JP6925675B1 - Construction management method of striking method and construction management system of striking method - Google Patents
Construction management method of striking method and construction management system of striking method Download PDFInfo
- Publication number
- JP6925675B1 JP6925675B1 JP2020195289A JP2020195289A JP6925675B1 JP 6925675 B1 JP6925675 B1 JP 6925675B1 JP 2020195289 A JP2020195289 A JP 2020195289A JP 2020195289 A JP2020195289 A JP 2020195289A JP 6925675 B1 JP6925675 B1 JP 6925675B1
- Authority
- JP
- Japan
- Prior art keywords
- pile
- amount
- striking
- support layer
- penetration
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Abstract
【課題】杭先端が地盤の支持層に到達したことを確実に確認でき、より完全な打ち止め管理を行うことができる打撃工法の施工管理方法を提供する。【解決手段】杭の外周面に設けられた格子柄部を撮影する、第一の撮影ステップと、第一の撮影ステップの撮影結果から、サンプリングモアレ法を用いて、杭の一打撃ごとの貫入量及びリバウンド量、所定深度あたりの打撃回数を算出する、第一の算出ステップと、第一の算出ステップで算出された貫入量及びリバウンド量を、杭の貫入深度に対してプロットした管理図を作成する、管理図作成ステップと、第一の算出ステップで算出された所定深度あたりの打撃回数を、杭の貫入深度に対してプロットした打撃回数図を作成する、打撃回数図作成ステップと、管理図と打撃回数図に基づいて、杭の支持層到達を判定する、支持層到達判定ステップと、を有する打撃工法の施工管理方法。【選択図】図3PROBLEM TO BE SOLVED: To provide a construction management method of a striking method capable of surely confirming that the tip of a pile has reached a support layer of the ground and performing more complete stoppage management. SOLUTION: From the shooting results of a first shooting step and a first shooting step in which a lattice pattern portion provided on an outer peripheral surface of a pile is photographed, a sampling moire method is used to penetrate the pile for each impact. A management diagram in which the first calculation step for calculating the amount and rebound amount and the number of hits per predetermined depth and the penetration amount and rebound amount calculated in the first calculation step are plotted against the penetration depth of the pile. Create, manage the control diagram creation step, and create the impact count diagram that plots the number of impacts per predetermined depth calculated in the first calculation step against the penetration depth of the pile. A construction management method of a striking method having a support layer arrival determination step for determining the arrival of a pile at a support layer based on a diagram and a striking frequency diagram. [Selection diagram] Fig. 3
Description
本発明は、打撃工法の施工管理方法及び打撃工法の施工管理システムに関する。 The present invention relates to a construction management method of a striking method and a construction management system of a striking method.
打撃工法の施工管理として、従来から、杭の貫入量及びリバウンド量を計測して杭の支持力を確認し、杭の打ち止めを管理することが行われている。杭の貫入量及びリバウンド量を計測する方法としては、杭の周面に貼り付けた記録紙に作業員が鉛筆を突き立て、打設時に上下動する杭の変位を記録する手動計測がある。また、杭の周面に設けられた目印の動きをカメラで撮影し、撮影した目印の軌跡を解析することによって貫入量及びリバウンド量を計測する方法がある(特許文献1乃至3)。
As the construction management of the striking method, conventionally, the intrusive amount and the rebound amount of the pile are measured to confirm the bearing capacity of the pile, and the pile stop is managed. As a method of measuring the penetration amount and the rebound amount of the pile, there is a manual measurement in which a worker thrusts a pencil on a recording paper attached to the peripheral surface of the pile and records the displacement of the pile that moves up and down at the time of driving. Further, there is a method of measuring the penetration amount and the rebound amount by photographing the movement of the mark provided on the peripheral surface of the pile with a camera and analyzing the trajectory of the photographed mark (
しかし、手動計測は、作業員がハンマの下に立つことになるため、より万全な安全対策が必要となる。また、この方法では、計測と記録に手間がかかるため、試験杭、もしくは例えば支持層が不陸している箇所等で、一定本数ごとに施工される管理杭での記録に留まっているのが現状である。 However, manual measurement requires more thorough safety measures because the worker stands under the hammer. In addition, since it takes time to measure and record with this method, the recording is limited to the test piles, or the management piles that are constructed at regular intervals, for example, in places where the support layer is not landing. The current situation.
特許文献1乃至3の方法によれば、手動計測の問題点を解決できることが期待される。しかし、特許文献1乃至3では、支持層に到達したと予想される地点から、貫入量及びリバウンド量を計測している。そのため、杭先端が地盤の支持層に到達したことを確実に確認し、より完全な打ち止め管理を行うことが求められている。
According to the methods of
本発明は上記課題に鑑みてなされたものであり、杭先端が地盤の支持層に到達したことを確実に確認でき、より完全な打ち止め管理を行うことができる打撃工法の施工管理方法及び施工管理システムを提供することを目的とする。 The present invention has been made in view of the above problems, and the construction management method and construction management of the striking method capable of surely confirming that the tip of the pile has reached the support layer of the ground and performing more complete stoppage management. The purpose is to provide a system.
本発明の打撃工法の施工管理方法は、
打撃工法の施工管理方法であって、
杭の外周面に設けられた格子柄部を撮影する、第一の撮影ステップと、
前記第一の撮影ステップの撮影結果から、サンプリングモアレ法を用いて、前記杭の一打撃ごとの貫入量及びリバウンド量、所定深度あたりの打撃回数を算出する、第一の算出ステップと、
前記第一の算出ステップで算出された貫入量及びリバウンド量を、前記杭の貫入深度に対してプロットした管理図を作成する、管理図作成ステップと、
前記第一の算出ステップで算出された所定深度あたりの打撃回数を、前記杭の貫入深度に対してプロットした打撃回数図を作成する、打撃回数図作成ステップと、
前記管理図と前記打撃回数図に基づいて、前記杭の支持層到達を判定する、支持層到達判定ステップと、
を有し、
前記支持層到達判定ステップは、
試験杭が計画支持層に到達した時の前記貫入量、前記リバウンド量及び前記所定深度あたりの打撃回数と、
前記管理図より求めた、試験杭が計画支持層に到達するまでの前記貫入量の変化傾向及び前記リバウンド量の変化傾向と、
前記打撃回数図より求めた、試験杭が計画支持層に到達するまでの前記所定深度あたりの打撃回数の変化傾向と、
を管理指標として、前記杭の支持層到達を判定するステップであることを特徴とする。
The construction management method of the striking method of the present invention is
It is a construction management method of the striking method,
The first shooting step to shoot the lattice pattern part provided on the outer peripheral surface of the pile,
From the shooting results of the first shooting step, the sampling moire method is used to calculate the penetration amount and rebound amount for each hit of the pile, and the number of hits per predetermined depth.
A control chart creation step for creating a control chart in which the intrusive amount and the rebound amount calculated in the first calculation step are plotted against the intrusive depth of the pile.
A striking number diagram creation step for creating a striking number diagram in which the number of striking per predetermined depth calculated in the first calculation step is plotted against the penetration depth of the pile.
A support layer arrival determination step for determining the arrival of the support layer of the pile based on the control chart and the impact count diagram, and
Have a,
The support layer arrival determination step is
The penetration amount, the rebound amount, and the number of hits per predetermined depth when the test pile reaches the planned support layer.
The change tendency of the penetration amount and the change tendency of the rebound amount until the test pile reaches the planned support layer, which are obtained from the control chart,
The tendency of change in the number of hits per predetermined depth until the test pile reaches the planned support layer, which was obtained from the number of hits diagram.
Is a step of determining the arrival of the support layer of the pile with the above as a management index .
また、本発明の打撃工法の施工管理システムは、
打撃工法の施工管理システムであって、
杭の外周面に設けられた格子柄部を撮影する、撮影手段と、
前記撮影手段の撮影結果から、サンプリングモアレ法を用いて、前記杭の一打撃ごとの貫入量及びリバウンド量、所定深度あたりの打撃回数を算出する、算出手段と、
前記算出手段で算出された貫入量及びリバウンド量を、前記杭の貫入深度に対してプロットした管理図を作成する、管理図作成手段と、
前記算出手段で算出された所定深度あたりの打撃回数を、前記杭の貫入深度に対してプロットした打撃回数図を作成する、打撃回数図作成手段と、
を有し、
更に、前記管理図と前記打撃回数図に基づいて、前記杭の支持層到達を判定する、支持層到達判定手段を有し、
前記支持層到達判定手段は、
試験杭が計画支持層に到達するまでの前記貫入量、前記リバウンド量及び前記所定深度あたりの打撃回数と、
前記管理図より求めた、試験杭が計画支持層に到達するまでの前記貫入量の変化傾向及び前記リバウンド量の変化傾向と、
前記打撃回数図より求めた、試験杭が計画支持層に到達するまでの前記所定深度あたりの打撃回数の変化傾向と、
を管理指標として、前記杭の支持層到達を判定することを特徴とする。
Further, the construction management system of the striking method of the present invention is
It is a construction management system of the striking method,
Photographing means for photographing the lattice pattern part provided on the outer peripheral surface of the pile,
From the imaging results of the imaging means, a calculation means for calculating the penetration amount and rebound amount for each impact of the pile, and the number of impacts per predetermined depth by using the sampling moiré method.
A control chart creating means for creating a control chart in which the intrusive amount and the rebound amount calculated by the calculation means are plotted against the intrusive depth of the pile.
A striking frequency diagram creating means for creating a striking frequency diagram in which the number of striking times per predetermined depth calculated by the calculating means is plotted against the penetration depth of the pile.
Have a,
Further, it has a support layer arrival determination means for determining the arrival of the support layer of the pile based on the control chart and the impact count diagram.
The support layer arrival determination means is
The penetration amount, the rebound amount, and the number of hits per predetermined depth until the test pile reaches the planned support layer.
The change tendency of the penetration amount and the change tendency of the rebound amount until the test pile reaches the planned support layer, which are obtained from the control chart,
The tendency of change in the number of hits per predetermined depth until the test pile reaches the planned support layer, which was obtained from the number of hits diagram.
Is used as a management index to determine the arrival of the support layer of the pile.
本発明によれば、杭先端が地盤の支持層に到達したことを確実に確認でき、より完全な打ち止め管理を行うことが可能である。 According to the present invention, it is possible to surely confirm that the tip of the pile has reached the support layer of the ground, and it is possible to perform more complete stoppage management.
以下、本発明を実施するための形態を、図面を用いて詳細に説明するが、本発明は、以下に説明する実施形態に限定されるものではない。 Hereinafter, embodiments for carrying out the present invention will be described in detail with reference to the drawings, but the present invention is not limited to the embodiments described below.
≪打撃工法の施工管理システム≫
本発明に係る施工管理システムは、油圧ハンマ、ドロップハンマ等により既製杭等の杭頭部を打撃して杭を打込む打撃工法の施工を管理するシステムである。本発明に係る施工管理システムは、直杭打設、斜杭打設のいずれにも適用可能である。また、本発明に係る施工管理システムは、施工管理を補助するシステムとして使用することもできる。
≪Construction management system for striking method≫
The construction management system according to the present invention is a system that manages the construction of a striking method in which a pile head of a ready-made pile or the like is striked with a hydraulic hammer, a drop hammer or the like to drive the pile. The construction management system according to the present invention can be applied to both straight pile driving and diagonal pile driving. Further, the construction management system according to the present invention can also be used as a system for assisting construction management.
図1は、本発明に係る打撃工法の施工管理システムの構成の一例を示すブロック図である。図1に示す施工管理システムは、撮影手段1とパーソナルコンピューター(PC)2を有する。図1において、1は撮影手段、2はパーソナルコンピューター、3は算出手段、4は管理図作成手段、5は打撃回数図作成手段、6は杭打ち特性図作成手段、7は支持層到達判定手段、8は打撃エネルギー決定手段、9は支持力算定手段、10は打ち止め判定手段、11は表示手段、12は制御手段である。 FIG. 1 is a block diagram showing an example of the configuration of the construction management system of the striking method according to the present invention. The construction management system shown in FIG. 1 includes a photographing means 1 and a personal computer (PC) 2. In FIG. 1, 1 is a photographing means, 2 is a personal computer, 3 is a calculation means, 4 is a control chart creating means, 5 is a striking count chart creating means, 6 is a pile driving characteristic diagram creating means, and 7 is a support layer arrival determination means. , 8 is a striking energy determining means, 9 is a bearing capacity calculating means, 10 is a stop determining means, 11 is a display means, and 12 is a control means.
<撮影手段1>
撮影手段1は、打設杭の外周面に設けられた格子柄部を撮影する手段である。撮影手段1は、例えば500コマ/秒程度の高速撮影が可能な高速度カメラであることが好ましい。また、撮影手段1は、モアレ測定解析手段を有し、パーソナルコンピューター2へのデータ伝送機能を有するものが好ましい。具体的には、例えば、「DSMC−100A」((株)共和電業製)等のサンプリングモアレカメラ等が挙げられる。撮影手段1は、望遠レンズを備えていても良い。撮影手段1は、打設される杭から比較的離れた、例えは10mから100m程度、好ましくは15mから50m程度離れた、杭打設の影響を受けにくい位置に設置することが好ましい。
<Shooting means 1>
The photographing means 1 is a means for photographing the lattice pattern portion provided on the outer peripheral surface of the driving pile. The photographing means 1 is preferably a high-speed camera capable of high-speed photographing of, for example, about 500 frames / sec. Further, it is preferable that the photographing means 1 has moire measurement and analysis means and has a data transmission function to the
<パーソナルコンピューター(PC)2>
パーソナルコンピューター2は、格子柄部を撮影した撮影手段1の撮影結果を算出手段3に取り込む。
<Personal computer (PC) 2>
The
算出手段3は、撮影手段1の撮影結果から、サンプリングモアレ法を用いて、例えば図4に示すような貫入量記録図を作成すると共に、杭の一打撃ごとの貫入量S及びリバウンド量K、更には、所定深度あたりの打撃回数を算出する。算出手段3は、複数回(例えば10回)の打撃の貫入量S及びリバウンド量Kを平均して、一打撃ごとの貫入量S及びリバウンド量Kとして算出することもできる。
The calculation means 3 creates a penetration amount recording diagram as shown in, for example, FIG. 4 by using the sampling moiré method from the shooting result of the photographing
管理図作成手段4は、算出手段3で算出された一打撃ごとの貫入量S及びリバウンド量Kを、杭の貫入深度に対してプロットし、例えば図5に示すような管理図を作成する。尚、図5では、貫入量Sの曲線とリバウンド量Kの曲線は所定の深度で交差しているが、両曲線が交差しない場合もある。打撃回数図作成手段5は、算出手段3で算出された所定深度あたりの打撃回数を、杭の貫入深度に対してプロットし、例えば図6に示すような打撃回数図を作成する。尚、図6は、25cmあたりの打撃回数を示している。杭打ち特性図作成手段6は、算出手段3で算出された一打撃ごとの貫入量S及びリバウンド量Kを、打撃エネルギーに対してプロットし、例えば図7に示すような杭打ち特性図を作成する。杭打ち特性図にプロットする各打撃エネルギーに対する貫入量S及びリバウンド量Kは、各打撃エネルギーにおいて複数回(例えば10回)の打撃の平均値でもよい。尚、図1の施工管理システムは、杭打ち特性図作成手段6を有するが、作業員が、パーソナルコンピューター2の入力手段(不図示)を用いて算出値を入力することにより杭打ち特性図を作成する場合には、杭打ち特性図作成手段6を設けなくてもよい。
The control chart creating means 4 plots the penetration amount S and the rebound amount K for each impact calculated by the calculation means 3 with respect to the penetration depth of the pile, and creates a control chart as shown in FIG. 5, for example. In FIG. 5, the curve of the penetration amount S and the curve of the rebound amount K intersect at a predetermined depth, but the two curves may not intersect. The hit count diagram creating means 5 plots the hit count per predetermined depth calculated by the calculation means 3 with respect to the penetration depth of the pile, and creates a hit count diagram as shown in FIG. 6, for example. Note that FIG. 6 shows the number of hits per 25 cm. The pile driving characteristic diagram creating means 6 plots the penetration amount S and the rebound amount K for each impact calculated by the calculating means 3 with respect to the impact energy, and creates a pile driving characteristic diagram as shown in FIG. 7, for example. do. The penetration amount S and the rebound amount K for each striking energy plotted on the pile driving characteristic diagram may be the average value of a plurality of (for example, 10) striking at each striking energy. The construction management system of FIG. 1 has a pile driving characteristic diagram creating means 6, but a worker inputs a calculated value using an input means (not shown) of the
支持層到達判定手段7は、管理図と打撃回数図に基づいて、杭の支持層到達を判定する。尚、図1の施工管理システムは、支持層到達判定手段7を有するが、管理図と打撃回数図を表示手段11に表示して作業員が目視で支持層到達を判定する場合には、支持層到達判定手段7を設けなくてもよい。 The support layer arrival determination means 7 determines the arrival of the support layer of the pile based on the control chart and the number of hits diagram. The construction management system of FIG. 1 has a support layer arrival determination means 7, but when the control chart and the hit count diagram are displayed on the display means 11 and the operator visually determines the arrival of the support layer, the support layer is supported. It is not necessary to provide the layer arrival determination means 7.
打撃エネルギー決定手段8は、杭打ち特性図に基づいて、リバウンド量Kがほぼ一定値になり始める打撃エネルギーを、支持層に根入れする際の打撃エネルギーとして決定する。尚、図1の施工管理システムは、打撃エネルギー決定手段8を有するが、杭打ち特性図を表示手段11に表示して作業員が目視で打撃エネルギーを決定する場合には、打撃エネルギー決定手段8を設けなくてもよい。
The striking
支持力算定手段9は、算出手段3で算出された一打撃ごとの貫入量及びリバウンド量を用いて、例えば、宇都・冬木の式(旧道示式)等の打止め管理式から支持力を算定する。打止め管理式から支持力を算定するために用いる貫入量S及びリバウンド量Kは、複数回(例えば10回)の打撃の平均値でもよい。打ち止め判定手段10は、算出手段3で算出された一打撃ごとの貫入量及びリバウンド量と、支持力算定手段9で算定された支持力に基づいて、杭の打ち止めを判定する。尚、図1の施工管理システムは、支持力算定手段9と、打ち止め判定手段10を有するが、打ち止め判定をしない場合には、打ち止め判定手段10を設けなくてもよいし、支持力算定手段9と打ち止め判定手段10を設けなくてもよい。 The bearing capacity calculation means 9 calculates the bearing capacity from a stop management formula such as the Uto / Fuyuki formula (old road indication formula) using the intrusive amount and the rebound amount for each hit calculated by the calculation means 3. do. The penetration amount S and the rebound amount K used for calculating the bearing capacity from the stop control formula may be the average value of a plurality of (for example, 10) hits. The stop determination means 10 determines the stop of the pile based on the penetration amount and the rebound amount for each impact calculated by the calculation means 3 and the bearing force calculated by the bearing capacity calculation means 9. The construction management system of FIG. 1 has a bearing capacity calculation means 9 and a stop determination means 10. However, when the stop determination is not made, the stop determination means 10 may not be provided, and the bearing capacity calculation means 9 may be provided. It is not necessary to provide the stop determination means 10.
表示手段11は、例えばディスプレイ等であり、貫入量記録図、管理図、打撃回数図、杭打ち特性図等を、リアルタイムで表示する。 The display means 11 is, for example, a display or the like, and displays a penetration amount record chart, a control chart, a hit count chart, a pile driving characteristic diagram, and the like in real time.
制御手段12は、撮影手段1、算出手段3、表示手段11等を制御する。
The control means 12 controls the photographing
杭の貫入量及びリバウンド量の算出、杭の支持層到達の判定、杭の打ち止め判定の詳細については後述する。 Details of the calculation of the intrusive amount and the rebound amount of the pile, the determination of reaching the support layer of the pile, and the determination of stopping the pile will be described later.
≪打撃工法の施工管理方法≫
以下、上述した本発明に係る施工管理システムを利用した、本発明に係る打撃工法の施工管理方法について、打ち止め判定まで行う場合を例にとり説明する。本発明に係る施工管理方法は、直杭打設、斜杭打設のいずれにも適用可能である。
≪Construction management method of striking method≫
Hereinafter, the construction management method of the striking method according to the present invention using the construction management system according to the present invention described above will be described by taking as an example a case where a stop determination is performed. The construction management method according to the present invention can be applied to both straight pile driving and diagonal pile driving.
[試験杭の施工(管理指標の作成)]
まずは、地盤調査を実施した箇所またはその直近の箇所で、試験杭を施工する。ここで、試験杭とは、その現場で最初に施工する杭である。試験杭の支持層上面の位置は、地盤調査結果を元に設計で決められた支持層上面(計画支持層面)と同じと判断でき、また、試験杭の支持層は、地盤調査結果に示されている深さにあるN値、厚さの土質と同じであると判断できる。したがって、試験杭で得られた施工データは、その地盤に施工される杭を代表する施工データを表していることになり、管理指標として使用できる。試験杭の施工は、具体的には、油圧ハンマ、ドロップハンマ等により既製杭等の杭頭部を打撃して杭を打込むことにより行われる。
[Construction of test piles (creation of management indicators)]
First, a test pile will be constructed at the location where the ground survey was conducted or at the location closest to it. Here, the test pile is the pile to be constructed first at the site. The position of the upper surface of the support layer of the test pile can be judged to be the same as the upper surface of the support layer (planned support layer surface) determined by design based on the ground survey results, and the support layer of the test pile is shown in the ground survey results. It can be judged that the N value and the thickness of the soil are the same as those of the soil. Therefore, the construction data obtained from the test pile represents the construction data representing the pile to be constructed on the ground, and can be used as a management index. Specifically, the test pile is constructed by hitting the pile head of a ready-made pile or the like with a hydraulic hammer, a drop hammer or the like to drive the pile.
<格子柄部の設置、撮影手段1の設置>
打撃を開始し、杭先端が計画支持層上面の手前の所定の位置、例えば、計画支持層上面の手前3D(D:杭径)の位置に到達したら、打撃を一旦停止する。
<Installation of lattice handle, installation of photography means 1>
The striking is started, and when the tip of the pile reaches a predetermined position in front of the upper surface of the planned support layer, for example, a position of 3D (D: pile diameter) in front of the upper surface of the planned support layer, the striking is temporarily stopped.
打撃を一旦停止した後、打設時に露出している杭の外周面に格子柄部を設置する。防音装置を使用する場合には、防音装置の窓越しに見える位置に格子柄部を設置すればよい。格子柄部の設置方法としては、例えば、格子柄シートを杭の外周面に貼り付ける方法、杭の外周面に格子柄を描画する方法等が挙げられる。設置の容易さより、格子柄シートを杭の外周面に貼り付ける方法が好ましい。格子柄シートとしては、例えば、裏面に粘着層を有する粘着タイプ、裏面にマグネット層を有するマグネットタイプ等が挙げられ、施工地盤の固さ、杭の材質・表面状態等を勘案して、適宜決定すればよい。格子柄シートの大きさとしては特に限定されないが、例えば、幅200mm程度×高さ600mm程度の大きさが挙げられる。また、格子柄シートは、格子柄の大きさやピッチが異なる複数種類の格子柄シートを予め用意しておくことが好ましい。そして、撮影対象の格子柄部と撮影手段との間の距離や、杭の打設時における格子柄部の変位量等に応じて、適切な大きさやピッチを有する格子柄シートを選定する。 After the striking is temporarily stopped, a grid handle is installed on the outer peripheral surface of the pile that is exposed at the time of driving. When the soundproofing device is used, the lattice pattern portion may be installed at a position visible through the window of the soundproofing device. Examples of the method of installing the lattice pattern portion include a method of attaching a lattice pattern sheet to the outer peripheral surface of the pile, a method of drawing a lattice pattern on the outer peripheral surface of the pile, and the like. From the viewpoint of ease of installation, a method of attaching a lattice pattern sheet to the outer peripheral surface of the pile is preferable. Examples of the lattice pattern sheet include an adhesive type having an adhesive layer on the back surface and a magnet type having a magnet layer on the back surface, and are appropriately determined in consideration of the hardness of the construction ground, the material and surface condition of the pile, and the like. do it. The size of the lattice pattern sheet is not particularly limited, and examples thereof include a size of about 200 mm in width × about 600 mm in height. Further, as the lattice pattern sheet, it is preferable to prepare a plurality of types of lattice pattern sheets having different sizes and pitches of the lattice patterns in advance. Then, a lattice pattern sheet having an appropriate size and pitch is selected according to the distance between the lattice pattern portion to be photographed and the photographing means, the amount of displacement of the lattice pattern portion at the time of driving the pile, and the like.
撮影手段1は、打設される杭から比較的離れた、例えは10mから100m程度、好ましくは15mから50m程度離れた、杭打設の影響を受けにくい位置に設置する。更に、パーソナルコンピューター2を、撮影手段1の設置位置に応じた適切な位置に設置する。
The photographing means 1 is installed at a position relatively far from the pile to be driven, for example, about 10 m to 100 m, preferably about 15 m to 50 m, and is not easily affected by the pile driving. Further, the
なお、格子柄部、撮影手段1は打撃開始前に設置してもよい。この場合は、打撃を一旦停止しなくてもよい。
The lattice handle portion and the photographing
以下、格子柄部の撮影開始後の手順について、図2に示すフロー図の流れに沿って説明する。 Hereinafter, the procedure after the start of photographing the lattice pattern portion will be described along with the flow of the flow chart shown in FIG.
<撮影開始(S1)>
撮影手段1で、杭の外周面に設けられた格子柄部の撮影を開始する。
<Start shooting (S1)>
The photographing means 1 starts photographing the lattice pattern portion provided on the outer peripheral surface of the pile.
<打撃(S2)>
油圧ハンマ等を使用して杭を1回打撃する。尚、通常、打撃は複数回行われるので、各打撃の打撃エネルギーは一定とする。
<Blow (S2)>
Hit the pile once using a hydraulic hammer or the like. Since the hits are usually performed a plurality of times, the hit energy of each hit is constant.
<貫入量S、リバウンド量K、所定深度あたりの打撃回数の算出(S3)>
算出手段3は、格子柄部の撮影結果から、サンプリングモアレ法を用いて、杭の一打撃ごとの貫入量S及びリバウンド量K、所定深度あたりの打撃回数を算出する。算出手段3は、複数回(例えば10回)の打撃の貫入量S及びリバウンド量Kを平均して、一打撃ごとの貫入量S及びリバウンド量Kとして算出することもできる。具体的には、打撃時に撮影手段1によって撮影された、格子柄部の撮影画像から、サンプリングモアレ法を利用して、経過時間毎の杭の変位量を算出する。このとき、撮影手段1が、杭への打撃の影響を受けない程度に離れた位置に設置されていれば、特に撮影手段1の振動の影響等は考慮せずに算出を行うことができる。そして算出手段3は、杭の変位量を経過時間に対してプロットし、例えば図4に示すような貫入量記録図を作成してリアルタイムでパーソナルコンピューター2の表示手段11に表示すると共に、図4に示す貫入量S、リバウンド量K、更には所定深度あたりの打撃回数を算出する。
<Calculation of penetration amount S, rebound amount K, number of hits per predetermined depth (S3)>
The calculation means 3 calculates the penetration amount S and the rebound amount K for each impact of the pile, and the number of impacts per predetermined depth by using the sampling moiré method from the imaging result of the lattice pattern portion. The calculation means 3 can also average the intrusive amount S and the rebound amount K of a plurality of (for example, 10) hits and calculate as the intrusive amount S and the rebound amount K for each hit. Specifically, the displacement amount of the pile for each elapsed time is calculated from the photographed image of the lattice pattern portion taken by the photographing
<管理図の作成、打撃回数図の作成(S4)>
管理図作成手段4は、S3で算出された貫入量S及びリバウンド量Kを、杭の貫入深度に対してプロットし、例えば図5に示すような管理図を作成する。管理図はリアルタイムで、パーソナルコンピューター2の表示手段11に表示される。
<Creation of control chart, creation of hit count chart (S4)>
The control chart creating means 4 plots the penetration amount S and the rebound amount K calculated in S3 with respect to the penetration depth of the pile, and creates a control chart as shown in FIG. 5, for example. The control chart is displayed in real time on the display means 11 of the
また、打撃回数図作成手段5は、S3で算出された所定深度あたりの打撃回数を、杭の貫入深度に対してプロットし、例えば図6に示すような打撃回数図を作成する。尚、図6は、25cmあたりの打撃回数を示しているが、50cmあたりまたは任意区間あたりの打撃回数を示してもよい。打撃回数図はリアルタイムで、パーソナルコンピューター2の表示手段11に表示される。
Further, the striking number chart creating means 5 plots the striking number per predetermined depth calculated in S3 with respect to the penetration depth of the pile, and creates a striking count diagram as shown in FIG. 6, for example. Although FIG. 6 shows the number of hits per 25 cm, the number of hits per 50 cm or an arbitrary section may be shown. The number of hits diagram is displayed in real time on the display means 11 of the
ここで得られた管理図、打撃回数図は、本杭の支持層到達判定の際に、管理指標として使用できる。 The control chart and the number of hits obtained here can be used as a control index when determining the arrival of the support layer of the main pile.
<計画支持層への到達判定(S5)>
算出手段3は、S3で求めた貫入量Sを用いて杭の貫入深度を算出し、杭の先端が地中の計画支持層に到達したか否かを判定する。その結果、杭が計画支持層に到達したと判定した場合(YES)は、S6へ移行し、まだ杭が計画支持層に到達してないと判定した場合(NO)は、S2へ復帰する。すなわち、杭が計画支持層に達するまで、S2からS5を繰り返し実行する。
<Determination of arrival at the plan support layer (S5)>
The calculation means 3 calculates the penetration depth of the pile using the penetration amount S obtained in S3, and determines whether or not the tip of the pile has reached the planned support layer in the ground. As a result, when it is determined that the pile has reached the planned support layer (YES), the process proceeds to S6, and when it is determined that the pile has not reached the planned support layer (NO), the process returns to S2. That is, S2 to S5 are repeatedly executed until the pile reaches the planned support layer.
<根入れ時の打撃エネルギーの決定(S6)>
打撃エネルギーを数段階変化させ、支持層に根入れする際の打撃エネルギーを決定する。具体的には、打撃エネルギーを数段階変化させ、S3と同様にして、各打撃エネルギーにおける一打撃ごとの貫入量Sとリバウンド量Kを算出する。杭打ち特性図作成手段6または作業員は、得られた貫入量Sとリバウンド量Kを用いて、例えば図7に示すような杭打ち特性図を作成する。杭打ち特性図にプロットする各打撃エネルギーに対する貫入量S及びリバウンド量Kは、各打撃エネルギーにおいて複数回(例えば10回)の打撃の平均値でもよい。杭打ち特性図は、パーソナルコンピューター2の表示手段11に表示される。尚、図7では、打撃エネルギーを、10kN・mから50kN・mの間で5段階変化させている。打撃エネルギー決定手段8または作業員が、杭打ち特性図より、リバウンド量Kがほぼ一定値になり始める打撃エネルギー、図7では40kN・mを、支持層に根入れする際の打撃エネルギーと決定する。尚、杭の本数が多い場合等には、一定本数ごとに施工される管理杭についても杭打ち特性図を作成し、支持層に根入れする際の打撃エネルギーの確認するのがよい。
<Determination of striking energy at the time of rooting (S6)>
The striking energy is changed in several steps to determine the striking energy when rooting in the support layer. Specifically, the striking energy is changed in several steps, and the penetration amount S and the rebound amount K for each striking at each striking energy are calculated in the same manner as in S3. The pile driving characteristic diagram creating means 6 or the worker creates a pile driving characteristic diagram as shown in FIG. 7, for example, by using the obtained penetration amount S and the rebound amount K. The penetration amount S and the rebound amount K for each striking energy plotted on the pile driving characteristic diagram may be the average value of a plurality of (for example, 10) striking at each striking energy. The pile driving characteristic diagram is displayed on the display means 11 of the
<打撃(S7)>
S6で決定した打撃エネルギーで杭を1回打撃して、支持層へ根入れする。
<Blow (S7)>
The pile is hit once with the hitting energy determined in S6 and rooted in the support layer.
<貫入量S及びリバウンド量Kの算出(S8)>
S7の打撃の撮影結果から、S3と同様にして、貫入量S及びリバウンド量Kを算出する。
<Calculation of penetration amount S and rebound amount K (S8)>
From the shooting result of the impact of S7, the penetration amount S and the rebound amount K are calculated in the same manner as in S3.
<根入れ深さの判定(S9)>
算出手段3は、S8で求めた貫入量Sを用いて根入れ深さを算出し、所定の深度、例えば設計で定められた深度まで根入れしたか否かを判定する。その結果、所定の深度まで根入れしたと判定した場合(YES)は、S10へ移行し、まだ所定の深度まで根入れしていないと判定した場合(NO)は、S7へ復帰する。すなわち、所定の深度まで根入れするまで、S7からS9を繰り返し実行する。
<Determination of rooting depth (S9)>
The calculation means 3 calculates the penetration depth using the penetration amount S obtained in S8, and determines whether or not the penetration has been made to a predetermined depth, for example, a depth determined by the design. As a result, if it is determined that the root has been rooted to a predetermined depth (YES), the process proceeds to S10, and if it is determined that the root has not yet been rooted to a predetermined depth (NO), the process returns to S7. That is, S7 to S9 are repeatedly executed until the root is rooted to a predetermined depth.
<支持力の算出(S10)>
支持力算定手段9は、S8で算出した、所定の深度まで根入れしたと判定された時の貫入量Sとリバウンド量Kを用いて、打止め管理式から支持力を求める。打ち止め管理式としては、例えば、宇都・冬木の式(旧道示式)、ハイリーの簡略式、5S式(旧建設省告示式)、これらの式において係数を考慮した式等が挙げられる。
<Calculation of bearing capacity (S10)>
The bearing capacity calculating means 9 obtains the bearing capacity from the stop management formula using the penetration amount S and the rebound amount K when it is determined that the root has been rooted to a predetermined depth calculated in S8. Examples of the stop management formula include the Uto / Fuyuki formula (former road indication formula), Hailey's simplified formula, 5S formula (former Ministry of Construction notification formula), and formulas that take factors into consideration in these formulas.
<終了(打ち止め)>
S10の後、試験杭の打ち止めとし、撮影を終了する。尚、打ち止めの最終判断は、S10で算出された支持力等に基づき、必要に応じて関係者間の協議を経た上で、責任者が行うことが好ましい。S10で用いた貫入量Sとリバウンド量K、S10で算出した支持力、即ち、試験杭の打ち止め時の貫入量S、リバウンド量K、支持力は、本杭の打ち止め判定の際に、管理指標として使用できる。
<End (stop)>
After S10, the test pile is stopped and the shooting is finished. It is preferable that the person in charge makes the final decision on the suspension after consulting with the parties concerned as necessary based on the bearing capacity calculated in S10. The penetration amount S and rebound amount K used in S10, and the bearing capacity calculated in S10, that is, the penetration amount S, the rebound amount K, and the bearing capacity at the time of stopping the test pile are management indexes when determining the stopping of the main pile. Can be used as.
[本杭の施工管理]
試験杭の施工後に本杭を施工する。ここで、本杭とは、その現場で二番目以降に施工する杭である。本杭の施工も、試験杭と同様に、油圧ハンマ等により杭頭部を打撃して杭を打込むことにより行われる。
[Construction management of this pile]
After the test pile is constructed, the main pile will be constructed. Here, the main pile is a pile to be constructed at the site after the second. Similar to the test pile, the construction of the main pile is also performed by hitting the pile head with a hydraulic hammer or the like to drive the pile.
まずは、打撃を開始し、杭先端が計画支持層上面の手前の所定の位置、例えば、計画支持層上面の手前3D(D:杭径)の位置に到達したら、打撃を一旦停止する。その後、試験杭の施工と同様にして、格子柄部と撮影手段1を設置する。試験杭の施工と同様、格子柄部、撮影手段1は打撃開始前に設置してもよく、この場合は打撃を一旦停止しなくてもよい。
First, the striking is started, and when the tip of the pile reaches a predetermined position in front of the upper surface of the planned support layer, for example, a position of 3D (D: pile diameter) in front of the upper surface of the planned support layer, the striking is temporarily stopped. After that, the lattice handle portion and the photographing
以下、格子柄部の撮影開始後の手順について、図3に示すフロー図の流れに沿って説明する。 Hereinafter, the procedure after the start of photographing the lattice pattern portion will be described along the flow of the flow chart shown in FIG.
<撮影開始(S21)>
撮影手段1で、杭の外周面に設けられた格子柄部の撮影を開始する。
<Start shooting (S21)>
The photographing means 1 starts photographing the lattice pattern portion provided on the outer peripheral surface of the pile.
<打撃(S22)>
油圧ハンマ等を使用して、試験杭と同じ打撃エネルギー、即ちS2と同じ打撃エネルギーで杭を1回打撃する。
<Blow (S22)>
Using a hydraulic hammer or the like, the pile is hit once with the same striking energy as the test pile, that is, the same striking energy as S2.
<貫入量S、リバウンド量K、所定深度あたりの打撃回数の算出(S23:第一の算出ステップ)>
S22の打撃の撮影(第一の撮影ステップ)結果から、S3と同様にして、貫入量S、リバウンド量K、所定深度あたりの打撃回数を算出する。
<Calculation of penetration amount S, rebound amount K, number of hits per predetermined depth (S23: first calculation step)>
From the result of shooting the blow of S22 (first shooting step), the penetration amount S, the rebound amount K, and the number of hits per predetermined depth are calculated in the same manner as in S3.
<管理図及び打撃回数図の作成(S24:管理図作成ステップ、打撃回数図作成ステップ)>
S23の算出結果から、S4と同様にして、管理図及び打撃回数図を作成する。
<Creation of control chart and hit count chart (S24: control chart creation step, hit count chart creation step)>
From the calculation result of S23, a control chart and a hit count chart are created in the same manner as in S4.
<支持層到達判定(S25:支持層到達判定ステップ)>
S24で作成した管理図と打撃回数図に基づいて、杭の先端が地中の支持層に到達したか否かを判定する。具体的には、下記要素1−4を、それぞれ対応する下記管理指標1−4と比較する。比較は、支持層到達判定手段7が行ってもよいし、表示手段11に表示された各要素に基づいて、作業員が目視により行ってもよい。
<Support layer arrival determination (S25: Support layer arrival determination step)>
Based on the control chart and the number of hits chart created in S24, it is determined whether or not the tip of the pile has reached the support layer in the ground. Specifically, the following elements 1-4 are compared with the corresponding following management indexes 1-4. The comparison may be performed by the support layer arrival determination means 7, or may be visually performed by an operator based on each element displayed on the display means 11.
(要素)
要素1:S23で算出した貫入量S、リバウンド量K。
要素2:S23で算出した所定深度あたりの打撃回数。
要素3:S24で作成した管理図より求めた、貫入量Sの変化傾向及びリバウンド量Kの変化傾向。
要素4:S24で作成した打撃回数図より求めた、所定深度あたりの打撃回数の変化傾向。
(element)
Element 1: Penetration amount S and rebound amount K calculated in S23.
Element 2: The number of hits per predetermined depth calculated in S23.
Element 3: The change tendency of the penetration amount S and the change tendency of the rebound amount K obtained from the control chart created in S24.
Element 4: Change tendency of the number of hits per predetermined depth obtained from the number of hits diagram created in S24.
(管理指標)
管理指標1:試験杭が計画支持層に到達した時の貫入量S、リバウンド量K。
管理指標2:試験杭が計画支持層に到達した時の所定深度あたりの打撃回数。
管理指標3:S4で作成した管理図より求めた、試験杭が計画支持層に到達するまでの貫入量Sの変化傾向及びリバウンド量Kの変化傾向。
管理指標4:S4で作成した打撃回数図より求めた、試験杭が計画支持層に到達するまでの所定深度あたりの打撃回数の変化傾向。
(management indicator)
Management index 1: Penetration amount S and rebound amount K when the test pile reaches the planned support layer.
Control index 2: The number of hits per predetermined depth when the test pile reaches the planned support layer.
Control index 3: The tendency of change in the penetration amount S and the change tendency of the rebound amount K until the test pile reaches the planned support layer, which is obtained from the control chart created in S4.
Management index 4: Change tendency of the number of hits per predetermined depth until the test pile reaches the planned support layer, which is obtained from the hit count diagram created in S4.
そして、各要素と、対応する管理指標がほぼ同等であれば、杭が支持層に到達したと判定する。その結果、杭が支持層に到達したと判定した場合(YES)は、S26へ移行し、まだ杭が支持層に到達してないと判定した場合(NO)は、S22へ復帰する。すなわち、杭が支持層に達するまで、S22からS25を繰り返し実行する。尚、支持層到達の最終判断は、各要素と対応する管理指標との比較結果に基づき、必要に応じて関係者間の協議を経た上で、責任者が行うことが好ましい。 Then, if each element and the corresponding management index are substantially the same, it is determined that the pile has reached the support layer. As a result, when it is determined that the pile has reached the support layer (YES), the process proceeds to S26, and when it is determined that the pile has not reached the support layer (NO), the process returns to S22. That is, S22 to S25 are repeatedly executed until the pile reaches the support layer. It is preferable that the person in charge makes the final decision to reach the support layer, based on the result of comparison between each element and the corresponding management index, and after consultation between the parties concerned as necessary.
<打撃(S26:打撃ステップ)>
S6で決定した根入れ時の打撃エネルギーで杭を1回打撃して、支持層へ根入れする。
<Blow (S26: Blow step)>
The pile is hit once with the striking energy at the time of rooting determined in S6, and rooted in the support layer.
<貫入量S及びリバウンド量Kの算出(S27:第二の算出ステップ)>
S22の打撃の撮影(第二の撮影ステップ)結果から、S23と同様にして、貫入量S及びリバウンド量Kを算出する。
<Calculation of penetration amount S and rebound amount K (S27: second calculation step)>
From the result of shooting the blow of S22 (second shooting step), the penetration amount S and the rebound amount K are calculated in the same manner as in S23.
<根入れ深さの判定(S28)>
S27で求めた貫入量Sを用いてS9と同様にして、所定の深度まで根入れしたか否かを判定する。その結果、所定の深度まで根入れしたと判定した場合(YES)は、S29へ移行し、まだ所定の深度まで根入れしていないと判定した場合(NO)は、S26へ復帰する。すなわち、所定の深度まで根入れするまで、S26からS28を繰り返し実行する。
<Determination of rooting depth (S28)>
Using the penetration amount S obtained in S27, it is determined in the same manner as in S9 whether or not the rooting has been performed to a predetermined depth. As a result, if it is determined that the root has been rooted to a predetermined depth (YES), the process proceeds to S29, and if it is determined that the root has not yet been rooted to the predetermined depth (NO), the process returns to S26. That is, S26 to S28 are repeatedly executed until the root is rooted to a predetermined depth.
<支持力の算出(S29)>
S27で算出した、所定の深度まで根入れしたと判定された時の貫入量Sとリバウンド量Kを用いて、S10と同様にして、支持力を算出する。
<Calculation of bearing capacity (S29)>
The bearing capacity is calculated in the same manner as in S10 by using the penetration amount S and the rebound amount K when it is determined that the root has been rooted to a predetermined depth calculated in S27.
<打ち止め判定(S30:打ち止め判定ステップ)>
S29で用いた貫入量S及びリバウンド量Kと、S29で算出した支持力とに基づいて、打ち止めするか否かを判定する。具体的には、下記要素11−12を、それぞれ対応する下記管理指標11−12と比較する。比較は、打ち止め判定手段10が行ってもよいし、表示手段11に表示された各要素に基づいて、作業員が目視により行ってもよい。作業員が比較する場合には、表示手段11に、例えば、図4に示すような貫入量記録図と、各要素を含む必要情報を表示してもよい。
<Stop Judgment (S30: Stop Judgment Step)>
Based on the penetration amount S and the rebound amount K used in S29 and the bearing capacity calculated in S29, it is determined whether or not to stop. Specifically, the following elements 11-12 are compared with the corresponding following management indicators 11-12, respectively. The comparison may be performed by the stop determination means 10 or may be visually performed by the operator based on each element displayed on the display means 11. When the workers compare, the display means 11 may display, for example, a penetration amount recording diagram as shown in FIG. 4 and necessary information including each element.
(要素)
要素11:S29で用いた貫入量S及びリバウンド量K。
要素12:S29で算出した支持力。
(element)
Element 11: Penetration amount S and rebound amount K used in S29.
Element 12: Bearing capacity calculated in S29.
(管理指標)
管理指標11:S10で用いた貫入量S及びリバウンド量K。
管理指標12:S10で算出した支持力。
(management indicator)
Management index 11: Penetration amount S and rebound amount K used in S10.
Management index 12: Supporting capacity calculated in S10.
そして、各要素と、対応する管理指標がほぼ同等であれば、打ち止めと判定し、撮影を終了する。その結果、打ち止めと判定した場合(YES)は、施工を終了し、打ち止めしないと判定した場合(NO)は、S26へ復帰する。すなわち、打ち止めと判定されるまで、S26からS29を繰り返し実行する。尚、打ち止めの最終判断は、各要素と対応する管理指標との比較結果に基づき、必要に応じて関係者間の協議を経た上で、責任者が行うことが好ましい。 Then, if each element and the corresponding management index are substantially the same, it is determined that the shooting is stopped, and the shooting is terminated. As a result, if it is determined that the work is to be stopped (YES), the construction is completed, and if it is determined that the work is not stopped (NO), the process returns to S26. That is, S26 to S29 are repeatedly executed until it is determined to be stopped. It is preferable that the person in charge makes the final decision on the termination based on the result of comparison between each element and the corresponding management index, and after consultation between the parties concerned as necessary.
1:撮影手段、2:パーソナルコンピューター、3:算出手段、4:管理図作成手段、5:打撃回数図作成手段、6:杭打ち特性図作成手段、7:支持層到達判定手段、8:打撃エネルギー決定手段、9:支持力算定手段、10:打ち止め判定手段、11:表示手段、12:制御手段 1: Imaging means, 2: Personal computer, 3: Calculation means, 4: Control chart creation means, 5: Strike count chart creation means, 6: Pile driving characteristic diagram creation means, 7: Support layer arrival determination means, 8: Strike Energy determination means, 9: bearing capacity calculation means, 10: stop determination means, 11: display means, 12: control means
Claims (7)
杭の外周面に設けられた格子柄部を撮影する、第一の撮影ステップと、
前記第一の撮影ステップの撮影結果から、サンプリングモアレ法を用いて、前記杭の一打撃ごとの貫入量及びリバウンド量、所定深度あたりの打撃回数を算出する、第一の算出ステップと、
前記第一の算出ステップで算出された貫入量及びリバウンド量を、前記杭の貫入深度に対してプロットした管理図を作成する、管理図作成ステップと、
前記第一の算出ステップで算出された所定深度あたりの打撃回数を、前記杭の貫入深度に対してプロットした打撃回数図を作成する、打撃回数図作成ステップと、
前記管理図と前記打撃回数図に基づいて、前記杭の支持層到達を判定する、支持層到達判定ステップと、
を有し、
前記支持層到達判定ステップは、
試験杭が計画支持層に到達した時の前記貫入量、前記リバウンド量及び前記所定深度あたりの打撃回数と、
前記管理図より求めた、試験杭が計画支持層に到達するまでの前記貫入量の変化傾向及び前記リバウンド量の変化傾向と、
前記打撃回数図より求めた、試験杭が計画支持層に到達するまでの前記所定深度あたりの打撃回数の変化傾向と、
を管理指標として、前記杭の支持層到達を判定するステップであることを特徴とする打撃工法の施工管理方法。 It is a construction management method of the striking method,
The first shooting step to shoot the lattice pattern part provided on the outer peripheral surface of the pile,
From the shooting results of the first shooting step, the sampling moire method is used to calculate the penetration amount and rebound amount for each hit of the pile, and the number of hits per predetermined depth.
A control chart creation step for creating a control chart in which the intrusive amount and the rebound amount calculated in the first calculation step are plotted against the intrusive depth of the pile.
A striking number diagram creation step for creating a striking number diagram in which the number of striking per predetermined depth calculated in the first calculation step is plotted against the penetration depth of the pile.
A support layer arrival determination step for determining the arrival of the support layer of the pile based on the control chart and the impact count diagram, and
Have a,
The support layer arrival determination step is
The penetration amount, the rebound amount, and the number of hits per predetermined depth when the test pile reaches the planned support layer.
The change tendency of the penetration amount and the change tendency of the rebound amount until the test pile reaches the planned support layer, which are obtained from the control chart,
The tendency of change in the number of hits per predetermined depth until the test pile reaches the planned support layer, which was obtained from the number of hits diagram.
A construction management method of a striking method, characterized in that it is a step of determining the arrival of the support layer of the pile using the above as a management index.
前記格子柄部を撮影する、第二の撮影ステップと、
前記第二の撮影ステップの撮影結果から、サンプリングモアレ法を用いて、前記杭の一打撃ごとの貫入量及びリバウンド量を算出する、第二の算出ステップと、
前記第二の算出ステップで算出された貫入量及びリバウンド量と、前記貫入量及びリバウンド量を用いて打止め管理式から求まる支持力と、に基づいて、前記杭の打ち止めを判定する、打ち止め判定ステップと、
を有することを特徴とする請求項1に記載の打撃工法の施工管理方法。 After confirming that the pile has reached the support layer,
The second shooting step of shooting the lattice pattern portion and
From the shooting results of the second shooting step, the second calculation step of calculating the penetration amount and the rebound amount for each impact of the pile by using the sampling moiré method.
A stop determination is made to determine the stop of the pile based on the intrusion amount and the rebound amount calculated in the second calculation step and the bearing capacity obtained from the stop control formula using the intrusion amount and the rebound amount. Steps and
The construction management method of the striking method according to claim 1, wherein the method is characterized by having.
試験杭の打ち止め時の貫入量及びリバウンド量と、
前記打ち止め時の貫入量及びリバウンド量を用いて打止め管理式から求まる支持力と、
を管理指標として、前記杭の打ち止めを判定するステップであることを特徴とする請求項2に記載の打撃工法の施工管理方法。 The stop determination step is
The amount of penetration and rebound when the test pile is stopped,
The bearing capacity obtained from the stop control formula using the penetration amount and rebound amount at the time of stopping,
The construction management method of the striking method according to claim 2 , wherein the step is a step of determining the stopping of the pile, using the above as a management index.
試験杭の施工で決定された打撃エネルギーで前記杭を打撃する打撃ステップを有することを特徴とする請求項1乃至3のいずれか一項に記載の打撃工法の施工管理方法。 After confirming that the pile has reached the support layer,
The construction management method of the striking method according to any one of claims 1 to 3 , further comprising a striking step of striking the pile with striking energy determined in the construction of the test pile.
杭の外周面に設けられた格子柄部を撮影する、撮影手段と、
前記撮影手段の撮影結果から、サンプリングモアレ法を用いて、前記杭の一打撃ごとの貫入量及びリバウンド量、所定深度あたりの打撃回数を算出する、算出手段と、
前記算出手段で算出された貫入量及びリバウンド量を、前記杭の貫入深度に対してプロットした管理図を作成する、管理図作成手段と、
前記算出手段で算出された所定深度あたりの打撃回数を、前記杭の貫入深度に対してプロットした打撃回数図を作成する、打撃回数図作成手段と、
を有し、
更に、前記管理図と前記打撃回数図に基づいて、前記杭の支持層到達を判定する、支持層到達判定手段を有し、
前記支持層到達判定手段は、
試験杭が計画支持層に到達するまでの前記貫入量、前記リバウンド量及び前記所定深度あたりの打撃回数と、
前記管理図より求めた、試験杭が計画支持層に到達するまでの前記貫入量の変化傾向及び前記リバウンド量の変化傾向と、
前記打撃回数図より求めた、試験杭が計画支持層に到達するまでの前記所定深度あたりの打撃回数の変化傾向と、
を管理指標として、前記杭の支持層到達を判定することを特徴とする打撃工法の施工管理システム。 It is a construction management system of the striking method,
Photographing means for photographing the lattice pattern part provided on the outer peripheral surface of the pile,
From the imaging results of the imaging means, a calculation means for calculating the penetration amount and rebound amount for each impact of the pile, and the number of impacts per predetermined depth by using the sampling moiré method.
A control chart creating means for creating a control chart in which the intrusive amount and the rebound amount calculated by the calculation means are plotted against the intrusive depth of the pile.
A striking frequency diagram creating means for creating a striking frequency diagram in which the number of striking times per predetermined depth calculated by the calculating means is plotted against the penetration depth of the pile.
Have a,
Further, it has a support layer arrival determination means for determining the arrival of the support layer of the pile based on the control chart and the impact count diagram.
The support layer arrival determination means is
The penetration amount, the rebound amount, and the number of hits per predetermined depth until the test pile reaches the planned support layer.
The change tendency of the penetration amount and the change tendency of the rebound amount until the test pile reaches the planned support layer, which are obtained from the control chart,
The tendency of change in the number of hits per predetermined depth until the test pile reaches the planned support layer, which was obtained from the number of hits diagram.
A construction management system of a striking method, characterized in that the arrival of the support layer of the pile is determined using the above as a management index.
試験杭の打ち止め時の貫入量及びリバウンド量と、
前記打ち止め時の貫入量及びリバウンド量を用いて打止め管理式から求まる支持力と、
を管理指標として、前記杭の打ち止めを判定することを特徴とする請求項6に記載の打撃工法の施工管理システム。 The stop determination means is
The amount of penetration and rebound when the test pile is stopped,
The bearing capacity obtained from the stop control formula using the penetration amount and rebound amount at the time of stopping,
The construction management system of the striking method according to claim 6 , wherein the pile is determined to be stopped by using the above as a management index.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2020195289A JP6925675B1 (en) | 2020-11-25 | 2020-11-25 | Construction management method of striking method and construction management system of striking method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2020195289A JP6925675B1 (en) | 2020-11-25 | 2020-11-25 | Construction management method of striking method and construction management system of striking method |
Publications (2)
Publication Number | Publication Date |
---|---|
JP6925675B1 true JP6925675B1 (en) | 2021-08-25 |
JP2022083767A JP2022083767A (en) | 2022-06-06 |
Family
ID=77364592
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2020195289A Active JP6925675B1 (en) | 2020-11-25 | 2020-11-25 | Construction management method of striking method and construction management system of striking method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP6925675B1 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP7093597B1 (en) | 2022-03-01 | 2022-06-30 | 株式会社オーク | Pile bearing capacity embedding length measurement system and its method |
Family Cites Families (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS57211430A (en) * | 1981-06-16 | 1982-12-25 | Sony Corp | Method for supplying parts to automatic assembly machine and carrier for it |
JPH11293674A (en) * | 1998-04-09 | 1999-10-26 | Tokyo Electric Power Co Inc:The | Penetration amount measuring device for pile |
JP6871886B2 (en) * | 2018-07-26 | 2021-05-19 | 東洋建設株式会社 | Stopping management method for driving piles and stopping management auxiliary system for driving piles |
JP2020094350A (en) * | 2018-12-11 | 2020-06-18 | 株式会社横山基礎工事 | Construction management device and method for steel pipe installation |
-
2020
- 2020-11-25 JP JP2020195289A patent/JP6925675B1/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP7093597B1 (en) | 2022-03-01 | 2022-06-30 | 株式会社オーク | Pile bearing capacity embedding length measurement system and its method |
JP2023127052A (en) * | 2022-03-01 | 2023-09-13 | 株式会社オーク | Pile support force embedment depth measuring system and method thereof |
Also Published As
Publication number | Publication date |
---|---|
JP2022083767A (en) | 2022-06-06 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US10060900B2 (en) | Concrete screeding system with floor quality feedback/control | |
KR102039443B1 (en) | Measuring system of pile penetration depth of pile driver | |
JP5585059B2 (en) | Measuring method of steel pipe installation error | |
JP6925675B1 (en) | Construction management method of striking method and construction management system of striking method | |
JP6874378B2 (en) | Support layer arrival judgment method and judgment support system | |
JP2019124110A (en) | Concrete compaction vibrator and concrete installation management system | |
KR101478906B1 (en) | auto measurement equipment of standard penetration test | |
JP6911356B2 (en) | Support layer arrival judgment method and judgment support system | |
JP2019157346A (en) | Ground evaluation system and ground evaluation method | |
JP5422465B2 (en) | Workmanship management system and workmanship management method | |
JP2017015445A (en) | Measurement method and measurement program by image processing | |
KR102403495B1 (en) | Multipurpose total inspection device and digital construction method of reinforced structure underground using the same | |
CN111021732A (en) | Concrete vibrating rod positioning method based on optical fiber sensing | |
JP6969212B2 (en) | Support layer arrival judgment method and judgment support system | |
JP3647445B1 (en) | Pile construction management device | |
JP2003119784A (en) | Pile driving system | |
JP7304126B2 (en) | Columnar structure verticality measurement method | |
JP6871886B2 (en) | Stopping management method for driving piles and stopping management auxiliary system for driving piles | |
JP6854230B2 (en) | Branch line anchor placement system, branch line anchor placement method, geological data measurement device, branch line anchor placement tool, and computer program | |
JPH093895A (en) | Device for controlling penetration amount of pile driving | |
JP2021191932A (en) | Installation data management system | |
KR101007111B1 (en) | The automatic measuring instrument and measuring method using image for penetration test | |
JP4043025B2 (en) | Pile verticality management device | |
JP3447544B2 (en) | Face rock state determination method and face rock state determination apparatus | |
JP7299501B2 (en) | Pipe soil measurement method and pipe soil measurement system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A80 | Written request to apply exceptions to lack of novelty of invention |
Free format text: JAPANESE INTERMEDIATE CODE: A80 Effective date: 20201204 |
|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20210325 |
|
A871 | Explanation of circumstances concerning accelerated examination |
Free format text: JAPANESE INTERMEDIATE CODE: A871 Effective date: 20210325 |
|
A975 | Report on accelerated examination |
Free format text: JAPANESE INTERMEDIATE CODE: A971005 Effective date: 20210421 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20210511 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20210617 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20210629 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20210728 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 6925675 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |