JP7175215B2 - Method of joining precast concrete columns - Google Patents

Method of joining precast concrete columns Download PDF

Info

Publication number
JP7175215B2
JP7175215B2 JP2019025119A JP2019025119A JP7175215B2 JP 7175215 B2 JP7175215 B2 JP 7175215B2 JP 2019025119 A JP2019025119 A JP 2019025119A JP 2019025119 A JP2019025119 A JP 2019025119A JP 7175215 B2 JP7175215 B2 JP 7175215B2
Authority
JP
Japan
Prior art keywords
joint space
precast concrete
joint
divided
concrete column
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2019025119A
Other languages
Japanese (ja)
Other versions
JP2020133158A (en
Inventor
正美 戸澤
正樹 淵本
隆浩 長田
佳名子 乙藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Corp
Original Assignee
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Corp filed Critical Shimizu Corp
Priority to JP2019025119A priority Critical patent/JP7175215B2/en
Publication of JP2020133158A publication Critical patent/JP2020133158A/en
Priority to JP2022177756A priority patent/JP7330346B2/en
Application granted granted Critical
Publication of JP7175215B2 publication Critical patent/JP7175215B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Description

本発明は、大断面のプレキャストコンクリート柱であってもグラウト材の充填率を担保することができるプレキャストコンクリート柱の接合方法を提供する。 The present invention provides a method for joining precast concrete columns, which can secure the filling rate of grout material even for precast concrete columns having a large cross section.

近年、ビルディングなどの建設にあたっては、壁や柱といった建築部材を、プレキャストコンクリート部材として、予め工場生産しておき、これを現場に搬入し組み上げる工法が広く用いられるようになっている。このような工法を採用することで、現場における工数を減らしたり、工期を短縮したりすることができるようになった。 2. Description of the Related Art In recent years, in the construction of a building or the like, a construction method has been widely used in which building members such as walls and columns are pre-produced as precast concrete members in a factory, and then brought to the site and assembled. By adopting such a construction method, it became possible to reduce the number of man-hours on site and shorten the construction period.

例えば、特許文献1(特開2001-164688号公報)には、コンクリート部材の上面の両端側に型枠形成部を備えたプレキャストコンクリート梁材を各柱間に架設し、これらのプレキャストコンクリート梁材間に、コンクリート板の上面に型枠形成部を備えたプレキャストコンクリート床板を敷設し、前記型枠形成部により構成された打ち継ぎ型枠内にコンクリートを打設することを特徴とする鉄筋コンクリート構造物の構築工法が開示されている。
特開2001-164688号公報
For example, in Patent Document 1 (Japanese Patent Application Laid-Open No. 2001-164688), precast concrete beams having formwork forming portions on both end sides of the upper surface of a concrete member are installed between each column, and these precast concrete beams A reinforced concrete structure characterized by laying a precast concrete floor plate having a formwork forming part on the upper surface of the concrete plate between the concrete plates, and pouring concrete into the joint formwork formed by the formwork forming part. construction method is disclosed.
JP-A-2001-164688

建設プロジェクトは現在大型化しており、超超高層建物が増加する傾向にある。その結果として、各部材の断面が大型化し、これまでにあまり施工実績のない、大断面のプレキャストコンクリートを施工する状況になりつつある。 Construction projects are currently getting larger, and there is a trend towards an increase in super high-rise buildings. As a result, the cross-section of each member has become larger, and we are now in a situation where precast concrete with a large cross-section, which has not been used so far, is being used.

プレキャストコンクリート柱においては、柱の脚部に鉄筋の機械式継手を設けて、柱脚の目地部分と継手部分のグラウトを同時に施工する方法が一般的である。しかしながら、当該柱の断面が大きくなると、グラウト材が所望する充填率で充填されない可能性がある、という問題があった。特に、施工時期が、グラウト材が硬化しやすい夏場などに当たる場合には、適切なグラウト充填率で施工を行うことがより一層困難になることが予想される。 In precast concrete columns, a common method is to provide mechanical joints of reinforcing bars at the base of the column and simultaneously apply grout to the joint portion and the joint portion of the column base. However, when the cross section of the column becomes large, there is a problem that the grout material may not be filled at a desired filling rate. In particular, when the construction period is summer, when the grout material tends to harden, it is expected that it will become even more difficult to perform construction with an appropriate grout filling rate.

この発明は、上記のような課題を解決するものであって、本発明に係るプレキャストコンクリート柱の接合方法は、複数のスリーブ式鉄筋継手部材が内挿されたプレキャストコンクリート柱をスラブ上に接合するプレキャストコンクリート柱の接合方法であって、前記スラブとの間に目地空間を設けて前記プレキャストコンクリート柱を配する工程と、前記目地空間に離隔部材を配し、前記目地空間を離隔部材で離隔し、複数の分割目地空間とする工程と、一の分割目地空間にスリーブ式鉄筋継手部材を介してグラウトを充填し養生する工程と、前記一の分割目地空間に充填したグラウトの養生が完了した後、前記一の分割目地空間に隣接する他の分割目地空間との間に配された離隔部材を撤去する工程と、前記他の分割目地空間にスリーブ式鉄筋継手部材を介してグラウトを充填し養生する工程と、を含むことを特徴とする。 The present invention is intended to solve the above-described problems, and a method for joining a precast concrete column according to the present invention joins a precast concrete column to a slab, in which a plurality of sleeve-type reinforcing-bar joint members are inserted. A method for joining precast concrete columns, comprising the steps of disposing the precast concrete column with a joint space between it and the slab, disposing a separation member in the joint space, and separating the joint space with the separation member. , a step of forming a plurality of divided joint spaces, a step of filling and curing one divided joint space with grout via a sleeve type reinforcing bar joint member, and after curing of the grout filled in the one divided joint space is completed , a step of removing a separating member disposed between said one divided joint space and another divided joint space adjacent to said divided joint space, and filling said other divided joint space with grout via a sleeve type reinforcing bar joint member for curing. and a step of performing.

また、本発明に係るプレキャストコンクリート柱の接合方法は、複数のスリーブ式鉄筋継手部材が内挿されたプレキャストコンクリート柱をスラブ上に接合するプレキャストコンクリート柱の接合方法であって、前記スラブとの間に目地空間を設けて前記プレキャストコンクリート柱を配する工程と、前記目地空間に離隔部材を配し、前記目地空間を離隔部材で離隔し、複数の分割目地空間とする工程と、一の分割目地空間にスリーブ式鉄筋継手部材を介してグラウトを充填し養生する工程と、前記一の分割目地空間に隣接する他の分割目地空間にスリーブ式鉄筋継手部材を介してグラウトを充填し養生する工程と、前記一の分割目地空間に充填したグラウトと、前記他の分割目地空間に充填したグラウトの養生が完了した後、前記一の分割目地空間に隣接する他の分割目地空間との間に配された離隔部材を撤去する工程と、前記離隔部材を撤去した後に形成された空間にてグラウトを充填し養生する工程と、を含むことを特徴とする。 In addition, a method for joining precast concrete columns according to the present invention is a method for joining a precast concrete column, in which a plurality of sleeve-type reinforcing-bar joint members are inserted, onto a slab, wherein providing a joint space and arranging the precast concrete column; placing a separating member in the joint space, separating the joint space with the separating member to form a plurality of divided joint spaces; A step of filling the space with grout via a sleeve-type reinforcing bar joint member and curing, and a step of filling and curing the other divided joint space adjacent to the one divided joint space with grout via the sleeve-type reinforcing bar joint member. , After curing of the grout filled in the one divided joint space and the grout filled in the other divided joint space is completed, it is arranged between the other divided joint space adjacent to the one divided joint space and a step of filling and curing grout in a space formed after removing the spacing member.

また、本発明に係るプレキャストコンクリート柱の接合方法は、複数のスリーブ式鉄筋継手部材が内挿されたプレキャストコンクリート柱をスラブ上に接合するプレキャストコンクリート柱の接合方法であって、前記プレキャストコンクリート柱が配されることで、前記スラブと前記プレキャストコンクリート柱の間で目地空間となる予定箇所に、前記目地空間を離隔し、複数の分割目地空間とする離隔部材を配する工程と、前記スラブとの間に目地空間を設けて前記プレキャストコンクリート柱を配する工程と、一の分割目地空間にスリーブ式鉄筋継手部材を介してグラウトを充填し養生する工程と、前記一の分割目地空間に隣接する他の分割目地空間にスリーブ式鉄筋継手部材を介してグラウトを充填し養生する工程と、を含むことを特徴とする。 A method for joining a precast concrete column according to the present invention is a method for joining a precast concrete column having a plurality of sleeve-type reinforcing-bar joint members inserted therein onto a slab, wherein the precast concrete column is a step of disposing a separation member to separate the joint space and to form a plurality of divided joint spaces at a planned location to be a joint space between the slab and the precast concrete column; and A step of disposing the precast concrete column with a joint space therebetween, a step of filling and curing the one divided joint space with grout via a sleeve type reinforcing bar joint member, and another adjacent to the one divided joint space and a step of filling and curing the grout into the divided joint space through the sleeve type reinforcing bar joint member.

本発明に係るプレキャストコンクリート柱の接合方法は、目地空間に離隔部材を配し、目地空間を離隔部材で離隔し、複数の分割目地空間とし、それぞれにグラウト材を充填し養生する工程を経るようになっており、このような本発明に係るプレキャストコンクリート柱の接合方法によれば、大断面のプレキャストコンクリート柱でも、適切な面積の分割目地空間に分割された上でグラウト材が充填されるので、十分なグラウト充填率が確保することができ、信頼性の高い施工を行うことが可能となる。 A method for joining precast concrete columns according to the present invention includes a step of disposing a separation member in a joint space, separating the joint space with the separation member to form a plurality of divided joint spaces, and filling and curing each of the joint spaces with grout material. According to the method for joining precast concrete columns according to the present invention, even a precast concrete column with a large cross section is divided into divided joint spaces having appropriate areas and then filled with grout material. , a sufficient grout filling rate can be secured, and highly reliable construction can be performed.

プレキャストコンクリート柱の接合方法を説明する透過的模式図である。It is a transparent schematic diagram explaining the joining method of a precast concrete column. プレキャストコンクリート柱の接合方法を説明する透過的模式図である。It is a transparent schematic diagram explaining the joining method of a precast concrete column. プレキャストコンクリート柱の接合方法を説明する透過的模式図である。It is a transparent schematic diagram explaining the joining method of a precast concrete column. プレキャストコンクリート柱の接合方法を説明する透過的模式図である。It is a transparent schematic diagram explaining the joining method of a precast concrete column. 本発明の第1実施形態に係るプレキャストコンクリート柱の接合方法を説明する図である。It is a figure explaining the joining method of the precast concrete column which concerns on 1st Embodiment of this invention. 本発明の第1実施形態に係るプレキャストコンクリート柱の接合方法を説明する図である。It is a figure explaining the joining method of the precast concrete column which concerns on 1st Embodiment of this invention. 本発明の第1実施形態に係るプレキャストコンクリート柱の接合方法を説明する図である。It is a figure explaining the joining method of the precast concrete column which concerns on 1st Embodiment of this invention. 本発明の第2実施形態に係るプレキャストコンクリート柱の接合方法を説明する図である。It is a figure explaining the joining method of the precast-concrete column which concerns on 2nd Embodiment of this invention. 本発明の第2実施形態に係るプレキャストコンクリート柱の接合方法を説明する図である。It is a figure explaining the joining method of the precast-concrete column which concerns on 2nd Embodiment of this invention. 本発明の第2実施形態に係るプレキャストコンクリート柱の接合方法を説明する図である。It is a figure explaining the joining method of the precast-concrete column which concerns on 2nd Embodiment of this invention. 本発明の第3実施形態に係るプレキャストコンクリート柱の接合方法を説明する図である。It is a figure explaining the joining method of the precast-concrete column which concerns on 3rd Embodiment of this invention.

以下、本発明の実施の形態を図面を参照しつつ説明する。まず、図1乃至図4は、前提となるプレキャストコンクリート柱の接合方法の各工程を順に、プレキャストコンクリート柱10とスラブ30とを透過的にみた模式図で示したものである。 BEST MODE FOR CARRYING OUT THE INVENTION Hereinafter, embodiments of the present invention will be described with reference to the drawings. First, FIGS. 1 to 4 are schematic diagrams in which the precast concrete column 10 and the slab 30 are seen transparently, in order, in each process of the precast concrete column joining method.

プレキャストコンクリート柱10には、垂直方向に延びるように、複数の柱側柱主筋13が埋設されている。また、図示していない箇所には、複数の柱側柱主筋13に対して垂直方向に、各柱側柱主筋13を連結する補強筋が設けられている。 A plurality of column side column main reinforcements 13 are embedded in the precast concrete column 10 so as to extend in the vertical direction. Further, reinforcing bars that connect the column side column main reinforcements 13 are provided in a portion not shown in the figure in a direction perpendicular to the plurality of column side column main reinforcements 13 .

それぞれの柱側柱主筋13の下端部は、それぞれの柱側柱主筋13に対応するスリーブ式鉄筋継手部材20に挿通されている。複数のスリーブ式鉄筋継手部材20も、プレキャストコンクリート柱10内に埋設されている。スリーブ式鉄筋継手部材20は、下側端部は開放された状態となっており、上側端部はコンクリート材で閉鎖された状態となっている。 A lower end portion of each column side column main reinforcement 13 is inserted into a sleeve type reinforcing bar joint member 20 corresponding to each column side column main reinforcement 13 . A plurality of sleeve-type rebar joint members 20 are also embedded within the precast concrete column 10 . The sleeve-type reinforcing-bar joint member 20 has an open lower end and a closed upper end with concrete material.

また、複数のスリーブ式鉄筋継手部材20それぞれの内部空間は、その下側で下端開口15と連通しており、上側で上端開口17と連通している。下端開口15及び上端開口17は、プレキャストコンクリート柱10の表面に設けられた開口であり、これらの開口を通してグラウト材が注入されたり或いは、充填した際の余剰のグラウト材が排出されたりするようになっている。 Further, the inner space of each of the plurality of sleeve type reinforcing bar joint members 20 communicates with the lower end opening 15 on the lower side and communicates with the upper end opening 17 on the upper side. The lower end opening 15 and the upper end opening 17 are openings provided on the surface of the precast concrete column 10, and grout material is injected through these openings, or surplus grout material at the time of filling is discharged. It's becoming

一方、プレキャストコンクリート柱10が接合される相手側であるスラブ30にも、複数のスラブ側柱主筋33が埋設されている。これらのスラブ側柱主筋33の上端側はスラブ30から露出するようになっている。また、図示していない箇所において、複数のスラブ側柱主筋33に対して垂直方向に、各スラブ側柱主筋33を連結する補強筋が設けられている。 On the other hand, a plurality of slab side column main reinforcements 33 are also embedded in the slab 30 to which the precast concrete column 10 is joined. The upper end sides of these slab side column main reinforcements 33 are exposed from the slab 30 . In addition, reinforcing bars that connect the slab side pillar main reinforcements 33 are provided in a direction perpendicular to the plurality of slab side pillar main reinforcements 33 at locations not shown.

なお、本実施形態では、プレキャストコンクリート柱10がスラブ30と接合される例に基づいて行うが、このようなスラブ30にはプレキャストコンクリート柱も含まれる。本発明に係るプレキャストコンクリート柱の接合方法は、プレキャストコンクリート柱10同士の接合などにも用い得るものである。 In this embodiment, the precast concrete column 10 is joined to the slab 30, but the slab 30 also includes the precast concrete column. The method for joining precast concrete columns according to the present invention can also be used for joining precast concrete columns 10 to each other.

図1は、プレキャストコンクリート柱10が不図示の吊下手段によって吊り下げられている状態を示している。吊下手段によって吊り下げられているプレキャストコンクリート柱10は降下させられ、目地空間40が残るようにスラブ30上に配される。目地空間40の形成には、スラブ30上に載置される不図示のスペーサーなどが用いられる。 FIG. 1 shows a state in which a precast concrete column 10 is suspended by suspension means (not shown). The precast concrete column 10 suspended by the suspension means is lowered and placed on the slab 30 so that the joint space 40 remains. A spacer (not shown) placed on the slab 30 is used to form the joint space 40 .

目地空間40が形成された状態でプレキャストコンクリート柱10が、スラブ30上に設置されると、続いて図2に示すように、複数のスリーブ式鉄筋継手部材20のうちの一つに対応する下端開口15に、グラウト材を注入するための注入ノズル49が装着される。 When the precast concrete column 10 is installed on the slab 30 with the joint space 40 formed, the lower end corresponding to one of the plurality of sleeve type rebar joint members 20 is subsequently installed as shown in FIG. An injection nozzle 49 for injecting grout material is attached to the opening 15 .

また、スラブ30の上面とプレキャストコンクリート柱10の底面との間に形成された目地空間40の周辺には型枠43が設けられ、目地空間40からグラウト材が溢れ出すことを防止するようになっている。これにより、グラウト材50の注入準備が完了する。 Formwork 43 is provided around the joint space 40 formed between the upper surface of the slab 30 and the bottom surface of the precast concrete column 10 to prevent the grout material from overflowing from the joint space 40. ing. This completes the preparation for injection of the grout material 50 .

続いて、不図示のポンプが駆動されることで、図3に示すように注入ノズル49から、スリーブ式鉄筋継手部材20へとグラウト材50が注入される。スリーブ式鉄筋継手部材20下方から溢れ出したグラウト材50は目地空間40を充填していき、目地空間40全体が充填されると、他のスリーブ式鉄筋継手部材20を下方側から充填していく。スリーブ式鉄筋継手部材20に対応する下端開口15と上端開口17の全てから、グラウト材50が排出されると、目地空間40と全てのスリーブ式鉄筋継手部材20内部空間にグラウト材50が充填されたことが確認できるので、そのようになったらポンプ(不図示)の駆動を停止、グラウト材50の充填を完了する。 Subsequently, a pump (not shown) is driven to inject the grout material 50 from the injection nozzle 49 into the sleeve-type reinforcing-bar joint member 20 as shown in FIG. The grout material 50 overflowing from the bottom of the sleeve type reinforcing bar joint member 20 fills the joint space 40, and when the entire joint space 40 is filled, the other sleeve type reinforcing bar joint member 20 is filled from below. . When the grout material 50 is discharged from all of the lower end opening 15 and the upper end opening 17 corresponding to the sleeve type reinforcing bar joint member 20, the joint space 40 and all internal spaces of the sleeve type reinforcing bar joint member 20 are filled with the grout material 50. When this is confirmed, the driving of the pump (not shown) is stopped, and the filling of the grout material 50 is completed.

その後、グラウト材50の養生を行い、養生が完了すると、目地空間40を囲っていた型枠43を撤去し、図4に示すようにスラブ30と、プレキャストコンクリート柱10との接合が完了する。このような接合方法によれば、目地空間40と、主筋同士の継ぎ手部分(スリーブ式鉄筋継手部材20)との双方を同時に接合することができる。 Thereafter, the grout material 50 is cured, and when the curing is completed, the formwork 43 surrounding the joint space 40 is removed, and the slab 30 and the precast concrete column 10 are joined together as shown in FIG. According to such a joining method, both the joint space 40 and the joint portion between the main bars (sleeve-type reinforcing bar joint member 20) can be joined at the same time.

従来、基本的に上記のようなプレキャストコンクリート柱の接合方法が採用されているが、近年、プレキャストコンクリート柱の断面積が増加傾向にあり、従来のような接合方法では、グラウト材が所望とする充填率で充填されない可能性がある、という問題があった。そこで、本発明では、以下に説明するような接合方法を採用する。 Conventionally, the above-described joining method for precast concrete columns has been basically adopted, but in recent years, the cross-sectional area of precast concrete columns tends to increase, and in the conventional joining method, the grout material is desired. There was a problem that it may not be filled at the filling rate. Therefore, in the present invention, a joining method as described below is adopted.

図5乃至図7は本発明の第1実施形態に係るプレキャストコンクリート柱の接合方法を説明する図である。なお、図5(A)はプレキャストコンクリート柱10を透過的平面図としてみた図であり、図5(B)はスラブ30とプレキャストコンクリート柱10とを側面から見た図である。また、図5乃至図7において、図1乃至図4で説明した注入ノズル49などについては図示省略すると共に、それに関連する工程も説明を省略している。 5 to 7 are diagrams illustrating a method for joining precast concrete columns according to the first embodiment of the present invention. 5A is a transparent plan view of the precast concrete column 10, and FIG. 5B is a side view of the slab 30 and the precast concrete column 10. FIG. 5 to 7, the injection nozzle 49 and the like explained in FIGS. 1 to 4 are omitted from illustration, and the explanation of the processes related thereto is also omitted.

図5に示すプレキャストコンクリート柱10は比較的に大きな断面を有しているものである。スラブ30との間に目地空間40を残して、プレキャストコンクリート柱10が配された後には、目地空間40を分割することが行われる。 The precast concrete column 10 shown in FIG. 5 has a relatively large cross section. The joint space 40 is divided after the precast concrete column 10 is placed, leaving the joint space 40 between the slab 30 and the slab 30 .

具体的には、目地空間40に離隔部材としてエアチューブ型枠100を配し、目地空間40をエアチューブ型枠100(離隔部材)で離隔し、複数の分割目地空間とする。本実施形態では、エアチューブ型枠100(離隔部材)により、目地空間40を分割目地空間40a、40bの2つの空間に分割する例に基づいて説明を行うが、本発明で目地空間を離隔して幾つの分割目地空間とするかは任意である。 Specifically, an air tube formwork 100 is arranged as a separation member in the joint space 40, and the joint space 40 is separated by the air tube formwork 100 (separation member) to form a plurality of divided joint spaces. In the present embodiment, an example in which the joint space 40 is divided into two spaces, ie, divided joint spaces 40a and 40b, by the air tube formwork 100 (separating member) will be described. The number of divided joint spaces is arbitrary.

また、上記のように、目地空間40に離隔部材としてエアチューブ型枠100を配する前段においては、エアチューブ型枠100に離型剤を塗布しておくと、養生後のグラウト材からの取り外しが容易となるので好ましい。目地空間40を離隔するために用いられるエアチューブ型枠100は、注入されるグラウト材の圧に負けて対象外の分割目地空間にグラウト材が移動しない程度に密かつ強固に取り付けられる。 In addition, as described above, before the air tube formwork 100 is placed as a separating member in the joint space 40, if a release agent is applied to the air tube formwork 100, it can be removed from the grout material after curing. is preferred because it facilitates The air tube formwork 100 used to separate the joint spaces 40 is attached densely and firmly to the extent that the grout material does not move to the non-target split joint space due to the pressure of the injected grout material.

目地空間40に配するエアチューブ型枠100は、コンプレッサ(不図示)によって空気が導入されることで膨張するホース状部分を有するエアー型枠である。エアチューブ型枠100は、空気の導入・排出によって膨張・収縮するので、そのセットそして脱型を容易に行うことができる、というメリットがある。ただし、本発明に係るプレキャストコンクリート柱の接合方法では、離隔部材として、例えば、ギャップガード(登録商標)などのエアチューブ型枠100のみならず、細径エアフェンス、発泡ポリエチレン製型枠(例えば、エサフォーム(登録商標)など)、硬練りのグラウト材、角材、山形鋼などを利用することも可能である。 The air tube mold 100 arranged in the joint space 40 is an air mold having a hose-like portion that expands when air is introduced by a compressor (not shown). Since the air tube formwork 100 expands and contracts by introducing and discharging air, it has the advantage that it can be easily set and demolded. However, in the method for joining precast concrete columns according to the present invention, the separation member is not only an air tube formwork 100 such as Gap Guard (registered trademark), but also a small diameter air fence, a formwork made of polyethylene foam (for example, Esafoam (registered trademark, etc.), hard-kneaded grout, square timber, angle steel, and the like can also be used.

さて、上記のようにエアチューブ型枠100によって、目地空間40を2つの分割目地空間40a、40bとした後には、一方の分割目地空間に対してグラウト材50を充填する準備がなされる。図5に示す例は、分割目地空間40aに対してグラウト材50を充填する準備がなされている様子であり、分割目地空間40aの周囲には型枠43が取り付けられている。 Now, after dividing the joint space 40 into the two divided joint spaces 40a and 40b by the air tube formwork 100 as described above, preparations are made to fill one of the divided joint spaces with the grout material 50. FIG. In the example shown in FIG. 5, preparations are being made to fill the split joint space 40a with the grout material 50, and a formwork 43 is attached around the split joint space 40a.

図5のように型枠43が取り付けられた後に、続いて、図1乃至図4の例で説明したように、複数のスリーブ式鉄筋継手部材20のうちの一つからグラウト材50が注入され、分割目地空間40a、分割目地空間40aと連通する全てのスリーブ式鉄筋継手部材20にグラウト材50が充填される。グラウト材50が注入される工程が実施されることで図6に示すような状態となる。このようにグラウト材50が充填され、養生が行われる。 After the formwork 43 is attached as shown in FIG. 5, the grout material 50 is subsequently injected from one of the plurality of sleeve type reinforcing bar joint members 20 as described in the examples of FIGS. 1 to 4. , the split joint space 40a, and all the sleeve-type reinforcing-bar joint members 20 communicating with the split joint space 40a are filled with the grout material 50. As shown in FIG. The state shown in FIG. 6 is obtained by performing the step of injecting the grout material 50 . The grout material 50 is thus filled and cured.

なお、グラウト材注入では、複数のスリーブ式鉄筋継手部材20のうちの一つからグラウト材50を注入すればよいが、より好ましくは、平面視で矩形の分割目地空間の角部に近いスリーブ式鉄筋継手部材のうちから一つを選択することがよい。具体的には、図5(A)で言えば、(p)、(q)、(r)、(s)からグラウト材50をするスリーブ式鉄筋継手部材を選択するとよい。角部に近いスリーブ式鉄筋継手部材を選択すると、より均等にグラウト材50が注入される。 In the grouting material injection, the grouting material 50 may be injected from one of the plurality of sleeve-type reinforcing-bar joint members 20. More preferably, the sleeve-type grouting material 50 near the corners of the rectangular split joint space in plan view It is preferable to select one of the reinforcing bar joint members. Specifically, referring to FIG. 5(A), it is preferable to select a sleeve-type reinforcing-bar joint member for grout material 50 from (p), (q), (r), and (s). Selecting a sleeved rebar joint member closer to the corner will result in a more even distribution of the grout material 50 .

分割目地空間40aに充填したグラウト材50の養生が完了すると次の工程に移る。続く工程では、分割目地空間40aに隣接する他の分割目地空間40bとの間に配されているエアチューブ型枠100を撤去がされ、さらに分割目地空間40aを囲んでいた型枠43も取り除かれる。エアチューブ型枠100を撤去する際には、導入されていた空気を排出して収縮させてから、これを行うと作業性がよい。 When curing of the grout material 50 filled in the divided joint space 40a is completed, the next step is performed. In the subsequent step, the air tube formwork 100 disposed between the joint division space 40a and another joint division space 40b adjacent to it is removed, and the formwork 43 surrounding the joint division space 40a is also removed. . When removing the air tube formwork 100, workability is improved if the introduced air is discharged and contracted before this is done.

さらに、他の分割目地空間である40b側の周辺に、型枠43が取り付けられる。続いて、分割目地空間40bと連通する複数のスリーブ式鉄筋継手部材20のうちの一つからグラウト材50が注入される。ここでも、平面視で矩形の分割目地空間40bの角部に近いスリーブ式鉄筋継手部材のうちから一つが選択される。 Furthermore, a formwork 43 is attached around the side of 40b, which is another divided joint space. Subsequently, the grout material 50 is injected from one of the plurality of sleeve-type reinforcing-bar joint members 20 communicating with the divided joint space 40b. Again, one of the sleeve-type reinforcing-bar joint members near the corners of the divided joint space 40b, which is rectangular in plan view, is selected.

分割目地空間40b、分割目地空間40bと連通する全てのスリーブ式鉄筋継手部材20にグラウト材50が充填されると図7に示すような状態となる。そして、続いて、グラウト材50の養生が行われる。グラウト材50の養生が完了すると型枠43が撤去されて、本発明に係るプレキャストコンクリート柱の接合方法における各工程が終了する。 When the split joint space 40b and all the sleeve-type reinforcing-bar joint members 20 communicating with the split joint space 40b are filled with the grout material 50, the state shown in FIG. 7 is obtained. Subsequently, curing of the grout material 50 is performed. When the curing of the grout material 50 is completed, the formwork 43 is removed, and each step in the method for joining precast concrete columns according to the present invention is completed.

以上のように、本発明に係るプレキャストコンクリート柱の接合方法は、目地空間40に離隔部材(エアチューブ型枠100)を配し、目地空間40を離隔部材(エアチューブ型枠100)で離隔し、複数の分割目地空間とし、それぞれにグラウト材50を充填し養生する工程を経るようになっており、このような本発明に係るプレキャストコンクリート柱の接合方法によれば、大断面のプレキャストコンクリート柱10でも、適切な面積の分割目地空間に分割された上でグラウト材50が充填されるので、十分なグラウト充填率が確保することができ、信頼性の高い施工を行うことが可能となる。 As described above, in the method for joining precast concrete columns according to the present invention, the separation member (air tube formwork 100) is placed in the joint space 40, and the joint space 40 is separated by the separation member (air tube formwork 100). , a plurality of divided joint spaces, each of which is filled with grout material 50 and cured. According to the method for joining precast concrete columns according to the present invention, a precast concrete column with a large cross section Even in 10, since the grout material 50 is filled after being divided into divided joint spaces with an appropriate area, a sufficient grout filling rate can be secured and highly reliable construction can be performed.

次に本発明に係る他の実施形態について説明する。先の第1実施形態では、目地空間40を離隔部材(エアチューブ型枠100)で離隔し、2つの分割目地空間40a、40bとして、段階的にそれぞれの分割目地空間毎にグラウト材を充填し、養生を行うようにしていた。これに対して、第2実施形態では、目地空間40を離隔部材(エアチューブ型枠100)で離隔し、2つの分割目地空間40a、40bとした後、略同時にそれぞれの分割目地空間毎にグラウト材を充填し、養生を行うものである。以下、図8乃至図10に基づいて、第2実施形態に係るプレキャストコンクリート柱の接合方法を説明する。 Next, another embodiment according to the present invention will be described. In the first embodiment described above, the joint space 40 is separated by the separation member (the air tube formwork 100) to form two divided joint spaces 40a and 40b, and the grout material is filled in each of the divided joint spaces step by step. , I was trying to take care of myself. On the other hand, in the second embodiment, after the joint space 40 is separated by the separation member (the air tube formwork 100) to form two divided joint spaces 40a and 40b, grout is applied to each of the divided joint spaces substantially simultaneously. It is filled with material and cured. A method for joining precast concrete columns according to the second embodiment will be described below with reference to FIGS. 8 to 10 .

なお、図8(A)はプレキャストコンクリート柱10を透過的平面図としてみた図であり、図8(B)はスラブ30とプレキャストコンクリート柱10とを側面から見た図である。また、図8乃至図10において、図1乃至図4で説明した注入ノズル49などについては図示省略すると共に、それに関連する工程も説明を省略している。 8A is a transparent plan view of the precast concrete column 10, and FIG. 8B is a side view of the slab 30 and the precast concrete column 10. FIG. 8 to 10, the injection nozzle 49 and the like explained in FIGS. 1 to 4 are omitted from illustration, and the explanation of the processes related thereto is also omitted.

図8に示すプレキャストコンクリート柱10は比較的に大きな断面を有するものである。スラブ30との間に目地空間40を残して、プレキャストコンクリート柱10が配された後には、目地空間40を分割することが行われる。 The precast concrete column 10 shown in FIG. 8 has a relatively large cross section. The joint space 40 is divided after the precast concrete column 10 is placed, leaving the joint space 40 between the slab 30 and the slab 30 .

具体的には、目地空間40に離隔部材として2本のエアチューブ型枠100を配し、目地空間40を2本のエアチューブ型枠100(離隔部材)で離隔し、複数の分割目地空間とする。本実施形態では、2本のエアチューブ型枠100(離隔部材)により、目地空間40を分割目地空間40a、40bの2つの空間に分割する例に基づいて説明を行うが、本発明で目地空間を離隔して幾つの分割目地空間とするかは任意である。 Specifically, two air tube forms 100 are arranged as separating members in the joint space 40, and the joint space 40 is separated by the two air tube forms 100 (separating members) to form a plurality of divided joint spaces. do. In this embodiment, an example in which the joint space 40 is divided into two divided joint spaces 40a and 40b by two air tube forms 100 (separating members) will be described. It is arbitrary how many divided joint spaces are separated from each other.

また、本実施形態においても、目地空間40に離隔部材としてエアチューブ型枠100を配する前段においては、エアチューブ型枠100に離型剤を塗布しておくようにすることが好ましい。また、目地空間40に配する離隔部材としては、エアチューブ型枠100などのエアー型枠(例えば、ギャップガード(登録商標)など)或いは細径エアフェンスの他に、発泡ポリエチレン製型枠(例えば、エサフォーム(登録商標)など)、硬練りのグラウト材、角材、山形鋼などを利用することも可能である。 Also in the present embodiment, it is preferable to apply a mold release agent to the air tube form 100 before disposing the air tube form 100 as a separating member in the joint space 40 . In addition, as the separation member arranged in the joint space 40, in addition to an air formwork such as the air tube formwork 100 (for example, Gap Guard (registered trademark), etc.) or a small-diameter air fence, a polyethylene foam formwork (for example, , Esafoam (registered trademark), etc.), hard grout, square timber, angle steel, and the like can also be used.

2本のエアチューブ型枠100によって、目地空間40を2つの分割目地空間40a、40bとした後には、両方の分割目地空間に対してグラウト材50を充填する準備がなされる。図8に示す例は、分割目地空間40a及び分割目地空間40bの両方に対してグラウト材50を充填する準備がなされている様子であり、分割目地空間40a及び分割目地空間40bの両方の周囲に型枠43が取り付けられる。 After the two air tube forms 100 divide the joint space 40 into two split joint spaces 40a, 40b, preparations are made to fill both split joint spaces with the grout material 50. As shown in FIG. The example shown in FIG. 8 shows preparations for filling both the divided joint space 40a and the divided joint space 40b with the grout material 50, and around both the divided joint space 40a and the divided joint space 40b. A formwork 43 is attached.

図8のように型枠43が取り付けられた後に、分割目地空間40aに対応するスリーブ式鉄筋継手部材20のうちの一つからグラウト材50が注入され、ほぼ同時期に、分割目地空間40bに対応するスリーブ式鉄筋継手部材20のうちの一つからグラウト材50が注入される。これにより、分割目地空間40a、40b及びこれらに連通する全てのスリーブ式鉄筋継手部材20にグラウト材50が充填される。なお、グラウト材50の注入口として選択されるスリーブ式鉄筋継手部材20は、先の実施形態と同様、平面視で矩形の分割目地空間の角部に近いスリーブ式鉄筋継手部材のうちから一つを選択する。 After the formwork 43 is attached as shown in FIG. 8, the grout material 50 is injected from one of the sleeve-type reinforcing-bar joint members 20 corresponding to the split joint space 40a, and almost simultaneously into the split joint space 40b. Grout material 50 is injected from one of the corresponding sleeved rebar joint members 20 . As a result, the split joint spaces 40a, 40b and all the sleeve-type reinforcing-bar joint members 20 communicating with them are filled with the grout material 50. As shown in FIG. As in the previous embodiment, the sleeve-type reinforcing-bar joint member 20 selected as the injection port for the grout material 50 is one of the sleeve-type reinforcing-bar joint members near the corners of the rectangular split joint space in plan view. to select.

上記のように、グラウト材50が注入される工程が実施されることで図9に示すような状態となる。このようにグラウト材50が充填され、養生が行われる。 As described above, the state shown in FIG. 9 is obtained by performing the step of injecting the grout material 50 . The grout material 50 is thus filled and cured.

分割目地空間40a及び分割目地空間40bに充填したグラウト材50の養生が完了すると次の工程に移る。続く工程では、分割目地空間40aと、これに隣接する他の分割目地空間40bとの間に配されている2本のエアチューブ型枠100が引き抜かれることで撤去がされ、さらに分割目地空間40a、分割目地空間40bを囲んでいた型枠43も取り除かれる。 When curing of the grout material 50 filled in the divided joint space 40a and the divided joint space 40b is completed, the next step is performed. In the subsequent step, the two air tube forms 100 arranged between the divided joint space 40a and the other divided joint space 40b adjacent thereto are pulled out and removed, and the divided joint space 40a is removed. , the formwork 43 surrounding the split joint space 40b is also removed.

ここで、本実施形態においては、目地空間40を2つの分割目地空間40a、40bとして離隔する際に、2本のエアチューブ型枠100を用いる理由について説明する。 Here, in this embodiment, the reason why two air tube forms 100 are used when dividing the joint space 40 into two divided joint spaces 40a and 40b will be described.

エアチューブ型枠100の先端部110は、カシメられることによって形成されている。従って、先端部110の幅は、空気が充填されるホース状部分の幅より大きい。仮に、1本のエアチューブ型枠100のみを用いて分割目地空間40aと40bを形成して、両方の分割目地空間にグラウト材50を充填・養生・固化した後、エアチューブ型枠100の空気を排出して引き抜こうとしても、固化したグラウト材50に先端部110が当たることで、当該1本のエアチューブ型枠100を引き抜くことが困難となってしまう。そこで、本実施形態においては、2本のエアチューブ型枠100を用いてグラウト材50が固化した後にできる空間を広めの空間とすることで、エアチューブ型枠100を引き抜きやすくするようにしている。 A tip portion 110 of the air tube formwork 100 is formed by caulking. Therefore, the width of the tip 110 is greater than the width of the hose-like portion filled with air. Suppose that the split joint spaces 40a and 40b are formed using only one air tube formwork 100, and the grout material 50 is filled, cured, and solidified in both split joint spaces, and then the air in the air tube formwork 100 Even if an attempt is made to extract the air tube formwork 100 by discharging the air tube formwork 100, the solidified grout material 50 is hit by the tip portion 110, making it difficult to pull out the single air tube formwork 100.例文帳に追加Therefore, in the present embodiment, the space created after the grout material 50 is solidified using the two air tube molds 100 is widened so that the air tube molds 100 can be easily pulled out. .

上記のように分割目地空間40a、40bにグラウト材50が充填・固化された後、2本のエアチューブ型枠100が引き抜かれる。続いて、2本のエアチューブ型枠100が引き抜かれた後に形成される分割目地空間40aと分割目地空間40bとの間の空間(図10の40c)に、グラウト材50を充填する工程が実施される。この準備のために、図10に示すように、空間40c全てにグラウト材50を充填した際に堰となる型枠43が、空間40cの両端開口部に設けられる。このような型枠43が設けられた後、空間40cにグラウト材50が充填され、養生が実施される。空間40cの前記両端開口部から溢れて固化したグラウト材50はカッターなどで除去される。 After the grout material 50 is filled and solidified in the divided joint spaces 40a and 40b as described above, the two air tube forms 100 are pulled out. Subsequently, a step of filling the grout material 50 into the space (40c in FIG. 10) between the divided joint space 40a and the divided joint space 40b formed after the two air tube forms 100 are pulled out is performed. be done. For this preparation, as shown in FIG. 10, forms 43 that act as weirs when the entire space 40c is filled with the grout material 50 are provided at both end openings of the space 40c. After such a formwork 43 is provided, the space 40c is filled with the grout material 50 and cured. The grout material 50 overflowing from the both end openings of the space 40c and solidified is removed with a cutter or the like.

以上のように、第2実施形態に係るプレキャストコンクリート柱の接合方法は、目地空間40に離隔部材(エアチューブ型枠100)を配し、目地空間40を離隔部材(エアチューブ型枠100)で離隔し、複数の分割目地空間とし、それぞれの分割目地空間にグラウト材50をほぼ同時期に充填し養生する工程を経るようになっている。 As described above, in the method for joining precast concrete columns according to the second embodiment, the separation member (air tube formwork 100) is arranged in the joint space 40, and the joint space 40 is formed by the separation member (air tube formwork 100). A plurality of divided joint spaces are separated from each other, and grout material 50 is filled and cured in each divided joint space almost at the same time.

このような第2実施形態に係るプレキャストコンクリート柱の接合方法によれば、大断面のプレキャストコンクリート柱10でも、適切な面積の分割目地空間に分割された上でグラウト材50が充填されるので、十分なグラウト充填率が確保することができ、信頼性の高い施工を行うことが可能となる。さらに、第2実施形態に係るプレキャストコンクリート柱の接合方法によれば、それぞれの分割目地空間にグラウト材50をほぼ同時期に充填し養生するので、主要となる工程に要する時間を短縮することができる。 According to the method for joining precast concrete columns according to the second embodiment, even a precast concrete column 10 having a large cross section is divided into divided joint spaces having appropriate areas and then filled with the grout material 50. A sufficient grout filling rate can be secured, and highly reliable construction can be performed. Furthermore, according to the method for joining precast concrete columns according to the second embodiment, the grout material 50 is filled and cured in the divided joint spaces at approximately the same time, so the time required for the main steps can be shortened. can.

次に本発明に係る他の実施形態について説明する。これまでの実施形態では、目地空間40を離隔し分割目地空間を形成するために、エアチューブ型枠100などの離隔部材を用いるようにしていた。これに対して、第3実施形態に係るプレキャストコンクリート柱の接合方法では、固練りしたグラウト材を離隔部材とし、この離隔部材で目地空間40を離隔し分割目地空間を形成するものである。 Next, another embodiment according to the present invention will be described. In the embodiments so far, a separating member such as the air tube formwork 100 has been used to separate the joint spaces 40 and form the divided joint spaces. On the other hand, in the method for joining precast concrete columns according to the third embodiment, a hard-kneaded grout material is used as a separating member, and the joint space 40 is separated by the separating member to form a divided joint space.

以下、図11を参照して第3実施形態に係るプレキャストコンクリート柱の接合方法について説明する。図11は、プレキャストコンクリート柱10が不図示の吊下手段によって吊り下げられている状態を示している。吊下手段によって吊り下げられているプレキャストコンクリート柱10は降下させられ、目地空間40が残るようにスラブ30上に配されるが、プレキャストコンクリート柱10がスラブ30上に配される前段に、本実施形態では固練りした先行グラウト材150を、目地空間となる予定箇所に設けておく。 Hereinafter, a method for joining precast concrete columns according to the third embodiment will be described with reference to FIG. 11 . FIG. 11 shows a state in which the precast concrete column 10 is suspended by suspension means (not shown). The precast concrete column 10 suspended by the suspension means is lowered and placed on the slab 30 so that the joint space 40 remains. In the embodiment, the preliminarily kneaded preceding grout material 150 is provided at a location to be a joint space.

先行グラウト材150の分量は、離隔部材として機能するエアチューブ型枠100の容積より若干多い程度とすることが望ましい。また、先行グラウト材150を配する際には、その高さは目地空間40の高さより高く盛るようにする。また、先行グラウト材150を配する箇所は、第1実施形態でエアチューブ型枠100を配した箇所と同様とする。 It is desirable that the volume of the leading grout material 150 is slightly larger than the volume of the air tube formwork 100 that functions as the separating member. Further, when the preceding grout material 150 is arranged, its height is set higher than the height of the joint space 40.例文帳に追加Also, the location where the preceding grout material 150 is arranged is the same as the location where the air tube formwork 100 is arranged in the first embodiment.

図11の状態からプレキャストコンクリート柱10を降下し、目地空間40が残るようにスラブ30上にこれを配する。プレキャストコンクリート柱10が配されると、先行グラウト材150の分量と高さの関係から、プレキャストコンクリート柱10の底面が先行グラウト材150の上部が押し潰される。これにより、目地空間40は先行グラウト材150で離隔され、2つの分割目地空間が形成される。先行グラウト材150が固化すると、続いて、第2実施形態同様、2つの分割目地空間に対して、グラウト材50をほぼ同時期に充填し養生する。これによれば、第3実施形態に係るプレキャストコンクリート柱の接合方法でも、主要となる工程に要する時間を短縮することができる。 The precast concrete column 10 is lowered from the state shown in FIG. 11 and placed on the slab 30 so that the joint space 40 remains. When the precast concrete column 10 is placed, the bottom surface of the precast concrete column 10 and the upper portion of the preceding grout material 150 are crushed due to the relationship between the amount and height of the preceding grout material 150 . Thereby, the joint space 40 is separated by the leading grout material 150 to form two divided joint spaces. After the preceding grout material 150 is solidified, the two divided joint spaces are filled with the grout material 50 and cured at substantially the same time as in the second embodiment. According to this, even in the method for joining precast concrete columns according to the third embodiment, the time required for the main steps can be shortened.

以上、本発明に係るプレキャストコンクリート柱の接合方法は、目地空間に離隔部材を配し、目地空間を離隔部材で離隔し、複数の分割目地空間とし、それぞれにグラウト材を充填し養生する工程を経るようになっており、このような本発明に係るプレキャストコンクリート柱の接合方法によれば、大断面のプレキャストコンクリート柱でも、適切な面積の分割目地空間に分割された上でグラウト材が充填されるので、十分なグラウト充填率が確保することができ、信頼性の高い施工を行うことが可能となる。 As described above, the method for joining precast concrete columns according to the present invention includes the steps of disposing a separating member in a joint space, separating the joint space with the separating member to form a plurality of divided joint spaces, and filling and curing each of the divided joint spaces with a grout material. According to the method for joining precast concrete columns according to the present invention, even a precast concrete column with a large cross section can be divided into divided joint spaces having appropriate areas and then filled with grout material. Therefore, a sufficient grout filling rate can be secured, and highly reliable construction can be performed.

10・・・プレキャストコンクリート柱
13・・・柱側柱主筋
15・・・下端開口
17・・・上端開口
20・・・スリーブ式鉄筋継手部材
30・・・スラブ
33・・・スラブ側柱主筋
40・・・目地空間
40a、40b・・・分割目地空間
40c・・・(分割目地)空間
43・・・型枠
49・・・注入ノズル
50・・・グラウト材
100・・・エアチューブ型枠(離隔部材)
110・・・先端部
150・・・先行グラウト材(離隔部材)
Reference Signs List 10 Precast concrete column 13 Column side column main reinforcement 15 Bottom end opening 17 Top end opening 20 Sleeve type reinforcing bar joint member 30 Slab 33 Slab side column main reinforcement 40 ... joint space 40a, 40b ... divided joint space 40c ... (divided joint) space 43 ... formwork 49 ... injection nozzle 50 ... grout material 100 ... air tube formwork ( separation member)
110... Tip part 150... Leading grout material (separating member)

Claims (3)

複数のスリーブ式鉄筋継手部材が内挿されたプレキャストコンクリート柱をスラブ上に接合するプレキャストコンクリート柱の接合方法であって、
前記スラブとの間に目地空間を設けて前記プレキャストコンクリート柱を配する工程と、
前記目地空間に離隔部材を配し、前記目地空間を離隔部材で離隔し、複数の分割目地空間とする工程と、
一の分割目地空間にスリーブ式鉄筋継手部材を介してグラウトを充填し養生する工程と、
前記一の分割目地空間に充填したグラウトの養生が完了した後、前記一の分割目地空間に隣接する他の分割目地空間との間に配された離隔部材を撤去する工程と、
前記他の分割目地空間にスリーブ式鉄筋継手部材を介してグラウトを充填し養生する工程と、
を含むことを特徴とするプレキャストコンクリート柱の接合方法。
A precast concrete column joining method for joining a precast concrete column in which a plurality of sleeve type reinforcing bar joint members are inserted onto a slab, comprising:
providing a joint space between the slab and arranging the precast concrete column;
a step of disposing a separation member in the joint space and separating the joint space with the separation member to form a plurality of divided joint spaces;
A step of filling and curing grout in one divided joint space via a sleeve type reinforcing bar joint member;
After the curing of the grout filled in the one divided joint space is completed, a step of removing the separating member disposed between the one divided joint space and another divided joint space adjacent to the one divided joint space;
a step of filling the other divided joint space with grout through a sleeve-type reinforcing bar joint member and curing the grout;
A method for joining precast concrete columns, comprising:
複数のスリーブ式鉄筋継手部材が内挿されたプレキャストコンクリート柱をスラブ上に接合するプレキャストコンクリート柱の接合方法であって、
前記スラブとの間に目地空間を設けて前記プレキャストコンクリート柱を配する工程と、
前記目地空間に離隔部材を配し、前記目地空間を離隔部材で離隔し、複数の分割目地空間とする工程と、
一の分割目地空間にスリーブ式鉄筋継手部材を介してグラウトを充填し養生する工程と、
前記一の分割目地空間に隣接する他の分割目地空間にスリーブ式鉄筋継手部材を介してグラウトを充填し養生する工程と、
前記一の分割目地空間に充填したグラウトと、前記他の分割目地空間に充填したグラウトの養生が完了した後、前記一の分割目地空間に隣接する他の分割目地空間との間に配された離隔部材を撤去する工程と、
前記離隔部材を撤去した後に形成された空間にてグラウトを充填し養生する工程と、
を含むことを特徴とするプレキャストコンクリート柱の接合方法。
A precast concrete column joining method for joining a precast concrete column in which a plurality of sleeve type reinforcing bar joint members are inserted onto a slab, comprising:
providing a joint space between the slab and arranging the precast concrete column;
a step of disposing a separation member in the joint space and separating the joint space with the separation member to form a plurality of divided joint spaces;
A step of filling and curing grout in one divided joint space via a sleeve type reinforcing bar joint member;
a step of filling and curing grout into another divided joint space adjacent to the one divided joint space via a sleeve type reinforcing bar joint member;
After curing of the grout filled in the one divided joint space and the grout filled in the other divided joint space is completed, it is arranged between the other divided joint space adjacent to the one divided joint space. removing the separating member;
a step of filling and curing grout in the space formed after removing the spacing member;
A method for joining precast concrete columns, comprising:
複数のスリーブ式鉄筋継手部材が内挿されたプレキャストコンクリート柱をスラブ上に接合するプレキャストコンクリート柱の接合方法であって、
前記プレキャストコンクリート柱が配されることで、前記スラブと前記プレキャストコンクリート柱の間で目地空間となる予定箇所に、前記目地空間を離隔し、複数の分割目地空間とする離隔部材を配する工程と、
前記スラブとの間に目地空間を設けて前記プレキャストコンクリート柱を配する工程と、
一の分割目地空間にスリーブ式鉄筋継手部材を介してグラウトを充填し養生する工程と、
前記一の分割目地空間に隣接する他の分割目地空間にスリーブ式鉄筋継手部材を介してグラウトを充填し養生する工程と、
を含むことを特徴とするプレキャストコンクリート柱の接合方法。
A precast concrete column joining method for joining a precast concrete column in which a plurality of sleeve type reinforcing bar joint members are inserted onto a slab, comprising:
arranging a separation member to separate the joint space and to form a plurality of divided joint spaces in a portion where the precast concrete column is arranged to form a joint space between the slab and the precast concrete column; ,
providing a joint space between the slab and arranging the precast concrete column;
A step of filling and curing grout in one divided joint space via a sleeve type reinforcing bar joint member;
a step of filling and curing grout into another divided joint space adjacent to the one divided joint space via a sleeve type reinforcing bar joint member;
A method for joining precast concrete columns, comprising:
JP2019025119A 2019-02-15 2019-02-15 Method of joining precast concrete columns Active JP7175215B2 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
JP2019025119A JP7175215B2 (en) 2019-02-15 2019-02-15 Method of joining precast concrete columns
JP2022177756A JP7330346B2 (en) 2019-02-15 2022-11-07 Method of joining precast concrete columns

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2019025119A JP7175215B2 (en) 2019-02-15 2019-02-15 Method of joining precast concrete columns

Related Child Applications (1)

Application Number Title Priority Date Filing Date
JP2022177756A Division JP7330346B2 (en) 2019-02-15 2022-11-07 Method of joining precast concrete columns

Publications (2)

Publication Number Publication Date
JP2020133158A JP2020133158A (en) 2020-08-31
JP7175215B2 true JP7175215B2 (en) 2022-11-18

Family

ID=72277894

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2019025119A Active JP7175215B2 (en) 2019-02-15 2019-02-15 Method of joining precast concrete columns

Country Status (1)

Country Link
JP (1) JP7175215B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112282214A (en) * 2020-09-21 2021-01-29 华南理工大学 Prefabricated FRP (fiber reinforced plastic) pipe-concrete-steel pipe combined column and construction method thereof

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02248543A (en) * 1989-03-20 1990-10-04 Fujita Corp Connecting method for precast concrete column
JPH10147978A (en) * 1996-11-19 1998-06-02 Nippon Splice Sleeve Kk Vertical member joining and erecting method for precast reinforced concrete

Also Published As

Publication number Publication date
JP2020133158A (en) 2020-08-31

Similar Documents

Publication Publication Date Title
KR100951097B1 (en) Slab and subgrade external wall structure and method for constructing underground slab and subgrade external wall, bracket
KR101842475B1 (en) Monolithically poured top pile foundation with cast-in-placed lower reinforced part and construction method thereof
JP6792329B2 (en) Construction method of column beam frame using precast concrete columns
CN108086488B (en) Assembled frame shear structure wall staggered connection structure and assembling method
JP2011094313A (en) Method for separately placing concrete in column-beam joint portion
CN206707055U (en) Assembled filling wall, inner wall structure and external wall structure
JP4866641B2 (en) Precast pillar manufacturing method, precast pillar construction method
JP7175215B2 (en) Method of joining precast concrete columns
JP7330346B2 (en) Method of joining precast concrete columns
KR102235873B1 (en) Fabrication method of partial pier cap, partial pier cap, and construction method of pier using partial pier cap
JPH08135087A (en) Precast concrete column member and joint method thereof
JP2017095915A (en) Junction structure between column-beam joint part and column, rigid-frame viaduct, construction method for junction structure between column-beam joint part and column, and precast concrete member
KR100640244B1 (en) Method for constructing underground slabs and walls using erection piles without preliminary wall-attached supports
JP2020084580A (en) Construction method of earth retaining wall structure in inverted construction method
CN205558007U (en) Can pack wallboard with atress structure synchronous construction's prefabrication
JP3914457B2 (en) Joining method of precast panel zone and lower column member
JPH0480444A (en) Connection unit of reinforced concrete pole and steel framed beam
JP7231523B2 (en) Concrete building and its construction method
JPH08144425A (en) Prefabricated member of mixed structure and construction method of mixed structure
JP2008014047A (en) Beam-column connection portion structure and method of constructing the same
JP6737722B2 (en) Body joint structure and concrete pouring method
JPS6311734A (en) Construction method for bonding pillar and concrete slab
KR100517373B1 (en) Wall Structure Using Tapered Hollow Precast Concrete Pannel and Constructing Method thereof
JP6931976B2 (en) Concrete placing method for vertical skeleton by post-casting
KR100694762B1 (en) Method for constructing underground slabs and walls without preliminary wall-attached supports

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20211223

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20221006

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20221019

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20221108

R150 Certificate of patent or registration of utility model

Ref document number: 7175215

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150