therefore, the display control unit 160 causes the interface unit 18 to display the element work of each process, as shown in FIG. 13 (S112).

上述したように、実施の形態1にかかる工程管理システム1は、追加作業時間及び要素作業時間に基づいて、追加作業を工程の少なくとも1つに追加して工程間で要素作業を再配置するように構成されている。そして、実施の形態1にかかる工程管理システム1は、複数の工程それぞれの作業時間のうちの最大作業時間がより小さくなるように、複数の工程についての追加作業及び複数の要素作業の組み合わせを算出するように構成されている。このような構成により、要素作業及び追加作業が再配置された各工程の作業時間が、より平滑化されるようになる。そして、各工程の作業時間がより平滑化されることによって、生産ラインの生産性が良好となり得る。したがって、実施の形態1にかかる工程管理システム1は、追加作業が発生した場合であっても、生産ラインの生産性を適正化することが可能となる。 As described above, the process control system 1 according to the first embodiment is configured to add additional work to at least one of the processes and rearrange the element work between the processes based on the additional work time and the element work time. The process control system 1 according to the first embodiment is configured to calculate a combination of additional work and element work for a plurality of processes so that the maximum work time among the work times of each of the plurality of processes is reduced. With this configuration, the work time of each process in which the element work and additional work have been rearranged is smoothed out. The smoothing of the work time of each process can improve the productivity of the production line. Therefore, the process control system 1 according to the first embodiment makes it possible to optimize the productivity of the production line even when additional work occurs.

また、実施の形態1にかかる工程管理システム1は、要素作業が再配置される再配置工程を決定するように構成されている。このような構成により、要素作業が再配置される工程を限定することができる。ここで、要素作業が再配置される工程が限定されないと、ある要素作業が、作業効率の悪い工程に再配置されてしまう可能性がある。例えば、ある要素作業が、元々配置されていた工程から離れた工程に再配置されると、その要素作業によるワークの移動が煩雑となる可能性がある。これに対し、要素作業が再配置される工程を限定することにより、作業効率の悪い工程に要素作業が再配置されることを、抑制することができる。例えば、上述した実施の形態1のように、基準工程を含む連続する2つ以上の工程を再配置工程とすることによって、ある要素作業が、元々配置されていた工程から離れた工程に再配置されることを、抑制することができる。したがって、実施の形態1にかかる工程管理システム1は、要素作業の再配置を適切に行うことが可能となる。 The process management system 1 according to the first embodiment is configured to determine a relocation process to which the element work is relocated. With this configuration, the process to which the element work is relocated can be limited. If the process to which the element work is relocated is not limited, a certain element work may be relocated to a process with poor work efficiency. For example, if a certain element work is relocated to a process away from the process in which it was originally located, the movement of the work by the element work may become complicated. In contrast, by limiting the process to which the element work is relocated, it is possible to prevent the element work from being relocated to a process with poor work efficiency. For example, as in the first embodiment described above, by setting two or more consecutive processes including the reference process as the relocation process, it is possible to prevent a certain element work from being relocated to a process away from the process in which it was originally located. Therefore, the process management system 1 according to the first embodiment can appropriately relocate the element work.

また、実施の形態1にかかる工程管理システム1は、最大作業時間が予め定められた時間(タクトタイム等)を超える場合に、再配置工程を変更し、変更された再配置工程について、要素作業の組み合わせを算出するように構成されている。このような構成により、要素作業が再配置される再配置工程を限定しつつ、最大作業時間が予め定められた時間以下となるような、要素作業の組み合わせを算出することが可能となる。これにより、追加作業が生産ラインに追加された場合であっても、生産計画に影響を及ぼすことを抑制することができる。 The process management system 1 according to the first embodiment is configured to change the rearrangement process and calculate a combination of element tasks for the changed rearrangement process when the maximum operation time exceeds a predetermined time (such as a takt time). This configuration makes it possible to calculate a combination of element tasks such that the maximum operation time is equal to or less than a predetermined time while limiting the rearrangement process to which the element tasks are rearranged. This makes it possible to prevent the production plan from being affected even when additional tasks are added to the production line.

また、実施の形態1にかかる工程管理システム1は、作業者情報に基づいて組み合わせを算出するように構成されている。このような構成により、作業者のスキルに応じた要素作業の組み合わせが算出されるので、要素作業の組み合わせの算出をより適切に行うことが可能となる。 The process control system 1 according to the first embodiment is configured to calculate the combination based on the worker information. With this configuration, the combination of element tasks is calculated according to the skills of the worker, so that the combination of element tasks can be calculated more appropriately.

また、実施の形態1にかかる工程管理システム1は、制限情報(前後作業制限情報等)に基づいて組み合わせを算出するように構成されている。このような構成により、要素作業の制限に応じた要素作業の組み合わせが算出されるので、要素作業の組み合わせの算出をより適切に行うことが可能となる。 The process control system 1 according to the first embodiment is configured to calculate combinations based on restriction information (pre- and post-task restriction information, etc.). With this configuration, a combination of element tasks is calculated according to the restrictions of the element tasks, making it possible to more appropriately calculate the combination of element tasks.

(変形例)
なお、本発明は上記実施の形態に限られたものではなく、趣旨を逸脱しない範囲で適宜変更することが可能である。例えば、上述したフローチャートの各ステップの順序は、適宜、変更可能である。また、フローチャートの各ステップの1つ以上は、省略されてもよい。例えば、図9に示したフローチャートにおいて、S102の処理及びS104の処理の順序は、逆であってもよい。また、S112の処理は、省略されてもよい。
(Modification)
The present invention is not limited to the above embodiment, and can be modified as appropriate without departing from the spirit of the present invention. For example, the order of the steps in the above-mentioned flowchart can be changed as appropriate. Furthermore, one or more steps in the flowchart can be omitted. For example, in the flowchart shown in FIG. 9, the order of the process of S102 and the process of S104 can be reversed. Furthermore, the process of S112 can be omitted.

また、図9に示したフローチャートにおいて、S106及びS110の処理は、省略されてもよい。つまり、本実施の形態にかかる工程管理システム1は、再配置工程が決定されていない状態で、最大作業時間が小さくなるように要素作業の組み合わせを算出してもよい。一方、S106及びS110の処理を行うことによって、上述したように、要素作業の再配置を適切に行うことが可能となり、生産計画に影響を及ぼすことを抑制することができる。 In addition, in the flowchart shown in FIG. 9, the processes of S106 and S110 may be omitted. In other words, the process management system 1 according to this embodiment may calculate a combination of element tasks so as to reduce the maximum work time when the rearrangement process has not been determined. On the other hand, by performing the processes of S106 and S110, it becomes possible to appropriately rearrange the element tasks as described above, and to suppress any impact on the production plan.

また、上述した実施の形態では、追加作業時間及び追加作業の作業種別を、代表作業者が追加作業を行うことによって取得するとしているが、このような構成に限られない。追加作業時間及び追加作業の作業種別を推定してもよい。例えば、追加作業に近い既存の要素作業に関する情報を用いて、追加作業時間及び追加作業の作業種別を推定してもよい。 In addition, in the above-described embodiment, the additional work time and the work type of the additional work are obtained by the representative worker performing the additional work, but this is not limited to the configuration. The additional work time and the work type of the additional work may also be estimated. For example, the additional work time and the work type of the additional work may be estimated using information about existing elemental work that is similar to the additional work.

また、上述した実施の形態では、追加作業が配置される基準工程は1つであるとしたが、このような構成に限られない。追加作業の内容によっては、追加作業は、複数の工程に追加されてもよい。つまり、基準工程は、複数であってもよい。言い換えると、基準工程は、少なくとも1つであってもよい。 In addition, in the above-described embodiment, there is one reference process in which the additional work is placed, but this is not limited to the configuration. Depending on the content of the additional work, the additional work may be added to multiple processes. In other words, there may be multiple reference processes. In other words, there may be at least one reference process.

また、上述の例において、プログラムは、様々なタイプの非一時的なコンピュータ可読媒体(non-transitory computer readable medium)を用いて格納され、コンピュータに供給することができる。非一時的なコンピュータ可読媒体は、様々なタイプの実体のある記録媒体(tangible storage medium)を含む。非一時的なコンピュータ可読媒体の例は、磁気記録媒体(例えばフレキシブルディスク、磁気テープ、ハードディスクドライブ)、光磁気記録媒体(例えば光磁気ディスク)、CD-ROM、CD-R、CD-R/W、半導体メモリ(例えば、マスクROM、PROM(Programmable ROM)、EPROM(Erasable PROM)、フラッシュROM、RAM)を含む。また、プログラムは、様々なタイプの一時的なコンピュータ可読媒体(transitory computer readable medium)によってコンピュータに供給されてもよい。一時的なコンピュータ可読媒体の例は、電気信号、光信号、及び電磁波を含む。一時的なコンピュータ可読媒体は、電線及び光ファイバ等の有線通信路、又は無線通信路を介して、プログラムをコンピュータに供給できる。 In the above example, the program can be stored and supplied to the computer using various types of non-transitory computer readable media. The non-transitory computer readable media includes various types of tangible storage media. Examples of the non-transitory computer readable media include magnetic recording media (e.g., flexible disks, magnetic tapes, hard disk drives), magneto-optical recording media (e.g., magneto-optical disks), CD-ROMs, CD-Rs, CD-R/Ws, and semiconductor memories (e.g., mask ROMs, PROMs (Programmable ROMs), EPROMs (Erasable PROMs), flash ROMs, and RAMs). The program may also be supplied to the computer by various types of transitory computer readable media. Examples of the transitory computer readable media include electrical signals, optical signals, and electromagnetic waves. The transitory computer readable media can supply the program to the computer via wired communication paths such as electric wires and optical fibers, or wireless communication paths.

1 工程管理システム
50 生産ライン
100 情報格納部
102 工程情報格納部
104 作業者情報格納部
106 追加作業情報格納部
120 取得部
122 追加作業情報取得部
124 既存作業情報取得部
130 工程決定部
140 算出部
150 判定部
160 表示制御部
REFERENCE SIGNS LIST 1 Process management system 50 Production line 100 Information storage unit 102 Process information storage unit 104 Worker information storage unit 106 Additional work information storage unit 120 Acquisition unit 122 Additional work information acquisition unit 124 Existing work information acquisition unit 130 Process determination unit 140 Calculation unit 150 Determination unit 160 Display control unit

Claims (6)

所定の作業が行われる既存の複数の工程を含む生産ラインを管理する工程管理システムであって、
前記生産ラインにおいて追加で実施される追加作業に必要な作業時間である追加作業時間と、前記工程内の1つ以上の要素作業それぞれに必要な作業時間である要素作業時間とを取得する取得部と、
取得された前記追加作業時間及び前記要素作業時間に基づいて、前記追加作業を前記工程の少なくとも1つに追加して工程間で前記要素作業を再配置したときの複数の前記工程それぞれの作業時間のうちの最大作業時間がより小さくなるように、前記複数の工程についての前記追加作業及び複数の前記要素作業の組み合わせを算出する算出部と、
を有する工程管理システム。
A process management system for managing a production line including a plurality of existing processes in which predetermined operations are performed,
an acquisition unit that acquires additional operation time, which is operation time required for an additional operation to be additionally performed in the production line, and element operation time, which is operation time required for each of one or more element operations in the process;
a calculation unit that calculates a combination of the additional work and the element work for the plurality of processes based on the acquired additional work time and the element work times so that a maximum work time among work times of each of the plurality of processes is shortened when the additional work is added to at least one of the processes and the element work is rearranged between the processes; and
A process control system having the following features:
前記複数の工程のうちの、前記要素作業が再配置される工程である再配置工程を決定する決定部、
をさらに有する請求項1に記載の工程管理システム。
a determination unit that determines a relocation process, among the plurality of processes, in which the element work is to be relocated;
The process control system of claim 1 further comprising:
前記算出部によって算出された前記最大作業時間が予め定められた時間を超える場合に、
前記決定部は、前記再配置工程を変更し、
前記算出部は、変更された前記再配置工程について、前記組み合わせを算出する、
請求項2に記載の工程管理システム。
When the maximum operation time calculated by the calculation unit exceeds a predetermined time,
The determination unit changes the rearrangement process,
The calculation unit calculates the combination for the changed rearrangement process.
The process control system according to claim 2.
前記取得部は、さらに、前記工程における作業を行う作業者に関する作業者情報を取得し、
前記算出部は、前記作業者情報に基づいて、前記組み合わせを算出する、
請求項1から3のいずれか1項に記載の工程管理システム。
The acquisition unit further acquires worker information related to a worker performing work in the process,
The calculation unit calculates the combination based on the worker information.
The process control system according to any one of claims 1 to 3.
前記取得部は、さらに、前記要素作業に関する制限を示す制限情報を取得し、
前記算出部は、前記制限情報に基づいて、前記組み合わせを算出する、
請求項1から4のいずれか1項に記載の工程管理システム。
The acquisition unit further acquires restriction information indicating restrictions on the element work,
The calculation unit calculates the combination based on the restriction information.
The process control system according to any one of claims 1 to 4.
所定の作業が行われる既存の複数の工程を含む生産ラインを管理する工程管理方法であって、
前記生産ラインにおいて追加で実施される追加作業に必要な作業時間である追加作業時間と、前記工程内の1つ以上の要素作業それぞれに必要な作業時間である要素作業時間とを取得し、
取得された前記追加作業時間及び前記要素作業時間に基づいて、前記追加作業を前記工程の少なくとも1つに追加して工程間で前記要素作業を再配置したときの複数の前記工程それぞれの作業時間のうちの最大作業時間がより小さくなるように、前記複数の工程についての前記追加作業及び複数の前記要素作業の組み合わせを算出する、
工程管理方法。
A process management method for managing a production line including a plurality of existing processes in which predetermined operations are performed, comprising the steps of:
Acquire additional operation time, which is operation time required for additional operation to be performed in the production line, and element operation time, which is operation time required for each of one or more element operations in the process;
calculating a combination of the additional work and the element work for the plurality of processes based on the acquired additional work time and the element work times such that a maximum work time among the work times of each of the plurality of processes is shortened when the additional work is added to at least one of the processes and the element work is rearranged between the processes;
Process control methods.
JP2021046757A 2021-03-22 2021-03-22 Process control system and process control method Active JP7537330B2 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
JP2021046757A JP7537330B2 (en) 2021-03-22 2021-03-22 Process control system and process control method
CN202210267794.2A CN115113589A (en) 2021-03-22 2022-03-17 Process management system and process management method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2021046757A JP7537330B2 (en) 2021-03-22 2021-03-22 Process control system and process control method

Publications (2)

Publication Number Publication Date
JP2022145993A JP2022145993A (en) 2022-10-05
JP7537330B2 true JP7537330B2 (en) 2024-08-21

Family

ID=83324932

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2021046757A Active JP7537330B2 (en) 2021-03-22 2021-03-22 Process control system and process control method

Country Status (2)

Country Link
JP (1) JP7537330B2 (en)
CN (1) CN115113589A (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2013156800A (en) 2012-01-30 2013-08-15 Bodyshop Eiichi Co Ltd Process control system and process management program
US20180046953A1 (en) 2016-08-12 2018-02-15 Fujitsu Limited Line balancing apparatus, line balancing method, and computer-readable recording medium
JP2020052663A (en) 2018-09-26 2020-04-02 日本電気株式会社 Process design support device and process design support method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2013156800A (en) 2012-01-30 2013-08-15 Bodyshop Eiichi Co Ltd Process control system and process management program
US20180046953A1 (en) 2016-08-12 2018-02-15 Fujitsu Limited Line balancing apparatus, line balancing method, and computer-readable recording medium
JP2018026070A (en) 2016-08-12 2018-02-15 富士通株式会社 Work organization device, work organization method, and work organization program
JP2020052663A (en) 2018-09-26 2020-04-02 日本電気株式会社 Process design support device and process design support method

Also Published As

Publication number Publication date
CN115113589A (en) 2022-09-27
JP2022145993A (en) 2022-10-05

Similar Documents

Publication Publication Date Title
US20230216914A1 (en) Automated server workload management using machine learning
US20040044718A1 (en) Submitting jobs in a distributed computing environment
KR102391510B1 (en) Method, device and system for predicting failure in advance of it infrastructure equipment based on artificial intelligence
KR101816770B1 (en) The system for managing railway facility based on BIM
CN104639639A (en) Regulating method, device and system for deployment position of virtual machine
Kim et al. Prediction based sub-task offloading in mobile edge computing
CN109586954B (en) Network traffic prediction method and device and electronic equipment
CN108366082A (en) Expansion method and flash chamber
CN111324471B (en) Service adjustment method, device, equipment and storage medium
JP2021077129A (en) Information processing system, model control method, and storage medium
JP5109799B2 (en) Information processing system, load control method, and load control program
JP2013008089A (en) Calculation method for configuration pattern of computer system, and calculation device for configuration pattern
JP7537330B2 (en) Process control system and process control method
KR102151756B1 (en) Apparatus and method of managing and arranging workers
KR102195886B1 (en) Distributed processing system and operating method thereof
Arruda et al. Stability and optimality of a multi-product production and storage system under demand uncertainty
Lin Scheduling efficiency on correlated parallel machine scheduling problems
WO2015058801A1 (en) Method for performing distributed geographic event processing and geographic event processing system
Larsen A heuristic joint replinishment policy for the case of heterogeneity among items
JP2020053711A (en) Orchestrator device, program, information processing system, and control method
CN113486583A (en) Health assessment method and device of equipment, computer equipment and computer-readable storage medium
Shankar et al. Reliability analysis of a maintenance network with repair and preventive maintenance
WO2014016950A1 (en) Parallel computer system, and method for arranging processing load in parallel computer system
CN101657806A (en) Assembly and associated method, for planning computer system resource requirements
CN110795151A (en) Operator concurrency degree adjusting method, device and equipment

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20230912

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20240628

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20240709

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20240722

R150 Certificate of patent or registration of utility model

Ref document number: 7537330

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150