JP7068123B2 - Pipe members, sand recovery systems, and sand recovery vessels - Google Patents

Pipe members, sand recovery systems, and sand recovery vessels Download PDF

Info

Publication number
JP7068123B2
JP7068123B2 JP2018181662A JP2018181662A JP7068123B2 JP 7068123 B2 JP7068123 B2 JP 7068123B2 JP 2018181662 A JP2018181662 A JP 2018181662A JP 2018181662 A JP2018181662 A JP 2018181662A JP 7068123 B2 JP7068123 B2 JP 7068123B2
Authority
JP
Japan
Prior art keywords
sand
pipe
pipe portion
earth
pump
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2018181662A
Other languages
Japanese (ja)
Other versions
JP2020051125A (en
Inventor
敏之 長野
宣宏 鈴木
Original Assignee
りんかい日産建設株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by りんかい日産建設株式会社 filed Critical りんかい日産建設株式会社
Priority to JP2018181662A priority Critical patent/JP7068123B2/en
Publication of JP2020051125A publication Critical patent/JP2020051125A/en
Application granted granted Critical
Publication of JP7068123B2 publication Critical patent/JP7068123B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Description

本発明は、管部材、砂回収システム、及び砂回収船に関する。 The present invention relates to a pipe member, a sand recovery system, and a sand recovery ship.

港湾、河川、湖沼等の浚渫作業で発生する土砂は、近くに埋め立て用地があるときは、埋め立て用地に送られ、埋め立て用土砂として再利用されることが多かった。浚渫作業現場の近くに埋め立て用地がない場合は、遠隔地にある埋め立て用地や土捨て場まで浚渫した土砂を運ぶ必要がある。一方、浚渫した土砂には、建設や土木工事に再利用可能な砂が含まれている。 When there is a landfill site nearby, the earth and sand generated by dredging work in harbors, rivers, lakes and marshes is often sent to the landfill site and reused as landfill earth and sand. If there is no landfill near the dredging work site, it is necessary to carry the dredged soil to a remote landfill or dumping site. On the other hand, the dredged earth and sand contains sand that can be reused for construction and civil engineering work.

そこで、浚渫作業現場近くで、浚渫作業で発生した土砂から砂を回収して再利用を図り、残った泥土を遠隔地にある埋め立て用地や土捨て場に運搬するようにすれば、運搬量が減少するので運搬コストの低減が可能となる。また、浚渫作業で発生した土砂から砂を回収して残った泥土のみを処分するので、処分量が少なくなり、土捨て場を延命することができる。 Therefore, if sand is collected from the earth and sand generated during the dredging work and reused near the dredging work site, and the remaining mud is transported to a remote landfill site or dumping site, the amount of transportation will be increased. Since it is reduced, it is possible to reduce the transportation cost. In addition, since the sand is collected from the earth and sand generated by the dredging work and only the remaining mud is disposed of, the amount of disposal is reduced and the life of the earth dumping site can be extended.

例えば、特許文献1には、砂分を含む浚渫土砂と水とが混合された泥水が、ポンプ輸送される送泥管路の途中に、粗粒分と細粒分とに分離させる粗分級手段を備え、更に希釈水を高含砂泥水に混合させ、高含砂泥水を沈殿分級槽で沈殿させる方法が開示されている。 For example, in Patent Document 1, a coarse classification means for separating mud water, which is a mixture of dredged earth and sand containing sand and water, into coarse particles and fine particles in the middle of a mud feed pipe transported by a pump. Further, a method of mixing diluted water with highly sand-containing muddy water and precipitating the highly sand-containing muddy water in a precipitation classification tank is disclosed.

特開2004-097873号公報Japanese Unexamined Patent Publication No. 2004-097873

しかし、特許文献1に記載の発明は、送泥管路の途中に設けられる粗粒分と細粒分とに分離させる粗分級手段の構造が複雑であり、又、沈殿槽において砂分を沈殿させていることから工程が複雑である。 However, in the invention described in Patent Document 1, the structure of the coarse classification means for separating the coarse particles and the fine particles provided in the middle of the mud feeding pipe is complicated, and the sand content is settled in the settling tank. The process is complicated because it is made to work.

本発明は、上述の問題を解決するためになされたものであり、浚渫された土砂から、砂を回収するための、構造容易な管部材を提案することを課題とする。 The present invention has been made to solve the above-mentioned problems, and an object of the present invention is to propose a pipe member having an easy structure for recovering sand from dredged earth and sand.

上記目的を達成するため、本発明に係る管部材は、砂を含む土砂水を圧送するポンプと接続されるポンプ接続部と、一端にポンプ接続部が配置され、且つ、口径が第1径である第1管部と、第1管部の他端に接続され、且つ、口径が第1径よりも大きい第2径である第2管部と、を有し、第2管部は、内壁から外壁に貫通し、ポンプから圧送された土砂水に含まれる砂を排出する単数又は複数の貫通孔が形成されることを特徴とする。 In order to achieve the above object, the pipe member according to the present invention has a pump connection portion connected to a pump for pumping earth and sand water containing sand, a pump connection portion at one end, and a diameter of the first diameter. It has a first pipe portion and a second pipe portion connected to the other end of the first pipe portion and having a second diameter larger than the first diameter, and the second pipe portion has an inner wall. It is characterized by forming one or more through holes that penetrate the outer wall and discharge the sand contained in the earth and sand water pumped from the pump.

更に、本発明に係る管部材は、第2管部の他端に接続され、且つ、口径が第2径よりも小さい第3径である第3管部を更に有することが好ましい。 Further, it is preferable that the pipe member according to the present invention further has a third pipe portion which is connected to the other end of the second pipe portion and has a third diameter smaller than the second diameter.

更に、本発明に係る管部材は、単数又は複数の貫通孔の少なくとも1つの下流側に第2管部の内壁から起立するように配置される邪魔板を更に有することが好ましい。 Further, it is preferable that the pipe member according to the present invention further has an obstacle plate arranged so as to stand up from the inner wall of the second pipe portion on the downstream side of at least one of the single or a plurality of through holes.

本発明に係る砂回収システムは、砂を含む土砂水を圧送するポンプと、ポンプに接続され、且つ、ポンプから圧送された土砂水に含まれる砂を排出する管部材と、管部材から排出された砂を回収する回収装置と、を有し、管部材は、砂を含む土砂水を圧送するポンプと接続されるポンプ接続部と、一端にポンプ接続部が配置され、且つ、口径が第1径である第1管部と、第1管部の他端に接続され、且つ、口径が第1径よりも大きい第2径である第2管部と、を有し、第2管部は、内壁から外壁に貫通し、ポンプから圧送された土砂水に含まれる砂を排出する単数又は複数の貫通孔が形成されることを特徴とする。 The sand recovery system according to the present invention has a pump that pumps sand-containing sediment water, a pipe member that is connected to the pump and discharges sand contained in the sediment water pumped from the pump, and a pipe member that discharges sand. It has a recovery device for collecting sand, and the pipe member has a pump connection portion connected to a pump for pumping earth and sand water containing sand, and a pump connection portion is arranged at one end and has a first diameter. The second pipe portion has a first pipe portion having a diameter and a second pipe portion having a second diameter connected to the other end of the first pipe portion and having a diameter larger than the first diameter. It is characterized in that one or more through holes are formed which penetrate from the inner wall to the outer wall and discharge the sand contained in the earth and sand water pumped from the pump.

更に、本発明に係る砂回収システムは、第2管部を流れる土砂水の流速が0.7m/sec以上3.0m/sec以下となるように吐出圧が調整されることが好ましい。 Further, in the sand recovery system according to the present invention, it is preferable that the discharge pressure is adjusted so that the flow velocity of the earth and sand water flowing through the second pipe portion is 0.7 m / sec or more and 3.0 m / sec or less.

本発明に係る砂回収船は、砂を含む土砂水を圧送するポンプと、ポンプに接続され、且つ、ポンプから圧送された土砂水に含まれる砂を排出する管部材と、管部材から排出された砂を回収する回収装置と、を有し、管部材は、砂を含む土砂水を圧送するポンプと接続されるポンプ接続部と、一端にポンプ接続部が配置され、且つ、口径が第1径である第1管部と、第1管部の他端に接続され、且つ、口径が第1径よりも大きい第2径である第2管部と、を有し、第2管部は、内壁から外壁に貫通し、ポンプから圧送された土砂水に含まれる砂を排出する単数又は複数の貫通孔が形成されることを特徴とする。 The sand recovery ship according to the present invention has a pump that pumps sand-containing sediment water, a pipe member that is connected to the pump and discharges sand contained in the sediment water pumped from the pump, and a pipe member that discharges sand. It has a recovery device for collecting sand, and the pipe member has a pump connection portion connected to a pump for pumping earth and sand water containing sand, and a pump connection portion is arranged at one end and has a first diameter. The second pipe portion has a first pipe portion having a diameter and a second pipe portion having a second diameter connected to the other end of the first pipe portion and having a diameter larger than the first diameter. It is characterized in that one or more through holes are formed which penetrate from the inner wall to the outer wall and discharge the sand contained in the earth and sand water pumped from the pump.

本発明に係る管部材によれば、土砂水から効率よく砂を回収することが可能となる。 According to the pipe member according to the present invention, sand can be efficiently recovered from earth and sand water.

砂回収システムの一例の概要を説明する図である。It is a figure explaining the outline of an example of a sand recovery system. 管部材3の一例の概要を説明する図であり、(a)は管部材の側面図であり、(b)は管部材3の平面視のときの断面図である。It is a figure explaining the outline of an example of a pipe member 3, (a) is a side view of a pipe member, and (b) is a sectional view of a pipe member 3 in a plan view. 貫通孔を有する鋼管用継手の一例を示す図であり、(a)は2つの主鋼管を鋼管用継手によりつないだ状態を示す図であり、(b)は貫通孔を有する鋼管用継手の正面図であり、(c)は(b)に示したA-A´平面における断面図である。It is a figure which shows an example of the steel pipe joint which has a through hole, (a) is the figure which shows the state which two main steel pipes are connected by the steel pipe joint, (b) is the front surface of the steel pipe joint which has a through hole. It is a figure, (c) is a cross-sectional view in the AA'plane shown in (b). 図3で示した鋼管用継手の貫通孔の前方に邪魔板を有する鋼管用継手の一例を示す図であり、(a)は邪魔板を有する鋼管用継手の正面図であり、(b)は(a)に示したA-A´平面における断面図であり、(c)は(a)に示したB-B´平面における断面図である。3 is a view showing an example of a steel pipe joint having a baffle plate in front of a through hole of the steel pipe joint shown in FIG. 3, FIG. 3A is a front view of a steel pipe joint having a baffle plate, and FIG. 3B is a front view. It is a cross-sectional view in the AA'plane shown in (a), and (c) is a cross-sectional view in the BB'plane shown in (a). 本発明に係る管部材の実験の概要を示す図である。It is a figure which shows the outline of the experiment of the pipe member which concerns on this invention. 第2管部内の流速を変化させたときの貫通孔毎の砂回収率(重量比)を示した図であり、(a)において第2管部内の流速は0.7m/secであり、(b)において第2管部内の流速は0.8m/secであり、(c)において第2管部内の流速は0.9m/secであり、(d)において第2管部内の流速は1.0m/secである。It is a figure which showed the sand recovery rate (weight ratio) for each through hole when the flow velocity in the 2nd pipe part was changed, and in (a), the flow velocity in the 2nd pipe part was 0.7m / sec, and ( In b), the flow velocity in the second pipe portion is 0.8 m / sec, in (c) the flow velocity in the second pipe portion is 0.9 m / sec, and in (d), the flow velocity in the second pipe portion is 1. It is 0 m / sec. 第1土砂水について、邪魔板を設けないときと設けたときの貫通孔毎の砂回収率(重量比)とを比較した図であり、(a)において第2管部内の流速は0.85m/secであり、(b)において第2管部内の流速は0.95m/secであり、(c)において第2管部内の流速は1.05m/secである。It is a figure which compared the sand recovery rate (weight ratio) for each through hole with respect to the 1st earth and sand water when the obstruction plate was not provided, and the flow velocity in the 2nd pipe part is 0.85m in (a). It is / sec, and in (b), the flow velocity in the second pipe portion is 0.95 m / sec, and in (c), the flow velocity in the second pipe portion is 1.05 m / sec. 第2土砂水について、邪魔板を設けないときと設けたときの貫通孔毎の砂回収率(重量比)とを比較した図であり、(a)において第2管部内の流速は0.85m/secであり、(b)において第2管部内の流速は1.0m/secであり、(c)において第2管部内の流速は1.1m/secである。It is a figure which compared the sand recovery rate (weight ratio) for each through hole with respect to the 2nd earth and sand water when the obstruction plate was not provided, and the flow velocity in the 2nd pipe part is 0.85m in (a). It is / sec, and in (b), the flow velocity in the second pipe portion is 1.0 m / sec, and in (c), the flow velocity in the second pipe portion is 1.1 m / sec. 第3土砂水について、邪魔板を設けないときと設けたときの貫通孔毎の砂回収率(重量比)とを比較した図であり、(a)において第2管部内の流速は0.8m/secであり、(b)において第2管部内の流速は1.0m/secであり、(c)において第2管部内の流速は1.1m/secである。It is a figure which compared the sand recovery rate (weight ratio) for each through hole with respect to the 3rd earth and sand water when the obstruction plate was not provided, and the flow velocity in the 2nd pipe part is 0.8m in (a). It is / sec, and in (b), the flow velocity in the second pipe portion is 1.0 m / sec, and in (c), the flow velocity in the second pipe portion is 1.1 m / sec. 砂回収船の一例の概要を説明する図である。It is a figure explaining the outline of an example of a sand recovery ship.

以下、本開示の一側面に係る管部材、砂回収システム、及び砂回収船について、図を参照しつつ説明する。但し、本開示の技術的範囲はそれらの実施の形態に限定されず、特許請求の範囲に記載された発明とその均等物に及ぶ点に留意されたい。尚、以下の説明及び図において、同一の機能構成を有する構成要素については、同一の符号を付することにより重複説明を省略する。 Hereinafter, the pipe member, the sand recovery system, and the sand recovery ship according to one aspect of the present disclosure will be described with reference to the drawings. However, it should be noted that the technical scope of the present disclosure is not limited to those embodiments, but extends to the inventions described in the claims and their equivalents. In the following description and figures, components having the same functional configuration are designated by the same reference numerals, so that duplicate description will be omitted.

(本発明に係る砂回収システムの概要)
図1は、実施形態に係る砂回収システムの一例の概要を説明する図である。
(Overview of the sand recovery system according to the present invention)
FIG. 1 is a diagram illustrating an outline of an example of a sand recovery system according to an embodiment.

砂回収システム1は、砂を含む土砂水を圧送するポンプ2と、砂を含む土砂水を圧送するポンプ2に接続される管部材3と、管部材3により排出された砂を搬送する回収装置4とを有する。ポンプ2は、例えば、浚渫された砂を含む土砂と海水又は淡水とが混合された土砂水を貯めた貯水槽5から土砂水を吸い上げ、管部材3に土砂水を圧送する。 The sand recovery system 1 is a pump 2 for pumping earth and sand water containing sand, a pipe member 3 connected to a pump 2 for pumping earth and sand water containing sand, and a recovery device for transporting sand discharged by the pipe member 3. Has 4 and. For example, the pump 2 sucks up the earth and sand water from the water tank 5 storing the earth and sand water in which the earth and sand including the dredged sand and the seawater or fresh water are mixed, and pumps the earth and sand water to the pipe member 3.

管部材3は、ポンプ2から圧送される土砂水から、砂を分離して管外に排出するための装置である。管部材3は、土砂水を圧送するポンプ2と接続されるポンプ接続部30と、一端にポンプ接続部30が接続される第1管部31と、第1管部31の他端に接続される第2管部32とを有する。更に、管部材3は、第2管部32の他端に接続される第3管部33を有してもよい。 The pipe member 3 is a device for separating sand from the earth and sand water pumped from the pump 2 and discharging it to the outside of the pipe. The pipe member 3 is connected to a pump connection portion 30 connected to a pump 2 for pumping earth and sand water, a first pipe portion 31 to which a pump connection portion 30 is connected to one end, and the other end of the first pipe portion 31. It has a second pipe portion 32. Further, the pipe member 3 may have a third pipe portion 33 connected to the other end of the second pipe portion 32.

ポンプ2から吐出された砂を含む土砂水は、ポンプ接続部30を通過して、第1管部31に流入する。ポンプ2から圧送された土砂水は、第1管部内を土砂が沈降しない第1流速で通過する。なお、管内で土砂水中の土砂が、沈降、堆積、静止して管内を閉塞するおそれがある速度を限界流速という。したがって、第1流速は限界流速より速い。第1管部の他端に接続される第2管部32は、口径が第1管部31の口径よりも大きい。 The earth and sand water containing sand discharged from the pump 2 passes through the pump connection portion 30 and flows into the first pipe portion 31. The earth and sand water pumped from the pump 2 passes through the first pipe portion at a first flow velocity at which the earth and sand do not settle. It should be noted that the speed at which the sediment in the sediment water in the pipe may settle, accumulate, or stand still and block the inside of the pipe is called the limit flow velocity. Therefore, the first flow velocity is faster than the critical flow velocity. The diameter of the second pipe portion 32 connected to the other end of the first pipe portion is larger than the diameter of the first pipe portion 31.

第1管部31に流れる単位時間当たりの土砂水量は、第1管部31の管断面積と第1流速の積であり、第2管部32に流れる単位時間当たりの土砂水量は、第2管部32の管断面積と第1流速の積である。第2管部32の口径は第1管部31の口径よりも大きい。又、土砂水の全量が第1管部31から全量が第2管部32に流入する。したがって、第1流速で第1管部31を通過した土砂水は、第1流速よりも遅い第2流速で第2管部32を流れることになる。第1流速と第2流速とが、限界流速以上となるように、ポンプ2の吐出圧は調整される。 The amount of sediment water flowing through the first pipe portion 31 per unit time is the product of the pipe cross-sectional area of the first pipe portion 31 and the first flow velocity, and the amount of sediment water flowing through the second pipe portion 32 per unit time is the second. It is the product of the pipe cross-sectional area of the pipe portion 32 and the first flow velocity. The diameter of the second pipe portion 32 is larger than the diameter of the first pipe portion 31. Further, the entire amount of earth and sand water flows from the first pipe portion 31 into the second pipe portion 32. Therefore, the earth and sand water that has passed through the first pipe portion 31 at the first flow velocity will flow through the second pipe portion 32 at a second flow velocity slower than the first flow velocity. The discharge pressure of the pump 2 is adjusted so that the first flow velocity and the second flow velocity become equal to or higher than the limit flow velocity.

又、流体に関するベルヌーイの定理によれば、非圧縮性流体である土砂水が、口径の小さい第1管部31から口径の大きい第2管部32に流れるとき、管内内壁に対する土砂水の水圧である静圧は、第2管部32のほうが第1管部31よりも高くなる。したがって、第2管部32内壁に対する土砂水の静圧は高くなるので、第2管部32内壁から外壁に貫通する貫通孔を適切に設けると、土砂水は、第2管部32の外に排出され易くなる。 Further, according to Bernoulli's theorem regarding fluid, when sediment water, which is a non-compressible fluid, flows from the first pipe portion 31 having a small diameter to the second pipe portion 32 having a large diameter, the water pressure of the sediment water with respect to the inner wall of the pipe A certain static pressure is higher in the second pipe portion 32 than in the first pipe portion 31. Therefore, since the static pressure of the earth and sand water on the inner wall of the second pipe portion 32 becomes high, if a through hole penetrating from the inner wall of the second pipe portion 32 to the outer wall is appropriately provided, the earth and sand water will be discharged to the outside of the second pipe portion 32. It becomes easy to be discharged.

第1管部31で、砂と泥が入り混じって流れている状態であった土砂水は、第1流速よりも遅い第2流速で第2管部32を流れる。流速が遅くなった土砂水は、粒子径が大きく重い砂を多く含む下部流水層と、粒子径が小さく泥を多く含む上部流水層とに分かれ始めて、第2管部32を流れることになる。 The earth and sand water, which was in a state where sand and mud were mixed and flowed in the first pipe portion 31, flows through the second pipe portion 32 at a second flow velocity slower than the first flow velocity. The sediment water having a slow flow velocity begins to separate into a lower running water layer having a large particle size and containing a large amount of heavy sand and an upper running water layer having a small particle size and containing a large amount of mud, and flows through the second pipe portion 32.

そこで、砂を多く含む流水層が流れる第2管部32の地上側に、単数又は複数単数又は複数の貫通孔321~325を設けることにより、砂を多く含む流水層の一部が管外に排出され、砂回収システム1は、土砂水に含まれる砂を回収することが可能となる。 Therefore, by providing a single or a plurality of singular or a plurality of through holes 321 to 325 on the ground side of the second pipe portion 32 through which the sand-rich running water layer flows, a part of the sand-rich running water layer is removed from the pipe. The sand is discharged, and the sand recovery system 1 can recover the sand contained in the earth and sand water.

第2管部32の第1管部31と接続されている反対側には、第2管部32の口径よりも小さい口径の第3管部33が接続される。第3管部33を介して、砂が回収された後の泥を多く含む土砂水を、例えば埋立地に送出することができる。 A third pipe portion 33 having a diameter smaller than that of the second pipe portion 32 is connected to the opposite side of the second pipe portion 32 connected to the first pipe portion 31. Through the third pipe portion 33, sediment water containing a large amount of mud after the sand has been collected can be sent to, for example, a landfill.

砂回収システム1は、管部材3の下側、すなわち地上側に、管部材3に並列する回収装置4を有する。例えば、回収装置4は、メッシュベルトを有するベルトコンベア41と振動ふるい42とを有する。管部材3の単数又は複数の貫通孔321~325から排出された砂を多く含む土砂水は、メッシュベルト上に落下して、水分は下に抜け、含水量の少ない砂が、ベルトコンベア41により搬送される。搬送された砂は、更に、振動ふるい42によって水分が排除される。砂は、例えば、不図示の土運船により砂再生場に運搬される。 The sand recovery system 1 has a recovery device 4 parallel to the pipe member 3 on the lower side of the pipe member 3, that is, on the ground side. For example, the recovery device 4 has a belt conveyor 41 having a mesh belt and a vibrating sieve 42. The earth and sand water containing a large amount of sand discharged from the single or a plurality of through holes 321 to 325 of the pipe member 3 falls on the mesh belt, the water escapes downward, and the sand having a low water content is removed by the belt conveyor 41. Be transported. Moisture is further removed from the transported sand by the vibrating sieve 42. The sand is transported to the sand reclamation site by, for example, a soil carrier (not shown).

また、回収装置4は、管部材3の下側に並列し、第2管部32と第3管部の接続側に傾斜させて設けられた樋を有してもよい。管部材3の単数又は複数の貫通孔321、322、323から排出された砂を多く含む土砂水は、樋に落下し、樋を伝って、1か所に集積され、振動ふるい42によって水分が排除される。砂を多く含む土砂水から水分をろ過して、集積された砂は、例えば、不図示の土運船により砂再生場に運搬される。なお、振動ふるい42はなくともよい。 Further, the recovery device 4 may have a gutter provided in parallel with the lower side of the pipe member 3 and inclined toward the connection side between the second pipe portion 32 and the third pipe portion. Sediment water containing a large amount of sand discharged from one or more through holes 321 or 322, 323 of the pipe member 3 falls into the gutter, travels through the gutter, is accumulated in one place, and the moisture is removed by the vibrating sieve 42. Be excluded. Moisture is filtered from the sand-rich soil water, and the accumulated sand is transported to the sand reclamation site by, for example, a soil carrier (not shown). The vibrating sieve 42 does not have to be provided.

(本発明に係る管部材の概要)
図2は、実施形態に係る管部材3の一例の概要を説明する図である。図2(a)は、管部材3の側面図であり、図2(b)は、管部材3の平面視のときの断面図である。
(Overview of Pipe Member According to the Present Invention)
FIG. 2 is a diagram illustrating an outline of an example of a pipe member 3 according to an embodiment. FIG. 2A is a side view of the pipe member 3, and FIG. 2B is a cross-sectional view of the pipe member 3 in a plan view.

管部材3は、土砂水を圧送するポンプ2と接続されるポンプ接続部30と、一端にポンプ接続部30が接続される第1管部31と、第1管部31の他端に接続される第2管部32とを有する。更に、管部材3は、第2管部32の他端に接続される第3管部33を有してもよい。第2管部32の口径径φ2は、第1管部31の口径φ1よりも大きい。第3管部33の口径φ3は、第2管部32の口径φ2よりも小さい。例えば、第1管部31の口径φ1は60mmであり、第2管部32の口径φ2は150mmであり、第3管部33の口径φ3は60mmである。 The pipe member 3 is connected to a pump connection portion 30 connected to a pump 2 for pumping earth and sand water, a first pipe portion 31 to which a pump connection portion 30 is connected to one end, and the other end of the first pipe portion 31. It has a second pipe portion 32. Further, the pipe member 3 may have a third pipe portion 33 connected to the other end of the second pipe portion 32. The diameter φ2 of the second pipe portion 32 is larger than the diameter φ1 of the first pipe portion 31. The diameter φ3 of the third pipe portion 33 is smaller than the diameter φ2 of the second pipe portion 32. For example, the diameter φ1 of the first pipe portion 31 is 60 mm, the diameter φ2 of the second pipe portion 32 is 150 mm, and the diameter φ3 of the third pipe portion 33 is 60 mm.

ポンプ接続部30は、一端が砂を含む土砂水を圧送する不図示のポンプ2と接続され、他端が、第1管部31の一端に接続される。第1管部31の口径は、φ1である。第1管部31の他端には第1接続部311があり、第2管部32に接続される。第2管部32の口径φ2は、第1管部31の口径φ1よりも大きいので、第1接続部311は、第2管部32側にテーパー状に広がっていることが好ましい。土砂水の流路径が緩やかに増加するので、不規則乱流の発生が防止できるからである。 One end of the pump connection portion 30 is connected to a pump 2 (not shown) for pumping earth and sand water containing sand, and the other end is connected to one end of the first pipe portion 31. The diameter of the first pipe portion 31 is φ1. At the other end of the first pipe portion 31, there is a first connection portion 311 which is connected to the second pipe portion 32. Since the diameter φ2 of the second pipe portion 32 is larger than the diameter φ1 of the first pipe portion 31, it is preferable that the first connection portion 311 is tapered toward the second pipe portion 32 side. This is because the channel diameter of the sediment water gradually increases, so that the occurrence of irregular turbulent flow can be prevented.

第2管部32の配管長は、10mから数10mである。管内を通過する土砂水の流速が第1管部31の流速に比べ緩やかになり、粒子径が大きく重い砂を多く含む下部流水層と、粒子径が小さく軽い泥を多く含む上部流水層とに分かれ始めて、安定した下部流水層と上部流水層として流れるには、適切な配管長が必要となるからである。 The pipe length of the second pipe portion 32 is from 10 m to several tens of m. The flow velocity of earth and sand water passing through the pipe is slower than the flow velocity of the first pipe portion 31, and it is divided into a lower running water layer containing a large amount of heavy sand with a large particle size and an upper running water layer containing a large amount of light mud with a small particle size. This is because an appropriate pipe length is required to start separating and flow as a stable lower running water layer and an upper running water layer.

したがって、通常、第2管部32は、複数の長尺同径の主鋼管341、342、243、344をつないで作られる。主鋼管相互をつなぐため、例えば、鋼管用継手351、352、353が使用される。鋼管用継手351、352,353には、それぞれの管側面の内壁から外壁に貫通し、ポンプから圧送された土砂水に含まれる砂を排出するための貫通孔321、322、323が形成されている。本例示では、3つの鋼管用継手351、352,353の全てに、貫通孔が設けられているが、第2配管の適当な位置に単数又は複数の貫通孔があればよく、すべての鋼管用継手に貫通孔がある必要はない。又、主鋼管341、342、243、344に貫通孔を設けてもよい。 Therefore, usually, the second pipe portion 32 is made by connecting a plurality of long main steel pipes 341, 342, 243, 344 having the same diameter. For connecting the main steel pipes to each other, for example, steel pipe joints 351 and 352, 353 are used. Through holes 321, 322, and 323 are formed in the steel pipe joints 351 and 352, 353 to penetrate from the inner wall of the side surface of each pipe to the outer wall and to discharge the sand contained in the earth and sand water pumped from the pump. There is. In this example, all three steel pipe joints 351 and 352, 353 are provided with through holes, but only one or more through holes may be provided at appropriate positions in the second pipe, and all steel pipe joints may be provided. The fitting does not need to have a through hole. Further, through holes may be provided in the main steel pipes 341, 342, 243 and 344.

貫通孔321、322、323は、管中心軸、すなわち第2管部32内を土砂水が流れる方向に垂直な平面と管内壁とが交差する位置に設けられる。貫通孔321、322、323は、平面視すると矩形形状で、矩形の短辺は、管中心軸に、すなわち土砂水が流れる方向に平行であることが好ましい。貫通孔は、他の形状であってもよい。 The through holes 321, 322, and 323 are provided at a position where the central axis of the pipe, that is, the plane perpendicular to the direction in which the earth and sand flow flows and the inner wall of the pipe intersect in the second pipe portion 32. It is preferable that the through holes 321, 322, and 323 have a rectangular shape when viewed in a plan view, and the short side of the rectangle is parallel to the central axis of the pipe, that is, in the direction in which sediment water flows. The through hole may have another shape.

更に、第2管部32の土砂水流出側には、第2接続部331を有する第3管部33が接続される。第3管部33の口径φ3は、第2管部32の口径φ2よりも小さい。好ましくは、第1管部31と同じ口径である。第3管部33の口径φ3は、第2管部32の口径φ2よりも小さいので、第2接続部331の管内は、第2管部32側からテーパー状に狭まっていることが好ましい。土砂水が、第2管部32側に逆流するのを防止するためである。 Further, a third pipe portion 33 having a second connecting portion 331 is connected to the sediment water outflow side of the second pipe portion 32. The diameter φ3 of the third pipe portion 33 is smaller than the diameter φ2 of the second pipe portion 32. Preferably, the diameter is the same as that of the first pipe portion 31. Since the diameter φ3 of the third pipe portion 33 is smaller than the diameter φ2 of the second pipe portion 32, it is preferable that the inside of the pipe of the second connecting portion 331 is tapered from the side of the second pipe portion 32. This is to prevent sediment water from flowing back to the second pipe portion 32 side.

第2管部32に第3管部33を接続することにより、第2管部32の管内は、土砂水で充たされ、第2管部32内の土砂水の流れが安定化するので、砂の沈降による砂の回収効率が向上する。又、砂が回収された後の土砂水は、第3管部33を通過して、埋立地や土捨て場に送出される。なお、管部材3は、第3管部33を有さなくてもよい。 By connecting the third pipe portion 33 to the second pipe portion 32, the inside of the pipe of the second pipe portion 32 is filled with earth and sand water, and the flow of the earth and sand water in the second pipe portion 32 is stabilized. The efficiency of sand recovery due to sand settling is improved. Further, the earth and sand water after the sand is collected passes through the third pipe portion 33 and is sent to a landfill or a dumping site. The pipe member 3 does not have to have the third pipe portion 33.

図3は、貫通孔を有する鋼管用継手の一例を示す図である。図3(a)は、2つの主鋼管を鋼管用継手によりつないだ状態を示す図である。図3(b)は、貫通孔を有する鋼管用継手の正面図である。図3(c)は、図3(b)に示したA-A´平面における断面図である。 FIG. 3 is a diagram showing an example of a steel pipe joint having a through hole. FIG. 3A is a diagram showing a state in which two main steel pipes are connected by a steel pipe joint. FIG. 3B is a front view of a steel pipe joint having a through hole. FIG. 3 (c) is a cross-sectional view taken along the line AA'shown in FIG. 3 (b).

主鋼管341、342は、それぞれ鋼管口の周囲にフランジ346を有し、フランジ346には、主鋼管と鋼管用継手とを締結するための4つの締結孔347が設けられている。鋼管用継手351は、両側の鋼管口の周囲にそれぞれフランジ356を有する。各フランジ356には、4つ以上の複数の締結孔357が設けられている。主鋼管341、342のフランジ346と鋼管用継手351の2つのフランジ356とが接合され、4つのボルト358が各締結孔347に通され、ナット359により締結される。鋼管用継手351は、第2管部32を流れる砂を多く含んだ土砂水を管外に排出するため、管側面に貫通孔321が設けられている。 The main steel pipes 341 and 342 each have a flange 346 around the steel pipe opening, and the flange 346 is provided with four fastening holes 347 for fastening the main steel pipe and the steel pipe joint. The steel pipe joint 351 has flanges 356 around the steel pipe openings on both sides. Each flange 356 is provided with four or more fastening holes 357. The flanges 346 of the main steel pipes 341 and 342 and the two flanges 356 of the steel pipe joint 351 are joined, and four bolts 358 are passed through the fastening holes 347 and fastened by nuts 359. The steel pipe joint 351 is provided with a through hole 321 on the side surface of the pipe in order to discharge the earth and sand water containing a large amount of sand flowing through the second pipe portion 32 to the outside of the pipe.

図3(b)は、貫通孔321が設けられた鋼管用継手351の正面図である。鋼管用継手351の口径はφ2である。図3(c)は、図3(b)に示したA-A´平面における断面図である。貫通孔321は、鋼管用継手351の管中心軸、すなわち土砂水が流れる方向に垂直な平面と鋼管用継手351の管内内壁とが交差する位置に設けられ、内壁から外壁に貫通して形成される。貫通孔321の形状は、例えば、平面視すると矩形形状で、矩形の短辺は、管中心軸に、すなわち土砂水が流れる方向に平行であることが好ましい。貫通孔は、他の形状であってもよい。 FIG. 3B is a front view of a steel pipe joint 351 provided with a through hole 321. The diameter of the steel pipe joint 351 is φ2. FIG. 3 (c) is a cross-sectional view taken along the line AA'shown in FIG. 3 (b). The through hole 321 is provided at a position where the pipe center axis of the steel pipe joint 351, that is, a plane perpendicular to the direction in which earth and sand flow flows, intersects the inner wall of the steel pipe joint 351 and is formed so as to penetrate from the inner wall to the outer wall. To. It is preferable that the shape of the through hole 321 is, for example, a rectangular shape when viewed in a plan view, and the short side of the rectangle is parallel to the central axis of the pipe, that is, in the direction in which sediment water flows. The through hole may have another shape.

貫通孔321を設けた鋼管用継手351を使用して複数の主鋼管をつなげて第2管部を構成する方法を説明したが、鋼管用継手はフランジ式に限られず、他の継手、例えば、ねじ込み式管継手でもよい。又、短い鋼管の内壁から外壁に貫通するように貫通孔を形成して、短い鋼管と主鋼管とを、例えばビクトリアジョイントでつないでもよい。 Although a method of connecting a plurality of main steel pipes to form a second pipe portion by using a steel pipe joint 351 provided with a through hole 321 has been described, the steel pipe joint is not limited to the flange type, and other joints such as, for example, A screw-in type pipe joint may be used. Further, a through hole may be formed so as to penetrate from the inner wall to the outer wall of the short steel pipe, and the short steel pipe and the main steel pipe may be connected by, for example, a Victoria joint.

図4は、図3で示した鋼管用継手の貫通孔の前方に邪魔板を有する鋼管用継手の一例を示す図である。 FIG. 4 is a diagram showing an example of a steel pipe joint having an obstacle plate in front of the through hole of the steel pipe joint shown in FIG.

図4(a)は、邪魔板361を有する鋼管用継手351´の正面図である。図4(b)は、図4(a)に示したA-A´平面における断面図である。邪魔板361は、鋼管用継手351´の矩形形状の貫通孔321の長辺と平行に、管内壁から管内中心に向かい起立して形成される、上端が直線である板である。 FIG. 4A is a front view of a steel pipe joint 351 ′ having a baffle plate 361. FIG. 4B is a cross-sectional view taken along the line AA'shown in FIG. 4A. The obstruction plate 361 is a plate having a straight upper end formed by standing upright from the inner wall of the pipe toward the center of the pipe in parallel with the long side of the rectangular through hole 321 of the steel pipe joint 351'.

図4(c)は、図4(a)に示したB-B´平面における断面図であり、邪魔板の効果を説明する図である。 FIG. 4C is a cross-sectional view taken along the line BB'shown in FIG. 4A, and is a diagram illustrating the effect of the baffle plate.

第1流速で第1管部を通過した土砂水は、第1流速より遅い第2流速で第2管部を流れる。第2管部の口径が第1管部の口径より大きいからである。第2管部を第2流速で流れる土砂水は、砂を多く含む流水層と泥を多く含む流水層とに分かれ始める。砂は、泥よりも粒子径が大きく、重いので、砂を多く含む流水層は、管内の下側、すなわち、管内の地上側を流れることになる。 The earth and sand water that has passed through the first pipe portion at the first flow velocity flows through the second pipe portion at a second flow velocity slower than the first flow velocity. This is because the diameter of the second pipe portion is larger than the diameter of the first pipe portion. The sediment water flowing through the second pipe portion at the second flow velocity begins to be divided into a running water layer containing a large amount of sand and a running water layer containing a large amount of mud. Since sand has a larger particle size and is heavier than mud, the running water layer containing a large amount of sand flows under the pipe, that is, on the above-ground side in the pipe.

砂を多く含む流水層が、邪魔板361に当たると、乱流が発生する。砂が沈降する位置には貫通孔321が形成されているので、砂を多く含む流水は管外に放出される。砂を多く含む流水層から貫通孔321から管外に排出される流水に、邪魔板361により発生した乱流による流水が更に加わるので、管外に排出される砂を含む水の量は増加する。したがって、砂の排出量は増加する。 When a running water layer containing a large amount of sand hits the obstruction plate 361, turbulence occurs. Since the through hole 321 is formed at the position where the sand settles, the running water containing a large amount of sand is discharged to the outside of the pipe. Since the flowing water due to the turbulent flow generated by the obstruction plate 361 is further added to the flowing water discharged from the through hole 321 to the outside of the pipe from the running water layer containing a large amount of sand, the amount of water containing sand discharged to the outside of the pipe increases. .. Therefore, the amount of sand discharged increases.

したがって、邪魔板361は、貫通孔321の近傍であって土砂水が流れる下流側に、管内壁から管中心に向かい起立して形成される。貫通孔と邪魔板361との距離は、好ましくは、0mm以上、20mm以下である。又、邪魔板361の内壁からの最大高さは、口径の1/4以下、1/8以上である。 Therefore, the baffle plate 361 is formed upright from the inner wall of the pipe toward the center of the pipe on the downstream side where the earth and sand water flows in the vicinity of the through hole 321. The distance between the through hole and the baffle plate 361 is preferably 0 mm or more and 20 mm or less. The maximum height of the baffle plate 361 from the inner wall is 1/4 or less and 1/8 or more of the diameter.

(管部材の実験)
発明者は、砂回収効率を高めるべく、本願発明に係る管部材のパラメータ検討のための実験を行った。
(Experiment of pipe member)
The inventor conducted an experiment for examining the parameters of the pipe member according to the present invention in order to improve the sand recovery efficiency.

パラメータの検討事項は、第1管部を土砂水が流れるときの第1流速と、第2管部を土砂水が流れるときの第2流速を適切に設定することと、第2管部に設ける最初の貫通孔(第1貫通孔)の位置を適切に設定することと、第2管部に設ける貫通孔数を適切に設定することと、貫通孔の土砂水が流れる下流側に邪魔板を設けたときの効果を検証することである。検討にあたっての一つの評価指標は、土砂水からの砂回収率である。 The items to be examined for the parameters are to appropriately set the first flow velocity when the earth and sand flow through the first pipe and the second flow velocity when the earth and sand flow through the second pipe, and to provide the second pipe. Appropriately set the position of the first through hole (first through hole), appropriately set the number of through holes provided in the second pipe part, and place a baffle plate on the downstream side where the earth and sand water of the through hole flows. It is to verify the effect when it is provided. One evaluation index for the study is the sand recovery rate from sediment water.

図5は、本発明に係る管部材の実験の概要を示す図である。 FIG. 5 is a diagram showing an outline of an experiment of a pipe member according to the present invention.

粗砂、細砂、粘土、及び水を混合した土砂水を貯水した貯水槽5、貯水槽5の土砂水を吐出するポンプ6、及び、ポンプ6から吐出される土砂水を通過させ、土砂水から砂を回収するための管部材7を陸上に設置して実験が行われた。 A water storage tank 5 that stores earth and sand water mixed with coarse sand, fine sand, clay, and water, a pump 6 that discharges earth and sand water from the water storage tank 5, and earth and sand water that is discharged from the pump 6 are passed through. An experiment was conducted by installing a pipe member 7 for recovering sand from the water on land.

管部材7は、ポンプ接続部70、第1管部71、第2管部72、第3管部73を有する。第2管部72は、5つの貫通孔721~725を設けることが可能である。本実験では、各貫通孔間の間隔は、6mとなるようにしている。各貫通孔の下には、各貫通孔から流れ出る土砂水を受けるバケツ81~85が設置してある。又、第3管部の土砂水排出側にはバケツ86が設置してある。各バケツ81~86で回収された土砂水の砂の量を計測することにより、管部材の砂回収の性能が分析可能となる。 The pipe member 7 has a pump connection portion 70, a first pipe portion 71, a second pipe portion 72, and a third pipe portion 73. The second pipe portion 72 can be provided with five through holes 721 to 725. In this experiment, the distance between each through hole is set to 6 m. Under each through hole, buckets 81 to 85 for receiving the earth and sand water flowing out of each through hole are installed. In addition, a bucket 86 is installed on the sediment water discharge side of the third pipe portion. By measuring the amount of sand in the earth and sand collected in each bucket 81 to 86, the sand recovery performance of the pipe member can be analyzed.

発明者は、第1管部71の内径φ1が60mmであり、第2管部72の内径φ2が150mmであり、及び第3管部73の内径φ3が60mmである管部材7を用いて、砂回収効率の高い管部材とするため、種々の設定パラメータと変えて実験を行った。なお、第1管部71の配管長は、1.25mに固定した。 The inventor uses a pipe member 7 in which the inner diameter φ1 of the first pipe portion 71 is 60 mm, the inner diameter φ2 of the second pipe portion 72 is 150 mm, and the inner diameter φ3 of the third pipe portion 73 is 60 mm. In order to obtain a pipe member with high sand recovery efficiency, experiments were conducted with various setting parameters changed. The pipe length of the first pipe portion 71 was fixed at 1.25 m.

管部材7の第1管部71と、第2管部72の第1管部に接続される側は、上にコ字形に湾曲している(図中、点線で示す部分74)。湾曲部に続く第2管部72の残りの部分は水平となっている。第2管部72の第1管部に接続される側が上にコ字形に湾曲しているのは、第2管部72の配管長を長くするためと、配管長の変更を容易にするためである。長さLp(m)は、ポンプ6から、第2管部72の第1貫通孔721までの配管長である。 The side of the pipe member 7 connected to the first pipe portion 71 and the second pipe portion 72 is curved upward in a U-shape (the portion 74 shown by the dotted line in the figure). The remaining portion of the second pipe portion 72 following the curved portion is horizontal. The side of the second pipe portion 72 connected to the first pipe portion is curved upward in a U-shape in order to lengthen the pipe length of the second pipe portion 72 and to facilitate the change of the pipe length. Is. The length Lp (m) is the pipe length from the pump 6 to the first through hole 721 of the second pipe portion 72.

更に、第1管部71に第1流速計91、第2管部72の土砂水流入側に第2流速計92、第3管部73の土砂水流入側に第3流速計93を設けて、各管部の流速である、第1流速、第2流速、第3流速が計測される。 Further, a first current meter 91 is provided in the first pipe portion 71, a second current meter 92 is provided on the sediment water inflow side of the second pipe portion 72, and a third current meter 93 is provided on the sediment water inflow side of the third pipe portion 73. , The first flow velocity, the second flow velocity, and the third flow velocity, which are the flow velocities of each pipe portion, are measured.

管内で、次第に、土砂水中の土粒子が、沈降、堆積、静止して遂には管内を閉塞するおそれがある速度を限界流速という。したがって、流速は、第1管部(φ1=60mm)での流速は、限界流速以上であって、砂が堆積しない流速範囲であることと、第2管部(φ2=150mm)の流速は、限界流速以上であって、砂が堆積するが粘土シルトは堆積しない流速範囲であること、が求められる。 The speed at which soil particles in the earth and sand water gradually settle, accumulate, and stand still in the pipe and finally block the inside of the pipe is called the limit flow velocity. Therefore, the flow velocity in the first pipe portion (φ1 = 60 mm) is equal to or higher than the limit flow velocity and is in the flow velocity range in which sand does not accumulate, and the flow velocity in the second pipe portion (φ2 = 150 mm) is determined. It is required that the flow velocity is equal to or higher than the limit flow velocity and the flow velocity range is such that sand is deposited but clay silt is not deposited.

本実験では、3種類の土砂水、第1土砂水、第2土砂水、第3土砂水を用いた。

Figure 0007068123000001
In this experiment, three types of sediment water, first sediment water, second sediment water, and third sediment water were used.
Figure 0007068123000001

(管内流速の検討)
浚渫土砂の標準的な構成である第1土砂水(粘土+中間砂)を使用して、適切な管内流速が検討された。第2管部72には、5つの貫通孔が設けられた。第1貫通孔721は、ポンプ6からの距離が10.6mの位置に形成されている。各貫通孔間の間隔は6mである。貫通孔は、すべて平面視10mm×50mmの矩形である。矩形の短辺は、土砂水が管内を流れる方向のときの長さであり、矩形の長辺は、管中心軸に垂直な平面のときの長さである。
(Examination of flow velocity in the pipe)
Appropriate in-pipe flow velocity was investigated using the first sediment water (clay + intermediate sand), which is the standard composition of dredged sediment. The second pipe portion 72 was provided with five through holes. The first through hole 721 is formed at a position where the distance from the pump 6 is 10.6 m. The distance between each through hole is 6 m. The through holes are all rectangular in a plan view of 10 mm × 50 mm. The short side of the rectangle is the length in the direction in which the earth and sand water flows in the pipe, and the long side of the rectangle is the length in the plane perpendicular to the central axis of the pipe.

貫通孔が20mm×100mm、30mm×100mmの矩形については、貫通孔から排出される土砂水量が多すぎ、粘土と中間砂が混じってしまい、砂回収には不適切な大きさであった。 For rectangles with through holes of 20 mm × 100 mm and 30 mm × 100 mm, the amount of earth and sand discharged from the through holes was too large, and clay and intermediate sand were mixed, which was an inappropriate size for sand recovery.

表2は、第1土砂水における、管部材7の各管部の管内流速の関係を示す表である。

Figure 0007068123000002
Table 2 is a table showing the relationship between the in-pipe flow velocities of each pipe portion of the pipe member 7 in the first earth and sand water.
Figure 0007068123000002

第2管部71の流速が、0.54m/secのときには、土砂水は第3管部73に達することができなかった。しかし、土砂水は、第3管部73に達しなくとも砂回収は可能である。したがって、第1管部71の流速は、3m/sec以上、好ましくは、4m/secである。又、第2管部72の流速は、0.7m/sec以上、好ましくは、0.8m/sec以上である。なお、第2管部72の口径は、第1管部71の口径より大きいので、第2管部72の流速は、第1管部71の流速を超えない。 When the flow velocity of the second pipe portion 71 was 0.54 m / sec, the earth and sand water could not reach the third pipe portion 73. However, the earth and sand water can be recovered even if it does not reach the third pipe portion 73. Therefore, the flow velocity of the first pipe portion 71 is 3 m / sec or more, preferably 4 m / sec. The flow velocity of the second pipe portion 72 is 0.7 m / sec or more, preferably 0.8 m / sec or more. Since the diameter of the second pipe portion 72 is larger than the diameter of the first pipe portion 71, the flow velocity of the second pipe portion 72 does not exceed the flow velocity of the first pipe portion 71.

次に、第1土砂水を管部材7に流したときの、5つの貫通孔毎の砂回収率を測定した。 Next, the sand recovery rate for each of the five through holes when the first earth and sand water was flowed through the pipe member 7 was measured.

図6は、貫通孔毎の砂回収率(重量比)を示した図である。図6(a)において第2管部内の流速は0.7m/secであり、図6(b)において第2管部内の流速は0.8m/secであり、図6(c)において第2管部内の流速は0.9m/secであり、図6(d)において第2管部内の流速は1.0m/secである。 FIG. 6 is a diagram showing the sand recovery rate (weight ratio) for each through hole. In FIG. 6A, the flow velocity in the second pipe portion is 0.7 m / sec, in FIG. 6B, the flow velocity in the second pipe portion is 0.8 m / sec, and in FIG. 6C, the second pipe portion is used. The flow velocity in the pipe portion is 0.9 m / sec, and the flow velocity in the second pipe portion is 1.0 m / sec in FIG. 6 (d).

第2管部内の流速が0.7m/secであるときの、5つの貫通孔の合計砂回収率は80%であり、0.8m/secであるときは80%、0.9m/secであるときは75%、1.0m/secであるときは87%である。したがって、浚渫土砂の標準的な構成である第1土砂水の場合には、貫通孔の個数は、3個以上5個以下がより好ましい。 When the flow velocity in the second pipe is 0.7 m / sec, the total sand recovery rate of the five through holes is 80%, and when it is 0.8 m / sec, it is 80% and 0.9 m / sec. At one time, it is 75%, and at 1.0 m / sec, it is 87%. Therefore, in the case of the first sediment water, which is the standard composition of dredged sediment, the number of through holes is more preferably 3 or more and 5 or less.

又、第1土砂水の場合には、第2管部内の流速は、0.7m/sec以上であることが好ましい。したがってポンプ2の吐出圧は、第2管部内の流速が、0.7m/sec以上となるように調整される。より好ましくは、第2管部内の流速は、1.0m/sec以上である。 Further, in the case of the first earth and sand water, the flow velocity in the second pipe portion is preferably 0.7 m / sec or more. Therefore, the discharge pressure of the pump 2 is adjusted so that the flow velocity in the second pipe portion is 0.7 m / sec or more. More preferably, the flow velocity in the second pipe portion is 1.0 m / sec or more.

(第1貫通孔の位置)
土砂水を吐出するポンプ6から、第1貫通孔721までの距離を変化させて適切な第1貫通孔の位置を検討した。
(Position of first through hole)
An appropriate position of the first through hole was examined by changing the distance from the pump 6 for discharging earth and sand water to the first through hole 721.

表3は、第1土砂水を流したときの第1貫通孔721から排出される土砂水(表では、泥水+砂と表記)と砂の量を測定した結果を示している。又、第2管部内の流速は、0.74m/secと0.90m/sec近傍の2通りで実験した。

Figure 0007068123000003
Table 3 shows the results of measuring the amount of earth and sand (indicated as muddy water + sand in the table) and the amount of sand discharged from the first through hole 721 when the first earth and sand water was flown. In addition, the flow velocities in the second pipe section were tested in two ways, 0.74 m / sec and around 0.90 m / sec.
Figure 0007068123000003

第1貫通孔721の位置(ポンプ6からの距離)が、10.6mから、16.6m、22.6mと遠くなるにつれて、砂の排出量はやや小さくなる傾向にある。又、ポンプ6から第1貫通孔721の距離を10m以上に取れば、乱流の影響は少ないと考えられる。したがって、第1貫通孔721の位置は、ポンプ6からの距離が10m以上であることが好ましい。又、第2管部内の流速は、0.8m/sec以上であることが好ましい。 As the position of the first through hole 721 (distance from the pump 6) increases from 10.6 m to 16.6 m and 22.6 m, the amount of sand discharged tends to be slightly smaller. Further, if the distance from the pump 6 to the first through hole 721 is set to 10 m or more, it is considered that the influence of the turbulent flow is small. Therefore, the position of the first through hole 721 preferably has a distance of 10 m or more from the pump 6. Further, the flow velocity in the second pipe portion is preferably 0.8 m / sec or more.

(邪魔板の効果)
図4において説明したように、貫通孔の前方に邪魔板を設けることにより、砂回収率が向上することが期待される。そこで、10mm×50mmの矩形貫通孔の土砂水流の下流側10mmの位置に、矩形長辺に平行に、管内壁から起立し、管内壁からの最大高さが20mmとなる厚さ6mmの板を設けて実験が行われた。なお、第1貫通孔721は、ポンプ6からの距離が10.6mの位置にあり、又、貫通孔数は、3つとして実験が行われた。
(Effect of obstacle board)
As described in FIG. 4, it is expected that the sand recovery rate will be improved by providing the baffle plate in front of the through hole. Therefore, a plate with a thickness of 6 mm, which stands up from the inner wall of the pipe and has a maximum height of 20 mm from the inner wall of the pipe, is installed at a position 10 mm downstream of the sediment water flow of the rectangular through hole of 10 mm × 50 mm in parallel with the long side of the rectangle. An experiment was conducted by setting it up. The experiment was conducted with the first through hole 721 at a position of 10.6 m from the pump 6 and the number of through holes being three.

図7は、第1土砂水について、邪魔板を設けないときと設けたときの貫通孔毎の砂回収率(重量比)とを比較した図である。図7(a)において第2管部内の流速は0.85m/secであり、図7(b)において第2管部内の流速は0.95m/secであり、図7(c)において第2管部内の流速は1.05m/secである。 FIG. 7 is a diagram comparing the sand recovery rate (weight ratio) for each through hole when the baffle plate is not provided and when the baffle plate is provided for the first earth and sand water. In FIG. 7A, the flow velocity in the second pipe portion is 0.85 m / sec, in FIG. 7B, the flow velocity in the second pipe portion is 0.95 m / sec, and in FIG. 7C, the second pipe portion is used. The flow velocity in the pipe portion is 1.05 m / sec.

貫通孔の前方に邪魔板を設けると、ほとんどの場合、砂回収率は向上する。特に、第1貫通孔における邪魔板の効果は高い。 In most cases, installing a baffle plate in front of the through hole will improve the sand recovery rate. In particular, the effect of the baffle plate in the first through hole is high.

(土砂水の特性に対する検討)
本実験では、表1に示したように、第1土砂水以外に、粘土と細砂を含む第2土砂水、粘土と粗砂を含む第3土砂水を用いて実験が行われた。第1土砂水と同様に、第2土砂水と第3土砂水について、貫通孔毎の砂回収率が測定された。
(Examination of the characteristics of earth and sand water)
In this experiment, as shown in Table 1, in addition to the first sediment water, the second sediment water containing clay and fine sand and the third sediment water containing clay and coarse sand were used. Similar to the first sediment water, the sand recovery rate for each through hole was measured for the second sediment water and the third sediment water.

図8は、第2土砂水について、邪魔板を設けないときと設けたときの貫通孔毎の砂回収率(重量比)とを比較した図である。図8(a)において第2管部内の流速は0.85m/secであり、図8(b)において第2管部内の流速は1.0m/secのであり、図8(c)において第2管部内の流速は1.1m/secである。 FIG. 8 is a diagram comparing the sand recovery rate (weight ratio) for each through hole when the baffle plate is not provided and when the second earth and sand water is provided. In FIG. 8A, the flow velocity in the second pipe portion is 0.85 m / sec, in FIG. 8B, the flow velocity in the second pipe portion is 1.0 m / sec, and in FIG. 8C, the second pipe portion is used. The flow velocity in the pipe portion is 1.1 m / sec.

貫通孔の前方に邪魔板を設けると、ほとんどの場合、砂回収率は向上する。特に、第1貫通孔における邪魔板の効果は高い。また、第1土砂水に比べ、第2土砂水の砂回収率は低い傾向にある。砂粒子が軽いからである。 In most cases, installing a baffle plate in front of the through hole will improve the sand recovery rate. In particular, the effect of the baffle plate in the first through hole is high. In addition, the sand recovery rate of the second sediment water tends to be lower than that of the first sediment water. This is because the sand particles are light.

図9は、第3土砂水について、邪魔板を設けないときと設けたときの貫通孔毎の砂回収率(重量比)とを比較した図である。図9(a)において第2管部内の流速は0.8m/secであり、図9(b)において第2管部内の流速は1.0m/secであり、図9(c)において第2管部内の流速は1.1m/secである。 FIG. 9 is a diagram comparing the sand recovery rate (weight ratio) for each through hole when the baffle plate is not provided and when the obstruction plate is provided for the third earth and sand water. In FIG. 9A, the flow velocity in the second pipe portion is 0.8 m / sec, in FIG. 9B, the flow velocity in the second pipe portion is 1.0 m / sec, and in FIG. 9C, the second pipe portion is used. The flow velocity in the pipe portion is 1.1 m / sec.

貫通孔の前方に邪魔板を設けると、ほとんどの場合、砂回収率は向上する。特に、第1貫通孔における邪魔板の効果は高い。 In most cases, installing a baffle plate in front of the through hole will improve the sand recovery rate. In particular, the effect of the baffle plate in the first through hole is high.

(本発明に係る砂回収船の概要)
浚渫作業は、港湾、河川、湖沼等、様々な場所で行われる。又、浚渫された土砂は、浚渫作業現場に近い埋め立て地に送られたり、近くに埋め立て地がない場合には、離れた土捨て場に送られたりする。そこで、本発明に係る砂回収システムを備えた砂回収船があれば、浚渫船に横付けしたり、埋め立て地の近くに接岸したりできるので、浚渫作業から砂回収までを効率的に行うことが可能になる。
(Outline of sand recovery ship according to the present invention)
Dredging work is carried out in various places such as harbors, rivers and lakes. In addition, the dredged soil is sent to a landfill near the dredging work site, or if there is no landfill nearby, it is sent to a remote landfill. Therefore, if there is a sand recovery ship equipped with the sand recovery system according to the present invention, it can be placed next to the dredging ship or berthed near the landfill, so that it is possible to efficiently perform the process from dredging work to sand recovery. become.

図10は、本発明に係る砂回収船の一例を示した図である。 FIG. 10 is a diagram showing an example of a sand recovery ship according to the present invention.

例えばグラブ浚渫船により浚渫された土砂は、土運船により陸岸に運搬される。陸岸には、砂回収船10が接岸されている。砂回収船10は、ポンプ2、管部材3、及び回収装置4を有する砂回収システム1を備えている。 For example, the earth and sand dredged by the grab dredger is transported to the shore by the earth carrier. A sand recovery vessel 10 is berthed on the shore. The sand recovery vessel 10 includes a sand recovery system 1 having a pump 2, a pipe member 3, and a recovery device 4.

土運船によって運搬された浚渫土砂は、必要であれば、海水等と混合され、土砂水となって、ポンプ2により管部材3に圧送される。管部材3によって回収された砂は、回収装置4により、例えば、ダンプカーに搭載され、砂再生場に運ばれる。一方、砂が回収された後の土砂水は、埋め立て地に送られる。本例では、砂回収船10は、接岸される例を示したが、砂回収船10は、グラブ浚渫船に横付けして砂回収処理をしてもよい。 If necessary, the dredged earth and sand carried by the earth carrier is mixed with seawater or the like to become earth and sand water, which is pumped to the pipe member 3 by the pump 2. The sand recovered by the pipe member 3 is mounted on a dump truck, for example, by the recovery device 4, and is carried to a sand recycling site. On the other hand, the earth and sand water after the sand is collected is sent to the landfill. In this example, the sand recovery vessel 10 is berthed, but the sand recovery vessel 10 may be placed next to the grab dredger to perform sand recovery processing.

当業者は、本発明の精神及び範囲から外れることなく、様々な変更、置換、及び修正をこれに加えることが可能であることを理解されたい。 It will be appreciated by those skilled in the art that various changes, substitutions and modifications can be made to this without departing from the spirit and scope of the invention.

1 砂回収システム
2、6 ポンプ
3、7 管部材
30、70 ポンプ接続部
31、71 第1管部
32、72 第2管部
321~325、721~725 貫通孔
361 邪魔板
33,73 第3管部
4 回収装置
10 砂回収船
1 Sand recovery system 2, 6 Pump 3, 7 Pipe member 30, 70 Pump connection part 31, 71 First pipe part 32, 72 Second pipe part 321 to 325, 721 to 725 Through hole 361 Obstacle plate 33, 73 Third Pipe 4 Recovery device 10 Sand recovery ship

Claims (6)

砂を含む土砂水を圧送するポンプと接続されるポンプ接続部と、
一端に前記ポンプ接続部が配置され、且つ、口径が第1径である第1管部と、
前記第1管部の他端に接続され、且つ、口径が前記第1径よりも大きい第2径である第2管部と、を有し、
前記第2管部は、内壁から外壁に貫通し、ポンプから圧送された土砂水に含まれる砂を排出する単数又は複数の貫通孔が形成される、ことを特徴とする管部材。
A pump connection that is connected to a pump that pumps earth and sand water containing sand,
A first pipe portion having the pump connection portion arranged at one end and having a diameter of the first diameter, and a first pipe portion.
It has a second pipe portion that is connected to the other end of the first pipe portion and has a second diameter larger than the first diameter.
The second pipe portion is a pipe member characterized in that a single or a plurality of through holes are formed so as to penetrate from the inner wall to the outer wall and discharge sand contained in the earth and sand water pumped from the pump.
前記第2管部の他端に接続され、且つ、口径が前記第2径よりも小さい第3径である第3管部を更に有する、請求項1に記載の管部材。 The pipe member according to claim 1, further comprising a third pipe portion which is connected to the other end of the second pipe portion and has a third diameter smaller than the second diameter. 前記単数又は複数の貫通孔の少なくとも1つの下流側に前記第2管部の内壁から起立するように配置される邪魔板を更に有する、請求項1又は2に記載の管部材。 The pipe member according to claim 1 or 2, further comprising a baffle plate arranged so as to stand up from the inner wall of the second pipe portion on the downstream side of at least one of the single or a plurality of through holes. 砂を含む土砂水を圧送するポンプと、
前記ポンプに接続され、且つ、前記ポンプから圧送された土砂水に含まれる砂を排出する管部材と、
前記管部材から排出された砂を回収する回収装置と、を有し、
前記管部材は、
前記砂を含む土砂水を圧送するポンプと接続されるポンプ接続部と、
一端に前記ポンプ接続部が配置され、且つ、口径が第1径である第1管部と、
前記第1管部の他端に接続され、且つ、口径が前記第1径よりも大きい第2径である第2管部と、を有し、
前記第2管部は、内壁から外壁に貫通し、ポンプから圧送された土砂水に含まれる砂を排出する単数又は複数の貫通孔が形成される、ことを特徴とする砂回収システム。
A pump that pumps earth and sand water containing sand,
A pipe member connected to the pump and discharging sand contained in the earth and sand water pumped from the pump.
It has a recovery device for recovering sand discharged from the pipe member, and has.
The pipe member is
A pump connection portion connected to a pump that pumps earth and sand water containing sand,
A first pipe portion having the pump connection portion arranged at one end and having a diameter of the first diameter, and a first pipe portion.
It has a second pipe portion that is connected to the other end of the first pipe portion and has a second diameter larger than the first diameter.
The second pipe portion is a sand recovery system characterized in that a single or a plurality of through holes are formed so as to penetrate from the inner wall to the outer wall and discharge the sand contained in the earth and sand water pumped from the pump.
前記ポンプは、前記第2管部を流れる土砂水の流速が0.7m/sec以上3.0m/sec以下となるように吐出圧が調整される、請求項4に記載の砂回収システム。 The sand recovery system according to claim 4, wherein the pump is adjusted in discharge pressure so that the flow velocity of the earth and sand water flowing through the second pipe portion is 0.7 m / sec or more and 3.0 m / sec or less. 砂を含む土砂水を圧送するポンプと、
前記ポンプに接続され、且つ、前記ポンプから圧送された土砂水に含まれる砂を排出する管部材と、
前記管部材から排出された砂を回収する回収装置と、を有し、
前記管部材は、
前記砂を含む土砂水を圧送するポンプと接続されるポンプ接続部と、
一端に前記ポンプ接続部が配置され、且つ、口径が第1径である第1管部と、
前記第1管部の他端に接続され、且つ、口径が前記第1径よりも大きい第2径である第2管部と、を有し、
前記第2管部は、内壁から外壁に貫通し、ポンプから圧送された土砂水に含まれる砂を排出する単数又は複数の貫通孔が形成される、ことを特徴とする砂回収船。
A pump that pumps earth and sand water containing sand,
A pipe member connected to the pump and discharging sand contained in the earth and sand water pumped from the pump.
It has a recovery device for recovering sand discharged from the pipe member, and has.
The pipe member is
A pump connection portion connected to a pump that pumps earth and sand water containing sand,
A first pipe portion having the pump connection portion arranged at one end and having a diameter of the first diameter, and a first pipe portion.
It has a second pipe portion that is connected to the other end of the first pipe portion and has a second diameter larger than the first diameter.
The second pipe portion is a sand recovery ship characterized in that a single or a plurality of through holes are formed so as to penetrate from the inner wall to the outer wall and discharge the sand contained in the earth and sand water pumped from the pump.
JP2018181662A 2018-09-27 2018-09-27 Pipe members, sand recovery systems, and sand recovery vessels Active JP7068123B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2018181662A JP7068123B2 (en) 2018-09-27 2018-09-27 Pipe members, sand recovery systems, and sand recovery vessels

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2018181662A JP7068123B2 (en) 2018-09-27 2018-09-27 Pipe members, sand recovery systems, and sand recovery vessels

Publications (2)

Publication Number Publication Date
JP2020051125A JP2020051125A (en) 2020-04-02
JP7068123B2 true JP7068123B2 (en) 2022-05-16

Family

ID=69996234

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2018181662A Active JP7068123B2 (en) 2018-09-27 2018-09-27 Pipe members, sand recovery systems, and sand recovery vessels

Country Status (1)

Country Link
JP (1) JP7068123B2 (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002113385A (en) 2000-10-05 2002-04-16 Kumamoto Sando Kogyo:Kk Apparatus for removing irregular-shaped matter in sand
JP2006241789A (en) 2005-03-02 2006-09-14 Taisei Corp Small-scale gravel removing equipment
JP6311725B2 (en) 2013-02-04 2018-04-18 アンカ・ピーティーワイ・リミテッド Pulse and gap control for electrical discharge machining equipment

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6311725A (en) * 1986-06-30 1988-01-19 Toa Harbor Works Co Ltd Method and apparatus for separating water and soil
JP2001073402A (en) * 1999-09-06 2001-03-21 Toyo Constr Co Ltd Method and device for processing dredging slurry
JP4573508B2 (en) * 2003-09-11 2010-11-04 五洋建設株式会社 Method and apparatus for classifying earth and sand slurry

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002113385A (en) 2000-10-05 2002-04-16 Kumamoto Sando Kogyo:Kk Apparatus for removing irregular-shaped matter in sand
JP2006241789A (en) 2005-03-02 2006-09-14 Taisei Corp Small-scale gravel removing equipment
JP6311725B2 (en) 2013-02-04 2018-04-18 アンカ・ピーティーワイ・リミテッド Pulse and gap control for electrical discharge machining equipment

Also Published As

Publication number Publication date
JP2020051125A (en) 2020-04-02

Similar Documents

Publication Publication Date Title
JP5679633B2 (en) Apparatus and method for slurry dewatering
US10927539B2 (en) Method and apparatus for cleaning large pipes, such as storm drain conduits
JP2013017989A (en) Method and system for dredging sludge
JP5209624B2 (en) Underwater concentration cell, sediment separator and sediment concentration method
CN210370791U (en) Tunnel adverse slope drainage auxiliary device
US9925564B2 (en) Fluidized aggregate separation system
JP7068123B2 (en) Pipe members, sand recovery systems, and sand recovery vessels
JP2005205251A (en) System and apparatus for classifying dredged soil by using pneumatic conveying system
JP4258799B2 (en) Classification method for dredged soil
US594041A (en) Placer-gold-extracting machine
JP2017002534A (en) System and method for recovering bottom mud
EP3130707A1 (en) Guide blade for an overflow structure to be placed on a vessel
JP2005282155A (en) Water bottom deleterious material removing device
KR20030005769A (en) System for segregating the dredged sediments, and a method therefor
JP2014091907A (en) System and method for separating mixture of sediment mixed with mixture
JPH03244716A (en) Dredge system
RU2789770C1 (en) Device and method for hydromechanized development of deposits of non-metallic building materials occurring in rocks with a high content of clay fraction
Zappi et al. Innovative technologies for dredging contaminated sediments
JPH01180255A (en) Classifier for dredged sediment
WO1993005243A2 (en) Suction dredger
KR100743893B1 (en) Apparatus prevention marine pollution of raw materials cargo wharf
JP2001276899A (en) Treating equipment for dredged earth and sand
NL2014509B1 (en) Overflow system.
JPH0642011A (en) Barge for pneumatic conveyance of mud
JPH0715174B2 (en) Dredging method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20210629

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20220311

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20220419

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20220428

R150 Certificate of patent or registration of utility model

Ref document number: 7068123

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350